Anda di halaman 1dari 6

CHAPTER XVI

COMMISSIONING OF RAILWAY PROJECTS


Commissioning of new lines
1601

Commissioning of New Lines-opening for Goods Traffic

1602

Arrangements to be made before opening of line to goods traffic

1603

Responsibility of the Construction Engineer

1604

incidence of Operating Expenses and Earnings

1605

Opening for Passenger Traffic

1606

Fixing date for opening for Passenger Traffic

1609

Handing over of New Lines to Open Line

1610

Allocation of Maintenance charges

1611

Commissioning of Doubling Projects

1615

Commissioning of gauge conversion Projects

1616

Commissioning of other Railway Projects

1617.

Taking over by Open Line

1601. Opening for Goods Traffic.-A line under construction should not be left unremunerative longer
than is a absolutely necessary. As soon as possible after the rails have been linked through a section of a
line under construction, reasonable facilities for the receipt and despatch of goods and parcels should be
provided at all the important station on that section, so that it may be opened for goods traffic, Reasonable
facilities for goods and parcels traffic at a station should include the following :-

(a) A siding or part of a siding of a suitable length set apart for the exclusive use of the goods
wagons when loading and unloading.
(b) A suitable space property dressed and free from all construction material or debris for the
stocking of inward and outward goods.
(c) A goods shed, if provision for one is included in the sanctioned estimate of the project;
otherwise tarpaulins should be provided for the protection of goods.

(d) A small office for the goods clerk when a goods shed is not provided.

(e) Office furniture according to the scale prescribed by the open line administration.

(f) A weighing machine and weights of standard types for the goods shed.

(g) Residential accommodation for the traffic staff.

(h) Supply of drinking water for the staff.

1602. The Chief Engineer (Construction) or the Senior Engineering Administrative Officer, under whose
Administrative control the line under construction is vested should fix the date of opening of the line or a
section thereof for goods traffic in consultation with the General Manager of the connected open line
administration. Before fixing the date the General Manager should arrange to have an inspection of the line
proposed to be opened for goods traffic by responsible officers of the Commercial and Operating
Departments so that they may satisfy themselves that adequate facilities will be provided before the date
fixed. He should at the same time arrange for :-

(a) the compilation and issue of the necessary rates and fare tables in accordance with regulations.
(b) advertising the opening of the line to goods traffic;
(c) the posting of the necessary goods booking clerks, etc. to all the stations to be opened.
(d) the supply of the station scale, consumable stores, form, stationery, etc. required by the goods
booking staff at call the stations to be opened.

1603. Responsibility of the Construction Engineer- The responsibility for opening a line to goods traffic
and for seeing that everything is ready for such opening rests entirely with the Chief Engineer
(Construction) or the Senior Engineering Administrative Officer, under whose administrative control the fine
under construction is vested. It is his duty to see that all stations are adequately equipped and staffed for
working of the goods traffic efficiently and cheaply. He should notify the Additional Commissioner of Railway
Safety concerned of the date fixed for opening the line for goods traffic.
1604. Incidence of Operating Expenses and Earnings.-The operating expenses (including the pay and
allowances of the traffic staff engaged) incurred in working the goods traffic on an "unopened" line (for
definition of 'opening' see paragraph 1702) are a charge against the construction estimate of the project,
and should, be debited to Capital 11970perating expenses pending opening of the line to traffic. The goods
earnings are likewise creditable to the project under the head 1198 Receipts on Capital AccountMiscellaneous Receipts.
Opening for Passenger Traffic
1605. Every new line or a section thereof should, before sanction can be obtained for its opening for public
carriage of passengers be inspected and passed by the Additional Commissioner of Railway Safety
concerned, in accordance with the "Rules for the opening of a Railway for the public carriage of passengers".
No new line or a section thereof should be offered for the inspection of Additional Commissioner of Railway
Safety until it has been completely equipped. No temporary or make-shift arrangements, however safe,
should be permitted.
1606. Fixing Date for opening for Passenger Traffic.-The date for the opening of a line for the public
carriage of passengers should be fixed by the Chief Engineer (Construction) or the Senior Engineering
Administrative Officer under whose administrative control of the line is vested, in consultation with the
General Manager of the connected open line administration so that the latter may make suitable
arrangements for working the new line for public traffic from the date fixed. After fixing the date the
Additional Commissioner or Railway Safety concerned should be invited to inspect the new line and give the
necessary permission for the opening of the line. At least one month's notice should be given to the
Additional Commissioner of Railway Safety of the date on which it is desired that the inspection should take
place.
1607. The date for the inspection of a line by the Additional Commissioner of, Railway Safety, prior to the
opening for the public carriage of passengers should in consultation with that Officer, be fixed a week or so
prior to the date of opening so as to allow time for complying. with the Inspecting Officer's requests or
recommendations before actual opening of the new line. The Chief Engineer (Construction) or the Senior
Engineering Administrative Officer under whose administrative control the new line is vested is responsible
for seeing that the new line offered for inspection of the Additional Commissioner of Railway Safety is in
every respect fit for opening by the date fixed for the inspection and is fully equipped.
1608. A new line should not ordinarily be considered fit for opening unless :-

(i) all station buildings and quarters included in the construction estimate are completed and ready
for occupation and use;

(ii) the track is thoroughly packed and boxed throughout;

(iii) all stations and locomotive yards provided in the construction estimate are completed;

(iv) all station signals, point indicators, derails or Scotch blocks are in position and in perfect
working order.

(v) all points and crossings are correctly and truly laid;

(vi) watering arrangements are complete;

(vii) All ....... Special", `W' and "B" class level crossings are manned by gatemen; and

(viii) Adequate arrangement is made for the maintenance of track and other infrastructure
facilities.

1609. Handling over of New Lines to Open Line.-All new lines should be taken over by Open line
organisation within six months of the date of opening for goods traffic. Ballasting and other residual works if
any should be got done by the open line against the construction estimates.

1610. Allocation of Maintenance Charges.--The maintenance charges of a new line is allocated


to Revenue from the date of its opening. The date of opening in the case of new line should be held to be
the date of opening for passenger traffic of the whole line included in the construction estimate. In case
there is likely to be much time lag between the date of opening of the new line for goods traffic and
passenger traffic, Board's specific orders should be obtained regarding the allocation of maintenance
charges.
Commissioning of Doubling Projects.
1611. Opening for Goods Traffic.--The new line of a doubling project should be opened to
traffic as early as possible after the rails have been linked through, to obtain financial benefits of the
investment made.
1612. Opening to Passenger Traffic.--Provisions contained in paras 1605 to 1608 will apply
mutatis mutandis to doubling projects also.
1613. Handing over of doubling projects to open line.--All doublings should be taken over by
open line organisation within six months of the date of opening to goods Traffic, Ballasting and other
residual works if any should be got done by the open line against the construction estimates.
1614. Allocation of maintenance Charges on doublings.--The doubling are usually justified
on goods traffic Kind hence the working expenses should be debited to Revenue from the date the new
double line is opened to goods traffic and earnings also credited to Revenue. If some works are yet to be
done on the date of opening to goods traffic, they should be charged to the doubling estimates.
Commissioning of Gauge Conversion Projects
1615. Gauge Conversion Projects are opened to passenger traffic straightway and provisions
contained in paras 1605 to 1608 will apply mutatis mutadis for conversion projects also.
Commissioning of other Railway Projects
1616. In the case of other projects the completion of the projects should be reckoned from the
date on which the project fulfils the purpose for which it when sanctioned was intended.

1617. Taking over by Open Line.--All such works should be taken over by the open line
organisation with the least possible delay within three months of their completion without prejudice to the
obligation of the contractors within the maintenance period prescribed under the relevant contracts.

Taking over by open Line


1618. When handing over a project or work to the open line authorities at least two copies of the
document specified in paragraphs 1620 to 1633 should be prepared. One copy of each of the documents
should be sent for record in the division and the other for record in the headquarters Office of the open line
administration.
1619. Transfer of Charge. --The charge should be made over to the open line Assistant Engineer
by the construction engineer in the manner indicated in Chapter 1.
1620. Narrative Handing over Notes under the following heads should be prepared by the
construction engineer: -(a)
General Description of the Line. --All point, of importance under several main heads of
works should be dealt with under this head. Special attention should be paid to:
curves.

(i)ruling grades, maximum curvature, compensation for grades, vertical curves, transition
(ii)

axle loads for which bridges hive been constructed;

(iii)

Number of sleepers per rail;

(iv)

type of ballast; and

(v)
list of works to be completed by the open line and charged to construction
estimates, the dates by which these should be billed and paid for being specified.
(b)
Important Bridges.--For each important major bridges a separate notes should be
prepared giving details of training works provided. Estimated discharges, maximum scour allowed for etc.;
(c)
Maintenance Notes.--Notes, in particular on special portions of banks , cuttings, catch
water drains, etc. which require special attention in monsoon or during sand storms should be prepared.
1621. List of Bridges.--This should be prepared on Form E. 1621, taking care that details

regarding founds are accurate:


Form E. 1621
LIST OF BRIDGES
Division............................
No. of
Bridge

Kilometerage and Spans


Telegraph post

Type

Standard strength of girders


Flange

Rivet
Shear

Rivet
bracing

Nature of Training
Found
works

Remarks

1622. List of Buildings.--This will be prepared on printed Form E. 1977.

1623. List of level Crossings.--This should be prepared on the following form:Form E. 1623
LIST OF LEVEL CROSSING
No.

Kilometre and
telegraph post

Chainage

Description and
class of level
crossings

Remarks

1624. List of Bench Marks.--This should be prepared in the following form:-Form E. 1624
LIST OF BENCH MARKS
No.

Value

Kilometre and telegraph post

Chainage

Description

Remarks

1625.
List of Completion Drawings.--A list of all the drawings and tracings, made over to the
open line should be prepared and signed by the construction engineer.
below:-

1626.

List of Tools and Plants Made Over.--This should be prepared in the form given

Form E. 1626
LIST SHOWING TOOLS AND PLANTS MADE OVER BY
P.W.I.. Construction to P.W. I . Open line.
Item
No.

Description

Number
handed
over

With gangs 1 2 3
4 5 6 7 8 9 10 so
on

Gate
Keepers

Work
shop
staff

PWI
Head
Trolley man

SWI
12

Handed over

Taken over..

(Signature)

(Signature)

1627. List of Permanent-Way Material Made Over as imprest.--This should be prepared in


the following form:-

Form E.1627
LIST OF PERMANENT-WAY MATERIAL MADE OVER BY
P.W.I. construction at . to P.W.I. Open line, as an imprest
Item No.

Particulars

With gangs

P.W.I.

Remark

1 2 3 4 5 6 7 8 9 10

Handed over ..

Taken over

(Signature)

(Signature)

1628. List of Petty and Consumable Stores Made Over.--This should be prepared in Form E.
1628. Petty stores, such as speed boards, clear, Boards, hand flags, etc., which are handed over to the open
line at the of Transfer should be shown in this form.
Form E. 1628
PETTY STORES HANDED OVER BY
P.W.I. . to P.W.I. .
First Equipment
Item No.

Description

Quantity or number

Remarks
(This should give notes as to distribution)

MM

Handed over ..

Taken over

(Signature)

(Signature)

1629. List of Interlocking Material Made Over.Interlocking if any, handed over by the
Construction Branch should be shown in the following form:Form E. 1629
LIST OF INTERLOCKING MATERIAL MADE OVER BY
P.W.I. construction at . to . Open
Item No.

Description

Quantity of material made over

(line)
Remarks

Handed over ..

Taken over

(Signature)

(Signature)

1630. List of Material lying at Site of Works Made Over--This should be prepared in the
following form:--

Form E. 1630
LIST OF MATERIAL LYING AT SITE OF WORKS ON
Construction made over to. . . . . . . . . . . . Division Open Line.
Item
Telegraph
No. post chainage

Ballast

Bricks

Brick Stone

1st 2nd 3rd

C.m. C.m.

No. No. No.

Bricks
bates

Lime

Surkhi

C.m.

C.m.

C.m.

Sand And as on

Remarks

C.m.

1631. List showing Maintenance Labour and Staff Transferred to Open Line--This statement should
show the name, father's name, rate of pay and date of appointment of the employees who are on
maintenance duty at the time of handing over and transferred to open line.
1632. Track Renewal Graphs--These should be prepared in accordance with the rules
prescribed by the open line administration.
1633. Statement showing Route and Track Kilometrage--This statement should show:-(a)

route Kilometrage;

(b)
track Kilometrage (which usually differs slightly from the route Kilometrage, the
latter being from the centre of station to centre of station);
(c)
siding
Commercial sidings; and

Kilometrage

(which

should

show

(i)

Operating

(d)

total sidings and

(d)

total kilometrage of tracks, i.e. total of (b) and (c).

(ii)

sidings,

(iii)

It should be noted that (b) "Track kilometrage" should correspond exactly with the track renewal
graph. This statement should be prepared in the form given below:-Form E. 1631
STATEMENT SHOWING KILOMETRAGE OPEN TO END OF... ON. RAILWAY
CONSTRUCTION.
Particulars

Route--Kilometres
Main
Line

Branch
Line

Total

Track--Kilometres
Main Line

Branch
Line

***********

Siding
Total track Remarks
Kilometres Kilometres
Total

Anda mungkin juga menyukai