Project Name:
PROJECT DETAILS
Details
CONSTRUCTION
Employer:
Commited Value
Engineer:
Commencement Date
Engineer's Representative:
Contractor:
Original Duration
Scope of Works:
Planned (%)
Actual (%)
RFIT STATUS
Description
VAR.
Nos.
Description
Submitted
Submitted
Days Delay
Approved/Accepted
Approved
Approved as Noted
Rejected/ Canceled
Pending
Status
FINANCIAL STATUS
Advance Payment
Amount
Remark
Remarks
CONSTRUCTION PROGRESS
ITEM
OVERALL PROGRESS
PRELIMINARIES
ENGINEERING
CONSTRUCTION
GENERAL
UTILITIES WORKS
WEIGHT
PLANNED
ACTUAL
VARIANCE
SPI%
PLANNED
START
FINISH
STRUCTURAL WORKS
Progress
ROAD WORKS
Site Activities
Issues/ Risk
AREAS OF CONCERN
DESCRIPTION
CONSTRUCTION DETAILS
MAINTENANCE DETAILS
REPO
Time Elapsed
Duration
0 DAYS
Time Remaining
% Time Elapsed
Material
Submitals
Method
statements
celled / Rejected
Shop Drawings
AJC
Status
Issued
Closed/App.
Canceled/Supersede
Safet
Issued to Contractor
Closed
R
Item
Man. Hrs(weekly)
Equip. Hrs
S-CURVE
ACTUAL/FORECAST
START
FINISH
REMARKS
8%
7%
6%
5%
4%
4%
3%
2%
1%
0%
-1%
PROJECT LAYOUT
Prepared by
xxxxx
xxxxx-xxxx-xxxxxx-xxxx-xxx-xxx-xxx
REPORTING DETAILS
Reporting Cut-off Date
Time Elapsed
Time Remaining
% Time Elapsed
Quality Issues
NCR's
CAR's
Resource Status
Planned
Actual
100%
90%
80%
70%
60%
50%
50%
40%
30%
20%
10%
0%
Progress Photos
Checked by
Approved by
xxxx
xxxxx