Learning Objectives
Our Menu
Introduction.
Pre Construction Activities.
Construction Activities.
A 3D Industry
Construction industry is a 3D
industry:
- D Difficult.
- D Dangerous.
- D Dirty.
The Scenario
The Statistic
Reported Construction Accidents for the Year 2006
(SOCSO)
CATEGORY
Reported
Cases
Reported
Disability
Reported
Fatality
Reported
Cases
Reported
Disability
Reported
Fatality
General contractors
including civil engineers
2,930
436
43
2,714
216
403
33
40
756
107
21
676
80
97
10
21
Total
3,686
543
64
3,390
296
500
43
61
It is Not a 3D Industry
Contributing Factors
The Victims
The Victims
The Victims
The Victims
The Victims
The Victims
Accident Causation
Basic/Root
Causes
Unsafe Acts
Direct Causes
Lack of
Management Control
Unplanned
Released of
Energy and/or
Hazardous Material
ACCIDENT
Personal Injury
Property Damage
Unsafe Conditions
Considerations
Kos
Introduction
CONSTRUCTION
PROJECT
TENDER
EVALUATION &
SELECTION
PRE-TENDER
STAGE
COMPLETION
OF PROJECT
CLOSED OUT
CONTRACT
MANAGEMENT
TENDER STAGE
Pre-Tender
PRE-TENDER
STAGE
Design Stage
Design Considerations:
- OSH during construction.
- Safety and health of end user.
TENDERING
Preparation of
Tender
Document
Contract
Signing
Commencement
of Work
Selection Criteria:
- Experience.
Award
- Technical Capabilities.
- Financial Capabilities.
- OSH Competencies & Records.
Administrative Matters
Prior to Commencement of
Work
Preliminary HIRARC
OSH MS
Documentation
Organisational
Structure
Statutory Notification
Execution of Work
Construction Activities
Introduction
The site environment - a dangerous mix:
- Temporary duration.
- Constantly changing.
- Many trade/sub-contractors.
- Long working hours.
- Time and cost constraint.
- Exposure to weather.
- Dangerous plant and equipment.
Introduction
Execution of
Work
M&E Installation
Sub-Structures
Finishing
Closed Out
Super Structures
Testing &
Commissioning
Introduction
Hazard:
- Anything that have the potential to cause harm.
To ensure work activities being carried out safely and
healthily, potential hazards need to be idenditified,
assesed and controlled.
Continual Improvement
HIRARC
HI
Hazard
Identification
RA
Risk
Assessment
RC
Risk Control
Hazard Identification
Hazard Identification
Risk Assessment
Severity (S)
Likelihood
(L)
Negligible
(1)
Minor
(2)
Serious
(3)
Fatal
(4)
Catastrophic
(5)
Most Likely
(5)
10
15
20
25
Possible
(4)
12
16
20
Conceivable
(3)
12
15
Remote
(2)
10
Inconceivable
(1)
Risk Assessment
Risk Factor
Action Level
A HIGH risk requires immediate action to control the hazard as detailed
in the hierarchy of control.
15 - 20
High
Actions taken must be documented on the risk assessment form
including date for completion.
A MEDIUM risk requires a planned approach to controlling the hazard
and applies temporary measure if required.
5 - 12
Medium
Actions taken must be documented on the risk assessment form
including date for completion.
A risk identified as LOW may be considered as acceptable and further
reduction may not be necessary.
1-4
Low
However, if the risk can be resolved quickly and efficiently, control
measures should be implemented and recorded.
Hierarchy of Control
Hazard
Yes
Eliminate
No
Substitute
Isolate/Engineering
Administrative
PPE
Define policy.
Establish and implement safe work procedures.
Establish and implement permit-to-work system where
appropriate.
Conduct training.
Clear instruction and information.
Electrical installation:
- Competent electrician.
- Weather proof distribution boxes.
- Proper layout out of cables and cords.
- Proper connections.
Use of ladders:
- Erected and safe angle and secured.
- Only one person should be on a ladder at any time.
- Maintain 3-points of contact:
use both hands when climbing or descending a ladder
nothing should be carried in hands.
- Always face the ladder when climbing up or down.
types
of
flammable
materials
to
be
stored