Design Example - 1
Bank Protection, JMREMP
River:
Meghna
Location: Thana: Matlab; District: Chandpur
Chainage N 585648 to N 589498
Design Data:
1.Discharge (Q):
2. Velocity (u):
3. High Water Level (HWL):
4. Av.Low Water Level (Av.LWL):
5. Flood Plain Level (FPL):
6. Wind velocity:
7.Wind Duration:
8. Fetch length:
9. Significant wave height (Hs):
10. Wave Period:
11.Bank slope, above low water (1V:2.5H):
12. Bank slope below low water (1V:2H):
13. Depth Factor (h/d): (from field observation)
130,000.00
2.50
6.20
0.55
4.25 - 5.00
20.00
1.50
5.0
1.25
4.2
21.80
26.57
m3/sec
100 yr flood
m/sec
m, PWD
m, PWD
m, PWD
m/sec
hr
km
m
25 yr return period
secs
Note: (1) Bank slope is considered from an average of cross-sections taken at the vicinity,
about 50% of the sections are steeper than 1V:2H and rest are flatter, (2) a slope stability
analysis to assess stable slope on observed soil data is needed to verify the assumed slope.
Design against velocity and shear:
Pilarczyk equation
Dn
0.035 u 2 sc K K h
m 2 g
K s cr
2.50 m/s
[-]
3
1000 kg/m
3
2250 kg/m
3
2650 kg/m
2
9.81 m/s
0.65 [-]
[-]
1.5
[-]
2 1/2;
[-]
21.80
26.57
[-]
MDIP-1
MDIP-2
7.50 [m]
[m]
[m]
Note: (3)Logarithmic velocity profiles exist for long stretches with constant bed roughness.
For most engineering works as slope or bottom protection, non-developed velocity profile
is usually present. (Pilarczyk, 2000)
(4) In this case non-developed velocity profile is considerd.
Non-Developed Velocity Profile
(1) CC blocks, concrete with stone aggregate (multi-layer):
Kh = depth factor (for non-developed vel. profile) = (h/D n+1)-0.2 =
Dn = nominal size of protection element (assumed) = (cc block)
h/Dn =
0.521
0.30 m
25
m = (s-w)/w =
= slope angle of bank structure = 1V:2H (below LWL)
= Angle of repose (cc blocks) =
Ks = [1-(sin/sins)2]1/2 =
sc = stability factor (application type) =
1.25 [-]
26.57
40
0.718
0.80 [-]
0.035 [-]
Dn =
35.16 kg
0.222 m =
250 mm
(2) Rocks:
Kh = depth factor (for non-developed vel. profile) = (h/D n+1)-0.2 =
Dn = nominal size of protection element (assumed) = (cc block)
h/Dn =
0.25 m
30
m = (s-w)/w =
= slope angle of bank structure = 1V:2H (below LWL)
= Angle of repose (rocks) =
Ks = [1-(sin/sins)2]1/2 =
sc = stability factor (application type) =
0.175 m =
1.65
26.57
35
0.626
[-]
[-]
0.75 [-]
0.503
0.035 [-]
200 mm
3.5 m
0.558
0.20 m
h/Dn =
17.5
m = (s-w)/w =
= slope angle of bank structure = 1:2 (below DLW)
= Angle of repose =
Ks = [1-(sin/sins)2]1/2 =
1.25
26.57
40
0.718
[-]
[-]
0.65 [-]
0.05 [-]
Dn =
7.59 kg
0.135 m =
150 mm
0.467
0.17 m
MDIP-3
MDIP-4
h/Dn =
s = Density of sand bag =
44
3
1750 kg/m
w = Density of water =
m = (s-w)/w =
= slope angle of bank structure = 1:2 (below DLW)
= Angle of repose =
Ks = [1-(sin/sins)2]1/2 =
1000
0.75
26.57
30
0.447
kg/m3
[-]
[-]
sc = stability factor =
0.50 [-]
0.05 [-]
Dn =
0.233 m =
250 mm
438 mm
373 mm
Note: (i) Both type A and Type-B bags fulfill the minimum requirement, (ii). Equivalent block
size against sand filled geobag is considered; (iii) Unit wt of field dry sand is considered for
calculating initial weight of sand filled geobag.
(5) Grout-filled mattress
h = depth of water infront of hand grout filled mattress =
Kh = depth factor (for non-developed vel. profile) = (h/D n+1)-0.2 =
4.5 m
0.532
0.20 m
h/Dn =
s = Density of grout =
22.5
3
2300 kg/m
w = Density of water =
m = (s-w)/w =
= slope angle of bank structure = 1:2 (below DLW)
= Angle of repose =
Ks = [1-(sin/sins)2]1/2 =
1000
1.30
26.57
30
0.447
sc = stability factor =
0.50 [-]
kg/m3
[-]
[-]
0.109 m =
0.07 [-]
150 mm
0.7 v
2 (ss 1) g
log(6h / d )
[1 (sin / sin ) ]
2 0.5
0.3
2.5
2.25
25.00
26.57
40
9.81
[m]
m/s
m/s2
Note: Logarithmic velocity profile is not fully developed in these cases, so JMBA formula may
MDIP-5
MDIP-6
H
D =
s
b
z
sw
cos
1.25 m
[-]
2
9.81 m/s
[-]
[-]
21.80
1.88
4.2 secs
2.00
2.25
0.67
1.25
Dn =
0.365 m
375 mm
1.45
2.75
0.50
1.25
0.370 m
375 mm
1.20
2.75
0.50
1.65
Dn =
0.339 m
350 mm
In consideration of velocity and shear, the hand placed single layer blocks are proposed to
be 400x400x200 mm size blocks, their performance against imposed load may be observed
in model and prototype.
Design of Launching apron:
(Protection element unit size is based on velocity and shear)
Thickness of protection
T = 1.5x Individual size of cc blocks against design velocity =
T1 = 1.5 x Individual size of rocks against design velocity =
Design scour depth, at MDIP =
(F
20.00 m
375 mm
300 mm
(FS Report, Halcrow)
MDIP-7
Av.LWL =
0.55 m, PWD
Design Scour level (as per FS) = 0.55 - 20.0 =
-19.45 m, PWD
Deepest observed scour level at the vicinity =
-12.00 m, PWD
Deepest known scour depth = 12.00 + 0.55 = 12.55 m, below Av.LWL, so design scour depth
suggested by the FS Report, being higher than the highest observed scour, is considered
for the toe protection; So Design Scour =
20.00 m
Length of launching apron, L = 1.5 x 20.0 =
30.00 m
562.5 mm
843.75 mm
3
21.09 m /m
3
31.64 m /m
450 mm
675.0 mm
3
16.88 m /m
3
25.31 m /m
In mass dumping concept, a falling apron is developed from the water line by dumping a
calculated quantity of sand filled geobags as a heap below low water level along the river
section, the geobags are assumed to launch at a slope of 1V:2H, to cover the slope and
future scour holes.
In the Feasibility Study Report protection thickness of 0.61 m on the scour surface for a scour
depth upto 17.0 m, and beyond that a thickness of 0.91 m is suggested.
As per FS report, for a scour depth of 20.0 m, volume of material (geobag) requird is:
3
V = (202+402)1/2 x 0.91 m3/m =
40.70 m /m
The FS indicated a protection unit, each unit comprising geobags of 4 differnet sizes( 126 kg,
78 kg, 36 kg and 11 kg), and each size comprising 25% of the unit. Dry weight of each unit
is 504 kg and volume is 0.336 m 3.
In MDIP, suggested volume of apron protection for 20.0 m scour depth is 121 units i.e.
3
(121 x 0.336)=
40.66 m /m
A comparative statement for protection to Meghna River bank upto a scour depth of 20 m
below design low water (+0.55 m, PWD) with different types of materials are:
1. CC Blocks
2.Rocks/boulders:
3. Geo-bag
3
31.64 m /m
3
25.31 m /m
3
40.70 m /m
Note: geo-bag coverage of 0.91 m thick after launching appear to be not realistic, normally
average of 1 layer thick coverage, after launching may be achieved. To attain the desired
thickness (at least 3 additional layers A-type bag i.e. 0.66 m or 0.61 m as suggested by FS)
MDIP-8
MDIP-9
Protection against 20 m scour with a 0.61 m thick launched material (geobag), the volume of
3
V =(202+402)1/2 x 0.67 =
29.96 m /m
geobags required is;
Considering geo-bags as protection element (areal coverage):
JMREMP has constructed bank protection by dumping geobags in a regular manner on the
existing natural river bank slopes and as wide falling aprons along the toe. Slope protection
and falling apron consisting of several layers (minimum 4 layers) of geobags is built from the
deep area of the river towards the bank infront of the toe.
Apron length according to suggested formula: 1.5 x 20.0 m =
30 m
In the arial coverage approach followed in JMREMP afterwards, to protect a 20.0 m scour by
sand filled geobags with single layer coverage on a slope of 1V:2H (20x5 = 45m, slope .
length) requires 90 geobags (A-type, 126 kg) i.e. 2 bags/ m2. The project finally used 4 layers
of A-type geobags (4x2 = 8 geobags/m2) as protection to the river bank.
No of 126 kg geobag per sqm (only A-type bag is used) = 4x2 =
Total volume of material placed on the apron (45m wide) =
Effective size of one A-type geobag is =
Volume of geobags (4 layers, A-type) placed/dumped =
Volume of 1 A-type geobag (size: 930x530x170 mm)
Average thicknes of A-Type geobag =
8
30.24
0.50
0.672
0.084
0.17
nos
m3/m
m2
m3/m2
m3
m
3
weight(kg) vol (m )
504
0.336
126
0.084
78.00
0.052
36.00
0.024
11.00
0.007
MDIP-10
41016/1250=
32.81 C-bags
MDIP-11
3
27.30 m /m
3
10.08 m /m
3
14.76 m /m
3
10.08 m /m
3
11.64 m /m (av.)
120 B-bags
3
6.24 m /m
96 B-bags
3
4.99 m /m
3
11.23 m /m
Protection provided at X-sec# 7 (N 588590) in November 2004 show that the materials were
placed (arial coverage) from (-) 9.35 m, PWD to (+) 0.75 m, PWD; (6 B-bag per m 2 i.e.
6.11 m 3 /m on 20m horizontal distance); -9.35 m PWD is the lowest elevation in the section.
Falling apron (8 B-bag per m 2 on 12m horizontal distance at river side end of apron i.e.
4.89 m 3 /m) were placed.
Monitoring of the section (N 588590) in August 2006 show that the lowest elevation in the
section is in the order of (-)10.0 m, PWD. The steepest under water slope is about 1V:2H;
indicating a section stable with a protection of about 11.00 m 3 /m (6.11+4.89= 11.00) i.e. a
thickness of average 0.34 m, which resembles approximately 2.2 layers of geobag type-B.
In the reach from Km.44.636 to Km.44746; total material dumped under arial coverage and
Falling Apron is 11.23 m 3 /m, that could protect a scour upto (-) 10.0m, PWD.
Km.46.230 to Km.48.320: ( 2090 m)
Falling apron per m of bank line =31350/2090=
(av. 6m width)
(52250)/2090=
(av.10 m width)
167200/2090=
15 A-bags
25 B-bags
80 B-bags
3
6.72 m /m
Protection provided from Km.46.230 to Km.48.320, from Feb 2004 to March 2006, in two
stages (1st level and 2nd level protection):
3
1st level prot.av. arial cover width is 30 m, and geobag dumped =
11.64 m /m (av.)
3
2nd level prot.av.falling apron width is 16m and geobag dumped=
6.72 m /m
Analysis of protection provided (Km.46.230 to Km.48.320) indicates that in total 18.36 m3/m
of geobag on a length of 46 m could maintain the reach in a stable section from February 2004
to March 2006. Average thickness of protection provided is about 0.40 m.
Protection provided at X-sec# 1 (N 586570) in November 2004 show that the materials were
placed (arial coverage) from (-) 15.43 m, PWD to (+) 0.75 m, PWD; (120 A-bag/meter on
30 m wide arial coverage i.e. 10.08 m 3 /m); -15.43m PWD being the deepest point at the end
of arial coverage, falling apron was placed from that elevation towards deeper section/mid river
for an width of 16 m, in two stages. 1st stage: 15 A-type bag /m on 6m wide slope distance and
MDIP-12
Monitoring of the section (N 586580) in August 2006 show that the lowest elevation in the
section is in the order of (-)17.0 m, PWD. The steepest under water slope is about 1V:2H.
Remarks: (1) The protection works executed in MDIP and monitoring done afterwords show
that the coverage of a critical section by about 2 to 3 layers of geobag (i.e. thickness of
protection is about 0.34 m to 0.51 m) upto its deep section near the bank (about 45 m from
LW line) could provide a sustainable protection to the eroding reaches of the river.
(2). Single size geobags (126 kg) for the River Meghna is preferable than a mix of different
sizes.
(3) To arrive at a geotecnically stable slope over the existing bank slope a berm below LWL
is a key to upper slope protection ( above low water level). The permanent protection shall be
built starting on a berm, about 2.0 to 3.0 m wide and at about 1.5 m below Design Low Water
(DLW) and subsequently sloping towards floodplain at 1V:2.5H. This measur unload the
slope and helps achieving the required safety factor for slope stability;
(4) The underwater berm and slope above that (upto DLW) shall be covered with minimum
two layers of randomly placed CC blocks over a layer of geobag (A-type);
(5) The volume of apron protection calculated as per T.S.N Rao is based on "Trench Fill
Revetment" method. This may not work in most of the places along the major rivers. The
total volume needed for protection/m of bank line (in case of rocks or blocks) may be adjusted
with (i) 1.5x thickness of slope pitching from low water line to the the existing bed of the river
and (ii) the rest volume of material is placed on the existing bed, (iii) the apron length in that
case shall be 1.5 times the anticipated scour from the existing bed.
(6) In case of geotextile bag as protection element 4 layers of geobags shall be placed on slope
from low water line to the existing bed level and the apron on horizontal bed shall consist of at
least three layers. The apron length in case of major rivers shall be at least 35m.
MDIP-13