Page 1 of 39
Approver Title
Approver
Role
Jawad Al Hamayel
Business Project
Sponsor
Adel Abdulhadi
VP, EBS
IT/EBS Project
Sponsor
Omar K Al-Belali
GM, GBS
Christo Esterhuizen
GM, GBP
Mansour Siddiqui
Project Manager
Mohammed Khadeer
Head of PMO
PMO
Othman M. Alshaikh
BP SBU Corporate
Business Partner
Signature
Date
Note: The final authority to sign this document is Project Sponsor; other
authorities can be included as per Project need.
Page 2 of 39
&
CHANGE/VERSION HISTORY
Version
No
Version
Date
Change Description
Changed
By
Document/File
Name
1.0
30/03/201
6
Othman
1.1
14/04/201
6
Business
project
sponsor changed from
Ryyan to Saeed
Othman
1.2
17/04/201
6
Changes requested by
PMO
Othman
1.3
19/04/201
6
Changes requested by
PMO
Othman
1.4
21/04/201
6
Mansoor
1.5
26/04/201
6
Procurement Strategy
Major
Project
milestones
and
deliverables
Project Functional and
Technical Teams
Section 3.2.1 added for
Project duration and
risk associated to it.
EBSPMO-003Project Charter
Hail
SAP
Project.docx
EBSPMO-003Project Charter
Hail SAP Project
v1.1.docx
EBSPMO-003Project Charter
Hail SAP Project
v1.2.docx
EBSPMO-003Project Charter
Hail SAP Project
v1.3.docx
EBSPMO-003Project Charter
Hail SAP Project
v1.4.docx
1.6
27/04/201
6
Christo
1.7
01/05/201
6
Othman
1.8
03/05/201
6
Committed changes
Othman
1.9
10/10/201
6
1. General Information
section updated
2. Project Business
team updated
3. Business/Project
sponsor updated
4. Risk Management
section updated
5. Key Contact list
updated
6. Project Functional &
Mansoor
Mansoor
Page 3 of 39
Technical Team
updated
7. Project steering
Committee updated
8. High level Project
Plan updated
CONTENTS
1.
Executive Summary.....................................................................................
1.1
1.2
1.3
1.4
1.5
2.
General Information.....................................................................................
Business Challenges.....................................................................................
Business Objectives......................................................................................
Business Benefit...........................................................................................
Impacted Organisations................................................................................
Project Overview..........................................................................................
2.1
2.2
2.3
2.4
2.5
2.6
2.7
3.
Business Requirement..................................................................................
Background..................................................................................................
Project Scope................................................................................................
Critical Success Factors..............................................................................
Assumptions...............................................................................................
Constraints.................................................................................................
Procurement Strategy.................................................................................
Project Delivery..........................................................................................
3.1
3.2
3.3
3.4
4.
Project Methodology...................................................................................
High-level Project Schedule........................................................................
Major Project Milestones/Deliverable..........................................................
Delivery Strategy (RACI).............................................................................
Project Organization...................................................................................
4.1
4.2
4.3
4.4
4.5
5.
5.1
5.2
6.
Funding Source...........................................................................................
Approved Budget........................................................................................
Organizational Change Management.........................................................
6.1
6.2
7.
Training Strategy........................................................................................
Project Communication Management.........................................................
Risk Management.......................................................................................
8.
Page 4 of 39
1. Executive Summary
1.1
General Information
Project Approved by IT Steering Committee (Circle the
right option)
Project
Project Sponsor
Hail SAP Project
Number
(Business)
Project
APR/2016 TO
Project Sponsor (IT)
Timeline
DEC/2016
Organizational Scope (Tick mark only one option)
SBU Titanium
T&I
SBU
Finance
Petrochemical
(CFO)
Corporate
SBU Downstream
HR
1.2
YES
/ NA
Jawad Al Hamayel
Adel Abdulhadi
Corporate-IT Infra
CorporateProcurement
Corporate-Others
Business Challenges
1.2.1 Totally new company from A to Z
1.2.2 Different plants that vary in operational processes
1.2.3 Financial challenges to reduce the cost
1.2.4 Limited and frequently changing resources
1.2.5 High visibility of the new company
1.2.6 Rowad Business Process and Documentation will be followed for:
Green Films = Rowad International Geosynthetics Co. (Dammam)
Plastic Pallets = Rowad National Plastic Co. (Riyadh)
Plastic Pipes = Rowad National Plastic Co. (Riyadh)
1.2.7 Water Recycling Units is completely new Plant and business
1.2.8 Ramadan work schedule and Eid Holidays
1.3
Business Objectives
1.3.1 To implement SAP ERP at Hail company
1.3.2 Implementation covers 4 plants
1.3.3 To follow Tasnee practices in other sites, particularly Rowads
Page 5 of 39
1.4
Business Benefit
1.4.1 To automate operational processes
1.4.2 Reduce manual work to manage the operations
1.4.3 Generate accurate reports from the ERP system
1.5
Impacted Organisations
This project impacts Hail site with its plants part of the Plastic unit of
downstreams SBU
Page 6 of 39
2. Project Overview
2.1
2.2
Business Requirement
Hail is a green field project which will be part of the Plastic BU. The
objective is to implement SAP in the HAIL operation complex to cover all
operations.
Background
2.2.1 Definitions:
2.3
2.2.1.1
2.2.1.2
2.2.1.3
2.2.1.4
2.2.1.5
BS Business Solutions
Project Scope
2.3.1 Modules in Scope
2.3.1.1 Finance FI / CO / IM (PS) (VIM )
2.3.1.2 Sales and Distribution SD
2.3.1.3 Quality Management QM
2.3.1.4 Procurement - MM
2.3.1.5 Supply Chain WM / LE
2.3.1.6 Production Planning PP
2.3.1.7 Plant Maintenance PM
2.3.1.8 Project System PS(IM)
2.3.1.9 Human Resource HR
2.3.1.10
Page 7 of 39
Process Track
Sub Processes
Page 8 of 39
Record to Report
(R2R)(FICO)
General Ledger
Payables
Payables
Payables
Payables
Payables
Payables
Payables
Payables
Receivables
Receivables
Receivables
Receivables
Receivables
Fixed Assets
Capitalization from Direct Purchases
Capitalization from AUC
Retirement of Assets
Depreciation Run
Revaluation of Assets
Asset Register and Inventory Management
CO Module - High-level Scope
PP / Costing
Order to Cash /
Logistics
execution
(OTC/LE)
Quality
Management
(QM)
Procure to Pay
(PTP)
(MM-LE-WM)
Page 10 of 39
Plan to Make
Return to Vendor
Procurement and Consumption of Consigned Inventory
Procurement on Quota Arrangement
Procurement of Batch-Managed Stock Materials
Procurement of Warehouse-Managed Stock Materials
Procurement of External Services / Sub-Contracting
Quality Management in Procurement
Invoice verification
Inventory management; Physical inventory
Define Message Outputs
Document Workflow (Approval Strategy) and Transmittals
Classification / Purchase Conditions
Follow on Functions
Reporting/Enhancements/LSMW
Data Uploading tools
Approved Manufacturers list and Vendor evaluation
Repairable and refurbishment
Reservation / Goods Movement
Supply Chain- WM High-level Scope
Warehouse Management
Stock Transfer with Delivery
Stock Transfer without Delivery
Physical Inventory / Inventory Count and Adjustment
Supply and Demand Planning
Barcoding for MRO
Tank Trailer Filling
Totes Handling
Vendor Managed Inventory
Reports
Material Master analyze report (created, changes, and
Min/Max)
Goods Receipt report (MIR)
Goods Issue and receive report
Inventory variance report
Material Aging report
Dead stock report
Slow moving report
Non stock report
Monthly and Annual report
Supply Chain-LE High-level Scope
Outbound Logistics
Inbound Logistics
Transportation/TRACKING/WEIGHBRIDGE
Page 11 of 39
(PTM)
Build to Maintain
(BTM)(PM)
Project systems
(PS)
Project Set up
Enter budgets in project
Process charges to a project
Capitalization from AUC
Retirement of Assets
Depreciation Run
Project Reporting
(PP)
Human Capital
Management
(HCM)
Organisational Management
Personnel Management
Payroll
Self-Services
o Business Travel
o Employment Letter
o Housing Advance
o Personal Data Maintenance
Page 12 of 39
o
o
o
o
o
o
o
Document
Management
System (DMS)
2.4
Page 13 of 39
2.5
Assumptions
2.5.1 SAP implementation at Hail will follow Tasnee practices at Rowad sites
2.5.2 Business Process Owners will be made available during the
implementation phases
2.5.3 SAP Project will be funded from the Hail projects budget
2.5.4 Project go-live depends highly on the availability of the above. Any
delay on the above objects will directly impact the total period of the
project
2.5.5 Business Process flow and Documentation will be made available during
implementation phase
2.6
Constraints
2.7
Procurement Strategy
2.7.1 Lump sum Project will award to vendor based on above Section 2.3
Project Scope.
3. Project Delivery
3.1
Project Methodology
Project will be executed as per the IT/EBS PMO Project Management
Methodology. EPM Project Server shall be utilized as the Core Project
Management Tool.
Project Manager shall refer the Project Management Process and Gate
Review Checklist (Quality Check) to comply with the requirements for
successful project delivery.
Below is the snap of the Project Methodology:
Page 14 of 39
3.2
3.3
S.
No.
1
2
P1-Initiation
3
4
P2Preparation
/Requirements
1
2
3
4
5
Deliverable(s)
Produ
cer
Final
Approver
Approved Business
Case Document
Approved Project
Charter
Project Team list
Gate review
checklist
Approved SoW - RFP
Updated Project
Schedule in EPM
Budget Spend Plan
Risks/Issues
management in EPM
Resource
Matrix/engagement
Plan
Page 15 of 39
6
7
Communication Plan
Developed Quality
Plan
Updated Risks/issue
Register in EPM
Approved Business
Blueprint Document
Updated Risk/Issue
Register
Test results
User Acceptance
Testing sign-off
Updated Risk/Issue
Register
Cut-over Plan/Script
Broadcast
information note
Updated Risk/Issue
Register
Lesson learnt
document
Approved project
closure report
8
1
P3-BBP/Design
P4Realization/Buil
d & Test
P5-Final
Preparation/
Deploy
2
1
2
3
1
2
3
1
P6-Golive &
Support
3.4
R-
A-
C-
I-
Responsi
ble
Accountabl
e
Consult
ed
Inform
ed
Project
Phase
Key mile
stones
/Activities
Deliverables
Preparatio
n
Detailed
document
ation and
prioritizati
on of
requireme
nts
Approved
Project
Management
Plans
Vendor
Company
Vendor
Company
Tasnee
Tasnee
Develop
release
plan for
approved
scope
Approved
release
scope
Vendor
Company
Vendor
Company
Tasnee
Tasnee
Data
Migration
Vendor
Company
Vendor
Company
Tasnee
Tasnee
Page 16 of 39
R-
A-
C-
I-
Responsi
ble
Accountabl
e
Consult
ed
Inform
ed
Realization
/Build &
Test
Applicatio
n design
Application
design
documents
Vendor
Company
Vendor
Company
Tasnee
Tasnee
Project
setup
Tasnee Basis
System
Admin
Tasnee
Tasnee
Vendor
Compan
y
Vendor
Compan
y
Conversio
n design
Conversion
design
documents
Vendor
Company
Vendor
Company
Tasnee
Tasnee
Business
process
flows
Updated
Business
process flows
Vendor
Company
, Tasnee
Vendor
Company
Vendor
Compan
y
Vendor
Compan
y
Solution
developm
ent
Configured
system and
documentati
on
Vendor
Company
Vendor
Company
Tasnee
Vendor
Compan
y
Detailed
functional
specification
s
Vendor
Company
Business
Process
Procedures
Vendor
Company
System
configurati
on
Unit
testing of
functional,
technical
and data
conversion
s.
Tasnee
Vendor
Company
Tasnee
Vendor
Compan
y
Tasnee
Vendor
Company
Tasnee
Vendor
Compan
y
Tasnee
Integration
test
Scenarios
/plans
Vendor
Company
Integration
test scripts
creation
Vendor
Company
Vendor
Company
Tasnee
Vendor
Compan
y
Tasnee
Vendor
Company
Vendor
Compan
y
Vendor
Compan
y
Tasnee
Training
requirements
defined
Tasnee
Tasnee
Vendor
Compan
y
Vendor
Compan
y
Tasnee
Page 17 of 39
Integration
testing
- User
Acceptanc
e Testing
R-
A-
C-
I-
Responsi
ble
Accountabl
e
Consult
ed
Inform
ed
Documented
Integration
test results
Vendor
Company
, Tasnee
Vendor
Company
Tasnee,
Vendor
Compan
y
Vendor
Compan
y
Global
signoff
Tasnee
Vendor
Compan
y
Vendor
Compan
y
Tasnee
Vendor
Company
Tasnee
Tasnee
- Defect
Resolution
Test
Results
Vendor
Company
Vendor
Company
Vendor
Compan
y
Vendor
Compan
y
Tasnee
- Data load
Vendor
Company
Vendor
Company
Tasnee
Vendor
Compan
y
Tasnee
Operation
al
readiness
assessmen
t
Final Prep
@
GoLive/De
ploy
Tasnee
Tasnee
Vendor
Compan
y
Vendor
Compan
y
Tasnee
Training
developm
ent and
delivery
Trained
users and
support
personnel
Tasnee,
Vendor
Company
Vendor
Company
Tasnee
Vendor
Compan
y
Train the
Trainer
Train Key
users and
Key support
personnel
Vendor
Company
Tasnee
Tasnee,
Vendor
Compan
y
Vendor
Compan
y
Release
migration
to
production
environme
nt
Businesses
readiness
approval
Tasnee
Tasnee
Vendor
Compan
y
Vendor
Compan
y,
Tasnee
Businesse
s
readiness
assessmen
t
Application
go-live
Vendor
Company
, Tasnee
Tasnee
Vendor
Compan
y
Vendor
Compan
y,
Tasnee
Tasnee
Page 18 of 39
Golive
Support
(Stabilisati
on)
R-
A-
C-
I-
Responsi
ble
Accountabl
e
Consult
ed
Inform
ed
Data
load and
cutover
Completed
cutover
Vendor
Company
, Tasnee
Vendor
Company
Vendor
Compan
y
Vendor
Compan
y,
Tasnee
Finalize
support
organizati
on
Perform
post
implementati
on support,
Tasnee
Tasnee
Vendor
Compan
y
Vendor
Compan
y
Conduct
post
implement
ation
support,
hyper care
Conduct
refresher
training,
Vendor
Company
Vendor
Company
Tasnee
Vendor
Compan
y,
Tasnee
Perform
production
fixes
Vendor
Company
Vendor
Company
Vendor
Compan
y,
Tasnee
Vendor
Compan
y,
Tasnee
4. Project Organization
4.1
4.2
Name
Designation
Role
(Chairman/Member)
Page 19 of 39
1.
Omar Najjar
eVP DS SBU
Chairman
2.
Adel Abdulhadi
VP EBS
Member
3.
Christo Esterhuizen
GM, GBP
Member
4.
Omar Albilali
GM, GBS
Member
Following team members will participate in project as and when required,
communication would be made in advance for their participation and they
will be required to spend max 20% time through the project lifecycle.
4.3
Name
Designation
Mansour Siddiqui
Mahmood Sultan
V Rengarajan
Senthil Andavar
Muniyandi
Alfred K. Kingsley
Mallikarjun Padmasri
Zafar valsal
Ali Taha Al Amin
Arif Bukharee
Muhammad Al Mulla
Hussam A. Almarwani
Sivaprasath
Nagappan
Lokeshwara Pollina
Role
Project Manager
FICO Consultant
PP Consultant
QM Consultant
Chairman
Member
Member
Member
PM Consultant
PS Consultant
MM/WM Consultant
SD Consultant
ABAP Lead
SAP Security team
Workflow Consultant
EP Consultant
Member
Member
Member
Member
Member
Member
Member
Member
HR Consultant
Member
Name
Designation
1.
2.
3.
4.
Majed AlShbnan
Jamal Eghrib
Inventory Management
Inventory Management
5.
Material Management
6.
7.
Mohamad Al
Koudmani
Faisal O. AlShagdali
Tariq Abduwahed
8.
Manuj chudhari
Role
(Chairman/Mem
ber)
Member
Member
(Backup)
Member
Member
(Backup)
Member
Member
Member
Member(Back
Page 20 of 39
9.
Sopan Thengadi
10.
Dixit Kumar
11.
Moamen Osman
12.
Amr Shady
13.
14.
Abdulhameed
Binoy.N.John
Molding
Production Planning
molding /Recycling
Production Planning
molding /Recycling
Production Planning
Film
Production Planning
Film
Production Planning
Production Planning
15.
16.
Ali Z. Sayyed
John PE.
Quality Management
Quality Management
17.
Agnelo Braganza
Quality Management
18.
Mohammed A. Aziz
19.
20.
Samir Abojbara
Ahmed Morsy
Mostafa
Rami Al Hammad
Plant Maintenance/Process
Engg.
Process Engg.
Plant Maintenance
21.
21.
22.
23.
24.
4.4
Mohammed Al
Sayed
AbdulKharim A. Al
Swayegh
Fawaz k. Al Fayez
Abdulquddus
- Roto
- Roto
- Blown
- Blown
- Pipe
- Pipe
up)
Member
Member(Back
up)
Member
Member
(Backup)
Member
Member
(Backup)
Member
Member
(Backup)
Member
(Backup)
Member
Project Systems
Member
Member
(Backup)
Member
(Backup)
Member
Human Resource
Member
Human Resource
Human Resource
Member
Member(Back
up)
Plant Maintenance
Total
1
1
0.5
1
0.5
4
Description
SAP - Support
Service Desk
Operations
IT Infrastructure
IT Security
Page 21 of 39
4.5
Steering
Committee
Responsibilities
1- Meet regularly to review project plan
impact on their departments
2- approve project deliverables
Commitm
ent time
As per High
level
Schedule
3- Resolve issues.
4- Steer the project to completion in an
orderly and progressive manner
5- Review and approve scope changes,
and provide direction and guidance to
the project
Page 22 of 39
Role
Project Sponsor
Responsibilities
1- Be the owner of the project and
promote the project throughout the
organization
Commitm
ent time
As
Needed
Page 23 of 39
Role
Project Manager
Responsibilities
1- Provide advice and strategic direction.
And a single point of Contact with
PMO.
Commitm
ent time
Full time
Page 24 of 39
Role
Project Technical
Lead
Responsibilities
Responsibilities
1- The Project Technical Lead will assist
the Project Manager for accomplishing
the project objectives within the
constraints of the project.
Commitm
ent time
Full
Time
(as
per
Project
schedule)
2- The
Project
Technical
Lead
is
responsible to report status and
provide recommendations on progress
toward
project
management
deliverables.
3- The Project Technical Lead will
represent the company in all internal
and external negotiations.
4- The
Project
Technical
Lead
is
responsible to provide pre-approvals
of necessary documents if necessary
5- The
Project
Technical
Lead
is
responsible for assigning the project
tasks to the team members and will
continuously monitor their timely
closure
6- The Project Technical Lead is a primary
point of contact for Business Users,
Internal and External Consultant.
7- The
Project
Technical
Lead
is
responsible to coordinate for Travel
and Commercial activities of the
Project
8- The Project Technical responsible to
report to Project Manager.
Business Process
Owner
3 hours/day
(as Needed
as
per
project
Schedule)
Page 25 of 39
Role
Commitm
ent time
Responsibilities
group members.
5. Provide sign-off of approvals when
requested.
6. Identify process or technical issues
that would affect the quality and
organizational acceptability of project
deliverables
7. Participate in solution testing activities
(test scenarios / scripts development;
testing) as directed by the Functional
Consultants.
8. Oversee
and
ensure
adequate
resources for data management
activities as directed by the Functional
Consultants
(data
cleansing;
construction and validation).
9. Oversee
resources
grouping.
and
ensure
adequate
for role definition and
10.Oversee
and
resources
for
development.
ensure
training
adequate
material
1. Identify requirements
2. Analyse and document as-is process
and process interfaces.
3. Discover process gaps
4 hours/day
(as Needed
according
to
Schedule)
Page 26 of 39
Role
Commitm
ent time
Responsibilities
and project management
9. Develop
process
standards
evaluate tools as needed.
System
Administrator
and
related
to
the
3- Identify
appropriate
software/hardware components based
on business solutions requirements
Full time
(as needed
for
Support)
Part time
(as Needed
from the
project
schedule)
Page 27 of 39
Role
Responsibilities
Commitm
ent time
As per
Project
Schedule
2- Provide
information
about
their
business objectives and the ways in
which their units operate and respond
to events in order to achieve those
objectives.
3- Describe the problems they face and
requirements for the systems
4- Participate in requirements definition
workshops
5- Participate in business requirements &
GAP analysis Workshops
6- Approves functional specification of
development tasks
7- Aware of the business processes
related to his department and can
recommend
and
approve
improvements.
Document No.: EBSPMO-003
TASNEE
Document Name: Project Charter - Hail SAP Project Version 1.9
Date: 10/10/2016
Page 28 of 39
Role
Commitm
ent time
Responsibilities
8- Review and
solutions
evaluate
alternative
As per
Schedule
Page 29 of 39
Responsibilities
1. Representing the interests of the
Contractor.
Commitm
ent time
n/a
is
the
plan
of
realistic and
Full time
Page 30 of 39
Role
Responsibilities
Commitm
ent time
As per Project
Schedule
architecture
based
on
requirements, application
Page 31 of 39
Role
Commitm
ent time
Responsibilities
and system landscape.
4. recommend improvements in the
existing business processes
5. Map and
indicators
validate
performance
6. Provide
support
during
the
implementation and assist with the
development
of
project
requirements,
scope
and
acceptance testing.
7. Generate business cases and assists
in defining project benefits/costs
and participates in project reviews
Technology
Architect
(Consultant)
1. Implement IT-Process
related IT-components
across
2. Develops
value-based
cases for customers
all
Full time
business
3. Define
detailed
blueprint
development requirements
for
scope
of
technical
to
the
9. Consult
and
mentor
technical
resources
concerning
methods,
procedures, and standards to be
used during design, development,
and unit testing phases of system
development projects
10.Support of operating system and
support for system optimization.
Page 32 of 39
Role
Functional
Consultant
Commitm
ent time
Responsibilities
2. Identify gap solutions and closely
coordinate with Project Management
for gap resolution in compliance
with the business objectives, as well
as,
for
timely
resolution
of
configuration; Reports, Interfaces,
Conversion,
Enhancement,
and
Form (RICEF) development and Test
Problem Reports.
Fulltime
the
at
Page 33 of 39
Role
Commitm
ent time
Responsibilities
advocate within the team.
17.Completion
tasks.
of
assigned
project
18.Conduct
internal
and
external
reviews and walk-throughs.
Basis and
Security
Consultant
planning
of
3. Define
detailed
blueprint
development requirements
Full time
ITfor
for
system
technical
systems
11.Liaise
between
technical
infrastructure and business teams.
12.Provide security support
organization role design
to
the
Page 34 of 39
Role
ABAP
Developer
Commitm
ent time
Responsibilities
Perform
technical
application
design,
construction,
and
implementation activities for the
following:
Full time
1- Interfaces
2- Conversions
3- ABAP/4 reports/queries
4- SAP script forms
5- Report status and identify issues.
Integration
Development
Analyst
based
Full time
on
Full time
and
lead
global
training
Page 35 of 39
Role
Responsibilities
Commitm
ent time
5. Project Budget
5.1
Funding Source
Fund to be allocated from Hail project budget
5.2
Approved Budget
SAR 5.2 M
Training Strategy
Onsite training to key users
Train the trainer
All training materials to be handed to Tasnee for future internal trainings
6.2
Page 36 of 39
Communication
Manage Performance
Information Distribution
Planning Stakeholders
Reporting
Collecting
Determining
Providing
and
information
distributing
project information
and
performance
available
to
needs
project
ofincluding
project
stakeholders
stakeholders
statusinissues
reporting,
a timely
manner
progress
measurement,
Managing
communications
to communication
satisfy
theinformation,
requirements
of
and resolve
with
project stakeholders
Freque
ncy
Project
Sponsor
Executives
Every
month/P
roject
Mileston
e
Content
1. Strategic /
level Update;
Audience
High
Project
Sponsors
2. Preparation
for
Strategic Approval
Method
Face-toface
Video
Conferenc
e
e-mail
Steering
Committee
Meeting
Every
month/P
roject
Mileston
e Based
1. Strategic /
level Update;
High
Project
management
meeting
Every
week
1. Update / Progress
2. Request
for
Strategic Approval
2. Verify direction
3. Project monitoring
and
progress
tracking
Steering
Committee
Members
Face-toface
Project
management
team
(PMOProject Mentor
and
Project
Managers)
Face-toFace.
Video
Conferenc
e
Video
Conferenc
e
4. Issue resolution
5. Escalation
management
Document No.: EBSPMO-003
TASNEE
Document Name: Project Charter - Hail SAP Project Version 1.9
Date: 10/10/2016
Page 37 of 39
Communica
tion Type
Freque
ncy
Project team
meeting
Every
week
Content
1. Update
Progress
track:
Audience
status/
of each
Method
Project
team
(consultants,
engineers,
developers,
SME, BP etc.)
Face-toface
According
to
requirements
According
to
requireme
nts
4. Latest Info
5. Open issues
Individual
Meetings for
action points
responsible
Upon
request
1. Detailed Status
2. Next Steps
3. Degree
of
completion
WBS
4. Critical Issues
5. Risks
7. Risk Management
S.N
o.
1.
Risk Description
Mitigation Plan
Severity
Project budget
allocation is not
confirmed yet. It was
agreed that project will
be funded from Hail
Project budget
High
2.
Shortage of EBS
resources
3.
Shortage of business
resources
(Critical,
High, Medium, Low)
High
High
Name
Title
Othman
Corporate
Othman.alshaikh@cristal.
Phone
+966500101
Page 38 of 39
2.
3.
Alshaikh
Mansour
Siddiqui
Jawad Al
Hamayel
Business Partner
Tasnee SAPCC
com
m.siddiqui@tasnee.com
Business/Project
Owner
j.alhamayel@rowadplasti
c.com
907
+966544469
847
+966504213
988
Page 39 of 39