6511100.
8. Maintain the assignment of cost element group. ie. assigned progress cost elemnt to cost
element group with default radio button selected. In the cost element group, select certain
cost elements which are used for project materials, project manhours, project contracts,
spares etc)
9. Run CJEN first then CNE1 and CNE5.
Also u need to maintain progress version for all ur project activities under the tab "Progress"
tab.
Process Flow
To enter data for progress analysis during the execution of your project, proceed as
follows:
Create your project structures.
Enter a measurement method for the WBS element, activity, or activity
element.
If you do not define a measurement method, the system determines the valid
one automatically - for example, from the default value you have defined in
customizing for the object. See Determining the Measurement Method .
Enter the planned data for the project (costs, dates, milestones, and so on).
Note that progress analysis only considers costs planned by cost element.
Enter the actual data for the project.
Determine the progress of your project.
Result
Progress analysis supplies you with precise information on the state of your project,
and the cost and schedule situation. You can recognize trends independently of the
costs planned and posted in CO, and can take appropriate action.
Example
The following example illustrates the importance of progress analysis for valuing your
projects progress and the resulting schedule and cost variances.
Progress Analysis Versus Plan/Actual Comparison
You expect a customer project to incur costs of $100,000. The project lasts four
periods. The planned costs are distributed evenly over these periods ($25,000 per
period). Total actual costs posted for periods 1 and 2 are $40,000.
The graphic below illustrates the plan/actual comparison, showing a favorable project
situation. The project costs seem likely to be less than the planned costs.
If you now look at the work actually done, the situation appears different.
In period 2, you run a progress analysis. The system determines the actual POC as
follows: With overall planned costs of $100,000, the BCWP is $25,000 (overall
planned costs * POC). As the actual costs at this point amount to $40,000, the BCWS
is also $40,000, meaning that there is a cost variance of $15,000. In addition to the
cost variance, the report shows that there is a time variance. The earned value of
$25,000 should have been reached at the end of period 1. This means that the
project is one period behind schedule.
Link:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/63/f9bb53707db44ce1000
0000a174cb4/content.htm?
frameset=/en/b3/d90e0851e911d2a63b00104b59c1ec/frameset.ht
m
&
current_toc=/en/ca/d8b65334e6b54ce10000000a174cb4/plain.ht
m&node_id=25&show_children=false
Resources
Purpose
Use this component to plan the resources required for the work that is carried out
internally in a project. That is work that is not procured externally via purchasing.
You specify the work and the work center where this work is to be carried out in the
internally processed network activity. During scheduling the system determines
the capacity requirements for the project.
You offset these capacity requirements against the available capacities of the work
centers involved. For optimal capacity utilization, use Capacity Leveling .
In projects the most important resource is the project staf . Workforce
Planning enables you to distribute work from network activities to people, positions,
and HR organization units according to periods.
The system can determine the available capacity from the work center or the HR shift
schedule.
During project execution the capacity requirements are reduced by confirmations .
Integration
If you use workforce planning and the Time Sheet (CATS), you can specify in
Customizing for the time sheet that the system uses the work distributed to people in
workforce planning as default values for entering values in the time sheet.
For detailed information about Capacity Planning functions, refer to the Capacity
Planning (PP-CRP) component.
For information about Work Centers and the data that you have to maintain there for
capacity planning, refer to theWork Centers (PP-BD-WKC) component.
http://help.sap.com/saphelp_erp60_sp/helpdata/en/09/c4b65334e6b54ce100
00000a174cb4/content.htm
Workforce Planning
Use
Use this function to distribute work in internally processed activities of a project to
personnel resources according to periods. The personnel resources that you can
assign to activities are persons , positions , and organizational units in human
resources (HR).
You can carry out workforce planning with a project view or a work center view,
depending on your responsibilities. In reporting you can analyze workforce planning
from project, work center, and personnel resource views.
The work distributed to a person can be used as a default by the system for the Time
Sheet (CATS), when entering personal working times.
Use
Use this function to distribute work in internally processed activities of a project to
personnel resources according to periods. The personnel resources that you can
assign to activities are persons , positions , and organizational units in human
resources (HR).
You can carry out workforce planning with a project view or a work center view,
depending on your responsibilities. In reporting you can analyze workforce planning
from project, work center, and personnel resource views.
The work distributed to a person can be used as a default by the system for the Time
Sheet (CATS), when entering personal working times.
Prerequisites
Prerequisites
For workforce planning you require the HR mini-master record (infotypes 0001and
0002). In addition you need infotype 0315 for the time sheet (CATS), and infotype
007 to be able to display the availability of personnel resources.
In Customizing for the Project System , you must have defined profiles for workforce
planning in Resources . However you can change the settings for the current working
environment from those of the profile, when you call up workforce planning.
You must have also:
Assigned work centers to the internally processed activities.
Entered Formulas in the work center to determine capacity requirements.
Scheduled the activities to generate capacity requirements.
Assigned only one labor capacity to a work center.
Note
Features
Project View
When you call up workforce planning in project view, you select projects, WBS
elements, or networks . The project view displays all the activities that are assigned
to the selected networks or WBS elements.
You assign personnel resources to these activities. The system proposes the
personnel resources that are assigned to the project team for the relevant WBS
element of its superior WBS element. However, you can assign personnel resources
from the work center or, if the relevant indicator has been set in the profile, other
personnel resources.
Work Center View
When you call up workforce planning in the work center view you can select work
centers , plants, or personnel resources . You can also restrict the selection of
activities by choosing Filter . In the top section of the work center view you can see
all the selected personnel resources or the personnel resources assigned to the
selected work centers. In the lower section you see the network activities that are
assigned to the work centers and that meet the filter conditions.
You can assign the displayed activities to the displayed personnel resources, the
personnel resources of the relevant work center, or if the corresponding has been
set in the profile other personnel resources.
Reporting
Reporting lets you display and evaluate workforce planning for projects, work
centers, or personnel resources. To use reporting for workforce planning, you
do not require change authorization and the objects you examine arenot locked .
Reporting is based on the ABAP List Viewer (ALV). Using standard ALV functions it is
possible in reporting to print the work distribution, to send it to another user, or to
MRP works with infinite capacity and creates planned orders at the
Work Center at the same time since it assumes that Work Center is
available all the time. So, it creates planned orders on the same
date based on the requirements despite capacity shortages. You
can execute those orders on that Work Center in the system which
is not practically feasible in the shop floor.
The main objective of the capacity leveling includes leveling
overloads at Work Center and to achieve optimum utilization of
Work Centers.
MRP generated planned orders are converted to production orders
which determine which Work Center is to be used, and accordingly
the capacity requirements are generated on that Work Center.
Capacity leveling at production order level is used for detailed
production planning purpose. This is done through planning table
which is used to carry detailed planning of capacity requirements
over time in future.
The capacity load needs to be checked at Work Center, and if it is
overloaded, then we need to shift the orders ahead to the same
Work Center or plan it in different Work Center to eliminate any
capacity constraints.
In this tutorial- you will learn,
Step 2) In this screen, the capacity situation at Work Center can be seen.
After filling in all the fields, click execute button on top to go to the next
screen.
Step 2) In this screen, you can see orders pool at the bottom and Work
Center pool at the upper half of the screen in the planning table.
Step 3) In the same screen of planning table, select the data as given
below.
Check the dispatched order in the Work Center pool. Similarly, you
can dispatch the others orders to the Work Center pool which
would shift adjacent to the previously dispatched orders.