CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
2012

POWER SYSTEM OPERATION

Time Allotted : 3 Hours

Full Marks : 70

pap

The figures in the margin indicate full marks.

Candidates are required to give their answers in their own words


as far as practicable.

GROUP A

wb
er.

( Multiple Choice Type Questions )


1.

Choose the correct alternatives for any ten of the following :


10 1 = 10
i)

7327

a)

Load Bus

c)

Generator Bus

b)

Slack Bus

d)

None of these.

Which one is correct in Static Load Flow Studies ?

in
a c.
ut .

ii)

Which bus is considered as reference bus in Static


Load Flow Study ?

a)

The convergence rate of GS method is faster than


NR method.

b)

The convergence rate of NR method is faster than


GS method.

c)

The convergence rates of GS method and NR


method are same.

d)

The convergence rates of GS method and NR


method are incomparable.

[ Turn over

CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
iii)

The transmission loss is a function of

/q
p:/
htt
iv)

a)

Plant generation

b)

Fuel cost of plant

c)

Plant age

d)

Type of automation technique used in plant.

If the excitation of a grid connected generator increases


then

b)

the steady state stability limit of the generator


increases

c)

the steady state stability limit of the generator


remains same

d)

the steady state stability limit of the generator


either increases or decreases.

wb
er.

vi)

the steady state stability limit of the generator


decreases

pap

v)

a)

How many limiters are there in AVR ?


a)

c)

d)

7.

in
a c.
ut .

7327

Which National Grid is not connected to other National


Grids through HVAC lines ?

vii)

b)

a)

East

b)

West

c)

North

d)

South.

Which type of fault is more common ?


a)

Symmetrical fault

b)

SLG fault

c)

LLG fault

d)

LL fault.

CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
viii) Active power is sensitive to

/q
p:/
htt
ix)

7327

change in voltage angle

c)

change in reactive power

d)

change in environmental condition.

STATCOM is
a)

series connected FACTS device

b)

shunt connected FACTS device

c)

combined series-shunt connected FACTS device

d)

combined series-series connected FACTS device.

The OLTC is used in transformer to


a)

regulate the bus voltage

b)

improve the power factor

c)

reduce load voltage

d)

to mitigate sub-synchronous resonance.

The transient stability limit is


a)

higher than the steady state stability limit

b)

equal to the steady state stability limit

c)

lower than the steady state stability limit

d)

infinite.

IEGC was published in

in
a c.
ut .

xii)

b)

wb
er.

xi)

change in voltage magnitude

pap

x)

a)

a)

2003

b)

2004

c)

2005

d)

2006.

[ Turn over

CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
GROUP B

/q
p:/
htt

( Short Answer Type Questions )


Answer any three of the following.

2.

5 = 15

Write down the different procedures of reactive power


compensation.

3.

A generating station has three section bus-bars connected

pap

with a tie-bar through 6% reactors rated at 5000 kVA. Each


generator is of 5000 kVA with 12% reactance and is
connected to one section of bus-bars. Find the total steady

wb
er.

input to a dead short-circuit between the lines on one of the


sections of bus-bar with reactors.

4.

Write down a few examples of grid in discipline.

5.

Draw the block diagram of load frequency controller and

in
a c.
ut .

excitation voltage regulator of a turbo generator and explain


it.

6.

What are the conditions for connecting power station to


grid ?

7327

CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
GROUP C

/q
p:/
htt

( Long Answer Type Questions )


Answer any three of the following.

7.

a)

15 = 45

Briefly explain the algorithm to solve static load flow


equation of n bus system considering Newton-Raphson
method.

b)

10

Determine the Y bus for the 3 bus system whose


connectivity and series line impedances are as follows :

pap

a)

Impedance ( pu )

12

0.06 + j0.18

13

0.03 + j0.09

2-3

0.08 + j0.24

wb
er.

8.

Line ( bus to bus )

Derive the co-ordination equations for optimum load


dispatch considering transmission losses.

b)

Prove that transmission losses are the function of plant


generation.

c)

A power system has two generating

4
plants

and

in
a c.
ut .

the power is being dispatched economically with


P 1 = 150 MW and P 2 = 275 MW. The loss coefficients
are :
B 11 = 0.10
B 12 = 0.01
B 22 = 0.13
7327

10 2 MW 1.

10 2 MW 1.
10 2 MW 1.
5

[ Turn over

CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
To raise the total load on the system by 1 MW will cost

/q
p:/
htt

an additional Rs. 200 per hour.


Find (i) the penalty factor of plant 1, (ii) the additional
cost per hour to increase the output of plant 1 by
1 MW.

9.

a)

Derive the expression of fault current for an SLG fault


and draw the sequential diagram of it.

pap

b)

The currents in a 3-phase unbalanced system are :


I R = 12 + j6 A, I Y = 12 j12 A, I B = 15 + j10 A.

wb
er.

Calculate the zero, positive and negative sequence


components of red and yellow phase currents.
c)

What do you mean by 'spinning reserve' and 'bottling of


reserve' of power plants ?

10. a)

in
a c.
ut .
5

Discuss about the different processes of improving the


power system stability.

7327

Explain the turbine speed governing system with neat


diagram.

c)

Draw the schematic diagram of TSC-TCR type SVC and


explain its principle of control.

b)

CS/B.TECH(PWE)/SEM-7/PWE-704/2012-13
11. a)

Write down the process of scheduling of power

/q
p:/
htt

generation and dispatch as per IEGC.

b)

What do you understand by UI charges ? Explain with


a suitable example.

c)

What are the general methodologies of grid restoration


after cascade tripping ?

wb
er.

pap
7

in
a c.
ut .

7327

[ Turn over