ROWAD NATIONAL PLASTIC Co. LTD.

Hail Complex

CONSOLIDATED
PUCH LIST
(BUILDING 2)
Updated

9th November, 2016

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

Electrical switches need to be fixed

ILLUSTRATION

STATUS

REMARKS

PENDING

Cable tray openings need


adjustments

Lights need to be fixed in room, towers


and ground floors

ON-GOING

AC unit frames need adjustments

PENDING

Electrical connections need to be


secured

PENDING

Opening in walls needs to be closed

PENDING

Missing parts in rest rooms

PENDING

COMPLETED

2|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

Office's roofs need to be fixed

ILLUSTRATION

STATUS

REMARKS

NEED FOR
REWORK

Ceiling is
done.
However,
The electrical
tray needs for
adjustment so
that it will not
block the
ceiling.

Doors need adjustment to lock and


emergency doors need fixing

10

Missing A.C. unit in MDB room

PENDING

11

Bus-way openings need to be closed

PENDING

12

Defected wall insulations need


replacements

PENDING

13

Opening around pipes need to be


closed

PENDING

14

3-phase Bus bar must be aligned

PENDING

COMPLETED

3|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

15

AC ducts supports and cable trays


supports need to be aligned

ILLUSTRATION

STATUS

REMARKS

PENDING

16

Bus bar must be away from working


area for safety

COMPLETED

17

Tungsten bulbs needs to be adjusted

PENDING

18

Insulation needs to be cleaned

PENDING

19

Lighting bulb must be installed in tower


floors

ON-GOING

20

Insulation must be fixed around the pipe

PENDING

21

3-phase plug cables are without tray

PENDING

Done by
Rowad
Team

4|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

REMARKS

22

Cable tray not covered and cable should


be single

PENDING

23

Valves should be in the floor not out side

PENDING

24

Opening in the wall need to be closed

PENDING

25

Empty plug should be removed or


covered

PENDING

26

Emergency light is not connected to the


power source

PENDING

27

Shutter doors are not working


automatically + no personnel doors

PENDING

28

Cable tray is not covered

PENDING

5|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

REMARKS

29

Incorrect routing of the cable

PENDING

30

Damage in the building wall

PENDING

31

Cable tray without cover

PENDING

32

Cable penetrating the wall

PENDING

33

Cables are coming from the wall without


any connection

ON-GOING

34

Plug without cover

PENDING

35

Cable trays without cover

PENDING

Done in
one point,
still not
complete

6|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

REMARKS

36

Openings around the bus bar should be


closed

PENDING

37

Cables coming from a damage wall

PENDING

38

Bus bar should be aligned and opening


around it should be closed

PENDING

39

Wooden piece kept in the top of A C


duct

PENDING

40

Cable tray coming from a pipe

PENDING

Emergency door painting not completed


41

42

COMPLETED

Cables are laying down from the tray

PENDING

7|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

BLOWN FILM PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

REMARKS

43

Cable tray cover not fixed properly

PENDING

44

Plugs without cover cable routing is not


correct

PENDING

Openings in the wall must be closed


45

PENDING

SUMMARY OF ANALYSIS:
NUMBER OF COMPLETED ITEMS
NUMBER OF PENDING ITEMS
NUMBER OF ON-GOING ITEMS
NUMBER OF REWORK ITEMS

4
37
3
1

9%
82 %
7%
2%

TOTAL NUMBER FOR PUNCH LIST CONCERN/ITEMS

45

100%

8|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

INJECTION MOULDING PRODUCTION AREA


SR No.

DESCRIPTION

Unwanted fitting materials observed


below the steps.
(Outside office below steps)

ILLUSTRATION

STATUS

REMARKS

COMPLETED

Tube light is not properly fitted.


(Inside office)

ON-GOING

Cable fitment not proper also not cover.


(Office top left corner)

ON-GOING

Pipe insulation materials observed on


shop floor.
(Office left corner on floor)

Nobody remove after work.


(Office top right corner)

COMPLETED

COMPLETED

Some construction material on floor.


(Office top)

ON-GOING

Insulation has damage many places in


shop floor.
(Office Top)

ON-GOING

9|P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

INJECTION MOULDING PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

Empty paint jar and cartoon are on


floor.
(Office Top)

COMPLETED

Electrical wirings are open.


(Office top right corner)

ON-GOING

10

Ladder and open wiring.


(Office front left corner)

COMPLETED

11

Insulation damage need to repair.


(Office front left corner)

ON-GOING

12

Electrical cables are observed.


(Office front on shop floor)

COMPLETED

13

Insulation damage.
(Office top right side middle)

COMPLETED

14

After work wood not remove.


(Office top right side near Penta)

COMPLETED

REMARKS

10 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

INJECTION MOULDING PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

15

After work wood not remove.


(Office top right side near Penta)

COMPLETED

16

After work the thing are not remove


from place.
(Office right side on Shop Floor)

COMPLETED

17

After work the thing are not remove


from place.
(Office right side on Shop Floor)

COMPLETED

18

Hanging internet cable not properly


fitted in cable tray.
(Office right side on shop floor)

COMPLETED

19

Cold water pipe insulation not proper.


(Behind Engle 2300 machine)

COMPLETED

20

After work the thing are not remove


from place.
(Behind Engle 2300 Machine)

COMPLETED

21

Open electrical cable in hanging


position.
(Office front right side)

ON-GOING

REMARKS

11 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

INJECTION MOULDING PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

22

Construction materials are observed on


shop floor.
(Office front right side corner)

COMPLETED

23

Construction materials are observed on


shop floor.
(Office front side)

COMPLETED

24

Electrical cables are open and not


properly fitted in cable tray.
(Office front side)

COMPLETED

25

Earthing cables are open in conditions.


(Behind SFM Machine)

COMPLETED

26

Insulation damage.
(Office front left side)

ON-GOING

27

Electrical cables are opens.


(Office side left corner near electrical
cabinet)

ON-GOING

28

Cable tray is not up to the bottom.


(Middle of Shop Floor)

ON-GOING

REMARKS

12 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

INJECTION MOULDING PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

29

No cable tray as well as horizontal


support
(Middle of Shop Floor)

ON-GOING

30

Cable tray is open.


(Middle of Shop Floor)

ON-GOING

REMARKS

SUMMARY OF ANALYSIS:
NUMBER OF COMPLETED ITEMS
NUMBER OF PENDING ITEMS
NUMBER OF ON-GOING ITEMS
NUMBER OF REWORK ITEMS

18
0
12
0

60 %
0
40 %
0

TOTAL NUMBER FOR PUNCH LIST CONCERN/ITEMS

30

100%

13 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

ROTOMOLDING PRODUCTION AREA


SR No.

DESCRIPTION

Big Hole temporarily covered by


wooden planks

Uncovered cable trays

Cable tray holes needs to be closed

Substandard finishing

Hole but no junction box

Uncovered electrical boxes

ILLUSTRATION

STATUS

REMARKS

ON-GOING

Covered by
MS Plate but
floor
finishing is
not
completed

PENDING

PENDING

PENDING

PENDING

PENDING

Toilet door handle needs fixing


7

PENDING

14 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

ROTOMOLDING PRODUCTION AREA


SR No.

DESCRIPTION

ILLUSTRATION

STATUS

REMARKS

Lights need to be fixed


8

10

PENDING

Left over electrical wires needs to be


removed

AC not working in roto office

COMPLETED

COMPLETED

Holes for cable trays needs fixing


11

ON-GOING

Wall gaps need to be closed


12

PENDING

Need Proper Fitting of Electrical Cable


13

PENDING

No need Wood support at door, Fix it


with proper material
14

PENDING

15 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

ROTOMOLDING PRODUCTION AREA


SR No.

DESCRIPTION

15

Big uncovered tunnel

ILLUSTRATION

STATUS

REMARKS

COMPLETED

SUMMARY OF ANALYSIS:
NUMBER OF COMPLETED ITEMS
NUMBER OF PENDING ITEMS
NUMBER OF ON-GOING ITEMS
NUMBER OF REWORK ITEMS

3
10
2
0

20 %
67 %
13 %
0

TOTAL NUMBER FOR PUNCH LIST CONCERN/ITEMS

15

100%

16 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

RECYCLING AREA
SR No.

DESCRIPTION

Water leakage from roof

ILLUSTRATION

STATUS

REMARKS

PENDING

(1) Office 3 not


completed

AC not working in Office- 3, Office-4 &


office-5

ON-GOING

(2) Office 4
completed
(3) Office 5
completed

Remove Drainage pipe from Electrical


room 2.

PENDING

Remove additional or extra cable from


the back side of NGR machine

PENDING

Do proper sealing on the wall inside


electrical room-2

PENDING

Cover of electrical box not present

PENDING

Need plaster on the roof of electrical


room-1

COMPLETED

17 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

RECYCLING PAREA
SR No.

DESCRIPTION

ILLUSTRATION

STATUS

Remove Door from plant

PENDING

Uncounted cable on the ground

PENDING

10

Missing panel cover of granulator

PENDING

11

Cable laying on the ground

PENDING

12

Improper fixing of cable tray

PENDING

13

Wrong cable termination

PENDING

14

Construction left overs need removing

PENDING

REMARKS

18 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

SUMMARY OF ANALYSIS:
NUMBER OF COMPLETED ITEMS
NUMBER OF PENDING ITEMS
NUMBER OF ON-GOING ITEMS
NUMBER OF REWORK ITEMS

1
12
1
0

7%
86 %
7%
0

TOTAL NUMBER FOR PUNCH LIST CONCERN/ITEMS

14

100%

19 | P a g e o f 2 0

ROWAD NATIONAL PLASTIC Co. LTD.


Hail Complex

CONSOLIDATED PUNCH LIST FOR BUILDING 2

OVER-ALL SUMMARY
STATUS

BLOWN FILM

PLANT AREA
INJECTION ROTOMOLDING

RECYCLING

COMPLETE

9%

60 %

20 %

7%

PENDING

82 %

0%

67 %

86 %

ON-GOING

7%

40 %

13 %

7%

REWORK

2%

0%

0%

0%

TOTAL
PERCENTILE

100 %

100 %

100 %

100 %

Analysis:
Percentage share of Pending Status for Blown Film, Rotomolding and Recycling are too
high. Therefore, it needs to apply proper rectification and course of action to complete
all the points under of said status.