2004 Thesis
Jarod F. Stanton
Mechanical Option
Architectural Features:
~ 32,000 ft2, Two Story Plus
Basement Museum Building
~ Masonry Faade Containing Brick,
Bluestone and Concrete
~ 24 x 28 x 13.5 Insulated Glass,
Pyramidal Skylight
~ Zinc Cornice on Roof, Concealing
the Equipment Well
Project Information:
> Estimated Project Cost of $5.7 Million, With A
New Estimate Forming As The Project is Being Bid
Upon
> Proposed Fast Track Delivery Method
> Only Bidding (Invitation Only) For Site,
Foundation And The Steel Package Has Taken
Place
Mechanical Features:
*Two RTUs & Three AHUs for 33,800 CFM
*19 VAV Boxes (Heating Only)
*Two 238 MBH Steam Generators
*Two 2000 MBH Boilers for the Hot Water Piping
Serving Two Duct Coils, VAV Boxes, Tube and
Panel Radiators, Fan Coil Unit, and the AHUs
*One 60 ton chiller
Structural Features:
^ Standard Steel Framing with
Reinforced Masonry Shear Walls\
^ Steel Stud Backing Behind Masonry
Walls
^ Concrete Floor Slabs on Metal
Decking Containing Support Draped
Mesh with Chairs
Electrical Features:
- 42 KA AIC Main Breaker, 1000/3 N-Frame With
160 KA TVSS Which Feeds Both RTUs, And The
Elevator
- Dimmable Track Lighting Located In The
Galleries And Conference Room
- Integrated Video Surveillance/ Door Intercom
System And Card Access System For Security
Purposes
Jarod F. Stanton
Mechanical Option
www.arche.psu.edu/thesis/2004/jfs73
Table Of Contents
Executive Summary
Introduction
Background / Site.
Existing Conditions
Architecture...
Structural...
Electrical/Lighting
Mechanical.
3
5
6
7
Depth Study
DOAS System ... 9
Breadth Study
Structural
Analysis of mechanical equipment on roof.
Construction Management
EPS formwork...
Smart Windows.
Cooling Tower Study
17
19
23
25
References.
26
Credits/Acknowledgements..........
Appendices
Appendix A: Mechanical
Appendix B: Structural
27
Jarod F. Stanton
Mechanical Option
13
Executive Summary
1
Jarod F. Stanton
Mechanical Option
Introduction To:
Background / site
The Lehigh County Historical Society has been collecting artifacts of the Lehigh
Valley since times as early as 1904. Since then over 30,000 historic artifacts have been
obtained, including items such as tools, clothes, pictures, artwork, books, products, family
documents, newspapers, maps, records of social event and buildings. The Lehigh County
Historical Society provides exhibits, literature and educational programs to inform visitors
about the history and development of the Lehigh Valley.
The Lehigh County Historical Society is based in Allentown, Pennsylvania. The
Old Courthouse, located on Hamilton and 5th Street, contains the offices of the Lehigh
Valley Historical Society. Other historical sites that the Lehigh Valley Historical Society
has helped maintain are the George Taylor House, Trout Hall, Troxell-Steckel House and
Farm Museum, Haines Mill Museum, Claussville School, Lock Ridge Furnace Museum
and the Saylor Park Cement Kilns. Another building that contains a large archive of the
Lehigh Valleys heritage is the Scott Andrew Trexler II Memorial Library.
The Lehigh County Historical Society decided to build a new building to house more
artifacts and offices. The new building, named The Lehigh Valley Heritage Center, will be
constructed on an existing plot where Trout Hall is located, on Walnut and South Penn
Streets. The Lehigh Valley Heritage Center will be a 32,000 ft2 multi-space building.
This two story, plus basement structure will contain offices, a conference room, a school
program room, an orientation room, galleries, storage space, a museum shop, library, and
a large, open lobby at the entrance. The building will not only serve as a visitors center,
to welcome and inform guests visiting the Lehigh Valley, but also as a research and
learning center to residents of the Lehigh Valley.
Although the Lehigh Valley Heritage Center wont be a historic building anytime
soon, the historic information contained inside the building will take people through time,
from the inhabitance of the Lenni Lenape Native American tribe to the arrival of the settlers to
the industrial revolution era and finally, to the modern day Lehigh Valley.
2
Jarod F. Stanton
Mechanical Option
Existing Conditions:
Architecture
The Lehigh Valley Heritage Center will serve as a collector for artifacts of the
Lehigh Valley. The 32,000 ft2 building is currently being constructed at the corner of
Walnut and South Penn Streets. The building will be two stories tall with a basement. A
portion of the basement wall will be exposed on the south and west faade of the building.
The building materials of the faade will be poured in place concrete for the basement, face
brick, ground face CMU block and bluestone for the first and second floor walls and a zinc
cornice around the roof. The northeast corner of the building will serve as the main
entrance and is designed as a large, open lobby with plenty of windows spanning the walls
as well as a pyramidal skylight above.
The spaces inside the Heritage Center are of mixed purposes, as the building is
designed to hold more than just artifacts. The building footprint is 12,310 ft2 yet the
basement is only 8,345 ft2. The northern area of the building containing the reading room
and workroom areas is slab on grade construction. The basement contains three storage
rooms, two mechanical rooms and corridor space. The loading dock/receiving area is
located off of the sidewalk level on the south faade, which is between the basement and
first floor. A south entrance to the building is also located off of the sidewalk elevation.
This entrance leads to a small vestibule where the elevator and a set of stairs are located.
The first floor contains an orientation room where presentations will be given
through various media, an archive storage room, a reading room/library (in conjunction
with the archive storage), a workroom for preparing artifacts, a museum shop, restrooms
and the lobby.
The second floor contains twelve offices (including the directors office), a volunteer
room, work stations, two galleries, a school program room (for children visiting on field
trips), restrooms, a copy room, a processing room, a conference room and a balcony above
the lobby. The area containing the two galleries and lobby has a higher roof structure
than does the rest of the building. The galleries have an open ceiling, exposing the open
3
Jarod F. Stanton
Mechanical Option
A cornice wraps around the lower ceiling height and is made of copper. A cornice
also wraps around the upper roof, but is made of zinc. A large glass pyramid is located on
the upper roof, above the lobby. The pyramid is approximately 28 wide by 32 long and is
17 above the upper roof elevation. Elevations of the building from the north, south and
west are given below in Figures 1, 2 and 3.
4
Jarod F. Stanton
Mechanical Option
Structural
The Lehigh Valley Heritage Center contains a steel skeleton. The steel framed
building sits on piers, connected to the footings in the foundation walls of the basement.
The basement walls are 16 thick around the perimeter of the building to withstand a
5,000 psf soil bearing pressure. Pilasters are located around the perimeter, which contain
steel columns supported on the piers. The basement walls are 17 tall. The northern
and eastern walls are underground, while the western and southern walls are partially
exposed. Depth of the footings varies around the building, as because of the excavated and
unexcavated areas of the basement. The footings are stepped as they approach the
excavated area of the basement, lowering them as much as 11.
The walls of the faade of the building are reinforced, shear masonry walls. The
walls will consist of face brick, crushed face CMU block, and concrete. The floor to floor
height from the first to second floor is 16, while the floor to roof height of the second floor
varies between 12-4 and 20-4. Behind the exterior walls are steel studs on which
gypsum board is attached.
The basement flooring will consist of 6 poured concrete containing 44 W4.0 x W4.0
welded wire fabric. The first and second floors will consist of 5 poured concrete,
containing 66 W2.9 x W2.9 welded wire fabric, on a 22 gauge composite galvanized metal
deck. In the museum shop and restrooms on the first floor, the slab is 7 thick. The roof
framing is made of girders, beams and open web steel trusses. Metal decking with board
insulation and built up roofing will sit on the structural members. A cornice wraps around
the perimeter of the building on both the lower and upper roof.
Some mechanical equipment is contained on the roof, in equipment well. The
equipment well is located on the south western area of the roof, butting up against the
higher roof structure of the main gallery. These units sit on dunnage, which is a support
system that sits above the roof elevation. The dunnage transfers the weight of the units
from its support system to the columns supporting the roof structure. The roof structure
consisting of the metal decking and built up roofing have negligible structural integrity.
The walls of the well are composed of rectangular hollow structural steel, mainly HSS 6 x
8 . The faade consists of a zinc cornice, open at the bottom 4 of the western wall.
5
Jarod F. Stanton
Mechanical Option
Electrical/lighting
The Heritage Center contains many types of lighting, inside the building and
outside. Outside fixtures include bollard metal halide, in-wall light, wall sconce metal
halide, in-ground well light, architectural wall light and area cutoff for the parking area.
The majority of the lighting is concentrated on the concrete terrace, located on the eastern
side of the building, outside the lobby. Lights also span the southern faade of the
building to illuminate the sidewalk and parking area.
Interior lighting fixtures are mainly fluorescent fixtures, recessed in the suspended
ceiling. Downlights are found in the corridor surrounding the lobby, the orientation room,
stairwells, bathrooms, conference room and in the galleries. Tracks are placed in the
galleries, but no fixtures are assigned to them, a note on the drawings indicates the owner
decides the type of lighting that will go on the track the positions that they will face.
Dimmable lights are specified in the galleries as well as the conference room. The lighting
can be remotely controlled by radio signals or by touch panels located on the walls. Lutron
is the specified company that will provide the controls for dimming capabilities.
Electricity to the building is supplied by PP&L Co. A transformer is located in
vault located on the southwest corner of the building. The secondary feeders from the
transformer are routed in mechanical room 006 in the basement where they are attached
to a switch gear. The switch gear contains a 42KA AIC Main Breaker. Several wires are
run from the switch gear to the roof top units, the elevator, power panels, lighting panels
and mechanical panels. These wires carry 277/480V 3 phase power. Another transformer
(150 KVA 480delta stepdown) is located after the switch gear and distributes 208Y/120V
to the rest of the power and light panels. The entire building contains 11 panel boards,
including the main distribution panel.
The building fire alarm and detection system is also served by the power
distribution equipment. The system contains smoke detectors, heat detectors, duct
detectors, pull stations and strobe lights, with and without horns, which are all connected
to a fire alarm control panel and the building control system. The building also contains
an integrated security system with cameras, card access readers, door contact sensors,
motion detectors and break glass sensors.
6
Jarod F. Stanton
Mechanical Option
Mechanical
Because the building has different spaces located within it, there isnt just one
mechanical system. The basement contains two mechanical rooms, mechanical room 006,
located on the southern area of the basement, and mechanical room 003, located adjacent
to and north of mechanical room 006. Mechanical room 006 contains a 60 ton air cooled
chiller, two 149 gpm circulating pumps for the chiller, a 3,055 cfm air handling unit (AHU3, containing HW and CHW coils) and a 4,200 cfm relief air fan connected to a motorized
louver (30x72x6).
Mechanical room 003 contains two 238 MBH steam generators (gas fired), a 11,993
cfm air handling unit (AHU-1), a 4,214 cfm air handling unit (AHU-2) and two 2,000 MBH
gas fired boilers. The boilers are located in an enclosed room within mechanical room 003
because of code dealing with explosion containment and egress from the space. The room
also contains several pumps for the boilers (two 135 gpm boiler pumps, one 125 gpm
primary loop pump, one 35 gpm pump for VAV boxes, one 8 gpm pump for panel radiators
located in the lobby and stairwell 001 and one 4 gpm pump for the baseboard units located
in the loading dock, reading room, directors office and south vestibule). The basement also
contains two outdoor air intake fans for the steam generators and boilers (combustion air),
one 1,668 cfm fan for the boilers and one 208 cfm fan for the steam generators.
The steam generators and boilers are direct vent equipment. The vents travel up
the mechanical shaft to the roof, which is approximately 53 ft above the basement floor.
The steam generators serve air handling units one and two, located in the same room.
This is because of the humidity control in the storage and gallery spaces that must be
maintained. The owner specified that the spaces be within 5%+/- of a 45% relative
humidity design condition. The Archival Storage, Museum Collections Storage and
Negative Storage rooms all require a climate consisting of forty-five percent relative
humidity (+/- five percent) at sixty five degrees Fahrenheit (+/- five degrees) dry bulb
temperature. The Galleries, Reading Room, Archival Processing and Collections
Processing rooms all require a climate of forty-five percent relative humidity (+/- five
percent) at seventy to seventy-five degrees Fahrenheit dry bulb temperature.
AHU-1 is located in the basement mechanical room, with its outdoor air being
supplied by a fan and corresponding ductwork from the roof. AHU-1 serves the basement
as well as spaces on the first floor such as the reading room, archive storage and the
archivists office and workroom. AHU-2 serves the two galleries on the second floor.
AHU-3 serves the orientation room, museum shop and restrooms on the first floor. AHU-1
and AHU-3 both supply air to VAV boxes (HW heating) located in each of their
corresponding zones.
VAV boxes are located throughout the building each one serving a zone within the
building. The VAV boxes are used as primary heating elements for the air supplied to
7
Jarod F. Stanton
Mechanical Option
8
Jarod F. Stanton
Mechanical Option
Depth Study:
Doas Design
DOAS stands for dedicated outdoor air systems. This type of system addresses the
issue of supplying the correct ventilation air requirements to each space in a
building/zone. DOAS contains two parallel working systems. One system handles the
distribution of ventilation air to the spaces as well as the total latent loads in the spaces,
which also satisfies some of the sensible loads in the spaces. The parallel system only
needs to satisfy the remaining sensible loads in the spaces. The separate conditioning of
the sensible and latent loads is called decoupling. The parallel system may be a parallel
all air VAV system, packaged unitary water source heat pumps, fan coil units, packaged
unitary equipment or radiant ceiling panels.
Table 2 of ASHRAE Std. 62-2001 contains outdoor air ventilation requirements for
a variety of rooms in different facilities. Table 2 contains an estimated maximum
occupancy for spaces, outdoor air ventilation requirements (based on occupancy or area)
and exhaust rates for bathrooms and other special processes. The ventilation rates are
based on human comfort. Humans generate carbon dioxide, which unless ventilated, can
cause discomfort to humans due to odors. The standard is based on keeping carbon
dioxide levels less than 700 ppm above outdoor air conditions.
ASHRAE Std. 90.1-2001 also affects DOAS. ASHRAE Std. 90.1-2001 requires that
Individual fan systems that have both a design supply air capacity of 5,000 cfm or greater
and have a minimum outside air supply of 70% or greater of the design supply air quantity
shall have an energy recovery system with at least 50% recovery effectiveness. This
means that any DOAS above 5,000 cfm will be required to have an energy recovery device
(enthalpy wheel). The standard also addresses the requirement that reheat is not allowed
because of the humidity control incorporated with the unit to satisfy the latent load.
Because of this requirement, a sensible wheel can be used for free heating.
The reason for choosing a DOAS for the Lehigh Valley Heritage Center was because
of the VAV boxes located throughout the building. VAV boxes are poor humidity
controllers and outdoor air distributors. Recirculated air mixes with outdoor air to be
supplied to the spaces. This means a certain fraction of that supply air is outdoor air.
When the boxes throttle down to the minimum setting, a small amount of air is
distributed to the room. This small amount of air has the same percentage of outdoor air
mixed in with it when it was traveling down the main duct, but because its volume was
reduced entering the space so was the amount of outdoor air mixed with it. This makes it
very hard for engineers to ensure the proper amount of outdoor air for a space. ASHRAE
Std. 62-2001 contains the multiple spaces equation, which calculates the amount of air
needed to be supplied to the critical space to ensure proper ventilation requirements. The
volume of air is usually increased which means that all other spaces are receiving more air
than needed, adding to the coiling coil load on the main air handling unit. The same
principle relates to the humidity control in the spaces. As the boxes throttle down,
9
Jarod F. Stanton
Mechanical Option
Component
Air System Fans
Cooling
2,477
Heating
4,638
Pumps
1,404
HVAC Sub-Total
Lights
13,236
12,429
Electric Equipment
695
Misc. Electric
7,042
Non-HVAC Sub-Total
20,166
Grand Total
33,401
In order to simulate a DOAS in HAP, all air handling units were turned into
ventilation units. The terminal (parallel) units were chosen to be four pipe fan coil units
since both hot and chilled water were existent in the building. A common ventilation
system was chosen on the general tab of the air distribution systems.
Under the ventilation system components tab, a constant airflow for the ventilation
air was chosen because the ventilation system only needs to supply the outdoor air
requirement for the spaces. The ventilation sizing method was chosen to be the sum of the
space outdoor air flows, which will provide the cfm necessary for the ventilation unit.
Ventilation reclaim simulates the enthalpy wheel on the ventilation unit. The enthalpy
wheel does both sensible and latent heat transfer. Its efficiency was guessed at 80% as
well was the power input at 0.8 kW. The coiling coil was arbitrarily chosen at 45 degrees
F, which will be modulated to determine the most feasible operating point. The coil
bypass factor was left set at 0.1. Chilled water will be providing the cooling through the
coils. The heating coil was checked, even though ASHRAE Std. 90.1 does not allow it; it
10
Jarod F. Stanton
Mechanical Option
11
Jarod F. Stanton
Mechanical Option
LVHC DOAS 45
55
($)
3,944
LVHC DOAS 55
55
($)
3,993
LVHC DOAS 60
60
($)
4,003
LVHC DOAS 65
65
($)
4,012
LVHC DOAS 70
70
($)
3,988
Cooling
8,562
6,062
5,567
5,189
4,956
Heating
4,567
3,915
3,053
2,276
1,661
401
407
402
394
329
Component
Air System Fans
Pumps
Cooling Tower Fans
HVAC Sub-Total
Lights
Electric Equipment
Misc. Electric
Misc. Fuel Use
17,474
14,377
13,025
11,871
10,934
13,800
13,982
13,983
13,974
13,855
715
724
725
724
718
Non-HVAC Sub-Total
14,515
14,707
14,708
14,698
14,573
Grand Total
31,989
29,084
27,733
26,569
25,506
YHYB models were chosen for the high use spaces, the lobby being one of them. All fan
coil units fit in the plenum spaces below the steel joists. A Semco Energy Recovery Unit
was chosen for the ventilation system. An EPD-18 model was chosen to satisfy the 41.5
ton load on the cooling coil.
Although the design intentions were to make the fan coil units a sensible only
system, the fan coil units will condense and must be equipped with drain pans and
condensate piping.
The entire mechanical system was able to be reduced. A new boiler rated at 750
MBH was selected from Bryan Boilers, the chiller was downsized to a 41.5 ton unit and,
accordingly, the air cooled condenser unit on the roof was downsized. A smaller steam
generator was selected, 140 MBH max input, while the roof top units, air handling units,
VAV boxes, an O/A intake fan, duct heaters and a louver were all able to be removed. The
approximate savings of the new system over the old system came out around $72,500.
This only accounts for the equipment in Appendix A. Ductwork and piping costs were not
included, which would lower the savings.
The new operating cost of the building comes out to be $1.17/ft2, which corresponds
to a savings of $0.22/ft which is $5,280. As well as saving money, mechanical room 006
contains no more equipment, since the new chiller and boiler moved to mechanical room
003. Mechanical room six is 890ft2, which can be utilized as storage for the museum.
12
Jarod F. Stanton
Mechanical Option
Breadth Study:
Structural
Analysis of the new mechanical equipment on the roof
A structural evaluation of the steel framing system supporting the equipment well
will be assessed since the mechanical equipment has changed throughout the building.
The original equipment well contained the two roof top units and the two condensing
units. Since the redesign of the mechanical equipment, all three air handling units and
both roof top units were removed and replaced with the EPD-18 Semco Unit. The EPD-18
was placed in the equipment well where the two roof top units had been. The two 30 ton
condensing units were also downsized into one 42.5 ton unit. This McQuay condensing
unit was also proposed to be placed in the same area as the existing condensing units.
Because new equipment is being installed in a confined space, serviceability and
spacing requirements must be taken into account before evaluating the support system. If
this was not checked, valuable time and money could be wasted after a redesign of the
steel was undertaken if afterwards it was found out that there was not enough clearance
around the equipment for proper operation or maintenance. The manufacturer of the
equipment has spacing and clearance requirements for operability.
The condensing unit requires a minimum of 4 clearance from each side for
serviceability. The condensing unit will be placed in the center of the area utilized by the
existing units. This area is approximately 24 wide by 20 long; the 24 dimension is the
width of the equipment well. The unit is 7-4 wide by 7-10 long which clearly meets the
minimum 4 clearance distance, when it is placed in the center of the area. Because the
unit is inside the equipment well, it must meet another spacing requirement by the
manufacturer. The space within the equipment well simulates a pit. Stagnant air can be
found in deep pits and circulation problems exist. The unit must not be placed in a pit
where the walls are equal to or taller than the unit itself, unless extra space is given along
the coil side. The unit is 8-4 tall, while the equipment well walls are 9 tall. The
minimum requirement for distance from the pit walls is 6 ft. Again, these two
requirements are met, as long as the unit is placed centrally in the area designated.
The Semco Energy Recovery Unit will also be placed centrally within its designated
space. The space is approximately 24 wide by 41 long. The unit itself is 10-2 wide, 258 long and 8-2 in height. The engineering data contains no spacing requirements
around the unit, but a general rule of thumb is to have spacing around the unit equal to
its width. This is a reasonable assumption, considering the recovery wheels inside span
most of the width and would more than likely be pulled out from the side. Placing the unit
in the center of the space would leave approximately 7 wide space running along the
length of the unit and 8 along its width. Although these limitations of space seem against
standards, the unit will stay in that designated area for the evaluation of the steel
members. One solution to the problem of spacing is to move the unit closer to one wall so
that the serviceability requirement can be met on the opposite side.
13
Jarod F. Stanton
Mechanical Option
Now that the units are set in their designated spaces, an evaluation of the steel
framing system will be undertaken. The comparison of loading on the frame from the
mechanical equipment is given below in Table 1. Although the new equipment is double
the load of the existing equipment, an analysis will be done to size beam and girder
members to withstand the mechanical load, whether it be an increase or reduction in steel.
Existing Equipment Operating Weight
Roof Top Unit One
5,025 lbs
Roof Top Unit Two
2,345 lbs
Air cooled condenser
1,585 lbs
Air Cooled Condenser 1,585 lbs
Total Weight = 9,113 lbs
New Equipment
Semco Unit EPD-18
McQuay air cooled
condenser
Operating Weight
17,500 lbs
3,650 lbs
The manual of steel construction using LRFD was used in the sizing of the beams and
girders. Refer to Appendix B for all calculations and drawings of the structural system for
the mechanical well. A distributed area method was undertaken to simplify the design
analysis. All loadings on the building were determined before the calculations took place.
The roof live load is controlled by snow loading, which is 31 psf. A superimposed dead load
was used in this process and was given a value of 25 psf, which includes roofing material,
steel members and ductwork/sprinklers. A safety factor of 1.15 was used in the
calculation of the dead loads. The equipment well walls were estimated at 30 psf for a
screen wall, which is conservative. The walls are composed of hollow structural steel,
CMU block and zinc. All beams considered for the analysis were checked for deflection
against the factor l/360.
There were only three beams which were not analyzed, and they were part of the
wall leading up to the higher roof elevation. They could have been resized, but the
construction methodology used with the beams is unknown. Two beams are placed side by
side along the wall, so there is an uncertainty of the walls load distribution on the side by
side beams.
The beam sizes were able to be reduced, mostly to size W12 X 14. The girders were
able to be downsized as well, reducing their weight by a factor of two. Using the new
beam and girder sizes, a cost savings calculation was performed. A recent article found on
the internet estimated the cost of steel to be $490.00 per ton. After the analysis it was
found that the savings based on the cost of steel were approximately $1,290.00. This is
not a significant cost savings, but the analysis only focused on a combination of fourteen
beams and girders. Please note that only a gravitational analysis was conducted and that
seismic and lateral loads were ignored.
14
Jarod F. Stanton
Mechanical Option
pounds and has lateral movement control. The springs can be adjusted to different
loadings for a fail safe design. The housing contains a neoprene snubber which will help
absorb the vibrations before they are passed through the housing and into the beams.
Another solution to the problem of vibration is concrete or equipment pads on which
the equipment is mounted. The large mass of the concrete pads absorb the vibration due
to the mass law. The problem with concrete pads is that they have a very high weight,
which can affect structural members of the building, depending on where it is located.
Equipment pads are made from polyolefin. These pads are extremely lighter than a
concrete pad and can be moved with ease from space to space. The equipment pads are
weather resistant and can allow pipes to run through it by means of drilling.
15
Jarod F. Stanton
Mechanical Option
16
Jarod F. Stanton
Mechanical Option
Construction Management
forms must be supported by shoring or scaffolding to keep the walls straight during the
placing of the concrete. Also, the formwork must be placed straight to ensure structural
integrity when constructing a wall from the base. Manufactures have made corner pieces
to help speed the process of installation. There is a significant difference in skill level
when it comes to traditional concrete forms and EPS. EPS is designed so that less skill is
involved in using the forms compared to the traditional concrete forms.
Because of the configuration of concrete, steel and formwork, a traditional vibrator
would not effectively compact the concrete. With a simple disk vibrator, one can compact
the concrete by placing the disk up against the formwork. Another option includes placing
the vibrator on the steal itself and let the vibrations travel down the rebar and into the
concrete. It is recommended that the maximum rise of concrete that should be poured in a
section is 4 ft/hr. Blowouts dont usually occur, but if they do, one can cut out the blowout
are and replace it.
Various finishes can be attached to the EPS forms by either means of furring strips
or gluing. Exterior finishes include paint, stucco, siding and brick while sheet rock is the
main interior finish. Towel racks and other small items can be attached directly to the
wall by means of anchors.
The purpose of studying this type of wall system was to see a dual outcome from a
single analysis. An energy impact and time savings in structural work were the two
searched outputs. Information on the internet made the forms out to be a super structure
that could better insulate the building, save time on construction, provide acoustical
privacy and reduce the amount of concrete used in a typical wall section. Although the
first three objectives could be reached, the last was not entirely true. Less concrete
certainly does not make the building any more structurally stable. Although the amount
of concrete for a certain section of the waffle grid form will be less than the same section of
a flat wall form, it does not mean they have the same structural properties.
18
Jarod F. Stanton
Mechanical Option
Suspended particle devices are light absorbing microscopic particles. When placed
in a liquid suspension film, then placed between two pieces of transparent conductive
objects, the particles randomly align themselves and block light from entering the window.
When a voltage is applied across the two conductive materials, the particles align
themselves parallel with the electric field and the light is able to pass through the window.
The amount of power needed to convert these windows is so small, that a residential house
with these types of windows would use as much power as a small lamp/light for the day.
Once the power is removed the particles realign themselves back to their original state.
Electrified variable tint SPD windows have a fairly quick response rate as well as a large
switchable durability. These windows can control solar light transmittance between 0.1%
and 70%. The average power consumption is less than 5W/ft2.
20
Jarod F. Stanton
Mechanical Option
Reflective hydrides are films made of nickel-magnesium alloy, which reflect light.
They are powered either by low voltage or by the injection of hydrogen and oxygen gasses
(gas-chromatic technology) which transform the window to a clear state. The difference in
these windows is that they reflect light rather than absorb it. Reflecting light is good, but
not at neighboring buildings which pick up the thermal load. Obviously, these windows
would be used in a non-urban environment.
The type of window proposed to be installed in the Heritage Center is
electrochromic glass manufactured by SAGE Electrochromics, Inc. A ceramic ion
conductor is sandwiched between a counter electrode and an electrochromic electrode.
These layers are then sandwiched between two transparent conductors which are located
on the inside of the glass layers. Multiple layers of ceramic thin films are applied to the
glass where it is fired on to ensure a strong, durable window. These windows consume low
DC voltage to transfer ions from one layer to another, which in turn, tints the window.
Electronic dimmable ballasts can be used to transform AC to DC for the windows. Unlike
SPDs SageGlass cannot become totally opaque, so visibility through the window is never
obstructed. Visible light ranges from 4% to 70% through the window at its darkest and
lightest stages, respectively. In its clearest stage SageGlass blocks 95% of the UV
radiation (99% in its darkest stage), which is helpful in preventing the interior
components (furniture, paintings, tapestries, etc.) of the building from fading. The
windows can be controlled as a functional parameter; a function of direct/total solar
radiation, tonnage, previous space loads or indoor lighting levels. The windows have a
memory associated with them. Unlike the SPDs, these windows will maintain tinted
once the power source is taken away. Various cases ranged from 12-48 hours until the
window went back to its original state.
Electrochromic windows have drawbacks as well. During the cold winter months,
the windows require a longer time to switch than in the warmer, summer months.
Thermal shock is the factor that affects the timing delay. The window is not at the same
temperature everywhere, and if switching occurs too fast, the window could crack or
21
Jarod F. Stanton
Mechanical Option
SageGlass properties
U-factor (Center of Glass)
Air Gap
Coating Properties
0.33
Argon
Low-e
24
Jarod F. Stanton
Mechanical Option
Based on the calculations performed through the HAP program, a dedicated outdoor
air system would prove beneficial, both cost wise and quality wise in the Lehigh Valley
Heritage Center. The overall calculated savings was around $77,780 for the first year.
This does not accurately show the true cost savings since ductwork, piping and pumping
costs were not included. Also, the data obtained from RS Means does not give exact
pricing cost for every piece of equipment. The dedicated outdoor air system will provide
the LVHC with a stricter controlled environment and will ensure the proper amount of
ventilation air to the spaces.
The structural analysis of the building showed a cost savings of $1,290.00. Please
note again that the calculations performed did not include seismic or lateral loading. The
roof framing system will hold the newly proposed equipment on it, as the maximum
moment did not exceed that of the beams or girders nor did the deflection due to the live
load exceed l/360. The only concern was not using the dunnage that the design engineer
designed for the equipment, and placing the equipment on the roof. Without proper
acoustical measures and vibration isolation dampers the structural steel skeleton of the
building can propagate sound into and throughout the building.
As far as new technology goes, the electrochromic windows would not be feasible
cost wise or energy wise. The southern faade of the building does not contain a vast
amount of fenestration, and areas that would integrate the windows with the indoor
lighting are only small offices. The majority of the lighting is contained in the galleries,
orientation, corridors and stairwells. These are the areas that need to have special
controls to conserve energy or incorporate natural lighting in the spaces.
EPS forms have a couple drawbacks in the application of the LVHC. The
engineering task involved in designing the concrete beams spanning from pilaster to
pilaster is one drawback (for a mechanical engineer) and the fact that extra material must
be used on the exposed forms on the south and western sides of the building to cover the
forms from any type of vandalism.
25
Jarod F. Stanton
Mechanical Option
References
2003 RS Means Mechanical Cost Data (2002) RS Means Co. Inc.
American Society of Heating, Refrigeration and Air Conditioning Engineers, Inc. 2001
ASHRAE Handbook, Fundamentals. Atlanta, GA: ASHRAE, 2001.
West, Harry H. Fundamentals of Structural Analysis. New York, Wiley and Sons, 1993.
AISC (2001) Manual of Steel Construction: Load and Resistance Factor Design. American
Institute of Steel Construction Inc.
McQuiston, Faye C., Jerald D. Parker, Jeffrey D. Spitler. Heating, Ventilation, and Air
Conditioning: Analysis and Design. New York, Wiley and Sons, 2000.
Mumma, S.A. 2001 Overview of Integrating Dedicated Outdoor Air Systems With Parallel
Terminal Systems ASHRAE Transactions 107(1)
Mumma, S.A. 2001 Dedicated Outdoor Air-Dual Wheel System Control Requirements.
ASHRAE Transactions 107(1)
Bosnor, Kevin. How Smart Windows Work. 14 Jan. 2004
<http://home.howstuffworks.com/smart-window.htm
Lee, E.S, D.L. DiBartolomeo, S.E. Selkowitz. 2000. Electrochromic windows for
commercial buildings:Monitored results from a full-scale testbed, Proc. ACEEE
2000 Summer Study on Energy Efficiency in Buildings, Asilomar, CA.
Mumma, S.A. 2001. 14 March 2004. < http://www.doas-radiant.psu.edu/doas.html>
< http://www.sage-ec.com/> for electrochromatic window information
< http://www.reddiform.com> for information of EPS
< http://www.polysteel.com> for information of EPS
< http://www.nfstyro.com/Building_Materials/iceblock.html> for information of EPS
26
Jarod F. Stanton
Mechanical Option
Credits / Acknowledgements:
Acknowledgements
I would like to thank God, for always helping me through any situation
My family, for always pushing me forward
My fellow classmates, for their support and respect
Dustin Wakefield for helping me on my structural
All the Mechanicals
27
Jarod F. Stanton
Mechanical Option
Appendices:
Appendix A
Mechanical:
Boiler Selection
Boiler Selection From Bryan Boilers
Reduction in boiler size, since the Semco Energy Unit (EPD-18) utilizes free heating with
the energy recovery system.
Calculations:
From the HAP output and equipment selection, the heating required for the Fan Coil
Units is 179.9 MBH and the existing panel and fin tube radiators in the lobby and stair
001 is 78.57 MBH.
I will have a preheat coil in the Semco unit on the roof before the enthalpy wheel to
condition outside air if it poses a freezing problem for the enthalpy wheel. For the worse
case scenario, the coil would heat the outside air from 0 to 32 degrees F.
Qpreheat coil = 1.08*scfm*(Tafter preheat Tbefore preheat)
Qpreheat coil = 1.08*(9278 scfm)*(32-0) = 320647.68 Btu = 320.65 MBH
Qboiler = Qfan coil + Qradiator + Qpreheat
Qboiler = 179.9 + 78.57 + 320.65 MBH = 579.12 MBH (No safety factor added since
the preheat coil load is worse case)
From Bryan Boilers, a CL-75 Boiler would be the best choice (from this manufacturer) that
provides hot water, has forced draft (the vents for the boilers must be able to extend to the
roof) and satisfies the heating demand.
Jarod F. Stanton
Mechanical Option
Chiller Selection
Chiller Selection from engineering guide for McQuay Air Conditioning: Air Cooled Scroll
Compressor Chiller
Chose Remote Evaporator Model AM/BM
Locate evaporator on roof where existing evaporators are
From HAP v4.2 output:
41.5 tons required capacity
90F ambient temperature
Cool 99.7 gpm from 54F to 44F
Evaporator fouling factor = 0.0001
384 foot altitude
1. Add 3% to the required capacity for approximate derate: 41.5 x 1.03 = 42.75 tons.
From Table 14 of the engineering guide, an AGZ-045B at the given conditions will
produce 42.5 tons with a unit kW input of 51.7 and a unit EER of 9.9
.
2. Determine derate factors:
Altitude correction from Table 6 of the engineering guide: 0.998 Capacity, 1.009
Power
3. Piping correction:
Assume 1 5/8 suction line based on connection size in Table 10 of the engineering
guide.
(4) 90 Standard ells 4 x 4 ft =16 ft
Plus actual linear feet 65 ft
Total Equivalent Feet 81 ft
Check Table 9 and find that 1 5/8 is maximum size for oil carry.
This means that the 1 5/8 riser will be satisfactory.
The capacity correction factor from Table 12 is 0.980.
4. The corrected capacity of the AGZ is: 42.5 tons x 0.998{altitude} x 0.98{piping} 41.5 tons.
This satisfies the 41.5 ton requirement.
5. Correct the unit power required: 51.7 kW x 1.009{altitude} = 52.2 kW.
6. Calculate the unit EER based on the correct capacity and power:
EER = (41.5 tons x 12,000)/ (52.2 kW x 1,000) = 9.5
7. Determine the evaporator pressure drop. Enter the pressure drop curves (Figure 8) at
99.7 gpm and read up to AGZ 045, read over to pressure drop of 2.6 ft.
Jarod F. Stanton
Mechanical Option
Jarod F. Stanton
Mechanical Option
Electric Rate
PP&L Electric Utilities Corporation supplies the electricity to the building. The
Lehigh Valley Heritage Center is classified as a GS-3 service building, which means a
large general service at secondary voltage or higher.
Base of 25 kW billed
Minimum Billing Demand = 25 kW
Minimum Distribution Charge = $71.00
Minimum Monthly Capacity and Energy Charge is 25 kW multiplied by the
Demand Step of the Effective Capacity and Energy Charge
Distribution Charge
$2.84 per kW for all kW of the billing kW
0.151 cents per kWH for the first 200 kWH per kW of the billing kW
0.199 cents per kWH for the next 200 kWH per kW of the billing kW
0.144 cents per kWH for all additional kWH
Competitive Transmission Charge
0.249 cents per kWH for the first 200 kWH per kW of the billing kW
0.195 cents per kWH for the next 200 kWH per kW of the billing kW
0.188 cents per kWH for all additional kWH
Intangible Transition Charge
1.220 cents per kWH for the first 200 kWH per kW of the billing kW
0.958 cents per kWH for the next 200 kWH per kW of the billing kW
0.918 cents per kWH for all additional kWH
Capacity and Energy Charge
$4.10 per kW for all kW of the billing kW
4.266 cents per kWH for the first 200 kWH per kW of the billing kW
4.240 cents per kWH for the next 200 kWH per kW of the billing kW
3.095 cents per kWH for all additional kWH
These rates were used in the energy analysis program.
Jarod F. Stanton
Mechanical Option
Gas Rate
UGI Gas Service provides natural gas to the building. Customers purchase gas on a
quarterly basis. The most current gas price obtained was for March 1, 2004, which was
$0.83 per CCF. The price per therm is then:
$0.83/CCF*(10 CCF / 1 MCF)*(1 MCF / 1.027x106 Btu)*(100,000 Btu / 1 therm) =
$0.8082 per therm
From an existing bill, obtained from Mr. Zolomij of the Lehigh Valley Historical
Society, other costs include:
Customer Charge = $8.55
Distribution Charges = $16.63
PA State Tax = 6%
So, a minimum charge of $25.12 was used with $0.8082 per therm plus 6% state
sales tax in the energy analysis.
Jarod F. Stanton
Mechanical Option
Corrected Flow
Fan size
BHP
max HP motor
rpm
wheel effectiveness
Corrected Flow
Fan Size
BHP
max HP motor
rpm
wheel effectiveness
Sensible wheel
Casing
Total
12,566
13
9.133
20
1900
0.82
0.44
0.3
1.594
11,558
13
7.2
20
1830
0.84
amps
SA 20 HP
RA 20 HP
VFD Sens. Wheel
Control Panel
Total FLA
54
54
4.4
0.8
113.2
113.2
13.5
126.7
Total FLA
75% of Largest Mtr.
Ckt. Bkr. Selection amp
amps
113.2
40.5
153.7
CFM
Watts
Hot Water
Delta P (ft) Heating (1000BTUH)
gpm
Zone Name /
Space Name
Zone 1
13YHBC-41
1400
8.6
23.9
41.5
29.5
530
2.9
45.2
44.1
(3x)20YHYB-3
2070
11.3
56.3
43.2
820
16
7.6
135
13YHBC-41
1400
8.6
23.9
41.5
29.5
530
2.9
45.2
44.1
13YHBC-31
1400
7.3
15.3
35.5
26.5
530
3.3
56.9
49.4
4YHBC-31
510
3.2
16.5
13.4
9.5
120
1.4
7.9
21.2
3YHBC-31
310
9.8
6.7
120
0.9
2.6
13.8
4YHBC-31
510
3.2
16.5
13.4
9.5
120
1.4
7.9
21.2
8YHBC-31
870
4.7
7.5
22.5
17
340
2.2
22.2
33.3
5YHBC-41
600
8.3
18
11.8
130
1.4
21.8
6YHBC-4
730
4.8
11.7
23
15.6
240
1.6
10.1
24.4
8YHBC-41
870
5.5
12.6
26.9
18.9
340
1.9
16.4
29.2
8YHBC-31
870
4.7
7.5
22.5
17
340
2.2
22.2
33.3
16YHBC-31
1780
9.6
4.2
48.2
36.8
710
13
7.3
133
13YHBC-31
1400
7.3
15.3
35.5
26.5
530
3.3
56.9
49.4
5YHBC-41
600
8.3
18
11.8
130
1.4
21.8
4YHBC-31
510
3.2
16.5
13.4
9.5
120
1.4
7.9
21.2
4YHBC-31
510
3.2
16.5
13.4
9.5
120
1.4
7.9
21.2
5YHBC-41
600
8.3
18
11.8
130
1.4
21.8
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room
116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing
Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office
(x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office
(x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection
Storage 001
B-Storage 002
Boilers
Division #
15510 Heat Generation
Equipment: Boilers and
Accessories
15620 Refrigeration
Equipment: Packaged
Water Chillers
Chiller
15670 Refrigeration
Equipment: Condensing
Condensers Units
Air Handling 15720 HVAC Equipment:
Units
Air Handling Units
Roof Top
Units
Louver
VAV boxes
OA fans
Line #
Description
5170 30 ton
5150 20 ton
100 Fans
Total $
11500
4475
31950
45700
8575
54275
29500
2800
64600
7150
935
8085
6250
600
6850
1625
540
2165
38600
23900
1950
1375
1
1
40550
25275
5575
271
11692
540
650
198
199
1
1
738
849
28
330
14.8
21
1
1
42.8
351
775
53.5
828.5
805
59
1728
860
76
3744
930
1025
107
133
5
7
5185
8106
545
273
818
267832.3
Total :
Division #
15510 Heat Generation
Equipment: Boilers and
Accessories
Boiler
15620 Refrigeration
Equipment: Packaged
Water Chillers
Chiller
15670 Refrigeration
Equipment: Condensing
Condensers Units
Semco Unit
Steam
Generators
Fan Coil
Units
NA
15750 HVAC Equipment:
Humidity control
Equipment
15765 HVAC Equipment:
FCU
Line #
Description
Total $
5125
2500
7625
32000
5175
37175
11250
973
12223
88200
88200
2850
135
2985
1470
1750
2100
2415
2660
3080
99.55
108.35
113.3
148.5
157.3
174.9
1 1569.55
7 13008.45
3
6639.9
3
7690.5
3
8451.9
3
9764.7
Total :
195333
Total Savings :
72499.3
04/05/2004
04:53AM
Component
Air System Fans
Cooling
2,477
Heating
4,638
Pumps
1,404
0
13,236
12,429
Electric Equipment
Misc. Electric
695
7,042
Non-HVAC Sub-Total
20,166
Grand Total
33,401
0.103
Heating
0.193
Pumps
0.058
0.000
HVAC Sub-Total
0.550
Lights
0.517
Electric Equipment
0.029
Misc. Electric
0.293
0.000
Non-HVAC Sub-Total
Grand Total
Gross Floor Area (ft)
0.838
1.389
24055.0
7.4
Heating
13.9
Pumps
4.2
0.0
HVAC Sub-Total
Lights
39.6
37.2
Electric Equipment
Misc. Electric
2.1
21.1
0.0
Non-HVAC Sub-Total
60.4
Grand Total
100.0
Page 1 of 1
04/05/2004
04:53AM
Component
HVAC Components
Electric
8,598
Natural Gas
4,638
Fuel Oil
Propane
Remote HW
Remote Steam
Remote CW
HVAC Sub-Total
13,236
Non-HVAC Components
Electric
20,166
Natural Gas
Fuel Oil
Propane
Remote HW
Remote Steam
Non-HVAC Sub-Total
20,166
Grand Total
33,401
Heritage Center
HVAC Components
Electric (kWh)
117,519
5,287
Propane (na)
Remote HW (na)
Remote CW (na)
Non-HVAC Components
Electric (kWh)
275,932
Propane (na)
Remote HW (na)
Totals
Electric (kWh)
Natural Gas (Therm)
Fuel Oil (na)
393,450
5,287
0
Propane (na)
Remote HW (na)
Remote CW (na)
Page 1 of 3
04/05/2004
04:53AM
Heritage Center
0
SO2 (kg)
NOx (kg)
0.357
Natural Gas
0.193
Fuel Oil
0.000
Propane
0.000
Remote HW
0.000
Remote Steam
0.000
Remote CW
0.000
HVAC Sub-Total
0.550
Non-HVAC Components
Electric
0.838
Natural Gas
0.000
Fuel Oil
0.000
Propane
0.000
Remote HW
0.000
Remote Steam
0.000
Non-HVAC Sub-Total
0.838
Grand Total
1.389
24055.0
Page 2 of 3
04/05/2004
04:53AM
25.7
Natural Gas
13.9
Fuel Oil
0.0
Propane
0.0
Remote HW
0.0
Remote Steam
0.0
Remote CW
0.0
HVAC Sub-Total
Non-HVAC Components
Electric
39.6
60.4
Natural Gas
0.0
Fuel Oil
0.0
Propane
0.0
Remote HW
0.0
Remote Steam
0.0
Non-HVAC Sub-Total
60.4
Grand Total
100.0
Page 3 of 3
04/05/2004
04:53AM
Cooling 7.4%
Heating 13.9%
Pumps 4.2%
37.2% Lights
1. Annual Costs
Annual Cost
($)
4,717
($/ft)
0.196
Cooling
2,477
0.103
7.4
Heating
4,638
0.193
13.9
Pumps
1,404
0.058
4.2
0.000
0.0
Component
Air System Fans
Percent of Total
(%)
14.1
13,236
0.550
39.6
12,429
0.517
37.2
695
0.029
2.1
7,042
0.293
21.1
0.000
0.0
20,166
0.838
60.4
Grand Total
33,401
1.389
Note: Cost per unit floor area is based on the gross building floor area.
100.0
Misc. Electric
Misc. Fuel Use
Non-HVAC Sub-Total
Page 1 of 1
04/05/2004
04:53AM
Load
(kBTU)
777,300
(kBTU/ft)
32.313
491,002
20.412
1,268,301
52.725
Site Energy
(kBTU/ft)
9.154
Source Energy
(kBTU)
786,399
Source Energy
(kBTU/ft)
32.692
Grand Total
Cooling
114,933
4.778
410,477
17.064
Heating
528,719
21.980
528,754
21.981
Pumps
65,831
2.737
235,111
9.774
Cooling Towers
0.000
0.000
929,675
38.648
1,960,741
81.511
580,238
24.121
2,072,277
86.148
32,456
1.349
115,913
4.819
328,782
13.668
1,174,222
48.814
0.000
0.000
Non-HVAC Sub-Total
941,475
39.138
3,362,412
139.780
Grand Total
1,871,151
77.786
5,323,152
221.291
HVAC Sub-Total
Lights
Electric Equipment
Misc. Electric
Misc. Fuel Use
Notes:
1. 'Cooling Coil Loads' is the sum of all air system cooling coil loads.
2. 'Heating Coil Loads' is the sum of all air system heating coil loads.
3. Site Energy is the actual energy consumed.
4. Source Energy is the site energy divided by the electric generating efficiency (28.0%).
5. Source Energy for fuels equals the site energy value.
6. Energy per unit floor area is based on the gross building floor area.
Gross Floor Area ............................................ 24055.0 ft
Conditioned Floor Area .................................. 24055.0 ft
Page 1 of 1
04/05/2004
04:53AM
Load
(kBTU)
777,300
(kBTU/ft)
32.313
491,002
20.412
1,268,301
52.725
Site Energy
(kBTU/ft)
Source Energy
(kBTU)
Source Energy
(kBTU/ft)
Grand Total
HVAC Components
Electric
400,973
16.669
1,432,047
59.532
Natural Gas
528,706
21.979
528,706
21.979
0.000
0.000
Fuel Oil
Propane
0.000
0.000
0.000
0.000
Remote Steam
0.000
0.000
0.000
0.000
929,679
38.648
1,960,752
81.511
HVAC Sub-Total
Non-HVAC Components
Electric
941,478
39.139
3,362,423
139.781
Natural Gas
0.000
0.000
Fuel Oil
0.000
0.000
Propane
0.000
0.000
0.000
0.000
Remote Steam
0.000
0.000
Non-HVAC Sub-Total
941,478
39.139
3,362,423
139.781
Grand Total
1,871,157
77.787
5,323,175
221.292
Notes:
1. 'Cooling Coil Loads' is the sum of all air system cooling coil loads.
2. 'Heating Coil Loads' is the sum of all air system heating coil loads.
3. Site Energy is the actual energy consumed.
4. Source Energy is the site energy divided by the electric generating efficiency (28.0%).
5. Source Energy for fuels equals the site energy value.
6. Energy per unit floor area is based on the gross building floor area.
Gross Floor Area ............................................ 24055.0 ft
Conditioned Floor Area .................................. 24055.0 ft
Page 1 of 1
04/05/2004
04:47AM
Tons
MBH
MBH
CFM
CFM
CFM
gpm
F
F
F
F
%
F
OK
F
Page 1 of 1
04/05/2004
04:47AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Maximum
Cooling
Sensible
(MBH)
7.8
17.3
33.0
31.6
8.9
Design
Air
Flow
(CFM)
540
1095
1550
1481
417
Minimum
Air
Flow
(CFM)
135
780
120
690
75
Time
of
Peak
Load
Aug 1700
Jan 1700
Aug 1700
Jul 1700
Jun 1700
Maximum
Heating
Load
(MBH)
16.0
3.8
3.0
18.2
4.3
Reheat
Coil
Load
(MBH)
18.2
16.2
4.9
29.2
5.5
Reheat
Coil
Water
gpm
@ 20.0 F
1.82
1.62
0.49
2.92
0.55
Zone
Htg
Coil
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
Zone
Htg
Water
gpm
@ 20.0 F
0.00
0.00
0.00
0.00
0.00
Mixing
Box Fan
Airflow
(CFM)
0
0
0
0
0
Zone
Floor
Area
(ft)
2700.0
2100.0
2220.0
1610.0
510.0
Zone
CFM/ft
0.20
0.52
0.70
0.92
0.82
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone Name /
Space Name
Zone 1
B-Storage 004
Zone 2
B-Storage 002
B-Collection Storage 001
Zone 3
1-Archive Storage
1-Negative Storage
Zone 4
1-Reading Room 116
Zone 5
1-Archivist
1-Processing Workroom
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
7.8
Aug 1700
540
16.0
2700.0
0.20
1
1
1.7
15.6
Jan 1700
Jan 1700
120
975
0.0
3.8
600.0
1500.0
0.20
0.65
1
1
31.9
1.1
Jul 1700
Aug 1700
1498
52
1.9
1.1
2075.0
145.0
0.72
0.36
31.6
Jul 1700
1481
18.2
1610.0
0.92
1
1
3.4
5.5
Jun 1700
Jun 1700
158
259
2.3
2.1
130.0
380.0
1.22
0.68
Page 1 of 1
04/05/2004
04:47AM
Tons
MBH
MBH
CFM
CFM
CFM
gpm
F
F
F
F
%
F
OK
F
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:47AM
Zone Name
Zone 1
Maximum
Cooling
Sensible
(MBH)
35.8
Design
Air
Flow
(CFM)
1976
Minimum
Air
Flow
(CFM)
1976
Time
of
Peak
Load
Jul 1600
Maximum
Heating
Load
(MBH)
13.5
Zone
Floor
Area
(ft)
3470.0
Zone
CFM/ft
0.57
Zone Name /
Space Name
Zone 1
2-Gallery
2-Main Gallery
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
10.7
25.1
Jul 1600
Jul 1600
590
1386
6.4
7.2
960.0
2510.0
0.61
0.55
Page 1 of 1
04/05/2004
04:47AM
Tons
MBH
MBH
CFM
CFM
CFM
gpm
F
F
F
F
%
F
OK
F
Page 1 of 1
04/05/2004
04:47AM
Zone Name
Zone 1
Zone 2
Maximum
Cooling
Sensible
(MBH)
28.9
14.7
Design
Air
Flow
(CFM)
1358
692
Minimum
Air
Flow
(CFM)
840
90
Time
of
Peak
Load
Sep 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.5
0.0
Reheat
Coil
Load
(MBH)
16.9
1.4
Reheat
Coil
Water
gpm
@ 20.0 F
1.69
0.14
Zone
Htg
Coil
Load
(MBH)
0.0
0.0
Zone
Htg
Water
gpm
@ 20.0 F
0.00
0.00
Mixing
Box Fan
Airflow
(CFM)
0
0
Zone
Floor
Area
(ft)
1665.0
975.0
Zone
CFM/ft
0.82
0.71
Zone Name
Zone 1
Zone 2
Zone Name /
Space Name
Zone 1
1-Orientation
Zone 2
1-Museum Shop
1-Corridor
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
28.9
Sep 1700
1358
3.5
1665.0
0.82
1
1
1
1
6.6
5.0
1.3
1.8
Jan 1700
Jan 1700
Jan 1700
Jan 1700
311
235
62
84
0.0
0.0
0.0
0.0
275.0
300.0
170.0
230.0
1.13
0.78
0.37
0.37
Page 1 of 1
04/05/2004
04:47AM
Zone Name
Zone 1
Maximum
Cooling
Sensible
(MBH)
6.4
Design
Air
Flow
(CFM)
870
Minimum
Air
Flow
(CFM)
870
Total
Coil
Load
(MBH)
9.3
Sens
Coil
Load
(MBH)
9.3
Coil
Entering
DB / WB
(F)
78.1 / 70.3
Time
of
Peak
Load
Sep 1200
Maximum
Heating
Load
(MBH)
6.2
Zone
Floor
Area
(ft)
585.0
Zone
CFM/ft
1.49
Zone Name
Zone 1
Coil
Leaving
DB / WB
(F)
68.1 / 67.3
Water
Flow
@ 10.0 F
(gpm)
1.86
Time
of
Peak
Load
Aug 1500
Zone Name
Zone 1
Fan
Motor
(BHP)
0.402
VENT
Fan
Motor
(kW)
0.300
Design
Airflow
(CFM)
128
Zone Name /
Space Name
Zone 1
1-Loading Dock
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
6.4
Sep 1200
870
6.2
585.0
1.49
Page 1 of 1
04/05/2004
04:47AM
Tons
MBH
MBH
CFM
CFM
CFM
F
F
F
F
%
F
OK
F
Page 1 of 1
04/05/2004
04:47AM
Zone Name
Zone 1
Zone 2
Zone 3
Maximum
Cooling
Sensible
(MBH)
12.9
18.4
133.5
Design
Air
Flow
(CFM)
607
866
6269
Minimum
Air
Flow
(CFM)
360
9
2265
Time
of
Peak
Load
Jun 1700
Jun 1700
Jun 1400
Maximum
Heating
Load
(MBH)
4.3
11.7
53.5
Reheat
Coil
Load
(MBH)
10.0
0.0
36.2
Reheat
Coil
Water
gpm
@ 20.0 F
1.00
0.00
3.62
Zone
Htg
Coil
Load
(MBH)
0.0
11.7
53.5
Zone
Htg
Water
gpm
@ 20.0 F
0.00
1.17
5.36
Mixing
Box Fan
Airflow
(CFM)
0
0
0
Zone
Floor
Area
(ft)
680.0
1075.0
1970.0
Zone
CFM/ft
0.89
0.81
3.18
Zone Name
Zone 1
Zone 2
Zone 3
Zone Name /
Space Name
Zone 1
2-School Program
Zone 2
2-Stair 1
2-East Corridor
Zone 3
1-Lobby
1-Stair 1
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
12.9
Jun 1700
607
4.3
680.0
0.89
1
1
13.3
5.2
Jun 1700
Jul 1700
625
242
10.1
1.6
210.0
865.0
2.98
0.28
1
1
131.9
1.8
Jun 1400
Jul 1700
6191
85
50.7
2.8
1760.0
210.0
3.52
0.41
Page 1 of 1
04/05/2004
04:47AM
Tons
MBH
MBH
CFM
CFM
CFM
F
F
F
F
%
F
OK
F
Page 1 of 1
04/05/2004
04:47AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Maximum
Cooling
Sensible
(MBH)
10.3
15.5
16.7
4.3
9.9
7.9
5.4
3.5
Design
Air
Flow
(CFM)
483
729
783
202
466
369
252
165
Minimum
Air
Flow
(CFM)
75
75
75
15
60
15
60
45
Time
of
Peak
Load
Sep 1300
Sep 1500
Aug 1600
Jun 1700
Jun 1700
Jul 1700
Jul 1700
Jul 1700
Maximum
Heating
Load
(MBH)
3.9
6.6
6.3
2.8
5.1
2.2
0.7
0.5
Reheat
Coil
Load
(MBH)
5.1
1.2
1.2
3.0
6.0
2.5
1.7
1.3
Reheat
Coil
Water
gpm
@ 20.0 F
0.51
0.12
0.12
0.30
0.60
0.25
0.17
0.13
Zone
Htg
Coil
Load
(MBH)
0.0
6.6
6.3
0.0
0.0
0.0
0.0
0.0
Zone
Htg
Water
gpm
@ 20.0 F
0.00
0.66
0.63
0.00
0.00
0.00
0.00
0.00
Mixing
Box Fan
Airflow
(CFM)
0
0
0
0
0
0
0
0
Zone
Floor
Area
(ft)
915.0
495.0
550.0
170.0
440.0
1235.0
385.0
305.0
Zone
CFM/ft
0.53
1.47
1.42
1.19
1.06
0.30
0.65
0.54
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone Name /
Space Name
Zone 1
2-Work Stations
2-Copy Room
2-Stair 2
Zone 2
2-Lunch
2-Western Office (x8)
Zone 3
2-Western Office (x8)
Zone 4
2-Directors Office
Zone 5
2-Northern Office (x4)
Zone 6
2-West Corridor
2-Office 205
Hourly Analysis Program v.4.2
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
1
6.1
2.2
2.4
Jul 1700
Jul 1700
Sep 1200
285
104
113
0.7
0.3
2.9
400.0
165.0
350.0
0.71
0.63
0.32
1
3
6.6
3.3
Sep 1200
Aug 1600
311
157
2.8
1.3
165.0
110.0
1.89
1.42
3.3
Aug 1600
157
1.3
110.0
1.42
4.3
Jun 1700
202
2.8
170.0
1.19
2.5
Jun 1700
117
1.3
110.0
1.06
1
1
4.4
2.4
Jul 1600
Jul 1700
208
112
1.6
0.3
900.0
180.0
0.23
0.62
Page 1 of 2
Zone Name /
Space Name
2-Network
2-Women
2-Men
Zone 7
2-Conference Room
Zone 8
2-Processing Room
04/05/2004
04:47AM
Mult.
1
1
1
Cooling
Sensible
(MBH)
0.4
0.4
0.4
Time
of
Load
Jul 1700
Jul 1600
Jul 1600
Air
Flow
(CFM)
17
17
17
Heating
Load
(MBH)
0.0
0.1
0.1
Floor
Area
(ft)
25.0
65.0
65.0
Space
CFM/ft
0.68
0.26
0.26
5.4
Jul 1700
252
0.7
385.0
0.65
3.5
Jul 1700
165
0.5
305.0
0.54
Page 2 of 2
04/05/2004
04:39AM
LVHC DOAS 55
55
($)
3,993
LVHC DOAS 60
60
($)
4,003
LVHC DOAS 65
65
($)
4,012
LVHC DOAS 70
70
($)
3,988
Cooling
8,562
6,062
5,567
5,189
4,956
Heating
4,567
3,915
3,053
2,276
1,661
401
407
402
394
329
Component
Air System Fans
Pumps
Cooling Tower Fans
HVAC Sub-Total
Lights
Electric Equipment
Misc. Electric
Misc. Fuel Use
17,474
14,377
13,025
11,871
10,934
13,800
13,982
13,983
13,974
13,855
715
724
725
724
718
Non-HVAC Sub-Total
14,515
14,707
14,708
14,698
14,573
Grand Total
31,989
29,084
27,733
26,569
25,506
LVHC DOAS 55
55
($/ft)
0.144
LVHC DOAS 60
60
($/ft)
0.144
LVHC DOAS 65
65
($/ft)
0.144
LVHC DOAS 70
70
($/ft)
0.144
Cooling
0.308
0.218
0.200
0.187
0.178
Heating
0.164
0.141
0.110
0.082
0.060
Pumps
0.014
0.015
0.015
0.014
0.012
0.000
0.000
0.000
0.000
0.000
HVAC Sub-Total
Lights
0.629
0.517
0.469
0.427
0.393
0.497
0.503
0.503
0.503
0.499
Electric Equipment
0.026
0.026
0.026
0.026
0.026
Misc. Electric
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.522
0.529
0.529
0.529
0.524
Non-HVAC Sub-Total
Grand Total
1.151
1.047
0.998
0.956
0.918
27790.0
27790.0
27790.0
27790.0
27790.0
27790.0
27790.0
27790.0
LVHC DOAS 60
60
(%)
14.4
LVHC DOAS 65
65
(%)
15.1
LVHC DOAS 70
70
(%)
15.6
26.8
20.8
20.1
19.5
19.4
Heating
14.3
13.5
11.0
8.6
6.5
Pumps
1.3
1.4
1.4
1.5
1.3
0.0
0.0
0.0
0.0
0.0
HVAC Sub-Total
Lights
54.6
49.4
47.0
44.7
42.9
43.1
48.1
50.4
52.6
54.3
Electric Equipment
2.2
2.5
2.6
2.7
2.8
Misc. Electric
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
Non-HVAC Sub-Total
45.4
50.6
53.0
55.3
57.1
Grand Total
100.0
100.0
100.0
100.0
100.0
Page 1 of 1
04/05/2004
04:33AM
Tons
MBH
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:33AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Maximum
Cooling
Sensible
(MBH)
26.5
132.3
29.1
26.0
7.4
5.4
8.5
15.2
13.0
13.3
17.5
15.9
32.4
32.0
11.4
6.6
6.5
15.5
Design
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
540
457
1095
Minimum
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
376
457
857
Total
Coil
Load
(MBH)
20.4
88.4
18.3
11.5
5.9
4.2
7.1
16.3
5.7
11.6
13.0
14.7
32.0
0.0
8.7
0.0
3.5
0.0
Sens
Coil
Load
(MBH)
20.4
88.4
18.3
11.5
5.9
4.2
7.1
16.1
5.7
11.6
13.0
14.7
32.0
0.0
8.7
0.0
3.5
0.0
Coil
Entering
DB / WB
(F)
71.6 / 56.4
71.0 / 52.2
68.7 / 52.4
65.5 / 50.3
71.3 / 57.7
72.1 / 61.6
73.3 / 58.1
77.0 / 64.3
67.0 / 51.1
73.3 / 60.3
71.0 / 55.2
75.5 / 60.7
75.8 / 59.6
0.0 / 0.0
72.1 / 62.3
0.0 / 0.0
68.9 / 60.3
0.0 / 0.0
Time
of
Peak
Load
Aug 1700
Jun 1400
Jul 1700
Sep 1300
Sep 1200
Sep 1200
Jun 1700
Jun 1700
Jun 1700
Jan 1700
Jul 1700
Jun 1700
Aug 1600
Jul 1700
Jul 1700
Aug 1700
Aug 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.0
50.7
18.2
3.5
7.4
10.8
4.3
12.9
4.3
0.0
2.3
8.2
12.9
13.5
3.5
16.0
16.7
3.8
Zone
Floor
Area
(ft)
2220.0
1760.0
1610.0
1665.0
870.0
1050.0
575.0
420.0
680.0
1305.0
1255.0
790.0
1045.0
3470.0
1960.0
2700.0
2315.0
2100.0
Zone
CFM/ft
0.66
4.15
1.00
0.86
0.48
0.38
0.82
2.01
1.06
0.56
0.77
1.11
1.77
0.51
0.32
0.20
0.20
0.52
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Coil
Leaving
DB / WB
(F)
58.5 / 51.0
59.7 / 47.2
58.0 / 47.7
58.0 / 46.9
58.0 / 52.4
62.1 / 57.9
59.1 / 52.4
59.1 / 57.9
59.6 / 47.8
58.5 / 54.6
58.4 / 49.9
59.7 / 54.8
59.6 / 53.3
0.0 / 0.0
59.1 / 57.6
0.0 / 0.0
61.7 / 57.7
0.0 / 0.0
Water
Flow
@ 10.0 F
(gpm)
4.09
17.69
3.67
2.29
1.18
0.84
1.42
3.26
1.13
2.31
2.61
2.94
6.40
0.00
1.75
0.00
0.69
0.00
Time
of
Peak
Load
Jul 0900
Jun 1500
Jul 0700
Sep 0800
Aug 1000
Aug 1200
Jul 1700
Jun 1700
Jun 1100
Jan 1300
Jul 1400
Jun 1700
Aug 1500
Des 0000
Jul 1600
Des 0000
Aug 0800
Des 0000
Page 1 of 3
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
04/05/2004
04:33AM
Fan
Motor
(BHP)
0.461
2.299
0.506
0.451
0.131
0.125
0.147
0.265
0.227
0.231
0.305
0.276
0.582
0.556
0.199
0.170
0.144
0.345
VENT
Fan
Motor
(kW)
0.344
1.714
0.378
0.336
0.098
0.093
0.110
0.198
0.169
0.172
0.227
0.205
0.434
0.414
0.148
0.127
0.107
0.257
Design
Airflow
(CFM)
453
2265
690
840
133
105
107
42
360
170
318
120
200
1605
178
540
188
1095
Zone Name /
Space Name
Zone 1
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room 116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
25.6
0.9
Jul 1700
Aug 1700
1413
51
1.9
1.1
2075.0
145.0
0.68
0.35
132.3
Jun 1400
7305
50.7
1760.0
4.15
29.1
Jul 1700
1609
18.2
1610.0
1.00
26.0
Sep 1300
1434
3.5
1665.0
0.86
1
1
1
1
5.9
0.5
0.2
0.9
Sep 1200
Jan 1700
Jan 1700
Aug 1700
328
26
13
50
6.2
0.0
0.0
1.2
585.0
100.0
70.0
115.0
0.56
0.26
0.18
0.43
1
1
1
2.3
2.4
1.3
Sep 1200
Sep 1200
Aug 1900
126
133
138
2.1
2.9
5.9
350.0
350.0
350.0
0.36
0.38
0.40
1
1
1
4.8
3.2
0.5
Jun 1700
Jun 1700
Jan 1700
267
176
25
2.1
2.3
0.0
380.0
130.0
65.0
0.70
1.36
0.39
1
1
1.8
13.4
Jul 1700
Jun 1700
102
741
2.8
10.1
210.0
210.0
0.49
3.53
13.0
Jun 1700
720
4.3
680.0
1.06
1
1
1.1
1.5
Jan 1700
Jan 1700
62
83
0.0
0.0
170.0
230.0
0.36
0.36
Page 2 of 3
Zone Name /
Space Name
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office (x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office (x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection Storage 001
B-Storage 002
04/05/2004
04:33AM
Mult.
1
1
1
1
1
1
Cooling
Sensible
(MBH)
0.2
0.4
0.3
3.7
0.4
5.7
Time
of
Load
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Air
Flow
(CFM)
9
21
17
202
22
317
Heating
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
0.0
Floor
Area
(ft)
60.0
110.0
100.0
300.0
60.0
275.0
Space
CFM/ft
0.14
0.19
0.17
0.67
0.37
1.15
1
1
1
1
2.2
5.5
3.6
6.2
Jul 1700
Jul 1700
Jul 1700
Jul 1700
124
304
198
343
0.3
0.7
0.5
0.7
165.0
385.0
305.0
400.0
0.75
0.79
0.65
0.86
1
4
1
1.9
2.5
3.9
Jul 1700
Jun 1700
Jun 1700
108
138
215
0.3
1.3
2.8
180.0
110.0
170.0
0.60
1.26
1.27
1
8
6.7
3.4
Sep 1200
Aug 1600
368
185
2.8
1.3
165.0
110.0
2.23
1.68
1
1
22.4
9.6
Jul 1700
Jul 1700
1235
531
7.2
6.4
2510.0
960.0
0.49
0.55
1
1
1
1
1
1
0.4
0.4
0.4
4.6
5.4
0.4
Jul 1600
Jul 1600
Jul 1700
Jul 1600
Jul 1700
Jul 1700
20
20
20
255
297
20
0.1
0.1
0.0
1.6
1.6
0.1
65.0
65.0
25.0
900.0
865.0
40.0
0.31
0.31
0.80
0.28
0.34
0.49
6.6
Aug 1700
540
16.0
2700.0
0.20
1
1
1
1
0.2
1.3
3.4
1.7
Jan 1700
Jan 1700
Aug 1700
Aug 1700
14
72
280
92
0.6
2.5
11.9
1.7
90.0
785.0
890.0
550.0
0.15
0.09
0.31
0.17
1
1
14.2
1.4
Jan 1700
Jan 1700
975
120
3.8
0.0
1500.0
600.0
0.65
0.20
Page 3 of 3
04/05/2004
04:33AM
Tons
MBH
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:33AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Maximum
Cooling
Sensible
(MBH)
26.5
132.3
29.1
26.0
7.4
5.4
8.5
15.2
13.0
13.3
17.5
15.9
32.4
32.0
11.4
6.6
6.5
15.5
Design
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
540
457
1095
Minimum
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
376
457
857
Total
Coil
Load
(MBH)
20.4
88.4
18.3
11.5
5.9
4.2
7.1
16.5
5.7
11.6
13.0
14.7
32.0
0.0
9.2
0.0
3.5
0.0
Sens
Coil
Load
(MBH)
20.4
88.4
18.3
11.5
5.9
4.2
7.1
16.1
5.7
11.6
13.0
14.7
32.0
0.0
8.7
0.0
3.5
0.0
Coil
Entering
DB / WB
(F)
71.6 / 58.0
71.0 / 53.9
68.7 / 54.1
65.5 / 52.0
71.3 / 59.2
72.1 / 63.0
73.3 / 59.6
77.0 / 64.4
67.0 / 52.8
73.3 / 61.7
71.0 / 56.8
75.5 / 62.2
75.8 / 61.0
0.0 / 0.0
72.1 / 63.1
0.0 / 0.0
68.9 / 61.8
0.0 / 0.0
Time
of
Peak
Load
Aug 1700
Jun 1400
Jul 1700
Sep 1300
Sep 1200
Sep 1200
Jun 1700
Jun 1700
Jun 1700
Jan 1700
Jul 1700
Jun 1700
Aug 1600
Jul 1700
Jul 1700
Aug 1700
Aug 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.0
50.7
18.2
3.5
7.4
10.8
4.3
12.9
4.3
0.0
2.3
8.2
12.9
13.5
3.5
16.0
16.7
3.8
Zone
Floor
Area
(ft)
2220.0
1760.0
1610.0
1665.0
870.0
1050.0
575.0
420.0
680.0
1305.0
1255.0
790.0
1045.0
3470.0
1960.0
2700.0
2315.0
2100.0
Zone
CFM/ft
0.66
4.15
1.00
0.86
0.48
0.38
0.82
2.01
1.06
0.56
0.77
1.11
1.77
0.51
0.32
0.20
0.20
0.52
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Coil
Leaving
DB / WB
(F)
58.5 / 52.8
59.7 / 49.1
58.0 / 49.6
58.0 / 48.7
58.0 / 54.1
62.1 / 59.5
59.1 / 54.1
59.1 / 57.9
59.6 / 49.6
58.5 / 56.2
58.4 / 51.7
59.7 / 56.4
59.6 / 54.9
0.0 / 0.0
59.1 / 58.3
0.0 / 0.0
61.7 / 59.2
0.0 / 0.0
Water
Flow
@ 10.0 F
(gpm)
4.09
17.69
3.67
2.29
1.18
0.84
1.42
3.29
1.13
2.31
2.61
2.94
6.40
0.00
1.84
0.00
0.69
0.00
Time
of
Peak
Load
Jul 0900
Jun 1500
Jul 0700
Sep 0800
Aug 1000
Aug 1200
Jul 1700
Jun 1700
Jun 1100
Jan 1300
Jul 1400
Jun 1700
Aug 1500
Des 0000
Jul 1600
Des 0000
Aug 0800
Des 0000
Page 1 of 3
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
04/05/2004
04:33AM
Fan
Motor
(BHP)
0.461
2.299
0.506
0.451
0.131
0.125
0.147
0.265
0.227
0.231
0.305
0.276
0.582
0.556
0.199
0.170
0.144
0.345
VENT
Fan
Motor
(kW)
0.344
1.714
0.378
0.336
0.098
0.093
0.110
0.198
0.169
0.172
0.227
0.205
0.434
0.414
0.148
0.127
0.107
0.257
Design
Airflow
(CFM)
453
2265
690
840
133
105
107
42
360
170
318
120
200
1605
178
540
188
1095
Zone Name /
Space Name
Zone 1
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room 116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
25.6
0.9
Jul 1700
Aug 1700
1413
51
1.9
1.1
2075.0
145.0
0.68
0.35
132.3
Jun 1400
7305
50.7
1760.0
4.15
29.1
Jul 1700
1609
18.2
1610.0
1.00
26.0
Sep 1300
1434
3.5
1665.0
0.86
1
1
1
1
5.9
0.5
0.2
0.9
Sep 1200
Jan 1700
Jan 1700
Aug 1700
328
26
13
50
6.2
0.0
0.0
1.2
585.0
100.0
70.0
115.0
0.56
0.26
0.18
0.43
1
1
1
2.3
2.4
1.3
Sep 1200
Sep 1200
Aug 1900
126
133
138
2.1
2.9
5.9
350.0
350.0
350.0
0.36
0.38
0.40
1
1
1
4.8
3.2
0.5
Jun 1700
Jun 1700
Jan 1700
267
176
25
2.1
2.3
0.0
380.0
130.0
65.0
0.70
1.36
0.39
1
1
1.8
13.4
Jul 1700
Jun 1700
102
741
2.8
10.1
210.0
210.0
0.49
3.53
13.0
Jun 1700
720
4.3
680.0
1.06
1
1
1.1
1.5
Jan 1700
Jan 1700
62
83
0.0
0.0
170.0
230.0
0.36
0.36
Page 2 of 3
Zone Name /
Space Name
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office (x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office (x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection Storage 001
B-Storage 002
04/05/2004
04:33AM
Mult.
1
1
1
1
1
1
Cooling
Sensible
(MBH)
0.2
0.4
0.3
3.7
0.4
5.7
Time
of
Load
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Air
Flow
(CFM)
9
21
17
202
22
317
Heating
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
0.0
Floor
Area
(ft)
60.0
110.0
100.0
300.0
60.0
275.0
Space
CFM/ft
0.14
0.19
0.17
0.67
0.37
1.15
1
1
1
1
2.2
5.5
3.6
6.2
Jul 1700
Jul 1700
Jul 1700
Jul 1700
124
304
198
343
0.3
0.7
0.5
0.7
165.0
385.0
305.0
400.0
0.75
0.79
0.65
0.86
1
4
1
1.9
2.5
3.9
Jul 1700
Jun 1700
Jun 1700
108
138
215
0.3
1.3
2.8
180.0
110.0
170.0
0.60
1.26
1.27
1
8
6.7
3.4
Sep 1200
Aug 1600
368
185
2.8
1.3
165.0
110.0
2.23
1.68
1
1
22.4
9.6
Jul 1700
Jul 1700
1235
531
7.2
6.4
2510.0
960.0
0.49
0.55
1
1
1
1
1
1
0.4
0.4
0.4
4.6
5.4
0.4
Jul 1600
Jul 1600
Jul 1700
Jul 1600
Jul 1700
Jul 1700
20
20
20
255
297
20
0.1
0.1
0.0
1.6
1.6
0.1
65.0
65.0
25.0
900.0
865.0
40.0
0.31
0.31
0.80
0.28
0.34
0.49
6.6
Aug 1700
540
16.0
2700.0
0.20
1
1
1
1
0.2
1.3
3.4
1.7
Jan 1700
Jan 1700
Aug 1700
Aug 1700
14
72
280
92
0.6
2.5
11.9
1.7
90.0
785.0
890.0
550.0
0.15
0.09
0.31
0.17
1
1
14.2
1.4
Jan 1700
Jan 1700
975
120
3.8
0.0
1500.0
600.0
0.65
0.20
Page 3 of 3
04/05/2004
04:33AM
Tons
MBH
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:33AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Maximum
Cooling
Sensible
(MBH)
26.5
132.3
29.1
26.0
7.4
5.4
8.5
15.2
13.0
13.3
17.5
15.9
32.4
32.0
11.4
6.6
6.5
15.5
Design
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
540
457
1095
Minimum
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
376
457
857
Total
Coil
Load
(MBH)
22.8
100.5
22.0
15.9
6.6
4.8
7.6
16.9
7.6
12.7
14.7
15.3
33.1
7.5
10.9
0.0
4.5
0.0
Sens
Coil
Load
(MBH)
22.8
100.5
22.0
15.9
6.6
4.8
7.6
16.3
7.6
12.5
14.7
15.3
33.1
7.5
9.7
0.0
4.5
0.0
Coil
Entering
DB / WB
(F)
73.1 / 60.0
72.6 / 56.2
70.8 / 56.6
68.4 / 54.9
72.9 / 61.3
73.4 / 64.8
74.4 / 61.4
77.3 / 64.5
69.5 / 55.5
74.5 / 63.2
72.6 / 58.9
76.2 / 63.8
76.3 / 62.6
62.4 / 51.5
73.5 / 64.0
0.0 / 0.0
70.9 / 63.8
0.0 / 0.0
Time
of
Peak
Load
Aug 1700
Jun 1400
Jul 1700
Sep 1300
Sep 1200
Sep 1200
Jun 1700
Jun 1700
Jun 1700
Jan 1700
Jul 1700
Jun 1700
Aug 1600
Jul 1700
Jul 1700
Aug 1700
Aug 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.0
50.7
18.2
3.5
7.4
10.8
4.3
12.9
4.3
0.0
2.3
8.2
12.9
13.5
3.5
16.0
16.7
3.8
Zone
Floor
Area
(ft)
2220.0
1760.0
1610.0
1665.0
870.0
1050.0
575.0
420.0
680.0
1305.0
1255.0
790.0
1045.0
3470.0
1960.0
2700.0
2315.0
2100.0
Zone
CFM/ft
0.66
4.15
1.00
0.86
0.48
0.38
0.82
2.01
1.06
0.56
0.77
1.11
1.77
0.51
0.32
0.20
0.20
0.52
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Coil
Leaving
DB / WB
(F)
58.5 / 54.4
59.7 / 50.9
58.0 / 51.3
58.0 / 50.6
58.0 / 55.7
62.1 / 60.9
59.1 / 55.7
59.1 / 57.9
59.6 / 51.4
58.5 / 57.4
58.4 / 53.3
59.7 / 57.9
59.6 / 56.5
58.4 / 49.8
59.1 / 58.2
0.0 / 0.0
61.7 / 60.7
0.0 / 0.0
Water
Flow
@ 10.0 F
(gpm)
4.57
20.10
4.40
3.19
1.32
0.96
1.53
3.37
1.52
2.53
2.95
3.06
6.62
1.50
2.19
0.00
0.89
0.00
Time
of
Peak
Load
Jul 0900
Jun 1500
Jul 0700
Sep 0800
Aug 1000
Aug 1200
Jul 1700
Jun 1700
Jun 1100
Jan 1300
Jul 1400
Jun 1700
Aug 1500
Aug 1500
Jul 1600
Des 0000
Aug 0800
Des 0000
Page 1 of 3
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
04/05/2004
04:33AM
Fan
Motor
(BHP)
0.461
2.299
0.506
0.451
0.131
0.125
0.147
0.265
0.227
0.231
0.305
0.276
0.582
0.556
0.199
0.170
0.144
0.345
VENT
Fan
Motor
(kW)
0.344
1.714
0.378
0.336
0.098
0.093
0.110
0.198
0.169
0.172
0.227
0.205
0.434
0.414
0.148
0.127
0.107
0.257
Design
Airflow
(CFM)
453
2265
690
840
133
105
107
42
360
170
318
120
200
1605
178
540
188
1095
Zone Name /
Space Name
Zone 1
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room 116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
25.6
0.9
Jul 1700
Aug 1700
1413
51
1.9
1.1
2075.0
145.0
0.68
0.35
132.3
Jun 1400
7305
50.7
1760.0
4.15
29.1
Jul 1700
1609
18.2
1610.0
1.00
26.0
Sep 1300
1434
3.5
1665.0
0.86
1
1
1
1
5.9
0.5
0.2
0.9
Sep 1200
Jan 1700
Jan 1700
Aug 1700
328
26
13
50
6.2
0.0
0.0
1.2
585.0
100.0
70.0
115.0
0.56
0.26
0.18
0.43
1
1
1
2.3
2.4
1.3
Sep 1200
Sep 1200
Aug 1900
126
133
138
2.1
2.9
5.9
350.0
350.0
350.0
0.36
0.38
0.40
1
1
1
4.8
3.2
0.5
Jun 1700
Jun 1700
Jan 1700
267
176
25
2.1
2.3
0.0
380.0
130.0
65.0
0.70
1.36
0.39
1
1
1.8
13.4
Jul 1700
Jun 1700
102
741
2.8
10.1
210.0
210.0
0.49
3.53
13.0
Jun 1700
720
4.3
680.0
1.06
1
1
1.1
1.5
Jan 1700
Jan 1700
62
83
0.0
0.0
170.0
230.0
0.36
0.36
Page 2 of 3
Zone Name /
Space Name
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office (x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office (x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection Storage 001
B-Storage 002
04/05/2004
04:33AM
Mult.
1
1
1
1
1
1
Cooling
Sensible
(MBH)
0.2
0.4
0.3
3.7
0.4
5.7
Time
of
Load
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Air
Flow
(CFM)
9
21
17
202
22
317
Heating
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
0.0
Floor
Area
(ft)
60.0
110.0
100.0
300.0
60.0
275.0
Space
CFM/ft
0.14
0.19
0.17
0.67
0.37
1.15
1
1
1
1
2.2
5.5
3.6
6.2
Jul 1700
Jul 1700
Jul 1700
Jul 1700
124
304
198
343
0.3
0.7
0.5
0.7
165.0
385.0
305.0
400.0
0.75
0.79
0.65
0.86
1
4
1
1.9
2.5
3.9
Jul 1700
Jun 1700
Jun 1700
108
138
215
0.3
1.3
2.8
180.0
110.0
170.0
0.60
1.26
1.27
1
8
6.7
3.4
Sep 1200
Aug 1600
368
185
2.8
1.3
165.0
110.0
2.23
1.68
1
1
22.4
9.6
Jul 1700
Jul 1700
1235
531
7.2
6.4
2510.0
960.0
0.49
0.55
1
1
1
1
1
1
0.4
0.4
0.4
4.6
5.4
0.4
Jul 1600
Jul 1600
Jul 1700
Jul 1600
Jul 1700
Jul 1700
20
20
20
255
297
20
0.1
0.1
0.0
1.6
1.6
0.1
65.0
65.0
25.0
900.0
865.0
40.0
0.31
0.31
0.80
0.28
0.34
0.49
6.6
Aug 1700
540
16.0
2700.0
0.20
1
1
1
1
0.2
1.3
3.4
1.7
Jan 1700
Jan 1700
Aug 1700
Aug 1700
14
72
280
92
0.6
2.5
11.9
1.7
90.0
785.0
890.0
550.0
0.15
0.09
0.31
0.17
1
1
14.2
1.4
Jan 1700
Jan 1700
975
120
3.8
0.0
1500.0
600.0
0.65
0.20
Page 3 of 3
04/05/2004
04:33AM
Tons
MBH
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:33AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Maximum
Cooling
Sensible
(MBH)
26.5
132.3
29.1
26.0
7.4
5.4
8.5
15.2
13.0
13.3
17.5
15.9
32.4
32.0
11.4
6.6
6.5
15.5
Design
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
540
457
1095
Minimum
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
376
457
857
Total
Coil
Load
(MBH)
25.2
112.5
25.7
20.4
7.6
5.8
8.2
17.3
9.5
14.4
16.4
16.3
34.1
16.0
12.8
2.5
6.2
5.5
Sens
Coil
Load
(MBH)
25.2
112.5
25.7
20.4
7.3
5.3
8.2
16.5
9.5
13.4
16.4
15.9
34.1
16.0
10.6
2.5
5.5
5.5
Coil
Entering
DB / WB
(F)
74.7 / 62.2
74.1 / 58.6
73.0 / 59.2
71.4 / 57.9
74.5 / 63.1
74.7 / 65.8
75.6 / 63.4
77.5 / 64.7
72.0 / 58.3
75.6 / 64.0
74.3 / 61.2
76.8 / 64.7
76.9 / 64.4
66.9 / 55.3
74.9 / 64.8
65.8 / 54.6
73.0 / 65.3
65.8 / 54.6
Time
of
Peak
Load
Aug 1700
Jun 1400
Jul 1700
Sep 1300
Sep 1200
Sep 1200
Jun 1700
Jun 1700
Jun 1700
Jan 1700
Jul 1700
Jun 1700
Aug 1600
Jul 1700
Jul 1700
Aug 1700
Aug 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.0
50.7
18.2
3.5
7.4
10.8
4.3
12.9
4.3
0.0
2.3
8.2
12.9
13.5
3.5
16.0
16.7
3.8
Zone
Floor
Area
(ft)
2220.0
1760.0
1610.0
1665.0
870.0
1050.0
575.0
420.0
680.0
1305.0
1255.0
790.0
1045.0
3470.0
1960.0
2700.0
2315.0
2100.0
Zone
CFM/ft
0.66
4.15
1.00
0.86
0.48
0.38
0.82
2.01
1.06
0.56
0.77
1.11
1.77
0.51
0.32
0.20
0.20
0.52
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Coil
Leaving
DB / WB
(F)
58.5 / 56.3
59.7 / 52.9
58.0 / 53.3
58.0 / 52.6
58.0 / 56.9
62.1 / 61.2
59.1 / 57.5
59.1 / 57.9
59.6 / 53.4
58.5 / 57.4
58.4 / 55.3
59.7 / 58.6
59.6 / 58.3
58.4 / 51.8
59.1 / 58.2
61.4 / 52.8
61.7 / 61.0
61.0 / 52.7
Water
Flow
@ 10.0 F
(gpm)
5.05
22.52
5.14
4.08
1.51
1.15
1.64
3.47
1.90
2.89
3.28
3.27
6.83
3.21
2.56
0.50
1.25
1.11
Time
of
Peak
Load
Jul 0900
Jun 1500
Jul 0700
Sep 0800
Aug 1000
Aug 1200
Jul 1700
Jun 1700
Jun 1100
Jan 1300
Jul 1400
Jun 1700
Aug 1500
Aug 1500
Jul 1600
Aug 0700
Aug 0800
Jan 1700
Page 1 of 3
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
04/05/2004
04:33AM
Fan
Motor
(BHP)
0.461
2.299
0.506
0.451
0.131
0.125
0.147
0.265
0.227
0.231
0.305
0.276
0.582
0.556
0.199
0.170
0.144
0.345
VENT
Fan
Motor
(kW)
0.344
1.714
0.378
0.336
0.098
0.093
0.110
0.198
0.169
0.172
0.227
0.205
0.434
0.414
0.148
0.127
0.107
0.257
Design
Airflow
(CFM)
453
2265
690
840
133
105
107
42
360
170
318
120
200
1605
178
540
188
1095
Zone Name /
Space Name
Zone 1
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room 116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
25.6
0.9
Jul 1700
Aug 1700
1413
51
1.9
1.1
2075.0
145.0
0.68
0.35
132.3
Jun 1400
7305
50.7
1760.0
4.15
29.1
Jul 1700
1609
18.2
1610.0
1.00
26.0
Sep 1300
1434
3.5
1665.0
0.86
1
1
1
1
5.9
0.5
0.2
0.9
Sep 1200
Jan 1700
Jan 1700
Aug 1700
328
26
13
50
6.2
0.0
0.0
1.2
585.0
100.0
70.0
115.0
0.56
0.26
0.18
0.43
1
1
1
2.3
2.4
1.3
Sep 1200
Sep 1200
Aug 1900
126
133
138
2.1
2.9
5.9
350.0
350.0
350.0
0.36
0.38
0.40
1
1
1
4.8
3.2
0.5
Jun 1700
Jun 1700
Jan 1700
267
176
25
2.1
2.3
0.0
380.0
130.0
65.0
0.70
1.36
0.39
1
1
1.8
13.4
Jul 1700
Jun 1700
102
741
2.8
10.1
210.0
210.0
0.49
3.53
13.0
Jun 1700
720
4.3
680.0
1.06
1
1
1.1
1.5
Jan 1700
Jan 1700
62
83
0.0
0.0
170.0
230.0
0.36
0.36
Page 2 of 3
Zone Name /
Space Name
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office (x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office (x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection Storage 001
B-Storage 002
04/05/2004
04:33AM
Mult.
1
1
1
1
1
1
Cooling
Sensible
(MBH)
0.2
0.4
0.3
3.7
0.4
5.7
Time
of
Load
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Air
Flow
(CFM)
9
21
17
202
22
317
Heating
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
0.0
Floor
Area
(ft)
60.0
110.0
100.0
300.0
60.0
275.0
Space
CFM/ft
0.14
0.19
0.17
0.67
0.37
1.15
1
1
1
1
2.2
5.5
3.6
6.2
Jul 1700
Jul 1700
Jul 1700
Jul 1700
124
304
198
343
0.3
0.7
0.5
0.7
165.0
385.0
305.0
400.0
0.75
0.79
0.65
0.86
1
4
1
1.9
2.5
3.9
Jul 1700
Jun 1700
Jun 1700
108
138
215
0.3
1.3
2.8
180.0
110.0
170.0
0.60
1.26
1.27
1
8
6.7
3.4
Sep 1200
Aug 1600
368
185
2.8
1.3
165.0
110.0
2.23
1.68
1
1
22.4
9.6
Jul 1700
Jul 1700
1235
531
7.2
6.4
2510.0
960.0
0.49
0.55
1
1
1
1
1
1
0.4
0.4
0.4
4.6
5.4
0.4
Jul 1600
Jul 1600
Jul 1700
Jul 1600
Jul 1700
Jul 1700
20
20
20
255
297
20
0.1
0.1
0.0
1.6
1.6
0.1
65.0
65.0
25.0
900.0
865.0
40.0
0.31
0.31
0.80
0.28
0.34
0.49
6.6
Aug 1700
540
16.0
2700.0
0.20
1
1
1
1
0.2
1.3
3.4
1.7
Jan 1700
Jan 1700
Aug 1700
Aug 1700
14
72
280
92
0.6
2.5
11.9
1.7
90.0
785.0
890.0
550.0
0.15
0.09
0.31
0.17
1
1
14.2
1.4
Jan 1700
Jan 1700
975
120
3.8
0.0
1500.0
600.0
0.65
0.20
Page 3 of 3
04/05/2004
04:33AM
Tons
MBH
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:33AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Maximum
Cooling
Sensible
(MBH)
26.5
132.3
29.1
26.0
7.4
5.4
8.5
15.2
13.0
13.3
17.5
15.9
32.4
32.0
11.4
6.6
6.5
15.5
Design
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
540
457
1095
Minimum
Air
Flow
(CFM)
1465
7305
1609
1434
417
396
469
843
720
733
969
876
1850
1766
632
376
457
857
Total
Coil
Load
(MBH)
29.1
124.6
29.4
24.9
9.1
6.9
9.3
17.8
11.4
16.4
18.3
17.7
36.4
24.6
14.8
5.4
8.4
11.4
Sens
Coil
Load
(MBH)
27.7
124.6
29.4
24.9
8.0
5.9
8.8
16.8
11.4
14.3
18.1
16.6
35.2
24.6
11.6
5.4
6.5
11.4
Coil
Entering
DB / WB
(F)
76.2 / 64.0
75.7 / 61.2
75.1 / 61.9
74.3 / 61.0
76.1 / 64.2
76.1 / 66.7
76.7 / 64.5
77.8 / 64.9
74.5 / 61.2
76.8 / 64.8
75.9 / 63.6
77.5 / 65.2
77.4 / 64.8
71.5 / 59.2
76.3 / 65.8
70.8 / 58.7
75.0 / 66.7
70.8 / 58.7
Time
of
Peak
Load
Aug 1700
Jun 1400
Jul 1700
Sep 1300
Sep 1200
Sep 1200
Jun 1700
Jun 1700
Jun 1700
Jan 1700
Jul 1700
Jun 1700
Aug 1600
Jul 1700
Jul 1700
Aug 1700
Aug 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.0
50.7
18.2
3.5
7.4
10.8
4.3
12.9
4.3
0.0
2.3
8.2
12.9
13.5
3.5
16.0
16.7
3.8
Zone
Floor
Area
(ft)
2220.0
1760.0
1610.0
1665.0
870.0
1050.0
575.0
420.0
680.0
1305.0
1255.0
790.0
1045.0
3470.0
1960.0
2700.0
2315.0
2100.0
Zone
CFM/ft
0.66
4.15
1.00
0.86
0.48
0.38
0.82
2.01
1.06
0.56
0.77
1.11
1.77
0.51
0.32
0.20
0.20
0.52
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Coil
Leaving
DB / WB
(F)
58.5 / 57.3
59.7 / 55.2
58.0 / 55.5
58.0 / 54.8
58.0 / 56.9
62.1 / 61.2
59.1 / 58.0
59.1 / 57.9
59.6 / 55.6
58.5 / 57.4
58.4 / 57.2
59.7 / 58.6
59.6 / 58.4
58.4 / 54.1
59.1 / 58.2
61.4 / 55.1
61.7 / 61.0
61.0 / 54.9
Water
Flow
@ 10.0 F
(gpm)
5.82
24.93
5.87
4.98
1.81
1.39
1.86
3.56
2.28
3.27
3.67
3.54
7.28
4.92
2.96
1.07
1.68
2.28
Time
of
Peak
Load
Jul 0900
Jun 1500
Jul 0700
Sep 0800
Aug 1000
Aug 1200
Jul 1700
Jun 1700
Jun 1100
Dec 1300
Jul 1400
Jun 1700
Aug 1500
Aug 1500
Jul 1600
Aug 0700
Aug 0800
Jan 1700
Page 1 of 3
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
04/05/2004
04:33AM
Fan
Motor
(BHP)
0.461
2.299
0.506
0.451
0.131
0.125
0.147
0.265
0.227
0.231
0.305
0.276
0.582
0.556
0.199
0.170
0.144
0.345
VENT
Fan
Motor
(kW)
0.344
1.714
0.378
0.336
0.098
0.093
0.110
0.198
0.169
0.172
0.227
0.205
0.434
0.414
0.148
0.127
0.107
0.257
Design
Airflow
(CFM)
453
2265
690
840
133
105
107
42
360
170
318
120
200
1605
178
540
188
1095
Zone Name /
Space Name
Zone 1
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room 116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
25.6
0.9
Jul 1700
Aug 1700
1413
51
1.9
1.1
2075.0
145.0
0.68
0.35
132.3
Jun 1400
7305
50.7
1760.0
4.15
29.1
Jul 1700
1609
18.2
1610.0
1.00
26.0
Sep 1300
1434
3.5
1665.0
0.86
1
1
1
1
5.9
0.5
0.2
0.9
Sep 1200
Jan 1700
Jan 1700
Aug 1700
328
26
13
50
6.2
0.0
0.0
1.2
585.0
100.0
70.0
115.0
0.56
0.26
0.18
0.43
1
1
1
2.3
2.4
1.3
Sep 1200
Sep 1200
Aug 1900
126
133
138
2.1
2.9
5.9
350.0
350.0
350.0
0.36
0.38
0.40
1
1
1
4.8
3.2
0.5
Jun 1700
Jun 1700
Jan 1700
267
176
25
2.1
2.3
0.0
380.0
130.0
65.0
0.70
1.36
0.39
1
1
1.8
13.4
Jul 1700
Jun 1700
102
741
2.8
10.1
210.0
210.0
0.49
3.53
13.0
Jun 1700
720
4.3
680.0
1.06
1
1
1.1
1.5
Jan 1700
Jan 1700
62
83
0.0
0.0
170.0
230.0
0.36
0.36
Page 2 of 3
Zone Name /
Space Name
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office (x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office (x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection Storage 001
B-Storage 002
04/05/2004
04:33AM
Mult.
1
1
1
1
1
1
Cooling
Sensible
(MBH)
0.2
0.4
0.3
3.7
0.4
5.7
Time
of
Load
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Air
Flow
(CFM)
9
21
17
202
22
317
Heating
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
0.0
Floor
Area
(ft)
60.0
110.0
100.0
300.0
60.0
275.0
Space
CFM/ft
0.14
0.19
0.17
0.67
0.37
1.15
1
1
1
1
2.2
5.5
3.6
6.2
Jul 1700
Jul 1700
Jul 1700
Jul 1700
124
304
198
343
0.3
0.7
0.5
0.7
165.0
385.0
305.0
400.0
0.75
0.79
0.65
0.86
1
4
1
1.9
2.5
3.9
Jul 1700
Jun 1700
Jun 1700
108
138
215
0.3
1.3
2.8
180.0
110.0
170.0
0.60
1.26
1.27
1
8
6.7
3.4
Sep 1200
Aug 1600
368
185
2.8
1.3
165.0
110.0
2.23
1.68
1
1
22.4
9.6
Jul 1700
Jul 1700
1235
531
7.2
6.4
2510.0
960.0
0.49
0.55
1
1
1
1
1
1
0.4
0.4
0.4
4.6
5.4
0.4
Jul 1600
Jul 1600
Jul 1700
Jul 1600
Jul 1700
Jul 1700
20
20
20
255
297
20
0.1
0.1
0.0
1.6
1.6
0.1
65.0
65.0
25.0
900.0
865.0
40.0
0.31
0.31
0.80
0.28
0.34
0.49
6.6
Aug 1700
540
16.0
2700.0
0.20
1
1
1
1
0.2
1.3
3.4
1.7
Jan 1700
Jan 1700
Aug 1700
Aug 1700
14
72
280
92
0.6
2.5
11.9
1.7
90.0
785.0
890.0
550.0
0.15
0.09
0.31
0.17
1
1
14.2
1.4
Jan 1700
Jan 1700
975
120
3.8
0.0
1500.0
600.0
0.65
0.20
Page 3 of 3
04/05/2004
04:33AM
Tons
MBH
MBH
CFM
CFM
gpm
Page 1 of 1
04/05/2004
04:33AM
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Maximum
Cooling
Sensible
(MBH)
26.5
132.3
29.1
26.0
7.4
5.4
8.5
15.2
13.0
13.3
17.5
15.9
32.4
32.0
11.4
6.6
6.5
15.5
Design
Air
Flow
(CFM)
1465
7305
1609
1434
510
396
510
870
720
733
969
876
1850
1766
632
540
510
1095
Minimum
Air
Flow
(CFM)
1465
7305
1609
1434
510
396
510
870
720
733
969
876
1850
1766
632
510
510
857
Total
Coil
Load
(MBH)
28.1
126.0
28.4
24.0
8.4
6.6
8.9
17.0
10.9
15.8
17.6
17.1
35.4
23.5
14.3
4.6
8.0
10.5
Sens
Coil
Load
(MBH)
26.8
126.0
28.4
24.0
7.9
5.6
8.6
16.1
10.9
13.8
17.4
16.0
34.2
23.5
11.1
4.6
6.2
10.5
Coil
Entering
DB / WB
(F)
75.6 / 63.8
75.9 / 61.2
74.6 / 61.7
73.7 / 60.8
75.4 / 65.2
75.4 / 66.5
75.9 / 64.7
77.2 / 65.1
73.7 / 60.9
76.1 / 64.6
75.3 / 63.4
76.9 / 65.0
76.9 / 64.7
70.9 / 59.0
75.6 / 65.6
70.0 / 58.4
74.5 / 67.1
70.0 / 58.4
Time
of
Peak
Load
Aug 1700
Jun 1400
Jul 1700
Sep 1300
Sep 1200
Sep 1200
Jun 1700
Jun 1700
Jun 1700
Jan 1700
Jul 1700
Jun 1700
Aug 1600
Jul 1700
Jul 1700
Aug 1700
Aug 1700
Jan 1700
Maximum
Heating
Load
(MBH)
3.0
50.7
18.2
3.5
7.4
10.8
4.3
12.9
4.3
0.0
2.3
8.2
12.9
13.5
3.5
16.0
16.7
3.8
Zone
Floor
Area
(ft)
2220.0
1760.0
1610.0
1665.0
870.0
1050.0
575.0
420.0
680.0
1305.0
1255.0
790.0
1045.0
3470.0
1960.0
2700.0
2315.0
2100.0
Zone
CFM/ft
0.66
4.15
1.00
0.86
0.59
0.38
0.89
2.07
1.06
0.56
0.77
1.11
1.77
0.51
0.32
0.20
0.22
0.52
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
Coil
Leaving
DB / WB
(F)
58.5 / 57.4
59.7 / 55.2
58.0 / 55.6
58.0 / 54.8
60.9 / 59.9
62.1 / 61.3
60.1 / 59.0
59.8 / 58.7
59.6 / 55.6
58.5 / 57.4
58.4 / 57.2
59.7 / 58.6
59.6 / 58.4
58.4 / 54.1
59.1 / 58.2
62.1 / 55.3
63.0 / 62.3
61.0 / 54.9
Water
Flow
@ 10.0 F
(gpm)
5.63
25.22
5.68
4.81
1.68
1.33
1.79
3.41
2.17
3.16
3.53
3.42
7.09
4.71
2.86
0.92
1.60
2.11
Time
of
Peak
Load
Jul 0900
Jun 1500
Jul 0700
Sep 0800
Aug 1200
Aug 1200
Jun 1700
Jun 1600
Jun 1100
Dec 1300
Jul 1400
Jun 1700
Aug 1500
Aug 1500
Jul 1600
Aug 0800
Aug 0900
Jan 1700
Page 1 of 3
Zone Name
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Zone 6
Zone 7
Zone 8
Zone 9
Zone 10
Zone 11
Zone 12
Zone 13
Zone 14
Zone 15
Zone 16
Zone 17
Zone 18
04/05/2004
04:33AM
Fan
Motor
(BHP)
0.671
3.353
0.671
0.671
0.134
0.161
0.134
0.402
0.134
0.268
0.402
0.456
0.939
0.671
0.134
0.161
0.161
0.134
VENT
Fan
Motor
(kW)
0.500
2.500
0.500
0.500
0.100
0.120
0.100
0.300
0.100
0.200
0.300
0.340
0.700
0.500
0.100
0.120
0.120
0.100
Design
Airflow
(CFM)
453
2265
690
840
133
105
107
42
360
170
318
120
200
1605
178
540
188
1095
Zone Name /
Space Name
Zone 1
1-Archive Storage
1-Negative Storage
Zone 2
1-Lobby
Zone 3
1-Reading Room 116
Zone 4
1-Orientation
Zone 5
1-Loading Dock
1-Receiving
1-Shower 102
1-Vestibule
Zone 6
1-Stair 2
2-Stair 2
B-Stair 2
Zone 7
1-Processing Workroom
1-Archivist
1-Corridor 112
Zone 8
1-Stair 1
2-Stair 1
Zone 9
2-School Program
Zone 10
1-Mens Room
1-Womens Room
Mult.
Cooling
Sensible
(MBH)
Time
of
Load
Air
Flow
(CFM)
Heating
Load
(MBH)
Floor
Area
(ft)
Space
CFM/ft
1
1
25.6
0.9
Jul 1700
Aug 1700
1413
51
1.9
1.1
2075.0
145.0
0.68
0.35
132.3
Jun 1400
7305
50.7
1760.0
4.15
29.1
Jul 1700
1609
18.2
1610.0
1.00
26.0
Sep 1300
1434
3.5
1665.0
0.86
1
1
1
1
5.9
0.5
0.2
0.9
Sep 1200
Jan 1700
Jan 1700
Aug 1700
401
32
16
61
6.2
0.0
0.0
1.2
585.0
100.0
70.0
115.0
0.69
0.32
0.22
0.53
1
1
1
2.3
2.4
1.3
Sep 1200
Sep 1200
Aug 1900
126
133
138
2.1
2.9
5.9
350.0
350.0
350.0
0.36
0.38
0.40
1
1
1
4.8
3.2
0.5
Jun 1700
Jun 1700
Jan 1700
290
192
28
2.1
2.3
0.0
380.0
130.0
65.0
0.76
1.48
0.43
1
1
1.8
13.4
Jul 1700
Jun 1700
105
765
2.8
10.1
210.0
210.0
0.50
3.64
13.0
Jun 1700
720
4.3
680.0
1.06
1
1
1.1
1.5
Jan 1700
Jan 1700
62
83
0.0
0.0
170.0
230.0
0.36
0.36
Page 2 of 3
Zone Name /
Space Name
1-Janitor 110
1-Coats 108
1-Storage 107
1-Corridor
1-Locker Vestibule
1-Museum Shop
Zone 11
2-Copy Room
2-Conference Room
2-Processing Room
2-Work Stations
Zone 12
2-Office 205
2-Northern Office (x4)
2-Directors Office
Zone 13
2-Lunch
2-Western Office (x8)
Zone 14
2-Main Gallery
2-Gallery
Zone 15
2-Women
2-Men
2-Network
2-West Corridor
2-East Corridor
2-Restroom 204
Zone 16
B-Storage 004
Zone 17
B-Boiler Room
B-Mech 003
B-Mech 006
B-Corridor 005
Zone 18
B-Collection Storage 001
B-Storage 002
04/05/2004
04:33AM
Mult.
1
1
1
1
1
1
Cooling
Sensible
(MBH)
0.2
0.4
0.3
3.7
0.4
5.7
Time
of
Load
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Jan 1700
Air
Flow
(CFM)
9
21
17
202
22
317
Heating
Load
(MBH)
0.0
0.0
0.0
0.0
0.0
0.0
Floor
Area
(ft)
60.0
110.0
100.0
300.0
60.0
275.0
Space
CFM/ft
0.14
0.19
0.17
0.67
0.37
1.15
1
1
1
1
2.2
5.5
3.6
6.2
Jul 1700
Jul 1700
Jul 1700
Jul 1700
124
304
198
343
0.3
0.7
0.5
0.7
165.0
385.0
305.0
400.0
0.75
0.79
0.65
0.86
1
4
1
1.9
2.5
3.9
Jul 1700
Jun 1700
Jun 1700
108
138
215
0.3
1.3
2.8
180.0
110.0
170.0
0.60
1.26
1.27
1
8
6.7
3.4
Sep 1200
Aug 1600
368
185
2.8
1.3
165.0
110.0
2.23
1.68
1
1
22.4
9.6
Jul 1700
Jul 1700
1235
531
7.2
6.4
2510.0
960.0
0.49
0.55
1
1
1
1
1
1
0.4
0.4
0.4
4.6
5.4
0.4
Jul 1600
Jul 1600
Jul 1700
Jul 1600
Jul 1700
Jul 1700
20
20
20
255
297
20
0.1
0.1
0.0
1.6
1.6
0.1
65.0
65.0
25.0
900.0
865.0
40.0
0.31
0.31
0.80
0.28
0.34
0.49
6.6
Aug 1700
540
16.0
2700.0
0.20
1
1
1
1
0.2
1.3
3.4
1.7
Jan 1700
Jan 1700
Aug 1700
Aug 1700
15
80
312
102
0.6
2.5
11.9
1.7
90.0
785.0
890.0
550.0
0.17
0.10
0.35
0.19
1
1
14.2
1.4
Jan 1700
Jan 1700
975
120
3.8
0.0
1500.0
600.0
0.65
0.20
Page 3 of 3
04/05/2004
04:43AM
Component
Air System Fans
Cooling
4,918
Heating
2,029
Pumps
48
0
15,261
13,588
Electric Equipment
Misc. Electric
704
2,929
Non-HVAC Sub-Total
17,221
Grand Total
32,482
0.177
Heating
0.073
Pumps
0.002
0.000
HVAC Sub-Total
0.549
Lights
0.489
Electric Equipment
0.025
Misc. Electric
0.105
0.000
Non-HVAC Sub-Total
Grand Total
Gross Floor Area (ft)
0.620
1.169
27790.0
15.1
Heating
6.2
Pumps
0.1
0.0
HVAC Sub-Total
Lights
47.0
41.8
Electric Equipment
2.2
Misc. Electric
9.0
0.0
Non-HVAC Sub-Total
53.0
Grand Total
100.0
Page 1 of 1
04/05/2004
04:43AM
Component
HVAC Components
Electric
13,233
Natural Gas
2,028
Fuel Oil
Propane
Remote HW
Remote Steam
Remote CW
HVAC Sub-Total
15,261
Non-HVAC Components
Electric
17,221
Natural Gas
Fuel Oil
Propane
Remote HW
Remote Steam
Non-HVAC Sub-Total
17,221
Grand Total
32,482
HVAC Components
Electric (kWh)
178,345
2,180
0
19
Remote HW (na)
Remote CW (na)
Non-HVAC Components
Electric (kWh)
231,726
Propane (Therm)
Remote HW (na)
Totals
Electric (kWh)
Natural Gas (Therm)
Fuel Oil (na)
410,071
2,180
0
Propane (Therm)
19
Remote HW (na)
Remote CW (na)
Page 1 of 3
04/05/2004
04:43AM
SO2 (kg)
NOx (kg)
0.476
Natural Gas
0.073
Fuel Oil
0.000
Propane
0.000
Remote HW
0.000
Remote Steam
0.000
Remote CW
0.000
HVAC Sub-Total
0.549
Non-HVAC Components
Electric
0.620
Natural Gas
0.000
Fuel Oil
0.000
Propane
0.000
Remote HW
0.000
Remote Steam
0.000
Non-HVAC Sub-Total
0.620
Grand Total
1.169
27790.0
Page 2 of 3
04/05/2004
04:43AM
40.7
6.2
Fuel Oil
0.0
Propane
0.0
Remote HW
0.0
Remote Steam
0.0
Remote CW
0.0
HVAC Sub-Total
Non-HVAC Components
Electric
47.0
53.0
Natural Gas
0.0
Fuel Oil
0.0
Propane
0.0
Remote HW
0.0
Remote Steam
0.0
Non-HVAC Sub-Total
53.0
Grand Total
100.0
Page 3 of 3
04/05/2004
04:43AM
41.8% Lights
Cooling 15.1%
Heating 6.2%
Pumps 0.1%
1. Annual Costs
Annual Cost
($)
8,267
($/ft)
0.298
Percent of Total
(%)
25.4
Cooling
4,918
0.177
15.1
Heating
2,029
0.073
6.2
Component
Air System Fans
Pumps
Cooling Tower Fans
HVAC Sub-Total
Lights
Electric Equipment
48
0.002
0.1
0.000
0.0
15,261
0.549
47.0
13,588
0.489
41.8
704
0.025
2.2
2,929
0.105
9.0
0.000
0.0
17,221
0.620
53.0
Grand Total
32,482
1.169
Note: Cost per unit floor area is based on the gross building floor area.
100.0
Misc. Electric
Misc. Fuel Use
Non-HVAC Sub-Total
Page 1 of 1
04/05/2004
04:43AM
Load
(kBTU)
929,407
(kBTU/ft)
33.444
403,459
14.518
1,332,866
47.962
Site Energy
(kBTU/ft)
13.661
Source Energy
(kBTU)
1,355,832
Source Energy
(kBTU/ft)
48.789
8.157
809,583
29.132
Grand Total
Cooling
226,683
Heating
219,948
7.915
219,965
7.915
2,189
0.079
7,819
0.281
Pumps
Cooling Towers
0.000
0.000
828,453
29.811
2,393,198
86.117
623,869
22.449
2,228,104
80.176
32,328
1.163
115,459
4.155
134,454
4.838
480,191
17.279
0.000
0.000
Non-HVAC Sub-Total
790,651
28.451
2,823,754
101.610
Grand Total
1,619,104
58.262
5,216,952
187.728
HVAC Sub-Total
Lights
Electric Equipment
Misc. Electric
Misc. Fuel Use
Notes:
1. 'Cooling Coil Loads' is the sum of all air system cooling coil loads.
2. 'Heating Coil Loads' is the sum of all air system heating coil loads.
3. Site Energy is the actual energy consumed.
4. Source Energy is the site energy divided by the electric generating efficiency (28.0%).
5. Source Energy for fuels equals the site energy value.
6. Energy per unit floor area is based on the gross building floor area.
Gross Floor Area ............................................ 27790.0 ft
Conditioned Floor Area .................................. 27790.0 ft
Page 1 of 1
04/05/2004
04:43AM
Load
(kBTU)
929,407
(kBTU/ft)
33.444
403,459
14.518
1,332,866
47.962
Site Energy
(kBTU/ft)
Source Energy
(kBTU)
Source Energy
(kBTU/ft)
21.897
2,173,259
78.203
Grand Total
HVAC Components
Electric
608,513
Natural Gas
218,020
7.845
218,020
7.845
0.000
0.000
1,921
0.069
1,921
0.069
0.000
0.000
Fuel Oil
Propane
Remote Hot Water
Remote Steam
0.000
0.000
0.000
0.000
828,454
29.811
2,393,201
86.117
HVAC Sub-Total
Non-HVAC Components
Electric
790,649
28.451
2,823,747
101.610
Natural Gas
0.000
0.000
Fuel Oil
0.000
0.000
Propane
0.000
0.000
0.000
0.000
Remote Steam
0.000
0.000
Non-HVAC Sub-Total
790,649
28.451
2,823,747
101.610
Grand Total
1,619,103
58.262
5,216,947
187.728
Notes:
1. 'Cooling Coil Loads' is the sum of all air system cooling coil loads.
2. 'Heating Coil Loads' is the sum of all air system heating coil loads.
3. Site Energy is the actual energy consumed.
4. Source Energy is the site energy divided by the electric generating efficiency (28.0%).
5. Source Energy for fuels equals the site energy value.
6. Energy per unit floor area is based on the gross building floor area.
Gross Floor Area ............................................ 27790.0 ft
Conditioned Floor Area .................................. 27790.0 ft
Page 1 of 1
Appendix B
Structural:
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Calculations
Jarod F. Stanton
Mechanical Option
Structural Detail
Jarod F. Stanton
Mechanical Option