Enter Project Name in File, Info, Project Information,Summary

Enter your company name in Project Information


ID

Task Name

Dur

Preliminaries

Start

Finish

Predecessors

98days 20 Mar '1715 Aug '17

Contract Award

0days

20 Mar '1720 Mar '17

Mobilise

4days

20 Mar '1723 Mar '17 2

Relocate site huts to Warehouse, remove


3days
hardstanding
11 Aug '17
& temporary
15 Aug '17crossover
20,21,22

4
5

Demolition & Excavation

67days 24 Mar '17 6 Jul '17

Clear rubbish

2days

24 Mar '1727 Mar '17 3

Remove shed, demolish floor & drive 7days

28 Mar '17 5 Apr '17 6

Excavate topsoil & dispose surplus

9
10
11

14

4days

6 Apr '17 12 Apr '17 7

Excavate site to U/S FCR

5days

13 Apr '17 21 Apr '17 8

Install Sewers, Drains & Services

13days

24 Apr '1712 May '17 9

Place & compact 200mm FCR

5days

29 Jun '17 6 Jul '17 10,40,41

Excavate portal footings & grd beams 7days

12
13

Warehouse
Concrete (including forms & rebar)

13 Apr '17 26 Apr '17 8

71days

27 Apr '17 10 Aug '17

71days

27 Apr '17 10 Aug '17

15

Portal Footings

5days

27 Apr '17 3 May '17 12

16

Cure portal footings

7edays

3 May '17 10 May '17 15

17

Ground Beams

7days

27 Apr '17 5 May '17 12

18

Cure Ground Beams

7edays

5 May '17 12 May '17 17

19

Floor Slab w'house

16days

23 Jun '17 17 Jul '17 25,27,24

20

Truck Apron & washdown

12days

18 Jul '17 3 Aug '17 19

21

Truck Crossover

6days

18 Jul '17 25 Jul '17 19

22

Cure Apron and crossover

7edays

3 Aug '17 10 Aug '17 20,21

23

Structure & Roof

29days 11 May '1722 Jun '17

24

Precast Conc Wall Panels

3days

25

Structural Steel w'house

15days 11 May '1731 May '17 16,17

26

Roller Shutter Doors

4days

7 Jun '17 13 Jun '17 24

27

Roof Plumbing

14days

1 Jun '17 22 Jun '17 25

58days

9 May '17 2 Aug '17

58days

9 May '17 2 Aug '17


9 May '17 15 May '17 12,17

28
29

Office
Concrete (including forms & rebar)

1 Jun '17 6 Jun '17 25,16,18SS

30

Ground Beams

5days

31

Cure Ground Beams

7edays 15 May '1722 May '17 30

32

Floor Slab & cure

9days

23 Jun '17 6 Jul '17 37,36,27

33

Car Park Apron & cure

11days

18 Jul '17 2 Aug '17 19

34

Car park Crossover & cure

8days

35

Structure & Roof

18 Jul '17 27 Jul '17 19

9days

16 May '1726 May '17

36

Precast Conc Wall Panels

3days

23 May '1725 May '17 37,31,16

37

Structural Steel office

5days

16 May '1722 May '17 30

38

Roofing office

4days

23 May '1726 May '17 37

39

Utilities & Fitout

56days 15 May '17 4 Aug '17

40

Sanitary Plumbing

4days

23 Jun '17 28 Jun '17 44SS

41

Electrical & Data utilities

4days

15 May '1718 May '17 9,10

42

Painted lines to carpark

2days

3 Aug '17 4 Aug '17 33

43

Office Windows & Doors

5days

19 May '1725 May '17 41

44
45

Office Ammenities Fitout


Landscaping

15days

23 Jun '17 14 Jul '17 27,38,43

16days

3 Aug '17 24 Aug '17

46

Concrete Kerb

8days

3 Aug '17 14 Aug '17 33,34

47

Garden Topsoil

2days

15 Aug '17 16 Aug '17 46

48

Planting

6days

17 Aug '17 24 Aug '17 47

49

Acceptance

18days 25 Aug '17 20 Sep '17

50

Clean up & demobilise

6days

25 Aug '17 4 Sep '17 45

51

Completion inspection

2days

5 Sep '17 6 Sep '17 50

52

Allowance for Wet weather & delays 10days

7 Sep '17 20 Sep '17 51

53

Handover

20 Sep '17 20 Sep '17 52

Task

20 Mar '17
27 Mar '17
3 Apr '17
10 Apr '17
17 Apr '17
24 Apr '17
1 May '17
8 May '17
15 May '17
22 May '17
29 May '17
5 Jun '17
12 Jun '17
19 Jun '17
26 Jun '17
3 Jul '17
10 Jul '17
17 Jul '17
24 Jul '17
31 Jul '17
7 Aug '17
14 Aug '17
21 Aug '17
28 Aug '17
4 Sep '17
11 Sep '17
18 Sep '17
S MTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S MTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S

0days
Milestone

Author: Enter your name in Project Information

Summary

Deadline

Critical

Progress

Total Foat

Neg Float
Page 1 of 1

Printed on: 23 Sep '16