(Final Draft)
Prepared by:
ZTS Environment and Development Consulting
Engineers
In association with
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Table of Content
LIST OF ACRONYMS .................................................................................................................6
EXECUTIVE SUMMARY ...........................................................................................................9
1. INTRODUCTION ...................................................................................................................10
2. BACKGROUND AND PROJECT JUSTIFICATION ........................................................12
2.1 OBJECTIVES ............................................................................................................................................................... 12
2.2 OBJECTIVE OF THE ESIA STUDY ..................................................................................................................................... 12
2.3 SCOPE OF THE ESIA STUDY ........................................................................................................................................... 12
Page 2
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
5. METHODOLOGY .................................................................................................................50
6. DESCRIPTION OF THE PROJECT ENVIRONMENT....................................................53
6.1 PHYSICAL ENVIRONMENT .............................................................................................................................................. 53
6.1.1 Climate ........................................................................................................................................................... 53
6.1.2 Topography of the project area...................................................................................................................... 54
6.1.3 Geology of Addis Ababa and its Surrounding................................................................................................. 55
6.1.3.1 Geology and Soil type of Sendafa Land fill site........................................................................................... 57
6.1.3.2 Geology and soil type of Bole Arbasa Transfer station site ....................................................................... 58
6.1.3.3 Geology and soil type of Koshe Transfer station site .................................................................................. 58
6.1.3.4 Geology and soil type of Akaki Transfer station site................................................................................... 59
6.1.4 Hydrology of the project area ........................................................................................................................ 60
6.1.4.1 Hydrology of the Sendafa Sanitary Landfill Area........................................................................................................60
6.1.4.2 Hydrology of the Bole Arbasa Transfer Station Area..................................................................................................61
6.1.4.3 Hydrology of the Koshe Transfer Station Area ...........................................................................................................61
6.1.4.3 Hydrology of the Akaki Transfer Station Area ............................................................................................................62
7. ANALYSIS OF ALTERNATIVES........................................................................................82
8. ENVIRONMENTAL IMPACT IDENTIFICATION, PREDICTION AND ANALYSIS 84
8.1 THE POSITIVE IMPACTS ................................................................................................................................................. 84
8.1.1 Impact on public health of the wider city ....................................................................................................... 84
8.1.2 Impact on public health of the residents of the five towns in Oromia special zone ....................................... 85
8.1.3 Impact on improvement of the overall solid waste management system of the city .................................... 86
8.1.4 Improvements on enhancing and formalizing ISWM ..................................................................................... 86
ZTS-EDCE & MTS
Page 3
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
8.1.5 Improvement on overall environmental quality and property value around Koshe....................................... 86
8.1.6 Employment creation ..................................................................................................................................... 87
8.1.7 Income generating and small businesses ....................................................................................................... 88
8.2 THE NEGATIVE IMPACTS ............................................................................................................................................... 89
8.2.1 Impact of leachate on the surface and ground water resources.................................................................... 89
8.2.1.1 Impact of Leachate on surface water resources ........................................................................................................90
8.2.1.2 Impact of Leachate on ground water resources ........................................................................................................91
Page 4
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
10.1.2 Responsibility for the implementation of ESMP in the construction phase................................................ 143
10.1.3 Responsibility for the implementation of ESMP in the operation phase .................................................... 144
Page 5
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
List of Acronyms
AACG EPA
AACG
AACMA
AARDPO
AAWSA
BOD5
CIS
COD
CSE
CW
Constructed Wetland
dB
Decibel
EHS
EIA
EPA
EPE
ESIA
ESMF
EWNHS
FDRE
FWSF
GHG
GIIP
GSE
HDPE
HSSF
IEC
IFC
LAEPB
Page 6
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
LEL
LFG
Landfill Gas
LTP
MoEF
MSE
NGO
NMOC
NIMBY
NSR
NUSWMS
OHS
PAP
PPE
ppm
RPF
STDs
SWM
UEL
UV
Ultra violate
VOCs
WWDCE
Page 7
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
List of Tables
Table 1: Geographical coordinates of the Sendafa landfill site
Table 2: Design dimension and function of the blocks of the transfer station
Table 3: Monthly Mean temperature (0c) and average rainfall (mm) data for 6 years (2007-2012) from Bole
Meteorological
Table 4: Average Monthly wind speed (km/hr) of 6 years (2007-2012)
Table 5: Population by sub city and number of kebelle
Table 6: Health professional by qualification
Table 7: Top ten diseases
Table 8: Showing school enrolment by gender
Table 9: Ratio of school boys to girls
Table 10: Population of the towns in Oromia Special zone
Page 8
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Executive Summary
Page 9
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
1. Introduction
Addis Ababa, the capital of Ethiopia, is one of the recently flourishing cities in Africa.
Encompassing nearly 3 million inhabitants in its area of 540km2 with a comfortable average
temperature of 160C and an altitude of 2500m above sea level, Addis Ababa is becoming the
attention-getting of many international agencies, tourists, and diplomatic corps to mention few to
live, work in and visit. Geographically, Addis Ababa is located in 8055 & 9005 North latitude and
38040 & 38050 East latitude.
Historically passing through different administrative restructurings, Addis Ababa now is managed
by four governmental hierarchies- The City Council and The City Government (Administration) at
the top, the Sub cities (10 in number) in the middle and Woredas (equivalent to districts) at the
bottom. Though Addis Ababa is astonishingly booming, the poor waste handling and management
practices both by the public and the municipality are putting their shadows on its international
image and development. Its causes are numerous and interwoven in nature attributed to an
individual inhabitant, the community, and the administrative level. Uncontrolled disposal of wastes
in general and solid wastes in particular to the earth, water, and air will seriously affect the health
of the growing, producing and elderly citizens of the City. Moreover, it will decrease the
productivity of the land, and change the image of the city as a capital of an exemplary country of
independence to Africans and a sit for different local and international organizations. Hence, the
need for integrated management approach and up-to-date collection, transport and controlled
removal of solid wastes in an organized landfill is necessary to avert these problems.
The development of well designed and planned solid waste disposal site that could address the long
term desire of the city is now under implementation. In this respect, the city has identified waste
management sites, namely, construction of new sanitary land fill at Sendafa, construction of three
transfer stations in Koshe/Repi, Bole Arabsa and Akaki. The construction of the Sendafa sanitary
land fill and three transfer stations is expected to respond to the long awaited problem of the city. In
addition since the services of the proposed solid waste project extends to cover Sebeta, Burayu,
Sululta, Sendafa, and Gelan towns, it will also respond to the emerging needs of these five towns
of Oromia Special Zone for such appropriate solid waste management facilities and services.
Environmental and Social Impact Assessment (ESIA) is a process for examining the environmental
and social consequences of a proposed development project. The ESIA process is designed to
ZTS-EDCE & MTS
Page 10
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
provide decision makers and stakeholders with adequate information to manage responsibly the
environmental and often social consequences of their actions. The present ESIA report is prepared
for the new Sendafa Sanitary Landfill and three transfer stations to be developed by the Addis
Ababa Solid waste management project. The stated project is implemented by the Addis Ababa
City Administration in cooperation with French Development Agency. The present ESIA report is
prepared to respond to the requirements of the National and Regional Environmental Impact
Assessment (EIA) legislations by meeting relevant International standards.
While undertaking this ESIA study due considerations were given to relevant International,
National and Regional requirements. Chapter one to three of the ESIA study report presents
information that introduces the proposed development project, its objectives and describes the key
components of the Solid waste management project. The baseline data reflecting the current status
of the physical and social environments of the project area are outlined in chapter six. Whereas
identification and analysis of all potential environmental and social impacts are thoroughly
discussed in chapter eight, the proposed mitigation measures for the major and significant adverse
impacts followed by the Environmental and Social Management Plan are presented in the
succeeding chapters.
Page 11
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The temporal scope of the ESIA study would mainly focus on assessing the potential impacts that
are likely to occur during construction and operational periods of the project. The environmental
and social assessment framework would identify the direct and indirect impacts on humans, flora
and fauna, soil, water, air, landscape, material assets and cultural heritage stemming from the
implementation activities of the project. It will also develop relevant mitigation/enhancement
ZTS-EDCE & MTS
Page 12
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Northing
Easting
CW0
999500.79209330
492458.49501042
CW1
999594.78457313
491843.04732505
CW2
999470.33567845
491727.10099301
CW3
997392.15479734
491784.92665263
CW4
997506.52507593
492459.67219718
Page 13
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Sendafa Sanitary
Landfill Site
Page 14
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Site Closure
Transfer Stations
The shape of the sanitary landfill site is a strip oriented in North-South direction with a natural
slope of 1.2% toward the south. It has a total area of 124.5 hectare out of which 102 hectares will
be used for the landfill development and the rest is free zone left as a buffer between the land fill
and the Bole airport. The area used for the construction of the landfill cells and leachate treatment
plant is about 82 hectares and the remaining space will be used for the development of all other
required facilities such as roads, buildings and drainages.
For preliminary planning purposes, it has been assumed that the landfill will be developed as five
cells including one for hazardous waste. Four of the five cells will be used for disposal of nonhazardous solid waste and the remaining one (cell No.5) for hazardous waste (see fig 1). Disposal
of wastes at the site will take place 12 hours a day, 6 days a week throughout the year.
The type of waste expected to be disposed in the new Sendafa sanitary landfill will be composed of
hazardous and non hazardous waste that will be generated from residential, industrial, institutional
and commercial sources as well as from service areas of Addis Ababa City, Legetafo, Sendafa,
Sebeta, Gelan and Burayu towns. However the new Sanitary landfill will not accept medical wastes
for disposal in the cells. The new sanitary land fill is expected to handle about 8,200,000 tons over
the next 20 years. It is anticipated that the life span of the new Sendafa Sanitary Landfill would be
20 years.
Page 15
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Fig 1: Showing the design layout of the new Sendafa Sanitary landfill
Access to the site will be through a newly constructed asphalt road on the north western
part of the landfill site. Approximately 170 meters of new road will be constructed from the access
road to the gate of the landfill.
Rainwater infiltration through disposed solid waste is expected to produce leachate. To prevent
infiltration of leachate into the ground that may pollute the soil and the groundwater, the bottom and
slopes of the constructed cells will be covered with active and passive barriers. The proposed liner
systems for active and passive barrier will have the following specifications;
-
Active barrier: The active barrier will be created by placing a 2mm thick HDPE geomembrane on the whole bottom surface of the cells. For the cell receiving hazardous wastes
(i.e. Cell No. 5), the active security barrier will be reinforced by an additional smooth and
UV protected 2mm thick HDPE geo-membrane.
Page 16
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
For checking the integrity of the active barrier system, a 15cm sand layer with slotted
HDPE pipes within it will be placed between the two HDPE geo-membranes. This will serve as
leakage detection layer. The pipes will lead to a leakage control manhole that will be checked
on a monthly basis as soon as the first raw of hazardous waste will be disposed of.
Page 17
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
(c)Wetland
A constructed (or engineered) wetlands (CW) is planned to be constructed to grow wetland
vegetation to assist in treating wastewater in a more controlled environment than what occurs in
natural wetlands. The pollutants removed by CWs include organic materials, suspended solids,
nutrients, pathogens, heavy metals and other toxic or hazardous pollutants. The choice has been
made to design a Horizontal Sub-Surface Flow (HSSF) system as the efficiency is higher than a
Free Water Surface Flow (FWSF) for the same plan area.
A drainage layer will be placed all over the bottom liner system and at the bottom of the cells and
on the side slopes. To avoid clogging and capillary action holding water in the drainage layer,
coarse material is used so that there is space within the drainage layer for leachate to drain freely.
A layer of 50 cm of gravels (with low CaCO3 content to prevent degradation by acidic leachate)
will be laid on top of the protection geo-textile (last layer of the Liner System) .The size of the
gravels will be 16/32mm. A geo-textile filter will be placed over the drainage layer to protect it
from clogging as a result of solids transport.
Since it is impossible to place 50cm of gravels on the side slopes, a geo-composite side slope
drainage layer with at least the same hydraulic conductivity will be placed. The geo-composite for
drainage will be composed of a HDPE core bonded on both sides by a non-woven filtration geotextile. The thickness of this geo-composite for drainage will never be less than 7.5mm.
At the bottom of the slopes, the geo-composite will be laid below the granular drainage layer, with
a minimum length of 1.5m, allowing for a safe discharge of sides slopes collected leachate into
the bottom LCRS.
Slotted collection pipes will be laid (embedded) within the gravel layer in such a manner that
the leachate will be drained within the gravels layer to these slotted pipes. Maximum spacing
between pipes varies. The slotted pipes will be connected to HDPE collectors (full pipes) at the
base of the slopes at each low point of cells.
The collectors shall lead to HDPE transmission pipes in the peripheral trenches near the ground
level and along the perimeter bunds. These pipes will lead the leachate by gravity to the
downstream part of the site.
ZTS-EDCE & MTS
Page 18
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
For the operation of Cell 1, the Leachate Treatment Plant will be fed by gravity only whereas for
the other Cells the gravity collector pipes will lead to a pumping manhole downstream of the
site, where a pump will be installed in order to feed the Leachate Treatment Plant. The maximum
leachate inflow at the LTP inlet will be controlled so as to never get over 650m3/day. Control
valves will therefore be installed on the feeding pipe and assure that this maximum flow is never
exceeded.
Page 19
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
profiled cap. Finally, the external slope of the peripheral bunds will be covered with local
vegetation at their installation whereas the surface of each cell will be covered as soon as the height
of waste reaches its final dimension.
Vertical pumping wells drilled within the waste body. Each well has a radius of about 30
meters. Each cell would have about 25 wells. These wells could also be used for leachate
pumping in case of clogging or breakdown of the bottom leachate drainage system;
Horizontal network of HDPE pipes connecting the wells to the extraction system and
the flare;
Blower creating a negative pressure in the LFG network for LFG extraction and
Flare burning the gas and converting the hazardous methane gas into CO2 reducing the
impact on global warming;
The LFG system including drilling of the wells will be constructed with the final cover at the end
of the lifetime of each cells or sub-cells. The LFG collection pipes are necessary to get the
vacuum to the wells and get the gas from the well to the flare.
Page 20
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Consulting, also in charge of the works supervision and contract management on behalf of
AACA. In addition a new 170 meter long access road will be connecting the entrance gate of the
sanitary landfill site to the main road at the northwest corner of the site.
A gate will be constructed across the entrance and instructions to the vehicle drivers delivering
the waste to the site will be put in place. A road 7.0 m wide with a two-lane cross section will be
constructed on the top of the bund between cells 1 and 2/3 and between Cells 4 and Cells 1/2/3.
These roads will be asphalted and the remaining bund crests will be gravel-surfaced so as to
allow for maintenance vehicle to access if needed.
Potable water to the landfill site will be provided from two water storage tanks of 10 m.cu
capacity that will be constructed next to the building facilities area. Moreover, electricity to
the site will be provided through an on-site generator owned and operated by the Landfill
operator.
The fencing of the entire sanitary landfill site with concrete pole and barbed wire has been
implemented already and is well underway. The fence is planned to be completed well before the
commencement of civil works of the sanitary landfill development. Weighbridges and gatehouse
are to be provided close to the entrance of the site to control access and record quantities and types
of the incoming waste. A guard house will be provided for the weighbridge attendant.
Trucks wheel cleaning is required to remove litter and mud at the tipping face of the waste
collection vehicles. The release of this mud and particularly litter on the site access road will create
an unacceptable environmental impact. To minimize such impact concrete hardstand for a highpressure washer will be provided.
An administration building will also be constructed close to the entrance and will provide offices
for the management and administration staff as well as meeting room, locker room and toilet for
operators. Shades will also be constructed for the maintenance of equipment and protection of
vehicles from direct sunlight.
Page 21
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Any excavated soil not utilized immediately will be stockpiled on site for future use. Stockpiling
will be the sole responsibility of the landfill operator. Any surplus of soil from excavation will be
used for daily, intermediate, and final cover on the landfill areas. Soil will also be needed for road
construction, any required backfilling operations, and berms. Sources of soil will include all
excavations within the site boundaries. As the south-western part of the site can be utilized neither
for any landfill cell nor for any leachate treatment facilities, it will only serve as borrow area for any
filling works both during construction and operation.
In case of a lack of suitable material from the landfill construction excavations, the following
borrow sites and quarries sites has been identified.
Clay material is found in a borrow area located 2km away from the landfill in the north-east
direction (493654E and 999834mN)
Gravel material is available within 3-4km radius of the Landfill site. The material is coming
from the basaltic rock formation which is moderately weathered. The site is currently used
as aggregate quarry site for gravel road construction
Typically, these functions will be performed by landfill compactors and wheeled loaders. A pick-up
truck will also be included in the typical on-site equipment fleet. Other functions requiring
equipment are landfill cell preparation, final cover construction, delivery of drop-off bin wastes to
the working face, road maintenance, and dust control. Some of these functions may be performed
ZTS-EDCE & MTS
Page 22
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
with on-site equipment, but others may require equipment to be leased or a contractor to be hired.
Routine maintenance and cleaning will be performed as necessary to keep onsite equipment in good
operating order.
In areas where land filling has been temporarily discontinued for six months or more, soil will be
placed to minimum thickness of 300 mm as intermediate cover. This intermediate cover will
facilitate the movement of equipment and prevent the exposure of waste from erosion. Intermediate
cover will be placed on the top of each lift of waste and on any interior slopes that will not be
disturbed until the next land filling stage.
Page 23
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
order to avoid confusion, the main blocks are listed in table 2 as Block 1 to 7. In addition the blocks
in each transfer station are equipped with the required basic facilities for the staff working in the
stations.
Block No.
Akaki
Bole Arabsa
Koshe
Block 1
1000 m2
1130 m2
1130 m2
Sorting room
Block 2
128 m2
128 m2
128 m2
Block 3
139.84 m2
165 m2
165 m2
Maintenance workshop
Block 4
12 m2
12 m2
12 m2
Generator House
Block 5
12.25 m2
30 m2
30 m2
Block 6
900 m2
1052 m2
2070 m2
Block 7
33 m2
33 m2
33 m2
Table 2: Design dimension and function of the blocks of the transfer station
Block 6 will consist of a shed where the 8m3 skip trucks unload the solid waste hauled from
different parts of the city to the transfer stations. Block 6 also serves as a loading ground for the
30m3 trucks that haul the solid waste to the sanitary landfill. The mode of operation of the proposed
transfer stations are designed to have low level of sophistication. Its operational mechanism will
fundamentally consist of depositing the waste onto a suitably designed platform for manual loading
into the large long-haul vehicle by scraping waste from the floor by front end loader. Access roads
for unloading trucks (8m3) and for loading trucks (long haul vehicles) will be separated. All the
access ways will be asphalt road and the manoeuvrings areas (loading & unloading docks) will be
paved with concrete slab (see fig. 3). The long haul trucks to be applied will be open top trailers that
unload by tipping in the Sanitary landfill cells. Loading will be achieved by front-end loader in the
transfer stations.
The catchment area for each transfer station is defined based on sub city limits while giving due
consideration to maintain the collection areas to be as close as possible to the transfer stations by
ZTS-EDCE & MTS
Page 24
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
taking into account distance between sub-cities and expected outlets. For those sub-cities or Oromia
special zone towns situated close to the Sanitary landfill (Such as Sendafa and Legetafo towns),
waste will be hauled directly from skip point to the landfill. According to the traffic flow analysis of
the detail design report of the transfer stations, about 333 trips of the 8m3 skip trucks and 34 trips of
the 30m3 long haul trucks are expected to be handled daily in each of the transfer stations.
The transfer station design have also incorporated a large shade (i.e. block 1) for undertaking waste
sorting activities where wastes will be segregated for recovery, reuse and recycling. On the other
hand, tracks that will be engaged in the transportation of wastes from the City to the transfer station
and then to the sanitary landfill will be maintained in block 3. The incoming trucks loaded with
waste will be weighed in Block 5 of the control room. The site layout of Bole Arabsa transfer
stations is shown in fig 2 as typical demonstration.
There will be fence around the transfer station sites and the length of the fences around Akaki,
Koshe and Bole Arabsa transfer station sites is about 2082 meters, 1820 meters and 1207 meters
respectively.
Page 25
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 26
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Fig 3: General layout of the transfer shade (Block 6) of Koshe Transfer Station
Page 27
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 28
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
part of the site is bounded by the ring road that already has its own drainage system, storm water
flow is not expected to enter into the transfer station area from outside.
Koshe transfer station is partially operating landfill site. The Koshe landfill site will be rehabilitated
in two phases. The first phase of 19 hectares will be rehabilitated with the aim of optimization of
the transportation of waste to the future Sendafa Landfill site. The site is characterized by organic
soil and rhyolite rock formation. The organic soil is characterized by partly decomposed waste
material with little clay and thickness of 10 to 80cm. Below the organic soil, there is rhyolitic
volcanic rock. Koshe site lies on Rhyolite rock formation that extends up to 7 meters deep. Koshe
transfer station site is located on zone 2 seismic zone of Ethiopia with pick ground acceleration of
0.1g.
Fig 5: Partial view the open land in Koshe/Repi for transfer station site
Page 29
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
moderately weathered rock and has moderate strength. Akaki and Bole Arabsa Sites are located on
Zone 3 of seismic earthquake zone with peak ground acceleration of 0.15g.
Page 30
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 31
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Article 92 of the Constitution states that the design and implementation of any program and
development projects shall not damage or destroy the environment, and people have the right to be
fully consulted and express their views in planning and implementation of environmental policies
and project.
Land resource use policy and strategies; physical land use planning.
Page 32
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
policy consists mainly of guiding principles and various sectoral and cross-sectoral policies for
sustainable environmental management.
The policy seeks to ensure the empowerment and participation of the people and their organizations
at all levels in environmental management activities, raise public awareness and promote
understanding of the essential linkage between environment and development. In addition to its
guiding principles, the policy addresses sectoral and cross sectoral environmental issues.
Environmental Impact Assessment (EIA) policies are included in the cross sectoral environmental
policies. The EIA policy emphasizes the early recognition of environmental issues in project
planning at all levels of administration. The principal features of the Environmental Policy in this
area are:
The policy establishes the Federal Environmental Protection Authority (nowadays Ministry of
Environment & Forestry) to harmonize sectoral development plans and implement environmental
management programs for the country.
Promotion of private sector and NGO participation in the provision of health care.
Page 33
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
program.
Health Sector Development Plans and Strategies have been designed to implement the stated health
principles within a defined period of time. The strategies include raising the awareness of personal
and environmental health care and sanitation through information, education and communication
(IEC); control of disease; and promotion of primary health care through community participation.
Page 34
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 35
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Licensing agencies to ensure that the requisite authorization has been duly received prior to
issuing an investment permit, a trade or operating license or a work permit to a business
organization.
The EPA or the relevant regional environmental agencies may issue an exemption from
carrying out an EIA in projects supposed to have an insignificant environmental impact.
A licensing agency may suspend or cancel a licence that has already been issued where the
EPA or the relevant regional environmental agency suspends or cancels environmental
authorization.
Page 36
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Submit an environmental impact study report to the EPA or the relevant regional
environmental agency for review.
Environmental guidelines are among the tools for facilitating the consideration of environmental
issues and principles of sustainable development and their inclusion in development proposals. To
put this Proclamation into effect the EPA issued guideline documents, which provide details of the
EIA process and its requirements. According to this EIA guideline projects are categorized into
three schedules:
Schedule 1: Projects which may have adverse and significant environmental impacts thus requiring
a full Environmental Impact Assessment
Schedule 2:
Projects whose type, scale or other relevant characteristics have potential to cause
some significant environmental impacts but are not likely to warrant a full EIA study
Schedule 3: Projects which would have no impact and do not require an EIA
However, projects situated in an environmentally sensitive areas such as land prone to erosion;
desertification; areas of historic or archaeological interest; important landscape; religiously
important area, etc. will fall under category 1 irrespective of the nature of the project.
According to this guideline all project proponents and executing bodies (agencies) in the country
should operate in close cooperation with the EPA to ensure that proper mitigating measures are
designed and implemented, especially for projects with an adverse effect on the environment. This
in effect means that an Environmental Impact Statement (EIS) should be prepared by project
proponents and be examined, commented and approved by the EPA.
Page 37
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Regional
State
Environmental
Impact
Assessment
The Oromia regional state has adopted the Federal Proclamation on Environmental Impact
Assessment after it customized it to the regional realities. The Oromia region version of the
proclamations is called Oromia National Regional state Environmental Impact Assessment
Proclamation No. 176/2012. In addition to the proclamations, the Land Administration and
Environmental Protection Bureau (LAEPB) of Oromiya is preparing detailed regulations on EIA.
The Environmental Impact Assessment Proclamation No. 176/2012 of the region clearly stipulates
the requirement for environmental assessment by stating that no person shall commence
implementation of a project that requires environmental impact assessment without the
authorization from the Bureau. The enforcement of this requirement for environmental assessment
is spearheaded by LEPB and its branch offices at Zonal, City and Woreda levels. According to the
regional proclamation, the environmental impact study report is required to contain sufficient and
accurate information that would enable the bureau to give its decision. This implies that the EIA
report is expected to contain all necessary information that is relevant to the project site, nature and
characteristics of the proposed project, technology and its application process, direct and indirect
impacts, cumulative impacts and e.t.c. The regional proclamation also stipulates that LEPB shall
ensure the inclusion of the opinion of the public, particularly of the affected community in
environmental impact assessment study and their participation while review of the EIA is made.
The LEPB is required by the law to review the EIA study report submitted to it within ten days and
issue the authorization letter if satisfied with the report within the stated time limit.
Page 38
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
country. The law addresses the management of hazardous waste, municipal waste, the
establishment of environmental quality standards for air, water and soil; and monitoring of
pollution. The proclamation also addresses noise as one source of environmental pollution and it
seeks for standards and limits for noise providing for the maximum allowable noise level taking
into account the settlement patterns. In general, the Proclamation provides a basis from which the
relevant environmental standards applicable to Ethiopia can be developed, while sanctioning
violation of these standards as criminally punishable offences
Furthermore, it empowers the Federal Environmental Protection Authority or the Regional
Environmental Authority to assign environmental inspectors with the duties and responsibilities of
controlling environmental pollution. In order to ensure implementation of environmental standards
and related requirements, inspectors belonging to the EPA or the relevant regional environmental
agency are empowered by the Proclamation to enter, without prior notice or court order, any land or
premises at any time, at their discretion. Such wide powers derive from Ethiopia's serious concern
and commitment to protecting the environment from pollution.
Regional states may require any transit of solid waste through their region to be packed and
transported in conformity with the directives and standards issued by the concerned
environmental agency.
Page 39
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Each urban administration shall in conformity with the relevant environmental standards,
ensure that solid waste disposal sites are constructed and properly used and managed.
Without prejudice to the mandate of the appropriate agency to register, undertake annual
registration and technical inspection of the motor vehicles as well as to issue a driving
license .the conformity of any vehicle or equipment with the specifications set by concerned
environmental agency shall be ascertained by the relevant urban administration prior to its
use for solid waste management
Each urban administration shall ,without prejudice to the weight and size of the vehicles
determine under the relevant laws, set standards to determine the skills of drivers and
appropriateness of the equipment and equipment operators and to prevent overload of the
solid wastes
Urban administrations shall ensure that a solid waste disposal site that was under
construction or was constructed prior to the coming into force of this proclamation is
subjected to environmental auditing as per the relevant laws.
Urban administration shall ensure that any new solid waste disposal site being constructed
or an existing solid waste disposal site undergoing any modification has had an
environmental impact assessment according to the relevant law.
Each urban administration is responsible for ensuring that an environmental audit is carried
out on every existing solid waste disposal sites.
The owner of any solid waste disposal site shall make the necessary modification if the
environmental audit made under sub-article (1) of this article shows that its continued
operation poses a risk to public health or the environment.
The authority may prescribe environmental criteria to determine the alternative use of a
solid waste disposal site that has ceased operation or is abandoned.
The owner of any solid waste disposal site shall, regardless of fault, be liable for any
damage caused to the environment, human health or property in the course of its operation
and after its closure
Page 40
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Without prejudice to sub-article (1) of the article ,exemption from liability shall be granted
only when certified that it is the victim himself or a third party for whom the owner of the
solid waste disposal site is not responsible that has caused the damage
Any claim for damage under sub-article (1) of this article shall be barred by a period of
limitation unless thought within two years from the date on which the occurrence of the
damage is known
The major intents of the proclamation, as described in the preamble and objective, are maximizing
the economic and social benefits of waste as well as promoting decentralized waste management
services which also include a more strong involvement of the community and public at all level in
the delivery of waste management services. The proclamation considers waste as a resource, and
accords due attention to the issue of waste recycling.
4.2.8 National Rural Land Administration and Use (Proclamation No. 456/2005)
The Rural Land Administration and Use Proclamation (Proclamation No. 456/2005) defines the
state ownership of rural land and the tenure rights of the land occupant, including rights to
"property produced on his land", rights of inter-generational tenure transfer, and rights of exchange
land and limited leasing rights. Provisions are made for the registration and certification of tenure
rights. Part Three of the Proclamation presents regulations relating to the use of rural land,
particularly as it relates to soil and water conservation and watershed management. The rural land
administration and land use laws are to be implemented by the regional states.
Land holding right gives the right to use the land for agricultural purposes as well as to lease it and,
while the right remains in effect, bequeath it to family members, as well as the right to acquire
property thereon, by labour or capital, and to sell, exchange and bequeath the same. The
Proclamation also addresses environmental concerns, including non-compliance with directives on
environmental protection.
Page 41
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Article 7(3) of the Proclamation reinforces the rights of land users to compensation for the
development they have made on the land. It also states that when the land holder is evicted by
federal government, the rate of compensation would be determined based on the federal land
administration law. When the rural land holder is evicted by regional governments, the rate of
compensation would be determined based on the rural land administration laws of regions.
It is envisaged that the Proclamation will create a sense of ownership among the vast majority of
the rural population and enable them to take initiatives and collectively engage in environmental
management activities.
4.2.9 Addis Ababa City Administration Waste Management, Collection & Disposal
Regulation
This is an elaborate piece of legislation (Regulation No 13/2004) which has 9 parts and 37 articles.
Among the key concerns of this regulation are environmental pollution and public health related
issues as well as the economic importance of waste. The general spirit of the regulation is the
promotion of a more decentralized, participatory and private sector driven waste management
service delivery in the City. The regulation also provides, among others, for the establishment of
governmental organizations dedicated for waste management related affairs both at the City, SubCity and Kebele levels.
As expected, the regulation stipulates general provisions that assume detail guidelines and
directives to be developed at a later stage to enable the proper implementation of the regulation.
The regulation gives a clear definition for the term hazardous waste. Article 13 which refers to
the management and disposal of hazardous wastes, for example, stipulates that a directive shall be
issued on this issue. The regulation also stresses the need to have special authorization from the
Citys Environmental Protection Authority, although specific tools that will be used in enforcing
these provisions are not indicated.
Notwithstanding the key roles residential and business establishments in the City play in achieving
the objectives stated in the regulations, it is more explicit about the responsibility of the generators
than on the commitment of the government. Likewise, Article 27 that refers to Safety and Health
of Online Workers stipulates that taking care of the safety and health of online workers is the
responsibility of the employer, although it does not provide for specific instruments to be employed
to ensure its proper adherence. It is also worthwhile to note that Article 29, which is about
incentives, explicitly promotes the use of appropriate technology for recycling and reduction of
ZTS-EDCE & MTS
Page 42
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
waste, but it is silent about the need to provide incentives to those that adopt and/or promote OHS
practices.
The MoEF is one of the line ministries which directly report to the prime minister. The MoEF is the
key national level environmental agency, with a mandate to address environmental issues. The
environmental legislation gives the MoEF powers to fulfil its role, support all federal agencies in
establishing environmental units, and develop skills in strategic environmental analysis of policies
and public instruments. The MoEF is involved in the development of environmental policy and
legislation, setting environmental quality standards for air, water and soils, monitoring pollution,
establishing EIA procedures and an environmental information system, and undertaking capacity
Page 43
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Notification of its decision to the concerned licensing agency at or before the time specified
in the appropriate law or directives.
Making its decisions and the EIA report available to the public.
Resolution of complaints and grievances in good faith and at the appropriate time.
Page 44
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The NUSWMS places responsibility on regional and local public authorities (hereinafter referred to
as the Competent Authorities) to:
Ensure that all urban residents are provided with regular and reliable waste collection
services that meet the basic minimum requirement to protect public health.
Ensure that collected waste is managed properly, regardless of whether it is destined for
recycling, treatment or disposal, in order to protect the quality of the environment.
Catalyze the economic development of the sector in terms of growth opportunities for small
and medium sized enterprises.
The Standards have been designed to ensure that they address the above priorities and at the same
time are realistically achievable and applicable to different contexts. Competent authorities shall
ensure that basic minimum standards of SWM are implemented to acceptable levels. Competent
authorities may exceed the standards, and implement alternative conforming waste management
system types, so long as the three basic minimum goals are achieved.
For the purpose of implementing the SWM standards urban settlements are categorised as follows:
Category 1 - towns/cities with population above 500,000.
Category 2 - towns/cities with population of 100,001 - 500,000.
Category 3 - towns with population of 50,001 to 100,000.
Category 4 - towns with population of 20,001 to 50,000.
Category 5 - towns with population of 2,001 to 20,000.
Hence the new Sendafa sanitary landfill project falls under Category 1. The following are some of
the requirements outlined in the standards for class I sanitary landfill and waste transfer stations.
a. Class 1 Sanitary landfill
The following are minimum standard requirements for class I sanitary land fill.
Establishment and operation of leachate treatment through the installation of oxidation
ponds etc.
Installation of active landfill gas collection systems with flaring (or utilization) of gas.
Installation of full liner system with groundwater monitoring and control measures and
seepage control.
Page 45
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Located with sufficient void space for a minimum of 10 years operational life.
Operation in accordance with management plan.
Auxiliary and amenity facilities
Minimum area requirement shall be area required for fill volume plus ~ 40% for additional
facilities and site activities.
Approximate waste acceptance capacity = 251 500 Tones/day
Whole tyres, medical and other hazardous wastes, industrial wastes, demolition and
construction wastes (except where utilized as cover and site engineering purposes) shall be
prohibited from being disposed at such sites.
In addition the solid waste management standards require the following as a minimum for category
1 landfill management.
Competent authorities shall ensure the installation and functioning of landfill gas
management systems at all landfill sites.
As a minimum passive landfill gas venting shall be ensured at all sites.
Where possible landfill gas shall be collected and flared, and where economically
justifiable, utilized as a source of renewable energy.
Category 1 and 2 landfills will have vehicle weigh scales installed to obtain exact records of
waste quantities being delivered. Weigh scales should be installed at all other landfill sites
where possible.
b. Waste transfer
Waste transfer involves transferring waste materials from a small collection vehicle / cart to a larger
vehicle / trailer. This allows small collection vehicles to return quickly to collection routes and
maximises efficiency of transporting large volumes of waste to distant treatment or disposal
facilities through use of larger capacity haulage vehicles. The location and type of transfer station
will depend upon the location of the final disposal/treatment facilities in relation to the location of
waste production and the type of collection system implemented.
The need for and design of waste transfer systems shall be considered in regional/city SWM
plans.
Page 46
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
However, where the final disposal/treatment centre is located close to the city/town centre
say within 2-3 km, there may be no need to employ waste transfer points / stations.
Depending on the design and management regime for the transfer station, they may be
located either within or outside of the urban area.
The competent authority shall ensure an EIA is completed in conjunction with consultation
with the local residents before final selection of a transfer-station location.
Category 1 and 2 municipalities shall evaluate the need for installing and operating transfer
stations at fixed sites within the urban area where waste from primary collection services
is to be transferred into larger containers/vehicles.
The design of the transfer operation shall enable the site operations to be efficient and
hygienic.
Incoming waste shall be transferred from the transfer-station within 1 day, unless temporary
operational reasons do not permit this.
Category 3, 4 & 5 municipalities shall evaluate the use of containers at agreed collection
points utilizing a hook-lift system or a crane-tipper system as a transfer option.
Transferring waste from the ground, using a front-end loader, or similar, shall only be
undertaken as a temporary or emergency measure.
Competent authorities shall ensure that waste transfer and waste transport is undertaken
during daylight hours other than where traffic congestion is a serious concern.
Where traffic density dictates the movement of waste at night time, enhanced health and
safety procedures and equipment shall be utilized to minimise the risk of accidents and
injuries.
Size of small transfer points shall be determined by the same methodology as calculating
container sizes as detailed in Box-1 plus minimum additional area of 2 times area of
containers to accommodate transfer vehicles, ramps, etc.
Service radius of transfer stations shall be determined by maximum radius of primary
collection vehicles serving the transfer point or station.
Page 47
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The type, design, location, site area and service radius of transfer stations shall be
determined through Feasibility Study.
Transfer station sites shall have a hard standing and security fencing with gate, sanitary
facilities, water and electricity.
All waste transfer points, facilities and containers shall be kept clean and orderly at all times
with containers and site area inspected and cleaned monthly, and a total area clean
extending to 20m in all directions around entire site every quarter (3 months).
c. Health and Safety
Page 48
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
a. Overview
The Environmental, Health, and Safety (EHS) Guidelines are technical reference documents with
general and industry-specific examples of Good International Industry Practice (GIIP). The EHS
Guidelines contain the performance levels and measures that are generally considered to be
achievable in new facilities by existing technology at reasonable costs. Application of the EHS
Guidelines to existing facilities may involve the establishment of site-specific targets, with an
appropriate timetable for achieving them. The applicability of the EHS Guidelines should be
tailored to the hazards and risks established for each project on the basis of the results of an
environmental assessment in which site-specific variables, such as host country context,
assimilative capacity of the environment, and other project factors, are taken into account.
b. General waste management
The following guidance applies to the management of nonhazardous and hazardous waste.
Additional guidance specifically applicable to hazardous wastes is also presented in IFC guideline
document. Waste management should be addressed through a Waste management system that
addresses issues linked to waste minimization, generation, transport, disposal, and monitoring.
c. Waste management planning
Facilities that generate waste should characterize their waste according to composition, source,
types of wastes produced, generation rates, or according to local regulatory requirements. Effective
planning and implementation of waste management strategies should include:
Review of new waste sources during planning, sitting, and design activities, including
during equipment modifications and process alterations, to identify expected waste
generation, pollution prevention opportunities, and necessary treatment, storage, and
disposal infrastructure
Collection of data and information about the process and waste streams in existing facilities,
including characterization of waste streams by type, quantities, and potential use/disposition
Establishment of priorities based on a risk analysis that takes into account the potential EHS
risks during the waste cycle and the availability of infrastructure to manage the waste in an
environmentally sound manner
Page 49
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
If waste materials are still generated after the implementation of feasible waste prevention,
reduction, reuse, recovery and recycling measures, waste materials should be treated and disposed
of and all measures should be taken to avoid potential impacts to human health and the
environment. Selected management approaches should be consistent with the characteristics of the
waste and local regulations, and may include one or more of the following:
e. Transportation
5. Methodology
The methodology adopted for conducting the environmental and social impact assessment study
includes the conventional methods, which are briefly discussed below.
ZTS-EDCE & MTS
Page 50
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
a. Field Surveys
The method of field surveying is second to none in understanding the likely impacts of a given
development project on the particular environment around the project site. The team of
environment consultants were mobilized for field survey to the project sites several times during
the extended project period, as it was necessary to ensure a thorough assessment of the project
impacts. The team has already made observations in and around the Sendafa landfill site, Bole
Arabsa, Koshe and Akaki transfer station sites and gathered essential field data. During the field
survey information on physical, biological and socio-economic environment was collected for each
site. In addition base line data collection was done through field investigations.
b. Interviews with designing firm specialists
The ESIA team has the opportunity to closely work with the consultancy firms (i.e. Artelia in
association with Metaferia Consult) that were in charge of designing the Sanitary landfill and
transfer stations project. The team discussed project detail designs and processes with the engineers
at different stages of the designing process. This has enabled the ESIA team to provide its inputs
and positively influence the design process to make it more environment friendly. In due course
extensive discussions were also made with the project management to develop common
understanding of the main components of the project.
c. Literature review
Information on existing environmental conditions was obtained from review of various published
and unpublished sources. In addition review of detail design reports and drawings of the new
sanitary landfill and transfer stations, national and regional policies, legislations and standards as
well as the World Bank Safeguard Policies, IFC-EHS guidelines on waste management, relevant
ESMF and resettlement policy framework (RPF) documents were also reviewed.
d. Competent authority guidelines
The Federal, Addis Ababa and Oromia Region EPAs legislative and institutional framework,
policies, procedures, standards, guidelines etc. are also reviewed and consulted. The recent draft
solid waste management standard hand books issued by the Ministry of Urban Development,
Housing and Construction were also extensively consulted. Sociological and environmental data
were gathered by discussing and filling questionnaires with the experts in concerned government
agencies. These include the Bereh woreda sector offices and Addis Ababa City Administration
ZTS-EDCE & MTS
Page 51
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
health, education, urban agriculture, culture and tourism, Water Supply and Sewerage, Cleansing
Management Agency, as well as the Addis Ababa Recycling and Disposal Project Office were
consulted.
e. Sampling and Monitoring
Two surface water samples were collected from Hambisa River and from a point below the
confluence of Legedadi River with Legetafo River. The Hambisa River is situated east of the
Sendafa landfill project site and both the Legetafo and Legedadi rivers drain on the west side. The
water samples were collected from upstream positions relative to the proposed landfill site. The
samples were collected on the same day at an interval of approximately one hour interval. The
samples were collected using grab sampling techniques and were sent to Addis Ababa Environment
Protection Authority Laboratory for analysis. The resulting data from the analysis is applied to
establish bench mark conditions as part of the baseline assessment.
Page 52
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
FDRE Constitution also reaffirms the participation of the public, in policies and projects that affect
their livelihood. Article 43 No.2 states that Nationals have the right to participate in national
development and, in particular, to be consulted with respect to policies and projects affecting their
community.
Stakeholders consultation was also conducted to ensure the participation of all interested parties,
including people residing in the project area, local government officials, Kebelle administrations
and Woreda experts and professionals from different offices in the woreda.
The objective of public and stakeholders consultation were;
To ensure that the public and stakeholders, interested groups, civil societies are informed
about the project and its impact and the information will clarify doubts about who will be
affected or benefit from the project.;
To enable meaningful and accessible participation of the public and the affected population
in particular;
To inform on the nature of potential social impacts of the project and its impacts on the
social, cultural and economic ties and networks during and after construction works;
To consult on the loss of productive resources mainly loss of farm and grazing land,
To solicit the views of local population what beneficial impact they expect from the project
Page 53
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
zone, a low-pressure zone marking the convergence of dry tropical easterlies and moist equatorial
westerlies across the catchment.
Meteorological data of the past six years (2007-2012) has been collected from Bole meteorological
station which is relatively representative to the project sites in Bole Arabsa, Akaki, Legedadi and
Koshe sites.
Based on the data collected and analyzed, mean maximum annual temperature over the record
periods is 23.5 0C, while mean minimum annual temperature value is 10.50C. The daily variation in
temperature in the area is more pronounced than the annual variation and the calculated mean
annual temperature is around 170C. The annual rainfall of Addis Ababa collected from Bole
meteorological station is 1040mm. Small variation in annual rainfall is observed towards Akaki and
Legedadi areas. In general, one can classify the climate in this area as warm temperate climate. The
average annual wind speed calculated is 0.55km/hr.
Jan
Feb
Mar
Apr
May
June
July
Aug
Sep
Oct
Nov
Dec
23.8 24.8
25.7
25.0
25.4
23.7
21.2
20.8
21.7
23.4
23.1
22.7
9.7
10.8
12.1
12.7
12.0
11.9
12.0
11.6
9.7
8.6
8.0
35.2
80.4
84.2
109.
253
251 140.5
17.1
16.1
19.1
8.8
Average
annual
rainfall (mm)
9.1 25.0
0
Table 3: Monthly Mean temperature ( c) and average rainfall (mm) data for 6 years (2007-2012) from Bole
Meteorological
Jan
Feb
Mar
Apr
May
June
July
Aug
Sep
Oct
Nov
Dec
0.62
0.77 0.67
0.67
0.55
0.37
0.27
0.3
0.4
0.65
0.68
0.63
Page 54
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
between the levels +2436m and +2470m ASL. Its shape represents a strip oriented North-South
with a natural slope of 1.2% (average value) toward the south. The site also presents on its Middle
Eastern part a slope toward the south-east ranging from 2 to 6%. On the other hand, the topography
of Akaki transfer station site has flat topography. The elevation difference is about 2m and it is
from 2066m to 2068m. Bole Arabsa transfer station site has gentle topography. Its elevation
difference is about 25m and it is from 2249m to 2225m.
Page 55
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
c. Nazareth Group
Aphanitic basalt, welded tuffs, ignimbrites, trachyte and rhyolites make up this group of younger
Volcanics. Aphanitic basalt flows cover the southern portion of Addis Ababa. Trachy basalt out
crops are found around Repi area and General Winget School and associated with undifferentiated
volcanic. An ignimbrite sheet (upper Welded tuff) out crop occurs in the northeast of Addis Ababa
at the base of Intoto Mountain and Lega Dadi areas. This formation is gray colored, vertically and
horizontally jointed (Hailesellasie Girmay and Getaneh Assefa, 1989). Rhyolite flows belonging to
this group outcrop at the top and southern flanks of Mt. Yerer. The exposed thickness of the lava
sequence is about 500m (Anteneh Girma, 1994).
d. Bofa Basalts
This unit comprises of olivine porphyritic basalt, scoria, vesicular & scoriaceous basalt, and trachy
- basalt lava flows. They extend in to the south from Akaki River and the unit is as thick as 10
meters (Anteneh Girma, 1994). They appear to have upper thick basalt of 20 - 40m over the Akaki
well field but thinner to absent in other places. They have well preserved shape of cones.
e. Lacustrine Deposits, alluvial & Residual soils:
These are quaternary to recent deposits. Lacustrine soils occur around Bole, Lideta, Mekanisa,
Between Abba Samuel Lake and small Akaki River. The thickness of this deposit varies between
5m to 50m.
The Akaki catchment where all the Addis Ababa SWM project sites are located has been subjected
to the rift tectonics, which is manifested by a number of major and minor fault systems. The general
trend of most of these faults follows the rift system (NE SW) orientation but there are some faults
with orientation of east-west and northwest-southeast. The major lineament oriented along east west that extends from Kessem River in the east through Addis Ababa to Ambo in the west, cuts
across the Western rift escarpment and uplifted its northern block (Zennettin et al., 1978).
Another major lineament oriented in Northwest direction & situated to the northeast of the Akaki
well field extends between Akaki and Dukem (following the main Debrezeit highway) is one of the
lineaments that do not follow the rift trend. The density of faults increases to the southeast of the
rift valley. Therefore, some of the basaltic lava and cinder cones situated to the Southeast &
Northeast of the Akaki well field probably have erupted through these fractures as they are
concentrated along the major NE SW trending fault systems of Akaki and Dukem areas.
Page 56
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 57
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
With regard to soil type, the entire project area is dominantly covered with black cotton soil. The
black cotton soil horizon or layer from the three test pits observed during field assessment has an
average thickness of 1.5m. Soils encountered in the site are black cotton soils with characteristics of
high plasticity and high degree of swelling.
6.1.3.2 Geology and soil type of Bole Arbasa Transfer station site
The southern segment of the site area is covered by basalt flows representing the oldest rock unit
exposed in the site area. It is well exposed all along the Akaki river gorge and its tributaries and
extensively excavated for various construction purposes. The rock is dark gray in colour, degree of
weathering ranges from strong to moderate, predominantly aphantic, vesicular, locally
amygdaloidal, strongly fractured and jointed, locally strongly layered.
The northern segment site is covered by Miocene ignimbrite (welded tuff) and trachyte underlain
by aphantic basalts. It is grey colored, vertically and horizontally jointed (Getaneh Aseffa et al.,
1989). There is a fault close to Bole Arabsa transfer station trends NNE-SSW direction like most
faults of Ethiopian rift valley.
From field observation, Bole Arabsa site is dominantly covered with black cotton soil. According
to the Test Pitting dug at the site, the black cotton soil cover above the weathered rock ranges
between 0.1m to 1m. Therefore the average of the soil cover is about 0.5m. The land is gently
sloping landscape. Its porous, dark-colored soils developed from volcanic origin, such as volcanic
ash, tuff and pumice.
6.1.3.3 Geology and soil type of Koshe Transfer station site
Koshe site is found in the younger volcanic of Chilalo formation comprising Trachyte, Trachy
basalts, Ignimbrites and Rhyolites. Trachytic flow and Trachy-basalts dominantly cover extensive
areas in the site as well as west and southwest part of the site, from Mt. Furi, Tulu Iyoo to Repi and
Wechecha Range. The trachyte flow is underlain by tuff and overlain by alternating flows of
plagioclase basalt and rhyolite at Repi (Anteneh Girma, 1994).
According to Solomon Tale (2000), Olivine porphyritic basalt (Addis Ababa Basalt) outcrop in the
north eastern part of the site and the central part of the city.
It was difficult to identify the soil type of the site from field observation as the site is filled with
solid waste and selected soil materials transported from other areas for recapping. However, from
soil map of Addis Ababa, the area around the site is covered dominantly with clay and to some
proportion of silt developed from young volcanic rocks of Mt. Furi and Mt. Wechecha.
ZTS-EDCE & MTS
Page 58
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Map 4: Geological Map and water points in Sendafa Sanitary Landfill Site
Page 59
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 60
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
From the deep test wells drilled up to depth 432 and 500m around the site to assess the hydrogeological characteristics of the Legedadi-Legatafo-Ayat groundwater prospective area, the major
aquifer in the area is fractured basalt, scoria and Scoraceous basalt. The deep test wells have water
yield of 15 and 20 l/s and static water level of 6m - 8m. During drilling significant amount of water
was struck at 60m and 180m depths.
Owner
Well
depth(m)
94
33
100
Static water
level(m)
29
-
borehole was observed within a radius of 1km from the site. However, the site is at the periphery of
South Ayat-North Fanta well field buffer zone which is one of the five Groundwater prospective
sites identified in Addis Ababa city.
Page 61
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The first hydro lithological units is alluvial sediment composed of clay and silty clay material and
its thickness is about 40m and it acts as confining layer of the upper aquifer. The upper aquifer is
composed of vesicular basalt intercalated with scoria and massive basalt layers of multi layered
aquifer. The massive basalt layers within this aquifer may act as a separating layer between the
upper and lower aquifer. The thickness of the upper aquifer is estimated to be a maximum of 360
meters; the thickness of the lower aquifer is penetrated by 500 meters deep wells. Deep wells
drilled up to 400m to 550m around the site yielding water from 22 l/s to 90 l/s with static water
level depth of 8m - 35m.
The general groundwater movement is from north to south. Akaki area groundwater prospective
site is one of the five prospective groundwater sites identified around Addis Ababa city. (WWDSE,
March 2008) showed that Akaki prospective site has high groundwater potential and the annual
exploitable groundwater resources from the Akaki prospective site is preliminarily estimated to be
about 168 MCM/Year or 537,000m3/day.
Currently, in addition to operational old Akaki well fields, Addis Ababa Water Supply Authority
has actively undertaking groundwater development through drilling deep wells in selected three
well fields named as WF01, WF02, and WF03.
Page 62
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Map 5: Water points and Geological structures around Akaki Transfer station
Page 63
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Fig 7: Showing current land use types at Sendafa landfill, Akaki and Bole Arbasa transfer station sites
Page 64
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 65
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Fig 8: Showing the confluence of Legetafo with Legedadi River where sample was collected
The Sendafa sanitary landfill site is located downstream of Legedadi dam which has reservoir
capacity of 40x106 m3 and supply rate of 127,000m3/day. From field observation, Hambisa River is
brackish and polluted with cattle dung as it is extensively used for grazing by the near community.
Parameters
Water quality
Hambissa river
Water quality of
Legetafo River after
joining with
Legedadi river
Remarks
PH
5.53
6.3
259
190
TDS (mg/l)
129
95
237
2435
18.3
179.5
0.02
2.5
Nitrate (mg/l)
10.5
Nil
Flouride (mg/l)
0.2
0.29
TOC (mg/l)
Nil
Nil
10
Phenol (mg/l)
0.009
Nil
11
Nil
2.0
Page 66
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
12
Salinity, %
Nil
Nil
13
235
750
14
450
862.5
15
Chloride, (mg/l)
210
675
16
COD (mg/l)
40
100
17
1.875
< 0.00001
18
< 0.00001
< 0.00001
19
< 0.00001
< 0.00001
20
BOD5, (mg/l)
38
40
Table 5: Laboratory analysis result of river water samples from Hambisa and legetafo-Legedadi rivers
Page 67
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 68
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
standards. While providing insight into air quality in Addis Ababaincluding spatial and temporal
distributionswhen no information existed before, this study had several major shortcomings that
ought to be addressed in future work.
6.2.2 Wildlife
The most common fauna (animal) species in Sendafa area and the surrounding are duiker, fox,
hyenas, poexuines, hare, servile, and monkey. This does not mean these animals exist abundantly in
the Sendafa area and the project site. No protected areas such as parks, sanctuaries or game reserves
has found at reasonably near distance of the project sites.
Page 69
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
urban population of the country and it is also 11 times of the second largest city, Dire Dawa. This
shows the importance and supremacy of Addis Ababa in every aspect of development. The
population size of the five towns in Oromia special zone which will utilize the Sendafa Sanitary
landfill and transfer station facilities are also shown in table 10.
No.
Sub City
Population
No. of kebeles
Arada
297,942
10
Kirkos
335,330
11
Gulele
318,508
10
Kolfe Keranyo
261,235
10
Akaki Kality
194,002
321,000
10
Lideta
296,073
Bole
320,389
11
Addis Ketema
320,389
10
Yeka
368,418
13
6.3.2 Administration
Addis Ababa has almost equal status to that of a regional state and is governed by a city
administration that directly reports to the Federal Government. Administratively, it is divided into
10 sub cities and 116 kebeles (which are termed woredas at present). Addis Ababa has its own city
council elected every 5 years.
The city Government is run by an elected Mayor. The Sectoral activities of the city Government are
run and managed by the different Bureaus and Agencies that are responsible for the implementation
of development activities.
Page 70
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
generate a lot of commercial and industrial waste that have impacts on the environment and health
of the residents of the city. The city is growing at an increasing rate demographically, economically
and has also stretched in size in every direction. Like any other metropolitan city, its growth and
economic development has initiated the development of satellite cities in future. Addis Ababa
houses more than half of the national labour force. The labour force is mainly concentrated in the
area of commercial activities, manufacturing and industry, and at household level (domestic
workers). The economic strength of Addis Ababa is also manifested in the financial sector as well.
It takes 48% of the share of financial institutions and 55% of insurance companies.
6.3.4 Health
The health institutions present in Addis Ababa include hospitals, health stations and clinics, which
are run under Government, NGO and private health institutions. Among the existing health
institutions, 39 are hospitals (12 are run by government and 27 private) and 26 health centres (50
more are under construction by government) and 406 are clinics (private). The ratio of hospitals to
population is 1:76,386.
No.
Percentage
596
17.7%
Health Officers
23
0.6%
Pharmacists
16
0.47%
1436
42.6%
Health Assistants
703
20.8%
Paramedicals
592
17.5%
Total
3366
Table 6: Health professional by qualification
Page 71
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The top ten leading diseases are not very much different from other parts of the country. The
leading top ten diseases of the city are presented in the table 7 below.
No.
Bronco-pneumonia
Other helminthes
Other toxemna
10
Acute bronchitis
6.3.6 Education
The city of Addis Ababa has 728 primary schools (1-8) and 168 secondary schools (9-12). In the
city there are also more than 192 different universities, colleges and institutes outside the
administration of the city.
The number of students in both primary and secondary schools in 2003E.Y (2010/11) is 654,853
and of which, 502,282 are in primary school (1-8) and 152,571 are in secondary schools (9-12).
Table 8 presents the school enrolment by gender and grade level in 2010/11.
Primary 1-8
Secondary 9-12
Boys
Girls
Total
AAGR
Boys
Girls
Total
AAGR
222,045
280,237
502,282
-0.3%
71,945
80,626
152,571
2.7%
Page 72
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The ratio of girls to boys in primary schools is 103. 1 and in secondary schools is 79.7. The
breakdown by sex and school level for 2003E.Y (2010/11) is presented in table 9.
Primary 1-8
Secondary 9-12
Boys
Girls
Total
Boys
Girls
Total
102.4
103.8
103.1
88
73.2
79.7
6.3.7 The current Municipal Solid Waste Management System in Addis Ababa
a.
Though the Addis Ababa Cleansing Management Agency is undertaking awareness raising
programs through different mass media, the segregation and storage of waste into different
containers by households is not a common practice, except for selling valuable waste to Kuralew.
b.
Collection
Solid waste collection in Addis Ababa is currently carried out in three different types of collection
systems: primary, secondary and street sweeping. The Primary Collection System is the one that is
carried out by Micro and Small Enterprises (MSEs) from door-to-door in households using simple
hand tools such as shovels, forks, pick-axes, rakes and wheel carts, and then temporarily stored into
(958) skips, point from where the waste is finally transported in vehicles to the disposal dumpsite
(Cambridge Industries, Nov 2012).
The report of the Evaluation of the 2003-2010 Development Plan of Addis Ababa City
Environmental Planning (February 2011) stated that 95% of the citys solid waste is collected by
these enterprises. According to the report there were 11 private micro and small enterprises
engaged in solid waste collection services, operating in eight Woredas of Addis Ababa before 2003.
ZTS-EDCE & MTS
Page 73
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
They had created 119 job opportunities and had the capacity of collecting about 204 m3 each week
with a monthly charging of 10 - 30 Birr for the service they were rendering. The service at the time
was being determined by a kind of bargaining with the household heads. However, in 2010 the
number increased to 521 Micro and Small Enterprise Unions with a total number of more than
10,000 operators working on solid waste collection (but the AACMA reported in 2013 that there
are about 563 SMEs managing 5573 solid waste collectors). The method of collection service
charges is also changed to the rate of water consumption. Hence, the service charges for solid waste
collection are not currently based on willingness and ability to pay as before. It is now compulsory
across all income groups. Thus, almost all of the households get the service of solid waste
collection service with direct service charge with the water bill. The solid waste collection service
fee for households and institutions is 20% and 40% of their monthly water consumption rate
respectively. Sanitation service fees of 30 birr per m3 for MSE, & 70 birr per m3 private companies
(Birr 240 for MSE & 560 for private companies) are paid as the current rate per an 8m3 container
solid waste collected. But it has been investigated that the existing means of payment has not been
made applicable for all waste generators in the city. This is because commercial centers in the city
like Merkato, Piaza, etc do not use water supply services, yet they are huge generators of solid
wastes in the city.
The evaluation finally indicated that more than 70% of the total solid waste generated was collected
in the city collection system in the year 2004 and 2005 (the lowest proposed cut of point at the
planning year in 2003 was 65%), but in the years followed (2006 - 2009) the annual solid waste
collection coverage was below this number as shown in the following figures adopted from the
report.
Page 74
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Years
Fig 10: Annual Solid waste generation and collection
Secondary Collection System is the block (container) collection that is carried out by private
companies (5% of the solid waste generated by the city) in hotels, hospitals, schools and other
service delivery and manufacturing organizations (Evaluation of the 2003 2010 Development
Plan of Addis Ababa City Environmental Planning, February 2011).
The third one is Street Sweeping System that is held by the AACMA. Streets requiring cleaning
have increased about 300% from the year 2003 to 2010, but streets being cleaned each day were
503km( 87%) and 800km (41%) in the year 2003 and 2010 respectively (see fig.11). Although the
ZTS-EDCE & MTS
Page 75
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
figures show an increased coverage of street cleaning in the city, it is clear to recognize that the
service delivery in this regard has not expanded hand in hand with the construction of new roads
that require regular cleaning to address the street sanitation problems in the city (Evaluation of the
2003 2010 Development Plan of Addis Ababa City Environmental Planning, February 2011).
2010
2007
2003
c.
Page 76
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
d.
Waste from the primary and secondary collections in combination with street sweepings is dumped
into the Koshe dumpsite under the authority of the Addis Ababa Recycling and Disposal Project
Office.
According to the 1992 NOR CONSULT estimation, the composition of the waste dumped to Koshe
accounts 76% from residential, 9% from commercial areas, 6% from street sweeping, 5% from
industries, 3% from hotels 1% from hospitals.
Studies indicated that about 70% of the solid waste generated in the city is compostable; however,
composting is not common practices both at households and dumpsite (only accounting 5%).
Recycling is not also performed, except informal picking of valuable waste at the dumpsite and
households (this also accounts only 5% of the total solid wasted produced in the city).
Serving for more than 47 years, Koshe now is beyond its carrying capacity, near to be closed.
About 17km2 of its area is recapped, but there is no any leachate and gas emission control
mechanism established so far.
There is no formal waste recycling or waste-to-energy facility known to the area up to now,
however, the Cambridge Industries Energy with the Ethiopian Electric Power Authority has
finalized its environmental and social impacts study report to establish a facility to generate power
out of waste at Repi.
Page 77
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
According to the report, it was found out that around 300 middle-men commercialize mainly metal
scrap, electrical devices, electric cables of various size and other items. Also, some 280 middlemen are dedicated to buy and sell keys and other door parts, as well as motor parts. An estimated 60
middle-men work in buying and selling corrugated iron sheets and items like rubber, plastics, and
car spare parts like batteries. Finally, 170 intermediaries work, rubber, metal and plastic barrels,
other plastic products, and glass bottles are recovered for reuse and recycling (IGNIS 2010).
a. Social baseline of Koshe waste pickers community
Waste picking (scavenging) is a regular activity that takes place in Koshe dump site. It is a practice
that has been going on for over three decades. The number of waste pickers has shown considerable
increase through time and currently it is confirmed that there are about 685 waste pickers who work
regularly in the dump site.
Waste pickers of Koshe comprise a broad range of age groups that extend from children to older
people. The presence of such broad range in age group is expected simply because it is more or less
a reflection of the wider society which is a source for them. There are also a sizable number of
female waste pickers in Koshe dump site. The Koshe waste pickers are characterized by
rudimentary and basic educational levels. A large portion of the waste pickers settle normally
integrated with the wider community as its ordinary members.
As it is the case in many parts of the world, people who are engaged in waste picking work at
landfill sites are usually driven by poverty and lack of other survival means. In line with it, the
social impact assessment study carried in Repi have confirmed that for the majority of the waste
pickers in Koshe dump site, the main reason and hence the main driver that push them to work is
lack of other income generation opportunities which they need to support their livelihood.
The waste pickers collect all types of salvageable materials from the waste stream and sell it to their
clients. Especially metal and plastic materials are diverted in large quantity from the waste stream.
Much of these salvaged materials are taken by dealers to plastic and metal recycling factories in the
city. Other reusable materials are fed into the market for reuse. The business of salvaged waste
involves a number of business people in the market chain. The waste pickers sell their salvaged
materials to the middle men and the middle men sell either to the big dealers or take it to the
recyclers. Waste picking work at Koshe dump site is full of challenges and risks. The work
environment is unhealthy and demeaning.
Page 78
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The amount of daily income generated by waste pickers depends on a number of factors. Firstly,
the preference of waste pickers to salvage high or low value material has a direct influence on the
daily income. The income is also influenced by the role of the waste picker in the market chain of
the salvaged materials. There are waste pickers who play the role of middle men in the market
chain. Those who buy salvaged materials directly from the waste pickers at the dumpsite and sell it
out to the next in the market chain will have a better income than the others.
6.3.9 Socio economic background of Bereh woreda and the five towns of
Oromia Special zone
The Sendafa Sanitary landfill project site is located in Oromia National Regional State, Finifine
Zurya Special Administrative zone in Bereh woreda. The Capital of Bereh Woreda is Sendafa
town. Bereh woreda is not only the place where the site for the Sendafa Sanitary landfill project is
situated but also is a beneficiary of the services of the sanitary landfill itself. Two of its main towns,
Sendafa and Legetafo towns, are going to use the sanitary landfill to dispose its solid wastes. In
general, the three transfer stations and Sendafa Sanitary landfill project will provide its service to
all the five towns found in Oromia Special Zone which include Sebeta, Sululta, Burayu, Gelan,
Sendafa and Legetafo towns.
Page 79
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
No.
Sub City
Population
Remarks
Burayu
89 057
Sebeta
79 722
>>
Lege Tafo
9 237
>>
Gelan
6 698
>>
Sululta
10 563
>>
Sendafa
10,750
(CSA, 2007)
The Bereh woreda has a total population of 79,972 people, and of which, 40,411 are male and
39,558 are female. The population of Sendafa town alone is estimated to be 10,750 (CSA, 2007).
Ethnically, the woreda population is predominately Oromo ethnic group and their language is also
Affan Oromo. The Oromo are the largest ethnic group in Ethiopia.
The Bereh woreda is predominantly rural and the mainstay of the population is crop farming.
Agricultural practices have not yet developed much and mainly practiced by using traditional
farming methods by using oxen plough share and it is also small scale household farm. Outside the
household farms, recently, three flower farms have been established in the woreda.
In Bereh woreda there is very little business and industrial development outside of agriculture; in
the town sections there are only small scale businesses, such as, bars, restaurants and grinding
mills.
The distribution of social services in the woreda shows that drinking water supply coverage has
reached 56% only. In terms of education, the woreda has 53 primary schools having 16,537
students. The number of teachers in the above schools is 338 (120 female) and among the above
teachers none have degree level qualification.
The health coverage shows that there are 3 health centres, 4 clinics, 20 health posts. The health
professionals working in the above health facilities including 4 Health officers, 46 Nurses, 4
Pharmacists, 3 Lab technician, 1Sanitarian, and 76 Health agents.
The top ten diseases in the year 2012 (2004 EC) in the woreda include;
Page 80
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Type of Disease
Number
Injury
901
6.27
Pneumonia
1321
9.1
Acute
Febrile 4256
29
Illness
4
Diarrhoea
2279
15.7
Dermatitis
390
2.7
Gastritis
554
3.8
Acute Upper
2219
15.3
Respiratory Tract
Infection
8
Intestinal Parasite
1360
9.4
Conjunctivitis
803
5.5
10
Urinary Tract
Infection
333
2.3
Page 81
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
7. Analysis of Alternatives
The alternatives considered for the solid waste management project include change of site, change
of design and the no project option. The selection of suitable site for the sanitary landfill project
had been conducted by different technical groups assigned by the Addis Ababa City
Administration. Initially, the Fillidoro, Bole Arabsa and Fincha sites were studied by different
technical groups. However, feasibility studies have revealed that these sites were found unsuitable
for use as sanitary landfills due to various reasons shown in table 12.
Site location
Fillidoro site
Fincha site
- Pollution of surface
water downstream of the
landfill site
- permeability of the
geological formations
were high
- Pollution of
groundwater due to the
high permeability of the
geological formations.
After the above sites failed to prove suitable, another task team was formed in September 2009 to
look for probable sites within 40km radius considering the hydro-geological, geological, ecological
and engineering geological aspects. The six potential sites considered includes Chebe Weregenu
(Legetafo), Gubaya (Tefike), Abeyi dibdbe (Dukem), Simbrite Kore (Menagesha), Daleti Ejersa
(Butajira road), and Geja Jewie (Sebeta). From these candidate sites the Chebe-Weregenu site (now
commonly called as Sendafa Sanitary landfill site) was selected as one of the first priority site.
A detailed feasibility study of the Chebe-weregenu site on geological, engineering geological,
hydro-geological, and geophysical investigations were carried out by the GSE during 2009 2010
ZTS-EDCE & MTS
Page 82
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
GC. The feasibility study conducted at 1:5000 scales allowed to generate data to understand the
subsurface conditions of the proposed site and make tangible conclusions on its suitability for
sanitary landfill. From engineering geological point of the host rock underlying the top soil has
medium mass strength. The permeability value of the residual soil covering the landfill site
indicates that the soil is semi-pervious. In terms of hydrogeology the immediate area surrounding
the site is found not much promising for water well development. According to geophysical
investigations the residual soil has sufficient thickness to protect leakage of leachate. The study
also concluded that due to topography and absence of prominent tectonic structures, flooding, slop
instability problems are not expected to pose any significant risk. Besides, construction raw
materials to be used as a blanket for the landfill is found at a distance of about 1500 meters NE of
the site. Moreover, the site is found entirely on an area of water shed free from surface drainage. It
is a flat land (table land) situated between 2400 to 2600 masl. Consequently, due to all the above
reasons, the current Sendafa sanitary landfill site was selected as suitable site for the purpose.
The design process of the sanitary landfill and transfer stations has passed through a number of
steps including preliminary and detailed design development stages. During these stages various
design alternatives were considered before arriving at the final detail design for the sanitary landfill
and transfer stations. The draft detailed designs were presented in a workshop held in December
2014 involving several stakeholders including representatives from regional and federal EPAs and
were discussed and commented thoroughly. As a result, the final detail designs have incorporated
the various comments forwarded by the workshop participants, which have been instrumental in
considering alternatives and improvements to the transfer stations and sanitary landfill designs.
The no project option will allow the continued use of Koshe Repi open dumpsite which is already
getting full and also causing environmental problems in the area. On the other hand, considering the
rapid development taking place both in Addis Ababa city and its surrounding, the no project option
will probably allow the utilization of the selected sanitary landfill and transfer station sites for other
competing priority purposes and deprive the city from its opportunity of getting suitable landfill site
in its peripheries.
Page 83
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 84
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
locality. Thus the construction of the new sanitary landfill will contribute indirectly towards the
improvement of public health of the city residents.
8.1.2 Impact on public health of the residents of the five towns in Oromia
special zone
Sebeta, Burayu, Sendafa, Legetafo, Gelan and Sululta are towns which are becoming increasingly
populated and more urbanized in recent times. These towns are found adjacent to Addis Ababa city
and their social and economic growths are observed to show a considerable leap in recent years. In
most of these towns industrial and residential development activities are taking place and are
expanding fast. On the other hand, despite the rapid urbanization and growth observed, almost all
of these towns do not have well organized solid waste management system that consists of proper
solid waste disposal facilities. As a result, the public health of the community was increasingly
getting threatened due to lack of proper solid waste collection and disposal facilities.
Fig 12: Showing recently abandoned and newly opened dump sites in Sebeta town
The establishment of the Sendafa sanitary landfill and three transfer stations and the opportunity to
use these facilities by the five Oromia special zone towns is anticipated to have a significant
positive impact on improving the solid waste management practices of the towns resulting in
improvement of their environmental sanitation and public health status. Sanitary landfill is a huge
urban infrastructure which may prove difficult to put in place by each of the stated towns for
themselves. Hence the opportunity to utilize the new transfer station and sanitary landfill project
facilities will present a medium and long term solution to the environmental and public health
concerns of the five towns of Oromia Special Zone.
Page 85
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The proposed sanitary landfill and transfer station project is designed not only to facilitate the
sound collection and disposal of solid waste, but also provides a space to undertake continued
waste sorting and segregation activities at the transfer stations. Each of the transfer stations
consists of a separate block where waste sorting and segregation will be conducted. The waste
segregation is expected to result in recovering reusable and recyclable materials from the solid
waste stream by employing a sizable number of formal waste pickers. The reusables and
recyclables recovered from the solid waste stream are expected to be channelled to the recycling
establishments through formalized means. Therefore, the proposed solid waste management project
will have a positive impact of enhancing environmental sustainability by facilitating for waste
recovery, reuse and recycling through sound and formal means.
Page 86
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
triggered by improved environmental quality, the lower property value observed in the immediate
neighbourhood of Koshe is anticipated to rise in the future. Thus, the new sanitary landfill
facilitating the closure of the existing dump site will have an indirect impact on property value of
the koshe neighbourhood.
Page 87
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The contractor should employ large proportion of casual and semi skilled workers from the
local population residing in the project area. The jobs that would be created would be during
construction and operation phases. During construction phase jobs to be created include
mainly casual jobs, such as, daily labourers, carpentry, masonry, etc. In the works contract
document of the contractor to be employed, a clause should be added to ensure the
employment of casual and semi skilled workers and that the employment has to be made
from among the people living in the project area. The jobs to be created during operation
phase are expected to be handled by AACMA and that will include employment of guards,
drivers, machine operators, mechanics and cleaners for offices.
Ensure womens employment and improve their employment opportunities and working
conditions. The project will give priority in employment to women and in particular to
female headed households. Women in the project area have very limited exposure of
working in such type of projects. However, the construction of the project in the area is
expected to create new opportunity and skill for women. During the construction phase of
the project women could work as daily labourers and in particular jobs that will not have
negative impact on their biological and social characteristics and during the operation phase
women can work as cleaners for offices and other related jobs. The above jobs apply mainly
for uneducated or for women who have very low level of education.
The contractor needs to observe the Labour code for employment, minimum wage, work
safety regulations, and related issues.
construction works; and it is also common that the above workforce will demand for different
services from the business persons operating in the direct influence area of the project.
Experiences from other infrastructure projects show that there is always a demand for some
services and goods by construction workers. Some of these services and goods in demand are
ZTS-EDCE & MTS
Page 88
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
kiosk for selling of basic items and consumables, eating places and selling of food, beverage, etc.
Whenever there is large number of workmen who have come either from outside or employed from
the locality it will become a driving force that initiates local communities to start income generating
and small business which has never been there.
The income generating activities and businesses that are expected to be established due to the
construction work would allow households to learn new skills and also earn additional income; and
to diversify their income sources and to exploit their potential. In general, it is anticipated that some
20-30 business persons will be directly providing the services and some 50 or more persons who
could indirectly serve as suppliers (mainly local farmers) for the business men could be able to
generate income during construction and operation phases. In general, it is anticipated that between
50 to 100 people could be able to generate income through various income generating activities.
The composition of leachate from landfill site varies greatly from site to site, and can also vary
within a particular site. Some of the factors affecting composition include age of landfill, types of
waste, degree of decomposition; and physical modification of the waste leachate. It is forecasted
that Sendafa Sanitary landfill would receive approximately 8,200,000 tonnes of waste over the next
20 years. The waste that will be disposed at the Sendafa Landfill is composed of Organic (57.1 %),
Plastic (8.8%), paper (4.1 %), cardboard (3.3 %), Textile (3.0%), hygienic textile (2.7%), glass
ZTS-EDCE & MTS
Page 89
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
(2.6%), unclassified combustible and incombustible (5.3 %), health care waste (1.1 %) and others
(9.7 %) (Artelia & MCE, 2013). It is proposed to construct five waste disposal cells and the fifth
cell will be dedicated for the disposal of hazardous waste. The volume of leachate that will be
generated from this disposal cells is anticipated to range from 645m3/day when cell one (1a) is
operating and the rest of the cells are closed to 1336 m3 /day when cell 4a is operated and other
cells are closed during the lifetime of the sanitary landfill.
If the landfill has no leachate collection system the leachate to be generated during the operational
phases can enter into ground and surface water resources found around the sanitary landfill site.
The predicted impacts of leachate on the important surface and ground water bodies found around
the proposed landfill site are further discussed below in the next sub-sections. Typically, landfill
leachate is acidic, and rich in organic acid groups, sulphate ions with high concentrations of
common metal ions, especially iron. The risks from waste leachate are due to its high organic
contaminant concentrations and high level of ammonia and nitrogen. Pathogenic microorganisms
and toxic substances that might be present in the waste are often cited as dangerous, but since
pathogenic organism counts will reduce rapidly with time in the landfill it will only be an issue to
the fresh leachate at the initial stage.
Page 90
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The Legedadi dam has also an area in its surrounding reserved for well field development. It is
predicted that the shallow depth of water level in the adjacent Legedadi well field boreholes and
absence of thick top clay soils may facilitate direct percolation of contaminants to the groundwater
reservoir. Though the piezometric surface constructed from groundwater point inventory made
during previous studies showed that the general groundwater flow in the area is towards southeast
direction and away from Legedadi well field where currently deep bore holes are being drilled to
expand the city water supply, the intensive pumping of groundwater from the Legedadi well field in
the future may result in rapid decline of groundwater levels leading to disturbance in the flow
direction system of the groundwater, eventually resulting in groundwater flow towards the
depression zone. This process potentially facilitates the rapid flow of contaminated water from the
aquifer underlying the proposed sanitary landfill site to the Legedadi well field. There are also more
than four springs on downstream of the landfill site aligned along N-S normal faults close to
periphery of the site. The manifestation of the springs downstream of the site can be an indication
of tectonic structure controlled groundwater flow system in the area. Therefore it is anticipated that
in the absence of proper management of the proposed sanitary landfill, leachate may have an
adverse impact on the nearby deep test wells and shallow wells drilled by AAWSA found within a
radius of 3.5km from the site, with static water level of less than 10m as well as springs emerging at
downstream. The shallow depth of water level in the adjacent boreholes and absence of thick top
clay soils may facilitate direct percolation of contaminants from the landfill to the groundwater
reservoir.
Page 91
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Akaki Transfer station is located within Well Field-1 from which a total of 60,000m3/day has been
produced from 15 deep boreholes since 2012. The transfer station is also not far from Well field-2
and Well field-3 (Map 8).
From geological log data taken from deep boreholes around the site, the 40-50m thick unsaturated
zone of lacustrine sediment with high proportion of clay soil can act as a geochemical and
biological filter, because of its low permeability, mostly black cotton soil. The impermeable layer,
massive basalt overlain with the thick clay soil, prevents downward percolation of contaminated
water into aquifer. It is, therefore, unlikely that the contaminants from the transfer station may
easily leak into the aquifer at a depth as a result of direct percolation. However, the area has been
subjected to the rift tectonics, which is manifested by a number of major and minor fault systems.
The general trend of most of these faults follows the rift system (NWSE and NE-SW) orientation.
Particularly, weak zone along the fault striking from NW-SE on western part of the site can be a
conducive path for contaminants leaked from the transfer station towards south part of the well
field where most of the deep and shallow wells are concentrated. Moreover, nearby shallow
unconfined aquifers may be exposed to pollution as a result of base flow from Akaki River drained
by the transfer stations.
Page 92
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Storm water discharge from Bole Arabsa transfer station is drained into Great Akaki River. It is
observed that since the Great Akaki River drains most of the central, north-eastern as well as southZTS-EDCE & MTS
Page 93
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
eastern parts of Addis Ababa city, it is exposed to a load of pollutants from urban solid waste and
sewage releases, industrial and commercial discharges as well as other diffused pollution sources
while draining through the city. Thus the Great Akaki River already contains an agglomeration of
pollutants from the upstream and further contamination from the transfer station will have a
cumulative and synergistic effect in enhancing the pollution level of the river. Thus it is important
to avoid or minimize sources of additional pollution load that can be washed away by storm water
from the transfer station.
Based on the intrinsic vulnerability map of Akaki Catchment, the Bole Arabsa transfer station site
is located in the range of medium vulnerability (Dereje 2003). This implies that leachate created
from decaying waste in the transfer station can have possibility of percolation down to the water
table if there is no proper prevention and control system in place. On the other hand, however, the
area around Bole Arabsa transfer station is not currently serving as well field area for Addis Ababa
city. The nearest ground water prospective areas under investigation by AAWSA are the South
Ayat-North Fanta well field which is found about 3.5 km south of the proposed transfer station.
Thus the transfer station may not become an immediate pollution threat to existing well field that
supply water to the city. However, it is imperative to take necessary measures that prevent the
seepage of leachate into the ground water during the operational phases of the transfer station to
avoid long term impacts on the ground water.
Page 94
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Koshe dump site and Mekanisa well which is also located 1.8km south of Koshe open dump site
were found to be out of acceptable drinking water quality standards (Tigstu H. etal, 2012).
Therefore, the presence of heavy metals and coliforms in the nearby groundwater samples is
expected to be a result of direct percolation and surface-ground water interaction in the Koshe
landfill area. Even though the contribution it may make would be comparatively small, the new
koshe transfer station may cause additional impact to the ground and surface water if not properly
managed and operated. Groundwater flow direction which is from north to south have made
conducive environment for contaminated water flow to downstream shallow unconfined aquifers.
Finally, since the larger source of impact on ground and surface waters in the koshe transfer station
area is the open landfill site itself, it is assumed that this will be further investigated and discussed
in detail in the ESIA report of the decommissioning and closure of the Koshe landfill to be prepared
in the future.
During operational phases, the proposed Sendafa Sanitary landfill will generate a Land Fill Gas
(LFG) which is likely to have significant potential impact on the ambient air quality and climate
change. Landfill gas is generated by the degradation of the disposed solid waste materials under
anaerobic conditions (i.e. e. in the absence of oxygen). Methane and carbon dioxide are the major
gases produced by the bacterial decay of the wastes. With its high content of methane, which is
toxic and inflammable gas, the generation of landfill gas poses significant risks to human, animal
and plant health and life. The most significant risk associated with landfill gas arises from its
potential to form flammable mixtures with air. If it is allowed to accumulate in a confined space it
could be a source of ignition and an explosion may result. The risk is greatest where gas is allowed
to build-up in confined spaces, such as within buildings or in collapsed void spaces within the
deposited waste.
In an open area, landfill gas can give rise to flash fires. The critical concentrations limits within
which a flammable gas will burn (or explode) are known as the Lower Explosive Limit (LEL) and
ZTS-EDCE & MTS
Page 95
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Upper Explosive limit (UEL). For methane these are approximately 5% and 15% respectively.
Carbon dioxide, the other major constituent of landfill gas has an adverse effect on respiration and
is a hazard to health if it is present in concentrations in excess of 1.5%. Landfill gas may also act as
an asphyxiant (suffocating agent), by displacing air (oxygen), if it accumulates in a confined space.
In the absence of proper landfill gas collection and management system, the proposed sanitary
landfill project can immensely contribute to deterioration of ambient air quality in the area through
smoke release caused by spontaneous burning of methane gas. As stated in the baseline chapter, the
air quality of Addis Ababa city is not regularly monitored due to shortage of equipments and
resources. However, from the pilot air quality monitoring study conducted, it was observed that
concentrations, especially in urban and residential areas within the city, are close to, if not higher,
than the EPAs ambient standards for PM10 and PM2.5. Therefore, the release of smoke caused by
open flare of LFG from the new sanitary landfill can exaggerate the situation due to synergistic
effect.
In the same way landfill gases that are expected to be released from the proposed Sendafa Sanitary
landfill have the potential to cause odour nuisance in neighbourhoods surrounding the landfill.
Other gases produced by landfill bacteria are termed reduced sulphur gases or sulphides (e.g.,
hydrogen sulphide, dimethyl sulfide, mercaptans). These odorous gases give the landfill gas
mixture its characteristic "rotting" smell. Other chemicals can also be present in landfill gases,
although their levels are typically very small compared to the levels of methane, carbon dioxide,
and sulfides. Also, the amounts and types of VOCs in landfill depend upon whether chemical
reactions are occurring which either remove or create them.
The gases generated tend to rise through the landfill and reach the air above, although the rate at
which this occurs is affected by landfill content and by the weather. Once emitted into the air,
landfill gases are carried on surface level winds. While this dilutes the gases with fresh air, it can
also move them into the community. Naturally, wind speed and direction determine whether local
residents will notice landfill odours so that the degree of the problem will vary greatly from day to
day. The average annual wind speed calculated for the area is 0.55km/hr with the maximum
18m/sec at 120 in the northeast direction. Mostly wind occurs at 120 and 130 in the northeast
direction at the Bole metrological station. Thus odour will be anticipated to occur in the vicinity of
the landfill work places especially at the cell filling areas and is likely to affect few rural
ZTS-EDCE & MTS
Page 96
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
households (villages) present northeast direction of the proposed new sanitary landfill. The nearest
densely populated area to the site is about 5 10 kms far away and thus the probability of the odour
affecting large size of population is very low. At locations near the landfill, the worst time of the
day may be early morning. This is when winds tend to be most gentle, providing the least dilution
of the gas.
Sulfides can cause unpleasant odours even at very low concentrations. These concentrations are
well below the level needed to produce toxicity. This means that landfill odours represent more of a
public nuisance than a community health hazard, with the odours not being a good indicator of
whether other chemicals are present. However, for some people, simply smelling an unpleasant
odour can be sufficient to create an adverse physiological response (nausea, headache, etc.).
Although this situation is highly undesirable, the effects usually reverse when the odour dissipates
and do not require medical attention. While there is some concern that odours might precipitate an
asthmatic attack in highly sensitive people, a controlled study of asthmatics found that exposure to
a high level of hydrogen sulphide (2ppm) did not trigger an asthmatic attack or upper respiratory
function.
Other VOCs that might be present in landfill gas are less odorous than sulfides, and the levels that
might reach surrounding homes are generally far below that which is known to cause ill effects. In
most cases landfills do not emit enough of these VOCs to increase their concentration above the
background levels commonly found in the community.
Measures to capture landfill gases and prevent their migration to the community are warranted for
the proposed sanitary landfill project where odours are anticipated to create a persistent nuisance. It
is also likely that similar foul odour can be released from the transfer stations if the solid wastes are
not promptly hauled without storing and keeping it for days and if the sanitary situation of the
transfer stations deteriorates. In either case the foul odour released from the transfer stations can
affect the neighbourhood inhabitants and the workers inside. Especially the foul odour release from
Koshe and Akaki transfer stations is anticipated to have the greatest effect due to presence of
inhabitants around it.
Page 97
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Emission of green house gases under the proposed project is anticipated to be considerably less in
comparison with the current solid waste disposal and dumping practices, due to the proposed
landfill gas collection system and the flaring of the gas to be installed in the new sanitary landfill.
Nevertheless, the proper disposal of waste in regulated landfill together with the capture and flaring
of the gas is a step in the overall movement towards control of greenhouse gas emissions and so the
effect is assessed as minimum.
Unless the solid wastes to be hauled through the transfer stations are taken to the landfill
continuously without delay, storing it for days inside the transfer sheds because of operational
failures could cause a serious odour problem to the surrounding. Moreover, it will continue to
biodegrade and decay and get washed with storm waters causing contamination to surface and
ground waters through seepage respectively.
Page 98
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
If the wastes reaching the new sanitary landfill is not spread, compacted and covered with daily or
intermediate soil cover in the appropriate cells, the whole concept of utilizing the sanitary landfill
will be jeopardized and it will ultimately fail to serve its purpose. Under such inappropriate
operational conditions the sanitary landfill will degenerate into an open landfill and become source
of environmental pollution and public health hazard.
Fig 13: Showing an engineered sanitary landfill turned to open dump site in Adama
From experience it has been observed that sanitary landfills built with all engineering design
features to protect the environment and public health are seen to fail because of failures in
operation. Fig 13 above shows an example in Adama town where one of the first sanitary landfills
built in the Country was turned to simple open dump site due to operational failures caused by lack
of equipments.
The potential impacts of operational failure can also go beyond public health concerns. Open
landfills attract undesirable vermin such as rodents, pests including dogs and birds. The attraction
of a large population of birds in ill operated sanitary landfill in particular may probably have
unintended potential impact on air transport route. Therefore, the importance of properly operating
the sanitary landfill and transfer stations is as important as building it with all its engineering design
features.
The potential impact of the new sanitary landfill and transfer stations project on soil is anticipated
to occure during construction and operation phases. The main activities of the project which are
identified to have likely potential impact on soil are the excavation works during construction.
Construction of the various components of the solid waste project will all require conducting
excavation to lay the foundations at certain depths. Unless disposed appropriately in a selected
place, the excavation material from the transfer stations that will be carted away can create a
ZTS-EDCE & MTS
Page 99
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
stockpile of construction waste that can cause undesired effects at the disposal site. Therefore, it is
essential that appropriate measures are taken to dispose the excavation material with out affecting
the activities in the disposal area. With regard to the Sanitary landfill, during operation phase, it is
going to require daily and intermediate cover material (i.e. soil material) to cover the wastes
disposed in the cells. The soil material from the project site is identified as a suitable cover soil and
thus there is a plan in the design to use it as a cover soil in the new sanitary landfill. Thus its impact
as construction waste will be minimum provided it is managed according to the design plans.
On the other hand, during operation phase, it is likely that littering of solid waste may occure in and
around the transfer stations and the sanitary landfill that are blown by wind or by mismanagement
of waste hauling and disposal activities. Under such conditions the waste litter can creat unsightly
places around and may likely contaminate the soil through decay in the long term. The potential
impact of waste litter on the soil can become significant if it remains uncontrolled and unattended.
Page 100
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The noise and vibration impacts to be created due to movement of heavy equipments operating the
landfill will be anticipated to be low for similar reasons stated in the preceding paragraph.
On the other hand the source of noise and vibration impacts during operational phase will be
mainly the movement of waste hauling skip trucks. The potential impact of noise released by
haulage trucks is likely to mainly affect those receptors found along the waste haulage routes. More
specifically, the significance of this impact is anticipated to be pronounced in those sections of the
haulage routes along the approach to the transfer stations situated close to residential areas. The
time of the day during which the noise and vibration is released will also be a factor in affecting the
receptors. This is because noise released during night time when the majority of the neighbourhood
go to sleep will have more sever nuisance impact than that during normal working hours of the day.
According to the draft emission limit standards of the MoEF (i.e. former EPA), the permissible
noise limits differ based on the dominant functions of the areas under consideration and the time of
the day. Table 13 below shows the permissible limit values for noise.
Table 13: Draft Noise emission standards of FEPA
Limits in dB (A) Leq
Day timeNote 1
Night timeNote 2
Industrial area
75
70
Commercial area
65
55
Residential area
55
45
Area Code
Category of area
The potential impact of dust release is essentially going to emerge from the construction activity
and its machineries as well as due to movement of waste hauling trucks during operation phases.
The vehicles and construction machines that will be used for excavations, for carting away the
excavated materials, and delivery of other construction materials will create dust resuspension in all
the project sites. In a simmilar manner, waste hauling trucks will also create dust along the dusty
road routes during operational phases on a daily basis. The dust release is expected to be significant
during the dry season. However, the impact of the re-suspended dust will vary from site to site
based on the presence of receptors or people to be affected. As a result the likely receipents of the
dust pollution in the sanitary landfill and Bole Arabsa transfer station sites will be largely the
construction workers themselves and few passer by villagers. The re-suspension of dust in the
Akaki and Koshe transfer stations will likely affect larger community in the neighbourhood. The
Page 101
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
presence of receptors of the dust pollution in the immediate neighbourhood to the project site
makes its impact to be of significance.
The potential impact of the Sendafa sanitary landfill on land use is anticipated to be of low
significance. It was stated in the baseline chapter that the major land use type dominating the areas
around Sendafa sanitary landfill is farming, grazing and residential uses. The project area itself was
majorly used for agriculture with less dense residential places around it. Thus, the agricultural land
use type is being changed to waste disposal site. This change in land use and its impact on income
generation and livelihood of the farmers that were tilling the land is compensated by paying out
cash compensations (This will be discussed further under the social impacts section). As a result
there appears to be no significant conflict caused by the land use change. Since the proposed
sanitary landfill area is sparsely populated, the Not In MY Back Yard (NIMBY) syndrome
associated with the location of the landfill site is not observable in the area. Moreover, since the
project site is situated in a typical rural setting with open farming fields around it, it is anticipated
that with proper management and operation of the landfill including capping the cells with daily
and intermediate cover, its visual (aesthetic) impact on the surrounding will be minimum as it may
not create a major contradiction with the landscape.
However, in the long term, after site closure and decommissioning, the Sendafa sanitary landfill
may remain unsuitable for any other forms of beneficial land uses because of the waste deposited.
As a result it may likely pose a certain level of contradiction with the land use types in the area and
may also cause a visual impact on the surrounding if left unattended. Thus proper mitigations
should be put in place to avoid the post closure land use and aesthetics impacts.
In a similar manner, with the realization of the proposed projects, the current agricultural land use
around Bole Arbasa and Akaki transfer stations will change to temporary solid waste handling
purposes. Nevertheless, the overall land use pattern in these areas is fast changing and the
dominance of agriculture is thinning out. However, since the transfer station activities are designed
to be undertaken inside building blocks, it is anticipated that it will not create major land use
conflict with the upcoming residential and industrial purposes in the future. Likewise the design of
the transfer station blocks is observed to be aesthetically in harmony with the developments taking
place in the area and the general landscape.
ZTS-EDCE & MTS
Page 102
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
The impact of the proposed project on traffic volume during operation phase can be analysed by
categorising it in two stages. The first stage is the impact on traffic volume during waste hauling to
the transfer stations. The second stage is the impact on traffic volume during transfer of waste from
the transfer stations to the sanitary landfill. In terms of impact on traffic volume, the first stage of
waste hauling to the transfer stations is likely to be more significant than the second stage. While
the first stage of hauling is likely to involve the movement of several waste skip trucks to and from
the transfer stations, the second stage of waste hauling will involve the movement of comparatively
few big long haul trucks and trailers that will carry large loads of the waste.
The impact of the first stage waste hauling on traffic volume is again likely to vary with the general
location of the specific transfer stations. In chapter three it was described that the Akaki, Bole
Arbasa, and Koshe transfer stations are situated at the south, south eastern and south western
suburbs of the city respectively. Whereas the Akaki transfer station is situated along one of the
busiest road of the city (Addis Ababa Akaki road), the Bole Arbasa transfer station is situated in
parts of the city where the traffic volume is comparatively low. On the other hand, the koshe
transfer station is situated along the moderately busy ring road system of the city. The net impact of
koshe transfer station on the traffic volume of the area will become lower than its current impact as
disposal site. This is because, Koshe as disposal site is receiving all the waste hauled by all
operational waste skip trucks available in the city. But with the coming of the transfer station into
operation, the available waste skip trucks will be distributed to haul the waste to the three transfer
stations.
Thus in terms of impacts on traffic volume the Akaki transfer station is likely to have a significant
impact than the other proposed transfer stations. This impact on traffic volume will not only affect
the general traffic flow along the Addis Ababa - Akaki road but also will negatively influence the
speed of waste hauling to the Akaki transfer station.
On the other hand, currently the Bole Arabsa and Akaki transfer stations have no well paved detour
roads that can be used to connect to the main roads and to approach the transfer stations. Especially
the Bole Arbasa transfer station is found in a remote place away from the main road that terminates
near the new Bole Lemi Industrial Zone Development Project. The road that leads to Akaki transfer
station is currently a gravel road which may cause traffic problem during wet seasons. Thus there is
Page 103
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
a need to connect the two transfer stations (Akaki & Bole Arabsa) with the main roads and make
them easily accessible.
The impact of the second stage waste hauling on traffic volume is anticipated to be insignificant for
a couple of reasons. Firstly, the number of big trucks that will haul the waste to Sendafa transfer
station are anticipated to be small in number. Secondly, the main highway that connects the
Sendafa sanitary landfill with Addis Ababa city is the Addis Ababa-Dessie road and comparatively
speaking the traffic volume along this road is moderately low. This is especially true after one
reaches the Gurd Sholla square and heads towards Sendafa town. The big waste hauling trucks can
use several alternative roads to reach to the Gurd Sholla square through which they can proceed to
Sendafa sanitary landfill.
The impact of the proposed project on traffic volume during construction phase is generally
anticipated to be low and insignificant. This is mainly because; the construction of the sanitary
landfill is going to take place outside the Addis Ababa - Dessie road where practically there is no
sizable traffic flow in the area. Similarly, because of the comparatively small scale of construction
activities to be undertaken to build the transfer stations, the additional traffic triggered by the
construction activities is anticipated to be low.
Page 104
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
occupational health aspects of waste management workers in the sanitary landfill and transfer
stations.
Fire Hazard is another important impact which can have an adverse impact not only on the sanitary
landfill, transfer stations and its surroundings, but also on the environment at large. Despite the
presence of landfill gas collection and flaring system in the design of the sanitary landfill, the
potential and likeliness of changing the spontaneous fire hazard caused by landfill gas (methane) to
a fire risk is generally higher in the stated waste management facilities. This is because methane gas
is highly flammable and it can aggravate combustion in case of accidents thereby damaging
properties and creating a cloud of thick smoke that can affect the air quality of the surrounding. Fire
hazard can have the potential of causing serious air pollution.
During operational phases an important source of contamination for the soil and surface water
bodies will be the spillage of used oil and lubricants from the maintenace workshop of the transfer
stations. Each transfer station will have a block where the maintenance of waste hauling trucks and
other equipments will be serviced and maintained.
Page 105
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Spillage of used oils and lubricants from the vehicles and machineries to be engaged during
operational phase can pose pollution risk to the soil grounds of the transfer stations and to the main
Akaki River and its tributaries found nearby the transfer stations. To minimize such impacts
introducing a mechanism for proper handling of oils, and lubricants spillages is essential.
On the other hand the Sendafa Sanitary landfill will have a facility where the wheel of waste
hauling trucks will be flushed with high-pressure washer to remove litter and mud at the tipping
face of the vehicle. The wastewater generated from the cleaning activities of skip truck wheel can
affect the tidiness of the premises there by affecting the soil grounds if not managed properly. Thus
it is important to handle the wastewater generated to avoid potential impacts on the soil grounds
and its tidiness.
The new Sendafa sanitary landfill project has caused permanent loss of 137.07 hectare of farmland
which used to be under the entitlement of 217 farmers. The project office has paid compensation
amounting to Birr 24,767,194 to the above farmers who have lost their land. Following the
compensation payment made in 2011, the land has formally been handed over to the project office.
The project office has started to fence the site with concrete pole and barbed wire which will be
completed soon.
During the public consultation, farmers reported that since each farmer had plots of land in
different locations they are able to continue their livelihood without much difficulty after losing
their farmland to the project for they didnt face total loss. The residential settlements of the
farmers were also outside the demarcated landfill area and hence there was no need for involuntary
resettlement of the farmers who have lost their farmland to the project.
The affected farmers have also reported that they were able to properly utilize the compensation
payment. Some reported that they were able to expand their agricultural activities by renting more
land, some were able to construct new houses, and some others have started to save.
The project may still temporarily acquire farmland from farmers for the construction of access road.
Currently, the project office has not acquired any land for the construction of access road to the
Page 106
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
land fill. But the land to be acquired for the construction of access road is anticipated to be much
less compared to the landfill area.
Valuation of property and assets as well as compensation for affected households was carried out
and administered as per FDRE law (proclamation No.455/2005) and regulation No. 135/2007.
8.3.2 Exposure to HIV / AIDS and other Sexually Transmitted Diseases (STD)
In Ethiopia, the HIV/AIDS pandemic, in recent years, has emerged as a major health hazard,
affecting mainly the age group of 15 to 49 years. Construction workers and truck drivers are
considered as having high potential (or good vectors) for the spread of Sexually Transmitted
Diseases (STDs) and HIV/AIDS virus due to their mobility.
Contacts and communications created between local communities and construction workers who
have come to the project area from major towns will expose the local community to new culture
and behaviour. The introduction of new cultures and behaviours mainly contribute to the spread of
communicable diseases such as STD and HIV/AIDS.
In infrastructure project, women always do not receive equal employment opportunities; and the
contractors, in most cases, favour to employ men rather than women, and female workers do not
obtain particular attention due to their biological and physical condition. It is well known and
common that infrastructure projects prefer to employ only men, and this will lead to unequal
treatment of women during employment of the construction work force.
Hence, the discrimination against women will negatively affect those women who want to work in
the construction work. Such discriminatory acts and lack of other employment opportunities may
force women to carry out other marginal activities.
Public and Stakeholders consultations are carried out in order to solicit the views of the public
residing nearby the project area, Project Affected Persons (PAPs) and also that of local authorities
(woreda and kebelle administration). The consultations were carried out in four locations, namely
ZTS-EDCE & MTS
Page 107
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Bereh woreda administration (with stakeholders), and with the public at Sire Goyo kebelle (Sendafa
land fill area), woreda 4; Gora ketena (Akaki transfer station) and at Bole Arabsa area (transfer
station) with residents and PAPs. The minutes of both public and stakeholders consultation is
attached in Annex-I. Since the minutes are written in Amharic the following is the English
translation of the minutes.
Outcomes of stakeholders consultation in Bereh Woreda
Issues and concerns for local level
In general, in all the locations where public consultations are held the public are highly
supportive and positive about the construction of the project.
The woreda anticipates that the local population will have employment opportunities during
the operation phase of the project and in future there is a potential for the establishment of
some factories producing goods through the process of recycling waste materials that are
collected from the land fill.
During operation phase there could be some potential negative impacts that might affect the
health and livelihood of the local population living in the surrounding. Some of the health
hazards could be due to odour, noise, dust and the like.
The project office needs to take the maximum care that no waste (from factories,
households or offices) is dumped outside of the land fill area.
The payment of compensation for affected households and procedures for valuation of
property and assets is carried out as per FDRE law (proclamation No.455/2005) and
regulation No. 135/2007.
The affected population has participated in the valuation of property and were made aware
of the procedures and guideline prior to the compensation payment. Affected persons have
also selected 5 persons to represent them in the valuation and compensation process.
Page 108
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
access road to the land fill area start and which kebeles it will cross and how will it affect
the farmlands along the route and what will be the size of farmland that will be affected if
constructed/affect?.
b. Outcomes of Public Consultation
The following is outcome of public consultations held in Sire Geyo kebele-Akaki Kile
village (located at Sendafa landfill area), Bole Arbasa and Woreda 4-Gora ketene (Akaki
transfer station). A total of fifty two PAPs participated in the three kebeles. During the
public consultations, a number of issues were raised and discussed and the following is
summary translation of the minutes of consultation meetings.
i)
Construction of social services: During public consultation meeting held with officials who
came to visit the landfill site previously from Addis Ababa, we were promised that the
project will construct various social service facilities such as school, electricity and drinking
water supply for the local population but so far there has not been any progress regarding its
implementation.
Lack of Access road to farmlands: Those who have farmland adjacent to the landfill area
have faced access problem due to the fencing of the project site. Before the project, they
were able to travel to their farmland by crossing the existing landfill area without any access
problem. But currently due to the fencing of the landfill area they have found it difficult to
travel to their farmland and were forced to take a detour around the fence of the landfill to
access their farmland. To solve the above problem the officials who have come from the
project office have promised us that they will construct access road and that will allow us to
have access through the landfill area.
Employment opportunity: We would like to be given priority in employment opportunities
that are created due to the implementation of the project; however, so far we did not have
any satisfactory employment opportunity.
We were promised by authorities from the project office that we will be given priority
during employment procedures and that no employment will be made outside of the
locality. But now it looks that the employment procedures and criteria is different from what
has been promised to us by the project office. For instance, the criterion set to employ a
guard is reported that he should be someone who has completed grade 10. This appears to
be difficult since there are not many people who have finished grade 10 among us.
ZTS-EDCE & MTS
Page 109
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Participation in land measurement and property valuation: Some PAPs complained that they
did not have sufficient information about the procedures of land measurement and property
valuation. However, the majority reported that they are aware of the procedures and the
process has been transparent and that they have elected their representatives (elders) from
among them to participate in the process of measuring affected land size, in carrying out
property valuation and in the procedure for compensation payment.
Delay in the implementation of project: The land was taken from us some three years ago
by the project office, however, in the last three years there has not been any significant work
carried out by the project office. The delay in the implementation of the project has made
the land to stay idle for such long time which we could have used the land to farm and grow
crops and generated income.
Changes in Livelihood: Participants of the consultation have reported that they have
received the appropriate compensation payment for loss of their production and some PAPs
even reported that they were able to improve their livelihood through the compensation
payment they received for their lost farmland. Some also reported that they have built CIS
roof houses, some have rented additional land to expand their farm business, some have
bought mini buses to use as public transport and some others have moved to town and built
house with the compensation payment received and started small business.
Impact on community health: Those of us who are living in close proximity to the project
site are worried and concerned that the project will affect our health in the future because of
the hazardous chemicals dumped in the site.
Conclusion: Generally, we have no objection in the implementation of the project in our nearby
vicinity as far as appropriate mitigation measures are considered and implemented to minimize the
negative impacts.
Fig 14: Showing the community consultation conducted at Sendafa landfill site
ZTS-EDCE & MTS
Page 110
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 111
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Lack of access to drinking water: The kebele does not have proper drinking water supply.
Hence, the community would like the project office to construct drinking water supply for
them.
Employment opportunity: The local population would like the employment of temporary
and regular project staff to be from the locality.
Page 112
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Project action
Environmental
Components/
Characteristics
Construction
Sendafa
Sanitary Landfill
Operation
Transfer
stations
Sendafa
Sanitary landfill
Post-closure
Transfer
stations
Sanitary
landfill
XX
XX
XXX
XXX
XX
Flora
Fauna
XX
XX
XXX
XX
XXX
XXX
XXX
XXX
XX
XXX
NA
Archaeological and
religious sites
Traffic
XX
XXX
XXX
XXX
XXX
XXX
XXX
XX
Employment
Impact on Public Health
(SWM facilities properly
operated)
Table 14: Magnitude Matrix showing the significance of potential impacts of the project
Page 113
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
In order to minimize and control the anticipated potential impacts of leachate on surface and ground
waters, the following mitigation measures as described in the following sub-sections will be taken.
The mitigation measures outlined below are fully incorporated in the design of the proposed
sanitary landfill and will be implemented as main components of the sanitary landfill development.
The first mitigation option to prevent the impact of leachate is to reduce its generation in the
sanitary landfill. In order to achieve this, the volume of rainwater or surface run-off that comes into
contact with the waste at the Sendafa Sanitary Landfill should be minimized. The surface of the
waste body will therefore need to be covered intermediately during operation of the landfill and
finally after closure of the landfill.
The rainwater that flows from the surrounding areas and (after filling) from the surface seal of the
landfill, will need to be captured by ditches around the landfill body and directed to the lowest
point of the landfill located in the south west. The ditches along the landfill should be lined to avoid
erosion of the cover layers of the closed cells. From this low point, the run-off water will be led by
gravity to the nearby streams in the south-west direction. Storm drainage of a size that will handle
the highest rainfall intensity is proposed to be constructed within and around the proposed sanitary
landfill site.
The next proposed mitigation measure to avoid and minimize the impact of leachate on surface and
ground waters is to prevent its infiltration and release from the landfill cells into the stated water
bodies. Accordingly, the design of the proposed project has incorporated a robust mechanism for
the development of leachate containment and collection mechanism as fundamental component of
the engineering measures. To minimize the release of leachete from the waste disposal cells into the
ZTS-EDCE & MTS
Page 114
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
surrounding environment it is proposed to install the following facilities as the disposal of waste
progresses during the life time of the sanitary landfill.
a. Passive and Active security barriers
The purpose of the passive security barrier is to ensure, in the long run, the prevention of soils;
groundwater and surface waters from getting polluted by leachate. At least 1 meter of natural clay
soil with a permeability < 10-6 m/s will be placed below the cell liner system and will play the role
of passive barrier. In most part of the cells, the clay soil depth below the liner system is proposed to
be more than 2 meters.
An active security barrier made of HDPE geo-membrane with 2mm thickness will be used for both
the bottom of the cell and the slopes and it should be UV protected. For cells receiving hazardous
wastes, the active security barrier will be reinforced by an additional HDPE geo-membrane of
2.0mm thickness. The active barrier ensures the hydraulic independence of the cell, the drainage
and the collection of leachate and avoids the use of the passive security barrier.
For checking the integrity of the active barrier system, a 15cm sand layer with slotted HDPE pipes
within it will be placed between the two HDPE geo-membranes. This will serve as leakage
detection layer. The pipes will lead to a leakage control manhole that will be checked on a monthly
basis as soon as the first raw of hazardous waste will be disposed of.
b. Leachate collection system
The leachate collection system comprises a high permeability drainage layer, perforated or slotted
collection pipes, and geo-textiles to protect the geo-membrane and prevent clogging of the drainage
layer. In the case of Sendafa sanitary Landfill, the liner is sloped toward the leachate collection
pipes which ones are also sloped toward the leachate transmission pipes and these slopes should be
between one and three per cent.
c. Leachate Drainage layer
A leachate drainage layer will be placed all over the bottom liner system. The leachate drainage
layer is made of a high-porosity medium providing a preferential flow-path to the leachate
collection pipes. This will consist of bottom drainage layer and side slope drainage layer. Slotted
pipes will be laid (embedded) within the gravel layer in such a manner that the leachate will be
drained within the gravels layer to these slotted pipes. The collectors shall lead to HDPE pipes in
Page 115
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
the peripheral trenches near the ground level and along the perimeter bunds. These pipes will lead
the leachate by gravity to the downstream part of the site.
To avoid clogging and capillary action holding water in the drainage layer, coarse material will be
used so that there is space within the drainage layer for leachate to drain freely. Using coarse
material also ensures leachate flow in the event of clogging of some parts within the leachate
collection pipes. The hydraulic conductivity of the drainage layer is proposed to be greater than
1x10-4 m/s. The drainage layer shall be placed across the entire landfill cells area and comprise at
least 0.5meter of coarse aggregates or the equivalent performance with a geo-synthetic drainage
material. This ensures that leachate is contained within the drainage layer, thus minimizing the
potential for clogging of the drainage layer. A geo-textile filter would also be placed over the
drainage layer to protect it from clogging as a result of solids transport.
The final mitigation measure proposed to prevent the impact of leachate is to treat it in a three stage
leachate treatment plant to bring down its pollutant load into internationally accepted levels and
render it harmless to the environment. The detail design of the proposed sanitary landfill consists of
a leachate treatment plant as one of its component which will be built together with the project.
Since there are no emission limit standards concerning leachate effluent concentration in Ethiopia,
the design for the proposed leachate treatment plant have adopted French regulation as a base for
treatment level. Accordingly, the required level of leachate concentration of the effluent that will be
discharged into the surrounding environment is proposed not to exceed COD of 300 mg/l, total
suspended solids of 100 mg/l, BOD5 of 100 mg/l and total nitrogen of 30mg/l.
To meet the required level of leachete effluent a three-stage treatment system is proposed. This
includes:
An anaerobic pond;
A facultative pond; and
A constructed wetland
a. Anaerobic pond
An anaerobic pond (3m deep) will receive leachate with high organic loads. This pond will not
contain dissolved oxygen or algae. In this anaerobic pond, COD and BOD5 removal is achieved by
ZTS-EDCE & MTS
Page 116
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
conversion of both soluble and non-soluble COD and BOD5 into mainly methane, carbon dioxide
and water. The process of anaerobic digestion is more intense at temperatures above 15C and can
reach up to 75% of BOD5 removal. A retention time of at least 20 days is used to ensure proper
treatment.
b. Facultative pond
The facultative aerobic pond (1.2m deep) is used to treat the remaining BOD5 and COD
downstream of the anaerobic pond. The process of oxidizing organic matter by algae and aerobic
bacteria is dominant at this stage.
c. Wetlands
A constructed (or engineered) wetlands (CW) is a planned system designed and constructed to
employ wetland vegetation to assist in treating wastewater in a more controlled environment than
what occurs in natural wetlands. For this project it is proposed to design a Horizontal Sub-Surface
Flow (HSSF) system as the efficiency is higher than a Free Water Surface Flow (FWSF) for the
same plan area.
The pollutants removed by CW s include organic materials, suspended solids, nutrients,
pathogens, heavy metals and other toxic or hazardous pollutants. Plants take up the dissolved
nutrients and other pollutants from the water, using them to produce additional plant biomass. The
nutrients and pollutants then move through the plant body to underground storage organs when the
plants senesce. It will then be deposited in the bottom sediments through litter and peat
accumulation when the plants die.
During operation of the treatment system, it will be necessary to periodically clean and scrap the
anaerobic and facultative ponds by scraping the sludge cake. Since the sludge cake will be rich in
heavy metal contents, it will need to be disposed in the sanitary landfill. The same will apply to the
senescing plants of the constructed wetland.
In summary it can be concluded that the key potential negative impacts identified in this
environmental analysis will be mitigated by the design of the sanitary landfill and through good
operational practices. This is because the conceptual site design takes into account the potential
impact of contamination of water resources from leachate emissions. A high standard of leachate
containment and management is ensured in the proposed site design through implementation of the
following of:
ZTS-EDCE & MTS
Page 117
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
the installation of two HDPE lining systems in the zone of leachate accumulation, both
designed to meet the maximum permeability specification.
the provision of a high permeability leachate collection and transfer system to facilitate
the collection of leachate percolating through waste materials and to drain the leachate
from the landfill in order to prevent a build-up of leachate within the body of the
deposited waste;
the provision of a leachate treatment pond and re-circulation facilities and equipment to
promote the evaporation of any collected leachate, in order to reduce leachate quantities
and leachate strength;
an operational and leachate management policy that is based on not discharging any
leachate offsite.
Page 118
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Re-open and clean the nearby streams to divert surface runoff around the transfer station
site and construct retaining walls around the perimeter of the transfer station
Dividing the transfer station site surface area into smaller catchments that contain
gravitational outlets to the proposed storm water drainage
These mitigation measures are also applicable to the remaining two transfer stations, namely Bole
Arbasa and Koshe transfer stations.
The following gas management systems are proposed to be introduced to minimize impact of
landfill gases at the Sendafa Sanitary landfill.
The anaerobic decomposition of organic substances inside the proposed Sendafa Sanitary Landfill
is expected to generate landfill gas during the operation phase. The gas can, in some circumstance,
migrate away from the site and cause explosions. Best practice is to collect the gas and burn it.
The landfill will be actively degasified by means of a vertical gas collecting system. An active gas
system is proposed for the project site in view of the relatively large quantities of organic waste that
will be deposited. Vertical gas wells will be installed in the waste progressively as the landfill
grows vertically towards final levels or after filling each cell of the landfill. These allow gas to be
collected through perforated HDPE pipes linked to a compressing station. A compensation layer
between the waste and the mineral surface sealing of the filled cells will be constructed through
which gas can flow easily and which allows supply to the gas vents. With a good degasifying
system it will be possible to collect at least 50% of the produced gas.
The gas pumping station will be located in facilities zone at the northern part of the landfill. Inside
the pumping station blowers will provide the required negative pressure gradient in the landfill
body which guarantees active degasifying at a high gas collection rate. The gas will be directed to a
landfill gas flare beside the gas pumping station where the gas will be incinerated at temperatures
of about 1,000 -1,200 C. The possible use of the extracted gas for electricity or heat generation has
not been considered at this stage of the project. There will be five year of operation at least before
Page 119
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
gas is collected from the first cell during which the feasibility of energy recovery can be
considered.
It is essential that a program of landfill gas monitoring is carried out at regular periodic intervals
during and after the working life of the site in order to assess the effectiveness of the gas control
measures in place. Should landfill gas be detected during routine site surveys, the method of gas
control will be reviewed and, as necessary, the passive gas wells converted to an active gas
abstraction system in which gas is sucked out of the landfill under a vacuum. Whilst the impacts
associated with landfill gas should be minimized by good site operational practices, there always
remains a residual moderate potential for landfill gas impacts, particularly if site management is not
of the highest standard. Thus it is important that good site operational practices are maintained in
the proposed sanitary landfill during operational phases.
Gas cleaning/conditioning before the flare to remove moisture and possibly impurities, such
as airborne debris, from the landfill gas;
A blower or booster developing the head of pressure needed to feed landfill gas to the flare;
One or more flame arrestors in the landfill gas feed line to prevent flash-back of the flame
down the pipe;
some method of control over the flow rate of landfill gas to the burner, and possibly over
the supply of combustion air;
A burner designed such that it maintains turbulent mixing of air and fuel and that the
velocity of the gas is high enough to reduce the risk of flash-back of the flame down the
feed pipe without blowing off the flame;
Page 120
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
A flame detector to check that ignition has been successful and combustion is taking place
this facility is normally provided with enclosed flares but it is more difficult for open flares
since the location of the flame can be highly unstable.
9.3.3 Mitigation measures for impacts of dust and vehicle exhaust smoke
The dust nuisances predicted to occur during construction and operation will be mitigated by
applying the following measures.
Re-suspension of dust in the construction sites will be prevented by frequent sprinkling of water.
This will be specially applied during the carting away operations of the excavation materials. Water
for sprinkling of the dust grounds should be fetched from the nearby Rivers to avoid using
municipal water.
As a matter of routine it is considered good practice to use modern, well-maintained and regularly
serviced vehicles in order to minimize vehicle exhaust release impacts in increased traffic flows at the
transfer stations and the neighbouring communities.
It was anticipated that the potential impact of the new sanitary landfill and transfer stations on
public health is anticipated to likely occur under future potential scenarios where the new sanitary
landfill and transfer station facilities to be developed by the project are not operated properly. In
order to avert the potential impacts from occurring, the sanitary landfill will have to be operated in
a way that complies to the draft Ethiopian standards on Solid waste management to the minimum.
The following are the minimum standards for sanitary landfill management that the Sendafa landfill
will need to observe during operation phases to mitigate the stated potential impacts.
AARDPO shall ensure that the site is operated in compliance with the standards for class I
sanitary landfill (refer sec 4.3.5.1a), has an operational plan, is adequately staffed, and that
suitable mobile equipment is in functional use.
To minimise leachate generation, breeding of pests, wind-blown litter and odours, cover
material shall be applied to the entire surface of the tipping-cell to a minimum depth of 15
cm at the completion of each working day but every third day as a minimum.
Page 121
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
AARDPO shall ensure that suitably qualified and experienced personnel are assigned to
manage the day-to-day landfill operations. The site manager must have ready access to
suitable equipment and resources to properly manage the site.
Mobile equipment sufficient to ensure that operational standards are met shall be provided
and maintained in use at the landfill site.
Landfill operators shall ensure that no fires are tolerated within landfill sites, and that any
persistent fires are reported to the competent authority.
During normal operational hours landfill operators shall allow regulated access of informal
recyclers/waste-pickers to the landfill site, to work in designated areas but not at the
working face of the landfill.
The AARDPO shall ensure the installation and functioning of landfill gas management
systems at all landfill cells.
Where possible landfill gas shall be collected and flared, and where economically
justifiable, utilised as a source of renewable energy.
Category 1 and 2 landfills will have vehicle weigh scales installed to obtain exact records of
waste quantities being delivered.
Similarly, in order to avert the potential impacts on public health and the environment arising from
ill operated transfer stations, it will have to be operated in a way that complies to the draft
Ethiopian standards on Solid waste management to the minimum. The following are among the
minimum standards for transfer station management that the Koshe, Akaki and Bole Arbasa
stations will need to observe during operation phases to mitigate the stated potential impacts.
The design of the transfer operation shall enable the site operations to be efficient and
hygienic.
Incoming waste shall be transferred from the transfer-station within 1 day, unless temporary
operational reasons do not permit this.
All waste transfer points, facilities and containers shall be kept clean and orderly at all times
with containers and site area inspected and cleaned monthly, and a total area clean
extending to 20m in all directions around entire site every quarter (3 months).
Therefore, in order to implement the above stated minimum standard requirements for the Sendafa
Sanitary landfill and transfer stations, it is recommended to develop detailed manuals and
procedures that translate the requirements into daily operational procedures for the staff and
management of the sanitary landfill. It is also recommended that the landfill and transfer station
operators should be trained on the landfill and transfer station management standards, basic
ZTS-EDCE & MTS
Page 122
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
operational procedures and associated manuals. The operational manuals and procedures coupled
with the necessary machinery, equipment, skilled and semi-skilled labour force are necessary for
the proper management of the Sanitary landfill and transfer stations.
If the sanitary landfill and transfer stations are operated properly by complying with the stated draft
operational standards of solid waste management, its risk to attract undesired vermin such as
rodents, pests including birds will be significantly decreased. Especially, it is anticipated that the
population of birds in the area that will be attracted by the landfill will be kept at minimum or nonexistent. The bird problem will be strongly minimized by good working practice, keeping the
working area to a minimum and covering the waste at the end of each working day. This will
always remain the best bird control system. The design of the landfill has carefully accounted for
this aspect by placing all infrastructures of the new landfill beyond a 13km radius from Bole airport
limits. Hence the standard 13km distance of the Sendafa sanitary landfill as a buffer zone from the
Bole Air Port will suffice to avoid any impact on the air transport route.
It has been shown in the impact analysis sections that inappropriate disposal of construction waste
generated during the foundation excavation activities of the transfer stations will be one aspect that
will potentially affect the environment. The project management and the contractor will ensure that
the construction waste to be generated during excavations and related activities will be disposed in
officially designated place. The project management and contractor will facilitate for obtaining
permission to access such tipping site which shall be designated by the AAEPA. The designated
site should be an eroded or degraded land which can be rehabilitated and remedied by filling it back
with soil and earth material. If there is absence of an officially designated site for disposal of
construction waste in the area, the project management and the contractor will ensure that a
degraded land that can be rehabilitated by tipping soil and other earth material is selected and used.
With regard to excavation soils from the Sendafa Sanitary landfill, the proposed project have design
plans to use surplus soil from excavation for daily, intermediate and final cover on the landfill cell
areas. Accordingly any excavated soil not utilized immediately will be stockpiled on site for future
use. Stockpiling will be the sole responsibility of the landfill operator. Thus the stockpiling of the
soil and future use as cover material for the landfill cells during operation by itself serves as
mitigation for its uncontrolled disposal.
ZTS-EDCE & MTS
Page 123
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
It was also anticipated that during operation phase, it is likely that littering of solid waste may
occure in and around the transfer stations and the sanitary landfill that are blown by wind or by
mismanagement of waste hauling and disposal practices. In order to mitigate it, on the landfill,
portable litter control fences will be used around the working area. The fences will be placed
immediately downwind of the working area to maximize the capture of windblown litter. Keeping
the working face to the practical minimum width will reduce litter generation. As there are no
controls that will completely prevent blowing litter during windy days, a regular (daily or weekly)
program of litter pick-up will be operated at the sanitary landfill and transfer station sites. Trucks
hauling the solid waste to and from the transfer station will also be covered with tents or other
suitable material to prevent littering of waste during transport.
In order to mitigate these potential impacts the following measures will be taken.
-
Earth moving equipments, trucks and other vehicle will have their normal muffler intact in
their smoke exhaust pipe and care will be taken to repair it when broken to avoid
unnecessary release of noise during operation in the fields.
Earth moving equipments, trucks and other vehicle operators will be advised not to
unnecessarily blow horns in areas where settlements are present
locating stationary equipment that is noisy as far as possible from the NSRs;
orienting equipment with high directivity to emit noise away from NSRs;
use of temporary noise baffles and noise fencing during the construction of the site access
road adjacent if necessary to protect adjacent NSRs;
Page 124
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Fitting of noise mufflers to mobile plant and equipment; and preventative maintenance of
equipment to minimize noise emissions
b. Operational phase
Effective noise management protocols to be implemented as part of the proposed project include:
- Earth moving equipments, trucks and other vehicle will have their normal muffler intact in their
smoke exhaust pipe and care will be taken to repair it when broken to avoid unnecessary release of
noise during operation in the fields.
- Mobile plant equipment will be used singly, while multiple use of mobile plant equipment is
restricted to short time periods, unlike construction activities;
- Land filling activities will be mobile and not fixed in that they move across the landfill footprint.
Therefore, no area is subjected to the operation of the dozer and/or track loader, for example, for long
continuous periods of time; and all site screening measures will be in place in advance of the start of
site operations.
9.7 Mitigation measures for land use and aesthetics (Post Closure of
the landfill).
In order to harmonize the sanitary landfill with the surrounding landscape and aesthetic views, a
progressive action will be taken to cover the completely filled cells with plant seedlings one after
the other. During site closure the last remaining cell of the landfill will be covered with final soil
cover and it will be planted with seedlings.
It was also anticipated that the Sendafa sanitary landfill is likely to have post closure land use and
aesthetics impacts. Thus it is recommended that a site closure plan shall be submitted to the
competent authority for review and approval by the time 90% of the sanitary landfill is filled. The
closure plan should outline a plan showing the final appearance (landscaped) of the site after
closure, a description of a proposed end use of the site that do not affect public health, and
inspection and maintenance of the final cover and landscaping. The closure plan shall also outline
the procedures for post-closure care of the site. The entrance gate and perimeter fencing will be
retained to control access and keep the site safe.
Page 125
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
In order to minimize the post closure impacts the following mitigation measures are proposed to be
implemented as part of the closure plan for the site.
Remove all infrastructure no longer required from the site.
Remove accessible scrap metal to recycling.
Collect and bury windblown litter and debris from the site.
Remove obvious hazards where obvious and practical
Implement rodent and nuisance control measures where a problem is identified
Consolidate waste and compact where appropriate
Shape and grade to the extent possible to achieve the required finished grades prior to
backfilling
Install final cover system to minimize the infiltration of liquids and soil erosion
Cover all refuse evenly with 60cm of back fill material which will include an erosion
control layer of 15cm of soil capable of sustaining native plant growth
Grade the final cover to accommodate settling of the waste, prevent surface ponding and
seepage, and direct surface drainage away from the waste disposal area.
Seed to initiate vegetation cover, reduce erosion potential and improve the appearance of
the site
Install drainage ditches, if not already in place, on the up-gradient sides of the site to divert
precipitation/drainage waters away from the disposal area and to prevent impact from future
overland flow
Delineate waste disposal site boundaries and features using available existing and historic
information, and geographic positioning system coordinates
Install and maintain permanent markers and/or fencing to indicate site boundaries
Install site signage to notify the public of the pending closure date; and providing directions
to, hours of operation and contact numbers for the alternate waste disposal site
Install No Trespassing and No Dumping signage at the former site entrance stating the
applicable fines for offense
The closure plan will have to include contingency plans to deal with the following:
Illegal dumping around the former waste disposal site following closure
Provide a summary report describing the work done to close/decommission the site, including as
built drawings pre and post closure, the existing condition, and the anticipated future condition
relating to environmental concerns.
ZTS-EDCE & MTS
Page 126
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Long-term maintenance will be carried on the final cover and leachate management system.
Erosion, ponding from settlement, and leachate seeps will be corrected, if required. Typically,
regular inspection and monitoring shall take place for a period of two years after site closure, after
which a long term monitoring and care program will be established.
The first priority in terms of mitigating impacts on traffic is to develop access roads to those
proposed solid waste management sites that do not have all weather access at present. These
include the Bole Arbasa and Akaki transfer stations as well as the Sendafa sanitary landfill. Though
construction is underway to build a new 8km road that connect the Sendafa landfill with the main
roads, the prevailing situation appears different with Bole Arbasa and Akaki transfer stations. Thus
it is recommended that a new all weather access roads that can handle the traffic flow to and from
the stated transfer stations should be built to mitigate the pending traffic problems that can be
created during operational phases. While building the access road to Akaki transfer station
consideration should be given to select alternative route that can avoid congested road stretches and
road junctions. Some of the proposed mitigation measures to minimize traffic impact along the
main waste hauling routes include:
Conduct traffic flow study on the routes and based on the study result widening and
rehabilitation of the roads leading to the transfer stations and to the waste disposal site
Provide separate entry and exit connections to the main road and a merging lane to access
the waste disposal site and to the transfer stations
Facilitate for proper maintenance and servicing of solid waste hauling fleet vehicles to
ensure continuous and uninterrupted traffic flow along the approach routes to the sanitary
landfill and transfer stations thereby avoiding traffic jams.
It was anticipated that there will be significant potential negative impact or risk on occupational
health and safety of workers involved in operational phase of the sanitary landfill and transfer
stations, if the project has not considered the issue of OHS of workers. In order to avert the
potential impacts (Physical/Mechanical hazard, Chemical hazard, Biological hazard, and bad
ZTS-EDCE & MTS
Page 127
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
ergonomics) that may occur from the hazard/risk, the health & safety system will have to be
operated in a manner that complies with the draft Ethiopian standards on Solid waste management
to the minimum. The following are the minimum standards for sanitary landfill management on
health & safety issue, which the Sendafa landfill and the three transfer stations will need to observe
during operation phases to mitigate the stated potential impacts.
AARDPO have an employers responsibility and humanitarian duty to prevent illness and
injury of the workforce. Consideration shall be given to all aspects of the work, including:
the design of the equipment; provision and use of personal protective equipment (PPE);
regular medical check-ups and immunization; and provision of toilets and washing
facilities.
AARDPO shall establish an accident and incident reporting system whereby every event is
recorded and investigated.
Health and safety training, supported by appropriate levels of supervision, shall be ensured
so that waste management workers understand the origins of the risks that they face and
know how to minimize these risks.
AARDPO shall ensure that collection workers should never be expected to lift wastes above
their shoulder height because the risk of serious injury.
In addition, to minimize impacts on waste recyclers the following mitigation measures will be
implemented.
Provide sorting facilities for semi-manual separation with disposal container to minimize
health risks.
Manual separation of recyclables will still be allowed in the early phases of the project, but
the personnel will have to be approved by site management and be appropriately equipped
and trained.
Formalize waste separation and introduce entry passes to prevent children from entering
these facilities for waste segregation
Provide appropriate training/skills development for both waste recyclers and the women in
their households in the pilot recycling scheme.
Page 128
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
During operational phase of project, the management of the three transfer stations will be advised
to set out work procedures for its employees working at the maintenance workshop to safely collect
used oils and lubricants while servicing and maintaining the waste hauling vehicles and
machineries. The used oils and lubricants should be collected in dedicated barrels and taken away
from the site to recyclers or to furnace oil dealers. In addition, in order to prevent the impact of
diffused lubricant and used oil spills from the maintenance workshop, the project management will
ensure that a settling tank that receives the wash waters from the maintenance workshop areas is
included in the design of the transfer station. The settling tank will be used to collect and separate
the lubricant and used oil by decantation. The decanted used oil and lubricant can be sold to dealers
for use as furnace fuel in brick factories e.t.c.
The following mitigation measures are proposed and were practically implemented to mitigate the
impacts on farm lands lost to the project sites.
Compensate farmers for loss of crops (perennial or annual), trees as per the Federal
legislation (Proclamation 455/2005) based on market prices.
Consult and involve PAPs in the estimation of costs for lost assets.
Page 129
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Allow enough time for PAPs to remove their crops (perennial or annual) and trees.
Compensate ahead of construction works for the loss of perennial crops/ trees compensate
based on market prices and as per the law.
The new Sendafa sanitary landfill project has caused permanent loss of 137.07 hectare of farmland
which used to be under the entitlement of 217 farmers. The project office has already paid
compensation amounting to Birr 24,767,194 to the above farmers who have lost their land.
Following the compensation payment made in 2011, the land has formally been handed over to the
project office.
9.13 Mitigation Measures for Exposure to HIV / AIDS and other STD
As a preventive measure, construction workers and local population must be informed through
awareness raising and education campaigns about HIV / AIDS. At the community level, special
information campaigns for women should be enhanced.
Conduct education and awareness creation campaigns on the spread and transmission of
STDs and HIV/AIDS for construction workers and local communities living close to the
construction camp sites.
Display educational posters and flyers about STD and HIV/AIDS, using local language
(Affan Oromo) at public gathering locations, schools and by road sides to minimize the
spread of HIV/AIDS.
Ensure women's participation and improve their employment and avoid discrimination
against women.
Support women from the locality to learn new skills and employ them during project
operation phase also.
Page 130
Project
Major Impacts
No
phase
Operation
Recommended Mitigation
measures
Anticipated
Residual
impacts
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 132
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Operation
Page 133
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Operation
- will become source of environmental pollution and public -AARDPO shall ensure that the site
health hazard
is operated with an operational plan,
is adequately staffed.
- cause a serious odour problem to the surrounding
-Cover material shall be applied to
- attracts vermin and birds which may have unintended
the entire surface of the tipping-cell
potential impact on air transport route.
to a minimum depth of 15 cm at the
completion of each working day
but every third day as a minimum.
-Suitably qualified and experienced
personnel and resources are assigned
to manage the day-to-day landfill
operations.
-Mobile equipment sufficient to
ensure that operational standards are
met shall be provided and maintained
in use at the landfill site.
-Ensure that no fires are tolerated
within landfill sites, and that any
persistent fires are reported to the
competent authority.
-Allow regulated access of informal
recyclers/waste-pickers to the landfill
site during normal operational hours
ZTS-EDCE & MTS
Page 134
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 135
Project
Major Impacts
Anticipated
Residual
impacts
None
No phase
4
Construction
and operation
Operation
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Operation
Page 137
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Operation
Page 138
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Project
Major Impacts
No
phase
Construction
Construction
Recommended Mitigation
measures
10
Construction
Anticipated
Residual
impacts
Chronic
health impact
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 140
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Anticipated
Project phase
Reinforcement measures
No
Residual
impacts
Construction
phase
Construction
The construction of the landfill project in
and operation the area will have positive impacts on
women (female headed households in
phases
particular) during and after the
construction works of the Sanitary
landfill through employment.
None
Operation
phase
None
Page 141
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Operation
phase
Operation
phase
Page 142
None
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
authorities regarding the implementation of the environmental mitigating measures and monitoring
of impacts.
Page 144
Potential environmental
-Uncontrolled leachate
release from the landfill
site into Hambisa River
will have an adverse
impact on the river.
Responsible
for
implementing
the mitigation
measures
- Landfill
b. Measures to Minimize
Leachate Infiltration from the
Disposal cells
Responsible for
monitoring the
implementation
of mitigation
measures
Mitigation
Monitoring
- AARDPO
During
Operation
phase
During
Operation
phase
During
Construction
Phase
During
Construction
Phase
-Construction
Supervisor
Time Horizon
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
Mitigation
Monitoring
- Construction
contractor
AARDPO,
Construction
Supervisor
During
Construction
Phase
During
Construction
Phase
-AARDPO,
Construction
Supervisor
During
Construction
phase
During
Construction
phase
>>
>>
Time Horizon
- Construction
contractor
>>
>>
- Installation of three-stage
leachate treatment system and recirculation facilities
c. Measures to minimize the
effects of Akaki Transfer
Station on Akaki well fields, as
well as Bole Arbasa & Koshe
Page 146
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible for
monitoring the
implementation
of mitigation
measures
Mitigation
Monitoring
-AARDPO,
Construction
Supervisor
During
Construction
phase
During
Construction
phase
-AARDPO
During
Construction
phase
During
Construction
phase
Responsible
for
implementing
the mitigation
measures
-Construction
Supervisor
Time Horizon
Page 147
social impacts
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
-Design
consultant
-AARDPO
- MoEF
-Construction
contractor
Time Horizon
Mitigation
Monitoring
- During
Operation
phase
- During
Operation
phase
- During
Operation
phase
- During
Operation
phase
- During
Operation
phase
- During
Operation
phase
- Oromia special
zone EPA office
incinerate
the
gas
at
temperatures of about 1,000 - - Landfill
- Emission of green house 1,200 C by the landfill gas flare. operator
gases (i.e. methane & CO2)
from the landfill will - Carryout monitoring program at
contribute
to
climate regular periodic intervals during - AACMA,
and after the working life of the
change.
site to assess effectiveness of the AARDPO
- Waste hauling trucks will landfill gas control measures.
create local air pollution
along the hauling routes
during operational phases.
AARDPO
- Oromia special
zone EPA, MoEF
staff
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
AA City
Roads
Authority
AARDPO
Responsible for
monitoring the
implementation
of mitigation
measures
Construction
Supervisor
AA City
Administration
(City Manager
Office)
AAEPA/Oromia
Special zone EPA
Page 149
Time Horizon
Mitigation
Monitoring
During
Construction
phase
During
Construction
phase
During
Construction/
Operation
phase
During
Construction/
Operation
phase
During
Operation
phase
During
Operation
phase
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible for
monitoring the
implementation
of mitigation
measures
-AA City
Administration
- Oromia Special
zone EPA
-AARDPO
- MOEF
Time Horizon
Mitigation
Monitoring
During
Operation
phase
During
Operation
phase
-Landfill
operator team
Responsible
for
implementing
the mitigation
measures
>>
>>
>>
>>
>>
>>
>>
>>
>>
>>
>>
>>
Page 150
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
- Oromia Special
-Mobile equipment sufficient to -AA City
ensure that operational standards Administration zone EPA
are met shall be provided and
- MOEF
maintained in use at the landfill -AARDPO
site.
Time Horizon
Mitigation
Monitoring
During
Operation
phase
During
Operation
phase
-Landfill
operator team
>>
>>
>>
>>
>>
>>
>>
>>
Page 151
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
-Design
consultant
AA City
Administration
- AACMA
-AAEPA, AA
Health Bureau
Time Horizon
Mitigation
Monitoring
AARDPO
Environmental
ist, Transfer
station
operating team
- AARDPO
-AAEPA, AA
Health Bureau
-AA City
Administration
City Manager
Office
- AARDPO
- AARDPO
-Development
Partners
Page 152
During PreConstruction
phase
During
Operation
phase
During PreConstruction
phase
During
Operation
phase
During
Operation
phase
During
Operation
phase
During
Construction
Phase
During
Construction
phase
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
- Improper disposal of
construction waste will
affect the environment
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
- Construction
Contractor ,
AARDPO
Environmental
ist
-Construction
contractor ,
Landfill
operating
Team
- Landfill
operating
Team
>>
Time Horizon
Mitigation
Monitoring
- AAEPA, Bereh
Woreda
Administration,
Construction
supervisor
- During
Construction
phase
- During
Construction
phase
-Construction
supervisor,
AARDPO
Environmentalist
- During
Operation
Phase
- During
Operation
Phase
- During
Operation
phase
- During
Operation
phase
-Oromia Special
zone EPA office
>>
Page 153
>>
>>
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
- Landfill
-Conduct regular (daily or
weekly) program of litter pick-up operating
at the sanitary landfill and transfer Team
station sites.
Responsible for
monitoring the
implementation
of mitigation
measures
- AARDPO
Environmentalist
Page 154
Time Horizon
Mitigation
Monitoring
- During
Operation
phase
-During
Operation
phase
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
-Construction
contractor ,
AARDPO
Environmental
ist
- Construction
Supervisor ,
AAEPA &
Oromia special
zone EPA
Environmentalists
>>
>>
Mitigation
Monitoring
-During
Construction
phase
-During
Construction
phase
>>
>>
>>
>>
>>
>>
>>
>>
>>
>>
Time Horizon
Page 155
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
Mitigation
Monitoring
>>
>>
>>
>>
>>
>>
>>
>>
Time Horizon
Page 156
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
Mitigation
Monitoring
-Landfill
operation
team,
AARDPO
Environmental
ist
- Oromia Special
zone EPA, MoEF
environmentalists
During
operation
phase
During
operation
phase
- AA City
Administration
, AARDPO
During
closure of
landfill
During
closure of
landfill
- AA City
Administration
, AARDPO
During
closure of
landfill
During
closure of
landfill
Page 157
Time Horizon
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
- AA City
Administration
, AARDPO
>>
>>
Time Horizon
Mitigation
Monitoring
During
closure of
landfill
During
closure of
landfill
>>
>>
>>
>>
>>
>>
Page 158
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
AA City
Administration
, AA Roads
Authority
AA City
Administration
>>
>>
- AACMA
- AACMA & AA
traffic police
department
-AA City
Administration
& its relevant
organs
AA City
Administration &
its relevant organs
Page 159
Time Horizon
Mitigation
Monitoring
During
construction
or Operation
phase
During
construction
or Operation
phase
>>
>>
-During
Operation
phase
-During
Operation
phase
-During
Operation
phase
-During
Operation
phase
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Workers involved in
waste sorting at transfer
stations, waste disposal at
the sanitary landfill cells
and other staffs directly
involved
in
waste
handling and hauling are
exposed
to negative
impact on occupational
health and safety.
Responsible for
monitoring the
implementation
of mitigation
measures
- AARDPO,
Landfill
operating team
A.A Bureau of
Labour and
Social Affairs,
AAEPA
Time Horizon
Mitigation
Monitoring
During
operation
phase
During
operation
phase
>>
A.A Bureau of
Labour and
Social Affairs
>>
>>
- Provision of training on
occupational safety and health
>>
>>
>>
>>
>>
>>
Responsible
for
implementing
the mitigation
measures
>>
>>
Page 160
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
Responsible for
monitoring the
implementation
of mitigation
measures
AARDPO &
Bereh Woreda
Administration
Bereh Woreda
Administration,
Oromia Region
EPA
Time Horizon
Mitigation
Monitoring
Before
construction
phase
Before
construction
phase
Responsible
for
implementing
the mitigation
measures
>>
>>
>>
>>
>>
>>
>>
>>
Page 161
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Potential environmental
10
- Construction workers
and truck drivers are
considered as having high
potential (or good
vectors) for the spread of
Sexually Transmitted
Diseases (STDs) and
HIV/AIDS virus due to
their mobility.
Responsible
for
implementing
the mitigation
measures
Responsible for
monitoring the
implementation
of mitigation
measures
Mitigation
Monitoring
-Construction
Contractor,
AARDPO,
AACMA
- AA Health
Bureau, Bereh
Woreda Health
Bureau
-During
Construction
& Operation
Phases
Before
construction
phase
Page 162
Time Horizon
Table 18: Environmental and social monitoring indicators, frequency of measurement and reporting
No.
Impact
Construction phase
Performance indicators to be
Frequency of
Frequency of Budget
Monitored
measurement
reporting
Bi-annually during
operation phase
(wet and dry
season)
Bi-annually
per
year in Birr
10,000
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Monthly starting
second year of
operation
monthly
30,000
Every year
Every year
9,000
Page 165
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Impact
No.
Performance indicators to be
Frequency of
Frequency of
Budget per
Monitored
measurement
reporting
year in Birr
biannually
6,000
biannually
5,000
The Sendafa sanitary landfill project will -Interview to check if adequate Prior to construction
cause permanent loss of 137.07 hectare of compensation is provided to the phase
farmland which used to be under the affected parties
entitlement of 217 farmers.
biannually
Once
before 10,000
the
construction
phase
Ones
Page 166
during 10,000
operation
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
II
Operation phase
Impact
No.
Performance indicators to be
Frequency of
Frequency of
Budget per
Monitored
measurement
reporting
year in Birr
Workers involved in waste sorting at Carry health surveillance on the Monthly for the first
transfer stations, waste disposal at the workers involved in waste sorting two years of
sanitary landfill cells and other staffs at the transfer stations
operation
directly involved in waste handling and
hauling are exposed to negative impact on
occupational health and safety.
biannually
20,000
yearly
3,000
first year of
operation
of operation phase
Page 167
month
for
a 25,000
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Note: -Monitoring reports from the various parties should be sent to the Addis Ababa Cleansing Management Agency for compilation and reporting to the Federal and
Regional offices in charge of the environment
-The Federal and regional offices in charge of the Environment will assign environmental inspector during project construction and operation
-Monitoring cost will be covered by the institutions assigned to undertake the monitoring.
Page 168
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Mitigation Measures
Unit
Quantity
Unit Cost
Cost in Birr
Remark
Cost is part of
the technical
component
(Birr)
The volume of leachate that will be
generated from the Sendafa
sanitary landfill site will range
from 645m3/day to 1336 m3/day
during the lifetime of the sanitary
landfill. If the landfill has no
leachate collection system the
leachate can enter into ground and
surface water resources around the
site.
-Uncontrolled leachate release
from the landfill site into Hambisa
River will have an adverse impact
on the river.
-In the absence of proper
management of the landfill,
leachate may have an adverse
impact on the Legedadi deep test
wells and shallow wells drilled by
AAWSA.
-The weak zone along the fault
striking from NW-SE on western
part of the Akaki transfer station
site can be a conducive path for
contaminants leaked from the
transfer station towards south part
of the Akaki well field where most
of the deep and shallow wells are
ZTS-EDCE & MTS
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
concentrated.
Cost is part of
the technical
contract
Page 170
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
quality
Cost is part of
the technical
contract
Page 171
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
300,000
Birr
150,000
Birr
Cost is part of
the technical
contract
Cost is part of
the operational
budget
Page 172
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
transport.
- Noise and vibration releases of
construction machines, vehicles
and waste hauling trucks will affect
residents in the neighborhood and
along the waste haulage routes.
A lump sum
of 50,000 Birr
per year
Cost is part of
the technical
contract
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Lump sum of
500,000
A lump sum of
100,000 Birr
per year
A lump sum of
200,000 Birr
Page 174
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
their mobility.
Page 175
No.
Item
Unit Cost
in Birr
Total cost
Environmental Mitigation
and Management Cost
850,000 Birr +
compensation of the
farmers that lost farm
land
2.
Environmental monitoring
costs
128,000
3.
4.
250,000
5.
200,000
6.
86,400
7.
Contingency (10%)
172,800
8.
Grand total
1, 987 200
300,000
Remark
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
However, the success of the Sendafa Sanitary landfill and transfer station project depends not only
on developing well engineered facilities, but also on the proper operation of these facilities. Hence
it is highly recommended that the Sanitary landfill and transfer stations are operated according to
the draft standards for Landfill Management as stipulated in the draft urban solid waste
management standards. For this purpose, it is also recommended to develop detailed manuals and
procedures that translate the requirements into daily operational procedures and to train the staff
and management of the sanitary landfill and transfer stations. Thus it is recommended that the
Sendafa sanitary landfill and transfer station project could be implemented with full
implementation of the mitigation measures.
Page 177
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
14. References
1. ARTELIA Ville et Transport and MCE, Detailed Design of Sendafa Sanitary Landfill, Solid
waste management project - Strategic and technical studies and Works supervision,
December 2013.
2. ARTELIA Ville et Transport and MCE, Detailed Design of Akaki Transfer Station, Solid
waste management project - Strategic and technical studies and Works supervision, March
2014.
3. ARTELIA Ville et Transport and MCE, Detailed Design of Bole Arbasa Transfer Station,
Solid waste management project - Strategic and technical studies and Works supervision,
March 2014.
4. Associated Engineering, Review of Feasibility Study and Preliminary Design Report, Water
Supply Project Stage III. Executive Summary. AAWSA April 1993.
5. Federal Environment Protection Authority, Draft Standards for Ambient Environmental
Quality, 2003.
6. Geological Survey of Ethiopia, Feasibility Study of the Chebe Weregenu Sanitary landfill
site for the City of Addis Ababa, April 2010.
7. IFC and World Bank Group, Environmental, Health, and Safety (EHS) Guidelines, April
2007.
8. Mekonnen M., Analysis of potential sanitary landfill waste disposal sites, the case of Addis
Ababa city (MSc thesis), Earth sciences Graduate programs, Addis Ababa University, June
2009.
9. Ministry of Urban Development, Housing and Construction, Urban Solid Waste
Management Standard (Part I), December 2013.
10. Shimeles K., Akaki Groundwater Project, Well field Summary Report, AAWSA May 1999.
11. TAHAL Consulting Engineers Ltd, Akaki Water Supply Project Phase 1; Hydro geological
Study Report, AAWSA, March 1992.
12. TAHAL Consulting Engineers Ltd in association with SHAWEL Consult International,
Akaki Water Supply Project. Feasibility Study; Volume II; Annexes. AAWSA, May 1992.
13. Tigistu Haile, Tamiru A. Abiye, Environmental impact and vulnerability of the surface and
ground water system from municipal solid waste disposal site: Koshe, Addis Ababa, 2012.
14. Yassin W. et.al, Evaluation of the 2003 2010 Development Plan of Addis Ababa City,
Addis Ababas National and International Settings and Roles, February 2011.
Page 178
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
15. WHO, Guidelines for Drinking Water Quality, Vol 1, Geneva World Health Organization,
2004
16. WWDCE, Evaluation of Groundwater Resources of Akaki Area Groundwater Prospective
Site (SWAWF), February, 2010.
17. WWDCE, Evaluation of Adaa and Becho Plains Groundwater Basins for Irrigation
Development Project, MOWR, 2008.
18. Zeleke Z. et.al, Evaluation of the 2003 2010 Development Plan of Addis Ababa City,
Final Summary: Main Social and Municipal Services, February 2011
Page 179
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Annexes
Page 180
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
To ensure that the public and stakeholders, interested groups, civil societies are informed
about the project and its impact and the information will clarify doubts about who will be
affected or benefit from the project.;
Enable meaningful and accessible participation of the public and the affected population in
particular;
Identify local issues and concerns to be addressed;
Obtain acceptance of the project both by the public and stakeholders.
On the nature of potential social impacts of the project and its impacts on the social, cultural
and economic ties and networks during and after construction works;
On the loss of productive resources mainly loss of farm and grazing land,
Identification of major social impact issues, such as involuntary resettlement, community
severance and compensation for affected properties and assets.
Soliciting the views of local population what beneficial impact they expect from the project
Social composition, settlement patterns, main sources of livelihood and past history of
displacement of the population, if any.
The minutes of both public and stakeholders consultation is attached in the Annex section. Since
the minutes are written in Amharic the following is the English translation of the minutes.
Page 181
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 182
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
8. We were promised that employment priority will be given to us. But now the employment
criteria and procedure is different from what has been promised earlier. Now the criteria to
employ a guard someone who has completed grade 10. This seems a deliberate action not to
employ from among us since there are not people who have finished grade 10.
9. Those of us who are living in close proximity to the project site are worried and concerned
that the project will affect our health in the future.
10. Generally, we have no objection in the implementation of the project as far as appropriate
mitigation measures are considered and implemented to minimize the negative impacts.
Figure 1 Public consultation at Sendafa
Page 183
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 184
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 185
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 186
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 187
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 188
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 189
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 190
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 191
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 192
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 193
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 194
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 195
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Page 196
Zero Draft ESIA Report of Sendafa Sanitary Landfill and Transfer Stations Project
Sociologist (B.Sc)
Page 197