Anda di halaman 1dari 50

PMP Certification Final Exam updated FOR THE

2016 Exam

You are here:

Home

PMP Certification Final Exam

Do you think you're ready for the PMP certification exam? Use this 100 question final exam to gauge your
readiness.
You must complete this exam in 2 hours and answer 75 questions correctly to pass. If you score lower
than that, then you still have work to do.
Achieve your PMP with confidence. Join an Edwel class! The leaders in PMP training since 1992.

1.

2.

3.

Vocal inflection accounts for how much understanding of verbal communication?


a.

55 percent

b.

38 percent

c.

100 percent

d.

7 percent

On your current project, EV = $45,000, AC = $50,000, PV = $40,000. What is the schedule


variance as a percentage of the work accomplished at this point in time?
a.

-90%

b.

+90.5%

c.

-85%

d.

+88.8%

During the Executing and the Monitoring and Controlling phases, project managers frequently
engage in replanning activity due to discovery or a change in customer needs. The term used to
describe this process is called?

4.

5.

6.

a.

Regression testing

b.

Progressive planning

c.

Progressive elaboration

d.

Project elaboration

One of your project team members approached you visibly upset. It appears the team member
overheard a director and another project manager discussing an apparent scheme to defraud the
company. What is the FIRST thing that you should do as the project manager?
a.

Validate and substantiate the claim

b.

Inform human resources of the attempted fraud

c.

If the breach is serious enough, inform local law enforcement. You are protected by
whistleblower statutes

d.

Casually mention the details of the attempted fraud to the other project manager to see if
it elicits a response

The project has been running smoothly; initiation phase is complete and the team is working on
all aspects of planning. You had meetings with stakeholders several times to collect requirements
and as a result, requirements documentation is almost complete, as are high-level and detailed
design documents. As construction begins on the project, several stakeholders have indicated the
need for changes to the requirements set. They are claiming these elements were missed in the
initial requirements collection process, and they want you to add these elements to the project
immediately. You perform an impact assessment and get it back to them only to hear that they are
not going to allow any changes in the project budget or the timeline to complete these additional
elements. What is the most effective tool that you could use to prevent this instance of scope creep?
a.

Change control system

b.

Configuration management system

c.

Murder Board

d.

Work Authorization System

Which type of procurement document is most appropriate for a cost reimbursable contract?
a.

IFB (invitation for bid)

b.

RFP (request for proposal)

7.

8.

9.

c.

RFB (request for bid)

d.

RFQ (request for quote)

Your vendor just shipped you 100,000 parts. What is the best quality tool to use given that you do
not have the time or the workers available to check each part?
a.

Pareto Chart

b.

Statistical Sampling

c.

Control Chart

d.

Scatter diagram

One of the risks identified in the projects risk register has a probability of 85%. As the project
manager what would you do first upon making this discovery?
a.

Make the risk a #1 priority in the risk register

b.

Move the risk to the issue log

c.

Risk data validation

d.

Raise a red jeopardy on a stoplight report

You have just created the scope management plan for your current project. As the project
manager, what is the next thing that you should do?
a.

Sit down with your customer to perform a risk assessment

b.

Ask your customer about their wants and needs for the project

c.

Determine the detailed scope of the project

d.

10.

Create a detailed work breakdown structure that details all the work packages for the
project

Stakeholders are generally classified based on their ________________________?


a.

Impact, influence, urgency

b.

Influence, immediacy, interest

c.

Power, impact, interest

d.
11.

12.

13.

14.

Interest, influence, involvement

The mechanical engineering manager has reported to you, a PMP, that the work due at the end of
this week is going to be two weeks late. Your manager has requested that you do not report this to
senior management. What does the PMI Code of Ethics require you to do?
a.

Because the manager is a friend, you do not report the slip, and help him get the work
back on schedule.

b.

Bury the issue in a revised status report that does not show the work slippage clearly.

c.

Report the status accurately.

d.

Wait until the work is completed; then report the slippage. At that point its a fait acomplis.

One of the goals of your current project is to automate a current process that is currently done
manually. What is the best quality tool to use in this situation?
a.

Flowchart

b.

Histogram

c.

Cost-benefit analysis

d.

Cost of quality

The buyer has established a CPFF vehicle for the current procurement activity. What is the buyer
most concerned about?
a.

Risk

b.

Cost

c.

Specifications

d.

Vendor expertise

Which of the following statements about earned value is true?


a.

Actual cost can never exceed earned value

b.

Planned value can never exceed earned value

c.

Planned value can never exceed actual cost

d.
15.

Actual cost can never exceed earned value

A Project Manager is using AOA to perform critical path analysis. The network diagram is
represented as shown using below. Which of the following represents the path:

Activity
A
C
B
D
E
F
G
H
I
R

Duration
3
2
2
4
3
5
3
1
2
0

Dependent on
none
none
A
C
none
E
D,F
D,F
B,G
H,I

16.

17.

18.

a.

ABIR

b.

CDHR

c.

CDGIR

d.

EFGIR

For the sequence diagram in question 15, what is the float of activity B
a.

b.

c.

d.

For the sequence diagram in question 15, what is the float of activity H
a.

19.

20.

21.

22.

b.

c.

d.

According to PMI, the PMO is not responsible for?


a.

Centralized and coordinated management of projects

b.

Providing accurate reporting of project metrics

c.

Helping to align projects with the strategic goals of the organization

d.

Administrative support, project methodologies, and policies

You decide to conduct a quality audit of the cryogenic capable hardware being manufactured by
your company during project execution. The quality audit will identify all of the following, except...?
a.

Whether the planned quality process and standards were followed by the project team

b.

Whether the product will be formally accepted by the sponsor

c.

Whether the product is fit for use

d.

The improvement opportunities for the existing product

Which of the following statements about risk is the most correct?


a.

All risks should be avoided

b.

Accept only the risks for which you can purchase insurance

c.

If the project has no risk, it is not really a project

d.

Only accept projects with upside risks

You have determined your project will optimistically take 24 weeks to complete, with a most likely
completion date of 36 weeks and a pessimistic completion date of 72 weeks. Based on this three
point estimate what is the likely completion timeline for the project?
a.

38.4 weeks

b.

39.6 weeks

23.

24.

25.

26.

c.

40 weeks

d.

42.4 weeks

The five elements of the sender-receiver model in communications are ?


a.

Encode, filter, feedback, medium, noise

b.

Encode, decode, feedback, filter, noise

c.

Encode, message and feedback, medium, noise, decode

d.

Encode, message, recode, medium and noise, feedback

The two basic standards that define the PMI Code of Ethics and Professional Conduct are:
a.

Government and industry

b.

Anticipated and required

c.

Aspirational and mandatory

d.

Intended and compulsory

A SIPOC diagram is a type of?


a.

Checklist

b.

Run Chart

c.

SPC chart

d.

Flowchart

You identified the possibility of several high-impact risks on your current project at the last
stakeholder meeting. A senior VP was in attendance and immediately announced, Were looking for
can-do people for this project. If you cant handle it, Ill find someone who can! What would be the
best response to this statement?
a.

Immediately resign from the project, stating that the VP himself constitutes the largest risk
on the project

b.

Offer to discuss the VPs concerns, offline

c.

State that the risk assessment is necessary to help ensure the success of the project

d.

27.

28.

29.

30.

Tell the VP that you are simply following what PMI recommends and that it is not
mandatory

If you add two more people to a team of five people, how many additional lines of communication
will be created?
a.

15

b.

10

c.

11

d.

The life cycle of a product or service begins with?


a.

An assessment of the business need and benefit to the organization

b.

The manufacturing of a product or service

c.

The identification of stakeholders

d.

The development of the project scope statement and work breakdown structure

An approved change request just increased the scope of your project. This could result in all of
the following except?
a.

A change to the scope baseline

b.

A change to a new project manager

c.

A change to the cost baseline

d.

A change to the schedule baseline

The essential difference between cost and price is?


a.
b.

c.

Price includes cost-of-living adjustment and cost does not


Cost is the expenses incurred by the project; price is what the customer is charged for the
work
Price minus cost equals the benefit cost ratio (BCR) for the project

d.

31.

32.

33.

34.

Cost is what the customer is charged for the project work; price is based on the retail
value of the project work

Which of the following would be least important on the risk register?


a.

Risk owner

b.

Who identified the risk

c.

Triggers

d.

Residual and secondary risks

A finish to finish relationship is defined as which of the following?


a.

Both activities have to finish at the same time

b.

The predecessor has to finish before the successor can finish

c.

Both activities are on the critical path

d.

The predecessor has a defined lead while the successor has a defined lag

Which of the following best describes a stakeholder?


a.

Someone who is thinking about buying your product

b.

A reviewer of your product in an industry trade journal

c.

A project team member

d.

The CFO in another division of your company

In the Influence/Impact grid, the best management technique for stakeholders who are high in
influence and high in impact is to?
a.

Keep satisfied

b.

Monitor

c.

Manage closely

d.

Keep informed

35.

36.

37.

38.

Senior management brought you in to run a project as an 'execution' project manager. The
timeline and the budget were already established by senior management and you have been asked
to simply bring the project in on time and on budget. You do a thorough examination of the project
parameters and discover that there is no way the current project can be completed for the budget
and the time allotted. In fact, your calculation shows the project will cost 40% over the authorized
budget and will take six months longer to complete. What should you do?
a.

Give management a reality check, offer some recommendations, and ask them how they
would like to proceed

b.

Agree to the current project parameters and look for ways you can fast-track the project

c.

Refuse to take on the project as the deliverable dates and dollars are not realistic

d.

Negotiate for a reduced scope to bring in the project on time and on budget

The quality control team has raised concerns about the quality of the output of a specific
manufacturing process consisting of 3 steps. The quality control team leader reports that there is a
99% probability step #1 will produce a defect free part, a 98% probability that step #2 will produce a
defect free part and a 96% probability step #3 will produce a defect free part. At the end of the third
step, what is the approximate probability that an article chosen at random will be defect free?
a.

99%

b.

93%

c.

91%

d.

96%

The ability of the project manager to expend funds and allocate resources on a project is a
function of?
a.

The charter

b.

The organizational structure

c.

Correct project management principles

d.

The responsibilities of the PMO

Reward power means that the project manager can issue rewards. Examples of rewards can
include bonuses or comp time. PMI regards reward power as?
a.

One of the worst forms of authority

39.

40.

41.

42.

b.

Unimportant

c.

One of the best forms of authority

d.

Subject to frequent misuse

Your customer is having difficulty verbalizing the requirements for the upcoming project. The key
stakeholder has stated to you "We want it to work sort of like this - I can't really describe it but I'll
know it when I see it..." In this instance, what would be the most effective project lifecycle to
implement?
a.

Sequential

b.

Overlapping

c.

Waterfall

d.

Iterative

What costs are the most important costs that need to be considered when making a purchase
decision for a product or service?
a.

All development costs

b.

The purchase price

c.

The life-cycle costs

d.

The purchase price + failure costs

Which of the following is not a leadership style in the Hersey/Blanchard situational leadership
model?
a.

Telling

b.

Facilitative

c.

Dictatorial

d.

Coaching

You are assessing two projects for risk. Project #1 has a most likely duration of 95 days with a
standard deviation of 10 days, and Project #2 has a most likely duration of 110 days with a standard
deviation of 5 days. All of the following statements are true except?

a.

Project #1 is riskier than Project #2 because its standard deviation is larger

b.

Project #2 is riskier than Project #1 because its most likely duration is longer

c.

d.
43.

44.

45.

46.

The maximum possible duration of Project #1 estimated at a 99 percent probability is


longer than the most likely duration of Project #2
Both projects can potentially be completed within 105 days.

Rolling wave planning is__________________.


a.

Planning near term work in detail

b.

Critical chain project management

c.

Critical Path method

d.

Precedence diagramming

To understand the requirements for the product of your current project, you have conducted a
systems analysis, a requirements analysis, a product breakdown and a value analysis. These
activities define what is known as a?
a.

Product verification

b.

Process analysis

c.

Product analysis

d.

Scope verification

The risk register usually includes all of the following, except?


a.

List of risks

b.

Events and Impacts

c.

List of potential risk responses

d.

Risk breakdown structure (RBS)

The Monitoring and Controlling phase of project management involves measuring your
performance against the plan, looking for changes and variances, and how to bring future
performance in line with the project plan. Which term best describes this type of action?

47.

48.

a.

Iterative actions

b.

Defect repairs

c.

Responsive actions

d.

Corrective actions

The purpose of a change request resulting in a recommended preventive action is to?


a.

Improve SPI

b.

Improve project flexibility

c.

Increase the probability of a negative CPI

d.

Reduce the probability of future negative performance

All of the following statements about change are true except?


a.

The project manager can approve or reject any or all change requests

b.

A change in any one Knowledge Area can impact all the other Knowledge Areas

c.

d.
49.

50.

A delay in implementing a critical CR can negatively affect time, cost, or the feasibility of a
change
An impact assessment of a change request must be documented

What do confronting, compromising, and forcing all describe?


a.

Team building activities

b.

Temporary solutions to project issues

c.

Negotiation tactics

d.

Conflict resolution techniques

Project managers are frequently performing activities to control the budget, timeline, output and
deliverables on a project. What does PMI mean by control?
a.

Predictable and repeatable processes

b.

Meeting quality standards

c.
d.

51.

52.

53.

54.

Conforming to requirements and meeting stakeholder expectations


Comparing actual performance to planned performance and recommending corrective
action

You are thinking of purchasing a software product from a relatively young organization - they have
been in business less than two years. This is a cutting edge financial product that would put you at
least 18 months ahead of all competitors in your market space. However, your concern is that if you
purchase software from them, there is a possibility that they may go out of business and you would
lose the investment in the software. You ask the company to outright purchase the software code,
but the company has rejected this as an option. What is your best option moving forward if the
companys survivability is an issue?
a.

Contract it as a work made for hire

b.

Set up a code escrow arrangement

c.

Offer to buy the company

d.

Look for viable alternatives

You are the Project Manager of ABC project. There was a conflict between two key project
members. The three of you meet and decide to use compromise as the conflict resolution technique.
Compromise generally leads to
a.

Win-win situation

b.

Win-Lose situation

c.

Lose-Lose situation

d.

None of these

The Procurement Statement of Work is an output of which of these processes?


a.

Plan Procurements

b.

Conduct Procurements

c.

Control Procurements

d.

Close Procurements

Which of these is a tool for Develop Project Charter process?

55.

a.

Project selection methods

b.

Project management methodology

c.

Expert Judgment

d.

Earned Value Technique

Which of the following best describes the purpose of a war room?


a.

A war room is used for meetings between the Project Manager and the customer.

b.

A war room is used for important meetings between the Project team and the senior
management.

c.
d.

56.

57.

58.

A war room is used for collocation


Whenever there is a resource conflict between different Project Managers, they meet in a
war room.

You are the Project Manager of a project involving designing a computer system. Your team
members follow what you tell them because you have the authority to provide negative feedback in
their performance appraisal. This is an example of which type of power?
a.

Coercive

b.

Referent

c.

Formal

d.

Reward

Cost baseline is usually represented using which curve or line?


a.

a Slanted line

b.

an S-curve

c.

a Z curve

d.

a PQ curve

You are in the process of Source Selection for a contract for your project. You are planning to use
weighing process for source selection. There are four vendors being considered. There are two
deciding factors price (weightage 40), quality (weightage 60). The scores of four vendors that your

team has computed are displayed in the table below. Which vendor among these four should be
chosen?
Vendor scores

Price
Quality

59.

60.

61.

Vendor 1
8
12

a.

Vendor 1

b.

Vendor 2

c.

Vendor 3

d.

Vendor 4

Vendor 2
10
10

Vendor 3
12
8

Vendor 4
11
11

Which of the following indicate that the project is doing well? Select the best option.
a.

A negative Cost Variance

b.

An SPI of less than one

c.

A negative Schedule Variance

d.

A CPI of greater than one.

You are performing Earned Value Reporting for your project. The project's CPI is 0.9 and the
budget at completion is one thousand dollars. What is the estimated cost at completion?
a.

Nine hundred dollars

b.

One thousand one hundred and eleven dollars

c.

One thousand dollars

d.

One thousand and one hundred dollars

You are working on a project to build a bridge. You have reached the planned half way mark. The
total planned cost at this stage is five hundred dollars. The actual physical work that has been
completed at this stage is worth $400. You have already spent one thousand dollars on the project.
What is the CPI?

62.

63.

64.

a.

0.8

b.

1.2

c.

0.5

d.

0.4

You are working on a project to build a bridge. You have reached the planned half way mark. The
total planned cost at this stage is five hundred dollars. The actual physical work that has been
completed at this stage is worth $400. You have already spent one thousand dollars on the project.
What is the Schedule Variance?
a.

-100

b.

100

c.

-600

d.

600

John needs to visit many countries as part of his job. He has learned that he needs to avoid being
ethno-centric. What does ethnocentrism mean?
a.

Not being friendly to strangers

b.

Unable to get adjusted to the food of a new place

c.

Belief that ones culture is superior to others.

d.

Initial shock of landing in a new country.

You are planning to use a screening system for source selection process to select a vendor for
supplying food for your company? Which of these is a good example of a screening system?
a.

You interview all the vendors and decide based upon the interviews.

b.

You negotiate with all the vendors and select the one that provides the best price.

c.

You only consider those vendors who have revenue of ten million dollars in the last
financial year.

d.
65.

You select the vendor who responds first to your advertisement.

Which of the following is not an input to the Conduct Procurements process?

66.

67.

68.

69.

a.

Source selection criteria

b.

Make-or-buy decisions

c.

Organizational process assets

d.

WBS

You are using control charts to perform quality control. Which of these situations does not indicate
that the process is out of control and an assignable cause needs to be assigned. Assume that the
control limits have been set to three sigma.
a.

One of the point is more than the mean + (3*sigma)

b.

Two points together are more than mean +(2*sigma), but less than mean + (3*sigma)

c.

Seven points together are on one side of the mean.

d.

Six points together are on one side of the mean.

You are the Project Manager of a car manufacturing company. As part of Quality Control you
decide to check only 5% of the cars assembled for environmental check. Which technique are you
using?
a.

Pareto Diagram

b.

Control Charts

c.

Statistical Sampling

d.

Sample Selection

Which of the following is true statement about risks?


a.

If a risk is identified in a risk response plan, then that means that risk has already
happened.

b.

Once a risk has happened, you refer to the risk management plan to determine what
action needs to be taken.

c.

A risk that was not planned but has happened is called a trigger.

d.

Risk identification happens in all the phases of the project.

Which of the following is not true about the Close Project or Phase process?

70.

71.

72.

a.

Contract closeout must be performed after the Administrative Closeout.

b.

The risk is the lowest at this stage of the project.

c.

The probability of completion is the highest at this stage of the project.

d.

Stakeholders have least amount of influence at this stage.

Which of the following is an output of the Identify Risks process.


a.

Lessons Learned

b.

Checklists

c.

Risk Register

d.

SWOT Analysis

In which process of the Project Risk Management knowledge area are numeric values assigned
to probabilities and impact of risks
a.

Perform Qualitative Risk Analysis

b.

Perform Quantitative Risk Analysis

c.

Perform Numeric Risk Analysis

d.

Plan Risk Response

Your project is well underway, and the project management plan as well as subsidiary plans have
been baselined and work is proceeding apace. A key project stakeholder has just approached you
with a problem: a requirement was missed by the business in the requirements gathering process
and they want it inserted into the project plan without having to go through the formal change
request process. They would consider it a huge favor if you did so and would be willing to
reciprocate at some later date. What should you do next?
a.

Talk to the stakeholder's manager about the stakeholder's request for a breach in the
formal corporate change management process

b.

Since the stakeholder has key resources on the project, it may pay off in the long run to
agree to the stakeholder's request

c.

Perform an impact assessment on the requested change and submit to the CCB for
approval

d.

73.

74.

75.

76.

Agree to the request only if the stakeholder is willing to remove a less important feature of
equal effort so as not to impact the costs or the timeline on the project

Expert judgment is a tool and technique of all of the following processes except...?
a.

Identify stakeholders

b.

Plan stakeholder management

c.

Manage stakeholder engagement

d.

Control stakeholder engagement

Which of these is not an example of a project?


a.

Buying clothes from the store on a special sale.

b.

Planning for your friends wedding.

c.

Building a bridge across the Amazon river.

d.

Cleaning the office building every day.

Describing stakeholders based on their power (ability to impose will), urgency (need for
immediate attention), and legitimacy (their involvement), describes what type of grid or model?
a.

Power/Influence grid

b.

Salience Model

c.

Influence/Impact grid

d.

Power model

Which of the following best describes Plan Stakeholder Management process?


a.

Creating and maintaining relationships between the project team and stakeholders

b.

Preventing negative stakeholders from derailing theproject

c.

Striking a balance between stakeholder needs and project needs

d.

Focusing on from the creation of the stakeholder management strategy

77.

78.

79.

A series of stakeholder meetings were called to address the needs of stakeholders for the
upcoming project. A list of 150 requirements was drawn up. After reviewing the list and developing a
high level estimate, the PM reported back to the stakeholder group that due to the budget limitations
on the project, it would be possible to deliver only 75 of these requirements. A new meeting was
called to cull the list from 150 to 75. The stakeholders were going through the list, when there was
serious contention about a group of requirements. The disagreement escalated to a shouting match,
and several stakeholders left the meeting infuriated. What risk tool would have best prevented this
situation?
a.

Brainstorming

b.

SWOT analysis

c.

Delphi Technique

d.

Nominal Group technique

Project roles and responsibilities can be graphically represented in what is called a?


a.

RBS: Resource breakdown structure

b.

RAM: Responsibility assignment matrix

c.

RARG: Roles and responsibility grid

d.

RAAM: Random access assignment matrix

On your current project, you have spent a week with the project team and the stakeholders
defining the activities that will be executed to complete the product of the project. What is the next
step you will perform in this process?
a.
b.

80.

Deliver an estimate on how long each activity will take to complete


Work with your stakeholders to determine what skill sets are needed to complete each
activity and who should be selected for these jobs

c.

Determine the costs for each of the activities

d.

Create a network diagram

While executing the project it becomes obvious that you're not going to hit your end date. The
project may be delayed by at least two months. This may impact the start date of another project
that was due to start right after yours completed. What type of float best describes this situation?
a.

Total float

81.

82.

83.

84.

b.

Project float

c.

Free float

d.

Slack float

The lowest level of the WBS addresses__________________.


a.

Deliverables

b.

Control accounts

c.

Activities

d.

Level of effort

Project Scope Management defines the work required to complete the project
successfully_______________.
a.

Along with the creation of a scope management plan

b.

No more, no less

c.

In the eyes of all key stakeholders

d.

At least one time in each project

You are developing a project statement of work for your current project. To what level of detail is
the statement of work developed?
a.

It is only as detailed as the WBS

b.

Only a narrative description of products or services

c.

It is tied in lockstep with the requirements traceability matrix

d.

Is created only when the detailed scope statement has been completed

Cost overruns on a project are usually caused by some combination of the following with the
exception of?
a.

Inadequate budget from management

b.

Stakeholder disagreement

85.

86.

87.

c.

Poor technical performance

d.

Scope creep

You are managing a project in which various stakeholders are for or against a specific change in
the project. The best tool to identify the reasons for or against the change is _______________.
a.

Force field analysis

b.

Design of experiments

c.

Benchmarking

d.

Statistical Sampling

Which of the following is not part of the Control Communications process?


a.

Issue log

b.

Communication models

c.

Change requests

d.

Work performance information

Project Communications Management involves the appropriate generation, election,


dissemination, storage, and occasional disposition of project information. The overall focus of project
communication is to?
a.

Ensuring that project stakeholders have been given an opportunity for input

b.

Ensuring project stakeholder expectations are met

c.

d.
88.

Deliver the requested information to the correct person or group of people at the correct
time
Deliver the requested information to senior management when needed

The manner in which individual resources, teams, and entire organizational units behave can be
described by?
a.

Chaos theory

b.

Theory Y

89.

90.

91.

92.

c.

Management by objectives

d.

Organizational theory

Your company makes a product that a potential buyer is very interested in. After several
discussions, the potential buyer issues a letter of intent to purchase the product within the next two
months. Your company president takes this letter of intent (LOI) to the local commercial bank in the
hopes of obtaining a short-term loan to purchase the necessary equipment to deliver on this
potentially lucrative contract. The bank turns him down flat, even though the sellers finances are in
good order. Why do you think this is the case?
a.

Issues with the buyers reputation

b.

The LOI is not a legal document

c.

The LOI does not contain enough money to cover the loan

d.

The seller has not reached the minimum funding limits for loans of this type

What does an SPC chart set the upper and lower control limits?
a.

+/- 2 sigma

b.

+/- 3 sigma

c.

+/- 6 sigma

d.

+/- 1 sigma

You are dealing with the stakeholder that views your project as a significant negative. What will
you use to help minimize negative stakeholder impact on the project?
a.

Stakeholder register

b.

Stakeholder management plan

c.

Risk tolerance indicator

d.

Stakeholder analysis

The wages of hourly workers on a time and materials project is considered


a/an_________________ cost.
a.

Direct/variable

93.

94.

95.

b.

Direct/fixed

c.

Indirect/variable

d.

Indirect/fixed

Training needs, recognition and rewards, and regulation or contract compliance are all items that
are addressed as part of the
a.

The project charter

b.

The staffing management plan

c.

The project scope statement

d.

The resource management plan

The hierarchy of needs is a motivational theory developed by: Category: Group HR


a.

Herzberg

b.

McGregor

c.

Maslow

d.

McClelland

You have been authorized by the contract administrator in your organization to handle specific
changes in the contract should the need arise. The vendor on this particular procurement has
indicated a need for a change in the current specification. You discuss the change with the vendor,
verbally agree to it, and implement the change via the standard change request process, as
specified in the contract. At an invoice audit several months later, the purchasing organization
refuses to pay for the work that was entered in the change system. What has the project manager
forgotten to do in this instance?
a.

Consult the technical team prior to implementing the change

b.

Implement a formal written change to the contract

c.

d.
96.

Verify that the change was within the project managers responsibility from the contract
administrator
Update the configuration documents on the project

The communication plan is developed based on which of the following elements?

97.

98.

99.

a.

The communications model employed and risk factors

b.

The projects organizational structure and external stakeholder requirements

c.

Standard communications heuristics and constraints

d.

The project management structure and performing team requirements

Validate Scope is part of what process group?


a.

Planning

b.

Executing

c.

Closing

d.

Monitoring and Controlling

Since you had indicated that unavailability of resources was a risk on your project, you had a
contingency strategy in place that allowed for a temporary staff augmentation. Management signed
off on this approach. This risk was realized and you implemented the contingency plan, however the
new staff may take longer to get up to speed in the environment than originally thought. What does
this new situation describe?
a.

Residual risk

b.

Risk trigger

c.

Secondary risk

d.

Passive risk response

The feature set for your companys newest jet-ski line contains fewer features than those normally
produced by the company. The QC manager is discussing this with the PM and is complaining that
the design does not meet standard company production guidelines. His argument is that the limited
feature set is inconsistent with the companys established quality policy. What is the best way for the
PM to respond to the QC manager?
a.

The PM states that the QC manager may have a point

b.

The PM states that the QC manager is confusing quality with grade

c.

The PM states that the issues will be addressed with the engineering department

d.

The PM states that the QC manager is missing the voice of the customer

100. Management from the customer side wants to bring in a project one month earlier than they had
originally planned. Based on the current project timeline, product testing will have to be cut short.
You have reviewed several options with the customer; they have decided that crashing the schedule
would be the best approach to bringing in the project earlier. As a result of customers decision, what
is your biggest concern using this approach?
a.

Additional expense

b.

Availability of additional resources to perform testing in a shorter time frame

c.

Customer buy-in

d.

Developing an adequate reward system to address the overtime that will be needed to
bring in this project one month early

101. Assessing how a stakeholder is likely to react in a given situation is described in


______________?

a.

Stakeholder management strategy

b.

Stakeholder register

c.

Stakeholder analysis

d.

Stakeholder power/interest grid

Answers

1.

B - Vocal inflection contributes approximately 38 percent of our understanding of a verbal


communication. From Hidden Messages by Albert Mehrabian, 1972.

2.

D - the formula for schedule variance is SV = EV PV. Therefore the schedule variance as a
percentage of the work accomplished is PV/EV or +88.8%

3.

C - Regression testing is a red herring. The correct PMI term for this activity is progressive
elaboration.

4.

A. The PMI Code of Ethics mandatory standard states that ethics complaints may only be filed
when first substantiated by fact

5.

D One of the defined uses of a work authorization system is for the control of scope creep. It
insures the right work is performed at the right time and in the correct sequence.

6.

B - the most appropriate form of contract for a cost plus/cost reimbursable contract is the RFP
because you are buying expertise. The statement of work may not be completely understood at the
start of the project.

7.

B - a random statistical sample will tell you approximately what percentage of defects youll find in
the hundred thousand parts.

8.

B At this point, this risk is an issue that will have to be addressed. A is premature while we
know the probability, we dont know the impact. C is incorrect: if you are performing a thorough risk
assessment, it is assumed you are validating the risk data before it is entered in the log. D might be
correct if the impact of the risk is high, but at this point it is an unknown

9.

B - The next step in the Planning process group for scope is to determine the customer's
requirements. Answer A is performed in the Risk Management knowledge area, and answers C and
D are performed after the requirements are collected.

10.

D - "Stakeholders should be classified according to their interest, influence, and involvement..."


PMBOK Guide, 5th edition, p. 394.

11.

C - The PMI code of ethics and professional responsibility states: We do not engage in or
condone behavior that is designed to deceive others, including but not limited to, making misleading
or false statements, stating half-truths, providing information out of context or withholding
information that, if known, would render our statements as misleading or incomplete. This means,
tell the truth whether the news is positive or negative.

12.

C Because you want to be sure if the automation will reduce costs, you want to perform a costbenefit analysis.

13.

A For a cost plus contract vehicle, the biggest concern is Risk from the buyers perspective

14.

B - You cannot earn more value on a project than you planned to spend. The actual cost could be
higher or lower than earned value or planed value.

15.

D. EFGIR represents the critical path. It is the longest path through the network with the duration
of 13.

16.

D. The path ABIR has duration of seven. Hence B can be delayed by six days before the next
event can begin.

17.

C. The path CDHR has duration of nine days. Hence H can be delayed by four days before the
next event can begin.

18.

B - Answer B describes one of the responsibilities of the project manager, not the project
management office.

19.

B - Answer B is correct because the quality audit is focused on whether project activities comply
with organizational and project policies, processes, and procedures. Acceptance of the deliverable
is the key output of the Validate scope process in Project Scope Management. PMBOK Guide, 5th
edition, p. 247.

20.

C Since a project is an endeavor that creates something unique, there will be unknowns and
uncertainties on the project. Therefore, projects automatically carry risk due to the existence of
unknowns/uncertainties. If there is no risk, then there is no uncertainty; i.e. if all elements are
known, your project is fundamentally an operational process.

21.

C - By straight PERT calculation - (O + 4*ML + P)/6. (24 + 4*36 + 72) / 6 yields 240/6 = 40

22.

C - PMBOK Guide, 5th edition, pp. 293-94.

23.

24.

C The standards are broken out into 2 categories: Aspirational standards and mandatory
standards
D - a SIPOC diagram is a type of flowchart. PMBOK Guide, 5th edition, p. 236.

25.

C Failure to address risk is one of the leading causes of troubled projects that suffer from
negative scope, cost or scheduling issues. It can also lead to project failure or early termination. PMI
considers that failure to perform an adequate risk assessment on a project is a plan-to-fail scenario.

26.

C By straight calculation: [N x (N 1)]/2 For five people, the number of communication links
would be: [5 x (5 1)]/2 = 20/2 = 10. For seven people, the number of communication links would
be: [7 x (7 1)]/2 = 42/2 = 21. 21 10 yields 11 additional lines of communication.

27.

A -The PMBOK Guide states, Many facets of the product life cycle lend themselves to being run
as projects, for example, performing a feasibility study conducting a product trial and a market, etc.

28.

B A change in scope can impact any of the triple constraints. The potential loss of the PM might
be a risk but not a CR.

29.

B - Answer A: the cost-of-living adjustment is cost based, not price based. C is wrong the BCR
is more complex than a simple price minus cost calculation. D is made up.

30.

B Who identified a risk is not a part of the risk register.

31.

B - This is the definition of a finish to finish relationship: I must complete activity a before I
complete Activity b

32.

C The team member is the stakeholder. Answer A describes a potential stakeholder. Answer B
gets paid to review the product whether they use it or not (although their opinion may impact your
sales!). Answer D is probably working to her own P&L, has nothing to do with your product and
probably hasnt heard of it.

33.

C - Answer A is for stakeholders who are high in influence and low in impact; B is for those
stakeholders who are low in influence and low in impact; D is for stakeholders who are low in
influence and high in impact. PMBOK Guide, 5th edition, p. 396.

34.

A - Your job is to report honestly to management and to the best of your ability. While the last
answer might be a recommended option, you must first give management the reality check

35.

B -Answer B is correct because the cumulative probability is calculated by multiplying the


percentages by each other: .99 x .98 x .96 will yield slightly over 93%. The concept is known as
RTY: Rolled Throughput Yield.

36.

A - Answer A is correct. It is the most commonly described benefit of the charter. Answers B and
D are partly true but do not apply. Answer C is misdirection.

37.

C PMI considers expert and reward power as the two best forms of project manager authority.

38.

D the iterative lifecycle is used for projects in which the project elements may not be clearly
defined or are uncertain. Per PMBOK Guide, p. 22.

39.

C Life-cycle costs are the inclusive costs that include purchase price, maintenance and support
and warranty costs. This is your ultimate cost for the product or service

40.

C - All of the other answers are leadership approaches of the situational continuum theory.

41.

B - Answer B is not true; a longer duration does not necessarily translate to higher risk. A is true,
because a larger standard deviation indicates a riskier estimate. C is true because the maximum
estimate for Project A at 95 percent probability is 115 days, whereas the most likely estimate for
Project B is 110 days. D is true because the minimum range within 2 standard deviations for project
#1 is 75-115 days and for project #2 is 100-120 days.

42.

A Rolling wave planning details the work to be performed in the near term while planning future
work at a higher level in the WBS.

43.

C these are elements of a product analysis.

44.

D - The RBS is part of the Risk Management Plan.

45.

D - When changes or variances to the original plan are discovered, the project manager and the
team should take corrective action. PMBOK Guide, 5th edition, p. 83.

46.

D - Recommended preventive actions are implemented to reduce the probability of a negative


future event.

47.

A - The project manager can approve or reject change requests only if explicitly granted this
authority by the charter, the customer, and the integrated change control system. Answers B, C, and
D are true.

48.

D - Confronting, compromising, and forcing are all forms of conflict resolution techniques. PMBOK
Guide, 5th edition, p. 283.

49.
50.

D - PMBOK Guide, 5th edition, p. 430.


B A code escrow arrangement will protect the seller and the buyer. If the seller goes out of
business, the buyer will have access to the code for continuing support of the product. Otherwise
the code stays in escrow

51.

C. According to PMI, Compromise is an example of a lose-lose situation.

52.

A. Procurement statements of work is an output of Plan Procurements process.

53.

C. Expert judgment is a tool for the Develop Project Charter process.

54.

C. War room is used for collocation to facilitate communication within the team.

55.

A. When the team is afraid of the Project Manager, the power yielded is of type Coercive.

56.

B. An S-curve is typically used to represent a cost baseline. The cost is low in the beginning and
end, and high during the middle of the project.

57.

D. We need to compute the following for all the vendors - (0.4*Price + 0.6*Quality). The scores
come out to be vendor 1 - 10.4, vendor 2 - 10, vendor 3 - 9.6, and vendor 4's 11. Since vendor 4 has
the highest score, it should get selected.

58.

D. A CPI of greater than one indicates you are taking less money than planed to do the project.

59.

B. EAC = (BAC/CPI).

60.

D. CPI = EV/AV. EV=400, AC = 1000, PV=500.

61.

A. SV=EV-PV. 400 minus 500 is -100.

62.

C. Ethnocentrism refers to belief that ones culture is superior to other cultures.

63.

64.

C. Screening system are predefined criteria that are used to short- list vendors for source
selection
D. WBS is not an input to the Conduct Procurements process.

65.
66.

B. The others are conditions that indicate the process is out of control.
C. Statistical Sampling is the standard technique that is used to test only A small sample of
products instead of all the products manufactured.

67.

A. This is the only correct statement.

68.

A. Contract Closeout is performed before administrative Closeout

69.

A. Risk Register is the only output of the Risk identification process.

70.

B. A numeric value is assigned to risks impact and probability during the Quantitative Risk
Analysis process.

71.

C - This is an ethics question dressed up as a stakeholder management question. What happens


next is an impact assessment. Under the mandatory Responsibility section: "We inform ourselves
and uphold the policies, rules, regulations and laws that govern our work..."

72.

C - Expert judgment is not a tool and technique of Manage Stakeholder Engagement. PMBOK
Guide, 5th edition, p. 398

73.

D. Cleaning the building is a repetitive task that is done everyday. Hence it is not an example of a
project.

74.

B This exactly describes the Salience model. PMBOK Guide, 5th edition, p. 396

75.

A - stakeholder management is about the creation and maintenance of relationships between the
project team and stakeholders. Under specific circumstances, answers B and C may be partially or.
Answer D is incorrect: what is created as the stakeholder management plan, not the stakeholder
management strategy. PMBOK Guide, 5th edition, p. 400

76.

C With the Delphi technique, participants remain anonymous to each other so that they can
simply focus on the facts without having to deal with the emotional components of the problem

77.

B - Answer A is incorrect it shows the resource hierarchy but not responsibility level. Answers C
and D are made-up terms.

78.

D - In the time management process, after the activity definitions have been established, we then
sequence the activities and create network diagrams.

79.

B Project float is the delay a project can incur without delaying a succeeding project. Total float
addresses delaying the project and date. Free float addresses the early start of a successor activity.
Slack float is a made-up term

80.

A The lowest level of decomposition in the WBS is the work package, which is deliverable
focused.

81.

B - Scope management is, the processes required to ensure that the project includes all the
work required, and only the work required is completed successfully.

82.

B The project statement of work is a high-level narrative that is an input to developing the
project charter, an initiating process. PMBOK Guide, 5th edition, p.75

83.

B stakeholder disagreement is common on all projects and must be addressed by the skill of
the project manager to facilitate an acceptable resolution for the stakeholders in conflict. It rarely, if
ever, results in a cost overrun. Fleming and Koppelman, Earned Value Management, Third Edition,
PMI 2005

84.

A - the force field analysis shows the pros and cons of an idea.

85.

B Communications models are a tool and technique of Plan Communications. PMBOK Guide,
5th edition, p. 288

86.

C Answer C is most correct. All the answers are somewhat correct, but all can be subsumed
within answer C: get the required information to the right person when it is needed or requested.
PMBOK Guide, 5th edition, p. 287.

87.

D - PMBOK Guide, 5th edition, p. 263

88.

B The letter of intent is not a legal document and does not obligate the buyer to follow through

89.

B The SPC chart sets upper and lower control limits at +/- 3 sigma

90.

B PMBOK Guide, 5th edition p. 404

91.

A - It is a direct cost because it is attributable to your project. It is also a variable cost because the
hourly workers could put in 30, 40, or 50 hours a week.

92.

B - PMBOK Guide, 5th edition, pp. 265-66.

93.

C The hierarchy of needs was developed by Abraham Maslow

94.

B The contract is the final arbiter of what gets paid and what does not. Only a formal written
change to the contract, specifying that the change would be paid for, is legally binding

95.

B - The projects organizational structure and external stakeholder requirements. New PMP Task
Classifications. Domain 2, Task 6. PMI, 2011

96.

D - Monitoring and Controlling is the only correct answer. PMBOK Guide 5th ed. p. 61

97.

C This is a classic example of a secondary risk: A new risk that is identified as a direct outcome
of implementing a risk response.

98.

B - Quality is defined as the degree to which a set of inherent characteristics fulfill requirements
(PMBOK Guide, 5th edition, p. 228) while grade is a category assigned to products or services
having the same functional use but different technical characteristics. (PMBOK Guide, 5th
edition). Absence of the standard feature set does not automatically imply low quality. The
customer may have requested a high-quality product but with fewer features at a better price point.

99.

B Since the customer has decided that crashing is an option, answer A has already been taken
into consideration as well as answer C. Answer D is a complete unknown at this point. Of the four
answers, the biggest concern is whether the testing resources are actually available to do the job

100. C - It is the 3rd step in the stakeholder analysis. PMBOK Guide, 5th edition, p. 396

Selection of questions courtesy of Richard Perrin, PMP

PMP Certification Practice Exam

You are here:

Home

PMP Certification Practice Exam

Studying for the PMP certification exam? Use this 50 question practice exam to gauge your readiness.
You must complete this exam within 1 hour and answer 40 questions correctly to pass. If you score lower
than that, then you should keep hitting the books.

1. The stakeholder analysis matrix is part of ...?


a. Part of the Stakeholder Management Strategy - an output of identify stakeholders
b. An output of Plan Communications
c.

Part of the stakeholder register

d. Part of Performance Reporting

2. Which relationship model is most commonly used in the Precedence diagrams?


a. start-to-start
b. start-to-finish
c.

finish-to-start

d. finish-to-finish
3. AOA activity diagrams are only represented using which representation?
a. start-to-start
b. start-to-finish
c.

finish-to-start

d. finish-to-finish
4. Which of the following is not true about the Delphi technique?
a. Individuals participating must know each other for Delphi technique to be successful.
b. Delphi technique is most commonly used to obtain expert opinion.
c.

In Delphi technique participants are generally anonymous.

d. Delphi technique has been in use for decades.


5. Typically, the signing of the project charter is the responsibility of
a. Project Sponsor
b. Senior Management
c.

Project Manager

d. Project stake-holders
6. You are the project manager of ABC project. Mid-way through the project a key component was
found defective. This was not planned for. The team met after the event and managed to make
the product work without the defective component. This is an example of a. Risk mitigation

b. Transfer of risk
c.

Work-around

d. Accepting the consequences passively.


7. Most common cause of conflict in a project is
a. Schedules
b. Technical opinions
c.

Personal Issues

d. Project priorities
8. The most long-lasting conflict resolution is caused by which of these techniques?
a. Smoothing
b. Confrontation
c.

Compromising

d. Forcing
9. You are the Project Manager of ABC project. The project is being executed in an earthquakeprone area. To take care of this you buy insurance for earthquakes. This is an example of
a. Risk mitigation
b. Transfer of risk
c.

Risk contingency planning

d. Accepting the consequences passively.


10. Which of these is correct with respect to a product developed or a service performed.
a. Bad quality is acceptable, but bad grade is not.
b. Bad grade is acceptable, but bad quality is not.
c.

Neither bad grade nor quality is acceptable.

d. Grade and quality is the same thing.


11. Which of the following theory was suggested by Deming?
a. Apply continuous small improvements to reduce costs and ensure consistency.
b. Marginal Analysis
c.

Expectancy theory - people expect to be rewarded for their efforts.

d. Plan-do-check-act to improve quality.


12. Which of the following is not a tool for Perform Quality Control process.
a. Inspection
b. Benchmarking
c.

Flow charting

d. Histogram
13. You are the Project Manager for ABC project. You need to find out which issue has maximum
impact on the project. Which tool should you use?
a. Pareto diagram
b. Control chart
c.

Trend analysis

d. Fishbone diagram
14. When analyzing quality for a project a Project Manager decides to use a tool that provides a
creative way to look at the causes or potential causes of a problem. Which tool is the Project
Manager planning to use?
a. Pareto diagram
b. Control chart
c.

Statistical sampling

d. Ishikawa diagram

15. A Project Manager is using AOA to perform critical path analysis. The network diagram is
represented as shown using below. Which of the following represents the path:

Activity

Duration

Dependent on

none

none

none

D,F

D,F

B,G

H,I

16.

a. ABIR
b. CDHR
c.

CDGIR

d. EFGIR
17. For the sequence diagram in question 15, what is the float of activity B
a. 2
b. 3
c.

d. 6
18. For the sequence diagram in question 15, what is the float of activity H

a. 2
b. 3
c.

d. 6
19. According to Herzberg which of these is not an example of hygiene factors?
a. job security
b. salary
c.

safe working conditions

d. appreciation of work
20. According to Maslow's hierarchy of needs, which is the lowest level which must be met before
other levels can be met.
a. Esteem
b. Physiological
c.

Social

d. Safety
21. Which of these is not a benefit measurement project selection method?
a. Integer Algorithm
b. Internal Rate of Return
c.

Scoring model

d. Discounted cash flow


22. Which of these is a constrained optimization project selection method?
a. Parallel algorithm
b. Number programming

c.

Murder board

d. Dynamic Programming
23. You are part of an expert committee deciding which project should be implemented by your
company. Your committee asks tough questions from the project teams and helps decide which
project your company should select. Which project selection technique are you using.
a. Scoring Model
b. Committee Selection
c.

Murder Board

d. Defined Benefit
24. Which of these is a process in the Scope Management knowledge area
a. Identify Scope
b. Clarify Scope
c.

Control Scope

d. Close Scope
25. You have just been made the Project Manager of the ABC project. You are trying to read the WBS
and are unable to understand some of the WBS components. Which should be your first step to
understand this?
a. Refer to the WBS dictionary
b. Refer to the scope statement
c.

Refer to the Project charter

d. Contact the previous Project Manager


26. Who among the following is responsible for performing the scope validation
a. Project Manager
b. Senior Management
c.

The quality team

d. The customer
27. You are planning to use PERT for the planning of your project. A task has a pessimistic estimate
of 24 days, a most likely estimate of 15 days and an optimistic estimate of 12 days. What is the
mean using the PERT technique?
a. 18 days
b. 25.5 days
c.

15 days

d. 16 days
28. Which of these is a process in the Project Procurement Management knowledge area?
a. Select Sellers
b. Control Procurements
c.

Control Contracts

d. Plan Purchases and Acquisitions


29. Oligopoly refers to which of these
a. There is only one qualified seller in the market.
b. There are no sellers in the market, so you have to build the product in-house.
c.

There are few sellers and action of one seller will have impact on other sellers prizes.

d. Your company prefers to contract with only one seller.


30. You are using straight line depreciation to compute the value of your computer after three years. If
the current cost is $1000, what will be the value after three years assuming that the computer's
life is five years.
a. $0
b. $400
c.

$500

d. $600

31. Which of the following is not true about analogous estimating.


a. Estimate is based on past projects.
b. It is not very accurate.
c.

It uses bottom-up approach

d. It is a form of an expert judgment


32. You have been asked to make an estimate for a project. The project involves manufacturing 1000
toys. You expect that as the team manufactures some toys, the time to make them will reduce.
Which estimation technique are you trying to use?
a. Analogous Estimation
b. Regression Analysis
c.

Bottom up Estimating

d. Learning Curve
33. John is an excellent engineer. The management assumes that since he is a good technical
performer, he will be a good project manager too. Based upon this, John was promoted to Project
Manager. This is an example of
a. Halo Effect
b. Expectancy Theory
c.

McGregory Theory of X and Y

d. Herzberg Theory
34. Which of these is an example of processes in the closing process group?
a. Project Closure
b. Scope Closure
c.

Close Project or phase

d. Scope Validation
35. The authority to approve or deny a change request lies with

a. Project Manager
b. Customer
c.

Project Sponsor

d. Configuration Control Board


36. You are the Project Manager of the XYZ project. You want to find the planned expenses for next
month. Which document do you need to refer to?
a. Cost Management Plan
b. Cost Baseline
c.

Cost Control Plan

d. Cost Variance report


37. Which of the following is not true about the WBS report?
a. The WBS should focus in on the activities that must be performed in the project and
should not focus on the deliverables.
b. The project team must be involved in developing the WBS.
c.

As a rule of thumb, each activity of the WBS should take less than 80 hours.

d. The WBS is usually represented in a hierarchical fashion.


38. Which of the following processes produces the WBS as an output?
a. Plan Scope
b. Initiate Project
c.

Define Activities

d. Create WBS
39. Which process identifies the project manager?
a. Develop Project Management Plan
b. Develop Project Charter

c.

Define Scope

d. Select Project Process


40. You are the Project Manager assigned to build a next generation vehicle. You identify a
dependency that the wheels must be designed and developed before the assembly of the vehicle
can be performed. This is an example of which type of dependency?
a. External
b. Discretionary
c.

Soft Logic

d. Mandatory
41. You are the Project Manager assigned to build a next generation vehicle. You identify a
dependency that before the vehicle can be sold, it must be approved by a governmental
regulatory authority. This is an example of which type of dependency?
a. External
b. Discretionary
c.

Soft Logic

d. Mandatory
42. You are required to estimate the time to paint a large wall. You know it takes two hours to paint
one square foot of wall. The wall has an area of 30 square foot. So you estimate that it will take
60 hours to paint the wall. Which estimation model are you using?
a. Bottom-up
b. Parametric modeling
c.

Analogous

d. Expert judgment
43. The level of accuracy for order of magnitude estimation is
a. -25% to +75%
b. -25% to +50%

c.

-25% to +25%

d. -25% to +10%
44. You are the project manager responsible for building a new web site. The project is running late.
To bring the project on schedule, you decide to add additional resources to the critical path. This
is an example of
a. Fast-tracking
b. Resource planning
c.

Crashing

d. Schedule Management
45. You are the project manager of ABC project. One of the risks that has been identifies is attrition of
team members. Mid-way through the project you notice that the morale and motivation of the
team members is going down. You think that this is a precursor to people leaving the
organization. For this risk, low motivation is an example of
a. work-around
b. trigger
c.

risk monitoring

d. risk planning
46. You are working on the project of painting of your house. You identify a dependency that the
painting of roof should begin only after two days of completion of painting of walls. This is an
example of
a. Lag
b. Lead
c.

Slack

d. Float
47. What percentage of Project Manager's time is spent on communicating?
a. 30

b. 50
c.

70

d. 90
48. You are the Project Manager for XYZ project. The scope of the project has been completed. You
receive a request for a new module to be developed as part of this project. What should you do
next?
a. You should approach the Project sponsor and ask her for a new module to be developed
as part of this project.
b. You should approach the Senior Management and ask them for a new module to be
developed as part of this project.
c.

You should send the request to Change Control Board for approval.

d. Since the project scope is completed you should inform the customer that this change
cannot be done as part of the project.
49. Perform Quality Assurance process is part of which phase?
a. Planning
b. Execution
c.

Control

d. Closure
50. You are managing the project of planning a party for your company employees. There is a risk
that the employees will not come to the party. You decide to not take any action against this as the
likelihood of this is low. Which risk response strategy are you following?
a. Acceptance
b. Avoidance
c.

Mitigation

d. Transference
51. The process of Conduct Procurements is part of which phase?

a. Planning
b. Execution
c.

Control

d. Closure

Answers

1. A It is part of the Stakeholder Management Strategy, which is an output of identify stakeholders.


PMBOK Guide, 5th edition, p. 396
2. c. finish-to-start is the most commonly used relationship.
3. c. AOA activity diagrams are represented using finish-to-start representation.
4. a. Experts participating in the Delphi technique are anonymous.
5. b. Senior Management is responsible for issuing the charter.
6. c. This was an unplanned event that happened. Work around refers to handling of risk that has
occurred but was not planned for.
7. a. Schedules are most common cause of conflicts.
8. b. Problem-solving or Confrontation is the best solution for resolving conflicts and leads to longlasting conflict resolution.
9. b. Insurance is an example of transferring risk.
10. b. Grade refers to category or rank given to entities having same functional use but different
technical characteristics. As an example a basic $10K car belongs to a different grade when
compared to a $50K luxury car. Your expectations from the two cars and their performances will
differ because they belong to different grades.
11. d. Continuous small improvements is part of Kaizen theory. Hence a is incorrect. The Plan-doCheck-Act doctrine was proposed by Deming.
12. b. Benchmarking is not a tool for Quality Control process
13. a. Pareto chart is built on the 80:20 theory. 80% of the defects are caused due to 20% of the
issues. A Project Manager needs to focus on these 20% issues.
14. d. Ishikawa or Fish bone diagram is the tool that the Project Manager is planning to use.

15. c. CDGIR represents the critical path. It is the longest path through the network with the duration
of 13.
16. d. The path ABIR has duration of seven. Hence B can be delayed by six days before the next
event can begin.
17. c. The path CDHR has duration of nine days. Hence H can be delayed by four days before the
next event can begin.
18. d. Job security, salary, clean and safe working conditions are examples of hygiene factors.
Appreciation at work is not a hygiene factor, but instead a motivating factor.
19. b. Physiological factors appear at the lowest level of Maslow's hierarchy triangle.
20. a. The other three options are examples of benefit measurement method.
21. d. Dynamic Programming is an example of Constrained Optimization method. Murder board is an
example of benefit measurement method.
22. c. Murder board is a process where a committee asks questions from project representatives as
part of the project selection process.
23. c. Control Scope process is part of scope management knowledge area.
24. a. WBS dictionary is the best option. WBS Dictionary identifies all the components used in the
WBS
25. d. Scope Validation is the process of the customer accepting the project deliverables.
26. d. Mean for PERT is defined as (P+4M+O)/6 which comes out to be 16 days.
27. b. Control Procurements is a process in the Project Procurement Management Knowledge area.
28. c. In oligopoly, the action of one seller has an impact on other sellers, as there are very few
sellers.
29. b. Each year $200 gets removed from the value of computer. After three years the value becomes
$400.
30. c. The others are true statements about analogous estimating.
31. d. Learning curve estimation uses the principal that the cost per unit will decrease as more units
of work are manufactured.
32. a. The behavior described is an illustration of Halo's effect.

33. c. Close Procurements and Close Project or phase are the two closure processes.
34. d. The Configuration (or Change) Control Board has the authority to approve or deny change
requests.
35. b. Cost baseline includes the project budget for each month.
36. a. WBS should focus on deliverables.
37. d. WBS is an output of the Create WBS.
38. b. Project Manager is identified as part of the Develop Project Charter process.
39. d. Mandatory dependency represents dependencies due to nature of work.
40. a. This is an example of dependency to an external (outside) body.
41. b. Parametric modeling is the best option.
42. a. The order of magnitude is preferred during initiation phase, and it has an accuracy range of
-25% to 75%
43. c. Crashing involves adding extra resources to reduce the project duration.
44. b. A risk trigger is an indication that the risk is about to occur or has occurred.
45. a. This is an example of lag. Lag is the amount of time after the completion of the predecessor
activity, when the successor activity can start.
46. d. According to PMBOK 90% of Project Managers time is spent in communicating.
47. d. As the scope is completed, the project is complete. Additional work should be done as part of a
new project.
48. b. Perform Quality Assurance is part of Execution phase.
49. a. This is an example of Acceptance risk response strategy.
50. b. Conduct Procurements is part of execution phase.

Selection of questions courtesy of Richard Perrin, PMP

Anda mungkin juga menyukai