Anda di halaman 1dari 44

Power Systems Engineering

Research Center (PSERC )

An NSF Industry / University


Cooperative Research Center

PSERC
1

Mission

PSERC

Universities working with industry and


government to find innovative
solutions to challenges facing a
restructured electric power industry.
Multi-disciplinary (engineering,
economics, operations research, etc.)
Multi-university
Collaborative
Research and education activities

PSERC Universities

PSERC

Cornell University (lead university)


Arizona State University
University of California at Berkeley
Carnegie Mellon University
Colorado School of Mines
Georgia Institute of Technology
The University Of Illinois at Urbana
Iowa State University
Texas A&M University
Washington State University
University of Wisconsin-Madison
3

Research Program

PSERC

Three research stems


Markets
Transmission and distribution technologies
Systems

Leveraged research (such as Consortium


for Electric Reliability Technology
Solutions)
Public documents: www.pserc.wisc.edu

Electric Service Reliability

Fernando L. Alvarado
Professor, University of Wisconsin
Invited Presentation
43rd NARUC Program
East Lansing, Michigan, August 15, 2001

Outline

PSERC

Traditional reliability concepts


LOLP
n-1 security
Reserve margins

Reliability in a market context


The Value Of Lost Load (VOLL)

Some market power issues


6

Traditional reliability concepts


Loss of load probability (LOLP)
Expected Demand Not Served (EDNS)

n-1 security
Reserve margins

Electric service reliability

PSERC

End-user perspective:

Any involuntary loss of power is a


reliability event

Bulk system perspective:

Any system condition leading to loss of


load is a reliability event

Only those leading to widespread or extended


outages are considered true reliability events
The outage of a component is not an event
8

Reliability Time Frames

PSERC

The planning time frame


The operations time frame
Reliability in this timeframe is sometimes
called security
In this talk we will emphasize the
operations time frame

Loss of load probability

PSERC

A planning concept
Based on random outage of generators,
what is the probability that the available
generators will be insufficient to meet
the anticipated load
Measured in frequency of expected outages

EDNS extends the concept to


consider energy not served
10

The n-1 security criterion

PSERC

The outage of any single piece of


equipment shall not result in an
uncontrolled loss of load
A pretty universal and fundamental way
of operating the system
Cost in not in the equation

Sometimes n-2 and n-3 criteria are


used
11

Applying the n-1 criterion

PSERC

Outage of any generator does not


cause overloads or other problems

n-1 criterion used to establish reserve


requirements

Outage of any line or transformer


should not cause any other overloads

If a potential problem exists, system is


redispatched for security reasons
(either via CED, via TLR, or via prices)
12

Why do systems fail?

PSERC

Cascading overloads

A simple line or transformer outage is


not enough except in radial situations
Most distribution systems are radial

Loss of system stability


Transient or dynamic

Voltage collapse
Insufficiency of generation
13

Reserves

PSERC

The loss of any generator shall not


cause an uncontrolled loss of load
The area control error (ACE) must
be brought under control
NERC has well-defined rules for this
At present the rules are voluntary

14

What is the ACE?

PSERC

To facilitate control, the power


system is divided into control areas

All exports and imports are monitored


Every area balances its energy to attain
the desired exports or imports
It also contributes to frequency control

The ACE is the deviation between the


intended frequency+exports and the
actual values
15

More on reserves

PSERC

Reserves may have to be locational


They must consider time of response
Reserves are often classified this way

Sustainability attribute of reserves


has been underconsidered to date
The cost of procuring reserves can be
quite important
Reactive reserves are important
16

Reserve margins

PSERC

How far are we from a failure under


normal conditions
And how about under contingency
conditions

A contingency is the loss of a component

You must also ask in what direction

How far is the nearest gas station is different


from how far is the next gas station
Often the direction is total system load

17

Choosing reserve margins

PSERC

Depends on largest credible event


Sometimes the probability of a
triggered event is factored in
Play it more conservative during bad
weather

Margins often expressed in terms of


size of largest generator or loss of
biggest import
18

Temporal classification

PSERC

Spinning reserves
Fast-responding, usually instantaneously

Supplemental reserves
You can bring resources on-line quickly

Backup reserves
They can be brought on line after some
time

19

Reliability in a market context


Reliability event occurs when demand
exceeds supply
The supply and demand curves do not
intersect!

10

What is reliability anyway? PSERC


The CAISO just disconnected you as
a result of insufficient reserves
This is an example of a reliability event

You had vountarily signed up for an


interruptible program and got cut off
This is not a reliability event

21

Economics 101
PSERC
Price

Demand function
(value of electricity
to customers)
Consumer
surplus

Total consumer
surplus (area)

Price

Equilibrium

Quantity

11

Economics 101
Price

PSERC
Production function
(cost of electricity
to producers)
Price
Producer
surplus
Equilibrium
Total producer
surplus (area)
Quantity

Economics 102
Price

PSERC
Total consumer
surplus (area)

Price

Equilibrium
Total producer
surplus (area)
Quantity

12

Some realities

PSERC

Demand function is closer to vertical


Supply function tends to have steps
Supply function does not extend to
infinity

25

A market problem
Price

PSERC

Price

No Equilibrium?

Quantity

13

A market failure
Price

PSERC

Inelastic
demand

No Equilibrium

Quantity

Reliability & market failure PSERC


Market failure Reliability event
Reliability event Market failure?
Certain reliability events are not the
result of market failure
There must have been a market in the first
place
28

14

Assumptions

PSERC

Exactly two technologies


Each technology has a known price

No market power
Inelastic demand

29

Deterministic Demand and Supply, low demand case

Available supply

Quantity (power)

Demand (inelastic)

Price

Security Margin

Maximum
available
power

Clearing
price

15

Deterministic Demand and Supply, high demand case

Available supply

Demand (inelastic)

Price

Clearing
price

Maximum
available
power

Quantity (power)

Unfeasible case, no demand elasticity

No intersection

16

The effect of demand elasticity


Demand elasticity makes case feasible

Greater elasticity does not help


much more (price is still high)

Interruptible demand

Interruptible demand also helps

17

Probabilistic Demand, high demand case

Probability of low prices

Outage
probability

Generator 6

Generator 5

Generator 4

Generator 3

Generator 2

Generator 1

The piece-wise nature of the supply curve

18

The effect of a generator outage

Outaged
generator

Old
supply
limit
New
supply
limit

Effect of demand uncertainty


and generator outage

Probability
p2

Probability p1
n-1 secure

insecure

Outage probability is p1*p2

19

Generator 1A
Generator 2A

Generator 5A
Generator 6A

System A

Generator 4A

Low price
Secure

System A

Low price
n-1 secure

Generator 3A

Generator 1B

Generator 4B
Generator 5B

System B

Generator 3B

High price
n-1 insecure

High price
n-1 secure

System B

Generator 2B

20

Flow

System A

System B
Low price
n-1 secure

Low price
n-1 secure

Temptation: construct a composite supply curve


unnecessary
Low price
n-1 secure

21

Situation with line transmission limits

System A

Max
flow
Flow

System B
Low price
n-1 insecure

Low price
n-1 secure
Outaged
generator

Normal conditions
Max
flow

Unable
to clear

Use of distributed reserves

System A
Low price
n-1 secure

Max
flow
Flow

System B
Low price
n-1 secure

22

Reality

Many flowgates
Networked sysyem
Demand can be elastic
Time delays important
Generators have fixed
(investment) costs and
restrictions
Load is uncertain

PSERC

Transmission outages
exacerbate problems
If one firm dominates
a technology, market
power occurs (next)
If one firm dominates
a location, market
power results

45

The effect of congestion


Price

PSERC
Total consumer
surplus (area)
Equilibrium
point
Equilibrium
region

Total producer
surplus (area)

Price

Congestion
level

Surplus
net loss
Quantity

23

Who gets what


PSERC
Price

Producer
surplus
loss

Producer
surplus
gain

Price

Congestion
level

Quantity

Who gets what, part II


Price

Only under monopsony or regulated conditions PSERC

Price

Consumer
surplus gain

Congestion
level

Quantity

24

Price

The incentive to congest


Producer
surplus
gain

Producer
surplus
loss

PSERC

Gain: p*C
Loss: C*p

Price
p

Congestion
level

Quantity

Equilibrium with congestion


Price

Gain: p*C
Loss: C*p

Price
p

Equilibrium when:
p*C = C*p, or
p/ C=p/C
Quantity

25

The effect of congestion

PSERC

Congestion creates gaming


opportunities

Producers have an incentive to congest


(Up to a point)

The only unambiguous way to


characterize the effect of congestion
is to look at net surplus loss

Translated: when we compute congestion


costs, we do not care who incurs them

Additional remarks

PSERC

Two-technology suppliers can lead to higher


than marginal prices as the knee of the
supply curve is approached
Larger number of suppliers reduces this
effect
Market power studies should consider
investment recovery issues
Transmission congestion makes matters
worse!!
52

26

Features of the example

PSERC

Only two areas (one flowgate)


Radial
Demand is inelastic
Time delays are not an issue
Generators have no startup/shutdown
costs or restrictions or minimum
power levels
53

Observations

PSERC

Demand elasticity is important


Locational aspects of reserves matter
LMP for reserves

Ramping rates matter


In deregulated markets only units explicitly
committed to reserves are available
In regulated markets and in PJM all units are

Reliability requires that we increase supply


Standby charges tend to reduce supply (Tim
Mount)

54

27

Reliability and price spikes*PSERC


What has happened in California?

Price caps have come down


Average prices have increased
Price volatility has decreased
There have been involuntary curtailments

(*) Some of this material comes from Tim Mount at Cornell


55

PJM daily average on-peak spot price and max load

$/MWh

MW

800.00
78000

Price
Maxload

600.00

70000
400.00
62000
200.00
54000
0.00
46000
-200.00
38000

-400.00

30000

-600.00

-800.00
4/97

22000
6/97

8/97 10/97 12/97 2/98

4/98

6/98

8/98 10/98 12/98 2/99

4/99

6/99

8/99 10/99 12/99 2/00

4/00

date

28

Assorted PJM offer curves

PJM Offer Curves at 5pm from April to August (last Tuesday)


Offer Price

1200
1000
800
600
400
200
0
0

April (4/27/99) : $29.4/MWh 28.2GW/h

10

20

10

20

10

20

Offer Price

1200
1000
800
600
400
200
0
0

50

60

70

30

40

50

60

70

30

40

50

60

70

50

60

70

50

60

70

July (7/27/99) : $935.0/MWh 49.2GW

10

20

30

40

August (8/24/99) : $33.7/MWh 38.5GW

Offer Price

1200
1000
800
600
400
200
0

40

June (6/29/99) : $59.5/MWh 48.1GW

Offer Price

1200
1000
800
600
400
200
0

30

May (5/25/99) : $25.9/MWh 30.3GW/h

Offer Price

1200
1000
800
600
400
200
0

10

20

30

40

29

Observations

PSERC

Price spikes have developed not so much


under high load conditions as under tight
reserve conditions
For suppliers that own more than one
technology, there are strong incentives to
withhold capacity
There is a strong connection between
reserves and reliability (and market power)

59

Market Power?
The ability to raise
prices significantly
above the efficient
economic equilibrium

Disclaimer: the slides


that follow are not
really a market power
study but rather they
represent a simplified
illustration of how
higher prices could
result as a result of
market concentration.

30

Market Power: Assumptions


There are exactly two technologies

Each technology has a fixed marginal price


availability of the expensive technology
Limited availability of the cheap technology
Cheap technology has fixed costs (investments) to recover

Demand is inelastic
All suppliers but a schedule all their cheap power
a owns P MW in n1 equal-sized generators

Supplier a can withhold one or more generators


Bidding above marginal cost is not allowed, withholding is

If generators bid marginal price,


the generators surplus is zero

Supplier a generator 1

Demand

Supplier a generator 2

Other suppliers

The piece-wise nature of the supply curve revisited

Clearing
price

31

Red generator decides to withhold one generator

Surplus for
red supplier

Surplus for
blue supplier

Clearing
price

Red supplier now


has large surplus

Withheld
generator

Of course blue supplier


has even LARGER surplus!

If margins are increased


Question: and how are the
expensive technology units
supposed to recover their
investment if they always
clear at their marginal cost?

Now it is not possible for red


supplier to withhold and gain

Answer: you may end


up with less capacity
than you thought

Raising prices
would require
collusion

Clearing
price

32

Probability p that
withholding will
result in surplus

Price

If demand is uncertain

P1
price 1
Quantity (power)
The expected surplus
gain is: p*(2-1)*P1

Since 1 is cheap units marginal


cost, there is no expected surplus loss

Additional observations

PSERC

If the margin to the knee is Pm, any


supplier with a total ownership above
Pm may profit from withholding
If more than one supplier meets this
conditions, chances are that someone will
withhold

66

33

Effect of granularity
Surplus is P*(2-1) for
demand above this level

With only one


generator, it is
impossible to
withhold and
benefit P

For two generators, surplus


is P*(2-1)/2 for demand
above this level

Effect of granularity, three generator case

Surplus is P*(2-1)/3 for


demand above this level

Surplus is 2P*(2-1)/3 for


demand above this level

34

With n=1, there is no surplus

Surplus

Effect of granularity

Surplus with n=2


Surplus with n=3
Surplus with n=4

Demand level
Surplus with n

Observations and assumptions


For worst case effect, assume n=

Assume withholding will occur


Withholding softens the supply curve

High cost periods needed for investment


recovery
Demand is probabilistic
Suggestion: market power occurs if expected
surplus far exceeds investment recovery
This is also a signal for system expansion

35

ers
10 suppli

On

lier
p
p
u
es

su
pp
lie
rs
3s
u pp
lier
s

Price

Effect of number of suppliers on supply curve

Demand

Effect of demand uncertainty on investment recovery

Price

Period during which


investment recovery
can take place

Withholding increases the period during


which surplus accrues but reduces the
amount that accrues

Demand

36

Price

The effect of demand uncertainty on investment recovery

Period during which


investment recovery
can take place

Demand

Numerical studies

PSERC

Demand is 60/70/80/90/95% of knee


for demand varies from 0 to 20%
Demand probability function is normal
Supplier has equal size units available
There are 3/6/10/15/
suppliers
We illustrate the investments that can be recovered
for each of the case combinations above according
to our earlier withholding assumptions
74

37

Investment recovery without market power ( suppliers)

Thousands per year per MW

250

99%

200

Demand level as a percentage


of available capacity

150

95%
100

90%
50

80%
0
0

0.02

0.04

0.06

0.08

0.1

0.12

0.14

0.16

0.18

0.2

Variance of demand (per unit)

suppliers, demand level as a parameter

Investment recovery (thousands per MW-year)

200
60%
70%
80%
90%
95%

180

160

140

120

Even for high


demand levels, some
demand variance
is essential for
cost recovery

100

80

60

40

20

0
0

10

12

14

16

18

20

Demand Variance (percent)

38

15 suppliers, demand level as a parameter


Investment recovery (thousands per MW-year)

250

200

For high enough demand levels


cost recovery is possible
even without demand
variance

150

60%
70%
80%
90%
95%

100

50

0
0

10

12

14

16

18

20

18

20

Demand Variance (percent)

10 suppliers, demand level as a parameter


Investment recovery (thousands per MW-year)

300

250

For high demand levels


demand variance can become
irrelevant

200

150
60%
70%
80%
90%
95%

100

50

0
0

10

12

14

16

Demand Variance (percent)

39

6 suppliers, demand level as a parameter


Investment recovery (thousands per MW-year)

400

350

300

250

200
60%
70%
80%
90%
95%

For low demand levels it is


very difficult to recover
investments

150

100

50

0
0

10

12

14

16

18

20

Demand Variance (percent)

4 suppliers, demand level as a parameter


Investment recovery (thousands per MW-year)

450

400

350

300

For high demand levels, high variance


can even be slightly detrimental to profits

250

200

60%
70%
80%
90%
95%

150

100

50

0
0

10

12

14

16

18

20

Demand Variance (percent)

40

3 suppliers, demand level as a parameter


Investment recovery (thousands per MW-year)

450

400

350
60%
70%
80%
90%
95%

300

250

200

With three or less suppliers, it becomes feasible


at high variances to recover investments by
withholding at low demand

150

100

50

0
0

10

12

14

16

18

20

18

20

Demand Variance (percent)

Demand level 60%, number of suppliers as a parameter


50

Investment recovery (thousands per MW-year)

suppliers
15 suppliers
10 suppliers
6 suppliers
4 suppliers
3 suppliers

45

40

35

30

25

At low demand and low


variance it is impossible
to recover investments

20

15

10

0
0

10

12

14

16

Demand Variance (percent)

41

Dem and lev e l 70% , num ber of suppliers as a param e ter


120

Fixed cost recovery (thousands per MW-year)

s upplie rs
15 s upplie rs
10 s upplie rs
6 s upplie rs
4 s upplie rs
3 s upplie rs

100

80

60

At higher demand with 3 suppliers


it is possible to recover
costs at low variance

40

20

0
0

10

12

14

16

18

20

De m and Variance (pe rce nt)

Dem and lev e l 90% , num ber of suppliers as a param e ter

Fixed cost recovery (thousands per MW-year)

400

350

300

As demand increases, withholding becomes


profitable even when there are many suppliers

250

200

s upplie rs
15 s upplie rs
10 s upplie rs
6 s upplie rs
4 s upplie rs
3 s upplie rs

150

100

50

0
0

10

12

14

16

18

20

De m and Variance (pe rce nt)

42

Dem and lev e l 95% , num ber of suppliers as a param e ter

Fixed cost recovery (thousands per MW-year)

450

400

350

300

250

200

150

100

s upplie rs

Only in the case


of infinite suppliers is it
impossible to recover costs

50

0
0

10

12

14

15 s upplie rs
10 s upplie rs
6 s upplie rs
4 s upplie rs
3 s upplie rs
16

18

20

De m and Variance (pe rce nt)

Comments on numerical results


The number of suppliers has a strong influence on
investment recovery
Below a certain number of suppliers, investment
recovery by withholding becomes easier

There are demand thresholds beyond which there


is a jump in the ability to recover investments
All studies have assumed that supplier adjusts
withholding after learning the demand
Demand variance affects reliability
It also influences the ability to recover investments

43

Final remarks

PSERC

Reliability not decoupled from economics


Tight reliability precursor to price spikes

The structure of two-technology suppliers


can lead to higher prices as the knee of
the supply curve is approached
More suppliers reduce this effect

Market power studies should consider


investment recovery, locational effects
Congestion, loop flows, voltage, frequency
are also important
87

Reliability

Reserves
Price spikes

44

Anda mungkin juga menyukai