PRESENTED BY
Muhammad Sohaib Shahid
2013-EE-121
Anas Tariq
2013-EE-112
Muahmmad Muneeb
2013-EE-24
Project Outset
A part of China Pakistan Economic Corridor
(CPEC), HUBCO is the only power project
under CPEC in Balochistan.
The project is being undertaken through a
joint venture between HUBCO and China
Power International Holding Limited (CPIH), a
wholly-owned core enterprise of State Power
Investment Corporation (SPIC), one of the five
State Power Corporations in China.
The construction consortium included:
Ansaldo ENERGIA of Italy, technical
coordinator and designer and supplier of the
turbine generators.
Design and supply of Boilers will be done by
Japan heavy industries Co Ltd.
SGE SNC France is given the civil contract of
the project.
Generation Capacity
ELECTRICAL SYSTEM
There are four generators which develop a power of 380 MVA each (power factor
0.85) and are of the windings direct cooling type. The stator winding is cooled by
the circulation of de-ionised water which passes through the hollow conductor
which forms part of the semi-coils. The rotor winding is cooled directly by hydrogen.
The generated power is dispatched to WAPDAs grid through two overhead 500 kV
lines through a half-breaker scheme, SF insulated substation. There are also two startup transformers. Station power supply and unit auxiliary power supply are provided
to minimize any effects of equipment failure or maintenance on continuity of
service.
The electrical auxiliary power system rests on three major sub-systems:
AC power system
DC power system
AC emergency power system
The station transformers performs the start-up and shut-down of the plant and
supplies the common services boards.
The emergency ac source is ensured by emergency diesel and 110V inverters,
supplying the loads necessary for the safe shut-down of the power plant.
Electricity Tariff
SITE DETAILS
Coal Jetty
Although Pakistan has very large coal reserves but mostly it is of inferior quality.
Miners have to go 500 1000 feet deep, which ultimately increases cost of production.
The local coal mines are not mechanized and this results in high production cost
Coal is by no means a homogenous term; and in fact can be categorized or ranked
according to the degree to which the original plant material has been transformed into
carbon.
The ranking of coal therefore, from most to least carbon content are:
Anthracite
Bituminous Coal
Sub-Bituminous Coal
Lignite
Pakistans coal reserves are almost exclusively comprised of Lignite-known to be the
dirtiest of the fossil fuels.
(Contd)
The Calorific Values of the coal that will be imported along with weighted
average of the calorific values of local coal and imported coal are given as
following;
The low weighted average calorific values of local coal solidifies the point of
importing coal from countries having coal reserves with good calorific
values.
THERMODYNAMICS OF PLANT
The Plant design and engineering are based on proven technology. It
operates on the basis of a conventional steam cycle such that the steam
produced by the boilers drives the turbine generator sets to make
electricity.
The thermodynamic characteristics of the units are as follows:
Steam pressure and temperature: 170 bar, 540OC;
single re-heating up to 540OC;
condensate and feed-water pre-heating, up to 250OC;
turbine exhaust pressure: 0.087 bar (2.5 in Hg). This is somewhat higher
than is normal because of the high average temperature of
circulating water available at the plant site.
The plant, when operating at full load converts energy in the residual
fuel oil (RFO) at a thermal efficiency of approximately 38.9%.
COOLING WATER
The cooling water used in the condensers and for the auxiliary plant is
drawn from the Arabian Sea through submerged concrete inlet channel
about 300m long
The sea water flows from the circulating water intake through screens to
remove debris and is pumped by the main sea water circulating pumps
through the intake piping and valves to the condensers.
The water is discharged through further piping and valves into a culvert
and seal pit before flowing into the Hub River estuary through a 1,000m
discharge canal.
The remainder of the auxiliary plant and systems are cooled by a closed
circuit water system, using demineralised water.
AUXILIARY PLANTS
In addition to the main electricity production and fuel storage facilities, the
plant has auxiliary plant or sub-plant facilities which include:
A desalination plant to convert sea water into feed, demineralised and
potable water
Water and waste water treatment plant
RFO and lubricating oil processing plant
Safety equipment
A fire fighting system
Hydrogen gas generation facilities
An auxiliary boiler house
Environmental Concerns
According to the financial statement, the
Balochistan Environmental Protection Agency
has granted CPHGC a no-objection certificate
for initiating work on the hub power plant and
construction work at the site has been started
a long ago.
Earlier, HUBCO conducted an environmental
and social impact assessment study, with the
assistance of renowned consultants Hagler
Bailey and submitted a report to the
environmental protection agency.
This was followed by a public hearing as well.
The remarks of the report were quite
satisfactory concerning the plant.
SOCIO-ECONOMIC BENEFITS
The project shall be instrumental in socioeconomic uplift of the remote area of Hub
The project construction will provide
employment opportunities through induction of
skilled, semi-skilled and unskilled workforce for
the project besides adding a significant amount
of power output to the national grid.
Hub coal power project will not only bring
prosperity to the country but will also accelerate
the pace of development in Balochistan by
generating employment opportunities for the
local population