ENGINEERING CONSULTANCY SERVICES FOR REVISION AND UPDATING OF
PQA MASTER PLAN AND ALLIED ASSIGNMENTS
FORM 6: WORK PLAN / ACTIVITY SCHEDULE
S. No.
ACTIVITY
1.
Commencement of Services.
2.
Meeting with the PQA and Data Collection.
Preparation of Inception Report which shall include the Introduction, background of assignment, objectives of report, existing layout & zoning point, cargo & vessel volumes, financial performance of PQA, major existing ongoing/future development project in PQA, project approach, planning & deliverables, vision & mission, issue & initial findings etc.
3.
4.
Submission of Inception Report.
5.
Review of current situation.
6.
Review of existing Industrial and Commercial Development.
7.
Preparation of Diagnostic Report which shall include land use,
zoning & land investigation, warehousing land, transportation, Public buildings, industrial/commercial communication, highway, roads, railways, jetties, wharves, moorings & navigational channel, telecommunications, utilization of water, power & natural resources, community planning, housing, slum clearance amelioration, community facilities including water supply, sewerage disposal, electricity supply, gas supply and other public utilities, residential accommodation & welfare facilities for PQA employees, environmental control & prevention of pollution etc.
8.
Submission of Diagnostic Report.
9.
Analysis of Port Development Scenario and Future Strategy.
MONTHS 1
Page 1 of 2
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
S. No.
ACTIVITY
MONTHS 1
Preparation of Strategic Optimizing Study Report shall include,
shipping & road traffic forecast, land use, zoning & land reservation, Karachi city & water land connection development, plan of Rail & Road connectivity corresponding to shipping & road 10. traffic forecast, efficiency analysis, traffic Management of vessel movement in the PQA navigation channel corresponding to shipping & road traffic forecast, capital dredging plan corresponding to shipping & road traffic forecast, annual Maintenance strategy for navigation channel etc. Submission of Strategic Optimizing Study Report. 9.
Revision and Updating of Port Qasim Master Plan.
Preparation of existing & future development / implementation
plans shall include the identification of projects for implementation, implementation plans considering available PQA funds, other lending options be considered and recommend most 10. feasible / doable option with arrangement of financing for implementation, use of simulation to determine what development projects options / plans can maximize the expected revenue, curve analysis to optimize the present / future revenue of PQA & assessment of future uncertainty etc. 11.
Submission of existing & future development / implementation
plans.
12. Recommendation for arrangement of water.
Financial Appraisal which shall include assessment of sources of 13. investments, cash flow projection financial and economic internal rate of return. Preparation of Draft Final Report which shall include master plan 14. and summary of work performed, consultants findings and recommendations. 15. Submission of Draft Final Report. Preparation of Final Report which shall incorporate all 16. revisions/modifications to the Draft Final Report as approved or necessary. 17. Submission of Final Report.