Anda di halaman 1dari 14

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER

ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
1

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

135,94 15 Oct '16 23 Oct '16 0 hrs


hrs

TIE-IN SUMPAL COMPRESSION PROJECT

135,94 15 Oct '16 23 Oct '16 0 hrs


hrs

EXECUTION
PIPING

52,97 15 Oct '16 18 Oct '16 1 hr


hrs

44-TP-009 (WP-09)

11 hrs 15 Oct '16 16 Oct '16 118,94 hrs

Energy isolation and depressurize gas

0 hrs 15 Oct '16 15 Oct '16 118,94 hrs

Release for Tie-in Certificate

1 hr

Unbolting existing flanges & remove existing pipe spool (tie-in connection
44-TP-009A_B_C_D

2 hrs 15 Oct '16 15 Oct '16 118,94 hrs

Connecting tie- in spool for 44-TP-009A_B_C_D. 1. Bolting Flange #1 to Existing 3 hrs 15 Oct '16 15 Oct '16 118,94 hrs
Gate Valve 3"-GA-AS- (3-2-44-003). 2. Bolting Flange #2 to Tie-in 44-TP-009B.
3. Bolting Flange #3 to Existing Flange Tie-in 44-TP-009D. 4. Bolting Flange #4
to Existing Gate
install new Blind flange at one - end of new valve 4"-GA-AS-3-2-44-3698 (For
1 hr 15 Oct '16 15 Oct '16 118,94 hrs
Safety reason, until continue spool is ready for installed)

15/10
15 Oct '16 15 Oct '16 118,94 hrs
YIN-1

YIN-1

YIN-1

YIN-1
10

Install U-Bolt (tightening U-Bolt)

1 hr

15 Oct '16 15 Oct '16 118,94 hrs

11

Construction Tightening bolts

1 hr

15 Oct '16 15 Oct '16 118,94 hrs

12

Flange Management (Manual)

1 hr

15 Oct '16 16 Oct '16 118,94 hrs

13

Joint Inspection and Hand over to operation

1 hr

16 Oct '16 16 Oct '16 118,94 hrs

YIN-1

YIN-1

PRECOM-1

PRECOM-1
14

3L-TP-001 (WP-10)

19 hrs 15 Oct '16 16 Oct '16 116,94 hrs

15

Depressurizing and ensure no gas in existing pipe

1 hr

15 Oct '16 15 Oct '16 116,94 hrs

16

Unbolting & Remove 20 CL.900 blind flange of existing spool

2 hrs 15 Oct '16 15 Oct '16 116,94 hrs

17

Connecting tie-in spools for 3L-TP-001. 1. Bolting pipe spool 3L-TP-001 to


Existing flange 2. Bolting Flange #1 to Gate Valve 16"-GA-DS-3-2-3L-3548 3.
Bolting Flange #2 to Gate Valve 16"-GA-DS-3-2-20-3670 4. Install
3/4"-VI-DS-C-1-3L-1004 & Mono flange 3L
Install Slip Blind #1 & Slip Blind #2 (For Safety reason, until continue spool is
ready for installed)

3 hrs 15 Oct '16 15 Oct '16 116,94 hrs

19

Install Clamp Support & guide

1 hr

20

Construction Tightening bolts (16"=2ea, 20"=1ea)

3 hrs 15 Oct '16 15 Oct '16 116,94 hrs

21

Flange Management

3 hrs 15 Oct '16 15 Oct '16 116,94 hrs

22

High Pressure Leak Test 1269psi and blanketing

3 hrs 15 Oct '16 16 Oct '16 116,94 hrs

23

Joint Inspection and Hand over to operation

1 hr

16 Oct '16 16 Oct '16 116,94 hrs

31,5
hrs

15 Oct '16 16 Oct '16 104,44 hrs

1 hr

15 Oct '16 15 Oct '16 104,44 hrs

YIN-2;PRECOM-2

YIN-2

18

YIN-2
2 hrs 15 Oct '16 15 Oct '16 116,94 hrs
YIN-2
15 Oct '16 15 Oct '16 116,94 hrs
YIN-2

YIN-2

PRECOM-2

PRECOM-2

PRECOM-2
24

25-TP-020A/B/C (WP-11A)

25

Depressurizing and ensure no gas in existing pipe

26

27

Unbolting flanges & remove of existing spool : 1. Unbolting Flange 1 2. Unbolting 6 hrs 15 Oct '16 15 Oct '16 104,44 hrs
Tie-in connection 25-TP-020A 3. Unbolting Tie-in Connection 25-TP-020C 4.
Remove Pipe Spool Existing 5. Unbolting Tie-in Connection 25-TP-020B 6.
Remove Check Valve 7. Remov
Unbolting Flange 2 on ground
1 hr 15 Oct '16 15 Oct '16 104,44 hrs

28

Install Pipe support - 2ea (Welding) -2hrs

2 hrs 15 Oct '16 15 Oct '16 104,44 hrs

29

Install and Connecting tie-in new spools sequencially : 1. Positioning pipe spool
#4. 2. Assembly Pipe spool #1, Check Valve, Pipe spool #2 for 25-TP-020B
(Include Bolting) 3. Bolting to 25-TP-020B & Valve 103-ESDV-101 4. Lifting
Pipe spool #3 for 25-T
Install ball valve at branch connection spools #1 & spool #4, Ball Valve
4"-BA-DR-3-1-25-4090. (Include accessories gasket, bolt and nuts)

6 hrs 15 Oct '16 16 Oct '16 104,44 hrs

31

Construction Tightening bolts

4 hrs 16 Oct '16 16 Oct '16 104,44 hrs

32

Flange Management

2 hrs 16 Oct '16 16 Oct '16 104,44 hrs

33

High Pressure Leak Test 1250 Psi and blanket (After WP11B complete)

3 hrs 16 Oct '16 16 Oct '16 104,44 hrs

34

Joint Inspection and Hand over to operation

1 hr

PRECOM-7;YIN-3

YIN-3

YIN-3

YIN-3;YIN-10

30

YIN-10
3 hrs 16 Oct '16 16 Oct '16 104,44 hrs
YIN-10

YIN-3

YIN-3;PRECOM-7

PRECOM-1
16 Oct '16 16 Oct '16 104,44 hrs
PRECOM-1
35

25-TP-020D/E (WP-11B)

52,97 15 Oct '16 18 Oct '16 82,97 hrs


hrs

36

Unbolting 2ea flanges & remove of existing spool 25-TP-020D & E (tie-in
connection, include Check valve)

4 hrs 15 Oct '16 15 Oct '16 101,94 hrs

37

Surface Demolition / chipping of existing pipe sleeper (Ground Level) with


pneumatic jack hammering

8 hrs 15 Oct '16 15 Oct '16 101,94 hrs

38

Unbolting Flange #1 on ground

2 hrs 15 Oct '16 15 Oct '16 101,94 hrs

39

Install Pipe support - 1ea (Welding)

2 hrs 15 Oct '16 16 Oct '16 101,94 hrs

40

Install and Connecting tie-in new spools sequencially: 1. Bolting Pipe spool #7 to 4 hrs 16 Oct '16 16 Oct '16 101,94 hrs
25-TP-020E 2. Bolting 25-TP-020E to Check valve (existing) 3. Bolting Check
Valve to Pipe spool #6 4. Bolting spool #6 to 25-TP-020D (103-ESDV-1010)
Include Spacer (Include
Install ball valve 4"-BA-DR-3-1-25-4091 at branch connection spools #7 (Include 2 hrs 16 Oct '16 16 Oct '16 101,94 hrs
accessories gasket, bolt and nuts)

YIN-4

Civil Crew-1

YIN-4

YIN-4

41

YIN-4

YIN-4
42

Connecting Flange of continues spool #5 line up to Work pack 11A


(25-TP-020A_B_C)

1 hr

16 Oct '16 16 Oct '16 101,94 hrs

43

Install Guide (Welding)

1 hr

16 Oct '16 16 Oct '16 101,94 hrs

44

Construction Tightening bolts 12=4ea, 4=3ea

4 hrs 16 Oct '16 16 Oct '16 101,94 hrs

YIN-4

YIN-4

YIN-4

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 1

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
45

Flange Management

2 hrs 16 Oct '16 16 Oct '16 101,94 hrs

46

High Pressure Leak Test 1250 Psi and blanket Include 25-TP-20A_B_C

3 hrs 18 Oct '16 18 Oct '16 82,97 hrs

47

Joint Inspection and Hand over to operation

1 hr

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

PRECOM-1

PRECOM-1
18 Oct '16 18 Oct '16 82,97 hrs
PRECOM-1
48

3L-TP-027 (WP-12)

12 hrs 15 Oct '16 15 Oct '16 20 hrs

49

Unbolting & remove blind flanges (tie-in connection 3L-TP-027)

2 hrs 15 Oct '16 15 Oct '16 20 hrs

50

Connecting tie-in spools for 3L-TP-027 1. Bolting pipe spool #1 to 3L-TP-027 2.


Bolting pipe spool #1 to pipe spool#2. (Include install accessories gasket, bolt
and nuts)

2 hrs 15 Oct '16 15 Oct '16 20 hrs

51

Install Temporary Blind flange 4=1ea, 2=1ea

1 hr

15 Oct '16 15 Oct '16 20 hrs

52

Install guide support

1 hr

15 Oct '16 15 Oct '16 20 hrs

53

Construction Tightening bolts

2 hrs 15 Oct '16 15 Oct '16 20 hrs

54

Flange Management

3 hrs 15 Oct '16 15 Oct '16 20 hrs

55

Joint Inspection and Hand over to operation

1 hr

YIN-5

YIN-5

YIN-5

YIN-5

YIN-5

PRECOM-3
15 Oct '16 15 Oct '16 20 hrs
PRECOM-3
56

43-TP-028 (WP-13)

16 hrs 15 Oct '16 16 Oct '16 16 hrs

57

Unbolting & remove blind flanges 24 (tie-in connection 43-TP-028) (Manual


Lifting activities will be required for removal blind flange)

2 hrs 15 Oct '16 15 Oct '16 16 hrs

58

Connecting tie-in spools for 43-TP-028

3 hrs 15 Oct '16 15 Oct '16 16 hrs

59

(Include install accessories gasket, bolt and nuts)

3 hrs 15 Oct '16 15 Oct '16 16 hrs

60

Install Temporary Slip Blind at up strem Gate valve 24-GA-AD-3-2-43-3540

2 hrs 15 Oct '16 15 Oct '16 16 hrs

61

Construction Tightening bolts 24=2ea

2 hrs 15 Oct '16 15 Oct '16 16 hrs

62

Flange Management

3 hrs 15 Oct '16 15 Oct '16 16 hrs

63

Joint Inspection and Hand over to operation

1 hr

YIN-6

YIN-6

YIN-6

YIN-6

YIN-6

PRECOM-4
15 Oct '16 16 Oct '16 16 hrs
PRECOM-4
64

43-TP-045A/B (WP-14)

31 hrs 15 Oct '16 16 Oct '16 1 hr

65

Open block valve at any point of existing pipe (drain or vent) & Loosen bolt Valve 2 hrs 15 Oct '16 15 Oct '16 1 hr
for drain point

66

Manual Cold Cutting at 43-TP-045A_B - 2 Points

4 hrs 15 Oct '16 15 Oct '16 1 hr

67

Dismantle Manual Cold cutting machine after complete cut out of pipe spool at
43-TP-045A_B

1 hr

15 Oct '16 15 Oct '16 1 hr

68

Remove (Demolish) of existing (cutted) pipe spool

1 hr

15 Oct '16 15 Oct '16 1 hr

69

Install Duct Seal for pipe 3 - 2 ea

1 hr

15 Oct '16 15 Oct '16 1 hr

70

Beveling, Fit-up and weld a 2ea new 3 Flanges on 43-TP-045A_B

4 hrs 15 Oct '16 15 Oct '16 1 hr

71

Weld Cooling down & Dismantle and remove Duct Seal at 43-TP-045A_B

2 hrs 15 Oct '16 15 Oct '16 1 hr

72

Mechanical Cleaning

0,5 hrs 15 Oct '16 15 Oct '16 1 hr

73

NDE Examination & Result

2,5 hrs 15 Oct '16 16 Oct '16 1 hr

74

Connection Spool Tie-in 43-TP-045A_B (Exclude gate valve


3-GA-AD-3-2-43-3594)

1 hr

75

Hydrotest (including existing pipe) : (filling water & Press up from up strem
check valve existing at line 1-GF-AA2-60-7003)

5 hrs 16 Oct '16 16 Oct '16 1 hr

76

Drain out after hydrotest (open any points of existing valves)

1 hr

77

Reinstatement after Hydrotest include existing flange

2 hrs 16 Oct '16 16 Oct '16 1 hr

78

Install U-Bolt (tightening U-Bolt) & guide - 1hr

1 hr

79

Flange Management

2 hrs 16 Oct '16 16 Oct '16 1 hr

80

Joint Inspection and Hand over to operation

1 hr

PRECOM-4;YIN-7

YIN-7

YIN-7

YIN-7

YIN-7

YIN-11;YIN-7

YIN-11

PRECOM-4

NDE TTEAM
16 Oct '16 16 Oct '16 1 hr
YIN-7

PRECOM-5
16 Oct '16 16 Oct '16 1 hr
YIN-7

YIN-7
16 Oct '16 16 Oct '16 1 hr
YIN-7

PRECOM-4
16 Oct '16 16 Oct '16 1 hr
PRECOM-4
81

60-TP-021 (WP-15)

7 hrs 15 Oct '16 15 Oct '16 128,94 hrs

82

Unbolting & remove blind flanges (tie-in connection 60-TP-021)

1 hr

15 Oct '16 15 Oct '16 128,94 hrs

83

Connecting tie-in spool for 60-TP-021 (Include install gate valve & accessories
gasket, bolt and nuts)

2 hrs 15 Oct '16 15 Oct '16 128,94 hrs

84

Re-install existing Blind flange at one - end of new valve (For Safety reason, until
continue spool is ready for installed)

1 hr

15 Oct '16 15 Oct '16 128,94 hrs

85

Install U-Bolt (tightening U-Bolt)

1 hr

15 Oct '16 15 Oct '16 128,94 hrs

86

Construction Tightening bolts

1 hr

15 Oct '16 15 Oct '16 128,94 hrs

87

Flange Management

1 hr

15 Oct '16 15 Oct '16 128,94 hrs

88

50-TP-013A/B (WP-16)

YIN-1

YIN-1

YIN-1

YIN-1

PRECOM-5

PRECOM-5

Project: Schedule Tie-In shutdown oct

9 hrs 15 Oct '16 15 Oct '16 126,94 hrs

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 2

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
89

Block valve (Fully close) of existing valve & LOTO Verification

1 hr

90

Unbolting flanges of existing spool & Remove of existing spool

2 hrs 15 Oct '16 15 Oct '16 126,94 hrs

91

Connecting tie-in spool for 60-TP-013A & B (Include install gate valve &
accessories gasket, bolt and nuts)

2 hrs 15 Oct '16 15 Oct '16 126,94 hrs

92

Install U-Bolt (tightening U-Bolt)

1 hr

93

Construction Tightening bolts

2 hrs 15 Oct '16 15 Oct '16 126,94 hrs

94

Flange Management

1 hr

95

67-TP-023A/B (WP-17)

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

15 Oct '16 15 Oct '16 126,94 hrs


YIN-8

YIN-8

YIN-8
15 Oct '16 15 Oct '16 126,94 hrs
YIN-8

PRECOM-5
15 Oct '16 15 Oct '16 126,94 hrs
PRECOM-5

96

17 hrs 15 Oct '16 16 Oct '16 118,94 hrs

Unbolting flanges of existing spool : 1. Unbolting Existing Flange #1 2. Remove


Existing spool #1 & PSV existing 3. Unbolting 60-TP-023B & install Slip blind 5.
Cutting spool existing for demolish (3 section) 6. Unbolting 60-TP-023A 7.
Unbolting U-bolt su
Fit & Welding Support #1 to existing vessel

6 hrs 15 Oct '16 15 Oct '16 118,94 hrs

98

Connecting tie-in new spool for 60-TP-023A & B: (Include install gate valves &
accessories - gasket, bolt and nuts) Note : New pipe spool already on site

2 hrs 15 Oct '16 15 Oct '16 118,94 hrs

99

Continue Connecting tie-in to new spools - PSV Lines (Include install PSV valve
& Accessories - gasket, bolt and nuts)

2 hrs 15 Oct '16 15 Oct '16 118,94 hrs

100

Install 2ea New Dummy Supports (pipe support to base plate) (welding)

2 hrs 15 Oct '16 15 Oct '16 118,94 hrs

101

Install U-Bolt (tightening U-Bolt) & guide

1 hr

102

Flange Management

2 hrs 15 Oct '16 16 Oct '16 118,94 hrs

103

Joint Inspection and Hand over to operation

1 hr

97

YIN-9
1 hr

15 Oct '16 15 Oct '16 118,94 hrs


YIN-9

YIN-9

YIN-9

YIN-9
15 Oct '16 15 Oct '16 118,94 hrs
YIN-9

PRECOM-6
16 Oct '16 16 Oct '16 118,94 hrs
PRECOM-6
104

20-TP-002 & 27-TP-006 (WP-01)

18 hrs 17 Oct '16 18 Oct '16 82,97 hrs

105

Open block valve at any vent point of existing pipe

2 hrs 17 Oct '16 17 Oct '16 82,97 hrs

106

Loosen bolts to flanges 4ea for :o Replace and install permanent Blind & Spacer
(incld. Replacement of gasket for all opening (flanges) o Install Instrument item
(SC 8001 & TT 1015) o Adjustment Supoort 3ea

6 hrs 17 Oct '16 17 Oct '16 82,97 hrs

107

Install pipe Spool Sampling Connection- Include 1ea Double Block & Bleed
(1-VI-CS-A-3-20-4148), Accessories Bolts & Gaskets

2 hrs 17 Oct '16 17 Oct '16 82,97 hrs

108

Construction Tightening bolts

2 hrs 17 Oct '16 17 Oct '16 82,97 hrs

109

Flange Management

2 hrs 17 Oct '16 17 Oct '16 82,97 hrs

110

High Pressure Leak Test 200 Psi and blanket

3 hrs 17 Oct '16 18 Oct '16 82,97 hrs

111

Joint Inspection and Hand over to operation

1 hr

PRECOM-7;YIN-2

YIN-2

YIN-2

YIN-2

PRECOM-7

PRECOM-7
18 Oct '16 18 Oct '16 85,97 hrs
PRECOM-7
112

20-TP-003 & 27-TP-007 (WP-02)

29 hrs 16 Oct '16 17 Oct '16 84,96 hrs

113

Open block valve at any vent point of existing pipe

2 hrs 16 Oct '16 16 Oct '16 84,96 hrs

114

Unbolting flange 4ea Glycol contactor - TP-003 (tie-in spool, loosen at two sides) 3 hrs 16 Oct '16 16 Oct '16 84,96 hrs

115

Adjustment & Fit-up 4ea flange & 3ea Support

5 hrs 16 Oct '16 16 Oct '16 84,96 hrs

116

Replace gasket at Nozzle, and tightening bolts at Nozzle separator contactor


(TP-003)

3 hrs 16 Oct '16 16 Oct '16 84,96 hrs

117

Continues loosen bolts to other flanges for : o Alignment and corrective position
of tie-in spool TP-003 o Replace and install permanent Blind & Spacer o Install
Instrument item (SC 8002 & TT 2015) - (Include. Replacement of gasket for all
opening flanges
Install pipe Spool Sampling Connection- Include 1ea Double Block & Bleed
(1-GP-CS1-20-3417-A015), Accessories Bolts & Gaskets

4 hrs 16 Oct '16 17 Oct '16 84,96 hrs

119

Construction Tightening bolts

2 hrs 17 Oct '16 17 Oct '16 84,96 hrs

120

Flange Management

3 hrs 17 Oct '16 17 Oct '16 84,96 hrs

121

High Pressure Leak Test 200 Psi and blanket

4 hrs 17 Oct '16 17 Oct '16 84,96 hrs

122

Joint Inspection and Hand over to operation

1 hr

YIN-1

YIN-1

YIN-1

YIN-11

118

YIN-11
2 hrs 17 Oct '16 17 Oct '16 84,96 hrs
YIN-11

YIN-11

PRECOM-7

PRECOM-7
17 Oct '16 17 Oct '16 90,96 hrs
PRECOM-7
123

50-TP-048 A/B (WP-NS02)

10 hrs 16 Oct '16 16 Oct '16 109,96 hrs

124

Block valve (Fully close) of 2ea existing valves

1 hr

16 Oct '16 16 Oct '16 109,96 hrs

125

Field Measurement and marking for cutting position 50-TP-048A_B

1 hr

16 Oct '16 16 Oct '16 109,96 hrs

126

Cutting at 20-TP-048A & 20-TP-048B

2 hrs 16 Oct '16 16 Oct '16 109,96 hrs

127

Fit-up and weld tie-in spool at position 1x3/4" Reducing Tee on 20-TP-048A &
20-TP-048B

2 hrs 16 Oct '16 16 Oct '16 109,96 hrs

128

Penetrant examination & Result

1 hr

16 Oct '16 16 Oct '16 109,96 hrs

129

Install U-Bolt (tightening U-Bolt)

1 hr

16 Oct '16 16 Oct '16 109,96 hrs

130

Install LOTO at new valve

1 hr

16 Oct '16 16 Oct '16 109,96 hrs

131

Joint Inspection and Hand over to operation

1 hr

16 Oct '16 16 Oct '16 109,96 hrs

YIN-5

YIN-5

YIN-5

YIN-5

YIN-5

YIN-5

YIN-5

YIN-5
132

69-TP-044A/B (WP-NS03)

Project: Schedule Tie-In shutdown oct

13 hrs 16 Oct '16 16 Oct '16 106,96 hrs

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 3

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
133

Block valve (Fully close) of existing valve

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

134

Field Measurement and marking for cutting position 69-TP-044A & 69-TP-044B

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

135

Cutting at 69-TP-044A & 69-TP-044B

2 hrs 16 Oct '16 16 Oct '16 106,96 hrs

136

Remove (Demolish) of existing (cutted) pipe spool

1 hr

137

Fit-up and 2ea weld new 1 SW Flange on 69-TP-044A & 69-TP-044B

3 hrs 16 Oct '16 16 Oct '16 106,96 hrs

138

Penetrant examination & Result

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

139

Install tie-in spool pipe (Include gate valves & accessories Gasket, bolts and
nuts)

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

140

Install U-bolts & support (tightening U-Bolt)

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

141

Install LOTO at new valve & Open block of existing valve (Open LOTO)

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

142

Joint Inspection and Hand over to operation

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

YIN-6

YIN-6

YIN-6
16 Oct '16 16 Oct '16 106,96 hrs
YIN-6

YIN-6

YIN-6

YIN-6

YIN-6

YIN-6

YIN-6
143

50-TP-049A/B (WP-NS12)

13 hrs 16 Oct '16 16 Oct '16 106,96 hrs

144

Block valve (Fully close) of existing valve

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

145

Field Measurement and marking for install position 50-TP-049A_B

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

146

Remove existing ball valve threaded

2 hrs 16 Oct '16 16 Oct '16 106,96 hrs

147

Cut existing nipple at the threaded end

2 hrs 16 Oct '16 16 Oct '16 106,96 hrs

148

Fit-up and weld tie-in spool at position 1x1 Reducing Tee on 20-TP-049A &
20-TP-049B

2 hrs 16 Oct '16 16 Oct '16 106,96 hrs

149

Install existing ball valve threaded c/w nipple PBE

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

150

Install U-Bolt (tightening U-Bolt)

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

151

Penetrant examination & Result

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

152

Install LOTO at new valve & Open existing valve (and also Open LOTO of
existing valve)

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

153

Joint Inspection and Hand over to operation

1 hr

16 Oct '16 16 Oct '16 106,96 hrs

YIN-8

YIN-8

YIN-8

YIN-8

YIN-8

YIN-8

YIN-8

YIN-8

YIN-8

YIN-8
154

155

156

ELECTRICAL

135,94 15 Oct '16 23 Oct '16 0 hrs


hrs

Penggantian PLC controller menjadi Ethernet Embeded, penambahan power


monitor dan panel view (WP-5)
Modifikasi UCP 108-G-401 (WP-5A)

25,98 15 Oct '16 16 Oct '16 7 hrs


hrs
25 hrs 15 Oct '16 16 Oct '16 7 hrs

157

Shut down process & Isolation Area

1 hr

15 Oct '16 15 Oct '16 7 hrs

158

PTW, PJSM

2 hrs 15 Oct '16 15 Oct '16 7 hrs

159

Glanding cable pada cover atas UCP 108-G-401

2 hrs 15 Oct '16 15 Oct '16 130,94 hrs

160

Back Up Existing Logic

2 hrs 15 Oct '16 15 Oct '16 7 hrs

161

Dismantle semua kabel pada door panel

2 hrs 15 Oct '16 15 Oct '16 7 hrs

162

Modifikasi door panel UCP 108-G-401 108-G-401

2 hrs 15 Oct '16 15 Oct '16 7 hrs

163

Mengganti existing panel view dengan AB PVP600

2 hrs 15 Oct '16 15 Oct '16 124,94 hrs

164

Mengganti PLC Controller dengan SLC 5/05 1747-L553

2 hrs 15 Oct '16 15 Oct '16 7 hrs

165

Install ETAP Ethernet communication module

1 hr

166

Install Modbus Master/Slave Communication Module

2 hrs 15 Oct '16 15 Oct '16 123,94 hrs

167

Install Power Monitor PM500

2 hrs 15 Oct '16 15 Oct '16 7 hrs

168

Internal Wiring (Ethernet, RS-485, UPS supply dan existing internal wiring)

3 hrs 15 Oct '16 15 Oct '16 7 hrs

169

Continuity check

3 hrs 16 Oct '16 16 Oct '16 7 hrs

170

Logic and address verification

4 hrs 16 Oct '16 16 Oct '16 7 hrs

171

Quality Inspection

1 hr

16 Oct '16 16 Oct '16 7 hrs

172

House keeping

1 hr

16 Oct '16 16 Oct '16 7 hrs

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1
15 Oct '16 15 Oct '16 7 hrs
TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1
173

Modifikasi UCP 108-G-402 (WP-5B)

25 hrs 15 Oct '16 16 Oct '16 7 hrs

174

Shut down process & Isolation Area

2 hrs 15 Oct '16 15 Oct '16 7 hrs

175

PTW, PJSM

1 hr

176

Glanding cable pada cover atas UCP 108-G-402

2 hrs 15 Oct '16 15 Oct '16 131,94 hrs

TOP-2
15 Oct '16 15 Oct '16 7 hrs
TOP-2

TOP-2

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 4

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
177

Back Up Existing Logic

2 hrs 15 Oct '16 15 Oct '16 7 hrs

178

Dismantle semua kabel pada door panel

2 hrs 15 Oct '16 15 Oct '16 7 hrs

179

Modifikasi door panel UCP 108-G-402

2 hrs 15 Oct '16 15 Oct '16 7 hrs

180

Mengganti existing panel view dengan AB PVP600

2 hrs 15 Oct '16 15 Oct '16 126,94 hrs

181

Mengganti PLC Controller dengan SLC 5/05 1747-L553

2 hrs 15 Oct '16 15 Oct '16 7 hrs

182

Install ETAP Ethernet communication module

1 hr

183

Install Modbus Master/Slave Communication Module

2 hrs 15 Oct '16 15 Oct '16 125,94 hrs

184

Install Power Monitor PM500

2 hrs 15 Oct '16 15 Oct '16 7 hrs

185

Internal Wiring (Ethernet, RS-485, UPS supply dan existing internal wiring)

3 hrs 15 Oct '16 15 Oct '16 7 hrs

186

Continuity check

3 hrs 16 Oct '16 16 Oct '16 7 hrs

187

Logic and address verification

4 hrs 16 Oct '16 16 Oct '16 7 hrs

188

Quality Inspection

1 hr

16 Oct '16 16 Oct '16 7 hrs

189

House keeping

1 hr

16 Oct '16 16 Oct '16 7 hrs

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

TOP-2

TOP-2

TOP-2

TOP-2

TOP-2
15 Oct '16 15 Oct '16 126,94 hrs
TOP-2

TOP-2

TOP-2

TOP-2

TOP-2

TOP-2

TOP-2

TOP-2
190

Modifikasi Synchronize Panel (WP-5C)

25 hrs 15 Oct '16 16 Oct '16 7 hrs

191

Shut down process & Isolation Area

2 hrs 15 Oct '16 15 Oct '16 7 hrs

192

PTW, PJSM

1 hr

193

Glanding cable pada cover atas synchronize Panel

2 hrs 15 Oct '16 15 Oct '16 131,94 hrs

194

Back Up Existing Logic

2 hrs 15 Oct '16 15 Oct '16 7 hrs

195

Dismantle semua kabel pada door panel

2 hrs 15 Oct '16 15 Oct '16 7 hrs

196

Modifikasi door synchronize Panel

2 hrs 15 Oct '16 15 Oct '16 7 hrs

197

Mengganti PLC Controller dengan SLC 5/05 1747-L553

2 hrs 15 Oct '16 15 Oct '16 7 hrs

198

Install ETAP Ethernet communication module

1 hr

199

Install Modbus Master/Slave Communication Module

2 hrs 15 Oct '16 15 Oct '16 7 hrs

200

Internal Wiring (Ethernet, RS-485, UPS supply dan existing internal wiring)

3 hrs 15 Oct '16 15 Oct '16 7 hrs

201

Continuity check

3 hrs 16 Oct '16 16 Oct '16 7 hrs

202

Logic and address verification

4 hrs 16 Oct '16 16 Oct '16 7 hrs

203

Quality Inspection

1 hr

16 Oct '16 16 Oct '16 7 hrs

204

House keeping

1 hr

16 Oct '16 16 Oct '16 7 hrs

TOP-1
15 Oct '16 15 Oct '16 7 hrs
TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1
15 Oct '16 15 Oct '16 126,94 hrs
TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1

TOP-1
205

Modifikasi UCP GTG 82SEG-403 (WP-5D)

10 hrs 16 Oct '16 16 Oct '16 6,02 hrs

206

Glanding Hardwire (CCCT, KW Load Share,Voltage & Speed Adjustment )


Ethernet (GTG Parameter) Cable pada top panel 82ZEC403

2 hrs 16 Oct '16 16 Oct '16 6,02 hrs

207

Terminasi Ethernet cable pada panel UCP 82ZEC-403

2 hrs 16 Oct '16 16 Oct '16 6,02 hrs

208

Terminasi Hardwire cable pada panel UCP 82ZEC-403

2 hrs 16 Oct '16 16 Oct '16 6,02 hrs

209

Continuity check

2 hrs 16 Oct '16 16 Oct '16 6,02 hrs

210

Logic and mapping verification

3 hrs 16 Oct '16 16 Oct '16 6,02 hrs

211

Quality Inspection

2 hrs 16 Oct '16 16 Oct '16 6,02 hrs

212

House keeping

1 hr

TOP

TOP

TOP

TOP

TOP

TOP
16 Oct '16 16 Oct '16 6,02 hrs
TOP
213

Terminasi Kabel bus Tie PT at existing bus 82ZEN-001 (WP-5E)

5 hrs 15 Oct '16 15 Oct '16 27 hrs

214

Terminasi Kabel bus Tie di 82ZEN-001 (3C+G-10 AWG)

2 hrs 15 Oct '16 15 Oct '16 27 hrs

215

Continuity check

1 hr

15 Oct '16 15 Oct '16 27 hrs

216

Quality Inspection

1 hr

15 Oct '16 15 Oct '16 27 hrs

217

House keeping

1 hr

15 Oct '16 15 Oct '16 27 hrs

SKP 1

SKP 1

SKP 1

SKP 1
218

219

220

Terminasi Kabel pada PCR-1 & PCR-2 MCC C & D dan Switchgear 82ZEN-001
(WP-6)
Terminasi Kabel pada PCR-1 Switchgear 82ZEN-001 (WP-06A)

24 hrs 15 Oct '16 16 Oct '16 111,94 hrs

5 hrs 15 Oct '16 15 Oct '16 130,94 hrs

Glanding kabel Modbus communication di switchgear 108-PSW2-01


(C-COM-108PSW201-1)

1 hr

15 Oct '16 15 Oct '16 130,94 hrs


SKP 1

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 5

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
221

Terminasi kabel Modbus communication di switchgear 108-PSW2-01


(C-COM-108PSW201-1)

1 hr

15 Oct '16 15 Oct '16 130,94 hrs

222

Continuity check

1 hr

15 Oct '16 15 Oct '16 130,94 hrs

223

Quality Inspection

1 hr

15 Oct '16 15 Oct '16 130,94 hrs

224

House Keeping

1 hr

15 Oct '16 15 Oct '16 130,94 hrs

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

SKP 1

SKP 1

SKP 1

SKP 1
225

Terminasi Kabel pada PCR-2 (MCC C,D & E) (WP-06B)

24 hrs 15 Oct '16 16 Oct '16 111,94 hrs

226

Glanding dan Terminasi Kabel dari PMS ke Fuel Gas Heater PCR-2
(C-I-60HEC001A)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

227

Glanding dan Terminasi dari Kabel dari PMS ke Fuel Gas Heater PCR-2
(C-I-60HEC001B)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

228

Terminasi dan Glanding Kabel dari PMS ke Immersion Heater PCR-2


(C-I-82HAP403)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

229

Glanding dan Terminasi Kabel dan Glanding dari PMS ke Enclosure Fan
PCR-2 (C-I-82VDE4031A)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

230

Terminasi Kabel dan Glanding dari PMS ke Enclosure Fan PCR-2


(C-I-82VDE4031B)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

231

Glanding dan Terminasi Kabel dari PMS ke LO cooler fan PCR-2


(C-I-82VDE4032)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

232

Glanding dan Terminasi Kabel dari PMS ke LO cooler fan PCR-2


(C-I-82VDE4031)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

233

Glanding dan Terminasi Kabel dari PMS ke Inlet Cooler PCR-2


(C-I-20VDE201A1)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

234

Glanding dan Terminasi Kabel dari PMS ke Inlet Cooler PCR-2


(C-I-20VDE201B1)

2 hrs 15 Oct '16 15 Oct '16 111,94 hrs

235

Continuity check

11 hrs 15 Oct '16 15 Oct '16 111,94 hrs

236

Quality Inspection

11 hrs 15 Oct '16 15 Oct '16 111,94 hrs

237

Glanding dan Terminasi Kabel dari PMS ke Inlet Cooler PCR-2


(C-I-20VDE201A2)

2 hrs 16 Oct '16 16 Oct '16 111,94 hrs

238

Glanding dan Terminasi Kabel dari PMS ke Inlet Cooler PCR-2


(C-I-20VDE201B2)

2 hrs 16 Oct '16 16 Oct '16 111,94 hrs

239

Glanding dan Terminasi Kabel dari PMS ke Glycol Contactor


(C-I-47PEX202-A)

2 hrs 16 Oct '16 16 Oct '16 111,94 hrs

240

Glanding dan Terminasi Kabel dari PMS ke Glycol Contactor


(C-I-47PEX202-B)

2 hrs 16 Oct '16 16 Oct '16 111,94 hrs

241

Continuity check

5 hrs 16 Oct '16 16 Oct '16 111,94 hrs

242

Quality Inspection

5 hrs 16 Oct '16 16 Oct '16 111,94 hrs

243

House keeping

1 hr

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1
16 Oct '16 16 Oct '16 111,94 hrs
SKP 1
244

Re-Route AC Power cable di PCR-2 (WP-7)

11 hrs 15 Oct '16 15 Oct '16 124,94 hrs

245

Shut down process & Isolation Area

2 hrs 15 Oct '16 15 Oct '16 124,94 hrs

246

PTW, PJSM

1 hr

247

Un-terminate power cable AC di MCC D

2 hrs 15 Oct '16 15 Oct '16 124,94 hrs

248

Pulback dan dressing cable menuju MCC E

3 hrs 15 Oct '16 15 Oct '16 124,94 hrs

249

Terminasi power cable AC di MCC E

2 hrs 15 Oct '16 15 Oct '16 124,94 hrs

250

Quality Inspection

1 hr

15 Oct '16 15 Oct '16 124,94 hrs

251

House keeping

1 hr

15 Oct '16 15 Oct '16 124,94 hrs

SKP 1
15 Oct '16 15 Oct '16 124,94 hrs
SKP 1

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1
252

PMS Function Test (WP-8)

103,94 17 Oct '16 23 Oct '16 0 hrs


hrs

253

Synchronizing, Load Sharing GTG 403 - GTG 404 & GTG 405 (WP-8A)

23,94 17 Oct '16 18 Oct '16 0 hrs


hrs

254

Preparation for warming up GTG, IA Compressor, Fuel Gas Heater

2 hrs 17 Oct '16 17 Oct '16 0 hrs

255

CGCM Fine tuning by Solar

8 hrs 17 Oct '16 17 Oct '16 93,94 hrs

256

Mapping Address Verification on PMS

8 hrs 17 Oct '16 17 Oct '16 0 hrs

257

Warming Up and Running Generator GTG 403 and connect to load bank

1 hr

258

Governor tuning untuk GTG 403 dalam kondisi berbeban

3 hrs 17 Oct '16 17 Oct '16 0 hrs

259

Check trend voltage dan speed adjustment

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

260

Open bus tie breaker PCR 2 dan PCR 3, open feeder to load bank

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

261

Warming up generator GTG 404 & 405

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

262

Check parameter generator GTG 403, GTG 404 & 405 di PMS dengan
kondisi 403 masuk ke bus, 404 dan 405 tidak masuk ke bus.

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

263

Close incoming breaker GTG 404

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

264

Check parameter pada bus

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

TOP

TOP

TOP
17 Oct '16 17 Oct '16 0 hrs
TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 6

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
265

Initiate Bus Synchronization dari PMS

2 hrs 17 Oct '16 18 Oct '16 87,94 hrs

266

Initiate GTG 405 to bus Synchronization dari PMS

2 hrs 17 Oct '16 18 Oct '16 0 hrs

267

Check Parameter System

1 hr

268

Test kondisi generator load share mode Isoch-Isoch

2 hrs 18 Oct '16 18 Oct '16 84,94 hrs

269

Check parameter system

2 hrs 18 Oct '16 18 Oct '16 84,94 hrs

270

Lakukan variasi beban

2 hrs 18 Oct '16 18 Oct '16 84,94 hrs

271

Check & Record trending dari parameter system

1,94
hrs

272

Test kondisi generator load share mode Isoch-Droop

2 hrs 18 Oct '16 18 Oct '16 83 hrs

273

Check parameter system

2 hrs 18 Oct '16 18 Oct '16 83 hrs

274

Lakukan variasi beban

2 hrs 18 Oct '16 18 Oct '16 83 hrs

275

Lakukan function test untuk voltage-speed adjusment

2 hrs 18 Oct '16 18 Oct '16 83 hrs

276

Check & Record trending dari parameter system

2 hrs 18 Oct '16 18 Oct '16 0 hrs

277

Test kondisi generator load share mode Isoch-Baseload

2 hrs 18 Oct '16 18 Oct '16 81 hrs

278

Check parameter system

2 hrs 18 Oct '16 18 Oct '16 81 hrs

279

Lakukan variasi beban

2 hrs 18 Oct '16 18 Oct '16 81 hrs

280

Lakukan function test untuk voltage-speed adjusment

2 hrs 18 Oct '16 18 Oct '16 81 hrs

281

Check & Record trending dari parameter system

2 hrs 18 Oct '16 18 Oct '16 0 hrs

282

Shutdown Process

1 hr

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

TOP

TOP
18 Oct '16 18 Oct '16 0 hrs
TOP

TOP

TOP

TOP
18 Oct '16 18 Oct '16 0 hrs
TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP
18 Oct '16 18 Oct '16 0 hrs
TOP
283

Synchronizing, Load Sharing GTG 403 - GTG 404- GTG 405 & EDG 406
(WP-8B)

13 hrs 20 Oct '16 21 Oct '16 0 hrs

284

Warming Up Generator EDG 406

1 hr

20 Oct '16 20 Oct '16 0 hrs

285

Warming up generator GTG 403, 404 & 405

1 hr

20 Oct '16 20 Oct '16 0 hrs

286

Close incoming breaker GTG 403, GTG 404

1 hr

20 Oct '16 20 Oct '16 0 hrs

287

Initiate Generator Synchronization dari PMS (82ZEN-001 & 82ZEN-004)

2 hrs 20 Oct '16 20 Oct '16 0 hrs

288

Close incoming breaker EDG 406

2 hrs 20 Oct '16 21 Oct '16 0 hrs

289

Initiate Bus Synchronization dari PMS (82ZEN-004 & 84ZEN-006)

1 hr

21 Oct '16 21 Oct '16 39 hrs

290

Warming up GTG 405

1 hr

21 Oct '16 21 Oct '16 39 hrs

291

Initiate Synchronization GTG 405 to bus

2 hrs 21 Oct '16 21 Oct '16 0 hrs

292

Test kondisi generator load share mode Isoch-Isoch

2 hrs 21 Oct '16 21 Oct '16 37 hrs

293

Check parameter system

2 hrs 21 Oct '16 21 Oct '16 37 hrs

294

Lakukan variasi beban

2 hrs 21 Oct '16 21 Oct '16 37 hrs

295

Check & Record trending dari parameter system

2 hrs 21 Oct '16 21 Oct '16 0 hrs

296

Test kondisi generator load share mode Isoch-Droop

2 hrs 21 Oct '16 21 Oct '16 35 hrs

297

Check parameter system

2 hrs 21 Oct '16 21 Oct '16 35 hrs

298

Lakukan variasi beban

2 hrs 21 Oct '16 21 Oct '16 35 hrs

299

Lakukan function test untuk voltage-speed adjusment

2 hrs 21 Oct '16 21 Oct '16 35 hrs

300

Check & Record trending dari parameter system

2 hrs 21 Oct '16 21 Oct '16 0 hrs

301

Test kondisi generator load share mode Isoch-Baseload

2 hrs 21 Oct '16 21 Oct '16 34 hrs

302

Check parameter system

2 hrs 21 Oct '16 21 Oct '16 34 hrs

303

Lakukan variasi beban

2 hrs 21 Oct '16 21 Oct '16 34 hrs

304

Lakukan function test untuk voltage-speed adjusment

2 hrs 21 Oct '16 21 Oct '16 34 hrs

305

Check & Record trending dari parameter system

2 hrs 21 Oct '16 21 Oct '16 0 hrs

306

Shutdown process

1 hr

Add Work Pack

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP
21 Oct '16 21 Oct '16 0 hrs
TOP
307

308

Load Shedding PCR 2 & PCR 3 (WP-8C)

14 hrs 18 Oct '16 19 Oct '16 0 hrs

Start up and synchronize GTG 404 and GTG 403

2 hrs 18 Oct '16 18 Oct '16 0 hrs


TOP

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 7

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
309

Preset Parameter Load Shedding

1 hr

310

Load inhibit test

3 hrs 18 Oct '16 19 Oct '16 0 hrs

311

Loop Check

2 hrs 18 Oct '16 19 Oct '16 0 hrs

312

Verifikasi HMI

1 hr

313

Gradual Load shedding Test

2 hrs 19 Oct '16 19 Oct '16 0 hrs

314

Loop check

2 hrs 19 Oct '16 19 Oct '16 0 hrs

315

Verifikasi HMI

2 hrs 19 Oct '16 19 Oct '16 0 hrs

316

Fast Load Shedding Test

2 hrs 19 Oct '16 19 Oct '16 0 hrs

317

Loop check

2 hrs 19 Oct '16 19 Oct '16 0 hrs

318

Verifikasi HMI

2 hrs 19 Oct '16 19 Oct '16 0 hrs

319

House Keeping

1 hr

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

18 Oct '16 18 Oct '16 74 hrs


TOP

TOP

TOP
19 Oct '16 19 Oct '16 70 hrs
TOP

TOP

TOP

TOP

TOP

TOP

TOP
19 Oct '16 19 Oct '16 0 hrs
TOP
320

Synchronizing, Load Sharing GEG 401 - GTG 403 (WP-8D)

16 hrs 21 Oct '16 22 Oct '16 0 hrs

321

Warming Up Generator GEG 401

1 hr

21 Oct '16 21 Oct '16 0 hrs

322

Warming up generator GTG 403

1 hr

21 Oct '16 21 Oct '16 28 hrs

323

Check parameter generator GEG 401, GTG 403

1 hr

21 Oct '16 21 Oct '16 28 hrs

324

Close incoming breaker GEG 401, GTG 403

1 hr

21 Oct '16 21 Oct '16 28 hrs

325

Check parameter pada bus

1 hr

21 Oct '16 21 Oct '16 28 hrs

326

Close bustie 108PSW2-01 to 82ZEN-001

1 hr

21 Oct '16 21 Oct '16 28 hrs

327

Initiate Generator Synchronization bus 82ZEN-001 to 82ZEN-004

3 hrs 21 Oct '16 21 Oct '16 0 hrs

328

Check Parameter System

1 hr

21 Oct '16 21 Oct '16 25 hrs

329

open incomer GTG 403

1 hr

21 Oct '16 21 Oct '16 25 hrs

330

Check parameter generator

1 hr

21 Oct '16 21 Oct '16 25 hrs

331

Check Parameter Bus

1 hr

21 Oct '16 21 Oct '16 25 hrs

332

Initiate GTG 403 Synchronization to Bus

2 hrs 21 Oct '16 22 Oct '16 0 hrs

333

open incomer GEG 401

1 hr

22 Oct '16 22 Oct '16 23 hrs

334

Check parameter generator

1 hr

22 Oct '16 22 Oct '16 23 hrs

335

Check Parameter Bus

1 hr

22 Oct '16 22 Oct '16 23 hrs

336

Initiate GEG 401 Synchronization to Bus

3 hrs 22 Oct '16 22 Oct '16 0 hrs

337

Test kondisi generator load share mode Isoch-Isoch

2 hrs 22 Oct '16 22 Oct '16 20 hrs

338

Check parameter system

2 hrs 22 Oct '16 22 Oct '16 20 hrs

339

Lakukan variasi beban

2 hrs 22 Oct '16 22 Oct '16 20 hrs

340

Check & Record trending dari parameter system

2 hrs 22 Oct '16 22 Oct '16 0 hrs

341

Test kondisi generator load share mode Isoch-Droop

2 hrs 22 Oct '16 22 Oct '16 18 hrs

342

Check parameter system

2 hrs 22 Oct '16 22 Oct '16 18 hrs

343

Lakukan variasi beban

3 hrs 22 Oct '16 22 Oct '16 0 hrs

344

Lakukan function test untuk voltage-speed adjusment

2 hrs 22 Oct '16 22 Oct '16 17 hrs

345

Check & Record trending dari parameter system

2 hrs 22 Oct '16 22 Oct '16 0 hrs

346

Test kondisi generator load share mode Isoch-Baseload

2 hrs 22 Oct '16 22 Oct '16 15 hrs

347

Check parameter system

2 hrs 22 Oct '16 22 Oct '16 15 hrs

348

Lakukan variasi beban

3 hrs 22 Oct '16 22 Oct '16 0 hrs

349

Lakukan function test untuk voltage-speed adjusment

2 hrs 22 Oct '16 22 Oct '16 14 hrs

350

Check & Record trending dari parameter system

1 hr

351

Shutdown Process

Add Work Pack

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP
22 Oct '16 22 Oct '16 0 hrs
TOP
0,5 hrs 22 Oct '16 22 Oct '16 0 hrs
TOP
352

Synchronizing, Load Sharing GEG 401 - GTG 404- GTG 405 (WP-8E)

Project: Schedule Tie-In shutdown oct

15,5
hrs

19 Oct '16 20 Oct '16 0 hrs

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 8

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
353

Warming Up Generator GEG 401

1 hr

354

Governor tuning untuk GEG 401

4 hrs 19 Oct '16 19 Oct '16 0 hrs

355

Check trend voltage dan speed adjustment

2 hrs 19 Oct '16 19 Oct '16 0 hrs

356

Close incoming breaker GEG 401, GTG 404

1 hr

19 Oct '16 19 Oct '16 58 hrs

357

Check parameter pada bus

1 hr

19 Oct '16 19 Oct '16 58 hrs

358

Close bustie 108PSW2-01 to 82ZEN-001

1 hr

19 Oct '16 19 Oct '16 0 hrs

359

Initiate Generator Synchronization bus 82ZEN-001 to 82ZEN-004

1 hr

19 Oct '16 19 Oct '16 57 hrs

360

Check Parameter System

1 hr

19 Oct '16 19 Oct '16 57 hrs

361

Warming up generator GTG 405

1 hr

19 Oct '16 19 Oct '16 57 hrs

362

Check parameter generator GTG 405

1 hr

19 Oct '16 19 Oct '16 0 hrs

363

Check parameter generator

1 hr

19 Oct '16 20 Oct '16 56 hrs

364

Check Parameter Bus

1 hr

19 Oct '16 20 Oct '16 56 hrs

365

Initiate GEG 401 Synchronization to Bus

2 hrs 19 Oct '16 20 Oct '16 0 hrs

366

Test kondisi generator load share mode Isoch-Isoch

2 hrs 20 Oct '16 20 Oct '16 54 hrs

367

Check parameter system

2 hrs 20 Oct '16 20 Oct '16 0 hrs

368

Lakukan variasi beban

2 hrs 20 Oct '16 20 Oct '16 53 hrs

369

Check & Record trending dari parameter system

2 hrs 20 Oct '16 20 Oct '16 0 hrs

370

Test kondisi generator load share mode Isoch-Droop

2 hrs 20 Oct '16 20 Oct '16 51 hrs

371

Check parameter system

2 hrs 20 Oct '16 20 Oct '16 0 hrs

372

Lakukan variasi beban

3 hrs 20 Oct '16 20 Oct '16 47 hrs

373

Lakukan function test untuk voltage-speed adjusment

2 hrs 20 Oct '16 20 Oct '16 48 hrs

374

Check & Record trending dari parameter system

2 hrs 20 Oct '16 20 Oct '16 48 hrs

375

Test kondisi generator load share mode Isoch-Baseload

2 hrs 20 Oct '16 20 Oct '16 48 hrs

376

Check parameter system

2 hrs 20 Oct '16 20 Oct '16 0 hrs

377

Lakukan variasi beban

2 hrs 20 Oct '16 20 Oct '16 47 hrs

378

Lakukan function test untuk voltage-speed adjusment

2 hrs 20 Oct '16 20 Oct '16 47 hrs

379

Check & Record trending dari parameter system

2 hrs 20 Oct '16 20 Oct '16 47 hrs

380

Check Parameter System

2 hrs 20 Oct '16 20 Oct '16 0 hrs

381

Shutdown process

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

19 Oct '16 19 Oct '16 0 hrs


TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP
0,5 hrs 20 Oct '16 20 Oct '16 0 hrs
TOP
382

Load Shedding PCR 2 & PCR 3 (GEG Scheme) (WP-8F)

14 hrs 22 Oct '16 23 Oct '16 0 hrs

383

Start up and synchronize GEG 401 and GTG 404

2 hrs 22 Oct '16 22 Oct '16 0 hrs

384

Preset parameter load shedding

1 hr

385

Load inhibit test

3 hrs 22 Oct '16 22 Oct '16 0 hrs

386

Loop Check

2 hrs 22 Oct '16 23 Oct '16 0 hrs

387

Verifikasi HMI

2 hrs 22 Oct '16 23 Oct '16 0 hrs

388

Gradual Load shedding Test

2 hrs 23 Oct '16 23 Oct '16 0 hrs

389

Loop check

2 hrs 23 Oct '16 23 Oct '16 0 hrs

390

Verifikasi HMI

2 hrs 23 Oct '16 23 Oct '16 0 hrs

391

Fast Load Shedding Test

2 hrs 23 Oct '16 23 Oct '16 0 hrs

392

Loop check

2 hrs 23 Oct '16 23 Oct '16 0 hrs

393

Verifikasi HMI

2 hrs 23 Oct '16 23 Oct '16 0 hrs

394

House Keeping

1 hr

Add Work Pack

TOP
22 Oct '16 22 Oct '16 11 hrs
TOP

TOP

TOP

TOP

395

396

INSTRUMENT

38 hrs 15 Oct '16 17 Oct '16 0 hrs

Replacement of ESDEDP Box (WP-3)

Project: Schedule Tie-In shutdown oct

23 Oct '16 23 Oct '16 0 hrs

23 hrs 15 Oct '16 16 Oct '16 112,94 hrs

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 9

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
397

PJSM

398

Disconnect all cables connecting to equipment on desk-4.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

399

Move them to supervisor room (temporary).

0,5 hrs 15 Oct '16 15 Oct '16 132,94 hrs

400

Isolate existing power cable (desk-4) at existing PCR-1 power socket.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

401

Demolish operator desk (desk-4) and move them to COPI warehouse.

1,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

402

Disconnect and isolate all cables to existing ESD/EDP box. Also, disconnect and
isolate the cables at the other end too (SIS marshaliing, PCR-2 instrument
room).

403

Demolish existing ESD/EDP box (move them to COPI's maintenance room).

404

Install new operator desk-4.

405

Install new ESD/EDP box on new operator workstation desks.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

406

Connect multipair cables at both ends, ones to ESD/EDP box and ones to
79-ZJM-002.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

407

Put back all equipment on desk-4.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

408

Plug power cables of equipment to power sockets at new desk-4.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

409

Connect grounding cables to new desk-4.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

410

Connect all connecting cables on new operator desk-4.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

411

Isolate cable which are supplying power for new desk-3 at UPS PCR-2.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

412

Connect cable jumper from feeder MCB new desk-3 to feeder MCB new desk-4. 0,5 hrs 15 Oct '16 15 Oct '16 125,44 hrs
Ensure that ferrule and shield tube are available.

413

Release the isolation for cable power new desk-3.

0,5 hrs 15 Oct '16 15 Oct '16 125,44 hrs

414

Power up equipment on new desk-4.

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

415

Install stanchion for mounting OWS4 monitors (42).

3 hrs 16 Oct '16 16 Oct '16 112,94 hrs

416

Install 42 monitors.

2 hrs 16 Oct '16 16 Oct '16 112,94 hrs

417

Connect all ethernet and VGA cables to OWS4 monitors and KVMs on new
operator desk.

1 hr

418

Perform loop test afterwards for ESD/EDP box.

0 hrs 16 Oct '16 16 Oct '16 112,94 hrs

419

Integration of New and Existing PCSSIS (WP-4)

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

2 hrs 15 Oct '16 15 Oct '16 112,94 hrs

SKP 1

SKP 1

SKP 1

SKP 1
1 hr

15 Oct '16 15 Oct '16 112,94 hrs


SKP 1

0,5 hrs 15 Oct '16 15 Oct '16 112,94 hrs

2 hrs 15 Oct '16 15 Oct '16 112,94 hrs

16 Oct '16 16 Oct '16 112,94 hrs

16/10
38 hrs 15 Oct '16 17 Oct '16 0 hrs

420

PJSM

2 hrs 15 Oct '16 15 Oct '16 0 hrs

421

Shutdown AWS1 and AWS2 servers, then disconnect all connecting cables
(ethernet and power) from them.

1 hr

422

Relocate and install AWS1 and AWS2 (including servers, monitors, KVMs,
2 hrs 15 Oct '16 15 Oct '16 0 hrs
keyboards, and mouses) to PCR-3 instrument room (87-ZJN-001 for servers and
workstation desk for monitors and KVMs). Previously, the servers are installed in
87-ZJN-002 (PCR-1 control
Connect ethernet cables at both ends, between: 1. AWS1 server and
0,5 hrs 15 Oct '16 15 Oct '16 0 hrs
SUM-CTRL-SW1 2. VIM switch and SUM-FTAC-01

PTCS,SKP (Worker)
15 Oct '16 15 Oct '16 0 hrs
PTCS,SKP (Worker)

423

PTCS,SKP (Worker)

PTCS,SKP (Worker)
424

Disconnect all existing patch cord at existing fiber optic patch panel inside
100-SIS-001 (PCR-2 instrument room).

0,5 hrs 15 Oct '16 15 Oct '16 129,94 hrs

425

Identify from-to of existing fiber optic (to PCR-1, to PCR-2, to well #6, and to well
#7). Reconnect patch cord from PCR-1 to well #6.

2 hrs 15 Oct '16 15 Oct '16 0 hrs

426

Connect patch cords as such SIS communication is ring-looped between


PCR-3, PCR-2, and well #7 and ensure every connection integrity is GOOD on
DeltaV diagnostics.

1 hr

427

Delete existing ESD & EDP tags from existing SLS and disable the channels at 0,5 hrs 15 Oct '16 15 Oct '16 127,94 hrs
EWS.

428

Import new IO Configuration SU_SIS05 and SU_SIS06 to existing database at


EWS.

0,5 hrs 15 Oct '16 15 Oct '16 0 hrs

429

Commission, Auto Sense, and download SU_SIS05 and SU_SIS06 from EWS.

0,5 hrs 15 Oct '16 15 Oct '16 0 hrs

430

Commission and download all new SLS Cards on SU_SIS05 and SU_SIS06
from EWS.

431

Import 2 new ESD modules.

0,5 hrs 15 Oct '16 15 Oct '16 0 hrs

432

Import modified existing ESD_DU module.

0,5 hrs 15 Oct '16 15 Oct '16 124,44 hrs

433

Import the remaining 10 new affected new modules and the 20 new modules
which are assigned at the same SLS cards include named set.

1 hr

15 Oct '16 15 Oct '16 0 hrs

434

Download new SLS cards in accordance to module importing progress from


EWS

1 hr

15 Oct '16 15 Oct '16 0 hrs

435

Import SIS named sets of the 11 modified existing modules to existing database. 0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

436

Import all remaining of the 11 modified existing modules to existing database.

437

Import new graphics which are related to 11 modified existing module & 32 new
modules.

438

Verify diagnostic for all existing SLS cards before C&E test.

1 hr

16 Oct '16 16 Oct '16 97,94 hrs

439

Update alarm priorities of existing modules.

1 hr

16 Oct '16 16 Oct '16 97,94 hrs

440

Add sumpal area ESD area to alarm and event to EWS, OWS4, and OWS5.

PTCS,SKP (Worker)

PTCS,SKP (Worker)
15 Oct '16 15 Oct '16 0 hrs
PTCS,SKP (Worker)

PTCS

PTCS

PTCS
2 hrs 15 Oct '16 15 Oct '16 0 hrs
PTCS

PTCS

PTCS

PTCS

PTCS

Software Eng (PTCS)


1 hr

15 Oct '16 15 Oct '16 0 hrs


Software Eng (PTCS)

0,5 hrs 16 Oct '16 16 Oct '16 97,94 hrs


Software Eng (PTCS)

Software Eng (PTCS)

Software Eng (PTCS)


0,5 hrs 16 Oct '16 16 Oct '16 97,94 hrs
Software Eng (PTCS)

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 10

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
441

Conduct C&E test via logic and observe through HMI.

442

Apply bypass according to bypass list (refer to appendix ). Bypass will be


released when all field devices are running normally.

1 hr

443

Modify set points of the transmitters as per existing set points.

2 hrs 17 Oct '16 17 Oct '16 97,94 hrs

444

Import sumpal compression graphic to EWS.

445

Reconfigure temporary EWS to become OWS5.

1 hr

446

Verify existing AWS and AWS2 functional (alarm & events, DeltaV analyze, PI
OPC).

2 hrs 17 Oct '16 17 Oct '16 97,94 hrs

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

13 hrs 16 Oct '16 17 Oct '16 97,94 hrs


Software Eng (PTCS)

447

17 Oct '16 17 Oct '16 97,94 hrs

0,5 hrs 17 Oct '16 17 Oct '16 100,44 hrs

Modification of existing UCP GTG (82-ZJP-403) (WP-5)

17 Oct '16 17 Oct '16 97,94 hrs

6 hrs 15 Oct '16 15 Oct '16 26 hrs

448

PJSM

2 hrs 15 Oct '16 15 Oct '16 26 hrs

449

Install cable-glands on top of the existing UCP GTG panel. Pass cables (coaxial
and ethernet) right through them.

1 hr

15 Oct '16 15 Oct '16 26 hrs

450

Crimp RJ-45 for ethernet cables and BNC for coaxial cables.

1 hr

15 Oct '16 15 Oct '16 26 hrs

451

Install/plug controlnet module at the existing UCP GTG and connect new
controlnet cable (to GTG-404) to the module.

0,5 hrs 15 Oct '16 15 Oct '16 26 hrs

452

Install/plug FMIM module at the existing UCP GTG and connect new ethernet
cable (from CMS) to the module.

0,5 hrs 15 Oct '16 15 Oct '16 26 hrs

453

Install/plug ethernet module at the existing UCP GTG and connect new ethernet 0,5 hrs 15 Oct '16 15 Oct '16 26 hrs
cables (from PMS) to the module.

454

Upgrade HMI graphic on UCP.

All Parties

SKP 1

SKP 1

Vendor Solar

Vendor Solar, Vendor GE

Vendor Solar
0,5 hrs 15 Oct '16 15 Oct '16 26 hrs
Vendor Solar
455

Modification of PCS communication to existing UCP GEG and UCP Glycol


(WP-6)

6,5 hrs 15 Oct '16 15 Oct '16 25,5 hrs

456

PJSM

2 hrs 15 Oct '16 15 Oct '16 25,5 hrs

457

Install new serial card (RS-485) at UCP GEG 401, GEG 402 and synchronizing
panel.

0,5 hrs 15 Oct '16 15 Oct '16 25,5 hrs

458

Connect new RS 485 cable from existing UCPs (synchronizing panel, GEG-2,
and GEG-2) to existing PCS cabinet with daisy chain configuration.

0,5 hrs 15 Oct '16 15 Oct '16 25,5 hrs

459

Modify DH+ daisy-chain wiring from BMS glycol package train #1 directly to KF2 0,5 hrs 15 Oct '16 15 Oct '16 25,5 hrs
in PCR-1

460

Termination at existing PCS serial card in cabinet PCR-1

461

Verify serial communication at PCS

462

Connect new ethernet cable from PMS to DAQ/FTAC switch.

All Parties

Vendor TOP

Vendor TOP, SKP

Vendor TOP, SKP


0,5 hrs 15 Oct '16 15 Oct '16 25,5 hrs
Vendor PTCS, SKP
2 hrs 15 Oct '16 15 Oct '16 25,5 hrs
Vendor PTCS, SKP
0,5 hrs 15 Oct '16 15 Oct '16 25,5 hrs
Vendor TOP, SKP
463

Replacement of Pressure Switch (101-PSHL-011) at Sumpal Well #1B (WP-7)

10 hrs 15 Oct '16 15 Oct '16 125,94 hrs

464

PJSM

3 hrs 15 Oct '16 15 Oct '16 125,94 hrs

465

Existing Wellhead Control Panel shall be tested (especially signal comment


related to these PSH/L) to ensure that existing Well Head Control Panel still
working properly.

1 hr

466

Close 101-ESDV-011 by manually Hydraulic self contained well head safety


valve, close valve 8-EF and depressurize line of 8-GP-101-002-EF1.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

467

Checking and ensure the process connection of field instrument which will be
installed in accordance with the requirement.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

468

Close the existing 2-way valve manifold, then open the bleed of 2-way valve
manifold to ensure it is completely depressurized.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

469

Close the existing valve in the upstream of PSH/L as a hydraulic supply line to
PSH/L and then start to bleed all pressure to zero.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

470

Apply teflon tape and/or teflon (PTFE) paste to NPT mounting connection.
Apply only to the male threads. (Do not lap the Teflon tape over the end of the
threads. Do not apply pipe dope to the female threads of the block. Sensors
have small orifices than
Install new PSH/L and associated tubing and fitting as per hook-up for pressure
lead piping and tubing. Install the high and low pressure sensor in the top
female connection.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

472

Ensure all installed tubing connection are in correct position/ port.

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs

473

Inspection and testing as per MFR's procedure i.e. Inspection procedure


(including leak test) (same activities with no.2 on above).

474

After test and everything working properly, then PSH/L ready to operate and
open the valve on the upstream of PSH/L to allow the line can be pressurized
and ready to operate.

All Parties
15 Oct '16 15 Oct '16 125,94 hrs
COPI Operation

COPI Operation

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

471

Vendor Sarana Instrument, SKP


0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs
Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP


2 hrs 15 Oct '16 15 Oct '16 125,94 hrs
Vendor Sarana Instrument, SKP

475

Replacement of Pressure Switches (3M-PSH/L-1002 & 3M-PSH/L-1003) at


Sumpal Well #6 (WP-8A)

0,5 hrs 15 Oct '16 15 Oct '16 125,94 hrs


Vendor Sarana Instrument, SKP
9,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

476

PJSM

2 hrs 15 Oct '16 15 Oct '16 126,44 hrs

477

Existing Wellhead Control Panel shall be tested (especially signal comment


related to these PSH/L) to ensure that existing Well Head Control Panel still
working properly.

1 hr

478

Close 3M-SDV-0001 & 3M-SDV-0002 by manually, ESD panel 3M-ZJP-001.


Close valve of 1- GA-DF-4-1, 6-GA-DF-4-2, 10-GA-DF-4-2 and depressurize
line of 10-GP-DF-1-3M-0003-P.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

479

Checking and ensure the process connection of field instrument which will be
installed in accordance with the requirement.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

480

Close the existing 2-way valve manifold, then open the bleed of 2-way valve
manifold to ensure it is completely depressurized.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

481

Close the isolation valve/monoflange, then open the bleed valve to ensure it is
completely depressurized. And, close valve in upstream side of PSH/L as a
pneumatic supply line to PSH/L and bleed all pressure to zero.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

482

Dismantle existing PSH/L by disassembly tubing and fitting.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

483

Apply teflon tape and/or teflon (PTFE) paste to NPT mounting connection.
Apply only to the male threads. (Do not lap the Teflon tape over the end of the
threads. Do not apply pipe dope to the female threads of the block. Sensors
have small orifices than
Install new PSH/L and required associated tube and fitting as per hook-up for
pressure lead piping and tubing. Install test nipple and block valve in the top of
female connection.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

All Parties
15 Oct '16 15 Oct '16 126,44 hrs
COPI Operation

COPI Operation

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

484

Project: Schedule Tie-In shutdown oct

Vendor Sarana Instrument, SKP


0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs
Vendor Sarana Instrument, SKP

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 11

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
485

Ensure all installed tubing connection are in correct position/ port.

486

Inspection and testing as per MFR's procedure i.e. Inspection procedure


(including leak test) (same activities with no.2 on above).

487

After test and everything working properly, then PSH/L ready to operate and
open the valve on the upstream of PSH/L to allow the line can be pressurized
and ready to operate.

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs


Vendor Sarana Instrument, SKP
2 hrs 15 Oct '16 15 Oct '16 126,44 hrs
Vendor Sarana Instrument, SKP

488

489

Resetting of Regulator (3M-PCV-0002 A/B) at Sumpal Well #6 (WP-8B)

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs


Vendor Sarana Instrument, SKP
27 hrs 15 Oct '16 16 Oct '16 108,94 hrs

Resetting valve of 3M-PCV-0002A

8,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

490

PJSM

2 hrs 15 Oct '16 15 Oct '16 108,94 hrs

491

Transfer/ mobilize tools, equipments and materials to final location.

1 hr

492

Block the isolation valve 1-GA-DF-4-1 from process fluid.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

493

Drain the remaining pressure from the drain valve -GA-DF-4-1.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

494

Disassembly the valve 3M-PCV-0002A by remove adjusting knob.

495

Remove SHCS and lift-off spring housing.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

496

Remove upper spring guide and range spring.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

497

Re-assembly the valve 3M-PCV-0002A by placing the new range spring and
upper spring guide.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

498

Replace the spring housing and thread the SHCS into the body.

499

Cross torque to 200 in/lbs

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

500

Thread the adjusting knob into the spring housing.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

All Parties
15 Oct '16 15 Oct '16 108,94 hrs
Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


1 hr

15 Oct '16 15 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


1 hr

15 Oct '16 15 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


501

Resetting valve of 3M-PCV-0002B

5,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

502

Block the isolation valve 1-GA-DF-4-1 from process fluid.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

503

Drain the remaining pressure from the drain valve -GA-DF-4-1.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

504

Disassembly the valve 3M-PCV-0002B by remove adjusting knob.

505

Remove SHCS and lift-off spring housing.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

506

Remove upper spring guide and range spring.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

507

Re-assembly the valve 3M-PCV-0002B by placing the new range spring and
upper spring guide.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

508

Replace the spring housing and thread the SHCS into the body.

509

Cross torque to 200 in/lbs

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

510

Thread the adjusting knob into the spring housing.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

Vendor Linkmet, SKP

Vendor Linkmet, SKP


1 hr

15 Oct '16 15 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


1 hr

15 Oct '16 15 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


511

Testing valve of 3M-PCV-0002A

6,5 hrs 15 Oct '16 16 Oct '16 108,94 hrs

512

Block the isolation valve 1-GA-DF-4-1 (Pic. On Tag A,C-1, D-1, F-1 and
F-2) from process fluid.

0,5 hrs 15 Oct '16 15 Oct '16 108,94 hrs

513

Open the isolated valve 1-GA-DF-4-1 (Pic. 3 Tag B, C-2, D-2 and E).

514

Relax the range spring by turning the adjusting knob counter-clockwise until
there is no noticeable spring tension.

0,5 hrs 15 Oct '16 16 Oct '16 108,94 hrs

515

Connect the supply pressure from Nitrogen bottle to the valve


3M-PCV-0002A inlet.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

516

Remove existing pressure gauge and connect the calibrated test gauge and
use the existing vent line of N2 gas to safe location.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

517

Set the required inlet pressure from the nitrogen bottle at 450 psig or up to
761 psig as the maximum inlet pressure.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

518

Closely monitor outlet pressure via pressure gauge and calibrated test gauge
at the downstream of valve. Downstream pressure shall be maintained at 450
psig.

519

If the outlet pressure exceeds the desired pressure then reset the regulator
0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs
set point by turning the adjusting screw clockwise to increase outlet pressure
or counter-clockwise to reduce outlet pressure.

520

Perform leak test and check valve body integrity.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

521

Reduce the pressure gradually. Disconnect the air supply from the nitrogen
bottle and calibrated test gauge as initial schematic of regulator valves.
Re-install existing pressure gauge.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

522

Open all the isolated / block valves

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

Vendor Linkmet, SKP


1 hr

15 Oct '16 15 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


1 hr

16 Oct '16 16 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


523

Testing valve of 3M-PCV-0002B

6,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

524

Block the isolation valve 1-GA-DF-4-1 (Pic. 3 Tag A,C-2, D-2, F-1 and F-2) 0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs
from process fluid

525

Open the isolated valve 1-GA-DF-4-1 (Pic. 3 Tag B, C-1, D-1 and E)

526

Relax the range spring by turning the adjusting knob counter-clockwise until
there is no noticeable spring tension.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

527

Connect the supply pressure from Nitrogen bottle to the valve


3M-PCV-0002B inlet.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

528

Remove existing pressure gauge and connect the calibrated test gauge and
use the existing vent line of N2 gas to safe location.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

Vendor Linkmet, SKP


1 hr

16 Oct '16 16 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 12

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
529

Set the required inlet pressure from the nitrogen bottle at 450 psig or up to
761 psig as the maximum inlet pressure.

530

Closely monitor outlet pressure via pressure gauge and calibrated test gauge
at the downstream of valve. Downstream pressure shall be maintained at 450
psig.

531

If the outlet pressure exceeds the desired pressure then reset the regulator
0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs
set point by turning the adjusting screw clockwise to increase outlet pressure
or counter-clockwise to reduce outlet pressure.

532

Perform leak test and check valve body integrity.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

533

Reduce the pressure gradually. Disconnect the air supply from the nitrogen
bottle and calibrated test gauge as initial schematic of regulator valves.
Re-install existing pressure gauge.

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

534

Open all the isolated / block valves

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

0,5 hrs 16 Oct '16 16 Oct '16 108,94 hrs


Vendor Linkmet, SKP
1 hr

16 Oct '16 16 Oct '16 108,94 hrs


Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP

Vendor Linkmet, SKP


535

Replacement of Pressure Switches (3M-PSH/L-0712 & 3M-PSH/L-0713) at


Sumpal Well #7 (WP-09)

9,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

536

PJSM

2 hrs 15 Oct '16 15 Oct '16 126,44 hrs

537

Existing Wellhead Control Panel shall be tested (especially signal comment


related to these PSH/L) to ensure that existing Well Head Control Panel still
working properly.

1 hr

538

Close valve of 3M-ESDV-0702, 3M-ESDV-0701 & 3M-ESDV-0742 by manually


and WHCP 3M-ZJP-007. Also to close valve of 16GAES43 3M001 and then
depressurize line of 16-GP-ES1-3M-2001-P.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

539

Checking and ensure the process connection of field instrument which will be
installed in accordance with the requirement.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

540

Close the existing 2-way valve manifold, then open the bleed of 2-way valve
manifold to ensure it is completely depressurized.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

541

Close the isolation valve/ mono flange, then open the bleed valve to ensure it is
completely depressurized. And, Close valve in upstream side of PSH/L as
pneumatic supply to PSH/L and bleed all pressure to zero.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

542

Dismantle existing PSH/L by disassembly tubing and fitting.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

543

Apply teflon tape and/or teflon (PTFE) paste to NPT mounting connection.
Apply only to the male threads. (Do not lap the Teflon tape over the end of the
threads. Do not apply pipe dope to the female threads of the block. Sensors
have small orifices than
Install new PSH/L and required associated tube and fitting as per hook-up for
pressure lead piping and tubing. Install test nipple and block valve in the top of
female connection.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

545

Ensure all installed tubing connection are in correct position/ port.

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs

546

Inspection and testing as per MFR's procedure i.e. Inspection procedure


(including leak test) (same activities with no.2 on above).

547

After test and everything working properly, then PSH/L ready to operate and
open the valve on the upstream of PSH/L to allow the line can be pressurized
and ready to operate.

All Parties
15 Oct '16 15 Oct '16 126,44 hrs
COPI Operation

COPI Operation

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP

544

Vendor Sarana Instrument, SKP


0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs
Vendor Sarana Instrument, SKP

Vendor Sarana Instrument, SKP


2 hrs 15 Oct '16 15 Oct '16 126,44 hrs
Vendor Sarana Instrument, SKP

548

Relocation of 103-ESDV-101 (WP-10)

0,5 hrs 15 Oct '16 15 Oct '16 126,44 hrs


Vendor Sarana Instrument, SKP
5,5 hrs 15 Oct '16 15 Oct '16 130,44 hrs

549

PJSM

2 hrs 15 Oct '16 15 Oct '16 130,44 hrs

550

Transfer/ mobilize tools and materials to final location

0,5 hrs 15 Oct '16 15 Oct '16 130,44 hrs

551

Disconnect existing cable from solenoid

0,5 hrs 15 Oct '16 15 Oct '16 130,44 hrs

552

Disconnect existing tubing from air set regulator valve

0,5 hrs 15 Oct '16 15 Oct '16 130,44 hrs

553

Re-route existing cable

0,5 hrs 15 Oct '16 15 Oct '16 130,44 hrs

554

Re-connect existing cable to solenoid and re-hookup tubing to air set regulator
after piping team has complish the relocation.

0,5 hrs 15 Oct '16 15 Oct '16 130,44 hrs

555

Inspection and test.

All Parties

SKP 1

SKP 1

SKP 1

SKP 1

SKP 1
1 hr

15 Oct '16 15 Oct '16 130,44 hrs


SKP 1

556

Resetting of Pressure Switch (108-PSL-403) (WP-11)

8 hrs 15 Oct '16 15 Oct '16 24 hrs

557

PJSM

2 hrs 15 Oct '16 15 Oct '16 24 hrs

558

Transfer/ mobilize tools, equipments and materials to final location.

0,5 hrs 15 Oct '16 15 Oct '16 24 hrs

559

Close Isolation valve B-1.

0,5 hrs 15 Oct '16 15 Oct '16 24 hrs

560

Close the existing 2-way valve manifold B-1, then open the bleed of 2-way valve 0,5 hrs 15 Oct '16 15 Oct '16 24 hrs
manifold to ensure it is completely depressurized.

561

Ensure there is no electrical powered during this activity by disconnect the wires 0,5 hrs 15 Oct '16 15 Oct '16 24 hrs
at field instrument side only.

562

Loosen the screws on the housing cover, and move it aside.

0,5 hrs 15 Oct '16 15 Oct '16 24 hrs

563

Before commence the adjustment activity, testing and recording the set point of
existing device shall be performed to ensure that existing device still working
properly.

0,5 hrs 15 Oct '16 15 Oct '16 24 hrs

564

The adjustment nut can be rotated by hand or with an open-end wrench or


similar tool. The range scale is intended to be used only as an approximate
guide ; it indicates the increasing set point

1 hr

15 Oct '16 15 Oct '16 24 hrs

565

To check the increasing set point of a pressure switch, connect a pressure


source (hand pump or nitrogen bottle) and a calibrated pressure gauge or
transducer to the pressure port and slowly apply increasing pressure until the
switch actuates. Actuation c
Replace the cover by moving it back into position over the top of the housing
and tightening the screws until the cover is snug against its gasket. Do not over
tighten, as this could damage the gasket.

1 hr

15 Oct '16 15 Oct '16 24 hrs

All Parties

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP

566

567

Final inspection, perform function test at least 3 times and record the result.

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP


0,5 hrs 15 Oct '16 15 Oct '16 24 hrs
Vendor PTCS, SKP
0,5 hrs 15 Oct '16 15 Oct '16 24 hrs
Vendor PTCS, SKP

568

Modification of Control Valve's Stopper (103-FV-100) (WP-12)

13,5
hrs

15 Oct '16 15 Oct '16 122,44 hrs

569

PJSM

2 hrs 15 Oct '16 15 Oct '16 122,44 hrs

570

Transfer/ mobilize tools, equipments and materials to final location.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

571

Close Isolation valve 4-CA & 8-CA.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

572

Open drain valve 3/4-CA to ensure the line has completely depressurized.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

All Parties

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 13

SUMPAL COMPRESSION PROJECT_TIE-IN SCHEDULE OCTOBER


ID

Task Name

Duration

Start

Finish

Total Slack

16 18 20 22
573

Isolate all any operating electric power or control signal

574

Connect the supply pressure from Nitrogen (N2) bottle by using the connector
and tubing from N2 bottle to the air set regulator on positioner

575

6 Set the pressure slowly until the air set regulator on positioner indicates
pressure required by Actuator (to push down the actuator) at 60 psig.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

576

Perform integrity test for existing mechanical stopper and recorded.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

577

Turn travel stop stem (key 133 at picture-1b) counter-clockwise so that the
pusher plate is not causing any spring compression

578

Current loop and HART communicator 475 or Valvelink is connected to HART


modem.

579

Perform calibration according size of actual travel.

1 hr

15 Oct '16 15 Oct '16 122,44 hrs

580

Valve Travelling is to be limited by adjusting signal from current loop to meet


maximum CVs. (29 %)

1 hr

15 Oct '16 15 Oct '16 122,44 hrs

581

Turn travel stop stem clockwise to 29% until control valve cannot open. Ensure
pusher plate touch the diaphragm plate at 29%.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

582

Travel stop nuts shall be locked.

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs

583

Perform re-calibration after CVs valve has been limited by using current
injection.

584

Perform functional test modification travel and recorded

585

Disconnect the nitrogen bottle, current loop and HART communicator from
device and reconnect existing tubing & signal cable as initial designed.

586

Open block valve & Start-up Valve.

Sat 15 Oct
8 10 12 14 16 18 20 22

Sun 16 Oct
8 10 12 14 16 18 20 22

Mon 17 Oct
10 12 14 16 18 20 22

Tue 18 Oct
10 12 14 16 18 20 22

Wed 19 Oct
10 12 14 16 18 20 22

17 October 2016
Thu 20 Oct
8 10 12 14 16 18 20 22

Fri 21 Oct
10 12 14 16 18 20 22

Sat 22 Oct
10 12 14 16 18 20 22

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP
1 hr

15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP


1 hr

15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP

Vendor PTCS, SKP


1 hr

15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP
1 hr

15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP

0,5 hrs 15 Oct '16 15 Oct '16 122,44 hrs


Vendor PTCS, SKP

Project: Schedule Tie-In shutdown oct

Baseline

Split

Summary

External Tasks

Inactive Milestone

Manual Task

Manual Summary Rollup

Start-only

External Tasks

Baseline Milestone

Critical

Progress

Task

Milestone

Project Summary

External Milestone

Inactive Summary

Duration-only

Manual Summary

Finish-only

External Milestone

Baseline Summary

Critical Split

Deadline

Page 14

Anda mungkin juga menyukai