discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/264732454
CITATION
READS
92
3 authors, including:
Eduardo Pilo
Ignacio Gonzlez-Franco
26 PUBLICATIONS 89 CITATIONS
8 PUBLICATIONS 14 CITATIONS
SEE PROFILE
SEE PROFILE
I. INTRODUCTION
First version of this paper was submitted for review on December 2013.
Eduardo Pilo is with EPRail Research and Consulting
(http://www.eprail.com) and a visiting professor at Department of Electrical
and Computer Engineering, University of Illinois at Chicago, USA (e-mail:
eduardo.pilo@eprail.com, epilod2@uic.edu).
Sudip K. Mazumder is with the Department of Electrical and Computer
Engineering, University of Illinois at Chicago, USA (e-mail:
mazumder@uic.edu).
Ignacio Gonzlez is with the Spanish Foundation of Railways, Madrid,
Spain (e-mail: igonzalez@ffe.es).
2
modifies the power distribution in a usual railway grid.
Section IV proposes an optimization-based methodology to
decide the dimensioning of the new elements to be installed.
Its purpose is to evaluate the improvements that can be
achieved with this technology, and therefore, its pertinence.
This optimization methodology is then applied in Section V
using a case study based on a 550-km section of the MadridBarcelona high-speed line and the results are analyzed.
Finally, Section VI outlines the conclusions of this work.
II. POWER SUPPLY SYSTEMS USED IN RAILWAYS
Industrial-frequency RPSs are normally split into several
feeding sections (FS), each of which is fed from the threephase public transmission or distribution grid (PTDG)
through a single transformer located in a traction substation
(TSS). Neutral zones (NZ) are used to ensure electrical
insulation between adjacent FSs.
Depending on the railways requirements, the FSs can be
fed with the single-phase system with a neutral (referred to
as 1x) or the unbalanced two-phase autotransformer (AT)
based system with a neutral (referred to as 2x), as illustrated
in Figs. 1 and 2, respectively.
R
S
T
Traction
substation
kURS
Traction
substation
kURS
kUST
kUTR
Train
Negative
Sneg,1=Pneg,1+jQneg,1
Sneg,2=Pneg,2+jQneg,2
Positive
Spos,1=Ppos,1+jQpos,1
Traction
substation
kUST
kUTR
Side 2
Spos,2=Ppos,2+jQpos,2
Neutral
Neutral Zone
Traction
substation
Traction
substation
PTD
(TSS-PTD)
PTD
(NZ-PTD)
Traction
substation
PTD
(TSS-PTD)
PTD
(NZ-PTD)
PTD
(TSS-PTD)
EMS
Traction
substation
kURS
kUST
kUTR
Traction
substation
Traction
substation
Traction
substation
Train
Neutral Zone
PTD
(TSS-PTD)
PTD
(NZ-PTD)
EMS
PTD
(TSS-PTD)
PTD
(NZ-PTD)
PTD
(TSS-PTD)
EMS
3
B. Description of operation of the modified system
The power-balance expressions can be established for the
general case (PTDs with star topology, with a higher
number of terminals):
s
N
(1)
s=1 p{pos,neg} p,s = 0
where is the number of sides of the PTDs.
For the two-side PTDs represented in Fig. 3, = 2 and
Eq. (1) becomes:
pos,1 pos,2 + neg,1 neg,2 = 0
(2)
The power balance can also be expressed as a function of
voltages and currents at the terminals of the PTDs using the
following expression:
(3)
=1 {,}(V, , ) (I, , + , )
where V, and I, are the voltage and the input current
modules respectively in the terminal (, ) (side and
phase of the PTD), , is the angle of the voltage in the
terminal (, ), , is the angle between the voltage and the
current in the terminal (, ), symbol represents the
conjugate operand.
If the angle , is taken as the reference in each terminal,
(3) can be expressed as follows:
(4)
=1 {,}(V, 0) (I, , )
Finally, if each phase is managed separately avoiding any
power transfer between different phases, (4) becomes:
NZ-PTD
IPTD,3,t
TSS-PTD
IPTD,2,t
NZ-PTD
IPTD,5,t
TSS-PTD
IPTD,4,t
IPTD,k,t
Sector k
I [A]
IPTD,k-1,t
IPTD,k+1,t
Shifted +IPTD,k,t
Isup,k,t
w/o
Isup,k,t
IPTD,k,t
-IPTD,k,t
Constant-Current
Sections
(defined by current steps)
,1, )
(9)
X [m]
Shifted IPTD,k,t
w/o
Isup,k+1,t
Isup,k+1,t
X [m]
I [A]
Time tN
Sector k+1
sector k
IPTD,k-1,t
Ssup,k,t
w/o
Isup,k+1,t
+IPTD,k+1,t IPTD,k,t
sector k+1
IPTD,k,t
IPTD,k+1,t
I PTD ,k ,t
4
and (ii) the electrification to be upgraded (electrical
description of the substations and catenaries) [16].
As indicated in (10), the cost of electricity C is
dependent on the usage of energy and the capacity of power
allocated to a customer; that is,
C = E + P
(10)
where is the cost of the energy in [/kWh], E is the
total energy consumption [in kWh], is the cost of the
allotted power capacity in [/kW] and P is the allotted
power capacity. Depending on the case, and may
depend on the specific hour of the day.
The optimization determines the value of the variables
listed in Table 1 in order to minimize the economic impact
of installing and operating PTDs, which include both the
required investments but also the savings in the electricity
bill due to the proposed enhancement.
As the restrictions (17) and (15) are quadratic with the set
of variables I,, , only non-linear solvers can be used to
solve the optimization problem. Hence, the problem is
transformed into a mixed integer programing (MIP) problem
by performing a piecewise linearization of the losses in
which the auxiliary variables described in Table 2 are
considered. To make the branch-and-bound process more
efficient, SOS2 (Special Ordered Sets type 2) have been
used [17], [18].
INV
OC
I,
I,,
C
C
C
Required investments []
Operating manageable cost [], as defined in
(14)
Rated current of the PTD [A]
Current through PTD at the instant [A]
Cost of the energy losses in the catenary []
Cost of the energy losses in the transformers []
Cost of the power capacity []
, (, + , I,, + I,,
)+
, , (, , I,1, +
2
I,1,
)
(17)
where
2
, = , , ,
{, = 2 , , ,
=
and is the length of sector k .
(18)
, , (, I,1, )
(16)
where , is the set of all the CCSs within the kth FS (see
Fig. 7) at time step t, , is the current in the jth CCS of a
Fig. 9. Sampling of the losses and the currents for use with SOS2 variables
(23)
5
where , is the cost of the allotted power capacity in
[/A], assuming a given voltage in the power measuring
point.
V. CASE STUDY
To evaluate the usefulness of the proposed system, a 549
km section of the high-speed line (HSL) between Madrid
and Barcelona is considered (from km 0 to km 549.153). In
Substation
Sectors
1
2, 3
4, 5
6, 7
8, 9
10, 11
12, 13
14, 15
15, 17
18, 19
20
Location
[km]
Villaverde (1x60MVA)
0 (*)
Anchuelo (2x60MVA)
44.332
Brihuega-El Espino (2x60MVA)
86.550
Medinaceli-Las Lastras (2x60MVA) 152.417
Terrer-Vega (2x60MVA)
214.819
Rueda de Jaln (2x60MVA)
268.884
Zaragoza-Alfidn (2x60MVA)
316.434
Pealba (2x60MVA)
377.587
Montagut (2x60MVA)
430.466
L'Espluga (2x60MVA)
490.795
La Gornal (1x60MVA)
549.253
Transformer ID
System
1-ph
2-ph
2-ph
2-ph
2-ph
2-ph
2-ph
2-ph
2-ph
2-ph
2-ph
(*)
The location has been modified from its actual location, in order to
match with the topology expected by the optimization model.
6
To simplify the evaluation of the performance of the
system, the periodic traffic mesh with trains every 10 min
has been considered to operate 9 hours per day, 365 days a
year. The number of operating hours may seem a bit low,
but the frequency corresponds to a peak period.
For this average operating conditions, Table 6 shows the
estimated costs of the electricity which has been considered:
TABLE 6. COST OF THE ELECTRICITY (AVERAGED FOR >145KV, 2012,
SPAIN)
Power capacity
Energy
23.92 /kW/year
598 /A/year at 25kV
0.07 /kWh
7
TABLE 8. ECONOMIC ANALYSIS
Power [kW] a supplied by each subestation for each time step (1 step=5 s). Scenario A.
1813
2620
-34%
-4%
127
183
-2760
-1778
-31%
0
-20%
2293
192 (2%)
Power [kW] a supplied by each subestation for each time step (1 step=5 s). Scenario B.
30000
30000
Villaverde
25000
Optim
-10000
50000
Brihuega-El Espino
30000
30000
15000
10000
Optim
30000
20000
20000
20000
10000
15000
10000
15000
10000
121
109
97
103
91
85
79
73
67
61
55
49
43
37
31
25
115
20000
10000
20000
10000
15000
5000
15000
30000
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
-5000
-10000
121
115
121
115
121
109
103
97
73
67
61
55
49
43
37
31
25
19
109
103
97
73
67
61
55
49
43
37
31
25
La Gornal
Optim
No optim
Optim
20000
15000
15000
10000
10000
5000
5000
No optim
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
-5000
Fig. 14. Current supplied by TSS for each instant. Reference vs Scenario A.
-5000
Fig. 15. Current supplied by TSS for each instant. Reference vs Scenario B.
121
115
109
103
97
91
73
67
61
-10000
-10000
25000
25000
20000
-5000
30000
La Gornal
No optim
55
-5000
Optim
5000
49
5000
10000
37
No optim
5000
Optim
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
-5000
19
25000
15000
30000
No optim
25000
10000
No optim
L'Espluga
35000
Optim
20000
30000
15000
40000
Montagut
25000
43
30000
Optim
35000
No optim
20000
L'Espluga
40000
Optim
5000
-5000
-20000
31
45000
Montagut
25000
19
-10000
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
-5000
5000
0
-20000
30000
10000
0
13
121
115
109
103
97
91
85
79
73
67
61
55
49
43
37
31
25
19
13
-10000
13
25000
No optim
20000
1
30000
25
No optim
13
121
115
109
97
103
91
85
79
73
67
61
55
49
43
37
31
25
19
25000
VillaverdePealba
Anchuelo
Brihuega-El Espino
Medinaceli-Las Lastras
Terrer-Vega
Rueda de Jaln
Zaragoza-Alfidn
Pealba
Montagut
L'Espluga
La Gornal
35000
19
No optim
Optim
-10000
40000
Zaragoza-Alfidn
40000
30000
0
-5000
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
Optim
30000
50000
Pealba
35000
40000
0
-5000
40000
Zaragoza-Alfidn
No optim
50000
-5000
-10000
5000
Optim
5000
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
No optim
10000
10000
0
1
No optim
-5000
15000
13
5000
Optim
25000
15000
5000
Optim
91
20000
10000
10000
30000
20000
15000
15000
91
25000
85
No optim
85
25000
35000
30000
20000
20000
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
121
115
109
103
97
91
85
79
73
67
61
55
49
43
37
31
25
19
Optim
40000
Terrer-Vega
35000
30000
-10000
13
25000
40000
35000
30000
No optim
-10000
40000
Terrer-Vega
35000
13
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
86
91
96
101
106
111
116
121
40000
Optim
115
10000
5000
Optim
No optim
No optim
20000
10000
5000
97
Optim
No optim
20000
10000
91
Medinaceli-LasLlastras
40000
20000
Optim
15000
85
121
115
97
109
91
85
79
73
67
61
55
49
43
37
31
25
19
103
-5000
-10000
25000
Medinaceli-LasLlastras
40000
20000
1
-10000
50000
Brihuega-El Espino
-5000
85
25000
No optim
13
121
115
97
109
91
103
85
79
73
67
61
55
49
43
37
31
25
19
-5000
Optim
79
-10000
13
121
115
97
109
91
103
85
79
0
73
5000
0
67
10000
5000
61
10000
5000
55
10000
5000
49
10000
43
15000
37
15000
31
15000
25
15000
20000
19
20000
20000
13
20000
-5000
Anchuelo
25000
No optim
109
No optim
79
25000
No optim
103
Optim
73
Anchuelo
79
25000
Optim
2737
67
30000
Villaverde
390
79
30000
354
61
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
NZ-PTD
371 (4%)
55
11, 12
12, 13
13, 14
14, 15
15, 16
16, 17
17, 18
18, 19
19, 20
+5%
49
11
12
13
14
15
16
17
18
19
Scenario A Scenario B
Rated I
Rated I
[A]
[A]
16920
4110
22000
0
18865
4861
17791
0
8887
1313
19795
0
13200
234
26798
0
24380
24380
5572
-5%
43
Type
5053
37
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
NZ-PTD
TSS-PTD
Between
sectors
5293
31
1, 2
2, 3
3, 4
4, 5
5, 6
6, 7
7, 8
8, 9
9, 10
10, 11
Id
-21%
6585
25
1
2
3
4
5
6
7
8
9
10
Scenario A Scenario B
Rated I
Rated I
[A]
[A]
11837
2444
15181
0
10135
98
9207
0
9025
2861
13200
0
13200
4294
13200
0
13863
11337
13200
0
275
-32%
5696
Type
238
8375 (94%)
19
Between
sectors
350
13
Id
Reference
Enhanced system
system Scenario A Scenario B
8
power capacity costs and very similarly the losses. In this
specific case, this would be an upper bound of the
enhancement the system could reach.
In the scenario B, where real prices and a charge-off of 10
years have been considered, improvements are lower than in
scenario B. However, a reduction of 20% in the manageable
costs is reached, mainly due to the savings in the power
capacity term (-21%). To achieve this, the system is able to
route the electrical power from different substations to the
sectors where it is required. In exchange, the currents have
to cross longer distances and the electrical losses rise up
(+5%). The losses in the transformer are however reduced (4%).
VI. CONCLUSIONS
This paper has presented a system to improve the AC
railway power supply systems which have neutral zones.
The system allows an improved degree of controllability of
the infrastructure, which allows for instance power routing
in traction electrical grids. The proposed system could be an
important milestone in the railways smart grids roadmap.
The proposed system would be able to route electrical
power routing making possible new ways of operation of
railway systems, more reliable and cost-efficient.
As an example of such intelligent operation of the railway
power system, a strategy focused on the minimization of the
manageable costs of the power supply (including power
capacity and losses costs) has been considered in a study
case which corresponds to a 550km long section of the highspeed line Madrid-Barcelona. The system would be able to
reduce up to 31% these manageable costs.
REFERENCES
[1] J. O. Estima and A. J. Marques Cardoso, "Efficiency Analysis of Drive
Train Topologies Applied to Electric/Hybrid Vehicles," Vehicular
Technology, IEEE Transactions On, vol. 61, pp. 1021-1031, 2012.
[2] M. Chymera, A. C. Renfrew, M. Barnes and J. Holden, "Simplified
Power Converter for Integrated Traction Energy Storage," Vehicular
Technology, IEEE Transactions On, vol. 60, pp. 1374-1383, 2011.
[3] P. Drabek, Z. Peroutka, M. Pittermann and M. Cedl, "New
Configuration of Traction Converter With Medium-Frequency
Transformer Using Matrix Converters," Industrial Electronics, IEEE
Transactions On, vol. 58, pp. 5041-5048, 2011.
[4] M. Pea-Alcaraz, A. Fernndez, A. P. Cucala, A. Ramos and R. R.
Pecharromn, "Optimal underground timetable design based on power
flow for maximizing the use of regenerative-braking energy," Proc
Inst Mech Eng Part F J Rail Rapid Transit, vol. 226, pp. 397-408,
2012.
[5] H. Hayashiya, Y. Watanabe, Y. Fukasawa, T. Miyagawa, A. Egami, T.
Iwagami, S. Kikuchi and H. Yoshizumi, "Cost impacts of high
efficiency power supply technologies in railway power supply traction and station -," in Power Electronics and Motion Control
Conference (EPE/PEMC), 2012 15th International, 2012, pp. LS3e.41-LS3e.4-6.
[6] Y. Watanabe, T. Kaito, R. Okuda, M. Minamoto, N. Kurosawa, H.
Hayashiya and H. Yoshizumi, "Examination on application of a smart
grid technology to stations," in Power Electronics and Motion Control
Conference (EPE/PEMC), 2012 15th International, 2012, pp.
DS2d.11-1-DS2d.11-5.
[7] H. Hayashiya, H. Yoshizumi, T. Suzuki, T. Furukawa, T. Kondoh, M.
Kitano, T. Aoki, T. Ishii, N. Kurosawa and T. Miyagawa, "Necessity
and possibility of smart grid technology application on railway power
supply system," in Power Electronics and Applications (EPE 2011),
Proceedings of the 2011-14th European Conference On, 2011, pp. 110.
[8] J. Verboomen, D. Van Hertem, P. H. Schavemaker, W. L. Kling and R.
Belmans, "Phase shifting transformers: Principles and applications,"
in Future Power Systems, 2005 International Conference On, 2005,
pp. 6 pp.-6.
9
Ignacio Gonzlez Franco received his degree in
Industrial Engineering from Vigo University (Spain)
and MSc in Railway Engineering from Pontifical
University of Comillas (Spain). He has experience
in the railways sector, having taken part in different
research projects. He is currently writing his
doctoral thesis in this optimization of transport
infrastructures. He is currently the coordinator of the
Energy and Emissions in Railways Research Group
and the Technical and Economic Transport Operations Research Group, in
the Spanish Railways Foundation (FFE).