RP 12-3
October 1994
Document Title
APPLICABILITY
Regional Applicability:
International
AMENDMENTS
Amd
Date
Page(s)
Description
___________________________________________________________________
Electrical
Issued by:-
CONTENTS
Section
Page
FOREWORD .........................................................................................................................iii
1. INTRODUCTION..............................................................................................................1
1.1 Scope ...................................................................................................................1
2. SYSTEM PARAMETERS.................................................................................................1
2.1 Voltage...................................................................................................................1
2.2 Frequency ...............................................................................................................2
2.3 Rating ...................................................................................................................2
3. LOADS ...............................................................................................................................3
3.1 Rating and Diversity Factors ...................................................................................3
3.2 Types of Load.........................................................................................................4
4. POWER SUPPLY SOURCES...........................................................................................5
4.1 General ...................................................................................................................5
4.2 Emergency Power Supply Equipment......................................................................8
4.3 Reliability................................................................................................................10
4.4 Primary Substation..................................................................................................10
4.5 Frequency and Voltage Regulation..........................................................................13
4.6 Synchronising .........................................................................................................15
4.7 Power Supplies for Control Systems .......................................................................16
5. POWER DISTRIBUTION SYSTEMS..............................................................................17
5.1 General ...................................................................................................................17
5.2 Single Radial...........................................................................................................18
5.3 Double Radial .........................................................................................................18
5.4 Triple Radial ...........................................................................................................19
5.5 Ring Fed Systems....................................................................................................20
5.6 Interconnected or Mesh Systems.............................................................................21
5.7 Power System Control ............................................................................................22
5.8 Electrical Distribution Substations...........................................................................25
6. POWER SYSTEM FAULT CONSIDERATIONS ...........................................................26
6.1 Fault Calculations ...................................................................................................26
6.2 Equipment Fault Current Ratings ............................................................................28
6.3 Methods of Limiting Fault Currents.........................................................................29
6.4 Effects of Faults on Distribution Systems ................................................................31
7. POWER SYSTEM EARTHING .......................................................................................32
7.1 General ...................................................................................................................32
7.2 Un-Earthed (Isolated) Neutral.................................................................................33
7.3 Solidly Earthed Neutrals (For systems below 1000 V).............................................33
7.4 Impedance Earthed Neutrals (For Systems rated 1000 V and above) .......................34
7.5 Generator Earthing .................................................................................................35
7.6 Earthing Resistors...................................................................................................37
8. POWER SYSTEM DESIGN PARAMETERS .................................................................37
8.1 Motor Starting ........................................................................................................37
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE i
8.2 Overvoltages...........................................................................................................38
8.3 Harmonics ..............................................................................................................40
8.4 Power Factor ..........................................................................................................42
9. POWER SYSTEM STUDIES............................................................................................44
9.1 General ...................................................................................................................44
9.2 Conventional Studies ..............................................................................................45
9.3 Special Studies........................................................................................................48
FIGURE 1 (A) ........................................................................................................................49
DOUBLE RADIAL FEED DISTRIBUTION ...............................................................49
FIGURE 1 (B) ........................................................................................................................50
CLOSED RING MAIN DISTRIBUTION ....................................................................50
FIGURE 1 (C) ........................................................................................................................51
OPEN RING MAIN DISTRIBUTION .........................................................................51
APPENDIX A.........................................................................................................................52
DEFINITIONS AND ABBREVIATIONS....................................................................52
APPENDIX B.........................................................................................................................53
LIST OF REFERENCED DOCUMENTS ....................................................................53
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE ii
FOREWORD
Introduction to BP Group Recommended Practices and Specifications for Engineering
The Introductory Volume contains a series of documents that provide an introduction to the
BP Group Recommended Practices and Specifications for Engineering (RPSEs). In particular,
the 'General Foreword' sets out the philosophy of the RPSEs. Other documents in the
Introductory Volume provide general guidance on using the RPSEs and background
information to Engineering Standards in BP. There are also recommendations for specific
definitions and requirements.
Value of this Recommended Practice
This document represents the accumulated practices of the BP Group for ensuring a high
degree of plant availability and electrical system integrity within the constraints for cost
effective engineering.
Application
Text in italics is Commentary. Commentary provides background information which supports
the requirements of the Recommended Practice, and may discuss alternative options.It also
gives guidance on the implementation of any 'Specification' or 'Approval' actions; specific
actions are indicated by an asterisk (*) preceding a paragraph number.
This document may refer to certain local, national or international regulations but the
responsibility to ensure compliance with legislation and any other statutory requirements lies
with the user. The user should adapt or supplement this document to ensure compliance for
the specific application.
Principal Changes from Previous Edition
This Recommended Practice is a major revision of BP CP 17 Pt. 3 Power Systems Design
which was last issued in April 1986. It has been updated in the Way Forward Style to reflect
significant advances in power system design.
Feedback and Further Information
Users are invited to feed back any comments and to detail experiences in the application of
BP RPSE's, to assist in the process of their continuous improvement.
For feedback and further information, please contact Standards Group, BP International or the
Custodian. See Quarterly Status List for contacts.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE iii
1.
INTRODUCTION
1.1
Scope
The BP Group RP 12 series of Recommended Practices specify general
requirements for electrical systems, equipment, materials and
installations. This document specifies those items which apply generally
to power system design for systems with a highest nominal voltage of
36 kV.
It is considered that most of the installations within the sphere of BP operations
would be 34.5kV or below. However, it has been found that even for voltages of
132 kV, the same principles would tend to apply for industrial systems.
1.2
Although the following items may form part of power systems in certain
activities of the BP Group, their designs are not covered by this
document. Where necessary, the relevant international or national
standard must be applied to these elements of electrical systems.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
The above exclusions are considered special in nature and/or can be undertaken
more efficiently by directly adopting practice which is common in the area where
the installation is to be employed.
2.
SYSTEM PARAMETERS
2.1
Voltage
The most economical voltages shall be selected for a Power System.
In general the voltages selected should accord with the economical voltage levels
for machines which are included in BP Group RP 12-11.
In any existing installation, the selection of voltage levels will be subject also to site
conditions. The requirement for having the most economic system voltage is
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 1
The nominal phase to phase voltage for systems where voltages exceed
1000 V, should be selected from those detailed in IEC 38. When the
phase to phase voltage is below 1000 V, the appropriate nominal
voltage to meet the national standards of the site location should be
used. For 'greenfield' sites or offshore locations, where the possibility
of interconnection with an outside authority is low, the use of nonstandard voltages below 1000 V (e.g. 660 V) shall be based on
economic considerations.
In the UK the nominal LV voltage would be either 415 V or 440 V, phase to phase
with a tolerance of 5%. (Notwithstanding current legislation which may suggest
that nominal voltages will in future be 380 V 10% or the provisions of the
Electricity Supply Regulations 1988 which require voltage tolerances to be within
6% for voltages less than 132 kV). See also 4.5.1
Any deployment of non standard voltage systems should be based upon specific
economic studies which take full account of the need to hold spares which may be
beyond normal stock levels.
2.2
Frequency
The frequency selected for power systems will be either 50 or 60 Hz
depending on the national standards of the site location. Where a site is
to be remotely located and powered only from on-site generation, the
frequency selected should be compatible with the frequency of supply
of the nearest local electrical supply source or public utility if it is
envisaged that future inter-connection is desirable. Where future interconnection with other sources of electricity supply is not envisaged as
being possible or where economic advantages outweigh the benefits in
future possible interconnections, the frequency of supply shall be
selected on economic considerations and on ease of obtaining suitable
equipment.
North Sea experience indicates that selecting 60 Hz frequency tends to offer
possible economic advantages and as European equipment (i.e. widely available
equipment) suppliers can gear their product range to this frequency and the
'standard' voltages within Europe, such selection becomes more likely.
2.3
Rating
(i)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 2
(ii)
For power systems with a voltage less than 1000V. the rms.
value of the a.c. component of the short-circuit breaking current
of circuit breakers designed to IEC 947 and/or BP Group GS
112-8 should not exceed 50 kA.
See the commentary for (i) above. Where economically viable the selection
of 80 kA or above rated switchgear is encouraged. BP Group GS 112-8
includes testing requirements for LV circuit breakers.
3.
LOADS
3.1
3.1.1
3.1.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 3
3.2
Types of Load
All loads shall be presented with clear definition of their types in
accordance with the following:-
3.2.1
Basic Information
For each identified electrical load, a description of the service should be
given together with an indication of whether the device is a machine or
a static load.
(i)
Dynamic
These are electric motors driving rotating equipment.
(ii)
Static
3.2.2
Essential Loads
These are loads which are important to the safety of the installation or
the operational staff, and which require power to permit a reasonably
controlled shutdown in emergency. They shall have a second
independent power source and be generally associated with no break
supplies. In certain cases, a short supply break may be acceptable if this
does not represent a hazard to safety.
BP Group RP 12-5 contains advice concerning the categorisation of power supplies
suitable for control systems. The concept of essential loads used here is fairly close
to the concept of Class A contained in that RP, however, the loads would not
require the level of duplication required for Class A systems. Included in the
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 4
concept of essential power system loads are such devices as Lub. oil pumps for Gas
Turbines, ventilation systems, helipad lighting some floodlighting systems,
navigational aids, radio systems etc. The term Essential used here was chosen to
align with the term Essential as defined in the IEE Recommendations for the
Electrical and Electronic Equipment of Mobile and Fixed Offshore Installations.
It is noted that some loads which are essential by this definition may require the
provision of Emergency Power Supply Facilities in order to meet Legislative
Requirements. This is not inconsistent with the definition of Essential Loads used
here which is aimed at providing a convenient process for being assured that all
such critical loads are covered by the appropriate level of power supply. (See
further Section 4.2.1)
3.2.3
3.2.4
Non-sensitive Loads
Non-sensitive loads are those which do not form an important
component of a production or process plant and their disconnection
could be borne for relatively long periods with minimal or nuisance
value. They usually form a small proportion of the total connected load
and may have a single power source.
Typical examples of these loads are the domestic part of accommodation, offices,
Workshops, some water injection, some potable water systems etc.
4.
General
The power supply system shall be designed to provide safe and
economical operation. The safety aspects should cover both plant and
personnel. Economic considerations shall cover capital, maintenance
and running costs and include an assessment of the reliability and
consequent availability of the system. The cost of improved power
systems reliability should be weighed against the progressive potential
savings due to decreased loss of production.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 5
It is expected that for any significant power system design there will have been an
economic comparison of alternative arrangements. Larger projects would be
expected to initiate a formal safety review and this process would ensure that the
basic safety needs of the project would be satisfied. For smaller projects or plant
extensions where such a formal review may not be arranged, the designer should
nonetheless consider safety aspects relating to the electrical system and produce an
outline document which presents these issues for the record.
The principal source of electrical supply for any location, subject to the
requirements of 4.1.1 to 4.1.3. shall be defined.
The power supply arrangements are fundamental to any operating site and need to
feature strongly in the overall project concept. A power supply philosophy
document which records the arrangements for power supply and the reasoning
associated with any selection is considered highly desirable. A contractor may
have part of his workscope associated with an evaluation and selection of power
supply arrangements in which case such a presentation is assured. The selection of
the power supply arrangements may have formed part of a feasibility (or Statement
of Requirements) study which may have been produced by BP in which case the
definition of the power supply arrangements would form part of a contractors
specification.
4.1.1
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 6
(ii)
(iii)
(iv)
(ii)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 7
4.1.3
(ii)
(iii)
A combination of both.
(iv)
It is expected that the power generation philosophy would consider these options
which would be contained within a formal design record. See also 4.1.1 where
there may be economic benefit in peak lopping of the Public Utility supply taking
advantage of tariff opportunities.
4.2
4.2.1
(ii)
(iii)
(iv)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 8
4.2.2
In the application of 4.2.1 (ii), the power supply to Essential loads shall
be designed to remain available in the event of at least two of the
installed main power generators being unavailable. The probability of
zero interruptions to the Essential load feed busbar over a 12 month
period shall be 99% or better. Where necessary a loadshedding scheme
shall be installed to secure the supply to the Essential loads. Essential
loads shall not form part of the loadshedding arrangements.
The concept of additional power generation being suitable for emergency supply
duty will clearly not be possible without there being at least 3 power generation sets
available. Where one power generator thus installed is of lower capacity than the
system maximum demand and/or the nature of the load can lead to instability, it is
expected that a load shedding scheme would be employed to ensure that the
Essential loads would be maintained for any fault condition which could leave a
single machine on the busbar.
4.2.3
4.2.4
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 9
emergency generator should be on an outside wall which can have louvers open to
supply combustion air. Care should be taken to ensure that the exhaust and air
intakes are located to avoid problems associated with other adjacent plant or
systems.
4.2.5
4.3
Reliability
For each power supply arrangement a reliability assessment shall be
carried out to determine the probability of failure of supply.
In the early stages of design a reliability study may be undertaken as part of the
comparison of alternative methods of providing power supplies. Such studies would
also be useful in determining the cost of material failures. The undertaking of
these studies may form part of the Contractors workscope. Where the Project Team
is required to carry out such a study, the terms of reference related to objectives,
data gathering, and evaluation shall be clearly specified.
4.4
Primary Substation
4.4.1
4.4.2
4.4.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 10
(i)
(ii)
(iii)
Unscheduled loss of busbar sections shall not shut down the system beyond
the level designed and provided for.
(iv)
It may often be found necessary to locate the incoming circuit breakers of a busbar
to a location half way along one side of a busbar in order to be more assured that
100% of the load is unlikely to flow in one section of the busbars.
The possibility of bus section circuit breaker fault conditions in metal enclosed
switchgear which may cause a full switchboard shutdown for remedial repairs
should be considered. However, unless there are overriding reasons for the
contrary, BP do not design switchboards to cater for this eventuality.
4.4.4
(ii)
(iii)
Where there would be 3 incoming transformer feeders, the busbar would normally
be expected to be in 3 parts with feeder circuit breakers arranged on each of the
sections of busbar.
4.4.5
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 11
4.4.6
4.4.7
Where the power supply is obtained from a public utility via equipment
such as transformers or feeders, the busbars shall be sectionalised to
prevent total power system shutdown in the event of unscheduled
outage of any busbar section. Coincidental maintenance of a public
utility intake transformer shall not be considered.
It is considered that maintenance of incoming transformers and feeds would be low
and would be quickly completed. Therefore high expense in order to reduce an
already unlikely event is not considered worthwhile.
4.4.8
The maximum number of busbar sections should not exceed the number
of individual power sources.
This requirement sets out to avoid over flexibility in a power system which, although
useful in contemplation, is of little economic benefit in practice.
4.4.9
4.4.10
(b)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 12
(c)
4.5
4.5.1
The power system design shall be arranged to ensure that the voltage
variation (between full load and lightly loaded conditions) experienced
at any piece of equipment designated as a load (i.e. not including
distribution equipment) shall not exceed 5% of the declared system
nominal voltage. Further the power system shall be arranged to be able
to withstand without undue stress a transient voltage variation to 80%
of nominal for a 10 second period or such longer duration at specific
points if necessary. Special consideration shall be given to power
frequency overvoltage effects and the need for Power System
equipment to withstand higher overvoltages under some circumstances.
This requirement ensures that standard equipment parameters would not be
compromised. Where the system voltage deviates beyond the 5% limit, apart from
equipment life expectation being eroded, there is a danger of exceeding the
hazardous area certification limits for that equipment installed in a hazardous area.
This may not actually yield failures or temperatures likely to cause ignition of a
vapour which may be present but will increase the likelihood of such occurrences
and will infringe the basic safety intention.
The Electricity Supply Regulations 1988 requires voltage variations to be within
6%. However, standards for equipment state a 5% tolerance for voltage. Hence
the lower limit is specified here.
Where power systems which have automatic voltage control can experience
significant load rejection (e.g. as may be the case of a Power System supplied by
generators must direct-on-line start large machines which subsequently exhibit
rapid VAr decrease leaving machines in an overexcited state), significant
overvoltage levels may be predicted (120% to 125% of nominal voltage can be
predicted). This may require special specification of transformers to avoid
problems caused by overfluxing or increased current due to magnetic excitation.
Special attention should be paid to voltage and frequency tolerance specifications
for generator transformers which may need to match the run up characteristic of the
generator. This can require the transformer to be capable of withstanding full rated
voltage at 80% of rated frequency.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 13
See 8.1.1 for motor starting requirements. This can give rise to a voltage
depression at motor terminals of 20% which therefore requires that the power
system should be able to successfully accept this condition for the starting period.
Typical starting periods can range from 1 to 10 seconds depending upon machine
and system ratings and machine inertia. Starting times beyond 10 seconds are
possible where particularly high inertia loads need to be accelerated (e.g. fans)
however, these would constitute a special application and should be treated by
exception.
4.5.2
4.5.3
4.5.4
4.5.5
4.5.6
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 14
4.5.7
4.6
Synchronising
4.6.1
4.6.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 15
4.6.3
4.6.4
4.7
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 16
5.
General
5.1.1
5.1.2
Where required the reliability associated with any part of the system
shall be assessed and presented in qualitative and quantitative terms.
In general the design of the power system distribution should be based upon
qualitative requirements which include assessments for meeting power supply
continuity in the event of maintenance and in the event of failure. Since electrical
distribution systems are inherently reliable, the design requirements are commonly
based upon the need to disconnect distribution electrical equipment to carry out
routine maintenance and at the same time keep power supplies available for
operating plant. However, under some circumstances the need to assess the
electrical reliability may arise (perhaps as part of an overall assessment of plant
failure but possibly as part of a comparison of alternative supplies for new plant).
Under these circumstances, the Mean Time Between Failure (MTBF) and the Mean
Time To Repair (MTTR), concerning power system failure at any particular
switchboard would be required. In addition it is recommended that the quantitative
statement indicate the probability of failure occurring over a particular timeframe.
(e.g. Provide a value and definition of the probability of zero failures over a 12
month period).
See also sections 4.1.2 (commentary), 4.2.2 and 4.3.
5.1.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 17
5.2
Single Radial
5.2.1
5.2.2
5.3
Double Radial
5.3.1
5.3.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 18
5.3.3
(a)
For bus section circuit breaker faults. These may sometimes cause damage
which may require complete switchboard shutdown. However, the
occurrence of such faults is sufficiently rare as to be neglected.
(b)
5.3.4
Where switchgear fault levels are found to be above the values outlined
in 2.3, attention shall be given to operating with bus-section breakers
open as opposed to purchasing higher fault level switchgear. Where an
open bus-section breaker philosophy is being given attention, the need
to restore rapidly the supplies to drives shall determine whether
automatic closure of bus section circuit breaker(s) is to be employed.
Switchgear fault levels could be readily reduced by increasing the impedance of
incoming transformers. (Where new transformers will be purchased.) However,
increasing the impedance of transformers increases the voltage regulation between
light and full load. There is therefore a trade-off between fault duty and normal
voltage regulation.
Triple Radial
5.4.1
5.4.2
5.4.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 19
5.5
5.5.1
5.5.2
Ring fed systems should normally duplicate only the primary cables to
the load substation. They may however, duplicate the load substation
transformers and the low voltage busbar by providing a low-voltage or
secondary bus section breaker.
Duplication of downstream equipment would be dependent upon the need to
maintain electrical equipment and retain electrical feeds to the downstream
substation.
5.5.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 20
Essential or critical loads may be supplied by ring systems if they are operated
closed. Their choice shall be based on the comparative reliability and cost as
compared to the duplicate radial systems.
Refer to Section 3.1.1 for detail on load estimation.
5.5.4
Ring fed systems which are operated open need not include circuit
breakers on the ring.
Fault clearance would be achieved at the source substation and in that event power
would be lost to all loads fed between the source and the open point on the ring.
Open operated ring fed systems shall be permitted only to supply nonsensitive loads.
The choice of an open ring system shall consider the comparative reliability and
cost of a single radially fed systems with a non automatic standby power supply
backup.
5.6
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 21
disturbance during a fault condition. For this reason and because they would
present a point of non-standardisation if used in hazardous areas they are to be
avoided.
5.7
5.7.1
Stop/Start.
(b)
Synchronising.
(c)
(d)
Additionally it is expected that the Central Control Room Operator would have
control of:(a)
(b)
(c)
See 5.7.2 for method of information and control. It is recommended that the
Central Control Room Operator have available information and control of the
entire power system by the means described. However, it is recognised that in
general there would need to be some limitations placed upon the ability of the
power system operator to individually control process loads.
5.7.2
The power system shall utilise protection relays which incorporate the
means for indication and control via a Hiway connection. The form and
performance of the dual function protection relay system shall detail;(a)
(b)
(c)
(d)
System architecture.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 22
(e)
(f)
(g)
The dual function protection and information/control relay should be arranged with
a clear and effective method for ensuring that protection settings cannot be
changed by the action of control system software. Sole reliance of a password
embedded in the high level software system is not considered sufficient for this
purpose and a relay located function is generally expected.
It is expected that in the longer term the availability of the information offered and
the availability of the control offered by such dual function relays will provide
benefit to BP operations. Therefore relaxing the requirement for new installations
to be equipped with these relays should be specific and based upon the assertions:(a)
That the site will never need to gather data and have such control
and
(b)
It is recognised that under some circumstances only the dual function relays may be
employed with a later intent to effect operator control via Hiway connections.
5.7.3
(b)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 23
5.7.4
5.7.5
5.7.6
5.7.7
Load transfer schemes for the start up, run up and loading of a standby
generator on to a busbar normally fed from a preferred a.c. source shall
be initiated by time delayed under voltage relaying which shall trip the
a.c. source and auto-start up the standby generator.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 24
The auto start of the emergency (or standby) generator could be initiated before
disconnection of the normal supply in order to provide the main power system
greater chance of recovery (i.e. taking advantage of the finite time it takes a
standby generator to start).
It is expected that start initiation would be based upon main power system collapse
below 75% for say 2 seconds and that trip of the main supply and energisation of
the emergency supply would be initiated upon 85% voltage at system frequency for
the incoming set. (NB energisation would need to be time delayed from the trip
signal to allow flux decay of the machines which may have been hitherto in
operation).
5.7.8
5.8
5.8.1
5.8.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 25
This requirement is designed to keep the more expensive and high capacity
electrical connections as short as possible.
5.8.3
6.
Fault Calculations
6.1.1
6.1.2
The voltage disturbance sustained during the faults and after fault
clearance should also be ascertained to ensure that transient
disturbances do not result in loss of supplies due to low voltages or
over stressing of plant insulation due to high voltages.
In assessing the transient performance of the system, accurate modelling of any
AVR action is required. It would also be necessary to model the governor system of
any rotating power generators.
6.1.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 26
6.1.4
(ii)
(iii)
6.1.5
On systems where the earth fault currents are limited by neutral earthing
equipment, the currents may be assumed to include no decrement and
shall be considered constant whatever the level of bonding between the
conductor and the faulted phase.
6.1.6
Both the a.c. and d.c. components of motor fault current contributions
should be calculated and included in calculation of prospective fault
currents.
At the instant of fault inception the a.c. peak symmetrical component and the d.c.
component shall be taken to be identical. Both values shall be taken as the peak
direct-on-line starting current, this being dictated by the motor locked rotor
reactance. Both these currents shall be taken to decay exponentially with time
using a.c. and d.c. short circuit time constants respectively. The a.c. time constant
should be determined by using the ratio of the locked rotor reactance and the
standstill rotor resistance. The d.c. time constant should be determined by using
the locked rotor reactance and the stator resistance.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 27
Where faults are not directly on the motor terminals, these time constants would
be modified (preferably by the integrated computer programme) to take account of
external impedances to the point of fault.
6.1.7
6.1.8
6.2
6.2.1
6.2.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 28
The backup fault current protection clearing times shall always be less
than the equipment short time current rating.
Generally 3 second short time ratings for switchgear are preferred to avoid the
necessity for rapid protection.
Where switchgear of 0.6 second short circuit withstand time is offered, the
protection arrangements should be reviewed to ensure that the switchgear will be
fully protected.
6.2.3
6.2.4
6.2.5
Where plant is protected by fault current limiting HRC type fuses, the
fuse characteristic may be taken into account in assessing the short
circuit duty of the plant.
It is expected that where fuse cut off action is accounted, there would be presented
appropriate calculations and fuse data to demonstrate the validity of the fault duty.
6.3
6.3.1
(ii)
(iii)
(iv)
(v)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 29
6.3.2
The selection of the most appropriate of the alternatives (i) to (v) given
in 6.3.1 shall be based on least cost.
Saturable reactors (used as resonant links) offer elegant methods for short circuit
limitation for HV systems and do not suffer from attendant regulation problems ,
however, their expense generally precludes their use. The use of Is limiters should
be avoided for new installations but sometimes find useful application where
existing systems will be expanded or interconnected with new systems.
6.3.3
Where fault limiting (series) reactors are used to increase the reactance
between the source and potential fault location, these shall comply with
BP Group GS 112-5.
Detailed guidance is given in BP Group RP 12-9.
6.3.4
6.3.5
6.3.6
The voltage drop through series reactors under the motor start, restart
or re acceleration conditions shall be checked to ascertain that no
unacceptable transient under voltage occurs.
6.3.7
Where series reactors are installed between two power systems, the
transient stability of the generator sets should feature in power systems
studies.
See also 10.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 30
6.4
(ii)
Three phase faults on the system (considering zero fault impedance) will depress the
voltage at the point of fault and downstream of the fault to approximately zero. All
locations between the source of fault current and the fault will experience reduced
voltages. This condition will apply until the faulty section has been cleared at
which stage voltages will be rapidly restored.
Such studies would form part of the conventional study series described in 9.2.1.
(iii)
The provision of emergency lighting systems may avoid the need to feature this as
discharge lighting may be limited to those areas where the outage time may not be
important. (e.g. Street lighting).
(iv)
The provision of d.c. or 'no break' supplies (possibly using UPS equipment) for vital
loads may avoid the need to feature this.
(v)
This could cause unacceptable transient recovery voltages occurring for short
periods which may have a destructive effect on electrical insulation. However, it is
recognised that many analysis programmes are based upon linear theory and may
not account for saturation effects which may preclude overvoltages occurring but
could result in an electrical protection relay trip.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 31
7.
General
Guidance on the earthing of equipment and systems is detailed in BP
Group RP 12-16. The following clauses relate only to neutral earthing
of power systems.
There is a statutory requirement to conform with the Electricity Supply Regulations
1988 and with the Electricity at Work Regulations 1989.
7.1.1
7.1.2
7.1.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 32
facility provided for each system. The neutral earthing system shall be
designed to ensure that there is no possibility of inadvertently operating
a system with an isolated neutral.
Under some circumstances, an alarm for the condition of power system in operation
without neutral earthing should be satisfactory. Typical of such circumstances is
the condition whereby a single earthed neutral is desirable (perhaps in order to
limit circulating currents between power generators) and there would be a complex
and difficult automatic system for earthing switching in the event of power system
disconnection.
7.1.4
7.2
7.2.1
7.3
7.3.1
All low voltage systems should have their neutrals solidly connected to
the plant earthing system. Impedance earthing of systems with a voltage
below 1000 V shall only be used subject to approval by BP.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 33
Where single phase supplies are taken from LV systems, the neutral shall be solidly
earthed at the supply point only. (TN-S system to IEE Regs Section 542). Where the
LV supply is taken from a Public Utility, the neutral will be solidly earthed but the
supply system may be defined as TN-C-S. In this latter case the installation within
the BP premises shall conform with a TN-S arrangement with no further neutral
earths being required within the installation. Where PME (Protective Multiple
Earth) power supplies are taken from a Public Utility it is considered that there
should be no need for isolation transformers to achieve the TN-S arrangement
within the BP premises, however, the design shall conform with government
legislation and this may require that under certain circumstances, isolation
transformers are required. (Refer to HS(G) 41).
Impedance earthed LV systems may be considered where the system will be 3 wire
without neutral connections and there is benefit in limiting damage during earth
fault conditions. (e.g. Where a special voltage 660 V may be used in preference to
say 3.3 k V and in effect replaces the HV system in its application).
7.4
7.4.1
7.4.2
(ii)
(iii)
At earthing transformers.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 34
Where reactance earthing is considered, its use should be tested against the
cost/benefit compared with resistance earthing. Special attention should be taken
of the possible tuning effects between the earthing reactor and the power system.
7.4.3
7.5
Generator Earthing
7.5.1
7.5.2
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 35
Grid type resistors offer a virtually maintenance free installation and should be
employed wherever possible. However, this type of earthing resistor will prove
uneconomic for 33 kV systems where liquid neutral earthing resistors will offer an
optimum choice.
7.5.3
7.5.4
7.5.5
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 36
Conservative sizing of the transformer is preferred as its reactance has little effect
on the earthing system. The secondary resistor should have a continuous duty as its
size and cost will not normally be significant.
7.6
Earthing Resistors
All earthing resistors shall be provided with insulation suitable for the
phase to phase voltage of the systems to which they are connected.
They shall be designed to carry their rated fault current for the times
specified in the preceding clauses, without any destructive effect to their
component parts.
It is expected that resistors will be located in an outdoor environment where
transformer earthing is involved but could be indoors for generators. There is no
mandatory requirement for locating these devices indoors other than normal
economic factors.
8.
Motor Starting
8.1.1
8.1.2
The acceptability of the above voltage dips during motor starting shall
be contingent on the motor satisfactorily accelerating, and the voltage
dips not causing unacceptable disturbances to the power system. The
DOL starting of the largest and electrically most remote motors (or
groups of motors on an automatic re-acceleration scheme) at all
voltages, shall be investigated to ensure that no problem exists. Where
unacceptable voltage dips during motor starting may be found, the
following solutions shall be considered:-
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 37
(i)
(ii)
(iii)
(iv)
(v)
(vi)
8.1.3
Where motor load shedding and restart schemes are adopted, the
method of initiation shall be developed on the basis of cost effectiveness
for the project under consideration.
Where the load is predominantly induction motors, voltage reductions would not
cause load shedding whereas lower system frequency would tend to be an effective
load shedding method. For this reason it is likely that system load shedding would
best be initiated by a frequency based arrangement. Anticipation of a power
generation deficiency can be employed if total generation capacity is known
together with total system load. Under these conditions immediate load shedding
may be initiated. Such immediate load/generation matching schemes can vary from
a simple generator auxiliary contact used to initiate fixed loadshedding to a
complex microprocessor based system which monitors multiple generators and
multiple loads and constantly updates the amount of loadshedding for any specific
incident.
The effect that electrical load shedding will have on the process system needs to be
presented for Project approval. There may need to be some massaging of the
scheme to ensure that particular loads critical to process well-being is not shed.
8.2
Overvoltages
8.2.1
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 38
8.2.2
8.2.3
8.2.4
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 39
8.2.5
8.2.6
8.3
Harmonics
8.3.1
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 40
case the machine should be certified for such use given the specific harmonics
yielded by the VSD)
Where more than 5% THF is anticipated and the manufacturer of the electrical
equipment cannot confirm its suitability for this service, then in principle the
following should be considered:-
.
8.3.2
8.3.3
8.3.4
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 41
8.3.5
8.4
Power Factor
8.4.1
8.4.2
8.4.3
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 42
8.4.5
(b)
The terminal voltage can remain high for a long period and thus
compromise reclosure.
Thus if capacitance on the motor side of the switchgear is excessive, either the
motor insulation should be able to withstand high overvoltages (not above 150% as
the induction motor iron circuit can be expected to show some signs of saturation)
or the capacitor needs to be separately switched.
8.4.6
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 43
9.
General
9.1.1
9.1.2
(ii)
(iii)
9.1.3
(a)
(b)
(c)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 44
Minimum power generation, one line (or transformer) out of service for
maintenance and starting of the largest induction machine (presumed
direct-on-line).
(b)
(c)
Simple loss of the largest capacity generator from the power system at
times of minimum spinning spare. (NB This may be a less severe condition
than if the generator were faulted but could illustrate the level of load
shedding which may occur).
(d)
9.2
Conventional Studies
9.2.1
(ii)
(iii)
(a)
(b)
(c)
(d)
Auto-changeover schemes.
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 45
(f)
(g)
(h)
See sections 4.5.1 (for steady state voltage conditions), 8.1.1 (for transient voltage
conditions). Motor Starting, Dynamic Performance (including load shedding
arrangements and protection arrangements) and Short Circuit requirements will be
subject to the specific design features of the project.
9.2.2
The studies detailed by 9.2.1 should be carried out with clear terms of
reference early as possible within a project. The software programs and
computer capability should also be defined. Models for generators,
automatic voltage regulators, governors, motors, transformers, cables
and loads should be sufficiently detailed and proven to give confidence
in the results of the studies.
The terms of reference for studies which are to be presented by a design contractor
should be developed as soon as possible. These should contain definitions for the
required system performance where this is not sufficiently detailed by sections
4.5.1, 5.7.3, 5.7.7 and 6.4.
In certain circumstances, preliminary study work may be carried out by BP to
ensure that design contractors terms of reference are reasonable and to instigate a
permanent data file, which would be suitable for operational use and can be
modified as changes occur. This would be the basis of detailed design, and should
be modified as necessary to include the detailed design equipment parameters. the
computer data file would then be available throughout the life of the installation.
This process would be considerably eased if the power system analysis software
were the same for preliminary studies through to final studies and the data files
were directly transferable between the systems used by Contractors and that used by
BP. Therefore, it is preferable that power system studies are undertaken using the
IPSA power systems analysis suite. Should an alternative power system analysis
programme suite be employed, the data should be transferable either manually or
via a computer based conversion programme into an IPSA compatible form.
See also section 6.1.9 for software validation.
9.2.3
9.2.4
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 46
(ii)
(iii)
Synchronous motors.
(iv)
9.2.5
Where transient stability studies are undertaken, (in order to assess the
ability of generators to remain in synchronism following a fault
disturbance) the steady state operating condition before the fault is
applied should be one in which the spinning reserve of generation is
kept at a minimum due to assumed maintenance of the largest onsite
generator.
The primary object should be to identify the maximum acceptable fault clearing
time, but secondary objectives, such as the best location of system open bus section
points and the relationship between impedance earthing to stability, should also be
ascertained from these studies. The studies would be used as support for a
particular system design and also to ensure that the protection arrangements would
not compromise the expected system performance. In pursuit of this latter factor,
the studies may be undertaken with actual protection arrangements if these are
known. In doing this it should be noted that if protection settings were to change,
the system response to fault conditions may need to be re-studied.
See also 9.1.3 (commentary).
9.2.6
9.2.7
System stability studies shall be carried out to consider the effect of the
loss of the largest power supply component under a fault condition
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 47
9.2.8
9.3
Special Studies
9.3.1
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 48
PUBLIC UTILTY
PRIMARY
SUBSTATION
A
A
UP TO 36KV
A
A
AREA
SUBSTATION
UP TO 12KV
C
DESCRIPTION
PROCESS
SUBSTATION
UP TO
7.5KV
C
D
A
C
M
G
C
C
A
PROCESS
SUBSTATION
GENERATOR
UP TO
1KV
C
M
MOTOR
FIGURE 1 (A)
DOUBLE RADIAL FEED DISTRIBUTION
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 49
AREA
SUBSTATION
UP TO 12KV
A
CLOSED RING
MAIN SYSTEM
(TYPICAL)
PROCESS
SUBSTATION
UP TO 12KV
C
DOUBLE RADIAL
MAIN DISTR.
(TYPICAL)
C
TRIPLE RADIAL
MAIN DISTR.
(TYPICAL)
SINGLE RADIAL
MAIN DISTR.
(TYPICAL)
C
D
UP TO 7.2KV
C
C
PROCESS SUBSTATION
PROCESS
SUBSTATION
C
UP TO 1KV
DESCRIPTION
M
DOUBLE RADIAL
FEED (TYPICAL)
SINGLE RADIAL
FEED (TYPICAL)
TRIPLE RADIAL
FEED (TYPICAL)
MOTOR
FIGURE 1 (B)
CLOSED RING MAIN DISTRIBUTION
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 50
A
AREA
SUBSTATION
A
UP TO 12KV
A
A
OPEN RING
MAIN SYSTEM
(TYPICAL)
PROCESS
SUBSTATION
UP TO 12KV
C
SINGLE RADIAL
MAIN DISTR.
(TYPICAL)
PROCESS
SUBSTATION
UP TO 12KV
DESCRIPTION
A
C
M
C
G
UP TO 1KV
PROCESS
SUBSTATION
GENERATOR
M
M
MOTOR
FIGURE 1 (C)
OPEN RING MAIN DISTRIBUTION
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 51
APPENDIX A
DEFINITIONS AND ABBREVIATIONS
Definitions
Standardised definitions may be found in the BP Group RPSEs Introductory Volume.
Abbreviations
AVR
DOL
HV
HRC
IEC
IEE
IPSA
LV
MTBF
MTTR
PME
THF
VSD
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 52
APPENDIX B
LIST OF REFERENCED DOCUMENTS
A reference invokes the latest published issue or amendment unless stated otherwise.
Referenced standards may be replaced by equivalent standards that are internationally or
otherwise recognised provided that it can be shown to the satisfaction of the purchaser's
professional engineer that they meet or exceed the requirements of the referenced standards.
International
IEC 34
IEC 38
IEC 56
IEC 947
Industrial
IEE Wiring Regulations (16th Edition)
Electricity Council Recommendation G5/3 (1976)
Health and Safety Executive Guidance Note 41
BP Group Documents
BP Group RP 4-4
Buildings
(replaces BP CP 19)
BP Group RP 12-2
BP Group RP 12-4
BP Group RP 12-5
BP Group RP 12-6
HV Switchgear
(replaces BP CP 17 Part 6)
BP Group RP 12-7
LV Switchgear
(replaces BP CP 17 Part 7)
BP Group RP 12-9
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 53
BP Group RP 12-11
Motors
(replaces BP CP 17 Part 11)
BP Group RP 12-16
BP Group GS 112-5
BP Group GS 112-6
BP Group GS 112-8
BP Group GS 112-9
BP Group GS 160-1
UK Law
Electricity supply Regulations (1988)
Electricity at work Regulations (1989)
RP 12-3
ELECTRICAL SYSTEMS AND INSTALLATIONS
POWER SYSTEM DESIGN
PAGE 54