VALORIZACIN A PRECIOS UNITARIOS

ESTRUCTURAS
VALORIZACIN N 01 (periodo 15 al 30/Nov./2014)

Obra

: CONSTRUCCIN DE POSTA MDICA

Ingeniero

LEONARDO GARCIA

Ubicac.

: PIURA

Modalidad de Ejecucin: A PRECIOS UNITARIOS

FECHA DE INICIO DE OBRA: 15/11/2014


Presupuesto 01: Estructuras
ITEM

PRESUPUESTO CONTRACTUAL

DESCRIPCION
UND.

CANT.

P.U.

VAL. ACTUAL

VAL ANTERIOR

PARCIAL

MET

(15-30/Nov/2014)

PARCIAL

MET

1.00

OBRAS DE CONCRETO SIMPLE

1.01

CONCRETO PARA CIMIENTOS CORRIDOS C:H-1:10 +


30% P.G.

m3

200.00

130.00

26,000.00

0.00

0.00

45.00

1.02

CONCRETO PARA SOBRECIMIENTOS C:H-1:8 + 25%


P.M.

m3

60.00

200.00

12,000.00

0.00

0.00

20.00

1.03

ENCOFRADO Y DESENCOFRADO DE
SOBRECIMIENTOS H=45cm.

m2

200.00

30.00

6,000.00

0.00

0.00

40.00

1.04

FALSO PISO DE CONCRETO 1:12 DE E=4"

m2

550.00

40.00

22,000.00

0.00

0.00

120.00

COSTO DIRECTO

66,000.00

GASTOS GENERALES (10%)

6,600.00

UTILIDAD (5%)

3,300.00

SUB-TOTAL OFERTADO

75,900.00

I.G.V. (18.00%)

13,662.00

PRESUPUESTO TOTAL OFERTADO

89,562.00

% AVANCE
NOTA:
- LA VAL. A PRECIOS UNITARIOS SE REALIZA CON LOS METRADOS EJECUTADOS Y LOS PRECIOS UNITARIOS OFERTADOS POR EL CONTRATISTA.

VAL. ACTUAL

VAL ACUMULADO

(15-30/Nov/2014)
PARCIAL

MET

PARCIAL

SALDO
MET

PARCIAL

5,850.00

45.00

5,850.00

155.00

20,150.00

4,000.00

20.00

4,000.00

40.00

8,000.00

1,200.00

40.00

1,200.00

160.00

4,800.00

4,800.00

120.00

4,800.00

430.00

17,200.00

15,850.00

15,850.00

50,150.00

1,585.00

1,585.00

5,015.00

792.50

792.50

2,507.50

18,227.50

18,227.50

57,672.50

3,280.95

3,280.95

10,381.05

CONTRATISTA.

21,508.45
24.02%

21,508.45
24.02%

68,053.55
75.98%

VALORIZACIN A SUMA ALZADA


ESTRUCTURAS
VALORIZACIN N 01 (periodo 10 al 31/Oct./2014)

Obra

: CONSTRUCCIN DE POSTA MDICA

Ingeniero

LEONARDO GARCIA

Ubicac.

: PIURA

Modalidad de Ejecucin: A SUMA ALZADA

FECHA DE INICIO DE OBRA: 10/10/2014


Presupuesto 01: Estructuras
ITEM

PRESUPUESTO CONTRACTUAL

DESCRIPCION
UND.

CANT.

P.U.

VAL. ACTUAL

VAL ANTERIOR

PARCIAL

MET

(10-31/Oct/2014)

PARCIAL

MET

1.00

OBRAS DE CONCRETO SIMPLE

1.01

CONCRETO PARA CIMIENTOS CORRIDOS C:H-1:10 +


30% P.G.

m3

200.00

130.00

26,000.00

0.00

0.00

45.00

1.02

CONCRETO PARA SOBRECIMIENTOS C:H-1:8 + 25%


P.M.

m3

60.00

200.00

12,000.00

0.00

0.00

20.00

1.03

ENCOFRADO Y DESENCOFRADO DE
SOBRECIMIENTOS H=45cm.

m2

200.00

30.00

6,000.00

0.00

0.00

40.00

1.04

FALSO PISO DE CONCRETO 1:12 DE E=4"

m2

550.00

40.00

22,000.00

0.00

0.00

120.00

COSTO DIRECTO

66,000.00

GASTOS GENERALES (10%)

6,600.00

UTILIDAD (5%)

3,300.00

SUB-TOTAL BASE

75,900.00

Factor de Relacin

SUB-TOTAL OFERTADO (SUB TOT. BASE x FR)


I.G.V. (18.00%)
PRESUPUESTO TOTAL

0.95834

72,738.01
13,662.00
86,400.01

% AVANCE

NOTA:

- LA VAL. A SUMA ALZADA SE REALIZA CON LOS METRADOS EJECUTADOS CONTRATADOS Y LOS PRECIOS UNITARIOS DEL VALOR REFERENCIAL AFECTADO POR EL
- EL FACTOR DE RELACIN DEBE SER CALCULADO HASTA LA QUINTA CIFRA DECIMAL

VAL. ACTUAL

VAL ACUMULADO

(10-31/Oct/2014)
PARCIAL

MET

PARCIAL

SALDO
MET

PARCIAL

5,850.00

45.00

5,850.00

155.00

20,150.00

4,000.00

20.00

4,000.00

40.00

8,000.00

1,200.00

40.00

1,200.00

160.00

4,800.00

4,800.00

120.00

4,800.00

430.00

17,200.00

15,850.00

15,850.00

50,150.00

1,585.00

1,585.00

5,015.00

792.50

792.50

2,507.50

18,227.50

18,227.50

57,672.50

0.95834

0.95834

0.95834

17,468.14

17,468.14

55,269.87

3,280.95
20,749.09

3,280.95
20,749.09

10,381.05
65,650.92

24.02%

24.02%

REFERENCIAL AFECTADO POR EL FACTOR DE RELACIN

75.98%

EJEMPLO
OBRA A SUMA ALZADA

MAYORES GASTOS GENERALES POR AMPLIACION DE PLAZO

MONTO CONTRACTUAL (Costo Directo):

S/. 5,000,000.00

(PRESUPUESTO REFERENCIAL)

GASTOS GENERALES VARIABLES

S/. 490,000.00

9.800%

GASTOS GENERALES FIJOS

S/. 10,000.00

0.200%

TOTAL GASTOS GENERALES 10%

S/. 500,000.00

(2)

PLAZO DE EJECUCION CONTRACTUAL

240

(3)

GASTO GENERAL DIARIO (1) / (2) = (3)

S/. 2,041.67

(4)

FACTOR DE RELACION

0.95876

(5)

GASTO GENERAL VARIABLE DIARIO ( 3 ) * ( 4 ) = ( 5 )

(1)

d/c
(S/. 490,000.00 / 240 das)
(Gasto General Variable / Plazo)

1,957.47

IU 39 - MES BASE
ITEM

AMPLIACION N

AMP. PLAZO
(Das)

GAST. GEN. VAR.


DIARIO

GGVD

MES

IU 39 - MES DE CAUSAL

Io

MES

Ip

FACTOR DE
REAJUSTE

MAYORES GASTOS
GENERALES

REAJUSTES DE MGG

R=Ip/Io

MGG=D x GGVD

REAJ=D x GGVD x (R1)

TOTAL MGG
IGV)

(sin

01

S/. 1,957.47

Nov-13

346.35

Jan-14

354.04

1.022

1,957.47

43.46

2,000.93

02

S/. 1,957.47

Nov-13

346.35

Apr-14

362.38

1.046

1,957.47

90.60

2,048.07

07

21

S/. 1,957.47

Nov-13

346.35

Jul-14

362.65

1.047

41,106.84

1,934.58

43,041.41

11

24

S/. 1,957.47

Nov-13

346.35

Aug-14

366.50

1.058

46,979.24

2,733.16

49,712.40

S/. 92,001.01

S/. 4,801.80

S/. 96,802.81

TOTALES

NOTA:
1.- OBRA A PRECIOS UNITARIOS: EL GASTO GENERAL DIARIO SE CALCULAR DIVIDIENDO LOS GASTOS GENERALES VARIABLES OFERTADOS POR
EL CONTRATISTA
2.- OBRA A SUMA ALZADA: EL GASTO GENERAL DIARIO SE CALCULAR DIVIDIENDO LOS GASTOS GENERALES VARIABLES DEL PRESUPUESTO
REFERENCIAL
3.- El IU=39 ES EL NDICE GENERAL DE PRECIOS AL CONSUMIDOR