Background
1.0. INTRODUCTION
References
Background
- Deep Foundation -
Type of Piles
- Installation Effect
- Material
- Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP PILE ACTION
Background
1.0. INTRODUCTION
References
Background
Pv
Pv
1.0. INTRODUCTION
Pu
Pu
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
- Material
-Material
- Installation Mode
Skin friction
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
End bearing
Vertical compressive loads:
Shallow foundation: by bearing capacity.
Deep foundation : by a combination of skin - friction and
end bearing.
12/4/2013
Background
Background
H
1.0. INTRODUCTION
References
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
-Material
-Material
-Installation Mode
-Installation Mode
Horizontal loads:
Shallow foundation:
by friction or adhesion developed along the foundation soil interface.
Deep foundation:
by lateral earth pressures.
Moments:
Shallow foundation:
By redistribution of bearing pressure.
Deep foundation:
by converting them to axial compression and uplift.
Background
Background
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
References
Background
-Material
-Installation Mode
1.0. INTRODUCTION
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
When the piles are installed in soft soils such that the
load is transferred through friction along the length of
piles, they are called friction piles.
Piles are also used to resist horizontal loads as in the
case of foundations for retaining walls, bridge
abutments and wharves. These piles are called laterally
loaded piles.
12/4/2013
Background
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
Background
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
Types of Pile
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
Types of Pile
1.0. INTRODUCTION
References
Background
Type of Piles
a) Material of construction
- Timber pile , steel pile , concrete pile, and composite
piles.
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
b) Cross-section
- Circular, square, hexagonal, I-section, H-section,
pipe, etc
e) Method of forming
- precast, prestressed, cast-in-situ, etc.
f) Method of installation
- driven, bored, vibrated, jetted, etc.
c) Shape
- Cylindrical, tapered, underreamed, etc
12/4/2013
Installation Effect
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
Displacement piles
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
Displacement piles:
if during the installation of pile, a large volume of soil is
displaced laterally and upwards.
-Installation Mode
2.0. PILE LOAD CAPACITY
Non-displacement piles:
their installation does not lead to any displacement of
soil at all.
Displacement piles
Displacement piles
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
12/4/2013
Non-displacement piles
Non-displacement piles
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
References
Type of Piles
Background
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
Non-displacement piles
Non-displacement piles
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
References
Type of Piles
- Installation Effect
-Material
Background
-Installation Mode
12/4/2013
Material of construction
Timber piles
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
References
Background
Type of Piles
Timber Piles
Steel Piles
Concrete Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
Steel piles
Steel piles
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Construction Material
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Installation Mode
-Construction Material
-Installation Mode
12/4/2013
Mode of Installation
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Construction Material
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Installation Mode
-Construction Material
-Installation Mode
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
Background
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
References
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
also
Splicing is difficult.
12/4/2013
References
Background
Type of Piles
- Installation Effect
-Construction Material
1.0. INTRODUCTION
References
Background
Type of Piles
-Installation Mode
2.0. PILE LOAD CAPACITY
- Installation Effect
-Construction Material
-Installation Mode
References
Background
Type of Piles
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
1.0. INTRODUCTION
References
Background
- Installation Effect
-Construction Material
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
12/4/2013
References
Background
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
References
Background
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
References
Background
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
References
Background
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
12/4/2013
References
Background
Type of Piles
- Installation Effect
-Construction Material
1.0. INTRODUCTION
References
Background
Type of Piles
- Installation Effect
-Installation Mode
-Construction Material
Underreamed piles
References
Background
Type of Piles
- Installation Effect
-Construction Material
References
Background
Type of Piles
-Installation Mode
- Installation Effect
-Construction Material
-Installation Mode
1.0. INTRODUCTION
-Installation Mode
Underreamed piles
10
12/4/2013
Underreamed piles
1.0. INTRODUCTION
References
Background
Type of Piles
-Installation Mode
2.0. PILE LOAD CAPACITY
1.0. INTRODUCTION
References
Background
- Installation Effect
-Construction Material
Underreamed piles
Type of Piles
- Installation Effect
-Construction Material
-Installation Mode
2.0. PILE LOAD CAPACITY
3.0. GROUP ACTION
1.0. INTRODUCTION
1.0. INTRODUCTION
References
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
-Construction Material
-Construction Material
-Installation Mode
-Installation Mode
11
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
References
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
-Construction Material
-Construction Material
-Installation Mode
-Installation Mode
Reinforcement cages
1.0. INTRODUCTION
1.0. INTRODUCTION
References
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
-Construction Material
-Construction Material
-Installation Mode
-Installation Mode
12
12/4/2013
Completed pile
Group of piles
1.0. INTRODUCTION
1.0. INTRODUCTION
References
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
-Construction Material
-Construction Material
-Installation Mode
-Installation Mode
1.0. INTRODUCTION
1.0. INTRODUCTION
References
References
Background
Background
Type of Piles
Type of Piles
- Installation Effect
- Installation Effect
-Construction Material
-Construction Material
-Installation Mode
-Installation Mode
13
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
References
Background
Type of Piles
Load Test
Cyclic Pile Load test
- Installation Effect
-Construction Material
Correlation N-Spt
-Installation Mode
1.0. INTRODUCTION
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
14
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
Correlation N-Spt
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
-Clay
-Examples
Load Test
If Qf >>Qpu,
the pile is called as a friction pile
15
12/4/2013
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
1.0. INTRODUCTION
1.0. INTRODUCTION
- Sand
- Sand
-Clay
-Clay
-Examples
-Examples
Load Test
Load Test
Where,
B = width of diameter of pile
= effective overburden pressure at the tip of pile
Nc , Nq , NY
C
L
16
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
-Clay
-Examples
Load Test
Cyclic Pile Load test
-Examples
Load Test
Cyclic Pile Load test
Correlation N-Spt
3.0. GROUP ACTION
Load Test
Qu = qpu Ab + fs As
-Clay
-Examples
Correlation N-Spt
Where,
fs = unit skin resistance and
As = surface area of the pile in contact with the soil.
-Examples
Load Test
1.0. INTRODUCTION
17
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
Driven piles:
using the effective stress analysis, one can assume
c = 0 for a granular soil. The ultimate load capacity of a
single pile, driven into a granular soil, is obtained by
Load Test
Qu = qpu Ab + fs As
Relationship
between Nq and '
1.0. INTRODUCTION
- Sand
- Sand
-Clay
-Clay
-Examples
-Examples
Load Test
Load Test
Correlation N-Spt
Correlation N-Spt
18
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
Correlation N-Spt
3.0. GROUP ACTION
1.0. INTRODUCTION
1.0. INTRODUCTION
Load Test
Load Test
Correlation N-Spt
Correlation N-Spt
19
12/4/2013
Skin friction
Skin friction
1.0. INTRODUCTION
1.0. INTRODUCTION
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
-Clay
-Examples
Load Test
Cyclic Pile Load test
Skin friction
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
or,
where,
av = average effective overburden pressure over the
embedded length of pile
1.0. INTRODUCTION
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile
material
Steel
Concrete
Timber
20
0.75
0.67
Correlation N-Spt
3.0. GROUP ACTION
Values of K
Loose
Dense
Sand
sand
0.5
1.0
1.0
2.0
1.5
4.0
20
12/4/2013
Skin friction
1.0. INTRODUCTION
1.0. INTRODUCTION
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
1.0. INTRODUCTION
Load Test
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
-Examples
Correlation N-Spt
3.0. GROUP ACTION
21
12/4/2013
1.0. INTRODUCTION
Load Test
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
Piles in clay
1.0. INTRODUCTION
1.0. INTRODUCTION
Load Test
Correlation N-Spt
Correlation N-Spt
22
12/4/2013
Piles in clay
Piles in clay
1.0. INTRODUCTION
1.0. INTRODUCTION
- Sand
- Sand
-Clay
-Clay
Qu= qpu Ab + fs As
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
-Examples
Load Test
Correlation N-Spt
Correlation N-Spt
Qu= cub Nc Ab + cu As
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Piles in clay
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
- Sand
Correlation N-Spt
3.0. GROUP ACTION
where,
cub = undrained cohesion at the base of pile
Nc = bearing capacity factor for a deep foundation
(usually is equal to 9).
Piles in clay
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
23
12/4/2013
Piles in clay
Piles in clay
1.0. INTRODUCTION
1.0. INTRODUCTION
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
Piles in clay
1.0. INTRODUCTION
1.0. INTRODUCTION
To determine skin friction capacity of bored and cast-insitu piles, Tomlinson recommended an average value of
= 0.45 in firm to stiff clays with an upper limiting value of
1 kg/cm for unit skin friction resistance.
Load Test
Cyclic Pile Load test
Pile Driving Formulae
Consistency
value
N value
Bored
piles
Driven
cast-insitu piles
Load Test
Correlation N-Spt
3.0. GROUP ACTION
Soft to very
soft
<4
0.7
1.0
Medium
48
0.5
0.7
Stiff
8 15
0.4
0.4
Stiff to hard
> 15
0.3
0.3
24
12/4/2013
Example 1
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
1.0. INTRODUCTION
-Clay
-Examples
Load Test
Cyclic Pile Load test
Correlation N-Spt
3.0. GROUP ACTION
Example 1
Example 1
1.0. INTRODUCTION
1.0. INTRODUCTION
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
qpu = Nq
fs(av) = (av) K tan
Correlation N-Spt
3.0. GROUP ACTION
25
12/4/2013
Example 1
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
- Sand
-Clay
-Examples
Load Test
Cyclic Pile Load test
Pile Driving Formulae
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
- Sand
-Clay
-Examples
Correlation N-Spt
3.0. GROUP ACTION
Example 2
Load Test
Cyclic Pile Load test
Example 2
Example 2
1.0. INTRODUCTION
1.0. INTRODUCTION
- Sand
-Clay
-Examples
- Sand
-Clay
-Examples
Load Test
Load Test
Correlation N-Spt
Correlation N-Spt
Qu= cub Nc Ab + cu As
Qu = (37.5 x 9 x 0.45 x 0.45) + (0.8 x 37.5 x 4 x 0.45 x 15)
= 68 + 810
= 878 kN
26
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
Pile Load Test
Cyclic Pile Load test
Pile Driving Formulae
Correlation N-Spt
3.0. GROUP ACTION
27
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
Correlation N-Spt
Correlation N-Spt
28
12/4/2013
Correlation N-Spt
3.0. GROUP ACTION
29
12/4/2013
Correlation N-Spt
3.0. GROUP ACTION
S = Se + Sp
Q = Qf + Qp
Correlation N-Spt
3.0. GROUP ACTION
S = l + Sb
Where,
l = compression of pile &
Sb = compression of soil at base
Typical load settlement plot
from cyclic pile load test
30
12/4/2013
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
Pile Load Test
Where,
Sc = elastic compression of soil at base
Sb = plastic compression of soil at base
S = l + Sc + Sb
Therefore,
or,
Se + Sp = l + Sc + Sb
Sc = (Sp Sb) + Se - l
Then, Sc = Se l
S = Se + Sp
Further,
Correlation N-Spt
Sc = Se
2. Draw a straight line parallel to straight portion of
Curve I to divide the load into two parts and
obtain the approximate values of point resistance,
Qp and skin friction resistance, Qp.
31
12/4/2013
Correlation N-Spt
3.0. GROUP ACTION
Correlation N-Spt
3.0. GROUP ACTION
Example 3
Example 3
1.0. INTRODUCTION
1.0. INTRODUCTION
Correlation N-Spt
Correlation N-Spt
32
12/4/2013
Example 3
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Qa = 2 x 500/3 = 333.33 kN
Correlation N-Spt
1.0. INTRODUCTION
Correlation N-Spt
3.0. GROUP ACTION
1.0. INTRODUCTION
1.0. INTRODUCTION
Correlation N-Spt
3.0. GROUP ACTION
Qs = WH/ F(S+C)
Where,
W = weight of hammer falling through a height H.
S = real set per blow
C =empirical factor, allowing reduction in the
theoretical set, due to energy loss
F = factor of safety, usually taken as 6.
33
12/4/2013
Qa = 166.64 E/ (S+2.54)
Where,
Qs = allowable pile load in kN
E = energy per blow in kilo joules (kJ)
S = average penetration in mm per blow for the
final 150 mm of driving
(minimum permissible value of S = 1.25 mm)
R = Wh / (S + C/2)
= Wh / (S+ (C1+C2+C3)/2)
Where,
R = ultimate driving resistance in tonnes. The safe load
is estimated by dividing the ultimate driving
resistance by a factor of safety of 2.5.
1.0. INTRODUCTION
1.0. INTRODUCTION
Correlation N-Spt
3.0. GROUP ACTION
34
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
C2 = 0.657 RL/A
C3 = 3.55 R/A
Where,
35
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
Where,
36
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
In terms of N values,
For displacement piles, fs = 2 Nav kN/m2
For H piles, fs = Nav kN/m2
Where,
Nav = average field value of N along the length
of the pile.
1.0. INTRODUCTION
1.0. INTRODUCTION
37
12/4/2013
Clays
qc / 25 < fs
Sands
Fs< qc/150
1.0. INTRODUCTION
2.0. PILE LOAD CAPACITY
Static Pile load
Pile Load Test
Cyclic Pile Load test
1.0. INTRODUCTION
1.0. INTRODUCTION
Where,
Correlation N-Spt
3.0. GROUP ACTION
Examples
38
12/4/2013
1.0. INTRODUCTION
1.0. INTRODUCTION
Settlement
Examples
The pile cap may either stand clearly above the ground
level or may rest on the soil, partially or fully buried
below ground level.
Failure
Settlement
Examples
When pile cap stand clearly above the ground level, the
pile group is called free standing pile group.
Settlement
Failure
Examples
Settlement
Examples
= Qug / n Qu
Where, n is the number of piles in group and Qu is
the load capacity of one pile.
39
12/4/2013
Friction Piles
INTRODUCTION
INTRODUCTION
GROUP ACTION
GROUP ACTION
Spacing of Piles
Spacing of Piles
Failure
Failure
Settlement
Settlement
Examples
Examples
INTRODUCTION
INTRODUCTION
GROUP ACTION
GROUP ACTION
Failure
Settlement
Examples
Settlement
Examples
40
12/4/2013
Spacing of Piles
Failure
Settlement
Examples
INTRODUCTION
PILE LOAD CAPACITY
GROUP ACTION
A. By block failure
Spacing of Piles
A. Block Failure
INTRODUCTION
Pile Failure
Settlement
Examples
B. Block Failure
INTRODUCTION
where,
Spacing of Piles
Pile Failure
Settlement
Examples
41
12/4/2013
Spacing of Piles
Pile Failure
Settlement
Examples
Pile Failure
Settlement
Examples
Settlement
Examples
42
12/4/2013
Settlement
Examples
Settlement
Examples
Spacing of Piles
Pile Failure
Settlement
Examples
GROUP ACTION
Pile Failure
Settlement
Examples
43
12/4/2013
Settlement
Examples
INTRODUCTION
PILE LOAD CAPACITY
GROUP ACTION
Examples
GROUP ACTION
Spacing of Piles
Spacing of Piles
Pile Failure
Pile Failure
Settlement
Settlement
Examples
Examples
Pile Failure
Settlement
where,
s = ratio of pile spacing to pile diameter.
r = number of rows in pile group.
44
12/4/2013
Spacing of Piles
Pile Failure
Settlement
Examples
45