B - SHIFT REPORT

Shift Members :Equipment Running Status


1

HVAC is in running condition.

TG running on barring gear with Both AOP, AC JOP & MOT`s OVEF B running condition.

Air & H2 side AC seal oil pump and Air Detraining Tank VEF- A are running condition, DP - 84.61 Kpa

Generator H2 pressure- 242.49 Kpa & Purity- 98.09 % @ 14:31 hrs.

Generator Stator Cooling Water Pump- A is running condirion.

EH oil pump- B & Recirculation pump is in running condition.

MDBFP- AOP is in running condition.

Coal Mill- A LOP-A and Mill- B LOP- B are running condition.

Coal Mill- H LOP-A and Hydraulic pump are running condition for flushing.

10

TG Lube oil MOT to MOT centrifuge & Pall filter in running condition.

11

Both APH main motor are running @ high speed condition.

12

AC scanner air fan is in running condition.

13

IDF A LOP B, IDF B LOP B, FDF A LOP A, FDF B LOP B are in running condition.

14

TDBFP A AOP and Tank to tank Pall & Paper are running condition.

15

TDBFP B & EH oil Tank to tank Pall is in running condition.

16

HP/LP bypass hydraulic pump B and filter pump & cooling fan are in running condition.

17

ACW-A, IAC & SAC-A, CCCW-A with PHE A & B and CW- C are in service.

18

LDO forwarding pump- A start & stop in short recirculation and Both suction strainer cleaning are in

Activities
1

16:44 hrs Both APH- A&B stopped for internal inspection by LITL.

Both APH Ash hoppers deashing completed.

18:45 hrs TDBFP- A Lube oil tank OVEF- B started.

Generator Hydrogen Pressure 240.20 Kpa & Purity- 98.07 % @ 22:30 hrs.

LDO forwarding pump- A start & stop in short recirculation and Both suction strainer cleaning are in
START [Hrs]
16:34

STOP [Hrs]
16:40

Long R/c

16:45

16:46

16:48

16:49

16:57

17:07

17:24

17:47

18:07

19:38

20:48

21:11

21:17

22:23

22:28

22:52

3. BOP AREA
1
2
3

Approx 13.8 KL LDO top-up done into Aux boiler storage & working oil tank.
03 nos of LDO tankers unloading completed (20+22+18 KL) LDO tank level @ 22:30 hrs- 2.996 mtr
Barrage River Water Intake Pump-2 is started at 15:50 hrs and stopped at 21:45 Hrs (Barrage FRL- 4

4. Electrical
1

DG set No 01 level - 900 Ltr. DG set 2 oil level - 200 ltr

400 KV Line-1 & 2 , Line Reactor 1 & 2 , Bus-1&2 are in charged condition.

GT back chraged condition and UT A & B charged condition and UAT B is in charged condition

ST is in charged condition.

B - SHIFT REPORT

MOT`s OVEF B running condition.

nk VEF- A are running condition, DP - 84.61 Kpa

% @ 14:31 hrs.

ondirion.

ndition.

dition.

ondition for flushing.

nning condition.

dition.

are in running condition.

ng condition.

ition.

oling fan are in running condition.

W- C are in service.

lation and Both suction strainer cleaning are in progress.

tion by LITL.

8.07 % @ 22:30 hrs.

lation and Both suction strainer cleaning are in progress.


Running Duration
6 min

Pump suction filter DP HI & Filter cleaned

1 min

Pump suction filter DP HI & Filter cleaned

1 min

Pump suction filter DP HI & Filter cleaned

10 min

Pump suction filter DP HI & Filter cleaned

23 min

Pump suction filter DP HI & Filter cleaned

01 Hrs 31 Mins

Pump suction filter DP HI & Filter cleaned

23 min
01 hrs 06 Mins

This time LDO long RC put in service (Delayed to start due to C&I work

at 22:09 hrs LDO long RC put in service. With Pump Disc . P

24 min

age & working oil tank.


+18 KL) LDO tank level @ 22:30 hrs- 2.996 mtr (local)
50 hrs and stopped at 21:45 Hrs (Barrage FRL- 476.48 mtr & Raw water reservior Lvl-514 mtr)

ltr
in charged condition.

ndition and UAT B is in charged condition

DATE :- 10.04.2015

n filter DP HI & Filter cleaned

n filter DP HI & Filter cleaned

n filter DP HI & Filter cleaned

n filter DP HI & Filter cleaned

n filter DP HI & Filter cleaned

n filter DP HI & Filter cleaned

layed to start due to C&I work on suction filter DP switch)

t in service. With Pump Disc . Pr. 25.83 kg/cm

4 mtr)

Unit - 1 Generator Hydrogen Pressure Drop


Date
06.04.2015
07.04.2015
08.04.2015
09.04.2015
10.04.2015

Time
06:00
18:00
06:00
16:00
18:00
06:00
18:00
06:00
18:00
06:00
18:00

hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs
hrs

H2 Pressure Drop Rate Drop Rate


(Kpa)
in 12 hrs (KPA/Hr)
288.17
279.25
269.94
266.95
271.13
263.16
259.21
252.58
250.45
244.69
241.93

8.92
9.31
2.99

0.7433333333
0.7758333333
0.299

7.97
3.95
6.63
2.13
5.76
2.76

0.6641666667
0.3291666667
0.5525
0.1775
0.48
0.23

ssure Drop Rate


Remark

10 nos of H2 filled & purge at


16:43 hrs to 17:52 hrs

Anda mungkin juga menyukai