2009
TABLE OF CONTENTS
DISTRIBUTION LIST (at end of Table of Contents)
DISCLAIMER
FORMS CD Safety Program Forms
1.0
INTRODUCTION
Section 1 - Forms
2.0
RESPONSIBILITIES
2.1
HARVARD
2.1.1
2.1.2
2.1.3
2.1.4
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
MANAGERS RESPONSIBILITIES
SUPERVISORS RESPONSIBILITIES
WORKERS RESPONSIBILITIES
SAFETY PROFESSIONALS RESPONSIBILITIES
VISITORS RESPONSIBILITIES
DUE DILIGENCE
DRILLING & COMPLETIONS SPECIFIC RESPONSIBILITIES
STANDARDS FOR WELLSITE SUPERVISION OF DRILLING,
COMPLETION AND WORKOVERS VOL. 7 2002
Section 2 - Forms
3.0
Safety Statement
Table of Contents - i
4.0
OVERVIEW
RESPONSIBILITY
SIZE AND SCOPE OF ASSESSMENTS
ASSESSMENT INTERVALS
PROCESS OF HAZARD IDENTIFICATION
TYPES OF INSPECTIONS
4.6.1 ON-GOING INFORMAL INSPECTIONS
4.6.2 PLANNED INSPECTIONS (FORMAL)
4.6.3 SAFETY AUDITS, LOSS PREVENTION SURVEYS AND REGULATORY INSPECTIONS
4.6.4 EQUIPMENT PREVENTATIVE MAINTENANCE
4.6.5 INCIDENT INVESTIGATION FINDINGS
Figure 1: Hazard Identification, Elimination & Control Flowchart
4.7
4.8
RISK MATRIX
HAZARD ASSESSMENT TOOLS & CHECKLISTS
4.8.1
4.8.2
4.8.3
4.8.4
4.8.5
4.8.6
4.8.7
4.8.8
4.8.9
4.8.10
4.8.11
4.8.12
4.8.13
4.8.14
4.8.15
4.8.16
4.8.17
4.8.18
4.8.19
4.8.20
4.8.21
4.8.22
4.8.23
4.8.24
4.8.25
4.8.26
4.8.27
4.8.28
4.8.29
4.8.30
4.8.31
4.8.32
4.8.33
4.8.34
4.8.35
4.8.36
4.8.37
4.8.38
4.9
Table of Contents - ii
4.10
4.11
5.0
COMMUNICATION
5.1
MEETINGS
5.1.1
5.1.2
5.2
Section 5 Forms
Work Permit
6.0
OVERVIEW
INCIDENT REPORTING
ACCIDENT INVESTIGATION AND FOLLOW-UP
LOSS CONTROL STATISTICS
INCIDENT INVESTIGATION RESPONSIBILITY FLOWCHART
INCIDENT INVESTIGATION METHODOLOGY FLOWCHART
INCIDENT INVESTIGATION REPORT
SUMMARY OF RESPONSIBILITIES AND EXPLANATIONS
FOR FILLING OUT THE FORM
Section 6 - Forms
7.0
EMERGENCY PREPAREDNESS
7.1
8.0
OVERVIEW
WORK PROCEDURES
8.1
CODES OF PRACTICE
8.1.1
8.1.2
8.1.3
8.1.4
8.1.5
8.1.6
8.2
ASBESTOS
BENZENE
CONFINED SPACE ENTRY
RELEASE OF HARMFUL SUBSTANCE
RESPIRATORY PROTECTIVE EQUIPMENT
8.1.5.1 SELECTION, MAINTENANCE & USE OF RESPIRATORY
PROTECTIVE EQUIPMENT
Figure 1: Selection of Respiratory Equipment
Respiratory Protective Equipment Worksheet
8.1.5.2 FIT TESTING REQUIREMENTS & PROCEDURES FOR RESPIRATORY
PROTECTION
8.1.5.3 INSPECTION OF AIR PURIFYING RESPIRATORS & ATMOSPHERE
SUPPLYING RESPIRATORS
8.1.5.4 CLEANING & STORAGE OF RESPIRATORY PROTECTIVE EQUIPMENT
8.1.5.5 TRAINING OF WORKERS IN THE SELECTION, USE, CARE AND
MAINTENANCE OF RESPIRATORY PROTECTION EQUIPMENT
8.1.5.6 DEFINITIONS RESPIRATORY HAZARDS
SOUR SERVICE
WORK PROCEDURES
8.2.1
8.2.2
8.2.3
8.2.4
8.2.5
8.2.6
8.2.7
8.2.8
8.2.9
8.2.10
8.2.11
8.2.12
8.2.13
8.2.14
8.2.15
8.2.16
8.2.17
8.2.18
8.2.19
8.2.20
AIRCRAFT AWARENESS
ALL TERRAIN VEHICLES (ATVs)
- ATV CHECKLIST
BLOWDOWNS
CABLES, CHAINS AND ROPES
CHEMICAL & BIOLOGICAL HAZARDS
8.2.5.1 ASBESTOS
8.2.5.2 BENZENE
8.2.5.3 HANTA VIRUS
8.2.5.4 SEWAGE
COMMUNICATION EQUIPMENT
COMPRESSED GAS CYLINDERS
CRANES AND HOISTING DEVICES
CRITICAL LIFT PROCEDURES
CROWN SAVERS
DRIVING CONDUCT
FALL PROTECTION
FIRE & EXPLOSION HAZARD MANAGEMENT
FIRE PREVENTION
FLAMMABLE AND HAZARDOUS LIQUID
FLOWBACKS
FUEL AND CHEMICAL STORAGE
GROUND DISTURBANCE
HAND AND POWER TOOLS
HEATERS & OPEN FLAME EQUIPMENT
Table of Contents - iv
8.2.21
8.2.22
8.2.23
8.2.24
8.2.25
8.2.26
8.2.27
8.2.28
8.2.29
8.2.30
8.2.31
8.2.32
8.2.33
9.0
TRAINING
9.1
OVERVIEW
9.1.1
9.1.2
9.1.3
9.1.4
9.1.5
9.2
9.3
9.4
9.5
9.6
9.7
SAFETY ORIENTATION
ON-THE-JOB TRAINING
OPTIONAL AND NON-OPTIONAL TRAINING
TECHNICAL TRAINING
SUPERVISORY TRAINING
TRAINING RECORDS
Section 9 - Forms
Table of Contents - v
10.0
CONTRACTOR OPERATIONS
10.1
10.2
10.3
10.4
OVERVIEW
SELECTION
CONTROL
FOLLOW-UP
Section 10 - Forms
OVERVIEW
STORAGE AND HANDLING OF HAZARDOUS MATERIALS
11.2.1 TRANSPORTATION OF DANGEROUS GOODS
11.3
11.4
11.5
HEARING CONSERVATION
NATURALLY OCCURRING RADIOACTIVE MATERIALS (NORM)
ASBESTOS CONTROL
BENZENE
GENERAL
HEAD PROTECTION
EYE AND FACE PROTECTION
HEARING PROTECTION
HAND PROTECTION
BODY PROTECTION
RESPIRATORY EQUIPMENT
FOOT PROTECTION
FIRE-RETARDANT CLOTHING STANDARD
PRESCRIPTION SAFETY GLASSES PURCHASE PROCEDURE
MANAGEMENT COMMUNICATION
Section 12 - Forms
OVERVIEW
MANAGEMENT OF CHANGE
REFERENCE DOCUMENTS
13.3.1 COMPANY DOCUMENTS
13.3.2 GOVERNMENT DOCUMENTS
13.3.3 GENERAL DOCUMENTS
13.4
RECORD KEEPING
Table of Contents - vi
OVERVIEW
WASTE MANAGEMENT
AUDITS AND INSPECTIONS
14.3.1 ENVIRONMENTAL IMPACTS
14.3.2 COMMUNICATION & REPORT
14.3.3 ENVIRONMENTAL MANAGEMENT SYSTEM
14.4
PROCEDURES
14.4.1
14.4.2
14.4.3
14.4.4
14.4.5
14.4.6
14.4.7
14.4.8
14.4.9
14.4.10
14.4.11
INTRODUCTION
SAFETY PLAN CHECKLIST
EMERGENCY CONTACT INFORMATION
WEEKLY SAFETY MEETINGS
SHUT DOWN OF PRODUCTION
Section 15 - Forms
DISTRIBUTION LIST
NAME
LOCATION
MANUAL
NUMBER
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Table of Contents - ix
DISCLAIMER
The information and data contained in this document has been set forth to be the best
knowledge, information and belief of OPX Consulting Inc.
Although every effort has been made to confirm all such information and data is factual,
complete and accurate, OPX Consulting Inc. make no guarantees or warranties whatsoever,
whether expressed or implied, with respect to such information or data and accepts no
responsibility for any loss or damage sustained by the use of this information.
Any use, which a third party makes of this document, any reliance on, or decision to be made
based on it, is the responsibility of such third parties. OPX Consulting Inc. accepts no
responsibility for damages, if any, suffered by any third party as a result of decisions or actions
based on this document.
Table of Contents - x
1.0
INTRODUCTION
Harvard Energy Ltd. is an oil and gas exploration and development company
operating primarily in Western Canada. HARVARD is committed to conducting
operations in a safe and environmentally sound manner. In support of this commitment,
HARVARD has developed a General Policy on Health, Safety and the Environment. A
copy of this document follows in this Introduction Section.
In order to fulfill this commitment, HARVARD has developed a Safety Program to
ensure its operations comply with this policy. The program includes a Management
Plan for implementing the Program. This manual is intended to present that Plan and to
provide management, employees and contractors with the tools, information and
references they need to carry out that Plan.
It is HARVARDs practice to provide each user of this manual (i.e. operators,
supervisors and contractors) with training in its use. This training should be considered
as the primary orientation of new personnel to HARVARDs operations.
Complementary documents, tools and training include HARVARDs:
This manual in its entirety should always be considered a work-in-progress. All users
are encouraged to provide suggestions to the Engineering and Operations Department
for improvements to its content and format.
The development of this Safety Program, together with supporting training, will help all
HARVARD staff, contractors and supervisors to:
1.
2.
3.
4.
Control work site hazards, thus minimizing the risk to HARVARD employees, its
contractors, and the public.
Section 1 - 1
All personnel directly involved with HARVARD operations, including both Company and
Contract personnel, are responsible for ensuring their activities are consistent with this
manual.
Following is a brief description of each section of this manual:
Section 2 of this manual describes the legislated responsibilities of Owners and Prime
Contractors at the work site. It is critically important that HARVARD staff and well site
supervisors understand their responsibilities as representatives of the Owner, who
normally will be the Prime Contractor. In addition, all contractors who are employers at
the well site must understand their responsibilities in providing their own safety
programs and competent employees to carry out their activities. Also in this section is a
summary of responsibilities of HARVARD Managers, Supervisors and Workers.
Section 3 contains information to assist HARVARD management and staff to plan for
implementing the Safety Program.
Section 4 provides information on hazard identification and assessment. Identifying
and eliminating hazards is the most important element of a safety program and must be
done at every work site to comply with Provincial regulations.
Section 5 deals with communication and gives the supervisor the necessary tools to
communicate with other employees and all workers at the site. Once hazards are
identified and procedures put into place to eliminate or mitigate the hazards it is
necessary to communicate that information to all affected workers. Of particular
importance in this section is the description of the use of Safe Work Permits.
Section 6 presents HARVARDs procedures for incident investigation and analysis.
This is an essential part of any safety program.
Section 7 gives the supervisor some basic information about area emergency
response plans and some suggestions for keeping area plans up to date.
Section 8 presents a number of established Codes of Practice and Work Procedures.
The Codes of Practice are to be followed when dealing with the subject issues. The
Work Procedures presented have been developed as HARVARDs policy. This section
of the manual should be considered a work in progress. The codes and procedures
should constantly be reviewed for relevancy to current HARVARD policies, government
regulations and practices in the industry. New codes and procedures will be developed
as the need arises.
Section 9 outlines the training expected of HARVARD production employees and the
employees of all contractors involved at a well site.
Section 10 gives the production supervisor some guidelines to use in selecting
contractors in the field.
Section 11 presents Health and Safety Controls. These, for the most part, are existing
regulations or HARVARD policy and must be strictly adhered to. Special attention
should be paid to HARVARDs Fire Retardant Clothing Standard.
Section 1 - 2
Section 1 - 3
SECTION 1 FORMS
Policy on Health, Safety and the Environment
Policy on Drug and Alcohol
Policy on Violence and Harassment
Petroleum Industry Guiding Principles for Worker Safety
Section 1 - 4
Section 1 - 6
Post-incident testing;
Section 1 - 7
RESPONSIBILITY
The operating company, when acting as prime contractor, is responsible for coordination
and general supervision of all activities at the worksite, including activities carried out
by contractors, subcontractors, service companies and suppliers. While all parties have a
responsibility to promote worker safety, the operating company recognizes its leadership role
worksite situations. It is the responsibility of workers and employers to refuse to perform
unsafe work practices.
PRIORITY
Activities will be conducted on the basis that safety of all personnel is of vital importance,
whether those personnel are employed by an operating company, a contractor, a subcontractor,
a service company or a supplier.
RECOGNITION
The process of selecting contractors, subcontractors, service companies and suppliers, and the
administration of contracts, will include recognition and support of good safety performance.
Support and recognition based on good safety performance will also be provided by all
employers to their employees.
IMPROVEMENT
The operating company, in cooperation with service companies within the industry, will
promote methods and practices that have potential for improving safety performance.
Wallace E. Baer
President/CEO
Enform
Signed on behalf of the following six sponsoring associations representing the Canadian
petroleum industry:
Signature
Title
Company
Date
2.0
RESPONSIBILITIES
2.1
HARVARD
Ensure the safety program and operations comply with contractual and regulatory
requirements.
Provide sufficient time for contractors and employees to do their job properly.
Hire contractors who have Safety Programs and good safety records.
Every work site must have a Prime Contractor, if there are two or more employers
involved in work at the worksite at the same time
The Prime Contractor for a worksite is the contractor, employer or other person who
enters into an agreement with the owner of the work site to be the Prime Contractor,
or if no agreement has been made or no agreement is in force, the owner of the
work site.
Owners, who have limited capabilities of performing the Prime Contractor function
have the opportunity to assign Prime Contractor responsibilities to a party that is
better equipped to manage those responsibilities.
Section 2 - 1
Once the Owner enters into an agreement, it should step away and not be involved
as a Prime Contractor of the work site. If the owner starts to assume the role of
Prime Contractor, it may become liable for those responsibilities even though it has
entered into an agreement to have someone else assume those responsibilities.
The Prime Contractor, be it the Owner/Operator or some other party, is responsible for
ensuring that the Occupational Health and Safety Act, Code, and its regulations are
complied with at the work site. In most situations, the Prime Contractor will meet these
responsibilities through the development of a system that will ensure compliance. The
Prime Contractor at a work site has the overall responsibility for occupational health and
safety. However, this does not relieve other employers of their responsibilities at the
work site.
The Well Site Supervisor usually accepts the role of Prime Contractors representative
at the work site.
In addition to developing a system for ensuring compliance, the role of the Prime
Contractor will be to implement the system, monitor to ensure that it is functioning, and
then make any necessary changes to ensure the system continues to perform as
intended.
The advantages of the system approach are that the process is manageable and that
the Prime Contractor limits its responsibilities. If the Prime Contractor were to take
direct control of all occupational health and safety activities at the work site, particularly
on a large site, it would become an onerous task. If the Prime Contractor begins to take
a more assertive role in directing the occupational health and safety activities of other
employers on the work site, it may end up with those responsibilities.
Section 2 - 2
Ensure that the workers are identifying, reporting and recording hazards on the site.
Ensure that critical or repetitive hazards are discussed by workers during a safety
meeting.
Section 2 - 3
2.2
Ensure all work site emergency safety equipment is easily identifiable to all site
personnel (e.g. fire suppression equipment, first aid room, stretcher, etc.) and is in
good operating condition.
MANAGERS RESPONSIBILITIES
Insisting on performance and behavior that meet the standards of HARVARDs safety
program.
Ensuring accidents and incidents are reported and investigated and corrective actions are
taken.
Providing appropriate, well-maintained safety and other equipment required for each job.
2.3
SUPERVISORS RESPONSIBILITIES
Section 2 - 4
Appropriate equipment is available and well maintained and workers are trained to safely
operate the equipment.
Workers know and are prepared to deal with the hazards of their work and any specific
hazards on the work site.
Personal protective equipment is available, properly used, stored, maintained and replaced
when necessary.
2.4
WORKERS RESPONSIBILITIES
Workers protect themselves, fellow workers, the public and the environment by:
Following safety standards and safe work procedures set out by the employer, employees
and regulatory requirements.
Refusing to perform work when unsafe conditions exist (as defined in provincial
occupational health and safety legislation).
Participating in all training offered by the employer, either on or off the work site (e.g. first aid or
H2S).
Checking tools and equipment, including personal protective and safety equipment, for
hazards before using them.
Section 2 - 5
Presenting themselves physically and mentally fit at the start of each working shift, capable
of performing their duties safely and efficiently. Reporting to the Supervisor any physical or
mental circumstances such as illnesses or fatigue as this may impede the worker from
safely completing their assigned tasks.
Performing their functions as efficiently as possible while giving due regard to the safety of
themselves, their co-workers and the public.
Having cranial and facial worn at a length that will not obstruct vision, snag moving parts or
if applicable, prevent the worker from utilizing a breathing apparatus or mechanical
resuscitator in a toxic or oxygen environment.
Ensuring they wear clothing that fits close to the body and do not wear dangling
jewelry (i.e. necklaces, wristwatches, bracelets) when working near moving parts of
machinery or electrically energized equipment.
Not smoking in any location regardless of a Hot Permit issued, except for designated areas.
Strike anywhere matches and single action lighters are not permitted.
Not being in possession of, or under the influence of, alcohol, illegal or mind altering drugs.
Workers will not be permitted to enter or be allowed to remain on a Harvard Work Site.
Refraining from engaging in practical jokes, wrestling and other forms of horseplay on
Harvard premises.
Reviewing applicable Data Sheets, as per WHMIS legislation, prior to handling chemicals.
Understanding Harvard prohibits all types of harassment and violence in the workplace.
Harassment, including harassment based on characteristics specified in human rights
legislation, such as sex, race, national origin, religion, disability and age is illegal and will
not be tolerated. As an employer, Harvard has a legal duty to maintain a safe and
harassment free workplace. Actual or threatened violence is strictly prohibited. Incidents of
this nature are to be reported to Harvard management.
Ensuring they have the necessary training and when applicable possesses a valid
certificate when responsible for the transporting of dangerous goods and handling material
or wastes.
Section 2 - 6
2.5
Develop and maintain a safety program manual and ensure this document is available to all
employees.
Maintain copies of legislation relevant to Companys operations and ensure copies are
available at all work sites.
Maintain files for results of audits, inspections, incident investigation reports and safety and
environmental performance assessments.
Develop and support loss control activities including inspections, loss control meetings, new
employee orientations, on-the-job training sessions, safety and environmental audits and
emergency response drills.
Develop and support a communication framework that may include management walkarounds at work sites, newsletters, memos, posters or other communication instruments.
Provide assistance to field personnel in the response and reporting of Safety and
Environmental incidents.
2.6
VISITORS RESPONSIBILITIES
Visitors must:
2.7
DUE DILIGENCE
See Workplace Health & Safety bulletin and the Bill C-45 Explanation at end of this Section.
Section 2 - 7
2.8
Implement an effective safety program, including visible management support, that meets
the requirements for a basic safety program as described in IRP #9, ensuring that all
employers on site are aware of, and comply with, all requirements of this program.
Select contractors that have implemented a safety program that effectively manages their
own operations, and that meets the requirements for a basic safety program as described
above, including safe work procedures and hazard assessments of the hazardous
procedures completed. Any independent contractors or self-employed workers, who do not
have a safety program, will be adopted into either HARVARDs safety program or the safety
program of HARVARD they are sub-contracted to.
Coordinate the efforts and actions of all contractors at the wellsite, ensuring all employers
are aware of their roles and responsibilities, and that they have been informed of any
known hazards of the specific wellsite, program or materials, ensuring that procedures are
in place to eliminate or control these hazards.
Ensure that all safety procedures are compatible and verify that contractors are providing
their workers with training and supervision that addresses the hazards of the tasks they are
exposed to at the wellsite. It is not HARVARDs role to do this training or supervision for
contracted workers, but to ensure that contractors provide training and supervision in a
manner that meets legislated requirements as a minimum, as per Section 7.4.3. of IRP #7.
(Please see IRP#7 on page 2-14)
Section 2 - 8
Ensure that site-specific emergency response procedures are in place and that all
employers and workers know these procedures, have completed drills and are prepared to
follow them.
Ensure that Site Supervisors safety responsibilities have been clearly established and
communicated to all workers completing supervisory activities and that monitoring is
completed on a regular basis.
Conduct an assessment of the supervisors work experience and training to ensure he has
the skills and knowledge required to meet the requirements for the work and duties being
assigned.
The evaluation will include the steps and content described below, and be documented, signed
and kept on file by the person to whom the supervisor is reporting to.
Identify themselves at the wellsite, through use of the applicable Safety Statement,
ensuring they can be either easily located and contacted or have identified an alternate,
competent, person who must also be easily contacted if the Wellsite Supervisor becomes
unavailable for any reason. Note: Site Supervisors are required to be on the worksite during
all non-standard/critical work tasks.
Ensure that all contractors on the worksite effectively implement their own safety programs
and work procedures, and that all contractors understand and agree to follow all
requirements of HARVARDs Safety Program that is not identified within their own Safety
Program.
Ensure that applicable corporate information has been posted in an appropriate place on
location, including the posting of HARVARDs Health and Safety Policy and Partnership
Certificate within the supervisors workspace, and that a copy of the Safety Statement and
Petroleum Industry Guiding Principles has been posted in the contractors workspace
(doghouse).
Section 2 - 9
Identify and document the name of the On-Site Supervisor for each employer prior to
starting any work and review and clarify the roles and responsibilities of all Contractors OnSite Supervisors prior to starting any work.
Check that all contractors have provided the applicable employees, including visitors, with
the training and supervision described in Section 7.4.3. of IRP #7. (Please see IRP#7 on
page 2-14)
Identify inexperienced workers arriving on the worksite, ensuring these workers receive
adequate supervision and provide a wellsite orientation on arrival at the wellsite.
Coordinate the efforts of all employers at the wellsite, resolving any discrepancies between
conflicting work procedures, identifying the hazards related to the specific wellsite, the
planned program or the materials provided by the contractors.
Inform all employers of the hazards identified and ensure proper controls are in place
before the work begins. Establish and coordinate site-specific emergency response
procedures and drills.
Ensure the hazard assessment and identification programs described in the Hazard
Identification and Assessment section of the Safety Program is implemented and reviewed
with relevant workers on the worksite.
Ensure the hazards identified on the worksite are communicated through the safety
meeting and work permit systems, ensuring safety meetings are conducted prior to all nonstandard/critical operations.
Ensure well control and blowout prevention measures meet regulations and operators
requirements and the appropriate information and procedures have been posted and
reviewed with all personnel on site.
Monitor the work performed by all employers to verify compliance with safety legislation and
Safety Program requirements.
Check that the procedures for handling, transportation, disposal, storage and use of all
hazardous substances follow applicable regulations and safe practices. Monitor the wellsite
for proper use, handling, storage and maintenance of personal protective equipment.
Ensure appropriate equipment is utilized to detect and control Hydrogen Sulfide and other
flammable or poisonous substances that may be emitted at the worksite.
Ensure work is stopped when an unsafe act or condition is identified, resuming work only
after the hazard is removed or safe procedures have been established.
Ensure all emergency equipment and specialized safety equipment is easily identifiable
and readily available to all site personnel.
Section 2 - 10
Section 2 - 11
Required Information
Record of Work History and References
List of references starting with the last three employers (or back five years), including:
o
o
o
Supervision and leadership, and the demonstration of safe personal work habits.
Ensuring contractors have, and are using, safe work procedures that follow regulations.
Carry out operations in accordance with environmental regulations, including the disposal
of wastes, BOP training and drills and training certificates.
Section 2 - 12
Containment and reporting of spills, leaks or other environmental damage, as per incident
reporting guidelines (see Section 6.0).
Ensuring BOPs and other well control equipment meet regulations, and is function tested
prior to commencing operations.
Ensuring transportation of equipment, rig and equipment layout and spacing meet
equipment spacing regulations.
Contractors Supervision
Legislation requires that contractors provide their workers with appropriate training and
supervision to ensure they carry out their work in a safe manner.
HARVARD requires all employers to provide the following:
A safety program that includes information that identifies the worker as responsible to follow
the requirements of the safety program.
Information to ensure workers are aware of their rights and responsibilities under OH&S
legislation, including their right and obligation to refuse to do unsafe work.
Safe work procedures and practices for the assigned tasks, including rules from relevant
safety legislation.
Direct supervision, by a competent worker, of workers new to a position until they have
demonstrated the ability to perform the assigned tasks safely.
Frequent inspections of the wellsite, to ensure workers are following safe worker practices
and applicable OH&S regulations.
A hazard identification program/process, ensuring all personnel on the worksite are made
aware of the hazards and procedures to remove or control the hazards.
Directions to stop work when unsafe acts or conditions are identified then take action to
ensure conditions are safe before work is resumed.
Site-specific emergency response procedures are in place and all workers are prepared to
play their role in the event of an emergency.
Directions for the prompt reporting and investigation of any incidents on location.
Section 2 - 13
2.9
IRP #7
Section 2 - 14
Industry Recommended
Practice (IRP)
Volume 7 - 2002
Sanctioned
2002 - 03
Table of Contents
7
7.5
7.6
Table of Contents i
Table of Contents ii
7.0
Saskatchewan Labour
Doug Fletcher
Petro-Canada
Les Groeller
Shell Canada
Kenn Hample
Barry Holland
Ron Hutzal
Noyes Supervision
Rod Loewen
John Mayall
EUB - Alberta
George Myette
Pajak Engineering
Mark Nicklom
Bissett Resources
Kim Richardson
Marathon Oil
Bob Ross
Brad Rowbotham
Ken Shewan
Frontier Engineering
Murray Sunstrum
Jack Thacker
Husky Oil
Willy Zukiwski
PanCanadian
Other
Contributors:
Ron Berg
Precision Drilling
Bob Cunningham
Adel Girgis
Dave Graber
Garth Gramlich
PanCanadian
Wayne Harvey
Safety Consultant
Ron Lapp
Jade Drilling
John Miller
PanCanadian
Ron Miller
Consultant
Lorne Polzin
Barry Rock
Shell Canada
Jim Shaffer
Bob Stockton
Consultant
Jim Storbakken
Imperial Oil
Rod Thomas
Bonus Resources
Layne Wilk
7.1
Introduction
7.2
Scope
This IRP deals with well operations that are generally known in the
industry as drilling, completions and workovers. Minor well
servicing on completed wells, which do not require removal of the
wellhead and do not require the installation of temporary blow out
prevention equipment to ensure well control during the operation, is
beyond the scope of this IRP. However, the responsibilities of the
prime contractor, in terms of safety management, are essentially the
same for any operation involving two or more employers at a
wellsite.
The subject of the IRP is supervision at the wellsite by the prime
contractor, which is usually the operator. Each employer or
contractor at the well site must also provide competent supervision
for their employees. Responsibilities of an employers supervisor
are discussed relative to the duties of the prime contractors
supervisor. Specific qualification requirements for supervisors of
other employers at the wellsite are not part of this IRP.
While the focus of the IRP is the wellsite supervisor, it must be
recognized that the responsibilities are basically those of the
operator and/or the prime contractor. Therefore the operator and/or
prime contractor must have a good understanding of these
requirements and a clear agreement with the wellsite supervisor as
to how these obligations will be met.
These recommendations are based on regulatory compliance and
due diligence. The specific requirements for the work planned in
drilling, completions and workover operations vary widely and part
of the operators due diligence is to assign competent supervision
for the specific work being supervised. This IRP does not attempt to
define supervisor competency requirements for every type of job
but does describe the minimum steps the operator or prime
contractor should take in making this determination.
7.3
Definitions
7.4
The operator, as owner and licensee of the well and wellsite, has
overall responsibility to ensure the safety of workers and the
public, the protection of the environment and the conservation of
resources related to all activity at the wellsite and in the
wellbore. There are many rules governing the design, planning
and execution of oil and gas operations. These are provided in
various legislated acts, regulations and guides as well as
recognized standards and IRPs. The operator must ensure
compliance with all of these. Responsibility for compliance with
many of the rules may be assigned to people doing the planning,
design and programming of well operations at the office level.
When these programs are implemented in the field, the wellsite
supervisor represents the operator/prime contractor.
7.4.1.2 Safety
10
11
12
7.4.2.2 Safety
13
14
15
16
7.5
IRP:
17
18
7.6
Training Requirements
19
Course
Renewal*
Frequency
(years)
Drilling
Supervisor
Completions
Workover
Supervisor
Person
Directing
Wellsite
Supervisor
Yes
Yes
Yes
Yes
No
No
Yes
Yes
for drilling
Yes
for
completions
& servicing
Optional
Yes
Optional
Yes
Yes
Yes
Yes
Yes
Optional
TDG **
Yes
Yes
Yes
Yes
Yes
Yes
H2S Alive
20
7.6.4.2 Safety
Management
and Regulatory
Awareness for
Wellsite
Supervision
(Refresher)
21
7.6.4.3 Second
Line
Supervisors
Well Control
This course deals with well control during open hole drilling
operations. Participants are required to perform well control
procedures and demonstrate the proper response to hole and
equipment problems using test well equipment. The course also
includes wellbore pressure concepts, well control strategies
while on bottom, tripping and while out of the hole, appropriate
techniques for management of people and equipment related to
well control at the wellsite.
7.6.4.4 Well
Service Blowout
Prevention
(BOP)
7.6.4.5
Detection and
Control of
Flammable
Substance
7.6.4.6
Workplace
Hazardous
Materials
Information
Systems
(WHMIS)
Training
22
7.6.4.7 Standard
First Aid
7.6.4.8
Transportation
of Dangerous
Goods (TDG)
7.6.4.9 H2S
Alive
23
7.7
24
7.7.2.2 Changes
in Job
Assignment
25
For each duty assigned, the assessor must determine if the skill
level of the candidate meets the requirements to carry out the
task. This determination must be based on the education, training
and work history record plus the skills observed by the
references and the assessor. It is suggested the assessor rate the
candidate as either 'meets or exceeds requirements' or as
'requires additional training or experience' in which case
comments should be included as to what is required.
7.7.3.2 Required
Information
Record of Work
History and
References
supervision
- experience as a wellsite supervisor, if not entry level
- other relevant industry experience not at the wellsite
26
and year
- was this reference contacted by assessor? If so, on what
date?
27
7.7.3.3 Minimum The candidate must be assessed as having the skills required in
the following categories, considering the points described and
Skill
the work assigned:
Assessment
Requirements
Supervision and Leadership
Emergency Response
-
28
Environmental Protection
-
Well Control
-
29
7.7.3.4
Additional Job
Specific Skill
Requirements
30
7.8
31
7.8.1 Documentation
Good management practices require that results achieved must
be compared to the goals and expectations on a regular basis in
order to identify performance gaps and opportunities for
improvement. The performance of wellsite supervisors must be
monitored and evaluated as part of this process. New supervisors
should be evaluated more frequently than supervisors with
proven track records.
32
33
34
Appendix A:
Levels of Control and Responsibility for Safety Management
Appendix A 35
Appendix B:
Notice of Wellsite Supervisor (Sample)
Note: Saskatchewan Labour has a sample Generic Form to assist in complying with Section 412 of OH&S
regulations in that province.
TAKE NOTICE that ___________________________________________(operator/prime contractor)
HEREBY APPOINTS _______________________________________________(name of supervisor)
as the wellsite supervisor of the following undertaking:
Drilling
Completion / Workover
Description of well operations to be carried out:
Check that all employers on the wellsite have a safety program including safe work procedures.
Ensure all employers understand and agree to follow all requirements of the prime contractors safety program that
are not already met by their own safety program.
Direct and co-ordinate the efforts of all employers at the wellsite, including:
review and clarification of roles and responsibilities of all employers and supervisors
resolution of discrepancies between safe work procedures
safe transportation, storage, use and disposal all hazardous substances
Identify hazards related to the specific wellsite, the planned program or the materials provided by the prime
contractor. Inform all employers of these hazards and ensure procedures are in place to control these hazards.
Ensure the following site specific hazard controls meet requirements and standards:
well control and blowout prevention
detection and control of Hydrogen Sulfide gas emissions
detection and control of any flammable substances that may be emitted
Establish and direct site-specific emergency response procedures
Monitor work activities of all employers and work activities to verify:
compliance with safety legislation
safe work procedures and proper use of PPE are followed
all employees receive supervision and training from their employer as per IRP Volume 7
The Supervisor is knowledgeable about and experienced in all of the matters listed above.
Assigned By:__________________________________ (representative of operator/ prime contractor)
Contact phone #s:___________________(work)___________________(cell)
Accepted By:__________________________________ (signed by wellsite supervisor )
Contact phone #s:___________________(work)___________________(cell)
Appendix B 36
SECTION 2 FORMS
Work Site Safety Plan Checklist
Bill C-45 Explanation
WH&S Bulletin Due Diligence
Section 2 - 15
OPERATOR:
LOCATION:
WELL SITE SUPERVISOR:
RIG# / RIG MANAGER:
DATES: From:
To:
The Operator is designated as the Prime Contractor for this operation. The Well Site Supervisor is
the agent of the Operator. The following checklist summarizes the key elements of the required work
site safety plan. Well Site Supervisors are requested to submit the completed checklist upon
completion of the job.
YES
NO
N/A
GENERAL
Have you reviewed and posted HARVARDs HS&E Policy & Safety Statement?
Have all identified landowner requirements been identified and addressed?
HAZARD IDENTIFICATION AND ASSESSMENTS / INSPECTIONS
Is a Hazard Assessment completed for each task being conducted?
Are the results of Hazard Assessments reviewed during the Safety Meeting Process?
Review Well Site Layout (as per provincial regulatory requirements).
Have the rig anchors been installed and tested as required?
Are CAODC rig inspections or equivalent being completed as required?
Have you received copies of all inspections completed on the worksite?
Has the CAODC BOP been completed as required?
Have the mouse/rat holes been identified prior to moving completion rig on site.
SAFETY COMMUNICATION
Are Safety Meetings held on regular basis?
Are the meetings documented and are you receiving copies of the meeting minutes?
As the Supervisor have you attended pre-job safety meetings for critical/non critical
operations?
Have you reviewed regulatory permits and license conditions?
Safe Work Permits: have you identified requirements and issued necessary permits?
Has a pre-job tailgate safety meeting been conducted prior to each specialized
operation?
INCIDENT REPORTING AND INVESTIGATION
Are Contractors and their personnel aware of the HARVARD incident reporting procedures,
and are they complying?
Are you ensuring all incidents/near misses are investigated reported and corrective
measures implemented?
EMERGENCY RESPONSE PLANNING
Has the Corporate/Site Specific ERP been reviewed with onsite personnel?
Have emergency numbers and directions to lease been posted and is a map of area
available for quick reference?
Are lease signs adequate to direct emergency response workers to the site?
YES
NO
N/A
Have muster points been identified and all personnel aware of them?
Are First Aid/Emergency Services available including a transportation method?
Are supplies well maintained and do they meet regulated standards?
Has the communication equipment on the worksite been tested for emergency response
procedures?
HAVE SAFE WORK PROCEDURES BEEN ESTABLISHED FOR THE FOLLOWING JOB
HAZARDS?
Sour operations.
Hot work.
Confined space / Restriced space entry.
Overhead power lines.
Hazardous materials.
Ground disturbances (buried pipelines, electrical, telephone)
Control Hazardous Energy
Pressure testing.
Radioactive sources.
Appropriate work procedures available on-site and posted as required.
Fall protection to include use of man basket & high angle rescue training.
Other non-regular operations. _____________________________
Well flow back operations including DST testing.
LEL Monitoring.
WORKER HEALTH AND SAFETY
Is appropriate personal protective equipment and other safety equipment available and
being used by all workers? (i.e. F. R. clothing).
Is the PPE and safety equipment in good working order and is there a preventative
maintenance and inspection program for equipment?
Is there special monitoring equipment available? (i.e. H2S, LEL).
Have you review local access hazards and speed limits?
TRAINING REQUIREMENTS
Have all workers on site completed an HARVARD Safety Orientation (Handbooks) and do
they have an orientation hardhat sticker?
Have you collected the orientation quizzes/acknowledgement sheets from the workers?
First Aid/CPR; verify number of qualified people available on site _______
H2S; verify number of qualified people on site ________.
Blow out prevention certification: Rig Manager ____ Drillers ____ Site Supervisor ____
WHMIS / TDG: Rig Manager ____ Drillers ____ Crew ____ Site Supervisor ____
CONTRACTOR SAFETY PROGRAMS
Do Contractors have safety programs in place and available on site?
ENVIRONMENTAL PROTECTION
Have fuels and chemicals are properly stored?
Is the required waste handling, storage and disposal procedures in place?
Have all spills been cleaned up immediately and reported?
CAMP (If Applicable)
Are there adequate smoke detectors and fire extinguishers?
Are regular emergency drills conducted, and do they correct deficiencies identified?
Have Camp Rules been posted at the main entrance and kitchen area of camp?
SUPERVISOR
DATE
On March 31, 2004, criminal code amendments made to bill C-45 became law. These
changes now base corporate criminal liability on the actions and moral fault of the
organization as a whole. This would include the failure of managerial officers who
reasonably ought to have known what was happening or who were not reasonably
diligent in establishing or monitoring mechanisms for compliance with corporate
policies.
An organization is defined as a public body, body corporate, society, company, firm,
partnership, trade union, municipality and associations, with a common purpose, with an
operational structure that holds itself out as an association.
The amendments to Bill C-45 have the following intent:
Criminal liability of corporations and organizations is no longer dependent on a senior
member of the organization but rather all PERSONS DIRECTING WORK must ensure
reasonable steps have been taken to safeguard BOTH WORKER and the PUBLIC.
The Criminal Code had the following provisions:
Criminal Negligence 219. (1) Everyone is criminally negligent who
(a) in doing anything, or
(b) in omitting to do anything that is his duty to do,
shows wanton or reckless disregard for the lives or safety
of other persons.
Definition of duty
(2) For the purposes of this section, duty means a duty
imposed by law.
Duty of persons
Section 217.1 creates an express legal duty for those directing minds who direct the
work or another. This responsibility expands to include all representatives of the
3.0
A Safety Program is ineffective unless there is a plan to manage it. The manual is full of
information to help manage the Program. Unless each element of the Program is put into
practice there is no Program and the manual becomes useless. Putting it into practice requires
the participation of all company employees and contractors. Safety is everyones responsibility.
This section of the manual attempts to provide a management plan that is easy to understand
and provides specific tools to assist the supervisor to manage the Program in the field.
3.1
The principle safety document for any drilling or completions operation should be the
Operations Program. The Program should be well thought out by the Drilling/Completions
Engineer and structured so that the project is accomplished in the most efficient and effective
way with safety of workers and environmental protection an unconditional priority.
It is important that the Wellsite Supervisor be clear in his/her understanding as to what his/her
responsibilities and expectations are as the representative of the owner/operator and/or Prime
Contractor. It is recommended that, in addition to a detailed operational procedure that
accomplishes the above, a section be added to each drilling and completions program similar
in content to the following:
Instructions to Well Site Supervisor Regarding Safety and Waste Management
All operations on this project must comply with HARVARDs Safety Program, the
drilling contractors' Safety Program and all applicable regulations.
The Well Site Supervisor is to complete the attached Work Site Safety Plan
Checklist at the beginning of this project and return it to the Calgary office with the
final operations report.
An Emergency Response Plan must be prepared based on the work site hazard
assessment with input from affected workers. Emergency response items must
address, at a minimum, key internal and external contacts, first aid plan / medical
transportation, fire protection, rescue and evacuation. Individual work sites may
need to add additional items specific to their operation based both on the work
site hazard assessment as well as regulatory requirements. Emergency response
training must be appropriate to the work site and potential emergencies identified
in the ERP. A copy of this ERP must be submitted with the final operations report.
Well Site Supervisor is to issue Safe Work Permits for all Hot Work, Confined
Space Entry and Ground Disturbances. Copies of these must be submitted with
the final report.
The CAODC rig inspection checklist must be completed and discussed with the
Drilling Engineer prior to drilling out surface casing. Further inspections are to be
completed as required.
Section 3 - 1
3.2
Have BOP stack and all associated equipment pressure tested individually and
recorded on a chart.
Attend and take a lead role at all safety meetings. Safety meetings should be held
regularly with each crew and before each critical operation.
In accordance with ERCB Directive D58 all waste must be manifested prior to
leaving the location. It is the Well Site Supervisors' responsibility to ensure this is
done.
All contractors must be fully covered by the WCB as well as carry a minimum
liability insurance of $2,000,000.
This Checklist has been designed to provide the Production/Wellsite Supervisor with a guide to
most of the safety issues that must be addressed on site. It is intended that the Checklist be
applied to each of HARVARDs operating areas. It is recommended that the
Production/Wellsite Supervisor for each area review the Checklist for his area(s) at regular
intervals and that they be reviewed at safety meetings.
3.3
This document is intended to be a statement to all workers at a work site from HARVARD
management. It is to be posted in a conspicuous location such as the field office, lunch areas,
etc.
Section 3 - 2
SECTION 3 FORMS
Safety Statement
Section 3 - 3
SAFETY STATEMENT
TO BE POSTED AT EVERY WORK SITE
Well/Facility Name: ________________________________________________________________
2.
3.
4.
Regular safety meetings and inspections must be carried out and properly
documented.
5.
Any accident, whether lost time or otherwise, unsafe acts or near misses must
be reported immediately by the work site supervisor to the above by telephone
and in writing by the next morning. The contractors written report, and if
required, copies of the applicable provincial W.C.B. forms MUST BE FAXED TO
THE CALGARY OFFICE AS SOON AS POSSIBLE.
Section 3 - 4
4.0
4.1
OVERVIEW
Occupational Health and Safety Codes require employers to assess a worksite and identify
existing or potential hazards before work begins or prior to the construction of a new work site,
or before the construction of significant additions or alterations to a work site. Employers must
prepare a report that provides the results of the assessment and specifies the methods that will
be used to control or eliminate the hazards.
All contractors are required to conduct their own pre-job safety hazard assessment. All
HARVARD personnel must conduct a pre-job assessment and complete the required Job
Safety Analysis (JSA) for the task at hand. HARVARDS HSE Department will review the prejob hazard assessments, update the JSA or develop new ones and review task analysis.
Hazards are to be eliminated whenever it is reasonably practicable to do so. If elimination is not
reasonably practicable, hazards must be controlled:
There may also be situations where emergency action is required to control or eliminate a
hazard that is dangerous to the safety or health of workers. Only those workers competent in
correcting the hazardous condition may be exposed to the hazard.
Recognizing potential hazards and taking steps to control them is a major part of HARVARDs
Safety Program. A hazard is any situation with the potential to do injury or damage to people,
property, or the environment.
The objectives of the hazard assessment guidelines are to:
Outline a strategy for identifying all potential process and work site hazards.
With the development of hazard assessment guidelines, and the implementation of training
programs, HARVARD is prepared to:
1. Identify, document, and assess any necessary process/operating safety information.
2. Identify, document, and report potential process and operative hazards and overall
risk.
3. Estimate the likelihood and consequence of each hazard utilizing the Risk Matrix.
Section 4 - 1
4.2
RESPONSIBILITY
Be able to show how information regarding hazards and their controls are communicated to
workers.
HARVARD must be able to show how workers were informed of findings and
recommendations, including when and by what means (ie: safety meetings, posted
checklists, etc.), and how workers can access the written assessment.
Ensure that any employer on a work site is made aware of any existing or potential work
site hazards that may affect that employers workers.
4.3
The size and scope of the written hazard assessment will vary based on the complexity of the
operations and the extent to which those operations present hazards to workers. A single
hazard assessment may be undertaken for multiple worksites IF the same hazards are faced at
all worksites and the safe work practices to be followed are identical at each worksite. Should
differences be discovered, then HARVARD must perform an individual assessment that takes
the new findings into consideration. Once new controls are implemented, the job or work
should be reviewed to ensure that the hazard(s) has been reduced to acceptable levels.
4.4
ASSESSMENT INTERVALS
The findings of the initial hazard assessment may not change for an extended period of time
but further assessments are required:
Section 4 - 2
When a new work process is introduced. This may involve the use of new or different
materials, chemicals, equipment, etc. with which workers are unfamiliar.
When a work process or operation changes. This may include the introduction of a new
process, operation, or piece of equipment.
If hazardous conditions are discovered every time an assessment or inspection is done, then
assessments or inspections should be done more frequently, thus reducing the length of time
that workers are exposed to a particular hazard. The presence of numerous, uncontrolled
hazards would suggest that the assessment was inadequate and efforts to eliminate or control
those hazards were incomplete or ineffective.
If no hazardous conditions are found, assessment intervals should not be reduced. If
everything is being done correctly and hazards are not being missed, then the inspections are
doing what they are supposed to do keeping conditions safe and under control.
4.5
In its simplest form, a hazard assessment answers the question What if?.
For example, What if
Section 4 - 3
Step 2
Determine the hazards associated with the listed work-related activities.
Hazards are often grouped into four categories:
Physical hazards, for example:
Working at heights
Pressurized systems
Vehicles
Fire
Electricity
Excess noise
Extreme temperatures
Chemical hazards, for example:
Viruses, bacteria
Moulds
Sewage
Psychological hazards, for example:
Stress
Fatigue
Working conditions
Workplace violence
Step 3
Based on these activities and hazards present, create checklists or similar tools to help
identify existing or potential hazards (refer to Hazard Assessment Tools and Checklists,
Section 4.8).
Step 4
Identify and prioritize (ie: high hazard jobs, tasks, work areas) in order to determine
which hazards need to be assessed first.
4.6
TYPES OF INSPECTIONS
Formal and informal work site inspections are a critical process in recognizing potential hazards
and in taking the necessary steps to control them. Inspections require the full participation
of all workers, supervisors and management, who must take responsibility for identifying
and controlling the hazards within their work area.
Any unsafe or harmful conditions found in the course of such inspections shall be
documented, remedied and communicated to workers without delay.
Section 4 - 4
4.6.1
4.6.2
4.6.3
4.6.4
Section 4 - 5
4.6.5
Ongoing (informal)
Planned (formal)
Safety & Loss Control Audit
Physical Conditions Survey
Loss Prevention Surveys Inspections
Process Hazard Analysis (PHAs)
(see Table 1, Summary of Inspections)
*Harvard recognizes
that for the majority of
field worksites, the
hazards identified are
addressed immediately
and would not require a
risk ranking procedure.
Section 4 - 6
4.7
RISK MATRIX
High: Requires Action
LIKELIHOOD
SEVERITY
MAJOR (Catastrophic)
Personnel:
SERIOUS
Lost time injury with
partial or no disability
Public:
Exposed to potential
injury accident
Environment: Large uncontained
product/chemical release
Equipment:
Damage which results in
downtime of 1-10 days
FREQUENT
PROBABLE
OCCASIONAL
Expected to occur
routinely or repeatedly
over the life of the
facility. Weekly or
monthly: probability
0.1
Commonly known to
occur but not routine.
Likely to happen at
several times in the
life of the facility.
Yearly or longer:
probability 0.01
EXTREME RISK
STOP:
Evaluate
thoroughly. Take
steps to reduce
risks before
restarting
2
Personnel:
MINOR
(Important / Noticeable)
Evaluate. Take
appropriate steps to
reduce risks.
MINIMAL RISK
Evaluate. Consider
alternatives for
reducing risks.
LOW RISK
MINIMAL RISK
NO RISK
Evaluate thoroughly.
Take all necessary
steps to reduce risks.
Evaluate. Take
appropriate steps to
reduce risks.
Evaluate. Consider
alternatives for reducing
risks.
Review and
evaluate need for
reducing potential
risks.
No review required
MEDIUM RISK
LOW RISK
MINIMAL RISK
Evaluate. Take
appropriate steps to
reduce risks.
Evaluate. Consider
alternatives for
reducing risks.
Personnel:
Injury requiring minimal or no first aid
Public:
No impact
Environment: Product/chemical release
contained in process
Equipment:
Negligible downtime of
less than 6 hours
NEGLIGIBLE
RISK
NO RISK
No review required
Review to confirm
potential risks.
7
LOW RISK
MINIMAL RISK
NEGLIGIBLE RISK
NO RISK
NO RISK
Evaluate. Consider
alternatives for
reducing risks.
Review to confirm
potential risks.
No review required
No review required
NEGLIGIBLE
RISK
NEGLIGIBLE
RISK
Review to confirm
potential risks
Review to confirm
potential risks
Evaluate thoroughly.
Take all necessary
steps to reduce risks.
LOW RISK
MEDIUM RISK
NONE
MEDIUM RISK
Has happened
somewhere and
could conceivably
occur at this facility
but is very unlikely.
Probability
0.000001 to 0.001
4
IMPROBABLE
So unlikely, assumed
impossible that this will
ever happen at this
facility. Probability
0.000001
HIGH RISK
Personnel:
NEGLIGIBLE
HIGH RISK
REMOTE
(Unlikely)
NO RISK
NO RISK
NO RISK
No review required
No review required
No review required
Section 4 - 7
4.8
Checklists or worksheets are a popular means of conducting an assessment and they serve as
a survey tool, directing the person or team performing the assessment to look at the specific
hazards.
For each hazard identified, recommendations to eliminate or control it must be addressed. This
process should include specific actions required to correct the problem, determine who is
responsible for performing the corrective action, and when each corrective action is to be
completed.
One approach for hazard identification is a checklist as follows:
Hazard
Potential Harm
Noise from
(indicate
equipment)
Hearing loss
assessed at more
than 85 dBA
Moving parts of
(indicate
equipment)
Chemical
(indicate
chemical)
Action Proposed /
Control
No alternative machinery.
Machine already enclosed.
Workers to wear hearing
protection.
Place guards over moving
parts.
Completion
Date
Not
applicable
No adequate alternative
chemical.
Enclose process.
Personal protective
equipment FR clothing,
gloves, safety glasses.
Review MSDS.
Within 1
week
Within 2
days
By who?
Frequency of
Follow-up
Annual noise
survey
Check
compliance
monthly
Check
compliance
monthly
Section 4 - 8
Visual
Monthly
Cranes
Visual
Fire Extinguishers
Visual
Yearly
Cylinders for air
quality
As per
manufacturers
specifications
As per NFPA 10
Portable Fire
Extinguisher
Other
Metal composite
cylinders hydrostatic
every 3 years
Fibre-wrapped
cylinders hydrostatic
every 5 years
Gas Detectors
Hard Hats
Visual
Visual
Oxygen Analyzers
Pressure Vessels
Stored pressure
hydrostatic every 5
years
Cartridge operated
hydrostatic every 12
years
As per manufacturers
specifications
Every 3 year
replacement
As per manufacturers
specifications
Per government
regulations
Per manufacturers
specifications
Before using
Per government
regulations
Per manufacturers
specifications
Section 4 - 9
The following lists are intended as a guideline for controlling identified hazards when
conducting detailed site inspections. Additional controls and inspections may be required
dependent upon the activities and identified hazards at the work site.
4.8.20
4.8.2
4.8.21
Noise Exposure
4.8.3
4.8.22
4.8.4
Confined/Restricted Space
Entry
Electrical Power Systems
4.8.23
Platforms/Scaffolding
4.8.5
Emergency Instructions
4.8.24
4.8.6
4.8.25
4.8.7
Emergency Rescue
Equipment
Energy Isolation
4.8.26
4.8.8
Ergonomic Factors
4.8.27
4.8.9
Exit/Egress
4.8.28
Stairs
4.8.10
4.8.29
Substance Abuse
4.8.11
Fatigue
4.8.30
Trenching/Excavating
4.8.12
Fire Protection
4.8.31
4.8.13
4.8.32
4.8.14
First Aid
Kits/Stations/Equipment
Hand and Portable Tools
4.8.33
4.8.15
4.8.34
4.8.16
Ladders
4.8.35
Warning Systems
4.8.17
Lifting/Gear Equipment
4.8.36
Waste Disposal
4.8.18
Lighting
4.8.37
WHMIS/TDG
4.8.19
Material Handling
4.8.38
4.8.1
4.8.2
4.8.3
Spaces that are restricted and which may become hazardous when a
worker enters it due to the hazards identified.
Spaces that are partially enclosed and have a restricted access/egress.
Procedures for entry are available.
Equipment is available.
Workers are trained in procedures, testing, breathing apparatus and
rescue.
Toxic vapours, materials, and harmful atmospheric contaminants are
identified.
Oxygen deficiencies/enrichment is rectified/noted.
4.8.4
4.8.5
Emergency Instructions
4.8.6
Exit/Egress
Positive energy isolators are provided for all power systems and
individually powered equipment.
Scissor lock-outs permit group lock-out by multiple personnel.
Tags or colour codes indicate user of lock-out.
Energy isolation provides means to reduce system/equipment to a zero
energy state; for example steam, air, electrical, hydraulic.
Ergonomic Factors
4.8.9
Energy Isolation
4.8.8
4.8.7
4.8.11 Fatigue
Section 4 - 13
4.8.16 Ladders
Section 4 - 14
4.8.18 Lighting
Approved respirators, suitable for hazards, are available and a copy of the
Code of Practice is available.
Hearing protection is available where required.
Working platforms are at least 0.5 m wide (light duty) or l m wide (heavy
duty). REMOVE 1 m wide repealed
Ladderjacks, pump jacks or similar systems may have a 0.3 m wide
platform.
Open spaces between the platform and structure must not be greater than
0.25 m in width.
Adequate footing for workers in place.
Continuous platform around obstructions.
Maximum working load is identified.
Toe boards are provided along all sides were prescribed.
Proper non-skid flooring.
Mesh screen below floor if open construction.
Safe access to movable platforms.
Access gates are self-closing and locking.
Equipped with standard guard rail or other fall protection if higher than 1.2
m (permanent) or 3.5 m (temporary).
Sound, rigid footing for scaffolds.
No excess accumulation of tools or materials.
No altering or moving of scaffolds in use.
Condition of casters is acceptable.
Condition of jacks and leveling screws is acceptable.
Hazard warning, directional and informational signs and tags are posted
where there are immediate dangers, potential hazards, or where there is a
need for general instructions.
Signs and tags are used consistently throughout the facility.
Tags are affixed to all defective equipment not secured against use.
WHMIS labels are available.
TDG labels are available.
4.8.28 Stairs
Properly identified.
Operational.
Readily accessible.
Measures are in place to prevent inadvertent operation.
Conduct risk assessment to determine risk of injury to workers from violence arising
from employment.
Establish procedures/policies and work arrangements to eliminate or minimize the
risk.
Train company and contractor personnel in identifying and addressing
violence/harassment in the workplace.
Establish procedures for reporting, investigating and documenting incidents of
violence and harassment.
Respond to incidents of violence/harassment (i.e. incident investigation, taking
corrective actions, assisting in referrals to physician for treatment.
Section 4 - 20
4.9
Section 4 - 21
Section 4 - 22
Section 4 - 23
SECTION 4 FORMS
Well Safety Checklist and Hazard Id
Vehicle Safety Inspection Checklist
Hazard Identification & Control Form
Service Rig Inspection Checklist
Drilling Rig Inspection Checklist
Section 4 - 24
Date Inspected:
Location:
Completed by:
1 = Acceptable
Item
SITE
Proper signage
Housekeeping. general appearance
Snow removal - sufficient or piled By
doors or on pipes.
Driving Hazards flagged
(risers, lines, etc)
Bull plugs in place
Fire extinguisher access and
inspection dates
Piping secured
Slipping and tripping hazards
Location access, road
Flammable liquid storage (safe
distance from heaters)
Proper storage of chemicals
Adequate WHIMIS labeling
Date PSVs serviced
Vegetation Control
Steps and handrails
Vibration
Shutdowns not bypassed
Safety equipment:
X = Unacceptable
SCBA
Burn Blankets
Date
Completed
Frequency of
Follow-up
Vehicle No.__________________________
Items to be checked
Date: ______________________
Comments/Deficiencies
_______________________________________
Emergency Brake
_______________________________________
_______________________________________
Windshield Wipers
_______________________________________
Turn Signals
_______________________________________
Horn
_______________________________________
Back up lights
_______________________________________
_______________________________________
Tread
Inflation
Spare
Brake Lights
_______________________________________
Hazard Lights
_______________________________________
Seat Belts
_______________________________________
_______________________________________
Tow Rope
______________________________________
Flares/Reflectors
______________________________________
Fire Extinguisher
______________________________________
Location:
Date:
Task:
Flammable Gas
Flammable Liquids
Pressure
H2S
Iron Sulphides
NORM/Asbestos
Chemicals
Noxious Vapours (Benzene)
Rotating Equipment
Hot/Cold Piping Equipment
Muster Area
Air Monitoring
Isolation (Blinding/Blocking)
Forced Ventilation
SCBA/SABA
Safety Inspections (CAODC, walkabouts etc.)
Hearing Protection
Guards/Shields
Respirator
Wash Facilities
Audits/HSE Contract Inspections
CONTROLS
Printed Name
(mo)
(day)
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
__________________ lbs.
Yes ______
No ______
__________________ lbs.
Yes ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Good ______
Good ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
Hazard ______
Hazard ______
Good ______
Good ______
Yes ______
Yes ______
Good ______
Hazard ______
Hazard ______
No ______
No ______
Hazard ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
POWER TONGS
46 Back-up in place and functional
47 Torque arms safety line, clamps in good
condition
48 Tong positioner - operational and in good
condition
49 Hoses, gauges and hydraulic fittings in good
condition
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Good ______
Yes ______
Hazard ______
No ______
Yes ______
Yes ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
No ______
No ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
MAST
27 Stand pipe properly anchored to mast
28 Kelly hose in good condition
29 Kelly hose safety lines or chain attached to derrick
and swivel ends while in use
30 Levels I, II, III or IV inspections completed as
required in CAODC RP 3.0
31 Ladders in good condition
32 Rod basket in good condition
N/A _______
33 Crown sheaves greased and in good condition
34 Safety cables attached to fingers on tubing board
35 Derrick locking pins in place
36 Derrick hydraulic system in good condition
37 Mast lighting secured adequately
38 Dead lines anchor and retainer properly placed
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
___________________________________________________________________________
COMMENTS/EXPLANATION:
DRAWWORKS
22 Conditions of drill line (slipped regularly)
(a) Slip and cut record
23 Sufficient wraps (min.7) left on drum with blocks
down
24 Braking system - Linkage/pin satisfactory
- Block wear
25 Condition of sandline & rope socket to sinker bars
26 Handling winch/line
Condition at:
- Winch anchor points
- Winch line
- Winch line thimble
- Tall chain
- Safety hook
- Hydraulic hoses & connections
- upper shivs & assembly
TRAVELING ASSEMBLY
39 Levels I, II, III or IV inspections completed as
required in CAODC RP 4.0
40 Blocks - nuts, safety pins in place and in
good condition
- Sheave guards/lock in good condition
41 Balls/links
- good condition
42 Elevators
- good condition
43 Rod hook
- good condition
44 Transfer elevators - good condition
45 Safety latch/ring in place
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
ELECTRICAL/LIGHTING
50 Light bulbs enclosed with vapour-proof and
shatter-proof covers
51 Covers on unused receptacles
52 Light switches vapour-proof
53 Electric motors within 8.5 metres radius must
be explosion-proof
54 Equipment properly grounded
55 All cords and plug ends in good condition
56 Proper clearance from power lines
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
RIG PUMP AND TANK
57 Condition of pipe and unions
58 Pump and return lines laid out and secured
59 Kill line attached to well with valve open
(steel lines only)
60 Pressure relief valve (proper size and rating)
61 Relief valve set at or below system working
pressure NOTE: Only shear pins appropriate
to the pop valve requirements as specified by
the manufacturer shall be used
62 Relief valve discharge points down and away
from pump motor and is securely fastened
NOTE: No valve on relief line
63 Manifold conditions
64 Check valve in place on pump discharge
65 Exhaust away from rig tank
66 Emergency shutoff checked and operational
67 Pump controls properly marked
68 All railings in place on walkways/stairs of rig
pumps and tank
Good ______
Yes ______
Hazard ______
No ______
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
Yes ______
No ______
Good ______
Yes ______
Yes ______
Yes ______
Yes ______
Hazard ______
No ______
No ______
No ______
No ______
Yes ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
DOCUMENTATION
69 Necessary transportation documentation and
equipment present (i.e. registration, insurance)
70 Required inspection certificates available
71 Derrick log book available and updated
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
F
COMMENTS/EXPLANATION:
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
BLOWOUT PREVENTER SYSTEM
72 BOP function tested - From remote controls
Yes ______
No ______
- From accumulator controls
Yes ______
No ______
73 All studs used on BOP stack
Yes ______
No ______
74 Hydraulic preventers installed
Yes ______
No ______
- Pipe rams
Yes ______
No ______
- Blind rams
Yes ______
No ______
- Annular preventer
Yes ______
No ______
75 Condition of ram rubbers and elements
Good ______
Hazard ______
76 Fire-shielded hoses and their condition within 7 metres
of wellhead
Good ______
Hazard ______
77 Remote stand 7 metres from well - Class I & II
- Refer to BOP regulations
Yes ______
No ______
- Or at remote accumulator - Class III
Yes ______
No ______
78 Nitrogen back-up supply pressure
__________________kPa
- Min. 12,500 kPa if annular preventer is installed
- Min. 7,000 kPa when only rams are installed
79 Pre-charge check date
____/____/____
Good ______
Hazard ______
80 BOP's adequately heated
Yes ______
No ______
81 Lines protected in vehicle crossing area when
remote accumulator is used
Yes ______
No ______
82 Safety valve fully opened with proper thread
connection on rig floor c/w closing wrench
Yes ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
ENVIRONMENTAL
83 All equipment free of leakage
- If no, adequately contained
84 Rig site free of material that may create a fire
hazard NOTE: Equipment spacing must ensure
unimpeded access to well at all times
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
COMMENTS/EXPLANATION:
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Good ______
Hazard ______
Yes ______
No ______
Yes ______
No ______
____/____/____
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Yes ______
No ______
Good ______
Hazard ______
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
BOILER
85 Chemical storage
86 Blowdown line labeled
87 Pop valve line labeled
88 Controls
- Labeled
- Condition
___________________________________________________________________________
Good ______
Yes ______
Yes ______
Yes ______
Good ______
Hazard ______
No ______
No ______
No ______
Hazard ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Operator: _________________________
Derrickman: _______________________
Floorhand: ________________________
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Floorhand: ________________________
Other: ____________________________
Other: ____________________________
Other: ____________________________
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
50 m
25 m
(A)
(I)
A. FUEL/WATER TANKS
(A)
01. No leaks
02. Pumps guarded
03. Signs at water/fuel tanks:
a) No smoking sign posted
b) Fuel sign posted
c) Dangerous Goods placard posted
B. BOILER HOUSE
04.
05.
06.
07.
08.
09.
10.
11.
12.
13.
No clothing etc.
Sight glass guarded
Pump guarded
Fire extinguisher
Safety valves: one year certificate
Boiler 25 m from wellheads
Housekeeping
Flammables removed from around boiler
Boiler License posted
Blow down line location & installation
of steam deflector
14. Fuel/water and steamline leaks
15. Chemical addition vessel (pot) at boiler
properly labeled (WHMIS)
C. GENERATOR BUILDING
16. Generator/motor control centre size; condition
17. Receptacles/circuit breakers identified
18. Properly grounded (2 grd rods 3 m apart)
19. Wiring off the ground & properly secured
20. No clothing/storage
21. Fans and belts guarded
22. No fuel/oil leaks
23. Compressor belts guarded
24. Fire extinguisher
25. All lights protected
26. Housekeeping
27. Rubber mat on floor at Motor Control Centre
28. Battery condition
29. Signs at Generator Building
a) Auto Start sings posted
b) Hearing Protection sign posted
c) Electrical/High Voltage signs posted
d) Water Hose Caution sign posted
e) Lockout and Procedures
30. Wiring/electrical fixtures condition
31. Current turned off prior to
connecting/disconnecting extension cords
65.
66.
67.
68.
69.
C. SUBSTRUCTURE
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
43.
No leaks/spillage
N2 bottles (12500 kPa/1800 psi)
Housekeeping
Storage of compressed gas cylinders,
secured
Controls identified/accessible
Safety device blind/sheer ram controls
Fire extinguisher
Grinder tool rest
Eye protection available
Compressor guarded
Signs at Accumulator and Tool House
a) Eye Protection signs posted
b) Auto Start signs: compressor / accum pump
c) Dangerous Goods placard/WHIMS label
Accumulator reservoir vented outside of
building/enclosure
General condition
Matting condition
Drive pins installed c/w safety pins
Spreaders in place
Vent doors/fan
Illumination
Winterization condition
Hydraulic control lines condition
fire guarded hose
Flow nipple split
Stripper/mud catcher split
Scaffolding/ladder(s) condition
Cellar area cribbed and drained
Wiring/electrical fixture condition
Housekeeping (oil leaks, etc.)
H. BOPS
84. BOP and rig equipment conform to
Government regulations
85. BOP secured properly
86. Non-steel hydraulic lines fire sheathed
87. Mud gas separator adequately connected
meets minimum requirements, including
line size and tie down
88. Required casing wear tests being preformed
89. BOP pressure tests recorded and test
procedures satisfactory
90. Adequate heating
91. Manual ram locking wheels available
I. DOGHOUSE
44.
45.
46.
47.
48.
49.
92.
93.
94.
95.
96.
97.
98.
99.
Page 1 of 3
(I)
(A)
(I)
100.
101.
102.
103.
104.
105.
106.
107.
(A)
165.
166.
167.
168.
K. RIG FLOOR
123.
124.
125.
126.
127.
128.
129.
130.
131.
132.
133.
134.
135.
136.
137.
138.
139.
140.
141.
142.
143.
144.
145.
146.
147.
148.
149.
150.
151.
152.
153.
Lockout on drawworks
Compound/drawworks guard
Crown saver (check)
Catline
Catline divider and spool
Spinning chain/wrench line
Headache post
Kelly cock condition
Kelly hose condition
Kelly hose safety line both ends
Line spooler/safety line
Backup post condition
Tongs condition
Tong line and tong line clamps
Slips condition
Dog collar condition
Stabbing valve and handle and X/O subs
Test plugs
Mud can condition
Drilling controls and identification
Brake handle hold-down cable/chain
Non-skid material around rotary
Lighting operational, floor and motor area
Motors:
a) Fans and belts guarded
b) No fuel/oil leaks
c) Motor shutoff
d) Fire extinguisher (No. ______)
e) Exhaust system
Stairs (min. 3 exits) from rig floor
Warning horn working
Hydromatic and guards
Brakes satisfactory
Tugger line condition, guards
V-door opening safety chained
Wiring/electrical fixture condition
O. MANIFOLD HOUSE
193. Heated
194. Valve handles installed
195. Proper gauges installed and positioned
196. Drill pipe pressure gauge installed
197. Unobstructed view to rig floor
198. Housekeeping
199. Manifold design meets Government requirements
200. Flare lines properly secured
201. Lighting operational
202. Choke/valve open to degasser
203. Well to:
- End of flare line 50 m
- Rubbish burn pile 50 m
- Crude oil storage tank 50 m
204. Signs at Manifold House:
a) Hold Back Pressure notice posted
b) No Smoking sign posted
205. Choke and degasser lines and manifold prepared
P. LEASE AREA
206.
207.
208.
209.
210.
211.
212.
213.
214.
Blocks
Bails/links
Elevators/latches
Weight indicator assembly
Weight indicator safety line
Automatic driller
Drilling line condition (slip/cut program)
Deadline anchor condition
Q. CAMP/GENERAL FACILITIES
215. Propane tanks location (No._______)
Propane distance from camp (min. 4 m)
216. Garbage disposal: incinerator - bins
217. Walkways
218. Kitchen First Aid kit
219. Kitchen fire extinguisher
220. Fire extinguisher (No._______)
Page 2 of 3
(I)
(A)
(I)
(A)
(I)
T. SAFETY/GENERAL
221. Generator Building:
a) Grounded
b) No clothing, storage
c) No fuel/oil leaks
d) Fire extinguisher
222. Furnace rooms
223. No unnecessary storage
224. Fire alarm system
225. Bedrooms exit to outside (shutters open)
226. Adequate distance from well centre
227. Housekeeping
228. Signs at Camp area:
a) Hearing Protection sign posted
229. Exit signs over doors installed and
illuminated
230. Emergency lighting installed and functional
231. Wiring/electrical fixtures condition
265.
266.
267.
268.
269.
270.
271.
272.
273.
274.
W. SPILL RESPONSE
S. TICKETS/DOCUMENTS (where not applicable)
284.
285.
286.
287.
Employees trained
Sorbents available
Spill response report form available
Emergency response procedure
X. WASTE MANAGEMENT
288.
289.
290.
291.
292.
Z. COMMENTS/EXPLANATIONS
5.0
COMMUNICATION
5.1
MEETINGS
Safety meetings provide the opportunity for the sharing of information among all
stakeholders. These meetings should include project kick-off safety meetings, tailgate safety
meetings, and/or regular scheduled monthly meetings. The frequency and type of meeting may
vary but the Occupational Health and Safety legislation states that employers hold regular
meetings at least once each month for the review of:
i)
ii)
iii)
Reports of current accidents, near misses and hazards, identifying root causes and
means of prevention.
Remedial actions taken or required by reports of assessments/inspections and
providing investigations.
Any other matters pertinent to health and safety.
5.1.1
Safety
Quality
Communication
Cost Control
Team relations
Environmental Awareness
To Reduce:
Misunderstandings
Resistance to change
Environmental damage
Get it going: start on time, thank attendees, introduce the subject, lay the groundwork
Maintain momentum: promote participation, apply the art of asking questions, deal with sticky
situations or problem participants, use repetition, memory and audiovisual aids
Bring it to a stop: summarize, highlight action steps, thank participants, end on time
After:
Follow-up
Safety grams
Hazard Assessment / Identification /
Controls
Incident / Accident / Spill Statistics
Emergency Preparedness
WHS/OH&S / WCB bulletins
Key policies and procedures
Section 5 - 2
Section 5 - 3
1. HARVARD expectations of contractors and orientation (see also handbook orientation quiz
in Section 9.0).
2. Authority of Company Representatives to shutdown contractor work.
3. Right and responsibility of any worker to refuse unsafe work.
4. Scope of work and work area layout
Trespassing Implications
5. Schedules
Project Schedule
Hours of Work
Schedule Delays
H2S
Overhead powerlines
Equipment/material lifts
Hot work
Combustible atmospheres
Housekeeping
Working at heights
Section 5 - 4
WHMIS / TDG
Housekeeping
Fracing
Acidizing
Coiled tubing
Pressure Testing
In-the-Derrick Work
Contractor Plan
Site-specific details such as emergency alarm system, safe areas, medical aid
procedures (first aid transportation plan), name and location of first aider, first
responder locations and contacts (ie: doctor, ambulance, hospital, fire
department, police)
Section 5 - 5
5.2
HARVARD has a work permit system which specifies the safety precautions to be taken
when certain types of potentially hazardous work is being undertaken. Before any work
begins the need for a JSA or work permit must be established.
Overall work permit requirements are as follows:
1.
All Calgary staff initiating and/or supervising in the field are required to obtain a
work permit or a work clearance. No work will commence without a work permit or
clearance in place unless otherwise authorized by the foreman responsible for the
area.
2.
3.
The existing work permit form will be used for both work permits and work
clearance. If being used as a work clearance, the permit should identify the length
of time the clearance is valid for.
4.
5.
Any HARVARD employee has the authority to suspend work until an approved
work permit or clearance is in place. Any non-compliance problems will be referred
to the employees/consultants manager for appropriate disciplinary action.
Each area is responsible for developing site-specific guidelines for when work permits should
be used.
All work permits must be checked off as being one of the following designations:
WORK CLEARANCE:
This is a special work permit that is issued when the complete control of a site is
turned over to another person. The person accepting the work clearance is
responsible for ensuring continued site safety and for issuing any other safe work
permits that may be required. This type of permit is good for the duration of the
tasks to be carried out.
NOTE: This is the type of permit that is given by the Production staff when they are
turning a lease over to the well site supervisors of the Drilling and Completions
department.
Section 5 - 6
WORK PERMIT:
Hot Work This is issued whenever work is carried out that may introduce an
ignition source in areas where combustible materials may or do exist. This includes
such things as cutting, welding, burning, air gouging, riveting, drilling, grinding,
chipping or using non-classified electrical equipment.
Cold Work This is issued for work where no danger exists from ignition but where
other potential hazards exist. This includes such things as toxic fumes, dust,
vapours, chemicals, steam or pressure.
BLANKET WORK PERMIT:
This type of permit may be issued for an extended period of time (one year
maximum). It is intended to be used for tasks that are carried out on an ongoing
basis and where procedural guidelines have been established and agreed to by the
contractor. An example of where this type of permit is used is for the hauling of
fluids in a production area.
NOTE: This type of permit would not be used in a drilling/completion operation.
WORK ORDER:
This permit is used by operating staff to communicate with maintenance staff
regarding maintenance work needing to be done. In this case the operator will be
his name on the Requested by: line and given an explanation of the work needing
to be done in the Description of Work to be Done section.
NOTE: This type of permit would not be used in a drilling/completion operation.
5.2.1
Section 5 - 7
For each confined space entry requirement, the following steps must be
taken in accordance with HARVARDs Confined Space Entry Code of
Practice. Primary steps include:
Section 5 - 8
Fracing
Drill Stem Testing, Swab Testing, Flow Testing
Acidizing
Coiled tubing
Pressure Testing
Energy-isolating devices activated (electrical
equipment)
In-the-Derrick Work
Use of the Man Basket
Other non-regular operations
or
auto-start
Work permits are not normally required for these operations. The Well Site
Supervisor may elect to use the work permit to improve communications
or to facilitate a pre-job safety meeting. The Well Operations Pre-Job
Safety Meeting checklist found in this section of the manual can also be
used for identifying and documenting the issues to be discussed.
Section 5 - 9
5.2.2
Turnaround
Scheduled shutdown
YES
Reschedule Work!
Review work permit
requirement at
suitable time.
NO
STOP
Consider:
Section 5 - 10
5.2.3
DEFINITIONS
Please Read Prior to Issuing Access/Work Permit
COLD WORK:
HOT WORK:
CONFINED
SPACE:
WORK
CLEARANCE:
TESTS:
FLAMMABLE
ATMOSPHERE:
Section 5 - 11
TOXIC
ATMOSPHERE:
OXYGEN
DEFICIENT
ATMOSPHERE:
OXYGEN
EXCESSIVE
ATMOSPHERE:
ENERGY
ISOLATION:
ENERGY
ISOLATION
DEVICE:
COMMUNICATION
AND ALERT:
Where the atmosphere contains a harmful substance or
a deficiency of oxygen, a worker must be attended by,
and be in communication with another worker stationed
at or near the entrance. Medical support must be
contacted at the time of an alarm.
NOTE: If any of the above gas levels are subject to change during the
operation due to the agitation of sludge, temperature change, welding or
cutting, use of solvents, purging with inert gases or deviation from
procedures previously set, they may be required to be monitored on a
continuous basis. Procedures to be followed may change accordingly.
Given this situation, a new permit may be required.
Section 5 - 12
SECTION 5 FORMS
Drilling and Completions HSE Meeting Report
Monthly HSE Meeting Report
Work Permit
Section 5 - 13
Start Time:
Adjournment Time:
Chair Person:
Meeting Agenda:
Date:
Action #
Mo/Yr
Action By
Closure
Date
Action #
Mo/Yr
Action By
Closure
Date
New Business:
Action #
Mo/Yr
Action By
Closure
Date
Handouts Circulated:
Page 1 of 2
Action #
Mo/Yr
Action By
Closure
Date
Action #
Mo/Yr
Action By
Closure
Date
Hazard Alerts:
Action #
Mo/Yr
Action By
Closure
Date
Date:
Start Time:
Chair Person:
Attendee Sign In:
Topic:
Page 2 of 2
WORK
Permit
Hot
Clearance
Order
Supervision
Cold
Location:
Contractor:
Description of Work to be Done / Comments:
PERMIT No:
Issued by:
Issued by:
Phone No:
Phone No:
PROCEDURES
1
2
3
4
5
6
7
8
9
31
32
33
34
35
36
37
38
39
40
41
10
11
12
13
14
15
16
17
HAZARDS
Combustible Material Removed
Drains Covered/Sumps Covered and Sealed
No Vessels/Pumps to be Vented/Depressured
Overheard Lines, Clearance Established
Underground Line, Located & Identified
Other Hazardous Material
High Voltage
Intrinsically Safe Equipment
18
19
20
21
22
23
EMERGENCY PLANNING
Safe Egress from Work Areas Identified
Fire Extinguisher Ready to Use
Note: Completed checkbox , should be completed by permit receiver after
Steam/Water hose Ready to Use
all requirements have been met.
Emergency Air horn
ERP Manual Discussed
Atmosphere Testing (Explosive, Toxic & Oxygen Deficiency ) Record Below
RETESTS
Hours
N/A
RETESTS
Hours
N/A
N/A
RETESTS
Hours
N/A
FIRST TEST
Hours
AREA FREE OF
(appropriate box)
N
O
T
E
24
25
26
27
28
29
30
% LEL
ppmH2S
ppmH2S
% LEL
ppmH2S
ppmH2S
% LEL
ppmH2S
ppmH2S
% LEL
ppmH2S
ppmH2S
% O2
% O2
% O2
% O2
This permit is valid only as long as work conditions existing at the time of its issuance continue and expires upon occurrence of any hazard such as gas leak, liquid spill, drastic operating change in equipment, or change in
wind direction blowing vapours into the work area. Any worker will have the right to stop the job if he has reasonable grounds to believe that the job is, or likely to become unsafe. Work shall not resume until a new permit is
issued.
Time:
Expiry Date:
Time:
Approval by:
Accepted By:
Supervisor
Contractor Representative/Worker
completed or
cannot be continued until the issuance of a new work permit.
Signed:
Supervisor
Contractor Representative/Worker
OVERVIEW
6.2
INCIDENT REPORTING
Every employee and contractor must immediately report all incidents, no matter how small, to
HARVARD Supervisor. Supervisors must report accidents and close calls to their manager
immediately to ensure the root cause of the incident has been identified and the follow up
process is in place. Supervisors must also assist in the investigation all incidents, at least to the
extent that the risk potential is determined, and then submit reports as required (i.e. ERCB,
OGC, OH&S).
All injury accidents must be classified as either first aid, medical aid, modified work, or lost time.
Any non-compliance is to be reported immediately to the regulator and an incident report
completed and submitted to HARVARD supervisor. This means at the first available
opportunity without jeopardizing the safety of personnel responding to an incident, not when it
is convenient and the emergency is over. You should be aware that failure to report an incident
is often seen to be more serious than the incident itself and can result in administrative penalty
or other enforcement action by the regulator.
All non-compliance events will be reviewed to determine what factors led to the noncompliance and actions items identified to ensure the non-compliance will not reoccur.
Additionally, all regulatory audits and inspections are to be reported as soon as results are
made available to company staff or representatives.
6.3
The first line supervisor may initially being investigating all incidents and making
recommendations to prevent occurrences. The HARVARD HSE person is responsible for
completing and signing off on all incident investigations. Assistance of a safety professional in
carry out the investigation may be required if the incident is, or has the potential of being, a
major loss.
6.4
Incident statistics are maintained and reviewed on a regular basis to determine the
effectiveness of the safety program. These reports are also used to help determine the types of
accidents occurring, common causal factors, where they are occurring, high risk tasks, program
needs, accomplishments and trends. The statistics are reviewed by HARVARDs management.
Section 6 - 1
6.5
LEVEL 1
Did the incident involve?
YES
Minor Incident
NO
NO
YES
LEVEL 2
Did the incident involve?
YES
Serious Incident
NO
LEVEL 3
Did the incident involve?
A fatality
A permanent disabling injury
Equipment damage in excess of
$250,000
Exposure of public to injury
YES
NO
YES
Major Incident
Section 6 - 2
6.6
COLLECT EVIDENCE:
- Photograph
- Sketch and map
- Test materials
- Reconstruct accident
- Examine response and loss
limitation actions
FOLLOW-UP:
- Ensure action items
identified have been
completed and are
working effectively
- Advise regulator of
steps taken to correct
non-compliance.
- A written report to
the regulator may be
required and is to be
submitted by the
manager.
Section 6 - 3
6.7
Section 6 - 4
WHERE?
Where did the accident occur?
Where was the employee at the time?
Where was the supervisor at the time?
Where were co-workers working at the time?
Where were other people who were involved at the time?
Where were witnesses when the accident occurred?
WHY?
HOW?
How was the employee injured? (Based on facts only)
How did the accident occur? ( Based on facts only)
Environment is checked if it is an oil, water, chemical spill, gas release or a TDG incident etc.
Safety is checked if it is an injury, vehicle accident, damaged property, etc.
SECTION 2
This section should be filled out by the person preparing the initial incident report form.
Close Call is checked if the incident did not result in an injury, environmental release,
damaged equipment or property leading to a loss of production, etc.
Injury is checked if the incident resulted in any type of injury no matter how small to
company or contract personnel working for or on one of HARVARDs locations.
Vehicle is checked if the incident involved a company vehicle even if there was no
noticeable damage to the vehicle. This is also checked if the incident involved a
contractors vehicle.
Release is checked if the incident involved a release of oil, water, produced water, gas
(sweet or sour) or chemical, etc.
Property Damage is checked if the incident involved damage to company equipment,
property or theft of equipment or property.
Section 6 - 5
SECTION 3
This section should be filled out by HARVARD Supervisor.
Interim Report is checked when the report is missing information such as final costs,
follow-up action to identified assignments, etc.
Final Report is checked when it is the final report completely filled out including final costs,
injury information, cleanup description and follow-up, etc.
Date of Occurrence is the date and time that the incident took place.
SECTION 6
This section should be filled out by the person preparing the initial incident report.
Date Reported is the date and time that the incident was first reported to the Calgary
Office.
SECTION 7
This section should be filled out by the person preparing the initial incident report.
Section 6 - 6
SECTION 8 - NOTIFICATIONS
This section should be filled out by the person who is doing the notifications.
Notifications include all government agencies or landowners that are notified. The
name of the person and time they were contacted should be recorded.
Following are the notification requirements for safety and environment incidents. (The following
is meant as a guide only. The appropriate regulation should be consulted for full details).
SAFETY INCIDENTS
AB WCB:
b.
c.
b.
Provide the worker with immediate transportation from the injury site
to a medical treatment facility. You must ensure that adequate
means of transport by land, water or air is available at all times.
c.
Pay the worker his regular salary for the day the injury occurred. If
disablement goes beyond the accident day, compensation
payments start the first regular working day afterward. Cheques are
issued every two weeks. If you continue to pay the worker his full
salary, you may arrange to receive compensation cheques on
assignment by notifying the WCB.
d.
a.
b.
c.
d.
AOH&S:
BC WCB:
a.
b.
c.
d.
e.
b.
c.
d.
The report must be on the form prescribed by the Board and must
state:
b.
b.
Provide the worker with transportation from the injury site to the
medical treatment facility. You must ensure that adequate means of
transport by land, water, or air is available at all times.
b.
c.
a.
b.
c.
d.
e.
a.
SASK OH & S
POLICE:
Any fatality
LANDOWNER/
OCCUPANT:
ENVIRONMENTAL INCIDENTS
LANDOWNER/
OCCUPANT:
GOVERNMENT
AGENCY:
Unit Number is the vehicle number if the incident involved a HARVARD vehicle.
Regulatory:
Section 6 - 10
Serious
Personnel:
Public:
Environment:
Equipment:
Regulatory:
Major
Personnel:
Public:
Environment:
Regulatory:
Probability of Occurrence
Seldom is checked when the likelihood to occur is sometime in the facilities life.
Not normally expected unless precautionary measures fail. Once every 10
years.
Copy of Applicable WCB Form Attached is checked when there was a reportable
injury. An injury that involved medical aid, modified work, lost time or fatality is
responsible. The applicable WCB form(s) are to accompany the incident form.
All injury incidents must be classified as either first aid, medical aid, modified work, or lost time.
The classification standard endorsed by the Canadian Association of Petroleum Producers and
being used by HARVARD is ANSI Z16.4. To assist you in accurately filling out our incident
report forms, outlined below are the four categories of injury accidents and some explanation of
what type of incident fits into each category.
Section 6 - 11
1.
First Aid
This is defined as any one treatment and subsequent observation of minor
scratches, cuts, burns, splinters and so forth, which do not ordinarily require medical
care by a physician. The transport of an injured worker to a physician for
observation or for diagnosis as a safety precaution can still be considered a first aid
case.
2.
Medical Aid
The decision as to whether a case involves medical aid should be made on the
basis of whether the case normally would require medical treatment. The decision
cannot be made on the basis of who treats the case. A physician can administer
first aid. Medical aid is defined as a work injury other than a first aid which requires
treatment by a physician or other medical professional and includes:
Impairment of body functions (e.g. loss of consciousness).
Damage of a non-superficial nature to physical structure (fractures, cuts
requiring stitches etc.)
Complications (e.g. debridement following burns, treatment of infections
arising from injury).
Ongoing medical treatment (e.g. physiotherapy, repeat administration of
a prescription pain killer, etc.)
Diagnostic procedures such as x-rays or preventive procedures such as tetanus shots
are not in and of themselves considered medical aid.
3.
Modified Work
This is any work injury which results in a temporary work assignment that does
not include all the normal duties of the persons regular job. The temporary work
assigned must be considered meaningful.
Initiation of Modified Work Plan
Section 6 - 12
4.
Public is checked if the person injured was someone that is not working for
HARVARD as an employee or contract worker.
Address, City and Postal Code is the injured persons home address.
Experience is the number of years the person has been doing their present job.
Injured Part of Body identifies which part of the body was injured in the
incident.
Section 6 - 13
SECTION 11 ENVIRONMENT
The first part of this section should be filled out by the person preparing the initial incident
report. The second part should be filled out by the Production Foreman or their equivalent.
Liquid is checked if the release was an unrefined petroleum product, produced water, fresh
water or crude oil.
Other is checked if the release was a chemical or a refined petroleum product such as
diesel, gasoline, etc.
Terrain Affected
o
o
o
Contained on Lease
o
o
Land is checked if the release affected any of the surrounding area including on
lease.
Water is checked if the release got into any river, creek or body of water.
Both are check when the release affected the surrounding area and body of water.
Rehabilitation Required
o
o
Yes is checked if work may have to be done at a later date to restore the spill area
back to its original condition.
No is checked if no work is required other than the initial clean up.
Waste Manifest is checked if a waste manifest needs to be filled out for any material
hauled off location.
Public Complaint is checked if there is a complaint from any party not working for
HARVARD or if a spill or release is reported by a landowner, etc.
GAS
Discharged is the estimated amount of gas released expressed in m3. This should include
accidental or emergency flared gas volumes.
Sweet or Sour indicates if the release contained H2S levels in excess of 10 ppm.
Section 6 - 14
LIQUID HYDROCARBON
OTHER
Smoke is checked yes if there was a fire involved in the release or a flare stack or lit pit
was involved. Otherwise no is checked.
Odour is checked yes if there was a release that emitted an odour that may be
noticeable to the surrounding public or contract personnel. Also if there was a complaint
in the area. No would be checked if none of these apply.
Noise is checked yes if there was a condition resulting in noise exceeding permitted
levels. Also if there is a complaint from the public. Otherwise no is checked.
Wind Direction is the direction the wind was blowing during or after the release.
CONTROL MEASURES
AMENDMENTS APPLIED
Quantab Values is the initial values obtained using the Quantabs provided in the spill
kits. The final report should state what values were achieved.
Government File Number is the file number issued by the government at the time the
release was reported. This number should be asked for when reporting the release.
Date Rehabilitation Was Completed is the final date work was performed on the
location.
Calcium Nitrate is the amount of calcium nitrate used in the reclamation expressed in Kgs.
Section 6 - 15
Seed Mixture Applied is the type and amount of seed used in the reclamation.
Other is any other product that may have been used in the reclamation of the lease
e.g. straw, hay or Oil-Gator, etc.
License Number is the Board license number found on the pipeline application to the
government.
Line OD is the outside diameter of the line in the area of the failure (expressed in mm).
Grade is the grade or type of pipe used: sour, sweet, schedule 40 etc.
MOP is the maximum operating pressure of the failed line as stated on the pipeline
license (expressed in kPa).
Type of Wrap is the type of outside coating of the line (e.g. yellow jacket).
Internal Coated yes is checked if the line has any type of internal coating. If not
coated check no.
Wall Thickness is the pipe thickness in the area of the failure (expressed in mm).
Normal Operating Pressure is the operating pressure of the line under normal
operating conditions (expressed in kPa).
Depth of Cover is the amount of material that is covering the line in the area of the
failure.
Vessel I.D. is the Alberta Number or CRN registration number off the vessel.
Repairs and Alterations is checked if the cause of the failure was related to any
repairs or alterations done to the line or vessel.
Section 6 - 16
Final Costs is checked if this is the known final cost of the incident.
Estimated Costs is checked if the costs are not known or there may be more costs
added at a later date.
Covering Costs
o Company is checked if HARVARD is covering all the repair or clean-up costs.
o Third Party is checked if the costs are being charged to or paid for by a
contractor, trucking company, or someone elses insurance company, etc.
Estimated Clean-Up Costs is the estimated cost of the clean-up including all
transportation, disposal, clean-up and seeding costs, etc. For larger incidents this
information is needed right away for insurance reporting requirements. This is a time
limit for reporting an incident to the insurance company that may result in a claim. This
can be done with a telephone call.
Final Clean-Up Costs is all actual costs associated with the clean-up of the site.
Describe any Unsafe Conditions. This is a detailed written explanation of any unsafe
condition or conditions and should include the what, how and why. Any unsafe
condition or conditions that contributed to the incident should be checked off. The
written description should also discuss any unsafe conditions that are not included in
the check boxes.
Describe any Unsafe Acts. This is a detailed written explanation of any unsafe act or
acts and should include the what, how and why. Any unsafe act or acts that contributed
to the incident should be checked off. The written description should also discuss any
unsafe acts that are not included in the check boxes.
Section 6 - 17
Corrective Action is a detailed explanation outlining what actions have or will be taken
to prevent the recurrence of a similar incident. The written description should also
discuss any recommended actions not included in the check boxes.
Section 6 - 18
SECTION 6 FORMS
Incident Investigation Report
Spill Site Assessment Sheet
Basic Causes of Loss
Regulatory Reporting Requirements for Spills and Releases
Reportable Spill Volumes for TDG Controlled Substances
Section 6 - 19
Please ensure you have provided all information for the incident you are reporting
ENVIRONMENT
NEAR MISS
SAFETY
INJURY
VEHICLE
PROPERTY DAMAGE
DISTRICT:
FIELD:
MER
TIME
N
O
T
I
F
I
C
A
T
I
O
N
TWP
FINAL REPORT
Date Reported:
YYYY / MM / DD
SEC
INTERIM REPORT
Date of Occurrence:
LOCATION
LSD
RELEASE
YYYY / MM / DD
ERCB / MEM
TIME
Name:
Time:
Name:
Time:
WCB / OH&S
Name:
Time:
AEP / MELP
Name:
Time:
POLICE
Name:
Time:
LANDOWNER
Name:
Time:
PROVIDE AN EXACT DETAILED DESCRIPTION OF THE INCIDENT, NON CONFORMANCE AND / OR PROPERTY AFFECTED: (attach diagram if appropriate)
EQUIPMENT / VEHICLE INFORMATION - (including QMP)
SEVERITY POTENTIAL
Minor
INJURY INFORMATION
First Aid
Serious
PROBABILITY OF OCCURRENCE
Major
Medical Aid
Lost Time
Injured party:
Employee
Public
Occasional
Frequent
Other Specify
Address:
City:
Experience:
Seldom
Fatality
Name:
Postal Code:
UNIT NO.
Yrs
Phone #
Occupation:
Immediate Supervisor:
Modified Work
_________________________________________________________________________
Any product spill - Off Lease, Into a Water Course, or Over 2m on Lease is to be reported. On Lease spills under 2m do not need to be reported.
ENVIRONMENTAL
Liquid
Contained on Lease?
Yes
No
Other
Rehabilitation Required ?
Gas:
Discharged:
Sweet/Sour
H2S %:
Smoke:
Terrain Affected
Yes
No
Waste Manifest
Land
Yes
Water
No
Both
Public Complaint?
Other:
Discharged:
Discharged:
Discharged:
Recovered:
Recovered:
Yes
No
PW
Odour:
FW
Yes
No
Noise:
Yes
No
Recovered:
Yes
No
Wind Direction:
CONTROL MEASURES INCLUDING A DESCRIPTION OF CLEAN UP AND REHABILITATION: (Recovered product recycled? - Contaminated Soil? - Treated? Hauled Away? - Where?)
Quantab Values:
Amendments Applied:
Date:
Calcium Nitrate:
kg
Ammonium Nitrate:
kg
Government File:
Other:
Straw etc.
Line No:
Line OD (mm):
Grade:
MOP (kPa):
Type of Wrap:
Type:
Vessel I.D. #:
Repairs or Alterations
Internal Coat:
Yes
No
Page 1 of 2
Indicate
Final Costs
Estimated Costs
Covering Costs
Company
Third Party
What was the cause of the accident? (Determine the cause by analyzing all factors concerned. A person, a machine, or a physical condition? How? Why?
HAZARDOUS SUBSTANCE
HAZARDOUS ATMOSPHERE:
INADEQUATE VENTILATION
EXCESSIVE NOISE
POOR HOUSEKEEPING
RADIATION EXPOSURE
VIOLENCE / HARASSMENT
FAILURE TO SECURE / LOCK-OUT
UNNECESSARY HASTE
HORSEPLAY
UNAWARE OF HAZARD
FATIGUE
Explain what you have done or what you recommended to prevent a recurrence of a similar incident / accident
SIGNATURE: INSPECTOR
DATE
FOLLOW-UP ASSIGNMENTS:
WHO?
WHEN?
WHAT?
INCIDENT REPORTED BY
FORWARD REPORT TO:
DATE
SUPERINTENDENT / MANAGER
Page 2 of 2
This report is required as part of Harvard obligations under the Occupational Health & Safety Act of Alberta and is subject to the protections of sections 18 and 19 of that act. Further, any
statements given herein are made subject to the protections provided by section 6 of the Alberta Evidence Act and section 5 of the Canada Evidence Act to the extent that they may apply.
____________________________________________________________Date:_________________
Wellhead
Underground tank
Spills/Contamination
Drainage direction
Sump
Pipeline
tsp
Berm
Erosion
Riser
Top soil pile
Trench
fp
ssp
Slope
Flare Pit
bl
st
Building
Surface Tanks
ac
Access
Comments:
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
_________________________________________________________________________________
Section 6 - 20
Lack of Knowledge
lack of experience
inadequate orientation
inadequate initial training
inadequate update training
misunderstood directions
Lack of Skill
inadequate initial instruction
inadequate practice
Improper Motivation
improper performance is rewarding
improper performance is punishing
lack of incentives
excessive frustration
inappropriate aggression
improper attempt to save time or effort
improper attempt to avoid discomfort
improper attempt to gain attention
inappropriate peer pressure
improper supervisory example
inadequate performance feedback
inadequate reinforcement of proper behaviour
improper production incentives
- infrequent performance
- lack of coaching
JOB FACTORS
Inadequate Engineering
inadequate assessment of loss exposures
inadequate consideration of human factors ergonomics
inadequate standards, specifications and/or design criteria
inadequate monitoring of construction
inadequate assessment of operational readiness
inadequate monitoring of initial operation
inadequate evaluation of charges
Inadequate Purchasing
inadequate specifications on requisitions
inadequate research on materials & equipment
inadequate specifications to vendors
inadequate mode or route of shipment
inadequate receiving inspection and acceptance
inadequate communication of safety and health data
improper handling of materials
improper storage of materials
improper transporting of materials
inadequate identification of hazardous items
improper salvage of waste disposal
Inadequate Maintenance
inadequate preventive
assessment of needs
lubrication and servicing
adjustment assembly
cleaning or resurfacing
Abuse or Misuse
condoned by supervision
not condoned by supervision
unintentional/intentional
- inadequate reparative
communication of needs
scheduling of work
examination of units
part substitution
Section 6 - 21
Life Safety
Spills
VOLUME/ SEVERITY
Any
WHS
ALTA
WCB
B.C.
Federal
NEB/TSB
Any
WHS
WCB
WCB
NEB/TSB
Any situation that has or potentially may threaten the health and
safety of the public
Any
PEP
OGC/PEP
Police
* DTH
NEB/TSB
ERCB
LDDS
EMA
Police
* AT-via EMA
ERCB
Off-Lease crude oil/ salt water spill or any pipeline release or any
pipeline release that may, has, or could cause an adverse effect
Crude oil/ salt water spill
Into watercourse
Any volume
ERCB
Any volume
ERCB
AEPCD
OGC/PEP
WLAP
OGC/PEP
WLAP
EMA
Local Police
OGC/PEP
Local Police
Notes:
1) In Alberta, WHS notification includes any hospital stay >2 days
due to medical aid, restricted duty or lost time accidents
2) WCB notification must occur immediately for fatalities or within
72 hours for injuries
3) Confirm with Incident Commander that local ambulance service
or Stars Link Centre (Alberta) has been notified.
OGC/PEP
WLAP
NEB/TSB
ECAN
DFO
NEB/TSB
VOLUME/ SEVERITY
Any volume
ALTA
ERCB
Releases
Nuisance / noticeable,
public complaint
received
AE-PCD: Exceeds facility
approval
ERCB: exceeds approved
volume or flaring for more
than 24 hours
ie: public complaint
received
Any
ERCB
Pipeline
Contact/Failure/
Rupture
Fire/
Explosion
Pressure vessel
Electrical
Vehicle accident
Security Incident
Abbreviation
ERCB
AE-PCD
EMA & AT*;
LDDS
WHS
OGC / PEP; DTH*;
WLAP
BC WCB
ECAN
DFO
SCO
NEB & TSB
ABSA
(* Highway Authorities for emergencies that impact or require closure of 1 or 2 digit highway
Any
Any
Any
Any
Any
AE-PCD or
ERCB
B.C.
OGC/PEP
WLAP
OGC/PEP
WLAP
Federal
NEB/TSB
OGC/PEP
WLAP
AE-PCD or
OGC/PEP
ERCB
WLAP
ERCB or NEB, as
applicable
WHS see
Note
ERCB
OGC/PEP
WHS
WCB
LDDS
ABSA
ML-BVS
SCO
ML-ES
Local Police
Local Police
Local Police
Local Police
* AT-via EMA
* DTH
NEB/TSB
NEB/TSB
NEB/TSB
NEB/TSB
NEB/TSB
PRODUCT/INCIDENT CONDITIONS
Any situation or dangerous occurrence that had the potential for serious
injury of workers: (ie: structural failure or collapse of a support system,
excavation, or contact with a pipeline)
VOLUME/SEVERITY
SASK.
MAN.
FEDERAL
Any
OH&S
WSH
NEB/TSB
OH&S
WSH
Any
WCB
WCB
NEB/TSB
Any situation that has or potentially may threaten the health and safety
of the public
Any
OH&S
Police
WSH
Police
NEB/TSB
SER
Manitoba
Conservation
Any Volume
SER
Manitoba
Conservation
Any Volume
Life Safety
Spills
NEB/TSB
Volumes according to
TDG regulations
SER
Dept. of
Environment
Dept. of
Environment
Local Police
Manitoba
Conservation
ECAN,
DFO,
NEB/TSB
Manitoba
Conservation
Local Police
Dept. of
Manitoba
Environment
Conservation
Reportable volumes in
TDG regulations & CEPA
In addition to above spill notification requirements notify ECAN
PRODUCT/INCIDENT CONDITIONS
VOLUME/SEVERITY
SASK.
MAN.
FEDERAL
Sour Gas
Any Volume
SER
Manitoba
Conservation
NEB/TSB
Nuisance/noticeable,
public complaint received
SER
Manitoba
Conservation
SER
Manitoba
Conservation
SER
Manitoba
Conservation
Any
Manitoba
Conservation
SER
Engineering
Services Branch
Any
SER
Fire Dept.
WSH
Fire Dept.
Corrections &
Public Safety
Man.
Labour/Imm.
Mechanical &
Engineering
Branch
Releases
Flaring - report
to agency which
issued approval
Pipeline
Contact/Failure/
Rupture
Fire/Explosion
Pressure Vessel
Any
NEB/TSB
NEB/TSB
NEB/TSB
PRODUCT/INCIDENT CONDITIONS
VOLUME/SEVERITY
SASK.
FEDERAL
Sask Power
MAN.
Labour/Imm.
Mechanical &
Engineering
Electrical
Any
Vehicle Accident
Any
Local Police
Local Police
NEB/TSB
Security Incident
Any
Local Police
Local Police
Abbreviation
SER
OH&S
Sask. WCB
Man. Conserv.
WSH
Man. WCB
ECAN
Manitoba Conservation
Manitoba Workplace Safety & Health
Manitoba Worker's Compensation Board
Environment Canada
DFO
NEB/TSB
NEB/TSB
ITEM
CLASS
DIVISION
QUANTITIES OR LEVELS
Explosives
2.1
Flammable Gases
2.2
2.3
Toxic Gases
Flammable Liquids
Flammable solids
5.1
Oxidizing substances
5.2
Organic Peroxides
10
6.1
Poisonous Substances
11
6.2
Infectious Substances
Non-Flammable,
Non-Toxic
12
13
Corrosive Substances
14
Miscellaneous Products,
Substances or Organisms
* Additional B.C. Reporting Requirements as per Waste Management Act Spill Reporting Regulation 166/93
(Items above listed in B.C.s Spill Reporting Schedule are reflected above as per new Federal Clear Language TDG
Regulations)
17
Waste asbestos as defined in section 1 of the Special 50 kg
Waste Regulation.
18
Waste oil as defined in section 1 of the Special Waste 100 L
Regulation.
19
Waste containing a pest control product as defined in 5 kg
section 1 of the Special Waste Regulation.
20
A substance not covered by items 1 to 19 that can cause 200 kg
pollution.
21
Natural Gas
10 kg, if there is a breakage in a pipeline or
fitting operated above 100 psi that results in a
sudden and uncontrolled release of natural gas.
7.0
EMERGENCY PREPAREDNESS
7.1
OVERVIEW
Although proper hazard assessment procedures will identify and address most worksite hazards,
some unanticipated emergencies must be planned for. The primary objectives of emergency
preparedness preparations are: to save lives, implement protective actions, and restore operations.
Supervisors are responsible for ensuring that emergency response requirements for their area are
identified and addressed.
Emergency Response Plans
Harvards mandate and commitment is to conduct all business in a competent and safe manner.
Harvard believes that although the likelihood of an emergency situation occurring is low, the
potential certainly exists. Therefore Harvard has developed both a Corporate Emergency
Response Plan and site or job-specific plans.
Emergency Response Plans must be developed to provide a seamless response structure and
built from an implementers perspective. They also outline the responsibilities of both Company and
contract personnel, as well as government agencies should an emergency incident occur.
Corporate ERP
All Company operations will be covered under a Corporate ERP. The Corporate ERP gives
general guidelines of what to do, who to notify, and how to plan for and manage an emergency.
Higher risk worksites such as: sour facilities, densely populated areas, drilling, or remote locations
may require higher levels of emergency response planning and site specific ERPs.
Harvards Corporate Emergency Response Plan defines the major categories of an emergency,
which are:
The Corporate Emergency response Plan contains telephone numbers of key Corporation
personnel and appropriate provincial regulatory agencies to contact in times of emergency.
Regulatory Requirements
In accordance with Alberta OH&S Code Part 7, Emergency Preparedness and Response, the
following applies in relation to the development and maintenance of an ERP.
Section 7 - 1
An employer must establish an emergency response plan for responding to an emergency that
may require rescue or evacuation. The employer must involve affected workers to ensure the
emergency response plan is current, and lastly, provide training and emergency simulation
exercises in keeping with sections 115 (1-3) and 117(3).
In accordance with Canadian Standards Association CAN/CSA-Z731 employers are required to
develop, maintain and implement their ERP in accordance with the requirements of the
aforementioned Standard.
ERCB Directive 071 (revised April 8, 2008) states that when a site-specific ERP is not required, a
corporate level ERP is used by the license to handle emergency events.
1)
All licensees must have a corporate-level ERP with preplanned procedures that will
aid in effective response to handle emergency events.
2)
Licensees are expected to determine the level of detail required to address each item
in a corporate level ERP, depending on the nature of the operations that the plan
covers.
3)
The licensee must include the following in the corporate level ERP:
4)
The licensee must define appropriate actions including protection measures that would be
taken for each level of emergency.
Corporate Level ERPs - Part A Section 2-4 & Part B Section 11-13
Sour Well Site-Specific Drilling/Completions ERPs - Part A Section 3-6 & Part B Section 12-15
Sour Operations ERPs - Part A Section 3-5, 7 & Part B Section 12- 14
ERPs for High Vapour Pressure Pipelines - Part A Section 3-5, 8 & Part B Section 12-14
ERPs for Cavern Storage Facilities Storing HVP Product - Part A Section 3-5, 9 & Part B
Section 12-14
Spill Cooperative Response Plans - Part A Section 10 & Part B Section 16
Section 7 - 2
Note: The reader is advised that the above references are for the Province of Alberta only.
Reference material for British Columbia can be found with BC-Oil and Gas Conservation
Regulation, BC Oil and Gas Handbook, BC Pipeline Act and Regulation, BC Drilling
Regulations. For Saskatchewan, the only reference identified is the CAN/CSA Z731.
Section 7 - 3
8.0
WORK PROCEDURES
Detailed work procedures for critical tasks are important to both management and workers. In
each jurisdiction, the Occupational Health and Safety Regulations require that safe work
procedures be developed and implemented where work to be performed constitutes a hazard
to the worker. Most importantly, work procedures set guidelines for operating performance and
provide reference for training.
Job Safety Analysis (JSA) and Observation
Job Safety Analysis (JSA) and observation help to eliminate hazards before they cause
problems. Supervisors must regularly observe the work site and work practices to assess the
safety of operations and determine where improvements are needed.
The key to successful work procedures is to continually encourage safe and efficient work
practices. Shortcuts which compromise safety are unacceptable.
The following HARVARD Codes of Practice and Work Procedures are included in this section
to help guide supervisors in maintaining safe working conditions at the work site:
8.1
Codes of Practice
8.1.1
8.1.2
8.1.3
Asbestos
Benzene
Confined Space Entry
8.2
Work Procedures
8.2.1
8.2.2
8.2.3
8.2.4
8.2.5
8.2.6
8.2.7
8.2.8
8.2.9
8.2.10
8.2.11
8.2.12
8.2.13
8.2.14
8.2.15
8.2.16
8.2.17
8.2.18
8.2.19
8.2.20
8.2.21
8.1.4
8.1.5
8.1.6
8.2.22
8.2.23
8.2.24
8.2.25
8.2.26
8.2.27
8.2.28
8.2.29
8.2.30
8.2.31
8.2.32
8.2.33
8.2.34
8.2.35
8.2.36
8.2.37
8.2.38
8.2.39
8.2.40
8.2.41
Hot Oiling
Hot Taps
Hot Work Procedures
Housekeeping
Hydrate / Ice Plug Handling
Managing Control of Hazardous Energy
Naturally Occurring Radioactive Materials (NORM)
Noise Exposure
Pigging Guidelines
Portable Pumping Equipment
Purging
Rig Anchors
Safe Work Permits
Tank Truck Loading Procedures For Flammable
Fluids
Timber Removal
Trailers & Bunkhouses
Trenching
Vehicle, Mobile Equipment & Machinery
Welding & Burning
Wildlife Awareness
8.2.42
8.2.43
Working Alone
Working Near Overhead Powerlines
Section 8 - 1
8.1
CODES OF PRACTICE
8.1.1 ASBESTOS Code of Practice
SCOPE AND PURPOSE
USES INCLUDE
Roof tiles, floor tiles, wallboard, brake shoes, clutch plates, gaskets
NOTE: Most insulation used before 1975 was asbestos or
asbestos based.
HEALTH HAZARD
Section 8 - 2
IDENTIFICATION
Four step process:
1. Visual Inspection
o Check drawings and blueprints
o Exposed asbestos may be soft or hard
o Check under physical barriers: gyproc, plywood, metal sheeting,
paint
NOTE: Asbestos that is encapsulated behind a barrier or sealed poses
very little risk to the worker, unless it is disturbed.
2. Collect Sample(s)
o Identification coupons (samples) should be taken as deep as
possible as other types of insulation may have been put over
top of asbestos insulation.
o See attached procedure
3. Sample Analysis
o Use only experienced specially equipped laboratories (contact the
Calgary Office for the list).
4. Inventory
o Indicate on drawings and blueprints
o Establish an asbestos log book. Record areas, removal and
disposal
o Identify area with placard:
CAUTION: INSULATION CONTAINS ASBESTOS FIBRES
DO NOT DISTURB or use label system similar to WHMIS Identification.
ASBESTOS REMOVAL
General Information
A.
Low Risk
Definition
o
No more than 2 workers are required
o
Volumes to be removed will fit into Glove Bag
o
Task is no longer than one shift
o
Worker can be protected by PPE
o
No power tools are used
Section 8 - 3
B.
Removal:
o
Glove Bag (see attached procedure)
Moderate to High Risk
Definition
o
More than 2 workers are required
o
Area to be removed is large than Glove Bag method can
accommodate
o
Power tools are used
o
Task lasts more than one day
o
Medical surveillance of workers required by provincial regulations
o
Disposal is, or can be, a problem
Removal
o
If one or more of the above conditions are present, removal by an
approved Removal and Abatement Contract is required.
Contact the provincial government for a list of approved
contractors. (Contractors must meet standards of Partnerships
Program and be able to supply references).
Section 8 - 4
______ Major
LIKELIHOOD
______ High
______ Serious
______ Moderate
______ Minor
______ Low
POTENTIAL HAZARDS:
PPE REQUIRED:
EQUIPMENT REQUIRED:
TRAINING:
Section 8 - 5
Put on PPE
Section 8 - 6
______ Major
______ Serious
______ Moderate
______ Minor
______ Low
POTENTIAL HAZARDS:
PPE REQUIRED:
EQUIPMENT REQUIRED:
TRAINING:
Section 8 - 7
8.1.2
Section 8 - 8
Worker Responsibility
8.1.3
AREA: _________________________________________________________________
INCIDENT POTENTIAL:
______ Major
LIKELIHOOD:
______ High
______ Serious
______ Moderate
______ Minor
______ Low
Isolation points
Venting procedures
Site-specific hazards
OPX Consulting Inc.
Section 8 - 10
POTENTIAL HAZARDS:
PPE REQUIRED:
SCBA/SABA
Fire retardant clothing
H2S monitor
Oxygen analyzer
Explosive meter
Safety harness and other rescue equipment
Head, eye, face, hand, foot and body protection as indicated by
hazards
EQUIPMENT REQUIRED:
TRAINING:
PROCEDURE/ACTION:
General:
Work permits must be issued and discussed with the workers each
day. Other topics to be discussed with workers include:
o
At Operating Facilities any alarms that may occur and their
meaning.
o
MSDS sheets of any chemicals that may be encountered.
Section 8 - 11
Preparation:
Ventilation:
Inerting:
Section 8 - 12
Initial Entry:
Ensuing Entries:
Waste Disposal:
Section 8 - 13
Job Completion:
8.1.4
Prevention
In order to prevent an uncontrolled release, the following procedures
apply:
The design of new facilities will comply with appropriate codes and
accepted industry engineering practices;
Controlled Release
There may be times in our operations when quantities of H2S (or other
hazardous substances) will be released during the course of normal
operation and maintenance activities. These releases are considered
controlled releases because they are anticipated and planned for.
Systems and procedures shall be in place to control the amount released
so that workers and the public are not at risk.
OPX Consulting Inc.
Section 8 - 14
Uncontrolled Release
Occasionally there are unplanned events in the movement or storage of
substances. Where this occurs, company and contract personnel will:
8.1.5
Protect people;
Take action to control the effect on the environment;
Not enter the area where the release has occurred unless equipped
with appropriate personal protection;
Initiate controlled shut down of affected equipment when failure to
do that would present greater risks;
Isolate and contain the release;
Document and report all occurrences in a proper manner to the
appropriate authorities; and
Investigate the occurrence to determine root cause, so as to prevent
future occurrences.
1.
2.
3.
Section 8 - 15
4.
5.
Training of Workers
The requirements for proper training of workers using
respiratory equipment.
Section 8 - 16
Toxic
Contaminant
Oxygen
Deficiency
Non-IDLH
IDLH
(Not immediately
dangerous to life or
health)
(Immediately
dangerous to life or
health)
Contaminant exceeds
Occupational
Exposure Limits
(Consult Provincial
Chemical Regulations)
Gas or Vapour
Chemical
Cartridge
Respirator
Gas
Mask
Gas or Vapour
and Particulate
Particulate
Powered
Air-Purifying
Respirator
Filter
Respirator
Combination
Cartridge Plus Filter
Respirator
Gas Mask
SCBA
(Self-Contained
Breathing Apparatus)
SABA
(Supplied Air Breathing
Apparatus with escape provision)
Section 8 - 17
Particulate (dust)
Gas
Vapour
Mist
Fume
Combination
Oxygen Deficiency
NOTE: Review MSDS and Provincial Regulations for toxic limits.
WORKER EXPOSURE
RESPIRATOR
Type ______________________________
Model _____________________________
Training
Manufacturer/Supplier Information
Section 8 - 18
Ammonia
Asbestos
Chemical Fumes
Chlorine
SCBA or SABA
Heavy Metals
SCBA or SABA
Hydrocarbon Vapours:
1.
Painting
2.
General
3.
Process Areas
Nuisance Dusts
Nuisance Odours
Welding Fumes
Oxygen Deficiency
Radioactive (NORM)
Section 8 - 19
TYPE OF DEVICE
USED FOR
LENGTH OF SERVICE
Mechanical Filter
Chemical Cartridge
1.
2.
PRECAUTIONS FOR
USE & SELECTION
STYLES AVAILABLE
1.
2.
Section 8 - 20
TYPE OF DEVICE
PRECAUTIONS FOR
USE & SELECTION
USED FOR
LENGTH OF SERVICE
Gas Masks
Self-Contained Breathing
Apparatus (SCBA)
oxygen-deficient environment
area containing multiple
hazards
confined space (providing
egress and mobility allow for
use of unit)
environment may be subject to
rapid change
environment where superheated air may be present
STYLES AVAILABLE
Section 8 - 21
TYPE OF DEVICE
Supplied Air Breathing
Apparatus (SABA)
USED FOR
LENGTH OF SERVICE
PRECAUTIONS FOR
USE & SELECTION
STYLES AVAILABLE
1. Same as above
Section 8 - 22
B.
B.
Section 8 - 23
8.1.5.3
Excess dirt
Cracks, tears, holes or physical distortion of shape
from improper storage
Inflexibility of rubber face-piece (stretch and knead to
restore flexibility)
Cracked or scratched lens in full face-piece
Incorrectly mounted full face-piece lenses
Broken or missing mounting clips
Cracked or broken air-purifying element holders, badly
worn threads, or missing gaskets (if required)
Nose cap
Breaks
Loss of elasticity
Broken or malfunctioning buckles and attachments
Excessive worn serration on head harness which might
permit slippage (full face-piece only)
Regulator
Gauges
Hoses
Connections
Cylinder for condition and hydrostatic test date
Section 8 - 24
8. Miscellaneous
2.
Dust
Direct sunlight
Excessive heat
Extreme cold
Excessive moisture
Damaging chemicals
3.
4.
5.
8.1.5.5
Supervisors must:
Section 8 - 26
On-the-Job Training
As a minimum, OTJ training should include:
Training Resources:
Hazardous Atmosphere: Any atmosphere that is oxygendeficient or that contains an air-borne toxin or diseaseproducing contaminant in concentrations exceeding the
exposure limit.
8.1.6
Section 8 - 28
Training:
Protection:
HARVARDs safe work guideline for working in sour production areas are
as follows:
1. H2S Monitoring:
H2S detection must be used to monitor the work environment in
areas where the potential of exposure to H2S levels above 10 ppm
exists. Detection equipment can be either continuous or personal
monitors. Personal H2S monitors shall be worn at all times by full
time personnel. Contractors shall wear H2S monitors as directed
by HARVARD representative and/or their work permit. Known
danger areas must be clearly posted in accordance with
Occupational Health and Safety requirements.
2. Normal Routine Operations
Normal routine operations in sour production areas may be
performed by an operator working alone subject to the following
restrictions:
a. When entering sour locations, employees are to ensure that:
Section 8 - 29
8.2
Hydrogen sulphide reacts with iron and steel to form iron sulphide.
Iron sulphide reacts with air to form iron oxide. The conversion of
iron sulphide to iron oxide creates heat sufficient to ignite
flammable vapours.
WORK PROCEDURES
8.2.1 AIRCRAFT SAFETY AWARENESS
The purpose of this section is to ensure employee and contractor personnel
are not subjected to unnecessary risk during the use of charter or other
aircraft, the following guidelines have been adopted from several insurance
industry sources, and are applicable to all employees and contract personnel
utilizing fixed wing, helicopter, charter, or other aircraft.
Standard Safety Briefing
The standard safety briefing shall consist of an oral briefing provided by a
crew member or by audio-visual means, and includes the following
information as applicable to the aircraft, equipment, and operation:
o Embarking and disembarking procedures;
o No smoking in or around any aircraft;
o When, where, why, and how carry-on baggage is required to be stowed;
o The fastening, unfastening, tightening, and general use of safety belts or
safety harnesses;
o The location of emergency exists, exit location signs, and how each exit
operates;
o The location, purpose of, and advisability of reading the craft specific
safety features card;
o The requirement to obey crew instructions;
o The use, location, operation, and deployment, as applicable, of
emergency equipment such as life rafts, life preservers, fire
extinguisher, ELT (Emergency Locator Transponder), survival
equipment, and first aid kit including means of access to any locked
compartment;
o Where applicable, the method of egress from a wide body helicopter in
the event of a roll-over incident; and
o Any special instructions related to emergency evacuation if the craft is
configured with external devices.
Where no additional passengers have boarded the flight for subsequent takeoffs on the same day, the pre-take-off and after take-off briefing may be
omitted provided a crew member has verified that all carry-on baggage is
properly stowed, safety belts or harnesses are properly fastened, and seat
back and chair table are properly secured.
Section 8 - 32
Note: This is not a complete guide for aircraft safety, please consult the pilot
and/or your supervisor for additional information.
Section 8 - 33
CSA-approved
helmet
Eye protection (safety glasses,
face shield and/or goggles)
Sturdy footwear
Work gloves
Long-sleeved shirt and pants
Hearing protection
(recommended)
Reflective vest and/or safety
flags
Working alone/check-in
procedure
Head lights and tail lights on
First Aid Kit (remote areas)
Operators manual
Survival Kit (remote areas)
Communication device and a
GPS (when working in remote
areas)
*Optional equipment may include an axe, gas line anti-freeze, spark plugs,
winch, bear deterrents, fire extinguisher.
Properly maintain their ATV (servicing, pre-ride inspection in
accordance with manufacturers guidelines see ATV Checklist).
When riding an ATV, all riders are expected to scan the area, identify
hazards, predict what will happen, decide what to do, and execute the
decision. All ATV riders must adjust their driving attitudes to the
surrounding conditions, where unfamiliarity and adverse weather
conditions require a more cautious approach in operations. Formal hazard
assessments are required when traversing slopes with a potentially
dangerous grade. If an ATV rider does not feel comfortable in their ability
to complete a task, they should inform their supervisor immediately.
Section 8 - 34
ATV CHECKLIST
Satisfactory S
Location (LSD):
Unsatisfactory U
Date (yy/mm/dd):
ATV Activities
Description of ATV activities (brief):
Make:
Model:
Pre-Use Inspection
S U N/A
Walk-Around
General ATV Condition
Tires, wheels, or tracks in good condition
U N/A
Engine
No leaks on drive shaft
Nuts and bolts securely fastened
Signature:
Comments
Section 8 - 35
8.2.3
BLOWDOWNS
SCOPE AND PURPOSE
To provide safe procedures for conducting blowdowns. Blowdowns
include operations to:
1. Depressurizing wells for the purpose of unloading accumulated
liquids.
2. Depressurizing pipelines and other facilities for the purpose of working
on them and for removing hydrates and other plugging substances.
For the purpose of this work procedure, it is assumed that all fluids
recovered from the well or facility are sweet and the facility is designed as
a typical sweet gas wellsite facility with separator of dehydrator and buried
blowdown tank. If sour fluids are expected refer to applicable safe work
procedures for sour fluids.
Refer to Industry Recommended Practice for Well Testing and Fluid
Handling IRP Vol. 4.
BLOWING DOWN WELLS
The following steps should be taken when a well is to be blown down to
unload liquids. In most cases a buried blowdown tank is provided as a
permanent facility. A block valve will be located in the flowline,
downstream of the blowdown line. A wellhead choke may also be
provided.
1. Shut the well in by closing the block valve in the flowline downstream
of the blowdown line.
2. If it is necessary to build up reservoir energy to facilitate the lifting of
liquids, leave the well shut in for sufficient time to build up pressure.
The necessity to blow down a well is usually characterized by low
tubing pressure and high casing pressure (if the well does not have a
packer). Blowdown is usually done from the tubing as that is the way
the well is normally produced.
3. Check and record the shut-in wellhead pressure(s).
4. Check fluid level in the blowdown tank to ensure there is room for the
anticipated volume of liquid to be recovered.
5. Check the blowdown tank vent line to ensure that it is unrestricted.
6. Check to ensure there are no potential sources of ignition within 25
meters of the blowdown tank vent line. If there are vehicles on
location, ensure they are parked upwind.
Section 8 - 36
7. Slowly open the block valve on the blowdown line to avoid pressure
shocking the blowdown tank and avoid blowing liquids out the vent
line. If the wellhead is equipped with a choke, the choke should be
used to slowly open the well to the blowdown tank.
8. Continuously monitor the blowdown until it is felt that all or sufficient
liquids have been recovered.
9. Close the choke at the wellhead (if one is provided) and then the block
valve on the blowdown line.
10. Check and record shut-in wellhead pressure(s).
11. Slowly open the block valve in the flowline downstream of the
blowdown line and then open the wellhead choke (if provided) to
return the well to production.
Note: If blowdown cannot be done upstream of meter run, then
ensure orifice plate is removed before blowdown. Once blowdown is
completed, re-install the orifice plate.
BLOWING DOWN PIPELINE SEGMENTS
The following procedure should be used when depressurizing pipelines to
remove hydrates or other obstructions. In all cases where hydrates are
suspected, the line must be depressurized on both sides of the hydrate.
Refer to safe working procedures for detecting and removing hydrates.
1. If Hot Tapping is required, refer to appropriate safe work procedures
for hot tapping and ensure that competent and suitably trained
personnel are available to perform the hot tapping operation.
2. If liquid recovery is anticipated during the blowdown, appropriate
containment must be planned for.
3. Slowly open the bleeder valve to avoid a surge of fluids to the
containment tank.
4. When all line pressure has depleted and there is no further flow, close
the bleeder valve.
Section 8 - 37
Inspect all chains, hooks and cables before using and do not use if worn
or frayed. Also inspect cables for kinks before use. Return defective
equipment to the approved repair shop and notify your immediate
supervisor.
8.2.5
ASBESTOS
HARVARD has developed an asbestos management plan,
located in detail in 8.1.1 of this manual. All employees and
contractors involved with handling of asbestos should be familiar
with this code. Contact the area supervisor to determine if there
is asbestos in the area facilities that you are working.
8.2.5.2
BENZENE
Benzene is found naturally in many geological formations and
therefore may be found at HARVARD production facilities. A
Code of Practice regarding Benzene can be located in section
8.1.2 of this manual.
8.2.5.3
HANTA VIRUS
Hanta Virus is a flu-like illness, which can be contracted from
inhaling air contaminated from saliva, droppings and dried urine
of rodents (ie: deer mice).
Avoid inhalation of contaminated air or direct contact with
contaminated areas by:
Section 8 - 38
8.2.5.4
SEWAGE
Proper site drainage and storage of biological wastes is
important for both health implications and reduction of
environmental impacts. Septic tanks should be stored away from
the primary residence area and be routinely cleaned out.
Proper PPE should be worn during this process.
8.2.6
COMMUNICATION EQUIPMENT
All electronic devices such as cell phones, pagers, and mobile phones
must be intrinsically safe if they are to be used in a potentially explosive
environment.
8.2.7
8.2.8
All lifting devices must have the rated load capacity marked on the
equipment as per manufacturers specifications;
If a lifting device is not commercially manufactured it must be
certified by an engineer;
Section 8 - 39
8.2.9
CRITICAL LIFTS
SCOPE
This section includes guidelines and requirements applicable to critical lifts
and describes the planning and documentation required to perform a
critical lift. Critical lift permit is required.
REFERENCES
29 CFR 1926, SUBPART N
ANSI/ASME B-30.7 SERIES
RESPONSIBILITIES
RESPONSIBILITIES
Management
Supervisors
Section 8 - 40
Employees
Section 8 - 41
NOTE: Sign offs in the procedure are generally appropriate. For example,
initials and time/date the procedures as key steps are completed. Hold
points or sign-off points should be provided for personnel assigned to
witness the work.
Rigging sketch(s), which include the following:
A load-path sketch that shows the load path and height at key points in
the job. (For lifts with mobile cranes, include the crane position(s) relative
to the load and relative to surrounding obstructions. Where appropriate,
include floor-loading diagrams).
A sketch indicating lifting and travel speed limitations. (This may be noted
on the load path sketch or on a separate sketch).
A sign-off sheet to verify that equipment and tackle inspections or tests
are current.
NOTE: Practice lifts are recommended. (If used, requirements for the
practice lift should be documented in the procedure.)
APPROVAL OF CRITICAL LIFTS
The critical lift procedure should be approved as required by the
responsible contractors procedures. In the absence of direction from the
Section 8 - 42
Procedure author
Manager of the lift operation
Engineer in charge
Safety department / Field safety consultant
Section 8 - 43
2.
3.
BEFORE STARTING
ON THE ROAD
Section 8 - 44
REFUELING
The fall protection plan must be updated when conditions affecting fall
protection change.
Furthermore OH&S regulations state that employers must ensure that a
worker at a permanent work area is protected from falling by a guardrail if
they worker can fall a vertical distance of more than 1.2 metres and less
than 3 metres). If it is not reasonable for guardrails to be in place then a
worker must use a travel restraint system or other effective means to keep
worker from falling.
Section 8 - 45
INSTRUCTION OF WORKERS
An employer must ensure that all workers are trained in the safe use of
the fall protection system before allowing the worker to work in an area
where a fall protection system must be used.
The training must include the following:
Section 8 - 46
o
o
o
o
o
D-rings
O-rings
Oval rings
Self locking connectors
Snap hooks
Selecting the shortest length of lanyard that will still permit unimpeded
performance of the duties.
Securing the lanyard to an anchor no lower than the workers
shoulder, or if not available to an anchor point that is as high as
reasonably practical.
Using only a single lanyard between worker and anchor, with the
exception of electrical danger noted above.
Section 8 - 47
The anchor must also be removed from use, immediately after the
work involving the anchor point is complete or at the time specified by
the manufacturer or a professional engineer.
Life Safety Ropes are one of the key components in fall arrest systems.
There are a number of critical points in regards to life safety ropes which
must be adhered to:
Section 8 - 48
Only one worker is to be attached to a life safety rope at any one time,
unless the manufacturers specifications or specifications of a certified
engineer allow for the attachment of more than one worker.
Any safety life rope must be effectively protected to prevent abrasion
by sharp or rough edges.
Be made of appropriate material to the hazard and able to withstand
adverse effects.
Is installed and used in a manner that minimizes the hazards of
swinging and limits the swing drop distance to 1.2 metres if a worker
falls.
CONTROL ZONES
Control zones are marked areas in which an unguarded edge is present.
Control zones may be used only if a worker can fall from a surface that
has a slope of no more than 4 degrees towards the unguarded edge or
that slopes inwardly away from an unguarded edge and is not less than 2
metres wide when measured from an unguarded edge. Control zones are
not to be used to protect workers from falling from a skeletal structure in a
work area. However, if the worker will at all times remain further from the
unguarded edge than the width of the control zone, no other fall protection
system is needed. Control zones are to be clearly marked with an
effective raised warning line or other equally effective method if a worker
is working within 2 meters of the control zone. If work must be done within
the control zone then the use of a travel restraint system or equally
effective means of preventing worker from getting to the unguarded edge
is necessary. Also no persons who are not directly required to work in the
control zone are permitted inside control zone.
PROCEDURES IN PLACE OF FALL PROTECTION EQUIPMENT
Procedures may be developed in place of fall protection equipment where
it is not reasonable practicable to use an approved fall protection system
or if the use of procedures in place of fall protection equipment is
restricted to the installation or removal of fall protection equipment; roof
inspection; emergency repairs, at height transfers between equipment and
Section 8 - 49
Section 8 - 50
Section 8 - 51
8.2.14
Gas leaks shall be located only with a gas detector, soap suds or
other safe means. If a gas leak is suspected or detected in any
confined area, all motors, engines and sources of ignition shall be
shut down immediately. DANGER: Leaks must never be located
with an open flame.
All building heating systems, offices, etc. are to be odorized ( Z66294)
The use of plastic pails or containers for flammable products are to
be avoided.
Barrels stored in buildings are to have bungs removed and capped.
All gas regulators are to be vented outside and their doors kept
closed.
NO SMOKING signs shall be permanently posted in all hazardous
areas.
Flammable liquids shall be disposed of in a proper manner. Sewer,
sump, or drain systems are not to be used for this purpose unless
the system is specifically designed for this use..
Iron sulphide or lead sludge shall be removed from vessels etc. as
quickly as practical and be kept wet with water until disposed of in a
pit or fill site.
Oils that cause sulphur deposits must be closely monitored at all
times.
Rags used to wipe zinc thread lubricant must be kept in a separate
covered metal container.
Static electricity shall be minimized or eliminated to prevent a spark
from causing a fire, explosion, or both.
Top fill lines on tanks should be avoided to reduce the chance of
static discharges. If unavoidable, a downpipe shall be installed near
the bottom of the tank and filling pipe bonded to the tank.
Only equipment approved by Underwriters Laboratories for
hazardous atmospheres are permitted for use in or around
flammable vapours. This shall include all power tools, flashlights,
electric lanterns etc.
Attach Ground Cable signs shall be posted at all truck loading /
unloading points.
Truckers shall not carry out repairs to electrical wiring systems while
engaged in loading or unloading fluids.
Section 8 - 52
Section 8 - 53
8.2.16 FLOWBACKS
SCOPE AND PURPOSE
To provide safe operating practices for equipment, procedures and
supervision of flowbacks from wells. This is intended to include all
situations of flow from wells, including circulating, swabbing, fracture and
chemical treatment cleanups, depressurizing, etc., but does not include
production testing or drill stem testing.
Reference: Alberta Industry Recommended Practice IRP Vol. 4,
Subsection 4.0.7.20
SAFE OPERATING PRACTICES
1. An open fluid handling system should only be used when sweet, nonflammable fluids are being pumping or flowed back from a well. Sour
and high-vapour pressure hydrocarbons must always be flowed back
into closed systems.
Section 8 - 54
Glycols
Amines
Demulsifiers
Corrosion inhibitors
Solvents
Fuel tanks
Methanol tanks and tanks that are less than 5 m3 do not normally require
any secondary containment unless they:
Section 8 - 55
Section 8 - 56
Section 8 - 57
Backfill
1. The line owner should inspect the crossings before and during burial.
Some other excellent sources of information and guidelines regarding
ground disturbances are:
a. Underground Facilities pamphlet published by the Alberta
Construction
b. Safety Association.
c. Safe Procedures for Pipelines and Utility Crossings booklet
published by the Edmonton Area Pipeline and Utility Operators
Committee.
2. Backfill inspection form must be completed.
Section 8 - 58
Section 8 - 59
8.2.22
HOT OILING
Field operations personnel shall follow the following procedure when hot
oiling equipment (wells, flowlines, etc,).
PROCEDURE
COMPLETE THE HOT WORK PERMIT
1. Whenever possible, rig up hot oiler upwind and 50 meters from well,
rig tanks, power lines, rig shacks, etc. (Note: if the hot oiler is equipped
with a flame arrestor the unit may be rigged up as close as 25 meters
from the well, etc.)
Many leases do not allow 50 meters distance from the wellhead.
Always try to maintain at least 25 meters from the wellhead.
When rigging up, ensure at the point of entry (wellhead, etc.) there is a
check valve with a bypass (for bleeding off) installed in the hot oilers
flowline.
Note: Hot oiling should only be done using the metal pipe supplied on
the hot oiler. The flexible, high pressure hose is only designed for cold
pressure work.
2. The hot oil unit must be grounded at all times and if accompanied by a
tank truck, it must be grounded to the hot oil unit before
unloading/loading and located at least 15 meters away ( down wind)
from the hot oil unit.
3. Ensure tank vapours are vented off down wind of the hot oil unit, This
can be done by connecting a section(s) of suction hose to the tank
vent.
4. Hold pre-job safety meeting.
Communicate clearly to the hot oil unit operator what work is required.
Maximum pressure, temperature and pump rate will be determined by
the equipment being hot oiled. (Type of scraper rods are nylon, plastic,
and metal. Pressure ratings of equipment.).
Do not exceed the manufacturers recommended temperature.
If H2S is present; define where all personnel are to proceed if a
catastrophic leak/failure occurs.
5. Pressure test the hot oilers lines to 1.5 times the anticipated
maximum working pressure. Ensure the maximum operating pressure
of the hot oilers lines are not exceeded and the pop valves have been
set accordingly.
Section 8 - 60
Section 8 - 61
EQUIPMENT ISOLATION
All equipment on which Hot Work is to be performed must be positively
isolated from all possible sources of combustible, explosive or toxic
material.
Positive isolation means blinding off, plugging or the complete removal
and blanking off of inter-connecting piping vessels or sewers which may
contain hazardous material.
PURGING AND GAS TESTING
No equipment, vessel, line or any type of container which has contained a
hazardous material shall be safe for Hot Work unless it has been purged,
gas tested and inspected. Steaming is an excellent way to remove
residual hydrocarbons.
HOT WORK PRECAUTIONS
1. All combustible materials within 7.5 meters of the Hot Work must be
suitably isolated or cleared from hot work location.
2. When welding is carried out for the purpose of hot tapping on a
pipeline, vessel or tank; the line shall be full of stock and have a
positive flow, or in the case of vessels and tanks, they shall be filled
with fluid at least one meter above the point at which welding is to be
carried out.
3. Oil surfaces and oil spills must be hosed down and sanded over
(minimum depth 1 inch). Oil soaked ground must be dug out and
removed.
4. Testing must show that the atmosphere does not contain a flammable
substance, in a mixture with air, in an amount exceeding 20 percent of
that substances lower explosive limit for gas or vapours or the
minimum ignitable concentration for dust.
5. All trash and oily rags must be removed.
6. Particular attention is required for the danger of expansion of oil or gas
in equipment (lines, vessels, etc.) immediately adjacent to the Hot
Work.
7. Flammable solvents must not be used or be present in the area of Hot
Work.
8. Fire blankets or appropriate fire retardant material shall be used when
there is a danger of sparks being carried outside the work area. Fire
blankets should be kept damp if spark impingement is intensive.
Section 8 - 62
8.2.25 HOUSEKEEPING
HARVARD shall ensure that healthy and safe working conditions are
provided and maintained for all employees. It is the responsibility for
employees to maintain these conditions through good housekeeping and
good personal hygiene practices. Good housekeeping is more then
cleanliness; it is cleanliness and order. Cultivate the habit of good
housekeeping.
Section 8 - 63
PRACTICES
All working areas shall be kept clean and free from obstructions at
all times. Tools, loose objects, oil, grease, and other materials are
tripping and slipping hazards.
Working areas shall be left clean and tidy at the end of each shift
and on completion of work assignments.
Materials shall not be stored in aisles or overhead.
Never place equipment and tools on stair treads.
Oil, paint, or chemically saturated rags must be placed in metal
containers with covers.
Rubbish must be placed in metal containers for waste disposal.
Pools of oil or water, acids or caustic, shall be cleaned up
immediately. If this is impractical, it should be reported your
supervisor and guarded by a standby until the condition is corrected.
Floor or ground openings shall be adequately barricaded.
Rags are to be used when cleaning up around compressors etc.
When purchasing rags, they should be of cotton base. Polyester
rags are NOT to be purchased.
All tools should be kept clean and in good repair at all times.
Section 8 - 64
Section 8 - 65
plug the line and trap pressure as well as dissolve and release
hydrocarbons and toxic gases under pressure.
3. Chemicals
a. Gas hydrates can be prevented or the hydrates dissolved by the
injection of methanol or glycol. Glycols are not recommended,
unless a specific circumstance dictates, particularly if the injection
point is upstream of any compressors.
b. When pumping of chemicals is to occur, the procedures on
portable pumping should be followed.
LOCKS
A person installing a lock has the only key that will operate that particular lock.
The supervisor may have an alternate key to be used in an emergency. Use
of the alternate key must be documented.
Have each worker or each trade or group of trade workers install their
own energy isolating device on the mechanical lock out clamp prior to
commencing work.
Locks must be removed by the person who installed it when they have
completed their work on the equipment.
Section 8 - 66
ISOLATION
Piping containing harmful substances under pressure must be able to be
isolated by blinding, blanking or by using double block and bleed valves
providing two blocking seals on either side of the isolation point and an
operable bleed-off between the two seals.
Blank, blind or double block and bleed the piping during repair,
modification, maintenance or replacement.
Where two valves and a bleed off are used to isolate the piping,
ensure that the bleed off valve is secured in the Open position and
the valves or similar blocking seals in the flow lines are functional and
secured in the Closed position. If it is not reasonably practicable to
provide blanking, blinding or double block and bleed isolation, an
employer must ensure that an alternate means of isolation provides
adequate protection to workers, certified as appropriate and safe by a
professional engineer, is implemented.
The device used to secure the valve or seals must have a positive
mechanical means of keeping the valves or seals in the required
position and is strong enough and designed to withstand inadvertent
opening without the use of excessive force, unusual measures, or
destructive techniques.
Work in confined or restricted spaces must be isolated from all
sources of contamination. This means that all lines to and from a
confined space must be blinded or blanked before work begins.
See applicable Provincial regulations (i.e. Alberta OH&S Code 2009) for
additional detailed information concerning the Control of Hazardous
Energy.
BULL PLUGS
Bull plugs must be installed in all open ended valves that, if accidentally
opened, could release a product that could create a hazard to personnel or
the environment.
PUMP JACKS
All oil well pump jack installations and dismantling must be supervised by
an experienced supervisor.
Section 8 - 67
All pump jacks are equipped with rotating weights that are needed to
counterbalance the weight of the rod string. A pump jack can start to
rotate on its own due to gravity. It is imperative to make it properly
secured by one of the following methods. The brake should not be used
as the only method for securing the jack.
a.
b.
c.
A chain threaded through the hole in the brake drum nearest the
trunnion and then around the trunnion, or,
If equipped, the brake pawl on the brake drum should be engaged,
or,
Use heavy timbers under the crank ends to stop downwards
movement. The brake must also be engaged.
Before starting up a jack pump, the crank guards and belt cover are to be
in place. If there is livestock present, the wellhead should also be
guarded.
All pump jack manufacturers supply manuals that give detailed instruction
for the safe installation and operation of pump jacks. When installing or
dismantling, it is the supervisors responsibility to be familiar with the
instructions in the appropriate manual. All production operators must be
familiar the operating instructions for the makes of pump jacks they
operate.
Section 8 - 68
Training workers in the proper use of PPE (disposable ear plugs, reuseable ear muffs, and/or custom-made ear plugs for noise-exposed
workers).
Section 8 - 69
Section 8 - 70
WORK PERMITS
An authorized HARVARD representative must be on site for all pumping
operations where a hazard exists for personnel or equipment. A work
permit must be issued for the job by HARVARD representative.
EQUIPMENT POSITIONING
1. The pumping equipment must be positioned a minimum of 25 meters
from the wellhead, tanks and any process equipment. The unit should
be positioned upwind and directed for quick exit. Refer to (Alberta) Oil
& Gas Conservation Regulations 8.090 and 8.100.
2. All fire equipment and safety equipment should be position for use. A
minimum of two 30 lb fire extinguishers must be on site.
3. The unit must be grounded to the equipment to be serviced.
PRE-JOB SAFETY MEETING
A pre-job safety meeting must be held and documented. The meeting
must cover; safety equipment and regulation checklist, a site-specific
procedure encompassing maximum testing and operating pressures, fluid
characteristics, maximum operating temperature, and equipment layout.
TIE-IN EQUIPMENT
1. The tie-in equipment must have a pressure rating sufficient for the
application and must include a check valve and isolated valve
upstream of the tie-in point.
2. Where the pressure is expected to exceed 1500 kPa, or hot or
corrosive fluids are to be pumped, all tie-in lines must be steel with
chick-sans. No flexible lines will be allowed. All lines must be securely
staked.
RETURN LINES
1. Where return lines are used, the specifications for tie-in lines will
apply. Where the return fluids are hot or contain flammable gases, the
returns must be made to a vented tank located 25 meters away from
any ignition sources or equipment. The vent line must be of sufficient
size to handle the quantity of vented gas, and terminated downwind
no less than 25 meters for any ignition source or equipment.
2. All lines must be pressure tested to 1.5 times maximum working
pressure. The maximum working pressure must not exceed the
allowable working pressure of the equipment to be serviced.
3. The working temperature must not exceed 80% of the flash
temperature of the fluids.
Section 8 - 71
4. While hot fluids are being pumped, attention should be paid to the
effect of metal or fluid expansion.
5. Reference Industry Recommend Practice for Well Testing and Fluid
Handling IRP Vol 4, Subsection 4.0.7.20.
8.2.32 PURGING
Purging is the practice of displacing the existing gas and/or fluid in a
vessel, container or piping system with another gas and/or fluid. Purging is
often used to remove toxic or explosive/flammable fluids and gases from a
system before opening the system to atmosphere or prior to shipment of
equipment. Alternately, before equipment start-up, air may be purged from
equipment in preparation for it being put back into service.
A site-specific purging procedure must be developed for any purging
operation other than routine operations covered by the Task Competency
Manual or other documented standard procedures. The site-specific
procedure must identify the hazards associated with the task and the
control methods utilized to address those hazards.
POSSIBLE PURGING MEDIUMS
Consideration should be given to the use of an inert purge medium.
However, it is recognized that it is not always practical to use an inert
purge medium for all operations. Flammable purge mediums can be
successfully used as long as special precautions and procedures are
used. Depending on the application, commonly used purge mediums are
listed below. Each of these has advantages and disadvantages.
INERT GASES (N2, CO2)
Section 8 - 72
WATER
STEAM
AIR
Section 8 - 73
GENERAL PRECAUTIONS
Regardless of the purge medium used, each presents its own hazards.
Hazards must be assessed and appropriate steps taken.
Depending on the task to be completed, and the purge medium used,
some general precautions include:
Pre-job safety meetings should be conducted whenever nonroutine purging operations take place.
Exhaust gases can be used to test for O2 content, LEL, and
toxicity.
When purging hydrocarbon with air or air with hydrocarbon,
introduce the purge gas slowly. This will help prevent the build up
of static and/or potentially causing any loose debris to tumble
through a pipe or vessel and causing a spark.
Purging should be done as near to atmospheric pressure as
possible, as increased pressure changes the explosive limits and
lowers the ignition temperature.
Individuals involved in purging operations, as a minimum, must
wear the proper personal protective equipment as outlined in this
Handbook.
All elements of the system being purged must be electrically
bonded and grounded.
Section 8 - 74
anchors installed and guy lines secured before operation of the rig is
commenced.
PROCEDURE
1.
2.
3.
4.
Section 8 - 75
Section 8 - 76
Permit Responsibilities
Permits issued where more than one department is involved, should be
issued to the senior person who will be involved from the start to finish of
the task at hand. He/she will be responsible for ensuring proper
communication and that safe work practices are followed. More than one
permit may be required depending on the scope of the job.
Displaying Permits
A copy of an active permit is to be displayed in a conspicuous place. If this
is not practical, it must be readily producible by the permit holder. A Safe
Work Permit is valid for one working day, but if conditions are unchanged
and communication occurs between the two concerned parties, an
extension on the permit may be given. On each copy of the permit, the
new date and/or times must be clearly indicated and initiated. No expired
permits are to be displayed. When the work has been completed, permits
are to be signed off and returned to the originator. If work is incomplete, it
should be noted on the permit when returned. Work permits will be kept
on file for a period of two years.
Blanket Work Permits
A blanket work permit is a special permit that may be issued for an
extended period of time (up to one year). It is intended to be issued for
tasks carried out on an on-going basis by contractors (e.g. field hauling of
fluids) where specific procedural guidelines have been established and
agreed to by the contractor.
Work Clearances
A Clearance may only be issued when Complete control of a site is to
be turned over to a worker. A Work Clearance may be issued for the total
period of time that is required to complete the tasks at that site. The
worker receiving the Clearance is responsible for issuing any Safe Work
Permits at the affected site as may be required by the Code of Practice or
the applicable government regulations. After the work covered under the
Work Clearance has been completed, the clearance must be signed off
and returned to the issuer.
Section 8 - 77
be
maintained
as
per
Section 8 - 78
8.2.38 TRENCHING
Precautions
NO worker shall enter a trench with a depth of more than:
Alberta
British Columbia
Saskatchewan
Manitoba
1.50 metres
1.22 metres
1.22 metres
1.80 metres
Cutting back
Shoring
Or a combination of both of the above
Section 8 - 79
Section 8 - 80
Section 8 - 81
Understanding the basics of animal life will assist workers to remain safe
and protected from animals. One of the primary ways to protect yourself
from bears is avoidance. If you suspect that bears are within your work
area, it is best to leave the area. Scan the horizon on a regular basis so
you dont suddenly encounter a bear. If you sight a bear, report the
sighting immediately to your supervisor.
BEAR SAFETY
Make noise
Keep food and garbage tripled sealed
Learn to identify bear signs like hair on trees, droppings, and paw
prints
Take note of working in areas of berry bushes and water holes
Do not use a walkman or stereo- must be able to hear all sounds
Carry a bear-scare device
Other Wildlife concerns; cougar, moose, wolf, fox, coyotes, caribou,
deer, ungulates, livestock, dogs, buffalo, etc.
GRIZZLY BEARS
Grizzly bears graze on:
Grizzly bears den from September to October and emerge March to May.
Dens are generally excavated in the ground and are composed of a tunnel
and nest chamber. Often dens can be found along in streams and
riverbanks, in sand dunes, along hillside and on mounds. The dens are
usually made for one season and then collapse.
General wildlife awareness is a component of this orientation standard.
However, changes in location, seasons and habitat may require expanded
wildlife orientation and or training. Site specific orientations are an
excellent opportunity to review worker knowledge as well as recent wildlife
sightings and behavior.
Section 8 - 82
Section 8 - 83
1.0 m
1.0 m
3.0 m
3.5 m
4.0 m
5.0 m
7.0 m
Section 8 - 84
Section 8 - 85
SECTION 8 FORMS
Figure 1: Check-in Procedure Worksheet
Figure 2: Working Alone Check-in Procedure
Fire and Explosion Prevention Plan Form
Fire Tetrahedron
Fall Protection Plan Form
Section 8 - 86
Date: ____________________
1)
2)
3)
4)
5)
Outline procedures for emergency response, including any sitespecific assistance contacts and their phone numbers.
Section 8 - 87
Working Alone
Task / Area
Check-in
Procedure
Date: ______________________
Emergency
Response Actions
Documentation
Section 8 - 88
Issued by:
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
CRITICAL RISK FACTORS:
FUELS
YES
YES
YES
YES
YES
YES
NO
NO
NO
NO
NO
NO
YES
YES
YES
YES
YES
YES
NO
NO
NO
NO
NO
NO
YES
YES
YES
YES
YES
YES
NO
NO
NO
NO
NO
NO
Fire and Explosion controls (Actions taken to prevent the completion of The Fire Triangle.)
Have the safety meeting and all applicable permits been completed?
YES
Have all the deficiencies identified in the inspection been rectified?
YES
NO
NO
LIQUID HYDROCARBONS
HYDRO CARBON VAPOURS
HYDROCARBON GASES
HYDROGEN SULPHIDE
HYDROCARBON-BASED WORKOVER FLUID
FLAMMABLE AND EXPLOSIVE CHEMICALS
IGNITION / ENERGY
OPEN FLAME SOURCE
HOT WORK
VEHICLES IN CLOSE PROXIMITY
ELECTRICAL EQUIPMENT
STATIC, FRICTION OR MECHANICAL SPARKS
PYROPHORS (ie: iron sulphide)
OXYGEN
PLANNED AIR INTRODUCTION (ie:purging)
UNDERBALANCED OPERATIONS
VACUUM CREATING OPERATIONS (ie: swabbing)
POCKETS FROM SERVICING OR INSTALLATION OF EQUIPMENT
OXIDIZERS OR CHEMICAL REACTIONS
WEATHERED HYDROCARBONS
YES
NO
___________________________________________________________
Initial
_____
Comments:____________________________________________________________________
Worksite Supervisors Name
Signature
OXYGEN SOURCES or
OXIDIZERS
Open Flames
Hot Work
Vehicles and Other Running
Engines
Electrical Equipment
Static, Friction or Mechanical
Sparks
Pyrophors (ie: Iron Sulphide)
Chemical Reactions and Sparks
Spontaneous Combustion
Sudden Decompression
Compression Ignition
Catalytic Reactions
GASES
Natural Gas
Hydrogen Sulphide
LPG Gases (ie:
propane, butane,
pentane.)
Other Ignitable
Gases.
Chemical
Chain
Reaction
LIQUIDS/VAPOURS
Crude Oil
Condensate
NGL Liquids
Gasoline, Diesel and
Other Fuels
Methane
CHEMICALS
SOLIDS
Lubricants
Sealants
Packings, O Rings,
Diaphragms and
Valve Seats
Paints and Coatings
9.0
TRAINING
9.1
OVERVIEW
Occupational health and safety regulations require that every employer ensure the
adequate direction and instruction of workers in the safe performance of their
duties. Every supervisor is responsible for the proper instruction of the workers
under his direction and control, and for ensuring the work is performed without
undue risk.
HARVARD recognizes that it is important for employees to be familiar both with
safety concerns and with technological advancements being made in our industry.
Employee participation in external and internal training programs is encouraged.
Some of this training is provided through orientations and on-the-job training, while
other training is provided through formal courses. HARVARD has established a
minimum standard that includes a number of core (required) safety courses that
must be completed by all staff at field locations as well as standards for those
headquartered in Calgary and temporarily working at field site locations.
The following outlines all training requirements.
9.1.1
9.1.2
On-The-Job Training
Begin in first days:
General Operations
o
Housekeeping
Safety Precautions
o
o
o
Hazards
Equipment
Procedures
Section 9 - 1
9.1.3
Safety Training
Personnel must have the appropriate training certification pertaining to
potential hazards in the workplace. These may include:
9.1.4
H2S Alive
Defensive Driving
First Aid/CPR
WHMIS
TDG
Fire Extinguisher Training
Supervisory Training
Those employees that are, or have potential for supervisory positions, shall
receive appropriate training.
9.1.5
Section 9 - 2
9.2
SAFETY ORIENTATION
Every worker and contractor who is new to a work site must receive an orientation
to the site. This orientation is an introduction to critical aspects of HARVARD 's
Health, Safety and Environment Program. It provides immediate information that
workers need to know and includes a review of Company policies and other
practices in the Health, Safety and Environment Handbook. A Handbook Review
Questionnaire and Answer Key are available to confirm that employees
understand the contents of the handbook. The employee is required to familiarize
themselves with the contents and then sign the acknowledgement form located on
the back page and turn it in to their supervisor. Individuals will then be issued a
HARVARD Safety Orientation hardhat sticker. The signed acknowledgement
forms and a copy of the questionnaire are to be filed at the applicable field offices.
As part of the orientation, core safety training requirements should be determined
and scheduled as soon as possible.
Following this, a site walk-through is given, highlighting locations of personal
protective and emergency equipment. Company safety procedures are discussed
and personal protective equipment is issued (i.e. coveralls, prescription safety
glasses, hard hats, etc.).
9.3
ON-THE-JOB TRAINING
After the initial orientation, employees receive regular on-the-job training. On-the-job
training is a hands-on explanation and demonstration of how to do the job(s) to
which the worker will be assigned. In addition, on-the-job training allows
supervisors to refresh their workers previous training by repeating information
learned earlier. All workers that are new to a job or work site should receive on-thejob training. It should be conducted when work procedures are changed or when
reviewing safety requirements.
An example for developing on-the-job training is provided in this section.
9.4
Additional optional and non-optional courses are suggested in Section 9.1 and may be
completed by employees as they move through their training program. These must be initially
approved by the Area Supervisor:
Note: Well Servicing BOP Training
For pump changes, etc. where it is not necessary to mount a BOP or move the
tubing string, HARVARD supervisor does not require the Well Servicing Blowout
Prevention certificate if at least one member of the rig crew on location at all times
has the required certificate. However, if a job requires that the tubing be moved and
the BOPs be utilized, then HARVARD supervisor must have the Well Servicing
Blowout Prevention Certification regardless of the certification of the rig crew
members.
Section 9 - 3
9.5
TECHNICAL TRAINING
9.6
SUPERVISORY TRAINING
Supervisors receive training in overseeing and managing technical work, including pertinent
procedures and components of safety programs. Employees having potential to become
supervisors may be identified and enrolled in supervisory training.
9.7
TRAINING RECORDS
The majority of safety courses are valid for a three (3) year period. It is the operations
managers responsibility to ensure training is kept up-to-date and adequate training records are
maintained. Certification must be maintained in the course that has an expiry date.
Section 9 - 4
SECTION 9 FORMS
Checklist for Developing an On-the-Job Training Program
HSE Handbook Review Questionnaire
HSE Handbook Review Questionnaire Answer Key
Section 9 - 5
Page1 of 1
Date:
Company:
HARVARD is committed to protecting the health and safety of all workers on our sites. Part of
this commitment is the expectation that all workers be familiar with and follow standard
guidelines and procedures. The initial step to accomplish this is an orientation to our Health,
Safety & Environment Handbook. This review checklist is intended to ensure that workers have
the basic knowledge associated with the HS&E handbook.
Complete the following questions by either circling the correct answer or filling in the blank(s) if
answers are not provided. It is acceptable to use the handbook to find the answers. Return the
review checklist to your supervisor or HARVARD Representative.
POLICY ON HEALTH, SAFETY & THE ENVIRONMENT
1) Who is responsible for protecting the health and safety of people and preserving the quality
of the environment:
a)
b)
c)
d)
employees
management
contractors
everyone
carry on as usual
refuse to perform the task
be extra careful as you carry out the assigned task
ask someone else to do the job for you
3) What must you do if you refuse to perform a task because there is imminent danger:
a)
b)
c)
d)
Page 1 of 6
EMERGENCIES
4) Local emergency phone numbers must
a)
b)
c)
d)
communication device
siren
flashing light
high ground clearance to be able to get off the lease
8) Smoking is permitted:
a)
b)
c)
d)
9) You are not permitted to do which of the following at an HARVARD work site:
a)
b)
c)
d)
Page 2 of 6
CONTRACTOR REQUIREMENTS
10) It is the Contractors responsibility to:
a)
b)
c)
d)
provide all tools, safety equipment, proper clothing for their workers
enforce all policies and procedures outlined in the HSE handbook
take steps necessary to ensure the safety of your employees and sub-contractors
all of the above
ensure that appropriate first aid supplies and services are on site
determine if an ambulance is required and where it is to be positioned
ensure that workers are aware of the location of all first aid supplies
all of the above
13) At work sites where there is a possibility for hydrocarbon release, clothing requirements
include:
a)
b)
c)
d)
HAZARDS
14) When lighting fired heaters and furnaces, face shields and gloves must be worn:
a) true
b) false
Page 3 of 6
16) Prior to any work being done in an area containing a flammable substance, testing may be
necessary:
a) true
b) false
H2S monitoring equipment is turned on and used at all times while on location
communication equipment is in good working order
a breathing apparatus in working order and with an adequate supply of air must be available
all of the Above
19) What is the maximum acceptable noise level on a worksite over an eight hour work period?
a) 80 dBA
b) 90 dBA
c) 75 dBA
d) 85 dBA
20) A written fall protection plan must be in place before work commences on a task where
there is a potential of a fall of more than:
a) metre
b) 10 metres
c) 20 metres
d) 3 metres
22) Employers should hold regular safety meetings at least once a month for the following
purposes:
a)
b)
c)
d)
Page 4 of 6
23) Before beginning any work at a HARVARD location, you must determine if a work permit
or work clearance is required.
a) true
b) false
a permit that is used for ongoing tasks where specific guidelines have been established
a permit that is issued for a maximum of one year
a permit that requires specialized blankets to keep the workers protected from the cold
both a & b
ENVIRONMENT
26) Only supervisors are responsible for meeting regulations and industry guidelines:
a) true
b) false
27) We must all take necessary steps to prevent spills and control emissions:
a) true
b) false
SOUR SERVICE
28) A facility is considered sour at:
a) 1 PPM H2S or greater
b) 10 PPM H2S or greater
c) 100 PPM H2S or greater
d) 1000 PPM H2S or greater
wildlife sightings
unsafe acts and/or conditions
incidents and infractions
b and c
Page 5 of 6
GOOD HOUSEKEEPING
31) Good housekeeping is:
a) only a minor issue
b) good to do when you have the time
c) mandatory
WHMIS/TDG
32) Before handling chemicals you should:
a)
b)
c)
d)
DRIVING CONDUCT
33) In general all ATV (All Terrain Vehicle) riders must
a)
b)
c)
d)
34) Driving incident are the leading cause of injury, fatalities and property damage in the oil and gas
industry.
a) true
b) false
Page 6 of 6
ANSWER KEY
HS & E HANDBOOK REVIEW QUESTIONNAIRE
ANSWER KEY
Date:
Company:
HARVARD is committed to protecting the health and safety of all workers on our sites. Part of
this commitment is the expectation that all workers be familiar with and follow standard
guidelines and procedures. The initial step to accomplish this is an orientation to our Health,
Safety & Environment Handbook. This review checklist is intended to ensure that workers have
the basic knowledge associated with the HS&E handbook.
Complete the following questions by either circling the correct answer or filling in the blank(s) if
answers are not provided. It is acceptable to use the handbook to find the answers. Return the
review checklist to your supervisor or HARVARD Representative.
POLICY ON HEALTH, SAFETY & THE ENVIRONMENT
1) Who is responsible for protecting the health and safety of people and preserving the quality
of the environment:
a) employees
b) management
c) contractors
d) everyone
carry on as usual
refuse to perform the task
be extra careful as you carry out the assigned task
ask someone else to do the job for you
3) What must you do if you refuse to perform a task because there is imminent danger:
a) leave the site immediately
b) go have coffee
c) notify the supervisor of your reasons
d) reconsider and carry on with the task
Page 1 of 6
EMERGENCIES
4) Local emergency phone numbers must
a) not be worried about
b) be confirmed and posted
c) be memorized
d) all of the above
8) Smoking is permitted:
a) in designated areas only
b) where ever you want
c) outside of buildings only
d) beside vehicles only
9) You are not permitted to do which of the following at a HARVARD work site:
a) to be under the influence of or in possession of drugs or alcohol
b) to engage in practical jokes
c) to harass other workers because of their race, sex, age or religion.
d) all of the above
Page 2 of 6
CONTRACTOR REQUIREMENTS
10) It is the Contractors responsibility to:
a) provide all tools, safety equipment, proper clothing for their workers
b) enforce all policies and procedures outlined in the HSE handbook
c) take steps necessary to ensure the safety of your employees and sub-contractors
d) all of the above
13) At work sites where there is a possibility for hydrocarbon release, clothing requirements
include:
a) fire retardant clothing as the outside layer
b) natural fiber clothing such as wool or cotton as inner wear
c) nylon outerwear
d) both a & b
HAZARDS
14) When lighting fired heaters and furnaces, face shields and gloves are to worn:
a) true
b) false
Page 3 of 6
16) Prior to any work being done in an area containing a flammable substance testing may be
necessary:
a) true
b) false
19) What is the maximum acceptable noise level on a worksite over an eight hour work period?
a) 80 dBA
b) 90 dBA
c) 75 dBA
d) 85 dBA
20) A written fall protection plan must be in place before work commences on a task where
there is a potential of a fall of more than:
a) metre
b) 10 metres
c) 20 metres
d) 3 metres
22) Employers should hold regular safety meetings at least once a month for the following
purposes:
a) to report current accidents or diseases, their causes and prevention
b) to see whose been slacking off on the work sites
c) to determine if there are any matters pertinent to health and safety
d) both a & c
Page 4 of 6
23) Before beginning any work at a HARVARD location you must determine if a work permit
or work clearance is required.
a) true
b) false
ENVIRONMENT
26) Only Supervisors are responsible for meeting regulations and industry guidelines:
a) true
b) false
27) We must all take necessary steps to prevent spills and control emissions:
a) true
b) false
SOUR SERVICE
28) A facility is considered sour at:
a) 1 PPM H2S or greater
Page 5 of 6
GOOD HOUSEKEEPING
31) Good housekeeping is:
a) only a minor issue
b) good to do when you have the time
c) mandatory
WHMIS/TDG
32) Before handling chemicals you should:
a) review the MSDS sheet
b) carefully breathe in the vapours to see if they are harmful
c) make sure no one else is in the area
d) move the chemicals outside
DRIVING CONDUCT
33) In general all ATV (All Terrain Vehicle) riders must
a) be competent in their ability to operate an ATV
b) drive the ATV in accordance with local regulations
c) possess a valid drivers license for insurance purposes
d) all of the above
34) Driving incidents are the leading cause of injury, fatalities and property damage in the oil and gas
industry:
a) true
b) false
Page 6 of 6
10.2 SELECTION
HARVARD as Prime Contractor, will give serious consideration to past safety performance and
membership in industry associations when selecting its contractors. All other factors being
equal, a contractor with a better safety record, or one taking significant measures to improve its
record, should be awarded contract work over others. All HARVARD documents and contracts
should contain a section on safety, detailing HARVARDs contractors and sub-contractors
safety specifications, requirements and guidelines.
10.3 CONTROL
On the job site, reporting to HARVARD will provide leadership in safe work practices and
ensure that all parties involved are knowledgeable of potential hazards and safety
expectations. This requires that adequate communication be established between the Calgary
office, the field office and contract personnel.
10.4 FOLLOW-UP
Steps should be taken to verify that the contractor is implementing sound safety practices as
required by their own safety programs, HARVARD guidelines and occupational health and
safety regulations. Follow-up on any deficiencies noted, or recommendations made, should
take place. Upon the completion of a contract, safety considerations should be taken into
account in the evaluation of the contractors overall performance.
The criteria used in the selection, control and follow-up of contractors may vary slightly
depending on the nature of the contract work. The following checklist provides suggestions for
the kinds of activities that will help HARVARD utilize contractors in a safe and efficient manner.
Section 10 - 1
SECTION 10 FORMS
Contractor Safety Evaluation
Section 10 - 2
Date:
INSURANCE
Yes
No
Yes
No
A. Certificate of Insurance
B. $2 million minimum general commercial liability insurance
C. $2 million minimum automotive liability insurance
D. Worker's Compensation coverage
SAFETY PROGRAM
A. Has the contractor submitted a current safety program manual?
B. Does the program meet the criteria of the base safety program?
ACCIDENT HISTORY
A. Workers Compensation:
WCB Number:
Statement Date:
Employer Rate:
Industry Rate:
Statement Date:
Employer Lost Time Rate:
Industry Lost Time Rate:
DESCRIPTION
DESCRIPTION
Page 1of 1
b.
c.
d.
e.
Section 11 - 1
See also Noise Exposure in Section 8.2.29 of this manual and the handbook.
Section 11 - 2
11.3.4 Benzene
Benzene is carcinogen. Exposure to high concentrations may lead to
symptoms ranging from headaches to irritability to death. It is present in crude
oil and natural gas condensate. The concentrations depend on characteristics
of the well. Workplace exposure assessments are required to determine if
benzene is a hazard requiring implementation of control measures. Workers
may need to protect themselves from exposure by inhalation, ingestion and
skin contact. Occupational exposure levels for Alberta are 0.5 ppm.
Reference can also be made to CAPPs publication Managing Human
Exposure to Benzene in the Upstream Oil & Gas Industry. As well as the
developed code of practice on benzene in this manual 8.1.2.
Section 11 - 3
Section 11 - 4
11.4.9
Section 11 - 5
ADMINISTRATION
HARVARD or HARVARDs designated Field Supervisors are responsible for
ensuring that all work activities are carried out in accordance with the
requirements of this policy. Failure to comply with this standard will result in
disciplinary action being taken.
Clothing must be in conformance with HARVARD policy.
Section 11 - 6
Section 11 - 7
Ensure that supervisors safety responsibilities are clearly established and monitored.
Ensure key hazards are identified, documented and communicated in project planning
and field work.
Provide visible management support for work of supervisors with respect to safety.
Guiding Principles
Both HARVARD and its contractors have a responsibility for protecting all workers
within the oil and gas industry. Five petroleum industry associations, representing both
contractors and operating companies, have established a set of guiding principles and
has them posted at worksites. HARVARD supports these guiding principles and has
them posted at worksites.
Safety Responsibilities
The general safety and loss control responsibilities required to implement HARVARD
Safety Program are identified in this manual. Management and supervisors at all levels
are responsible for ensuring that specific responsibilities are identified and
communicated effectively to all employees and contractors. These responsibilities are
used to set standards for performance evaluation.
Section 12 - 1
General Communication
Company management will provide and assume a leadership role in the promotion of
safety through policies, guidelines, loss control meetings, monthly reports, and other
communications. In addition, a Safety and Environment Review Committee is
established to provide guidance and support to HARVARDs Safety Program.
Management will conduct walk-arounds on work sites to observe operations and talk to
employees about safety concerns. Employees should present any safety concerns to
management during these walk-arounds.
Section 12 - 2
SECTION 12 FORMS
Health, Safety and Environment Management Review
Section 12 - 3
Note: If unsatisfactory is selected, an explanation must be provided in the Comments section. The contractor is
responsible to ensure that all deficiencies in this inspection are corrected.
Management Involvement
Comments:___________________________________________________________________________________________
Records Management and documentation
1. Is all critical data for operation and environmental concerns stored onsite and updated?
Comments: _________________________________________________________________________________________
Quality Management
Comments: _________________________________________________________________________________________
Communication
1. Is the permit system being used? (ie:safe work permits, hot work permits)
2. Are Loss Control Meetings taken place in a timely manner?
3. Are Risk Management and OH&S bulletins posted and discussed?
Comments: _________________________________________________________________________________________
Emergency Response Planning
Comments: _________________________________________________________________________________________
Hazard Identification Control
1. Are Equipment and vehicles inspected and at what frequency? (Show examples and completed documentation.)
2. Is there a system for hazard assessment, reporting and follow-up (written or verbal)?
Comments: _________________________________________________________________________________________
Page 1 of 3
1. Are there procedures for high risk or critical work? Are they available and used?
2. Are there written emergency plans available and communicated to personnel at the work site?
i) ERP
Comments: _________________________________________________________________________________________
Incident Reporting
1. Do you have an incident reporting process?
2. Do you have a near miss/incident reporting form that includes follow-up?
3. Are incidents reported and was the problem rectified the previous near miss or accident, and were management
Comments: _________________________________________________________________________________________
Training
1. Have you received a safety orientation? (What and When)
2. How often are Loss Control meetings held? (Show examples and documentation)
3. Is the appropriate training in place?
4. First Aid Training
5. H2S Training
6. WHMIS Training
7. TDG Training
8. Fire Extinguisher or Fire Fighting Training
9. Job Specific Training/Certification
Personal Protective Equipment
1. Is the appropriate PPE available and being used?
2. Hard Hat
3. Safety Glasses or Eye Protection
4. Footwear
5. Protective Clothing
6. Hearing Protection
7. Respiratory Protection (For the Nature of the Hazard)
8. Personal Monitor or H2S Detector
9. Communication Equipment
N/A
N/A
Comments: ________________________________________________________________________________________
Safety Equipment
1. Is the appropriate Safety Equipment available and being used?
2. Fire Fighting Equipment (ie: inspected, tagged, accessible and condition)
3. Rotating Equipment Guards
4. First Aid Kit
5. Fall Arrest Equipment (including ladders, steps or stairways, safety belts and lanyards)
6. Bonding and Grounding Equipment
7. Emergency Shut Down and Alarm Systems (including diesel positive air shutoffs and backup alarms)
N/A
Comments: __________________________________________________________________________________________
Page 2 of 3
Contractors
N/A
1. Is the contractor aware of the safety expectations and standards of the Corporation?
Comments: __________________________________________________________________________________________
Environmental, Storage and Handling
1.
2. D-58 Compliance (Proper waste storage, ie: filters, contaminated soil and fluid. Show waste manifests.)
3. D-55 Compliance (ie: double walled tanks, tank condition, secondary containment.)
Comments____________________________________________________________________________________________
NO
PHOTOCOPY DISTRIBUTION:
Page 3 of 3
Provided in Section 13.4 is a list of key records that should be kept, and some indication of how
long, for each element of the Safety Program.
Section 13 - 1
British Columbia
1.
2.
3.
4.
5.
6.
7.
Manitoba
1.
2.
3.
4.
Saskatchewan
1.
2.
3.
4.
5.
Federal
1. Transportation of Dangerous Goods Act and Regulations
2. Canadian Standards Association regulations (ie: Z-731, Z-622)
3. Canadian Environmental Protection Act
Section 13 - 2
2.
COMMENTS
Permanent file.
3.
4.
ENVIRONMENT
Incident Reports and Spill Clean-up Records
Section 13 - 3
5.
WORK PROCEDURES
Site Specific Work Procedures and
Codes of Practice
b. Contractor Evaluations
8.
9.
TRAINING
a. Safety Orientation
b. On-the-Job Training
c. Non-certifiable Safety Training
(Fire Fighting, WHMIS, ERP Training)
6.
7.
CONTRACTOR OPERATIONS
Section 13 - 4
10.
11.
MANAGEMENT COMMUNICATION
AND PROGRAM AUDITING
a. Safety Audit Reports
Section 13 - 5
The following programs have been developed by HARVARD to help manage environmental
issues.
Section 14 - 1
DRILLING WASTE
Wastes generated from drilling operations at the lease are divided into non-sump wastes and
sump wastes. The following regulatory directives govern the management of these two types of
waste:
The focus of D-50 and D-58 is to place responsibility for waste on the generator. Once a waste
has been generated the generator is responsible for the waste from cradle to grave. Properly
characterizing, tracking and disposing of waste will demonstrate compliance of HARVARD 'S
Waste Management System with these regulatory initiatives.
Properly managed sump waste includes:
Copies of all submissions are to be forwarded to the Calgary Office. Submitting forms for the
Drilling Waste Database to HARVARD office will allow HARVARD to demonstrate compliance
and ensure wastes are tracked.
The management of non-sump wastes includes:
Completing a manifest or tracking form occurs only when waste is sent off a lease for disposal
or treatment. This form does not need to be completed when transferring waste from one drill
site to another. For additional information regarding non-sump waste, reference the Waste
Management Manual for drilling. For additional information or assistance contact the Calgary
Office directly.
PRODUCTION WASTES
Under the AEPEA, the Waste Control Regulation (AR 192-96) provides for management and
disposal of Hazardous Wastes in Alberta. Oilfield wastes are exempt from this Act and the
Regulation. Instead they are regulated by ERCB rather then by Alberta Environment. Within the
upstream petroleum industry, wastes that would be considered hazardous wastes are termed
dangerous oilfield wastes.
In British Columbia, special wastes are classified in a similar way to hazardous wastes in
Alberta, with a few exceptions. The following are the two most significant exceptions:
There is no exemption for wastes produced by the oil and gas industry.
Any wastes containing greater than 3% oil by weight are classified as special
wastes.
OPX Consulting Inc.
Section 14 - 2
Once the waste has been classified, the generator can then decide on the best method of
treatment and disposal. Handling and shipping must be done in accordance with TDG
Regulations.
OPX Consulting Inc.
Section 14 - 3
Dangerous oilfield wastes are regulated for the transportation by the Transportation of
Dangerous Goods Act and also require an Alberta Waste Manifest for disposal.
WASTE MANIFESTING
Records must be kept of wastes destined for treatment, transportation and disposal. Refer to
Directive 58-Oilfiield Waste Management Requirements for the Upstream Petroleum Industry.
A manifest is a document that must accompany dangerous oilfield wastes when they are
transported. Most upstream petroleum industry wastes will be classified as Dangerous Goods
due to flammable or corrosive properties and will therefore be required to meet the manifest
requirements of the TDG Regulations.
14.3
14.3.1
ENVIRONMENTAL IMPACTS
Section 14 - 4
14.3.2
Changing regulations are shifting the emphasis to companies policing their own
activities. As a result, the requirements for monitoring, communicating and reporting
environmental activities and performance is increasing. NOW is the time to begin to
build working relationships with government agencies and residents NOT when there is
a problem. Regular contact with local government agencies to clarify expectations and
improve environmental performance is important.
Remember too, the public and other stakeholders have a legal right to be informed. It is
important to let our neighbours know about and contribute to matters that affect the
environment, their lives, families and communities. Neighborly communication is good
business and the benefits far exceed that of addressing any specific problem.
14.3.3
The programs outlined above are a key part of the overall environmental management
system our Company is expected to develop to deal with specific issues. All programs
should outline standards and guidelines for consistent Company wide environmental
performance including:
1. Identify key environmental issues and the strategy for dealing with these issues.
2. Identify the responsibilities for achieving environmental objectives and targets.
3. The means and time frame by which they are to be achieved.
To ensure the effectiveness of our environmental efforts, a program of audits and
assessments will be maintained to monitor the impact of our activities and our
compliance with relevant environmental regulations.
Section 14 - 5
14.4
Procedures
14.4.1 ENVIRONMENTAL PROTECTION Drilling Waste
Management
PURPOSE
Effective drilling waste management minimizes environmental impacts form
drilling operations and drilling waste disposal.
BACKGROUND
Drilling rigs and service rigs have the potential to contaminate soil or
groundwater by spilling chemicals or drilling mud.
CONSIDERATIONS
The Directive 50 Drilling Waste Management describes methods for drilling
waste management disposal and IL 2001-03 Management of Drilling Wastes
Associated with Advanced Gel Chemical Systems.
LANDSPREADING
Landspreading is a disposal method in which waste is spread over a
predetermined land area based on an acceptable loading rate, and is
incorporated into the soil. Landspreading is usually done on the drilling lease.
Its goal is to dispose of waste in a manner that preserves the soils chemical,
biological and physical properties and protects the quality of surface water
and groundwater.
Typical methods for landspreading are:
Section 14 - 6
MIX-BURY-COVER
Mix-bury-cover (MBC) is a disposal method whereby sump solids (and
sometimes liquids or the total waste) are stabilized and diluted by mixing with
subsoil. The ratio of soil to waste is at least three parts soil to one part waste.
The soil/waste mixture is then placed into the original sump or other PITS
where the base of the final soil/waste mixture is at least 1m above the water
table or a layer of impermeable material and is covered with at least 1m of
clean subsoil, and then with the original surface soil.
The goal of MBC is to incorporate waste, (meeting the required criteria) into
the soil below the major rooting zone and above the water table in a manner
that preserves soil chemical properties and protects groundwater quality.
Typical MBC methods are:
Mixing waste and soil on the surface, putting the mixture back in the
sump and covering.
Mixing waste and soil, putting the mixture into a new pit and covering.
Bailing the waste onto the surface, mixing with the soil, and burying
when filling a cut.
Section 14 - 7
Gypsum Water
Any other mud systems proposed for LWD must be proven to the appropriate
regulatory office by a Microtox bioassay.
Fluids recovered from drill stem tests and cement returns must be isolated
from the drilling wastes and may not be disposed of by LWD. Cement returns
may be buried under 1m of clean fill. Drill stem test fluids must be conserved
or disposed by the other disposal methods.
LANDFARMING
Landfarming is a waste treatment/disposal method whereby a single
application (or multiple applications from one waste source) of biodegradable
waste is made on a dedicated parcel of land. The land is managed in a
manner which allows the soil system to degrade, transform and assimilate the
waste constituents. The landfarming site may be used only once.
The goal of landfarming is to biodegrade the organic constituents in a waste
using natural soil processes in a manner that protects soils and groundwater
quality. Elevated oil contents may arise when hydrocarbon based systems are
used or drilling conditions result in the unforeseen production of
hydrocarbons.
Landfarming may be used for wastes where landspreading or MBC oil criteria
cannot be met. Wastes that require landfarming may have high salt contents,
thus management practices must deal with both the salt and the organic
constituents.
Section 14 - 8
Testing Requirements
Sampling and Analysis
Calculation of Spreading Rates
Disposal Criteria
Notification
RELEASE PREVENTION
Inspect service rigs for leaks at valves, fittings, pumps, tanks, etc.
Provide adequate containment for all fluids, including those that can
be produced from the formation.
Do not dump the contents of rig or other tanks on-site.
Prevent all wash fluids from spilling on the ground.
MISCELLANEOUS
REFERENCES:
ERCB
ID
ID
81-01
90-01
ID
IL
96-03
2001-03
Directive
Directive
Directive
Directive
Directive
D-70
D-50
D-58
D-37
D-36
Section 14 - 10
Section 14 - 11
CONSIDERATIONS
The Historical Resources Act (1980) is intended to protect archaeological,
historical and paleoecological resources of Alberta and minimize the risk of
damage to these resources.
The ERCB requires a Historical Resources Impact Assessment with some
project applications as described in IL 82-11.
As described in the Alberta Environmental Protection and Enhancement Act,
pipelines with a construction index greater than 2690 require a formal
Historical Resources Impact Assessment.
If a known or suspected archaeological or historical site is encountered during
construction, contact the Resource Management Program (403-431-2300).
REFERENCES:
Alberta Historical Resources Act (1980)
Alberta Environmental Protection and Enhancement Act
Conservation and Reclamation Reservation (AR 115/93)
Alberta ERCB
IL
82-11
On side hills with a cut and fill layout, the cut material should be
placed on the downslope side for future recovery and reclamation.
CLEARING
At the edge of the lease, care should be taken to ensure trees are
felled so they fall within the lease and not onto the surrounding forest
where they will be difficult to recover.
Salvaged timber may only be used as rip-rap in wet areas and stream
crossings with Forestry approval.
Unburned debris and ash from a burn pile may be buried with at least
1m of cover and the surface area recontoured.
Cleared slash and debris must be disposed of within one year to avoid
unnecessary fire risk.
In some cases, it is preferable to save slash and limbs to work into the
surface of slopes as a way to minimize erosion potential.
Section 14 - 13
SITE LAYOUT
The lease layout must meet the ERCB and OH&S spacing
requirements.
In all agricultural areas (including land that has the potential for future
agriculture), it is required that surface soils be salvaged and stored for
recovery during reclamation at the time of abandonment. (Alberta
Environmental Protection and Enhancement Act, Part 5 and
Conservation and Reclamation Regulations, AR 115/93).
Earthen PITS may not be used to store produced fluids. (IL 946).
Section 14 - 14
The drilling flare pit shall (ERCB Drilling Rig Inspection Manual):
o
o
o
o
o
DYKING REQUIREMENTS
Dykes are required around all tanks containing any fluid except fresh
water.
Although dykes are not required around pop tanks they provide an added
degree of protection. The pop tank must be maintained empty, must have
a capacity equal to the unattended production and the pop lines must be
self draining to the upper third of the pop tank.
DYKING CONSTRUCTION
Section 14 - 15
Shall be sized to at least 110% of the capacity of the largest tank within
the dyke. Larger dyked volumes should be considered at unattended
facilities that have potential for larger releases.
Land lines should be routed to terminate outside the dyke wall to reduce
unnecessary traffic over the dyke and to reduce the risk of entering a sour
atmosphere. The load line should also be protected with secondary
containment.
PIPELINE ROUTE SELECTION
The objective in pipeline route selection is to choose a route that
considers engineering, economic and environmental constraints (physical,
biological and cultural) and minimizes disturbance and adverse
environmental effects.
The following steps are suggested for pipeline selection:
Identify the approximate corridor within which the proposed pipeline will be
located.
Section 14 - 16
Section 14 - 17
REFERENCES:
Alberta Environmental Protection and Enhancement Act
Alberta Environmental Protection and Enhancement Regulations
Conservation and Reclamation Regulations (AR 115/93)
Conservation and Reclamation Information Letter,
Reclamation Criteria for Wellsites and Associated Facilities
(C&R/IL/94-1)
ERCB
IL
2001-05 Construction of a Wellsite Prior to the Issuance of a Well
License
IL
94-6
Discharge of Produced Liquids to Earthen Structures
Section 14 - 18
If new dwellings are constructed near existing facilities, the operator may be
required to retrofit the equipment to meet applicable sound levels.
This interim directive applies to all facilities under the jurisdiction of the ERCB.
It applies to both new and existing facilities and to temporary and permanent
facilities. A noise impact statement may be required for new facilities or for
expansion to existing facilities.
The permissible sound level is the maximum sound level to which a facility
must be designed. If a noise-related complaint is received, the comprehensive
sound level must be measured and compared to the permissible sound level.
The comprehensive sound level is determined by conducting a continuous
sound monitoring survey for a 6 or a 24 hour period.
The permissible sound level can be determined following the procedures
described in the directive. It reflects a basic sound level which depends on
population density and is adjusted for a number of factors including a daytime
adjustment, seasonal adjustment, whether the facility is permanent or
temporary and some other factors. In no case is it less than 40 dBa or more
than 66 dBa.
HEARING PROTECTION
Noise is unwanted sound. Noise can prevent people from performing at
optimum levels. At high level it can cause hearing damage. There are
regulations to control noise levels in the work environment and to control the
noise resulting from industrial activities that may affect the public.
The human ear can hear sound over a wide range of sound pressure levels.
The unit of measurement commonly used is the decibel (dB), which is usually
expressed on the A scale which attempts to represent the way a human ear
hears different sounds. In addition to the sound level measured at any instant
in time, dBA, the average noise level over a six or 24 hour time period can be
measured to provide an average noise level. This is called the equivalent
sound level (Leq).
Some typical sound levels of familiar sources are:
SOURCE
Quiet Office
Quiet Street
Noisy Office
Highway Traffic at 15 m
Tractor at 15 m
Freight Train at 15 m
Jet Taking Off at 600 m
Air Raid Siren
SOUND LEVEL
(dBA)
40
50
60
75
80 to 95
95
100
130
Section 14 - 19
At oil and gas facilities, the common noise sources are large engines and
compressors. Noise levels are a potential concern to employees working in
the vicinity of the equipment and to neighbours who could be disturbed by the
noise. This environmental standard focuses primarily on the effect of noise on
the public.
GUIDELINES
Operators should discuss noise matters with area residents during the
design, construction and operating phases of an energy facility.
These requirements also apply to drilling and service rigs. They are
considered temporary if they will be on location less than two months.
For drilling rigs and service rigs, the responsibility for noise control
belongs to the well licensee.
REFERENCES:
ERCB
ID
Directive
99-8
D-38
CONSIDERATIONS
Selection and construction of lease sites and pipeline routes involve
consideration of many aspects of the ERCB and Alberta Environment
Regulations, Interim Directives and Informational Letters. The approval of the
location of an oil and gas facility begins with application to the ERCB for a
Well License. In parallel, surface approval must be obtained from the
landowner (White Zone) or Land and Forest Services or Public Lands (Green
Zone).
TERRAIN FACTORS
Sites within areas of Native Prairie (roughly the area east and south
of Red Deer) require special land preservation techniques (IL-96-9).
VEGETATION IMPACTS
Section 14 - 21
WILDLIFE CONCERNS
Sites for winter operations in many forested areas may face activity
restrictions to reduce disturbance to large mammals. Check with local
Fish and Wildlife Officers for restrictions.
Wells must be 100 m from the high water mark of a river, stream or
waterbody (O&G Regulations Sec. 2.12).
Before looking for a location for a new gas plant, operators are required by
the ERCB to look for existing processing capacity in the local area to
avoid unnecessary proliferation of gas plants.
Applicants for new wells and production facilities are required to advise
the Rural Authority of their intent to apply for ERCB approval. Similarly,
for locations within 1.5 km of the corporate limits of an urban center, the
applicant must advise the Urban Authority.
LOCATION OF ROADS
Following site selection, the operator must acquire a well license and a
surface lease from the landowner or the Crown before beginning
construction.
Section 14 - 23
REFERENCES:
Oil and Gas Conservation Act
Oil and Gas Conservation Regulations
Pipeline Act
Pipeline Regulations
Alberta Environmental Protection and Enhancement Act
Alberta Environmental Protection and Enhancement Regulations (AR
115/93)
Conservation and Reclamation Regulations
C&R/IL
94-1
C&R/IL
94-2
C&R/IL
94-3
C&R/IL
94-4
C&R/IL
94-5
Environmental
Pipelines
C&R/IL
94-6
C&R/IL
94-7
C&R/IL
95-1
Protection
Guidelines
for
Section 14 - 24
C&R/IL
95-2
for
C&R/IL
95-3
and
ERCB
ID
ID
IL
IL
IL
IL
IL
IL
IL
Directive
Directive
Directive
81-3
PURPOSE
Proper site maintenance and reclamation procedures will reduce the impact of
oil and salt water releases on land surrounding oil and gas facilities.
BACKGROUND
Both oil and produced salt water can be toxic to vegetation and cause
damage to soils. Most produced water is high in salts, largely sodium chloride
(NaCl), which can cause significant long term damage to soils. In fact, salt
water releases can be much more damaging to soils than hydrocarbon
releases since oil is biodegradable and the site usually can be reclaimed
within a year or two. Without prompt action, releases of produced water can
take much longer to reclaim.
CONSIDERATIONS
The Oil and Gas Conservation Regulations (Section 8.050) and the Pipeline
Regulations (Section 54) require that the operator take immediate steps to
contain and clean up releases.
The Alberta Environmental Protection and Enhancement Act states that An
operator must conserve and reclaim specified land and secure a reclamation
certificate in respect of the conservation and reclamation. The regulations
accompanying the Alberta Environmental Protection and Enhancement Act
OPX Consulting Inc.
Section 14 - 26
define specified lands as sites occupied by wells, pipelines and plants. The
Alberta Environmental Protection and Enhancement Act also has provisions
for enforcement whereby orders can be given for clean-up of adversely
affected sites.
SITE ASSESSMENT
After as much fluid as possible has been recovered and the site is safe to
work on, reclamation activities can begin. Hot water is often used to flush oil
into collection trenches, berms or bellholes. Caution should be exercised with
hot water since it could increase the flammable vapour concentrations or
cause the release of hydrogen sulphide. IF THERE IS SALT WATER
ASSOCIATED WITH THE RELEASE, DO NOT FLUSH WITH WATER. See
Salt Water Releases.
Releases that are contained entirely within the lease do not usually require
immediate reclamation of the soil for plant growth. In this case, the
contaminated soil should be excavated and the area repaired with clean fill or
gravel. The contaminated soil can be sent to an approved waste management
facility or treated on site by landfarming.
For off-lease releases, it is usually necessary to restore the chemical and
physical properties of the soil to allow crops or native vegetation to reestablish. This can often be accomplished by adding the appropriate soil
amendments and allowing the natural micro-organisms in the soil to
decompose the residual oil. A reclamation program should begin with a site
assessment to establish the extent of contamination and to use the results of
soil analysis to develop a reclamation plan. This information should be
documented for submission to regulatory officials and to keep track of the
work since it usually takes several years to completely restore the site.
Some suggestions for site assessment include the following:
Make a sketch of the site, take photographs, and make notes of the
surrounding terrain conditions and nearest watercourses.
Section 14 - 27
OIL RELEASES
For oil releases on water, specialized equipment (booms, skimmers, etc.) can
be obtained from the nearest co-op equipment unit or from the PROSCARAC
trailer. These units also have a variety of general purpose equipment for
release clean-up. Consult the Oil Spill Co-Op Manual for techniques to
contain and clean-up oil releases, and Oil Spills Cooperatives for a listing of
Cooperatives in Western Canada.
The local office of the ERCB should be contacted for approval of a release
reclamation project. It is very important to work with the landowner to
understand his requirements for that seasons land use and his long term
plans.
There are a variety of factors to consider in designing the reclamation plan for
an oil release. In most cases, it is possible to spread the oil contaminated soil
on the surface and add fertilizer to encourage natural decomposition.
Generally the maximum oil loading rate in the surface soil should be in the
order of three to five percent. A temporary fence may be needed to keep out
stock. In most cases, the area should not be seeded unless the oil
concentration is less than one percent.
Manure and fertilizer should be worked into the soil and tilled every three or
four weeks. Lime will probably be needed to correct the pH and generally the
laboratory can recommend the required addition rates. Once the oil
concentration has been degraded to less than one percent, the site can be
revegetated.
SALT WATER RELEASES
After as much fluid as possible has been recovered, soil remediation should
begin IMMEDIATELY. This is of the utmost importance for salt water
releases. ON AGRICULTURAL LANDS, DO NOT FLUSH WITH WATER AS
THIS IS DETRIMENTAL TO THE SOIL. Flush with a diluted solution of
calcium nitrate as soon as possible. Caution should be used to ensure that
calcium nitrate does not contaminate any surface water. Gypsum can be used
after the initial application of calcium nitrate to make further calcium available
to the soil.
On forest soils, water can be used to flush released fluid toward ditches and
bellholes where it can be recovered.
On agricultural soils, a source of calcium should be added immediately after
fluid recovery is complete.
Section 14 - 28
Section 14 - 29
REFERENCES:
Alberta Environmental Protection and Enhancement Act
Release Reporting Regulations (AR 117/93)
Release Reporting Guidelines (June, 2001)
Oil and Gas Conservation Act
Oil and Gas Conservation Regulations: Section 8.050
Pipeline Act
Pipeline Regulations: Section 54
Section 14 - 30
Produced Water
Crude Oil
Emulsions
Condensates
Chemicals
Solvents
Produced Sand
Oily Wastes
Bitumen
The guideline does not change the following current regulatory requirements:
Section 14 - 32
Section 14 - 33
Leak detection systems for above ground storage tanks must include
one or more of the following on a monthly basis;
Section 14 - 34
Section 14 - 35
Any of the above storage systems installed prior to January 1, 2002, will be
required to meet the requirements within the appropriate sections of Appendix
2 of D-55.
REFERENCES:
National Standard of Canada Propane Installation Code CAN/CGAB149.2M86
Alberta Fire Code, Section 4.3
Alberta Labour Act and Regulations, MUST Program
Fire Protection Handbook, 15th Edition, NFPA 30
- Flammable and Combustible Liquids Code National Fire Protection
Association
Alberta Boilers Safety Association (formerly Alberta Boilers Branch)
ERCB
IL
84-11
GB
92-4
Directive
D-55
Storage Requirements
Petroleum Industry
for
the
Upstream
Section 14 - 36
Section 14 - 37
CONSIDERATIONS
Some guidelines to avoid surface water or groundwater contamination
problems include the following:
Section 14 - 38
Landowner consent
REFERENCES:
Oil and Gas Conservation Act
- Oil and Gas Conservation Regulations Section 8.030
ERCB
Directive
D-55
Directive
D-64
Section 14 - 39
Other working interest owners are still available to share the cost.
Section 14 - 40
many cases, it is worth while to check this out by telephone with the
Environmental Assessment Branch of Saskatchewan Environment.
RECLAMATION TERMS
The following terms are commonly used in abandonment and reclamation
work.
Reclamation Criteria
Reclamation Criteria are the standards to which a lease site must be
reclaimed in order to receive a Reclamation Certificate.
A Reclamation Certificate is issued by AE or Alberta Agriculture,
Food and Rural Development (AFRD) following an inspection that
proves the operator has reclaimed the site to a standard that is
consistent with the reclamation criteria.
Decommissioning
Decommissioning refers to the closure of all or part of an industrial
facility followed by the removal of process equipment, buildings and
structures, surface and subsurface decontamination.
Reclamation
Reclamation refers to the entire process from abandoning a facility to
returning the land to equivalent land capability. A Reclamation
Certificate will be issued for those facilities that fall into the Alberta
Environmental Protection and Enhancement Act definition of specified
land when reclamation is completed to the satisfaction of the AE.
Those facilities that are not specified land under the Alberta
Environmental Protection and Enhancement Act will have to meet
decontamination requirements.
Decontamination
Decontamination is the removal or neutralization of substances and/or
hazardous material from a site as to prevent, minimize, or mitigate any
adverse effects on the environment now or in the future.
Land Reclamation
Land Reclamation is the stabilization, contouring, maintenance,
conditioning, or reconstruction of the surface of the land to a state that
permanently renders the land with a capability equivalent to its predisturbed state.
Section 14 - 41
CONSIDERATIONS
Specific reclamation practices vary from one area of the province to another.
Often specialists are required to develop a site-specific plan. In general it will
include:
Initial Site Assessment:
Reclamation Plan:
Site Decommissioning
Section 14 - 42
GB
ID
ID
2000-17
90-4
2000-09
Directive
D-20
Directive
Directive
D-56
D-59
Filing
Section 14 - 44
General Terrain:
____________ Flat
______________Rolling
_______________Steep Slopes
Comments:
Soil Type:
____________Dry
____________Sandy
Land Use:
__________Forestry
_____________Wet
_____________Loam
__________Cultivated
___________Gravel
__________Grazing/Livestock
__________Muskeg
_________Wildlife (Y/N)
Comments:
Closest Residence:
_________< 1 km
__________1 4 km
____________> 4 km
__________100 500 m
____________> 500 m
__________Size
____________Flowing (Y/N)
Comments:
Section 14 - 45
1.
AUDIT ITEM
Is there an Environmental Policy and Procedures Manual; is it current
and available?
Presence of CAODC Waste Management Wall Chart
(Drilling Locations)
CAMP RULES / ENVIRONMENTAL STANDARDS is a standard present,
understandable and adhered to? Are biodegradable cleaning products used?
RIG INSPECTIONS Standard is to have rigs inspected for environmental
deficiencies on a regular basis. Ensure that inspections are done and that records
are kept. Determine if identified deficiencies are corrected in a timely manner.
All vehicles shall arrive on site free of weeds.
Is there a C&R Plan for this project? (If yes, proceed to C&R section to follow)
2.
N/A
SAT
U/S
N/A
SAT
U/S
AUDIT ITEM
Are regular environmental meetings held in the field?
Are following tops covered in meetings?
Proper Maintenance
Release Detection / Assessment
Handling of Specific Hazardous Chemicals
Hazardous Waste Disposal
Company Policies
Legal Responsibilities
Reporting Requirements
What are the environmental training requirements for field staff?
ERP
Waste Management
TDG / WHMIS
Company Environmental Policy Review
Section 14 - 46
3.
Following is a listing of potential impacts from the project determine applicability of each
impact and provide documentation of mitigation strategy employed (Rating system should
reflect success of mitigation for impact).
AUDIT ITEM
N/A
SAT
1.
Agricultural
d) disturbance of farming operations
e) disturbance of livestock operations
f) risk of fire spreading off r.o.w.
10. Native Consultation / Issues
11. Archaeological, paleontological sites or historical resources
12. Operations Phase
a) reclamation
b) maintenance
13. Abandonment
Section 14 - 47
U/S
4.
AUDIT ITEM
N/A
SAT
U/S
5.
AUDIT ITEM
N/A
SAT
Observe number and condition of river crossings. Are all crossing approvals in place? Are any
C&R conditions in place? Are they met?
Is erosion on the access controlled? Are soil conservation methods required / in place?
Are there any special license conditions that must be adhered to? (ie: wildlife issues, restricted
access, access controls)
Is wildlife protection required in this area? What is being done to protect wildlife? Are
requirements detailed under C&R plan?
Construction activities shall be confined to the allotted ROW.
Construction traffic shall be restricted to existing roads, approved ROW and approved shooflies.
Construction traffic shall be restricted to work side of the ROW to reduced area subjected to
compaction.
Wildlife shall not be harassed or fed. Dogs and firearms are not allowed on the ROW.
The recreational use of ATVs by the construction personnel on the ROW is not allowed.
Any incidents with nuisance wildlife or collisions with wildlife are to be reported to Fish and
Wildlife and the local police detachment.
Fires:
Personnel shall be made aware of proper disposal methods for welding rods, cigarette
butts, and other hot or burning materials;
Equipment exhaust and engine systems shall be in good working condition. When the
fire hazard is high, equipment should not be parked in tall grass;
Construction equipment shall be equipped with spark arrestors;
A water truck should be available when the fire hazard is high;
Each crew shall carry (minimum) 2 shovels, 1 fire extinguisher, and a radio;
A fire contingency plan should be in place and implemented when necessary.
Floods: Drainage construction shall be postponed if excessive flow or flood conditions are
present or anticipated. Ensure that all spoil piles are above the flood line.
Archaeological or Historical Discoveries: Work shall be suspended if discoveries are made.
Work shall not recommence until permission from authorities is received.
Damaged trees: Fell or prune trees damaged during construction activities immediately. Do not
postpone until clean-up.
Section 14 - 48
U/S
6.
AUDIT ITEM
N/A
SAT
U/S
N/A
SAT
U/S
N/A
SAT
U/S
7.
AUDIT ITEM
Landowners are to be notified prior to entry
Staking:
- both sides of an r.o.w. are to be marked. Do not clear beyond stakes unless approval is given
- staking should be done to cross drainages and roads at right angles, and slopes should be
traversed along the fall line
Working Space:
- extra working space should be taken at sidebend and slopes, as well as at drainage crossings
- approval must be obtained before taking additional working space
Fences: need to be braced before cutting, install gates and keep closed
Drainages:
- minimize removal of vegetation adjacent to drainages
- fell trees away from drainages, remove anything within the high water area
Slash Disposal dispose of slash as directed by landowner. Do not conduct burning during high
winds
8.
AUDIT ITEM
Grading minimize along routs, minimize graded widths and on slopes
Strip topsoil where grading is required and windrow to near edge.
Drainage should be away from graded area.
Cut and Fill should not exceed 4:1, ensure graded material does not spread onto r.o.w.
Topsoil salvage measures are to be used.
Section 14 - 49
9.
CONSTRUCTION / DRILLING
AUDIT ITEM
N/A
SAT
U/S
N/A
SAT
U/S
What is typical for clean-up efforts prior to leaving the site permanently? Are there policies in place
and who is responsible? Is documentation available (checklists, sign-offs, etc.)?
Are all applicable licenses and permits available as part of the EPP? Ensure these permits and
licenses were obtained prior to beginning activity. List all applicable permits / licenses and ensure
conditions are being met.
If shoo-flies are used, they must be reclaimed as part of the clean-up.
10.
11.
N/A
SAT
Section 14 - 50
U/S
12.
WASTE MANAGEMENT
Minimization, Storage Disposal, Record Keeping, Special Materials (Asbestos, Radioactive)
AUDIT ITEM
N/A
SAT
U/S
N/A
SAT
U/S
AUDIT ITEM
Waste bin on site? Supplied by? What is disposal path?
Storage for waste lube oil.
Used filter barrel storage.
Mud sack storage.
Casing protector storage.
All construction garbage shall be continuously collected and disposed of at an approved facility to
avoid the attraction of nuisance animals.
Waste containers shall accompany each working unit.
All garbage will be stored in bear proof containers when conflict may occur.
Storage for recyclables at camp (bottles/cans).
14.
AUDIT ITEM
N/A
SAT
Section 14 - 51
U/S
AUDIT ITEM
N/A
SAT
U/S
N/A
SAT
U/S
N/A
SAT
U/S
15.
16.
Section 14 - 52
17.
N/A
SAT
U/S
Approvals required under WMA for any emissions. As of September 1/96 many of these
emissions are authorized.
Applications in writing must be made before any well testing involving flaring is done. In
emergencies, this may be done over the telephone.
18.
N/A
SAT
U/S
N/A
SAT
U/S
19.
AUDIT ITEM
Does company have an Emergency Response Plan for releases? Provide copy if available. What
are reporting requirements/flows?
Release response kit on-site / complete?
Any release incidents reported / cleaned-up?
Incidents are to be reported to regulatory and local officials.
Section 14 - 53
15.0
CONSTRUCTION SAFETY
15.1
INTRODUCTION
The Construction Supervisor, as HARVARDs representative is responsible for
ensuring compliance with Occupational Health and Safety Act regulations. Of prime
concern is coordinating safety activities when there is more than one employer on
site. The Construction Supervisor must be aware of and fulfill his responsibilities as
the representative of the Prime Contractor (See Section 2.0).
All sections of this manual apply to HARVARDs facility and pipeline construction
activities.
15.2
15.3
15.4
15.5
Section 15 -1
SECTION 15 FORMS
Construction Safety Plan Checklist
Emergency Contact Information
Lease Construction Tailgate Meeting Report
Construction HSE Meeting Report
Safety Meeting Attendance
Ground Disturbance Permit
Backfill Inspection Form
Section 15 -2
DATE: _________________
CONTRACTOR: _______________________________________________________________
SAFETY
First Aid Kits on Site
Contractor has Safety Program on Site and
Responsible for Worker Safety
Safety Meeting Requirements Established
Safety Committee (Multi-Contractor)
Contractor Safety Meetings
Tailgate Meetings
Housekeeping Procedures Reviewed
Work Permit Requirements Established
Safety Equipment Requirements Determined
Personal Protection Equipment Requirements
Determined
Location of Safety and Emergency Equipment
Established
Driving Procedures Established
Vehicle and Equipment Operation Procedures
Established
Accident/Incident Reporting Procedures Reviewed
Authority of Supervisor to Shut Down Work
Identified
HAZARD REVIEW
PROJECT SCOPE
Scope of Work Reviewed
Restricted Work Areas Established (Where
Applicable)
Project Schedule Reviewed
Hours of Work Established
EMERGENCY
Harvard Emergency Response Plan
Reviewed
Emergency Procedures Reviewed
Contact Information Sheet Posted
Safe Areas Established
First Aid Personnel Identified
Fire Extinguisher Stations Established
Method to Track Number of Workers on Site
Established
Plant Emergency Alarm Operation (Where
Applicable)
OTHER (list)
ENVIRONMENTAL REVIEW
Topsoil Handling and Site Grading
Fuel and Chemical Storage
Waste Handling, Storage and Disposal
Equipment Oil Changes
______
_______
Section 15 - 3
Date:________________________
Contractor:____________________
Project#:_____________________
Employees Present:
Print
________________________________
________________________________
________________________________
________________________________
________________________________
________________________________
Signature
_____________________________
_____________________________
_____________________________
_____________________________
_____________________________
_____________________________
No
N/A
Action to be Taken
Location of:
Buried Cables
Overhead Lines
Wellhead
Sumps
Digging Sumps
Towing of Trucks
Ditch Cut
Digging Burrows/Snakepits
Driving Speed Limits
Other Personnel/Equipment
PPE Required
Emergency Contact #s
Other
Other
Buried Pipelines
Worksite Plan
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
_______________________
____________________
Signature
________________________________
___________________________
Signature
DATE:
OPERATION:
PIPELINE
SITE/LOCATION:
CONTRACTOR(S):
CONTRACTOR SUPERVISOR(S):
Harvard REPRESENTATIVE:
OUTSTANDING CONCERNS:
RECOMMENDED ACTION:
TARGET DATE:
NEW CONCERNS:
RECOMMENDED ACTION:
TARGET DATE:
TRAINING GIVEN:
_______________________________________
REPRESENTATIVE SIGNATURE
MEETING DATE:
NAME
SIGNATURE
Section 15 - 4
RECORD CONFIRMATION
YES
NO
N/A
1. Do you have a copy of the Survey Drawing for the well site, access road, and/or proposed ground disturbance area?
*NOTE* If the survey drawing is older than 60 days, consideration should be given to getting an updated survey drawing.
2. Do you have a copy of the Surface Acquisition report?
3. Does the survey drawing Table of Crossing match with the Surface Acquisition Report Table of Crossings?
4. If questions 1-3 are N/A, has the proposed area of the disturbance and buffer zone been electronically scanned?
5. Do you have a recent copy of the Land Title Certificate or Public Land Standing Report?
6. Do you have a copy of the most recent Provincial/Company Pipeline baseline map?
7. Did you notify the Land Agent (Crown Land) or Land Owner (Freehold Land) of your intentions and review any existing underground
facilities? Name:
8. Do you have a copy of all Crossing Agreements for any facility identified within 30 metres of the work area?
9. Did you adhere to the crossing notification requirements?
10. Did you contact local Production office and review scope of work and crossings?
Name:
11. Have all pipelines, power lines, and utilities in the 30 metre search/controlled area been identified?
12. Has the One Call System been notified of our intentions?
VISUAL INSPECTION
1. Are all buried pipelines, power lines, or utilities identified on above drawings, and staked on the ground in proposed area?
2. Are overhead power line Caution Signs in place?
3. Are all the locate stakes or marks referenced to fixed features?
4. Are all of the lines within the 30 meter search/controlled zone identified on the ground?
5. Are there any signs of new ground disturbances within the proposed working area, including the search/controlled zone? This may
include pipelines, power lines, Gas Co-op, utility cables, new clearings, road construction, pipeline signs, settlement, vegetation
color change or growth. If there is any visual sign of activity that is not reflected on Survey Drawing, re-surveying should be
considered.
PRE-CONSTRUCTION
1. Is the proposed ground disturbance expected to be any depth below the surface?
*CAUTION* - any depth below the surface is a general rule. Ground disturbances located at any depth may encounter lines
improperly installed or changed due to shifting ground disturbances. Additional crossing material should be considered.
2. Are there any pipelines, power lines, or utility cables being crossed within the 5 meters where no right-of-way or within the distance
outline in crossing agreements?
3. Are ALL the conditions of the Crossing Agreements being met?
4. Have all the underground facilities been exposed as per the company requirements, crossing agreements, and the Regulations?
5. Distance to which mechanical equipment may be operated after exposure from agreement
mm
6. Did you conduct a pre-job task meeting with foreman and equipment operators? Review Procedures & ERP.
NOTE: This document is designed to be a GUIDE to the minimum safety standards for Ground Disturbance. Refer to the Provincial Regulations, Company Standard
Safety Practices Manual, contractors safety program, and Provincial Health & Safety Statute and Regulations for further details. If project involves interprovince activity, the National Energy Board has additional requirements. SEE NEXT PAGE FOR REFERENCES.
Comments:
Company
Representative:
Ver. 1.0
Contractor
Representative:
DEFINITIONS
GROUND DISTURBANCE - is any work, operation, or activity without limitation that results in a disturbance of
the earth at any depth.
SEARCH AREA- is the 30 meters surrounding the ground disturbance area in which all reasonably necessary
precautions must be taken to determine whether or not an underground facility exists.
NOTIFICATION - Every owner within the ground disturbance area and the 30 meter search area must be
notified of the nature and schedule of the ground disturbance. Notification must be done as per the crossing
agreement or as per provincial Regulations of a minimum of 2 working days and a maximum of 7 working
days, or greater, as specified in the crossing agreement.
CROSSING AGREEMENTS (also referred to as APPROVALS) - Anytime a ground disturbance takes place
within a right-of-way, or within 5 meters of a facility where there is no right-of-way, an approval must be in
writing.
NOTE: A crossing agreement is commonly used as the approval and does not mean an actual crossing is
taking place.
HAND EXPOSURE - Hand exposure must be done if the ground disturbance crosses or is carried out within 5
meters of an existing underground facility before commencing any mechanical excavation. When exposing the
underground facility it must be done sufficiently to identify the facility. Excavation techniques have been
developed using water or air jets. These have generally been accepted, although all procedures may not have
specific regulatory approval. Care should be taken to evaluate the best method of hand exposure, taking into
consideration, damage to coatings, and methods of soil disposal.
CAUTION:
Even after hand exposure, mechanical equipment must not be used within the distance
specified on the crossing agreement, OR, if a crossing agreement is not present, not closer than
60 cm. to the underground facility.
REFERENCES
ITEMS # 1, 2, 3, 5, & 6
ITEM # 5:
ITEM # 10:
ITEM # 12:
GENERAL:
Ver. 1.0
The Provincial Acts and Regulations should be available for reference and further resources.
Crossing
Agreement Number
PROJECT:
AB/BC LSD
BC QTR UNIT
SEC
TWP
RGE
/MAP
BLOCK
SUB DIV
SHEET
Depth Existing
Depth New
River
Bed
Existing
Depth
OR
Depth New PL
Depth
Depth Existing
Grade
Cased
Uncased
Existing
Road, RR X-ing River/Creek
Pipeline - R/W
INDICATE:
1.
2.
3.
4.
Approval
Print Name
Date Completed
Company Signature
Print Name
Date Completed
Contract Signature
Ver 1.0
R/W
Section 16 - 1
COMBUSTIBLE MATERIAL
Combustible materials are ones that, either by themselves or in combination with their
packaging, are highly susceptible to ignition and will contribute to the intensity and rapid spread
of fire.
Moderately combustible materials are ones that, either by themselves or in combination with
their packaging, will contribute fuel to fire.
Noncombustible materials are ones that will neither ignite nor support combustion.
COMPETENT
Competent, when referring to a worker, means adequately qualified, suitably trained and with
sufficient experience to safely perform work without or with minimal supervision.
CONFINED SPACE
A restricted space which may become hazardous to a worker entering it because of: an
atmosphere that is or may be injurious by reason of oxygen deficiency or enrichment,
flammability, explosivity or toxicity; a condition or changing set of circumstances within the
space that presents a potential for injury or illness; or has the potential or inherent
characteristics of any activity which can produce adverse or harmful consequences within the
space. Confined spaces include but are not limited to: tanks, bins, vessels, towers, furnaces,
tank cars, sewers, pipeline, sumps, utility tunnels, dyked areas, excavations, boilers, silos,
ventilation and exhaust ducts, vessel skirts, utility vaults, valve wells and pipe racks.
CONFINED SPACE ENTRY
A person is considered to have entered a confined space when that person has sufficiently
approached or passed the threshold of the confined space, to be essentially breathing the
atmosphere of the confined space.
CONSULTANT
An individual hired to provide professional or expert advice or services.
CONTRACTOR
An individual or company hired under contract to provide services or supplies to another
individual or company.
CONTROLLED PRODUCT
A product, material or substance included in any of the classes listed in Schedule II of the
Hazardous Products Act (specified by the regulations made pursuant to paragraph 15 (1) (a) of
the Act).
CORROSIVE
Having the quality to corrode or consume (e.g., acid, or H2S).
CRITICAL JOB/TASK
A specific element of work which historically has produced and/or which possesses the
potential to produce major loss (people, property or financial) when not properly performed.
Section 16 - 2
Section 16 - 3
FLAMMABLE LIQUID
Any liquid with a flash point below 200F.
FLASH POINT
The lowest temperature at which vapours over volatile combustible substances will ignite when
exposed to external sources of ignition (and will continue to burn after the source is removed).
FUGITIVE EMISSION
Gas, solid, liquid, fume, mist, fog or dust that escapes, unplanned from process equipment,
emission control equipment or from a product.
HANDLING
Storing, dispensing and disposing of materials or containers.
HARMFUL SUBSTANCE
A substance which because of its properties, application, or presence, creates or could create
a danger, including a chemical or biological hazard, to the health and safety of a worker
exposed to it.
HAZARD CLASSIFICATION
A designation of relative loss potential. A system that classifies substandard practices or
conditions by the potential severity of the loss, should an accident or loss occur.
HAZARD LABEL
A label required on controlled products.
HAZARDOUS CONDITION
Any situation which exposes workers to a physical, chemical, electrical, high energy, etc.
hazard that may adversely affect their health or safety.
HAZARDOUS ENERGY
Means electrical, mechanical, hydraulic, pneumatic, chemical thermal, gravitational, or any
other form of energy that could cause injury due to the unintended motion, energizing, start-up
or release of such stored or residual energy in machinery, equipment, piping, pipelines or
process systems.
HAZARDOUS LOCATION
A place where fire or explosion hazards may exist due to flammable gases or vapours,
flammable or combustible dust or ignitable fibres or flyings, as described in the Canadian
Electrical Code
HAZARDOUS PRODUCT
Any product that is prohibited, restricted or controlled, and can cause harm to workers or the
environment.
Section 16 - 4
HOT TAPPING
The process of welding a branch or connection onto a pressure vessel, tank, connected piping
or pipeline that contains flammable or other materials. The welding is done without blinding and
purging the equipment beforehand.
HOT WORK
Any work involving burning, welding, riveting, grinding or other similar fire or spark-producing
tools or operations, as well as work which produces a source of ignition, such as drilling,
abrasive blasting, and space heating.
H2S
Hydrogen Sulphide
IAPA
Industrial Accident Prevention Association of Ontario
ILCI
International Loss Control Institute
INCIDENT
An undesired event that, under slightly different circumstances, could have resulted in personal
harm, property damage, or loss to process. Also referred to as a near miss (ICLI)
INSPECTION
The careful examination of people, equipment, materials, and the environment, the close and
critical scrutiny for comparison with standards.
ISOLATE
Means using a mechanical device to restrain, regulate, direct, or dissipate hazardous energy.
ISOLATION
A process whereby a confined or isolated space is completely protected against the inadvertent
release of material or energy.
JOB/TASK ANALYSIS
A systematic analysis of the steps involved with doing a job/task, the loss exposures involved,
and the controls necessary to prevent loss. It should be a prerequisite to the development of
work procedures and practices. An important step in the analysis would be consideration of the
elimination or reduction of hazards.
JOURNEYMAN ELECTRICIAN
An electrician who has completed a specified number of hours of practical work and training as
well as classroom study and exams. The requirements vary among the provinces.
LC50
Lethal concentration. LC50 indicates the atmospheric concentration of a substance at which half
of the group of test animals die after a specified exposure time.
Section 16 - 5
LD50
Lethal dose; lowest dose of a substance introduced by any route, other than inhalation, over
any given period of time in one or more divided portions and reported to have caused death in
half of the test animals.
LEL
Lower explosive limit.
LOCAL VENTILATION
Removal by mechanical means of gases, dust, etc., at their source or origin.
LOST-TIME ACCIDENT
An accident that causes a person to be away from work beyond the day of the injury.
OR
A disabling injury where the employee was not able to show up for his or her regular work shift
the next day.
LOWER EXPOSURE LIMIT
The minimum concentration of a combustible gas or vapour in air, expressed in percent by
volume, which will ignite if an ignition source is present.
MANAGER/SUPERVISOR
A person who has charge of a work place or authority over a worker.
MANUFACTURERS RATED CAPACITY
The manufacturers specifications, instructions or recommendations which outline how
equipment is to be erected, installed, assembled, started, operated, used, handled, stored,
stopped, adjusted, maintained, repaired or dismantled. They may include manufacturers
instruction, operating or maintenance manual and drawings.
MATERIAL SAFETY DATA SHEET (MSDS)
An information sheet containing health and safety information on the handling and storage of a
product.
MEDICAL AID
An injury that requires treatment from a professional medical doctor or dentist. The injury is not
severe enough to prevent the employee from returning to work the next day.
MEDIVAC
Medical evacuation service.
MSHA
Mine Safety and Health Administration (of the U.S. Department of Labour)
NEC
National Electrical Code
NFPA
National Fire Protection Association
Section 16 - 6
NIOSH
National Institute for Occupational Safety and Health
OCCUPATIONAL ILLNESS
Any abnormal condition or disorder of an employee (other than one resulting from an
occupational injury), caused by exposure to environmental factors associated with
employment.
OCCUPATIONAL INJURY
Any injury that results from a work accident or from exposure to environmental factors
associated with employment.
OH&S
Occupational Health and Safety
OSHA
Occupational Safety and Health Administration (USA)
PERSONAL PROTECTIVE EQUIPMENT
The equipment or clothing worn by a worker to reduce the consequences of exposure to
various hazards associated with working conditions or a work site. Personal protective
equipment includes: burning goggles, chainsaw pants, chemical goggles, chemical suits and
aprons, cold weather clothing, dust masks, face shields, fire-retardant clothing, gloves, hard
hats, hearing protection, high visibility safety vests, hoods, safety goggles, safety helmets and
safety toes footwear.
POLICY
A senior management statement which guides administration, reflects managements attitudes
and commitment to safety and health, and defines the authority and respective relationships
required to accomplish the organizations objectives.
POSITIVE ISOLATION
The blinding off, plugging or the complete removal and blanking off of inter-connecting piping,
vessels or sewers which may contain hazardous material.
PPM
Parts Per Million
PRESSURE VESSELS
Devices designed to contain gas or vapour under pressure.
PREVENTABLE MOTOR VEHICLE ACCIDENT
A preventable accident is any occurrence involved in a Company owned, leased, rented or
operated vehicle which results in property damage and/or personal injury regardless of who
was injured, what property was damaged, to what extent, or where it occurred, in which the
driver in question failed to do everything the worker reasonably could have done to prevent the
occurrence.
Section 16 - 7
PROCEDURE
An established and defined method of performing specified work.
PRODUCT IDENTIFIER
The brand name, code name or code number specified by a supplier, or the products chemical
name, common name, generic name or trade name. This should be the name under which the
product is sold.
PSV
Pressure Safety Valve
PURGE
To rid of impurities or undesirable by bleeding, venting, etc., generally with steam, inert gas,
nitrogen or C02.
QUALIFIED PERSON
A person designated by the employer as capable (by experience, education and/or specified
training) to properly fulfill the required function.
RESPIRATORY PROTECTION
Refers to any respiratory protective device or system designed to protect the wearer from
inhalation of toxic or irritating substances. It can include air-purifying respirators, supplied air
respirators or self-contained breathing apparatus.
RESTRICTED SPACE
An enclosed or partially enclosed space that is not designed or intended for continuous human
occupancy with a restricted means of entry or exit and may become hazardous to a worker
entering it because of its design, construction, location or atmosphere; the work activities,
materials or substances in it; provision of first aid, evacuation, rescue or other emergency
response service is compromised or of other hazards relating to it.
SAFE WORK PERMIT
A written record that authorizes specific work at a specific work location. It identified the known
hazards and safe work practices required for the work.
SAFE WORK PROCEDURE
A set of guidelines for performing specific work assignments properly (efficiently, safely,
productively).
SAFETY EQUIPMENT
Equipment used to reduce the consequences of worker exposure to various work site hazards.
Safety equipment includes oxygen and other monitors, personal protective equipment, safety
belts, lanyards and lifelines.
SECURE
Refers to an energy-isolating device that cannot be released or activated by removing any
activating device, attaching a lock to the energy-isolating device that is operated by a key or
similar device, or attaching to the energy-isolating device a mechanism other than a lock which
is designed to withstand inadvertent opening without the use of excessive force, unusual
measures, or destructive techniques.
Section 16 - 8
SCBA
Self-Contained Breathing Apparatus
SNUBBING
Means the act of moving tubulars into or out a wellbore when pressure is contained in the well
through the use of stripping components or closed blowout preventers (BOPs) and mechanical
force is required to move the tubular in order to overcome hydraulic force exerted on the
tubular in the wellbore.
SPECIFICATIONS
The written instructions, procedures, drawings, or other documents of a professional engineer
or employer. They can relate to equipment, work process or operation.
SPOIL
The material resulting from an excavation.
STANDARD
The defined criterion of effective performance.
SUB-CONTRACTOR
An individual or company hired to perform all or part of the work contracted to someone else.
TDG
Transportation of Dangerous Goods (Act)
THRESHOLD LIMIT VALVE (TLV)
Concentration of airborne materials which are used as guides in the control of health hazards
and represent time weighted averaged concentration to which workers may be repeatedly
exposed eight (8) hours per day over extended periods without adverse effects.
TOXIC SUBSTANCE
Any substance that is present or has the potential to be present in concentrations which may
adversely affect the health of an exposed individual, as defined by provincial chemical
exposure regulations.
TOXICITY
The ability of a chemical to cause harmful effects in a biological system.
TRENCH
A narrow excavation made below the surface of the ground. In general, the depth is greater
than the width, but the width of a trench is not greater than 4.6m (15 feet).
TRENCH SHIELD
A shoring system composed of steel plate and bracing, welded or bolted together to support
the walls of a trench from the ground level to the trench bottom. The shield can be moved along
as the work progresses.
Section 16 - 9
UEL
Upper explosive limit, or the maximum proportion of vapour or gas in air above which
propagation of flame does not occur.
VAPOUR
Gaseous phase of a substance which is liquid at normal temperature and pressure.
WCB
Workers Compensation Board
WORK POSITIONING SYSTEM
Means a system of components attached to a vertical safety line and including a full body
harness, descent controllers and positioning lanyards used to support or suspend a worker in
tension at a work position.
WHMIS
Workplace Hazardous Materials Information System
WORKER
An employee under the supervision of a manager or supervisor.
ZERO ENERGY
A piece of equipment is in a state of zero energy when all sources of energy (e.g. electrical,
mechanical, hydraulic, pneumatic pressures, spring tension, gravitational etc.) are effectively
blocked or isolated and physically prevented from being energized by a isolation device.
Section 16 - 10
Section 17-1
Section 1 - 6
Post-incident testing;
Section 1 - 7
SAFETY STATEMENT
TO BE POSTED AT EVERY WORK SITE
Well/Facility Name: ________________________________________________________________
2.
3.
4.
Regular safety meetings and inspections must be carried out and properly
documented.
5.
Any accident, whether lost time or otherwise, unsafe acts or near misses must
be reported immediately by the work site supervisor to the above by telephone
and in writing by the next morning. The contractors written report, and if
required, copies of the applicable provincial W.C.B. forms MUST BE FAXED TO
THE CALGARY OFFICE AS SOON AS POSSIBLE.
Section 3 - 5
OPERATOR:
LOCATION:
WELL SITE SUPERVISOR:
RIG# / RIG MANAGER:
DATES: From:
To:
The Operator is designated as the Prime Contractor for this operation. The Well Site Supervisor is
the agent of the Operator. The following checklist summarizes the key elements of the required work
site safety plan. Well Site Supervisors are requested to submit the completed checklist upon
completion of the job.
YES
NO
N/A
GENERAL
Have you reviewed and posted HARVARDs HS&E Policy & Safety Statement?
Have all identified landowner requirements been identified and addressed?
HAZARD IDENTIFICATION AND ASSESSMENTS / INSPECTIONS
Is a Hazard Assessment completed for each task being conducted?
Are the results of Hazard Assessments reviewed during the Safety Meeting Process?
Review Well Site Layout (as per provincial regulatory requirements).
Have the rig anchors been installed and tested as required?
Are CAODC rig inspections or equivalent being completed as required?
Have you received copies of all inspections completed on the worksite?
Has the CAODC BOP been completed as required?
Have the mouse/rat holes been identified prior to moving completion rig on site.
SAFETY COMMUNICATION
Are Safety Meetings held on regular basis?
Are the meetings documented and are you receiving copies of the meeting minutes?
As the Supervisor have you attended pre-job safety meetings for critical/non critical
operations?
Have you reviewed regulatory permits and license conditions?
Safe Work Permits: have you identified requirements and issued necessary permits?
Has a pre-job tailgate safety meeting been conducted prior to each specialized
operation?
INCIDENT REPORTING AND INVESTIGATION
Are Contractors and their personnel aware of the HARVARD incident reporting procedures,
and are they complying?
Are you ensuring all incidents/near misses are investigated reported and corrective
measures implemented?
EMERGENCY RESPONSE PLANNING
Has the Corporate/Site Specific ERP been reviewed with onsite personnel?
Have emergency numbers and directions to lease been posted and is a map of area
available for quick reference?
Are lease signs adequate to direct emergency response workers to the site?
YES
NO
N/A
Have muster points been identified and all personnel aware of them?
Are First Aid/Emergency Services available including a transportation method?
Are supplies well maintained and do they meet regulated standards?
Has the communication equipment on the worksite been tested for emergency response
procedures?
HAVE SAFE WORK PROCEDURES BEEN ESTABLISHED FOR THE FOLLOWING JOB
HAZARDS?
Sour operations.
Hot work.
Confined space / Restriced space entry.
Overhead power lines.
Hazardous materials.
Ground disturbances (buried pipelines, electrical, telephone)
Control Hazardous Energy
Pressure testing.
Radioactive sources.
Appropriate work procedures available on-site and posted as required.
Fall protection to include use of man basket & high angle rescue training.
Other non-regular operations. _____________________________
Well flow back operations including DST testing.
LEL Monitoring.
WORKER HEALTH AND SAFETY
Is appropriate personal protective equipment and other safety equipment available and
being used by all workers? (i.e. F. R. clothing).
Is the PPE and safety equipment in good working order and is there a preventative
maintenance and inspection program for equipment?
Is there special monitoring equipment available? (i.e. H2S, LEL).
Have you review local access hazards and speed limits?
TRAINING REQUIREMENTS
Have all workers on site completed an HARVARD Safety Orientation (Handbooks) and do
they have an orientation hardhat sticker?
Have you collected the orientation quizzes/acknowledgement sheets from the workers?
First Aid/CPR; verify number of qualified people available on site _______
H2S; verify number of qualified people on site ________.
Blow out prevention certification: Rig Manager ____ Drillers ____ Site Supervisor ____
WHMIS / TDG: Rig Manager ____ Drillers ____ Crew ____ Site Supervisor ____
CONTRACTOR SAFETY PROGRAMS
Do Contractors have safety programs in place and available on site?
ENVIRONMENTAL PROTECTION
Have fuels and chemicals are properly stored?
Is the required waste handling, storage and disposal procedures in place?
Have all spills been cleaned up immediately and reported?
CAMP (If Applicable)
Are there adequate smoke detectors and fire extinguishers?
Are regular emergency drills conducted, and do they correct deficiencies identified?
Have Camp Rules been posted at the main entrance and kitchen area of camp?
SUPERVISOR
DATE
Date Inspected:
Location:
Completed by:
1 = Acceptable
Item
SITE
Proper signage
Housekeeping. general appearance
Snow removal - sufficient or piled By
doors or on pipes.
Driving Hazards flagged
(risers, lines, etc)
Bull plugs in place
Fire extinguisher access and
inspection dates
Piping secured
Slipping and tripping hazards
Location access, road
Flammable liquid storage (safe
distance from heaters)
Proper storage of chemicals
Adequate WHIMIS labeling
Date PSVs serviced
Vegetation Control
Steps and handrails
Vibration
Shutdowns not bypassed
Safety equipment:
X = Unacceptable
SCBA
Burn Blankets
Date
Completed
Frequency of
Follow-up
(mo)
(day)
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
__________________ lbs.
Yes ______
No ______
__________________ lbs.
Yes ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Good ______
Good ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
Hazard ______
Hazard ______
Good ______
Good ______
Yes ______
Yes ______
Good ______
Hazard ______
Hazard ______
No ______
No ______
Hazard ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
POWER TONGS
46 Back-up in place and functional
47 Torque arms safety line, clamps in good
condition
48 Tong positioner - operational and in good
condition
49 Hoses, gauges and hydraulic fittings in good
condition
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Good ______
Yes ______
Hazard ______
No ______
Yes ______
Yes ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
Good ______
No ______
No ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
Hazard ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
MAST
27 Stand pipe properly anchored to mast
28 Kelly hose in good condition
29 Kelly hose safety lines or chain attached to derrick
and swivel ends while in use
30 Levels I, II, III or IV inspections completed as
required in CAODC RP 3.0
31 Ladders in good condition
32 Rod basket in good condition
N/A _______
33 Crown sheaves greased and in good condition
34 Safety cables attached to fingers on tubing board
35 Derrick locking pins in place
36 Derrick hydraulic system in good condition
37 Mast lighting secured adequately
38 Dead lines anchor and retainer properly placed
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
___________________________________________________________________________
COMMENTS/EXPLANATION:
DRAWWORKS
22 Conditions of drill line (slipped regularly)
(a) Slip and cut record
23 Sufficient wraps (min.7) left on drum with blocks
down
24 Braking system - Linkage/pin satisfactory
- Block wear
25 Condition of sandline & rope socket to sinker bars
26 Handling winch/line
Condition at:
- Winch anchor points
- Winch line
- Winch line thimble
- Tall chain
- Safety hook
- Hydraulic hoses & connections
- upper shivs & assembly
TRAVELING ASSEMBLY
39 Levels I, II, III or IV inspections completed as
required in CAODC RP 4.0
40 Blocks - nuts, safety pins in place and in
good condition
- Sheave guards/lock in good condition
41 Balls/links
- good condition
42 Elevators
- good condition
43 Rod hook
- good condition
44 Transfer elevators - good condition
45 Safety latch/ring in place
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
ELECTRICAL/LIGHTING
50 Light bulbs enclosed with vapour-proof and
shatter-proof covers
51 Covers on unused receptacles
52 Light switches vapour-proof
53 Electric motors within 8.5 metres radius must
be explosion-proof
54 Equipment properly grounded
55 All cords and plug ends in good condition
56 Proper clearance from power lines
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
RIG PUMP AND TANK
57 Condition of pipe and unions
58 Pump and return lines laid out and secured
59 Kill line attached to well with valve open
(steel lines only)
60 Pressure relief valve (proper size and rating)
61 Relief valve set at or below system working
pressure NOTE: Only shear pins appropriate
to the pop valve requirements as specified by
the manufacturer shall be used
62 Relief valve discharge points down and away
from pump motor and is securely fastened
NOTE: No valve on relief line
63 Manifold conditions
64 Check valve in place on pump discharge
65 Exhaust away from rig tank
66 Emergency shutoff checked and operational
67 Pump controls properly marked
68 All railings in place on walkways/stairs of rig
pumps and tank
Good ______
Yes ______
Hazard ______
No ______
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
Yes ______
No ______
Good ______
Yes ______
Yes ______
Yes ______
Yes ______
Hazard ______
No ______
No ______
No ______
No ______
Yes ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
DOCUMENTATION
69 Necessary transportation documentation and
equipment present (i.e. registration, insurance)
70 Required inspection certificates available
71 Derrick log book available and updated
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
F
COMMENTS/EXPLANATION:
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
BLOWOUT PREVENTER SYSTEM
72 BOP function tested - From remote controls
Yes ______
No ______
- From accumulator controls
Yes ______
No ______
73 All studs used on BOP stack
Yes ______
No ______
74 Hydraulic preventers installed
Yes ______
No ______
- Pipe rams
Yes ______
No ______
- Blind rams
Yes ______
No ______
- Annular preventer
Yes ______
No ______
75 Condition of ram rubbers and elements
Good ______
Hazard ______
76 Fire-shielded hoses and their condition within 7 metres
of wellhead
Good ______
Hazard ______
77 Remote stand 7 metres from well - Class I & II
- Refer to BOP regulations
Yes ______
No ______
- Or at remote accumulator - Class III
Yes ______
No ______
78 Nitrogen back-up supply pressure
__________________kPa
- Min. 12,500 kPa if annular preventer is installed
- Min. 7,000 kPa when only rams are installed
79 Pre-charge check date
____/____/____
Good ______
Hazard ______
80 BOP's adequately heated
Yes ______
No ______
81 Lines protected in vehicle crossing area when
remote accumulator is used
Yes ______
No ______
82 Safety valve fully opened with proper thread
connection on rig floor c/w closing wrench
Yes ______
No ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
ENVIRONMENTAL
83 All equipment free of leakage
- If no, adequately contained
84 Rig site free of material that may create a fire
hazard NOTE: Equipment spacing must ensure
unimpeded access to well at all times
Yes ______
Yes ______
No ______
No ______
Yes ______
No ______
COMMENTS/EXPLANATION:
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
Yes ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Good ______
Hazard ______
Yes ______
No ______
Yes ______
No ______
____/____/____
Yes ______
No ______
Yes ______
No ______
Yes ______
No ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Good ______
Hazard ______
Yes ______
No ______
Good ______
Hazard ______
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
BOILER
85 Chemical storage
86 Blowdown line labeled
87 Pop valve line labeled
88 Controls
- Labeled
- Condition
___________________________________________________________________________
Good ______
Yes ______
Yes ______
Yes ______
Good ______
Hazard ______
No ______
No ______
No ______
Hazard ______
COMMENTS/EXPLANATION:
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
Operator: _________________________
Derrickman: _______________________
Floorhand: ________________________
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Floorhand: ________________________
Other: ____________________________
Other: ____________________________
Other: ____________________________
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
BOP _________
H2S
First Aid
TDG
WHIMS
Boiler
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Exp. ____/____
Other: ____________________________
50 m
25 m
(A)
(I)
A. FUEL/WATER TANKS
(A)
01. No leaks
02. Pumps guarded
03. Signs at water/fuel tanks:
a) No smoking sign posted
b) Fuel sign posted
c) Dangerous Goods placard posted
B. BOILER HOUSE
04.
05.
06.
07.
08.
09.
10.
11.
12.
13.
No clothing etc.
Sight glass guarded
Pump guarded
Fire extinguisher
Safety valves: one year certificate
Boiler 25 m from wellheads
Housekeeping
Flammables removed from around boiler
Boiler License posted
Blow down line location & installation
of steam deflector
14. Fuel/water and steamline leaks
15. Chemical addition vessel (pot) at boiler
properly labeled (WHMIS)
C. GENERATOR BUILDING
16. Generator/motor control centre size; condition
17. Receptacles/circuit breakers identified
18. Properly grounded (2 grd rods 3 m apart)
19. Wiring off the ground & properly secured
20. No clothing/storage
21. Fans and belts guarded
22. No fuel/oil leaks
23. Compressor belts guarded
24. Fire extinguisher
25. All lights protected
26. Housekeeping
27. Rubber mat on floor at Motor Control Centre
28. Battery condition
29. Signs at Generator Building
a) Auto Start sings posted
b) Hearing Protection sign posted
c) Electrical/High Voltage signs posted
d) Water Hose Caution sign posted
e) Lockout and Procedures
30. Wiring/electrical fixtures condition
31. Current turned off prior to
connecting/disconnecting extension cords
65.
66.
67.
68.
69.
C. SUBSTRUCTURE
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
43.
No leaks/spillage
N2 bottles (12500 kPa/1800 psi)
Housekeeping
Storage of compressed gas cylinders,
secured
Controls identified/accessible
Safety device blind/sheer ram controls
Fire extinguisher
Grinder tool rest
Eye protection available
Compressor guarded
Signs at Accumulator and Tool House
a) Eye Protection signs posted
b) Auto Start signs: compressor / accum pump
c) Dangerous Goods placard/WHIMS label
Accumulator reservoir vented outside of
building/enclosure
General condition
Matting condition
Drive pins installed c/w safety pins
Spreaders in place
Vent doors/fan
Illumination
Winterization condition
Hydraulic control lines condition
fire guarded hose
Flow nipple split
Stripper/mud catcher split
Scaffolding/ladder(s) condition
Cellar area cribbed and drained
Wiring/electrical fixture condition
Housekeeping (oil leaks, etc.)
H. BOPS
84. BOP and rig equipment conform to
Government regulations
85. BOP secured properly
86. Non-steel hydraulic lines fire sheathed
87. Mud gas separator adequately connected
meets minimum requirements, including
line size and tie down
88. Required casing wear tests being preformed
89. BOP pressure tests recorded and test
procedures satisfactory
90. Adequate heating
91. Manual ram locking wheels available
I. DOGHOUSE
44.
45.
46.
47.
48.
49.
92.
93.
94.
95.
96.
97.
98.
99.
Page 1 of 3
(I)
(A)
(I)
100.
101.
102.
103.
104.
105.
106.
107.
(A)
165.
166.
167.
168.
K. RIG FLOOR
123.
124.
125.
126.
127.
128.
129.
130.
131.
132.
133.
134.
135.
136.
137.
138.
139.
140.
141.
142.
143.
144.
145.
146.
147.
148.
149.
150.
151.
152.
153.
Lockout on drawworks
Compound/drawworks guard
Crown saver (check)
Catline
Catline divider and spool
Spinning chain/wrench line
Headache post
Kelly cock condition
Kelly hose condition
Kelly hose safety line both ends
Line spooler/safety line
Backup post condition
Tongs condition
Tong line and tong line clamps
Slips condition
Dog collar condition
Stabbing valve and handle and X/O subs
Test plugs
Mud can condition
Drilling controls and identification
Brake handle hold-down cable/chain
Non-skid material around rotary
Lighting operational, floor and motor area
Motors:
a) Fans and belts guarded
b) No fuel/oil leaks
c) Motor shutoff
d) Fire extinguisher (No. ______)
e) Exhaust system
Stairs (min. 3 exits) from rig floor
Warning horn working
Hydromatic and guards
Brakes satisfactory
Tugger line condition, guards
V-door opening safety chained
Wiring/electrical fixture condition
O. MANIFOLD HOUSE
193. Heated
194. Valve handles installed
195. Proper gauges installed and positioned
196. Drill pipe pressure gauge installed
197. Unobstructed view to rig floor
198. Housekeeping
199. Manifold design meets Government requirements
200. Flare lines properly secured
201. Lighting operational
202. Choke/valve open to degasser
203. Well to:
- End of flare line 50 m
- Rubbish burn pile 50 m
- Crude oil storage tank 50 m
204. Signs at Manifold House:
a) Hold Back Pressure notice posted
b) No Smoking sign posted
205. Choke and degasser lines and manifold prepared
P. LEASE AREA
206.
207.
208.
209.
210.
211.
212.
213.
214.
Blocks
Bails/links
Elevators/latches
Weight indicator assembly
Weight indicator safety line
Automatic driller
Drilling line condition (slip/cut program)
Deadline anchor condition
Q. CAMP/GENERAL FACILITIES
215. Propane tanks location (No._______)
Propane distance from camp (min. 4 m)
216. Garbage disposal: incinerator - bins
217. Walkways
218. Kitchen First Aid kit
219. Kitchen fire extinguisher
220. Fire extinguisher (No._______)
Page 2 of 3
(I)
(A)
(I)
(A)
(I)
T. SAFETY/GENERAL
221. Generator Building:
a) Grounded
b) No clothing, storage
c) No fuel/oil leaks
d) Fire extinguisher
222. Furnace rooms
223. No unnecessary storage
224. Fire alarm system
225. Bedrooms exit to outside (shutters open)
226. Adequate distance from well centre
227. Housekeeping
228. Signs at Camp area:
a) Hearing Protection sign posted
229. Exit signs over doors installed and
illuminated
230. Emergency lighting installed and functional
231. Wiring/electrical fixtures condition
265.
266.
267.
268.
269.
270.
271.
272.
273.
274.
W. SPILL RESPONSE
S. TICKETS/DOCUMENTS (where not applicable)
284.
285.
286.
287.
Employees trained
Sorbents available
Spill response report form available
Emergency response procedure
X. WASTE MANAGEMENT
288.
289.
290.
291.
292.
Z. COMMENTS/EXPLANATIONS
Start Time:
Adjournment Time:
Chair Person:
Meeting Agenda:
Date:
Action #
Mo/Yr
Action By
Closure
Date
Action #
Mo/Yr
Action By
Closure
Date
New Business:
Action #
Mo/Yr
Action By
Closure
Date
Handouts Circulated:
Page 1 of 2
Action #
Mo/Yr
Action By
Closure
Date
Action #
Mo/Yr
Action By
Closure
Date
Hazard Alerts:
Action #
Mo/Yr
Action By
Closure
Date
Date:
Start Time:
Chair Person:
Attendee Sign In:
Topic:
Page 2 of 2
Location:
Date:
Task:
Flammable Gas
Flammable Liquids
Pressure
H2S
Iron Sulphides
NORM/Asbestos
Chemicals
Noxious Vapours (Benzene)
Rotating Equipment
Hot/Cold Piping Equipment
Muster Area
Air Monitoring
Isolation (Blinding/Blocking)
Forced Ventilation
SCBA/SABA
Safety Inspections (CAODC, walkabouts etc.)
Hearing Protection
Guards/Shields
Respirator
Wash Facilities
Audits/HSE Contract Inspections
CONTROLS
Printed Name
WORK
Permit
Hot
Clearance
Order
Supervision
Cold
Location:
Contractor:
Description of Work to be Done / Comments:
PERMIT No:
Issued by:
Issued by:
Phone No:
Phone No:
PROCEDURES
1
2
3
4
5
6
7
8
9
31
32
33
34
35
36
37
38
39
40
41
10
11
12
13
14
15
16
17
HAZARDS
Combustible Material Removed
Drains Covered/Sumps Covered and Sealed
No Vessels/Pumps to be Vented/Depressured
Overheard Lines, Clearance Established
Underground Line, Located & Identified
Other Hazardous Material
High Voltage
Intrinsically Safe Equipment
18
19
20
21
22
23
EMERGENCY PLANNING
Safe Egress from Work Areas Identified
Fire Extinguisher Ready to Use
Note: Completed checkbox , should be completed by permit receiver after
Steam/Water hose Ready to Use
all requirements have been met.
Emergency Air horn
ERP Manual Discussed
Atmosphere Testing (Explosive, Toxic & Oxygen Deficiency ) Record Below
RETESTS
Hours
N/A
RETESTS
Hours
N/A
N/A
RETESTS
Hours
N/A
FIRST TEST
Hours
AREA FREE OF
(appropriate box)
N
O
T
E
24
25
26
27
28
29
30
% LEL
ppmH2S
ppmH2S
% LEL
ppmH2S
ppmH2S
% LEL
ppmH2S
ppmH2S
% LEL
ppmH2S
ppmH2S
% O2
% O2
% O2
% O2
This permit is valid only as long as work conditions existing at the time of its issuance continue and expires upon occurrence of any hazard such as gas leak, liquid spill, drastic operating change in equipment, or change in
wind direction blowing vapours into the work area. Any worker will have the right to stop the job if he has reasonable grounds to believe that the job is, or likely to become unsafe. Work shall not resume until a new permit is
issued.
Time:
Expiry Date:
Time:
Approval by:
Accepted By:
Supervisor
Contractor Representative/Worker
completed or
cannot be continued until the issuance of a new work permit.
Signed:
Supervisor
Contractor Representative/Worker
Please ensure you have provided all information for the incident you are reporting
ENVIRONMENT
NEAR MISS
SAFETY
INJURY
VEHICLE
PROPERTY DAMAGE
DISTRICT:
FIELD:
MER
TIME
N
O
T
I
F
I
C
A
T
I
O
N
TWP
FINAL REPORT
Date Reported:
YYYY / MM / DD
SEC
INTERIM REPORT
Date of Occurrence:
LOCATION
LSD
RELEASE
YYYY / MM / DD
ERCB / MEM
TIME
Name:
Time:
Name:
Time:
WCB / OH&S
Name:
Time:
AEP / MELP
Name:
Time:
POLICE
Name:
Time:
LANDOWNER
Name:
Time:
PROVIDE AN EXACT DETAILED DESCRIPTION OF THE INCIDENT, NON CONFORMANCE AND / OR PROPERTY AFFECTED: (attach diagram if appropriate)
EQUIPMENT / VEHICLE INFORMATION - (including QMP)
SEVERITY POTENTIAL
Minor
INJURY INFORMATION
First Aid
Serious
PROBABILITY OF OCCURRENCE
Major
Medical Aid
Lost Time
Injured party:
Employee
Public
Occasional
Frequent
Other Specify
Address:
City:
Experience:
Seldom
Fatality
Name:
Postal Code:
UNIT NO.
Yrs
Phone #
Occupation:
Immediate Supervisor:
Modified Work
_________________________________________________________________________
Any product spill - Off Lease, Into a Water Course, or Over 2m on Lease is to be reported. On Lease spills under 2m do not need to be reported.
ENVIRONMENTAL
Liquid
Contained on Lease?
Yes
No
Other
Rehabilitation Required ?
Gas:
Discharged:
Sweet/Sour
H2S %:
Smoke:
Terrain Affected
Yes
No
Waste Manifest
Land
Yes
Water
No
Both
Public Complaint?
Other:
Discharged:
Discharged:
Discharged:
Recovered:
Recovered:
Yes
No
PW
Odour:
FW
Yes
No
Noise:
Yes
No
Recovered:
Yes
No
Wind Direction:
CONTROL MEASURES INCLUDING A DESCRIPTION OF CLEAN UP AND REHABILITATION: (Recovered product recycled? - Contaminated Soil? - Treated? Hauled Away? - Where?)
Quantab Values:
Amendments Applied:
Date:
Calcium Nitrate:
kg
Ammonium Nitrate:
kg
Government File:
Other:
Straw etc.
Line No:
Line OD (mm):
Grade:
MOP (kPa):
Type of Wrap:
Type:
Vessel I.D. #:
Repairs or Alterations
Internal Coat:
Yes
No
Page 1 of 2
Indicate
Final Costs
Estimated Costs
Covering Costs
Company
Third Party
What was the cause of the accident? (Determine the cause by analyzing all factors concerned. A person, a machine, or a physical condition? How? Why?
HAZARDOUS SUBSTANCE
HAZARDOUS ATMOSPHERE:
INADEQUATE VENTILATION
EXCESSIVE NOISE
POOR HOUSEKEEPING
RADIATION EXPOSURE
VIOLENCE / HARASSMENT
FAILURE TO SECURE / LOCK-OUT
UNNECESSARY HASTE
HORSEPLAY
UNAWARE OF HAZARD
FATIGUE
Explain what you have done or what you recommended to prevent a recurrence of a similar incident / accident
SIGNATURE: INSPECTOR
DATE
FOLLOW-UP ASSIGNMENTS:
WHO?
WHEN?
WHAT?
INCIDENT REPORTED BY
FORWARD REPORT TO:
DATE
SUPERINTENDENT / MANAGER
Page 2 of 2
This report is required as part of Harvard obligations under the Occupational Health & Safety Act of Alberta and is subject to the protections of sections 18 and 19 of that act. Further, any
statements given herein are made subject to the protections provided by section 6 of the Alberta Evidence Act and section 5 of the Canada Evidence Act to the extent that they may apply.
Date:
Company:
HARVARD is committed to protecting the health and safety of all workers on our sites. Part of
this commitment is the expectation that all workers be familiar with and follow standard
guidelines and procedures. The initial step to accomplish this is an orientation to our Health,
Safety & Environment Handbook. This review checklist is intended to ensure that workers have
the basic knowledge associated with the HS&E handbook.
Complete the following questions by either circling the correct answer or filling in the blank(s) if
answers are not provided. It is acceptable to use the handbook to find the answers. Return the
review checklist to your supervisor or HARVARD Representative.
POLICY ON HEALTH, SAFETY & THE ENVIRONMENT
1) Who is responsible for protecting the health and safety of people and preserving the quality
of the environment:
a)
b)
c)
d)
employees
management
contractors
everyone
carry on as usual
refuse to perform the task
be extra careful as you carry out the assigned task
ask someone else to do the job for you
3) What must you do if you refuse to perform a task because there is imminent danger:
a)
b)
c)
d)
Page 1 of 6
EMERGENCIES
4) Local emergency phone numbers must
a)
b)
c)
d)
communication device
siren
flashing light
high ground clearance to be able to get off the lease
8) Smoking is permitted:
a)
b)
c)
d)
9) You are not permitted to do which of the following at an HARVARD work site:
a)
b)
c)
d)
Page 2 of 6
CONTRACTOR REQUIREMENTS
10) It is the Contractors responsibility to:
a)
b)
c)
d)
provide all tools, safety equipment, proper clothing for their workers
enforce all policies and procedures outlined in the HSE handbook
take steps necessary to ensure the safety of your employees and sub-contractors
all of the above
ensure that appropriate first aid supplies and services are on site
determine if an ambulance is required and where it is to be positioned
ensure that workers are aware of the location of all first aid supplies
all of the above
13) At work sites where there is a possibility for hydrocarbon release, clothing requirements
include:
a)
b)
c)
d)
HAZARDS
14) When lighting fired heaters and furnaces, face shields and gloves must be worn:
a) true
b) false
Page 3 of 6
16) Prior to any work being done in an area containing a flammable substance, testing may be
necessary:
a) true
b) false
H2S monitoring equipment is turned on and used at all times while on location
communication equipment is in good working order
a breathing apparatus in working order and with an adequate supply of air must be available
all of the Above
19) What is the maximum acceptable noise level on a worksite over an eight hour work period?
a) 80 dBA
b) 90 dBA
c) 75 dBA
d) 85 dBA
20) A written fall protection plan must be in place before work commences on a task where
there is a potential of a fall of more than:
a) metre
b) 10 metres
c) 20 metres
d) 3 metres
22) Employers should hold regular safety meetings at least once a month for the following
purposes:
a)
b)
c)
d)
Page 4 of 6
23) Before beginning any work at a HARVARD location, you must determine if a work permit
or work clearance is required.
a) true
b) false
a permit that is used for ongoing tasks where specific guidelines have been established
a permit that is issued for a maximum of one year
a permit that requires specialized blankets to keep the workers protected from the cold
both a & b
ENVIRONMENT
26) Only supervisors are responsible for meeting regulations and industry guidelines:
a) true
b) false
27) We must all take necessary steps to prevent spills and control emissions:
a) true
b) false
SOUR SERVICE
28) A facility is considered sour at:
a) 1 PPM H2S or greater
b) 10 PPM H2S or greater
c) 100 PPM H2S or greater
d) 1000 PPM H2S or greater
wildlife sightings
unsafe acts and/or conditions
incidents and infractions
b and c
Page 5 of 6
GOOD HOUSEKEEPING
31) Good housekeeping is:
a) only a minor issue
b) good to do when you have the time
c) mandatory
WHMIS/TDG
32) Before handling chemicals you should:
a)
b)
c)
d)
DRIVING CONDUCT
33) In general all ATV (All Terrain Vehicle) riders must
a)
b)
c)
d)
34) Driving incident are the leading cause of injury, fatalities and property damage in the oil and gas
industry.
a) true
b) false
Page 6 of 6
ANSWER KEY
HS & E HANDBOOK REVIEW QUESTIONNAIRE
ANSWER KEY
Date:
Company:
HARVARD is committed to protecting the health and safety of all workers on our sites. Part of
this commitment is the expectation that all workers be familiar with and follow standard
guidelines and procedures. The initial step to accomplish this is an orientation to our Health,
Safety & Environment Handbook. This review checklist is intended to ensure that workers have
the basic knowledge associated with the HS&E handbook.
Complete the following questions by either circling the correct answer or filling in the blank(s) if
answers are not provided. It is acceptable to use the handbook to find the answers. Return the
review checklist to your supervisor or HARVARD Representative.
POLICY ON HEALTH, SAFETY & THE ENVIRONMENT
1) Who is responsible for protecting the health and safety of people and preserving the quality
of the environment:
a) employees
b) management
c) contractors
d) everyone
carry on as usual
refuse to perform the task
be extra careful as you carry out the assigned task
ask someone else to do the job for you
3) What must you do if you refuse to perform a task because there is imminent danger:
a) leave the site immediately
b) go have coffee
c) notify the supervisor of your reasons
d) reconsider and carry on with the task
Page 1 of 6
EMERGENCIES
4) Local emergency phone numbers must
a) not be worried about
b) be confirmed and posted
c) be memorized
d) all of the above
8) Smoking is permitted:
a) in designated areas only
b) where ever you want
c) outside of buildings only
d) beside vehicles only
9) You are not permitted to do which of the following at a HARVARD work site:
a) to be under the influence of or in possession of drugs or alcohol
b) to engage in practical jokes
c) to harass other workers because of their race, sex, age or religion.
d) all of the above
Page 2 of 6
CONTRACTOR REQUIREMENTS
10) It is the Contractors responsibility to:
a) provide all tools, safety equipment, proper clothing for their workers
b) enforce all policies and procedures outlined in the HSE handbook
c) take steps necessary to ensure the safety of your employees and sub-contractors
d) all of the above
13) At work sites where there is a possibility for hydrocarbon release, clothing requirements
include:
a) fire retardant clothing as the outside layer
b) natural fiber clothing such as wool or cotton as inner wear
c) nylon outerwear
d) both a & b
HAZARDS
14) When lighting fired heaters and furnaces, face shields and gloves are to worn:
a) true
b) false
Page 3 of 6
16) Prior to any work being done in an area containing a flammable substance testing may be
necessary:
a) true
b) false
19) What is the maximum acceptable noise level on a worksite over an eight hour work period?
a) 80 dBA
b) 90 dBA
c) 75 dBA
d) 85 dBA
20) A written fall protection plan must be in place before work commences on a task where
there is a potential of a fall of more than:
a) metre
b) 10 metres
c) 20 metres
d) 3 metres
22) Employers should hold regular safety meetings at least once a month for the following
purposes:
a) to report current accidents or diseases, their causes and prevention
b) to see whose been slacking off on the work sites
c) to determine if there are any matters pertinent to health and safety
d) both a & c
Page 4 of 6
23) Before beginning any work at a HARVARD location you must determine if a work permit
or work clearance is required.
a) true
b) false
ENVIRONMENT
26) Only Supervisors are responsible for meeting regulations and industry guidelines:
a) true
b) false
27) We must all take necessary steps to prevent spills and control emissions:
a) true
b) false
SOUR SERVICE
28) A facility is considered sour at:
a) 1 PPM H2S or greater
Page 5 of 6
GOOD HOUSEKEEPING
31) Good housekeeping is:
a) only a minor issue
b) good to do when you have the time
c) mandatory
WHMIS/TDG
32) Before handling chemicals you should:
a) review the MSDS sheet
b) carefully breathe in the vapours to see if they are harmful
c) make sure no one else is in the area
d) move the chemicals outside
DRIVING CONDUCT
33) In general all ATV (All Terrain Vehicle) riders must
a) be competent in their ability to operate an ATV
b) drive the ATV in accordance with local regulations
c) possess a valid drivers license for insurance purposes
d) all of the above
34) Driving incidents are the leading cause of injury, fatalities and property damage in the oil and gas
industry:
a) true
b) false
Page 6 of 6
Note: If unsatisfactory is selected, an explanation must be provided in the Comments section. The contractor is
responsible to ensure that all deficiencies in this inspection are corrected.
Management Involvement
Comments:___________________________________________________________________________________________
Records Management and documentation
1. Is all critical data for operation and environmental concerns stored onsite and updated?
Comments: _________________________________________________________________________________________
Quality Management
Comments: _________________________________________________________________________________________
Communication
1. Is the permit system being used? (ie:safe work permits, hot work permits)
2. Are Loss Control Meetings taken place in a timely manner?
3. Are Risk Management and OH&S bulletins posted and discussed?
Comments: _________________________________________________________________________________________
Emergency Response Planning
Comments: _________________________________________________________________________________________
Hazard Identification Control
1. Are Equipment and vehicles inspected and at what frequency? (Show examples and completed documentation.)
2. Is there a system for hazard assessment, reporting and follow-up (written or verbal)?
Comments: _________________________________________________________________________________________
Page 1 of 3
1. Are there procedures for high risk or critical work? Are they available and used?
2. Are there written emergency plans available and communicated to personnel at the work site?
i) ERP
Comments: _________________________________________________________________________________________
Incident Reporting
1. Do you have an incident reporting process?
2. Do you have a near miss/incident reporting form that includes follow-up?
3. Are incidents reported and was the problem rectified the previous near miss or accident, and were management
Comments: _________________________________________________________________________________________
Training
1. Have you received a safety orientation? (What and When)
2. How often are Loss Control meetings held? (Show examples and documentation)
3. Is the appropriate training in place?
4. First Aid Training
5. H2S Training
6. WHMIS Training
7. TDG Training
8. Fire Extinguisher or Fire Fighting Training
9. Job Specific Training/Certification
Personal Protective Equipment
1. Is the appropriate PPE available and being used?
2. Hard Hat
3. Safety Glasses or Eye Protection
4. Footwear
5. Protective Clothing
6. Hearing Protection
7. Respiratory Protection (For the Nature of the Hazard)
8. Personal Monitor or H2S Detector
9. Communication Equipment
N/A
N/A
Comments: ________________________________________________________________________________________
Safety Equipment
1. Is the appropriate Safety Equipment available and being used?
2. Fire Fighting Equipment (ie: inspected, tagged, accessible and condition)
3. Rotating Equipment Guards
4. First Aid Kit
5. Fall Arrest Equipment (including ladders, steps or stairways, safety belts and lanyards)
6. Bonding and Grounding Equipment
7. Emergency Shut Down and Alarm Systems (including diesel positive air shutoffs and backup alarms)
N/A
Comments: __________________________________________________________________________________________
Page 2 of 3
Contractors
N/A
1. Is the contractor aware of the safety expectations and standards of the Corporation?
Comments: __________________________________________________________________________________________
Environmental, Storage and Handling
1.
2. D-58 Compliance (Proper waste storage, ie: filters, contaminated soil and fluid. Show waste manifests.)
3. D-55 Compliance (ie: double walled tanks, tank condition, secondary containment.)
Comments____________________________________________________________________________________________
NO
PHOTOCOPY DISTRIBUTION:
Page 3 of 3
DATE: _________________
CONTRACTOR: _______________________________________________________________
SAFETY
First Aid Kits on Site
Contractor has Safety Program on Site and
Responsible for Worker Safety
Safety Meeting Requirements Established
Safety Committee (Multi-Contractor)
Contractor Safety Meetings
Tailgate Meetings
Housekeeping Procedures Reviewed
Work Permit Requirements Established
Safety Equipment Requirements Determined
Personal Protection Equipment Requirements
Determined
Location of Safety and Emergency Equipment
Established
Driving Procedures Established
Vehicle and Equipment Operation Procedures
Established
Accident/Incident Reporting Procedures Reviewed
Authority of Supervisor to Shut Down Work
Identified
HAZARD REVIEW
PROJECT SCOPE
Scope of Work Reviewed
Restricted Work Areas Established (Where
Applicable)
Project Schedule Reviewed
Hours of Work Established
EMERGENCY
Harvard Emergency Response Plan
Reviewed
Emergency Procedures Reviewed
Contact Information Sheet Posted
Safe Areas Established
First Aid Personnel Identified
Fire Extinguisher Stations Established
Method to Track Number of Workers on Site
Established
Plant Emergency Alarm Operation (Where
Applicable)
OTHER (list)
ENVIRONMENTAL REVIEW
Topsoil Handling and Site Grading
Fuel and Chemical Storage
Waste Handling, Storage and Disposal
Equipment Oil Changes
______
_______
Section 15-3
DATE:
OPERATION:
PIPELINE
SITE/LOCATION:
CONTRACTOR(S):
CONTRACTOR SUPERVISOR(S):
Harvard REPRESENTATIVE:
OUTSTANDING CONCERNS:
RECOMMENDED ACTION:
TARGET DATE:
NEW CONCERNS:
RECOMMENDED ACTION:
TARGET DATE:
TRAINING GIVEN:
_______________________________________
REPRESENTATIVE SIGNATURE
MEETING DATE:
NAME
SIGNATURE
RECORD CONFIRMATION
YES
NO
N/A
1. Do you have a copy of the Survey Drawing for the well site, access road, and/or proposed ground disturbance area?
*NOTE* If the survey drawing is older than 60 days, consideration should be given to getting an updated survey drawing.
2. Do you have a copy of the Surface Acquisition report?
3. Does the survey drawing Table of Crossing match with the Surface Acquisition Report Table of Crossings?
4. If questions 1-3 are N/A, has the proposed area of the disturbance and buffer zone been electronically scanned?
5. Do you have a recent copy of the Land Title Certificate or Public Land Standing Report?
6. Do you have a copy of the most recent Provincial/Company Pipeline baseline map?
7. Did you notify the Land Agent (Crown Land) or Land Owner (Freehold Land) of your intentions and review any existing underground
facilities? Name:
8. Do you have a copy of all Crossing Agreements for any facility identified within 30 metres of the work area?
9. Did you adhere to the crossing notification requirements?
10. Did you contact local Production office and review scope of work and crossings?
Name:
11. Have all pipelines, power lines, and utilities in the 30 metre search/controlled area been identified?
12. Has the One Call System been notified of our intentions?
VISUAL INSPECTION
1. Are all buried pipelines, power lines, or utilities identified on above drawings, and staked on the ground in proposed area?
2. Are overhead power line Caution Signs in place?
3. Are all the locate stakes or marks referenced to fixed features?
4. Are all of the lines within the 30 meter search/controlled zone identified on the ground?
5. Are there any signs of new ground disturbances within the proposed working area, including the search/controlled zone? This may
include pipelines, power lines, Gas Co-op, utility cables, new clearings, road construction, pipeline signs, settlement, vegetation
color change or growth. If there is any visual sign of activity that is not reflected on Survey Drawing, re-surveying should be
considered.
PRE-CONSTRUCTION
1. Is the proposed ground disturbance expected to be any depth below the surface?
*CAUTION* - any depth below the surface is a general rule. Ground disturbances located at any depth may encounter lines
improperly installed or changed due to shifting ground disturbances. Additional crossing material should be considered.
2. Are there any pipelines, power lines, or utility cables being crossed within the 5 meters where no right-of-way or within the distance
outline in crossing agreements?
3. Are ALL the conditions of the Crossing Agreements being met?
4. Have all the underground facilities been exposed as per the company requirements, crossing agreements, and the Regulations?
5. Distance to which mechanical equipment may be operated after exposure from agreement
mm
6. Did you conduct a pre-job task meeting with foreman and equipment operators? Review Procedures & ERP.
NOTE: This document is designed to be a GUIDE to the minimum safety standards for Ground Disturbance. Refer to the Provincial Regulations, Company Standard
Safety Practices Manual, contractors safety program, and Provincial Health & Safety Statute and Regulations for further details. If project involves interprovince activity, the National Energy Board has additional requirements. SEE NEXT PAGE FOR REFERENCES.
Comments:
Company
Representative:
Ver. 1.0
Contractor
Representative:
DEFINITIONS
GROUND DISTURBANCE - is any work, operation, or activity without limitation that results in a disturbance of
the earth at any depth.
SEARCH AREA- is the 30 meters surrounding the ground disturbance area in which all reasonably necessary
precautions must be taken to determine whether or not an underground facility exists.
NOTIFICATION - Every owner within the ground disturbance area and the 30 meter search area must be
notified of the nature and schedule of the ground disturbance. Notification must be done as per the crossing
agreement or as per provincial Regulations of a minimum of 2 working days and a maximum of 7 working
days, or greater, as specified in the crossing agreement.
CROSSING AGREEMENTS (also referred to as APPROVALS) - Anytime a ground disturbance takes place
within a right-of-way, or within 5 meters of a facility where there is no right-of-way, an approval must be in
writing.
NOTE: A crossing agreement is commonly used as the approval and does not mean an actual crossing is
taking place.
HAND EXPOSURE - Hand exposure must be done if the ground disturbance crosses or is carried out within 5
meters of an existing underground facility before commencing any mechanical excavation. When exposing the
underground facility it must be done sufficiently to identify the facility. Excavation techniques have been
developed using water or air jets. These have generally been accepted, although all procedures may not have
specific regulatory approval. Care should be taken to evaluate the best method of hand exposure, taking into
consideration, damage to coatings, and methods of soil disposal.
CAUTION:
Even after hand exposure, mechanical equipment must not be used within the distance
specified on the crossing agreement, OR, if a crossing agreement is not present, not closer than
60 cm. to the underground facility.
REFERENCES
ITEMS # 1, 2, 3, 5, & 6
ITEM # 5:
ITEM # 10:
ITEM # 12:
GENERAL:
Ver. 1.0
The Provincial Acts and Regulations should be available for reference and further resources.
Date:
INSURANCE
Yes
No
Yes
No
A. Certificate of Insurance
B. $2 million minimum general commercial liability insurance
C. $2 million minimum automotive liability insurance
D. Worker's Compensation coverage
SAFETY PROGRAM
A. Has the contractor submitted a current safety program manual?
B. Does the program meet the criteria of the base safety program?
ACCIDENT HISTORY
A. Workers Compensation:
WCB Number:
Statement Date:
Employer Rate:
Industry Rate:
Statement Date:
Employer Lost Time Rate:
Industry Lost Time Rate:
DESCRIPTION
DESCRIPTION
Page 1of 1
Crossing
Agreement Number
PROJECT:
AB/BC LSD
BC QTR UNIT
SEC
TWP
RGE
/MAP
BLOCK
SUB DIV
SHEET
Depth Existing
Depth New
River
Bed
Existing
Depth
OR
Depth New PL
Depth
Depth Existing
Grade
Cased
Uncased
Existing
Road, RR X-ing River/Creek
Pipeline - R/W
INDICATE:
1.
2.
3.
4.
Approval
Print Name
Date Completed
Company Signature
Print Name
Date Completed
Contract Signature
Ver 1.0
R/W
Drilling/Completions/Workovers
Pre-job Safety Meeting Form
Date:
_______________________________________________________________________
Location: _______________________________________________________________________
______________________________________________________________
Persons in Attendance
Name (Please Sign)
Company
Date:________________________
Contractor:____________________
Project#:_____________________
Employees Present:
Print
________________________________
________________________________
________________________________
________________________________
________________________________
________________________________
Signature
_____________________________
_____________________________
_____________________________
_____________________________
_____________________________
_____________________________
No
N/A
Action to be Taken
Location of:
Buried Cables
Overhead Lines
Wellhead
Sumps
Digging Sumps
Towing of Trucks
Ditch Cut
Digging Burrows/Snakepits
Driving Speed Limits
Other Personnel/Equipment
PPE Required
Emergency Contact #s
Other
Other
Buried Pipelines
Worksite Plan
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
_______________________
____________________
Signature
________________________________
___________________________
Signature