2016
E/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
Nov. 2016
ELECTRICAL REVIEW
The reviewer should be thoroughly familiar with the following standards before conducting a
design review.
1. NFPA 101
2.
NFPA 70
3.
NFPA 72
4.
BS 7671
5.
QCS 2014
6.
KAHRAMAA REGULATIONS
7.
OOREDOO REGULATIONS
8.
QCDD REGULATIONS
Nov. 2016
E/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
SCHEMATICS
ELECTRICAL REVIEW
NO.
1
COMMENTS/
YES/NO/NA
ITEM
POWER
a. MV room, TX room and LV room architecture
b. Generator room spacing
c. Surge protection on each LVP
d. Protection and cabling sizes on each LVP
e. REF relay on each LVP
f. Under voltage relay on each LVP
g. kWh meter on each LVP
h. Interface with power factor corrector from each LVP
i. Verification of voltage drop on each outgoing
j. Coordinate drawings with other technical and architectural
disciplines
k. Socket circuits shall be ring with 30mA ELCB protection
LIGHTING
a. Circuits shall not exceed 1800W
b. 30mA ELCB protection for lighting in wet areas
c. Ballasts shall be electronic
d. Follow Kahramaa tarsheed requirements
FIRE ALARM
a. Coverage above false ceiling
b. Coverage in case of drop greater than 460mm
c. Smoked detection to be spaced at least 910mm from air grills
d.
Nov. 2016
E/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
SCHEMATICS
ELECTRICAL REVIEW
NO.
3
4
COMMENTS/
YES/NO/NA
ITEM
Compliance with Kahramaa Regulations
Nov. 2016
E/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
DESIGN DEVELOPMENT
ELECTRICAL REVIEW
COMMENTS/
YES/NO/NA
NO.
ITEM
All electrical rooms, transformer vaults and closets shall not be located
directly below showers, laboratories, kitchens, dishwashing areas or
other areas where water service is provided. Pipe containing liquids or
gases shall not pass through these rooms. See Physical Security Design
Manual.
Compliance To NEC
a. Requirements for Essential Electrical system distribution follow
NEC 517-30/517-40
b. Receptacles, mounting heights as required in different areas (see
Electrical Design Manual)
c. Raceways required in Fluoroscopic, Radiographic and Deep
Therapy rooms (see Electrical Design Manual).
d. Raceway systems as required in Electrical Design Manual.
(1) All wiring shall be installed in raceways.
(2) Underground raceways shall be encased in concrete.
Alarms: Nonflammable medical gas and medical- surgical vacuum
systems. See NFPA 99.
a. Master alarm panels required at the telephone switchboard and
engineering control center or boiler plant.
b. Area alarms provided at nurses stations where medical gas
systems are installed.
Nov. 2016
E/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
DESIGN DEVELOPMENT
ELECTRICAL REVIEW
COMMENTS/
YES/NO/NA
NO.
ITEM
5
6
7
8
Nov. 2016
A/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
CONSTRUCTION DOCUMENTS
ELECTRICAL REVIEW
COMMENTS/
YES/NO/NA
NO.
ITEM
2
3
4
6
7
Nov. 2016
E/E CHECKLIST
TITLE________________________________PROJECT NO.________________
LOCATION___________________________________DATE________________
REVIEWED BY_____________________________________________________
ORGANIZATION___________________________________________________
CONSTRUCTION DOCUMENTS
ELECTRICAL REVIEW
NO.
9
10
11
COMMENTS/
YES/NO/NA
ITEM
Fire Alarm Systems: See Fire Protection Design Manual
Coordinate drawings with other technical disciplines
Compliance with VA National CAD Standard Application Guide and
applicable National CAD Standard modules