Anda di halaman 1dari 18

RESUMEN GENERAL VALORIZACIN N 01

NOVIEMBRE 2016

OBRA
UBICACIN
PROPIETARIO
EJECUTOR
SUPERVISION
SUPERVISOR
RESIDENTE
PRESUPUESTO BASE

S/

INC IGV

PRESUPUESTO CONTRATADO

S/

INC IGV

PRESUPUESTO CONTRATADO

S/

ITEM

SIN IGV
FECHA

NOVIEMBRE 2016

FECHA PRESUPUESTO

SETIEMBRE DEL 2016

DESCRIPCION

ACTUAL

1.00

VALORIZACIONES

660,069.66

1.10

VALORIZACIN N01 (26 OCTUBRE -30 NOVIEMBRE 2016)

660,069.66

2.00

REAJUSTES

2.10

PRESUPUESTO CONTRACTUAL
SUB TOTAL

660,069.66

3.00

TOTAL

660,069.66

4.00

AMORTIZACIONES DE ADELANTOS

198,020.90

4.10

ADELANTO DIRECTO

4.20

AMORTIZACION DEL ADELANTO DIRECTO 10%


ADELANTO DE MATERIALES
AMORTIZACION DE ADELANTO DE MATERIALES 20%

5.00

D.R.Q.N.C.

5.10

ADELANTO DIRECTO

5.20

ADELANTO DE MATERIALES

0.00

6.00

RETENCIONES

0.00

6.10

RETENCION POR ATRAZO

7.00

TOTAL GENERAL ( 3 - 4 + 5 + 6 )
IGV

66,006.97
66,006.97
132,013.93
132,013.93
0.00

0.00
462,048.76

18%

83,168.78

VALORIZACION N. 01
6.00

PENALIDADES

6.10

MULTA POR DEMORA EN TERMINO DE OBRA

7.00

SALDO A CANCELAR

545,217.54
Multa por Aplicar S/.
0.00

Monto a cancelar en efectivo


Monto a cancelar del IGV
MONTO FACTURADO A CANCELAR

VALORIZACION N. 01

Multa Aplicada S/.


0.00

N GENERAL VALORIZACIN N 01
NOVIEMBRE 2016

Saldo a Reintegrar
0.00
Montos S/.
S/.

462,048.76

S/.

83,168.78

S/.

545,217.54

CONTROL DE AMORTIZACIONES - VALORIZACION N01 - 2016


OBRA

EJECUTA
SUPERVISION
SUPERVISOR
RESIDENTE
MES VALORIZADO
MONTO DEL PRESUPUESTO BASE
FECHA PRESUPUESTO BASE
MONTO DEL PRESUP. CONTRATADO CON IGV:
FACTOR DE RELACION
ADELANTO DIRECTO EN EFECT. CON IGV 18%:

A) AMORTIZACION DEL ADELANTO DIRECTO

Valorizacion N

Fecha

01

02 JUNIO-15JUNIO 2016

Adelanto en
Efectivo sin IGV

Valorizacin de Obra

S/.

AMORTIZACION
MES (S/.)

0.00

660,069.66

66,006.97

0.00

660,069.66

66,006.97

02
03
04
05
06
07
08

TOTAL

AMORTIZACION ACUMULADA - ADELANTO DIRECTO

66,006.97

AMORTIZACION ACUMULADA ANTERIOR


AMORTIZACION DEL MES

0.00
66,006.97

PORCENTAJE DE ADELANTO EN EFECTIVO

10.00%

AMORTIZACION DEL ADELANTO DIRECTO


PORCENTAJE
AMORTIZADO
10.00%

ACION N01 - 2016

(incl. I.G.V.)
(incl. I.G.V.)
% AUTORIZADO

AMORTIZACION DEL ADELANTO DIRECTO


AMORTIZACION
ACUMULADA
66,006.97

SALDO A
AMORTIZAR
(66,006.97)

(66,006.97)

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
01
01.01

Descripcin
OBRAS PROVISIONALES
ALMACEN, OFICINA DE OBRAS

Und.

Metrado

mes

6.00

Precio S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

300.00

1,800.00

0.00%

0.00

1.00

17.00%

300.00

1.00

17.00%

300.00

5.00

83.00%

1,500.00

3,068.06
48,960.00

0.00%
0.00%

0.00
0.00

2.00
0.30

100.00%
30.00%

3,068.06
14,688.00

2.00
0.30

100.00%
30.00%

3,068.06
14,688.00

0.70

0.00%
70.00%

0.00
34,272.00

01.02

CARTEL DE OBRA 3.00 X 5.00 M UNA CARA

und

2.00

1,534.03

01.03

MOVILIZACION Y DESMOVILIZACION DE EQUIPOS

glb

1.00

48,960.00

02
02.01

SEGURIDAD Y SALUD
EQUIPOS DE PROTECCION INDIVIDUAL

und

1.00

386.06

386.06

0.00%

0.00

1.00

100.00%

386.06

1.00

100.00%

386.06

02.02

EQUIPOS DE PROTECCION COLECTIVA

und

1.00

2,500.00

0.00%

0.00

1.00

100.00%

2,500.00

1.00

100.00%

2,500.00

0.00%

0.00

1.00
1.00

1,962.21
666.07

2,500.00
1,962.21

und
und

0.00%
0.00%

0.00
0.00

0.20
1.00

20.00%
100.00%

392.44
666.07

0.20
1.00

20.00%
100.00%

392.44
666.07

0.80
-

80.00%
0.00%

1,569.77
0.00

m2

21.70

1.17

25.39

m2

21.70

2.84

61.63

0.00%
0.00%

0.00
0.00

21.70

0.00%
100.00%

0.00
61.63

21.70

0.00%
100.00%

0.00
61.63

21.70
-

100.00%
0.00%

25.39
0.00

24.93

486.88

02.03
02.04
03
03.01
03.01.01
03.01.01.01
03.01.01.02
03.01.02

SEALIZACION TEMPORAL DE SEGURIDAD


RECURSO PARA RESPUESTA ANTE EMERG. EN SEGUR. Y SALUD DURANTE EL TRABAJO
SISTEMA DE AGUA POTABLE

666.07

0.00%

0.00

CAPATACION DE AGUA
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

03.01.02.01

EXCAVACION MANUAL DE ZANJAS

m3

19.53

486.88

0.00%

0.00

0.00%

0.00

0.00%

0.00

19.53

100.00%

03.01.02.02

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

21.70

2.61

56.64

0.00%

0.00

0.00%

0.00

0.00%

0.00

21.70

100.00%

56.64

03.01.02.03

ELIMINACION DE MATERIAL EXCEDENTE

m3

24.41

15.32

373.96

0.00%

0.00

0.00%

0.00

0.00%

0.00

24.41

100.00%

373.96

03.01.03
03.01.03.01

OBRAS DE CONCRETO SIMPLE


CONCRETO f'c=175 kg/cm2

m3

3.00

374.56

1,123.68

0.00%

0.00

0.00%

0.00

0.00%

0.00

3.00

100.00%

1,123.68

03.01.03.02

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

m2

20.70

36.22

749.75

03.01.03.03

PISO ASENTADO C/MAMPOSTERIA DE PIEDRA 1:5 +70% PM

m2

1.03

427.21

440.03

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

20.70
1.03

100.00%
100.00%

749.75
440.03

03.01.04
03.01.04.01

OBRAS DE CONCRETO ARMADO


ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

kg

117.51

5.23

614.58

0.00%

0.00

0.00%

0.00

0.00%

0.00

117.51

100.00%

614.58

03.01.04.02

ENCOFRADO Y DESENCOFRADO NORMAL

m2

38.00

52.84

2,007.92

03.01.04.03

CONCRETO fc = 210 kg/cm2

m3

3.89

435.50

1,694.10

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

38.00
3.89

100.00%
100.00%

2,007.92
1,694.10

m2

9.69

22.83

221.22

0.00%

0.00

0.00%

0.00

0.00%

0.00

9.69

100.00%

221.22

m2

11.80

19.76

233.17

0.00%

0.00

0.00%

0.00

0.00%

0.00

11.80

100.00%

233.17

m2

11.80

17.18

202.72

0.00%

0.00

0.00%

0.00

0.00%

0.00

11.80

100.00%

202.72

glb

1.12

25.64

28.72

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.12

100.00%

28.72

MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.6M x 0.6M

und

1.00

487.55

487.55

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

487.55

MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.4M x 0.4M

und

1.00

349.21

349.21

SUMINISTRO E INSTALACION DE ACCESORIOS EN CAPTACION

glb

1.00

155.55

155.55

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

1.00
1.00

100.00%
100.00%

349.21
155.55

03.01.05
03.01.05.01
03.01.05.02

REVOQUES ENDUCIDOS Y MOLDADURAS


TARRAJEO MUROS INTERIORES
TARRAJEO MUROS EXTERIORES

03.01.06

PINTURA

03.01.06.01
03.01.07

PINTURA LATEX EN MUROS EXTERIORES


FILTROS

03.01.07.01
03.01.08
03.01.08.01
03.01.08.02
03.01.08.03

SUMINISTRO DE FILTRO CON MATERIAL GRAVA Y ARENA


TAPAS METALICAS Y ACCESORIOS

03.01.09

PRUEBA Y CONTROL DE CALIDAD

03.01.09.01
03.01.10

PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)


CERCO PERIMTRICO

03.01.10.01
03.02
03.02.01
03.02.01.01

CERCO PERIMTRICO

9.00

25.00

225.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

9.00

100.00%

225.00

24.00

29.24

701.76

0.00%

0.00

0.00%

0.00

0.00%

0.00

24.00

100.00%

701.76

0.00%
0.00%

0.00
0.00

5,594.96
945.27

100.00%
17.00%

9,791.18
1,881.09

5,594.96
945.27

100.00%
17.00%

9,791.18
1,881.09

4,649.69

0.00%
83.00%

0.00
9,252.88

0.00%

0.00

945.27

17.00%

1,077.61

945.27

17.00%

1,077.61

4,649.69

83.00%

5,300.65

und

LINEA DE CONDUCCION CAPTACION - RESERVORIO


TRABAJOS PRELIMINARES
TRAZO, NIVELACION Y REPLANTEO INICIAL

5,594.96

1.75

9,791.18

03.02.01.02

TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO

5,594.96

1.99

03.02.01.03

LIMPIEZA DEL TERRENO MANUAL

5,594.96

1.14

11,133.97
6,378.25

03.02.02

MOVIMIENTO DE TIERRAS

03.02.02.01

LIMPIEZA DEL TERRENO MANUAL

5,594.96

1.14

6,378.25

0.00%

0.00

945.27

17.00%

1,077.61

945.27

17.00%

1,077.61

4,649.69

83.00%

5,300.65

03.02.02.02

EXCAV. ZANJAS C/EQUIPO EN TSR ANCHO =0.60 H=1.00m

5,594.96

7.93

0.00%

0.00

945.27

17.00%

7,495.99

945.27

17.00%

7,495.99

4,649.69

83.00%

36,872.04

REFINE, NIVELACION Y FONDOS P/TUB PVC EN TSR ANCHO 0.60m


PREPARACION CAMA DE APOYO P/FONDOS TUB. PVC. e=0.10M TSR A=0.6M

m
m

5,594.96
5,594.96

1.63
7.41

44,368.03
9,119.78

03.02.02.03
03.02.02.04

0.00%

0.00

945.27

17.00%

1,540.79

945.27

17.00%

1,540.79

4,649.69

83.00%

7,578.99

41,458.65

0.00%

0.00

0.00%

0.00

0.00%

0.00

5,594.96

100.00%

41,458.65

03.02.02.05

RELLENO COMPACTADO ZANJA H<1.5M

5,594.96

6.90

38,605.22

ELIMINACION DE MATERIAL EXCEDENTE

m3

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

5,594.96
436.41

100.00%
100.00%

38,605.22
6,685.80

436.41

15.32

6,685.80

SUMINISTRO E INST. DE TUBERIAS PVC


SUMINISTRO E INSTALACION DE TUB. U.F. D.N. 75mm C-7.5

2,615.14

14.15

37,004.23

0.00%

0.00

0.00%

0.00

0.00%

0.00

2,615.14

100.00%

37,004.23

03.02.03.02

SUMINISTRO E INSTALACION DE TUB. U.F. D.N. 63mm C-7.5

2,976.82

13.94

03.02.03.03

ACCESORIOS PARA LINEA DE CONDUCCION

glb

1.00

992.98

41,496.87
992.98

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

2,976.82
1.00

100.00%
100.00%

41,496.87
992.98

5,594.96

0.54

3,021.28

0.00%

0.00

0.00%

0.00

0.00%

0.00

5,594.96

100.00%

3,021.28

03.02.02.06
03.02.03
03.02.03.01

03.02.03.04
03.03
03.03.01

PRUEBA HIDRAULICA PARA AGUA


RESERVORIO 17 m3 - PACHACAYO

TRABAJOS PRELIMINARES

03.03.01.01

LIMPIEZA MANUAL DE TERRENO NORMAL

m2

12.60

1.17

14.74

0.00%

0.00

12.60

100.00%

14.74

12.60

100.00%

14.74

0.00%

0.00

03.03.01.02

TRAZO Y REPLANTEO INICAL

m2

12.60

2.84

35.78

0.00%

0.00

12.60

100.00%

35.78

12.60

100.00%

35.78

0.00%

0.00

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
03.03.01.03
03.03.02

Descripcin
TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO

Und.

Metrado

Precio S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

12.60

1.99

25.07

0.00%

0.00

12.60

100.00%

25.07

12.60

100.00%

25.07

0.00%

6.30

30.00

189.00

0.00%

0.00

6.30

100.00%

189.00

6.30

100.00%

189.00

0.00%

0.00
0.00

0.00%

0.00

100.00%

125.47

12.60

100.00%

20.54

MOVIMIENTO DE TIERRAS

03.03.02.01

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

m3

03.03.02.02

ELIMINACION DE MATERIAL EXCEDENTE

m3

8.19

15.32

125.47

0.00%

0.00

03.03.02.03

REFINE, NIVELACION Y FONDOS P/TUB PVC EN TSR ANCHO 0.60m

12.60

1.63

20.54

0.00%

0.00

12.60

36.22

456.37

0.00%

0.00

0.00%

0.00

03.03.03

OBRAS DE CONCRETO SIMPLE

03.03.03.01
03.03.04

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


OBRAS DE CONCRETO ARMADO

m2

CONCRETO EN LOSAS MACISAS f'c=210 kg/cm2

m3

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

0.00%

0.00

100.00%

20.54

0.00%

0.00

12.60

8.19
-

0.00%

0.00

12.60

100.00%

456.37

11.09

370.80

0.00%

0.00

0.00%

0.00

0.00%

0.00

11.09

100.00%

4,112.17

87.56

40.05

4,112.17
3,506.78

m2

0.00%

0.00

0.00%

0.00

0.00%

0.00

87.56

100.00%

3,506.78

03.03.04.03
03.03.05

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60


REVOQUES ENDUCIDOS Y MOLDADURAS

kg

996.56

5.23

5,212.01

0.00%

0.00

0.00%

0.00

0.00%

0.00

996.56

100.00%

5,212.01

03.03.05.01

TARRAJEO INTERIOR CON IMPERMEABILIZANTES

m2

45.26

30.73

0.00%

0.00

0.00%

0.00

0.00%

0.00

45.26

100.00%

1,390.84

TARRAJEO MUROS EXTERIORES

m2

75.35

19.76

0.00%

0.00

0.00%

0.00

0.00%

0.00

75.35

100.00%

1,488.92

0.00%

0.00

0.00%

0.00

0.00%

0.00

59.51

100.00%

1,022.38

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

85.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

1.00
1.00

100.00%
100.00%

487.55
350.00

03.03.04.01
03.03.04.02

03.03.05.02
03.03.06
03.03.06.01

PINTURA
PINTURA LATEX EN MUROS EXTERIORES

03.03.07

HIPOCLORADOR DE FLUJO DIFUSO

03.03.07.01
03.03.08

SUMINISTRO E INSTALACION DE HIPOCLORADOR PVC DIFUSO


TAPAS METALICAS Y ACCESORIOS

03.03.08.01
03.03.08.02

59.51

17.18

1,022.38

und

1.00

85.00

85.00

MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.6M x 0.6M

und

1.00

487.55

487.55

ESCALERA METALICA TIPO GATO

und

JUNTAS
WATER STOP DE PVC DE 6" PROVISION Y COLOCADO DE JUNTA

03.03.10

CONTROL DE CALIDAD

03.03.10.02
03.04
03.04.01
03.04.01.01
03.04.01.02
03.04.02

m2

03.03.09
03.03.09.01
03.03.10.01

1,390.84
1,488.92

PRUEBA DE DISEO DE MEZCLAS DE CONCRETO


PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)
CASETA DE VALVULA DE RESERVORIO 17m3

1.00

350.00

350.00

15.60

11.29

176.12

0.00%

0.00

0.00%

0.00

0.00%

0.00

15.60

100.00%

176.12

und

1.00

350.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

350.00

und

18.00

25.00

350.00
450.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

18.00

100.00%

450.00

m2

2.14

1.17

0.00%

0.00

2.14

100.00%

2.50

2.14

100.00%

2.50

0.00%

0.00

2.14

2.84

2.50
6.08

m2

0.00%

0.00

2.14

100.00%

6.08

2.14

100.00%

6.08

0.00%

0.00

24.93

11.72

0.00%
0.00%

0.00
0.00

0.47
2.14

100.00%
100.00%

11.72
3.49

0.47
2.14

100.00%
100.00%

11.72
3.49

0.00%
0.00%

0.00
0.00

TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

03.04.02.01

EXCAVACION MANUAL DE ZANJAS

m3

0.47

03.04.02.02

REFINE, NIVELACION Y FONDOS P/TUB PVC EN TSR ANCHO 0.60m

2.14

1.63

3.49

03.04.02.03

ELIMINACION DE MATERIAL EXCEDENTE

m3

0.30

15.32

4.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

0.30

100.00%

4.60

m2

1.56

36.22

56.50

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.56

100.00%

56.50

03.04.03
03.04.03.01
03.04.04

OBRAS DE CONCRETO SIMPLE


SOLADO DE CONCRETO E=4" DE CONCRETO 1:10
OBRAS DE CONCRETO ARMADO

03.04.04.01
03.04.04.02

CONCRETO f'c=175 kg/cm2


ENCOFRADO Y DESENCOFRADO NORMAL

m3
m2

1.07
14.14

374.56
52.84

400.78

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.07

100.00%

400.78

747.16

03.04.04.03

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

kg

112.73

5.23

589.58

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

14.14
112.73

100.00%
100.00%

747.16
589.58

m2

17.92

19.76

354.10

0.00%

0.00

0.00%

0.00

0.00%

0.00

17.92

100.00%

354.10

m2

12.91

17.18

221.79

0.00%

0.00

0.00%

0.00

0.00%

0.00

12.91

100.00%

221.79

und
und

1.00
1.00

487.55
350.00

487.55

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

487.55

350.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

350.00

03.04.05

REVOQUES ENDUCIDOS Y MOLDADURAS

03.04.05.01
03.04.06

TARRAJEO DE MUROS DE INTERIORES Y EXTERIORES


PINTURA

03.04.06.01
03.04.07
03.04.07.01
03.04.07.02
03.05
03.05.01
03.05.01.01

PINTURA LATEX EN MUROS EXTERIORES


TAPAS METALICAS Y ACCESORIOS
MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.6M x 0.6M
COLOCACION DE ACCESORIOS DE CAJA DE VALVULA
RESERVORIO 17 M3 - SAN JUAN DE PACHACAYO
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL

m2

12.60

1.17

14.74

0.00%

0.00

03.05.01.02

TRAZO Y REPLANTEO INICAL

m2

12.60

2.84

35.78

03.05.01.03

TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO

12.60

1.99

25.07

0.00%
0.00%

0.00
0.00

03.05.02
03.05.02.01

MOVIMIENTO DE TIERRAS
EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

12.60

0.00%

0.00

100.00%
0.00%

35.78
0.00

12.60
-

0.00%

0.00

12.60

100.00%

14.74

100.00%
0.00%

35.78
0.00

12.60

0.00%
100.00%

0.00
25.07

6.30

30.00

189.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

6.30

100.00%

189.00

03.05.02.02

ELIMINACION DE MATERIAL EXCEDENTE

m3

8.19

15.32

125.47

03.05.02.03

REFINE, NIVELACION Y FONDOS P/TUB PVC EN TSR ANCHO 0.60m

12.60

1.63

20.54

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

8.19
12.60

100.00%
100.00%

125.47
20.54

03.05.03
03.05.03.01

OBRAS DE CONCRETO SIMPLE


SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

03.05.04

OBRAS DE CONCRETO ARMADO

03.05.04.01
03.05.04.02
03.05.04.03
03.05.05

m3

m2

12.60

36.22

456.37

0.00%

0.00

0.00%

0.00

0.00%

0.00

12.60

100.00%

456.37

CONCRETO EN LOSAS MACISAS f'c=210 kg/cm2

m3

11.09

370.80

4,112.17

0.00%

0.00

0.00%

0.00

0.00%

0.00

11.09

100.00%

4,112.17

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS


ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

m2
kg

87.96
996.56

40.05
5.23

3,522.80

0.00%

0.00

0.00%

0.00

0.00%

0.00

87.96

100.00%

3,522.80

5,212.01

0.00%

0.00

0.00%

0.00

0.00%

0.00

996.56

100.00%

5,212.01

REVOQUES ENDUCIDOS Y MOLDADURAS

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
03.05.05.01
03.05.05.02
03.05.06
03.05.06.01
03.05.07
03.05.07.01
03.05.08
03.05.08.01
03.05.08.02

Descripcin

03.06.01.02
03.06.02
03.06.02.01
03.06.02.02
03.06.02.03
03.06.03
03.06.03.01
03.06.04

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

1,488.92

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

45.26
75.35

100.00%
100.00%

1,390.84
1,488.92

17.18

1,022.38

0.00%

0.00

0.00%

0.00

0.00%

0.00

59.51

100.00%

1,022.38

85.00

85.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

85.00

1.00

487.55

487.55

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

1.00
1.00

100.00%
100.00%

487.55
350.00

30.73

1,390.84

TARRAJEO MUROS EXTERIORES

m2

75.35

19.76

m2

59.51

und

1.00

und

PINTURA
PINTURA LATEX EN MUROS EXTERIORES
HIPOCLORADOR DE FLUJO DIFUSO
SUMINISTRO E INSTALACION DE HIPOCLORADOR PVC DIFUSO
TAPAS METALICAS Y ACCESORIOS
MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.6M x 0.6M
ESCALERA METALICA TIPO GATO
WATER STOP DE PVC DE 6" PROVISION Y COLOCADO DE JUNTA
CONTROL DE CALIDAD

03.06.01.01

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

45.26

JUNTAS

03.06
03.06.01

Precio S/.

m2

03.05.09.01
03.05.10
03.05.10.02

Metrado

TARRAJEO INTERIOR CON IMPERMEABILIZANTES

03.05.09

03.05.10.01

Und.

und
m

1.00

350.00

350.00

15.60

11.29

176.12

0.00%

0.00

0.00%

0.00

0.00%

0.00

15.60

100.00%

176.12

350.00
450.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

350.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

18.00

100.00%

450.00

100.00%

3.51

PRUEBA DE DISEO DE MEZCLAS DE CONCRETO

und

1.00

350.00

PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION)

und

18.00

25.00

m2

3.00

1.17

0.00%

0.00

3.00

2.84

3.51
8.52

m2

0.00%

0.00

EXCAVACION MANUAL DE ZANJAS

m3

0.66

24.93

16.45

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

3.00

2.61

7.83

0.00%
0.00%

m3

0.30

15.32

4.60

m2

2.19

36.22

79.32

CASETA DE VALVULA DE RESERVORIO 17m3


TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

ELIMINACION DE MATERIAL EXCEDENTE


OBRAS DE CONCRETO SIMPLE
SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

0.00%

0.00

100.00%

8.52

3.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%

0.00

0.00%

0.00%

0.00

0.00%

3.00

0.00%

0.00

3.00

100.00%

8.52

0.00%
0.00%

0.00
0.00

0.00

0.00%

0.00

0.00%

0.00%

0.00

0.66
3.00

100.00%
100.00%

16.45
7.83

0.00

0.30

100.00%

4.60

0.00

2.19

100.00%

79.32

OBRAS DE CONCRETO ARMADO

03.06.04.01
03.06.04.02

CONCRETO f'c=175 kg/cm2


ENCOFRADO Y DESENCOFRADO NORMAL

m3
m2

1.50
19.80

374.56
52.84

561.84

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.50

100.00%

561.84

1,046.23

0.00%

0.00

0.00%

0.00

0.00%

0.00

19.80

100.00%

1,046.23

03.06.04.03

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

kg

157.82

5.23

825.40

0.00%

0.00

0.00%

0.00

0.00%

0.00

157.82

100.00%

825.40

m2

25.09

19.76

495.78

0.00%

0.00

0.00%

0.00

0.00%

0.00

25.09

100.00%

495.78

m2

18.07

17.18

310.44

0.00%

0.00

0.00%

0.00

0.00%

0.00

18.07

100.00%

310.44

MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.6M x 0.6M

und

1.00

487.55

487.55

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

487.55

COLOCACION DE ACCESORIOS DE CAJA DE VALVULA

und

1.00

350.00

350.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

350.00

03.06.05

REVOQUES ENDUCIDOS Y MOLDADURAS

03.06.05.01
03.06.06

TARRAJEO DE MUROS DE INTERIORES Y EXTERIORES


PINTURA

03.06.06.01
03.06.07
03.06.07.01
03.06.07.02
03.07
03.07.01

PINTURA LATEX EN MUROS EXTERIORES


TAPAS METALICAS Y ACCESORIOS

LINEA DE ADUCCION Y DISTRIBUCION


TRABAJOS PRELIMINARES

03.07.01.01
03.07.01.02

TRAZO, NIVELACION Y REPLANTEO INICIAL


TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO

m
m

10,198.02
10,198.02

1.75
1.99

17,846.54

0.00%

0.00

100.00%

17,846.54

100.00%

17,846.54

0.00%

0.00

20,294.06

03.07.01.03

LIMPIEZA DEL TERRENO MANUAL

10,198.02

1.14

11,625.74

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

10,198.02
10,198.02

100.00%
100.00%

20,294.06
11,625.74

11,625.74

0.00%

0.00

0.00%

0.00

0.00%

0.00

10,198.02

100.00%

11,625.74

80,870.30

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

10,198.02
10,198.02

100.00%
100.00%

80,870.30
16,622.77

0.00%

0.00

0.00%

0.00

0.00%

0.00

10,198.02

100.00%

75,567.33

03.07.02

10,198.02

10,198.02

MOVIMIENTO DE TIERRAS

03.07.02.01
03.07.02.02

LIMPIEZA DEL TERRENO MANUAL


EXCAV. ZANJAS C/EQUIPO EN TSR ANCHO =0.60 H=1.00m

m
m

10,198.02
10,198.02

1.14
7.93

03.07.02.03

REFINE, NIVELACION Y FONDOS P/TUB PVC EN TSR ANCHO 0.60m

10,198.02

1.63

03.07.02.04

PREPARACION CAMA DE APOYO P/FONDOS TUB. PVC. e=0.10M TSR A=0.6M

10,198.02

7.41

03.07.02.05
03.07.02.06

RELLENO COMPACTADO ZANJA H<1.5M


ELIMINACION DE MATERIAL EXCEDENTE

m
m3

10,198.02
795.45

6.90
15.32

70,366.34

0.00%

0.00

0.00%

0.00

0.00%

0.00

10,198.02

100.00%

70,366.34

12,186.29

0.00%

0.00

0.00%

0.00

0.00%

0.00

795.45

100.00%

12,186.29

m
m

2,700.53
7,497.49

13.94
17.94

37,645.39

0.00%

0.00

0.00%

0.00

0.00%

0.00

2,700.53

100.00%

37,645.39

134,504.97

0.00%

0.00

0.00%

0.00

0.00%

0.00

7,497.49

100.00%

134,504.97

585.24

0.54

316.03

0.00%

0.00

0.00%

0.00

0.00%

0.00

585.24

100.00%

316.03

0.00%
0.00%

0.00
0.00

0.00%
100.00%

0.00
1,757.88

0.00%
100.00%

0.00
1,757.88

1,004.50
-

100.00%
0.00%

1,145.13
0.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,004.50

100.00%

1,998.96

26,177.27
8,297.17

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

1,004.50
1,004.50

100.00%
100.00%

26,177.27
8,297.17

6,931.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,004.50

100.00%

6,931.05

1,000.24

0.00%

0.00

0.00%

0.00

0.00%

0.00

65.29

100.00%

1,000.24

03.07.03
03.07.03.01
03.07.03.02
03.07.04
03.07.04.01
03.08
03.08.01

16,622.77
75,567.33

SUMINISTRO E INST. DE TUBERIAS PVC


SUMINISTRO E INSTALACION DE TUB. U.F. D.N. 63mm C-7.5
SUMINISTRO E INSTALACION DE TUB. U.F. D.N. 32mm C-7.5
PRUEBAS HIDRAULICAS Y DESINFECCION DE TUBERIAS
PRUEBA HIDRAULICA PARA AGUA
CONEXIONES DOMICILIARIAS DE AGUA
TRABAJOS PRELIMINARES

03.08.01.01

LIMPIEZA DEL TERRENO MANUAL

1,004.50

1.14

1,145.13

03.08.01.02

TRAZO, NIVELACION Y REPLANTEO INICIAL

1,004.50

1.75

1,004.50

1.99

1,757.88
1,998.96

26.06

03.08.01.03
03.08.02

TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO


MOVIMIENTO DE TIERRAS

03.08.02.01

EXCAVACION DE ZANJA PARA CONEXIONES DOMICILIARIAS

1,004.50

03.08.02.02

CAMA DE APOYO e=0.10 TSR A=0.50 M CONEXION DOMICILIARIA

1,004.50

8.26

03.08.02.03
03.08.02.04

RELLENO COMPACTADO ZANJA H<1.5M


ELIMINACION DE MATERIAL EXCEDENTE D PROM = 1KM C/ EQUIPO

m
m3

1,004.50
65.29

6.90
15.32

03.08.03

CONEXIONES DOMICILIARIAS

1,004.50

1,004.50

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
03.08.03.01
03.08.03.02
03.08.04
03.08.04.01
03.08.04.02
03.09
03.09.01
03.09.01.01
03.09.01.02
03.09.02

Descripcin

Und.

Metrado

Precio S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

1,273.24

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

278.00
278.00

100.00%
100.00%

66,152.88
1,273.24

CONEXION AGUA TUB. 1/2"

und

278.00

237.96

66,152.88

RECUBRIMIENTO CON TUB. 2"

und

278.00

4.58

VARIOS
PRUEBA HIDRAULICA A ZANJA ABIERTA

1,004.50

1.14

1,145.13

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,004.50

100.00%

1,145.13

PRUEBA HIDRAULICA A ZANJA TAPADA

1,004.50

0.54

542.43

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,004.50

100.00%

542.43

m2

12.15

1.17

14.22

m2

12.15

2.84

34.51

0.00%
0.00%

0.00
0.00

0.00%
100.00%

0.00
34.51

0.00%
100.00%

0.00
34.51

12.15
-

100.00%
0.00%

14.22
0.00

VALVULAS DE CONTROL DE COMPUERTA


TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL

12.15

12.15

MOVIMIENTO DE TIERRAS

03.09.02.01
03.09.02.02

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA


ELIMINACION DE MATERIAL EXCEDENTE

m3
m3

14.58
17.58

30.00
15.32

437.40

0.00%

0.00

0.00%

0.00

0.00%

0.00

14.58

100.00%

437.40

269.33

03.09.02.03

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

12.15

2.61

31.71

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

17.58
12.15

100.00%
100.00%

269.33
31.71

03.09.03

OBRAS DE CONCRETO SIMPLE

03.09.03.01
03.09.04

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


OBRAS DE CONCRETO ARMADO

03.09.04.01
03.09.04.02
03.09.04.03
03.09.05
03.09.05.01

m2

7.89

36.22

285.78

0.00%

0.00

0.00%

0.00

0.00%

0.00

7.89

100.00%

285.78

CONCRETO f'c=175 kg/cm2

m3

7.93

374.56

0.00%

0.00

0.00%

0.00

0.00%

0.00

7.93

100.00%

2,970.26

ENCOFRADO Y DESENCOFRADO NORMAL


ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

m2
kg

73.92
296.46

52.84
5.23

2,970.26
3,905.93

0.00%

0.00

0.00%

0.00

0.00%

0.00

73.92

100.00%

3,905.93

1,550.49

0.00%

0.00

0.00%

0.00

0.00%

0.00

296.46

100.00%

1,550.49

m2

36.00

30.73

1,106.28

0.00%

0.00

0.00%

0.00

0.00%

0.00

36.00

100.00%

1,106.28

m2

9.00

17.18

154.62

0.00%

0.00

0.00%

0.00

0.00%

0.00

9.00

100.00%

154.62

und

32.00

681.58

0.00%

0.00

0.00%

0.00

0.00%

0.00

32.00

100.00%

21,810.56

und

32.00

250.00

21,810.56
8,000.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

32.00

100.00%

8,000.00

und

10.00

120.00

1,200.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

10.00

100.00%

1,200.00

m2

2.56

1.17

3.00

0.00%

0.00

100.00%

3.00

m2

2.56

2.84

7.27

0.00%

0.00

REVOQUES ENDUCIDOS Y MOLDADURAS


TARRAJEO INTERIOR CON IMPERMEABILIZANTES

03.09.06
03.09.06.01

PINTURA
PINTURA LATEX EN MUROS EXTERIORES

03.09.07

TAPAS METALICAS Y ACCESORIOS

03.09.07.01
03.09.07.02
03.10
03.10.01
03.11
03.11.01
03.11.01.01
03.11.01.02
03.11.02
03.11.02.01
03.11.02.02
03.11.02.03

MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.3M x 0.3M


SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULAS DE CONTROL
VALVULA DE PURGA
CONSTRUCCION DE VALVULA DE PURGA C/VALV. DE 2"
VALVULA DE AIRE
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

0.00%

0.00

2.69

100.00%

67.06

ELIMINACION DE MATERIAL EXCEDENTE

m3

19.90

15.32

304.87

0.00%

0.00

0.00%

0.00

0.00%

0.00

19.90

100.00%

304.87

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

2.56

2.61

6.68

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.56

100.00%

6.68

m2

1.96

36.22

70.99

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.96

100.00%

70.99

CONCRETO f'c=175 kg/cm2

m3

0.96

374.56

0.00%

0.00

0.00%

0.00

0.00%

0.00

0.96

100.00%

359.58

m2

21.12

52.84

359.58
1,115.98

ENCOFRADO Y DESENCOFRADO NORMAL

0.00%

0.00

0.00%

0.00

0.00%

0.00

21.12

100.00%

1,115.98

kg

71.32

5.23

373.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

71.32

100.00%

373.00

m2

11.28

30.73

346.63

0.00%

0.00

0.00%

0.00

0.00%

0.00

11.28

100.00%

346.63

m2

5.64

17.18

96.90

0.00%

0.00

0.00%

0.00

0.00%

0.00

5.64

100.00%

96.90

und

6.00

681.58

0.00%

0.00

0.00%

0.00

0.00%

0.00

6.00

100.00%

4,089.48

und

6.00

120.00

4,089.48
720.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

6.00

100.00%

720.00

m2

36.00

1.17

42.12

0.00%

0.00

36.00

100.00%

42.12

m2

5.76

2.84

16.36

0.00%

0.00

EXCAVACION MANUAL DE ZANJAS

m3

9.22

24.93

229.85

ELIMINACION DE MATERIAL EXCEDENTE

m3

8.39

15.32

128.53

0.00%
0.00%

m2

2.88

36.22

104.31

CONCRETO f'c=210 kg/cm2

m3

7.41

370.80

2,747.63

ENCOFRADO Y DESENCOFRADO NORMAL


ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

m2
kg

8.00
8.00

52.84
5.23

422.72
41.84

PINTURA
PINTURA LATEX EN MUROS EXTERIORES
TAPAS METALICAS Y ACCESORIOS
MARCO Y TAPA METALICA PLANCHA LAC. 2MM C/MECAN 0.3M x 0.3M
SUMINISTRO E INSTALACION DE ACCESORIOS EN VALVULAS DE AIRE
PASE AEREO PARA LINEA DE CONDUCCION
TRABAJOS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

03.12.03
03.12.03.01

OBRAS DE CONCRETO SIMPLE


SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

03.12.04

OBRAS DE CONCRETO ARMADO

03.12.04.02
03.12.04.03
03.12.05

0.00

0.00

03.11.06.01
03.11.07

03.12.04.01

0.00%

0.00%

03.11.06

03.12.02.02

0.00

TARRAJEO INTERIOR CON IMPERMEABILIZANTES

03.12.02.01

2.56

7.27

0.00%

03.11.05.01

03.12.01.02
03.12.02

0.00

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60


REVOQUES ENDUCIDOS Y MOLDADURAS

03.12.01.01

0.00%
100.00%

67.06

03.11.04.03
03.11.05

03.12.01

2.56

24.93

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


OBRAS DE CONCRETO ARMADO

03.11.07.02
03.12

7.27

2.69

03.11.03.01
03.11.04

03.11.07.01

0.00

m3

OBRAS DE CONCRETO SIMPLE

03.11.04.02

0.00%
100.00%

EXCAVACION MANUAL DE ZANJAS

03.11.03

03.11.04.01

2.56

0.00

REVOQUES ENDUCIDOS Y MOLDADURAS

0.00%

0.00

100.00%

16.36

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%

0.00

0.00%

0.00%

0.00

0.00%

0.00%

0.00

0.00%

0.00

5.76

0.00%

0.00

100.00%

16.36

0.00%
0.00%

0.00
0.00

0.00

0.00%

0.00

0.00%

0.00%

0.00

0.00%

0.00

5.76

0.00%

0.00

9.22
8.39

100.00%
100.00%

229.85
128.53

0.00

2.88

100.00%

104.31

0.00

7.41

100.00%

2,747.63

0.00%

0.00

8.00

100.00%

422.72

0.00%

0.00

8.00

100.00%

41.84

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
03.12.05.01
03.12.06
03.12.06.01
03.12.06.02
03.12.07
03.12.07.01
03.12.07.02
04
04.01
04.01.01

Descripcin
TARRAJEO DE TORRES DE ANCLAJE

Und.
m2

Metrado

Precio S/.

Parcial S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO
METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

8.00

30.62

244.96

0.00%

0.00

0.00%

0.00

0.00%

0.00

8.00

100.00%

244.96

16.12

8,201.53

0.00%

0.00

0.00%

0.00

0.00%

0.00

508.78

100.00%

8,201.53

SUMINISTRO E INST. DE CABLES


SUMINISTRO E INSTALCION PARA CABLE PRINCIPAL CABLE DE ACERO TIPO BOA 6x19 D=1/4"

508.78

SUMINISTRO E INSTALACION PARA PENDOLA

17.40

16.17

281.36

0.00%

0.00

0.00%

0.00

0.00%

0.00

17.40

100.00%

281.36

glb

1.00

444.67

444.67

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

444.67

glb

1.00

139.87

139.87

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

139.87

ACCESORIOS
ACCESORIOS PARA FIJACION PRINCIPAL
ACCESORIOS PARA FIJACION DE PENDOLA
SISTEMA DE ALCANTARILLADO
RED COLECTORA Y EMISORA
TRABAJOS PRELIMINARES

04.01.01.01
04.01.01.02

LIMPIEZA DEL TERRENO MANUAL


TRAZO, NIVELACION Y REPLANTEO INICIAL

m
m

9,822.39
9,822.39

1.14
1.75

11,197.52

0.00%

0.00

1,732.80

18.00%

1,975.39

1,732.80

18.00%

1,975.39

8,089.59

82.00%

9,222.13

17,189.18

04.01.01.03

TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO

9,822.39

1.99

19,546.56

0.00%
0.00%

0.00
0.00

9,822.39
1,732.80

100.00%
18.00%

17,189.18
3,448.27

9,822.39
1,732.80

100.00%
18.00%

17,189.18
3,448.27

8,089.59

0.00%
82.00%

0.00
16,098.28

4,124.08

0.00%

0.00

188.40

100.00%

4,124.08

188.40

100.00%

4,124.08

0.00%

0.00

186,298.95

0.00%

0.00

1,544.40

23.00%

43,474.86

1,544.40

23.00%

43,474.86

5,073.68

77.00%

142,824.09

88,574.26
10,727.44

0.00%

0.00

0.00%

0.00

0.00%

0.00

2,471.38

100.00%

88,574.26

0.00

10,727.44

04.01.02

MOVIMIENTO DE TIERRAS
-

04.01.02.01
04.01.02.02

EXCAVACION DE ZANJAS PARA TUB. 200mm TSR, HASTA 1.5m


EXCAVACION DE ZANJAS PARA TUB. 200mm TSR, HASTA 2.0 m

m
m

188.40
6,618.08

21.89
28.15

04.01.02.03

EXCAVACION DE ZANJAS PARA TUB. 200mm TSR, HASTA 2.5 m

2,471.38

35.84

04.01.02.04
04.01.02.05

EXCAVACION DE ZANJAS PARA TUB. 160mm TSR, HASTA 1.2 m


EXCAVACION PARA BUZON EN TSR HASTA 1.50 m

m
m3

544.54
39.20

19.70
43.39

0.00%

0.00

544.54

100.00%

1,700.89

0.00%

0.00

30.15

77.00%

1,308.21

30.15

77.00%

1,308.21

9.05

23.00%

392.68

04.01.02.06

EXCAVACION PARA BUZON EN TSR HASTA 2.00 m

m3

367.65

52.08

19,147.21

EXCAVACION PARA BUZON EN TSR HASTA 2.50 m

m3

109.45

65.09

7,124.10

0.00%
0.00%

0.00
0.00

345.81

04.01.02.07

94.00%
0.00%

18,009.78
0.00

345.81
-

94.00%
0.00%

18,009.78
0.00

21.84
109.45

6.00%
100.00%

1,137.43
7,124.10

04.01.02.08
04.01.02.09

EXCAVACION PARA BUZON EN TSR HASTA 3.00 m


EXCAVACION PARA BUZONETA EN TSR HASTA 1.20 m

m3
m3

72.88
39.68

72.32
32.55

5,270.68

0.00%

0.00

1,291.58

0.00%

0.00

0.00%

0.00

04.01.02.10

REFINE Y NIVELACION DE ZANJA TSR P/TUB D=6" - 8"

9,277.85

4.89

45,368.69

04.01.02.11

CAMA DE APOYO e=0.10 TSR A=0.70m RED COLECTORA

9,277.85

7.41

0.00%
0.00%

0.00
0.00

1,732.80
1,732.80

19.00%
19.00%

8,473.39
12,840.05

04.01.02.12
04.01.02.13

CAMA DE APOYO e=0.10 TSR A=0.50m RED CONDOMINIAL


PRIMER RELLENO DE ZANJA TSR DN=200MM H=0.30M S/ CLAVE TUBERIA MAT. PRESTAMO

m
m

544.54
9,277.85

6.74
7.79

68,748.87
3,670.20

0.00%

0.00

0.00%

0.00

0.00%

72,274.45

0.00%

0.00

1,732.80

19.00%

13,498.51

1,732.80

19.00%

04.01.02.14

PRIMER RELLENO DE ZANJA TSR DN=160MM H=0.30M S/ CLAVE TUBERIA MAT. PRESTAMO

544.54

7.26

3,953.36

04.01.02.15

SEGUNDO RELLENO 100% MAT. PROPIO Y COMP. DE ZANJA TN P/TUB HASTA 1.5m

188.40

18.31

0.00%
0.00%

0.00
0.00

188.40

0.00%
100.00%

0.00
3,449.60

188.40

0.00%
100.00%

0.00
3,449.60

04.01.02.16
04.01.02.17

SEGUNDO RELLENO 100% MAT. PROPIO Y COMP. DE ZANJA TN P/TUB 160m HASTA 1.20m
SEGUNDO RELLENO 100% MAT. PROPIO Y COMP. DE ZANJA TN P/TUB HASTA 2.00m

m
m

544.40
6,618.08

17.39
11.50

3,449.60
9,467.12

0.00%

0.00

0.00%

0.00

0.00%

76,107.92

0.00%

0.00

23.00%

17,760.60

04.01.02.18

SEGUNDO RELLENO 100% MAT. PROPIO Y COMP. DE ZANJA TN P/TUB HASTA 2.50m

2,471.38

12.48

30,842.82

ELIMINACION DE MATERIAL EXCEDENTE D PROM = 1KM C/ EQUIPO

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

04.01.02.19
04.01.03
04.01.03.01
04.01.03.02
04.02

1,544.40

0.00

1,732.80
1,732.80
-

1,544.40
-

0.00%

72.88

100.00%

0.00%

0.00

39.68

100.00%

1,291.58

19.00%
19.00%

0.00%

8,473.39
12,840.05

0.00

7,545.05
7,545.05

81.00%
81.00%

36,895.29
55,908.82

5,270.68

0.00

544.54

100.00%

3,670.20

13,498.51

7,545.05

81.00%

58,775.94

544.54
-

100.00%
0.00%

3,953.36
0.00

0.00

544.40

100.00%

9,467.12

23.00%

17,760.60

5,073.68

77.00%

58,347.32

0.00%
0.00%

0.00
0.00

2,471.38
995.90

100.00%
100.00%

30,842.82
15,257.19

m3

995.90

15.32

15,257.19

SUMINISTRO E INSTALACION DE TUBERIA PVC UF ISO 4435 , DN= 160mm

544.54

24.37

13,270.44

0.00%

0.00

0.00%

0.00

0.00%

0.00

544.54

100.00%

13,270.44

SUMINISTRO E INSTALACION DE TUBERIA PVC UF ISO 4435 , DN= 200mm

9,277.85

35.14

326,023.65

0.00%

0.00

1,732.80

19.00%

60,890.59

1,732.80

19.00%

60,890.59

7,545.05

81.00%

265,133.06

30,950.70

0.00%

0.00

10.00

67.00%

20,633.80

10.00

67.00%

20,633.80

5.00

33.00%

10,316.90

246,480.74

0.00%
0.00%

0.00
0.00

95.00

90.00%
0.00%

220,902.55
0.00

95.00
-

90.00%
0.00%

220,902.55
0.00

11.00
37.00

10.00%
100.00%

25,578.19
112,361.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

64.00

100.00%

131,200.00

SUMINISTRO E INST. DE TUBERIAS PVC


-

CONSTRUCCION DE BUZONES
CONSTRUCCION DE BUZON TIPO I EN TERRENO SEMIROCOSO HASTA 1.50m
CONSTRUCCION DE BUZON TIPO I EN TERRENO SEMIROCOSO DE 1.51m - 2m

und
und

15.00
106.00

2,063.38
2,325.29

04.02.03

CONSTRUCCION DE BUZON TIPO I EN TERRENO SEMIROCOSO DE 2.01m - 3m

und

37.00

3,036.80

CONSTRUCCION DE BUZONETAS TSR HASTA 1m

und

64.00

2,050.00

04.03
04.03.01

0.00%

0.00

04.02.01
04.02.02
04.02.04

0.00%

112,361.60
131,200.00

CONEXIONES DOMICILIARIAS
TRABAJOS PRELIMINARES

04.03.01.01

LIMPIEZA DEL TERRENO MANUAL

834.00

1.14

0.00%

0.00

0.00%

0.00

0.00%

0.00

834.00

100.00%

950.76

TRAZO, NIVELACION Y REPLANTEO INICIAL

834.00

1.75

950.76
1,459.50

04.03.01.02

0.00%

0.00

0.00%

0.00

0.00%

0.00

834.00

100.00%

1,459.50

834.00

1.99

1,659.66

0.00%

0.00

0.00%

0.00

0.00%

0.00

834.00

100.00%

1,659.66

21,734.04
6,179.94

0.00%

0.00

0.00%

0.00

0.00%

0.00

834.00

100.00%

21,734.04

0.00%

0.00

0.00%

0.00

0.00%

0.00

834.00

100.00%

6,179.94

10,641.84

0.00%

0.00

0.00%

0.00

0.00%

0.00

834.00

100.00%

10,641.84

04.03.01.03
04.03.02

TRAZO Y REPLANTEO DE NIVELES DURANTE EL PROCESO


MOVIMIENTO DE TIERRAS

04.03.02.01

EXCAVACION DE ZANJA PARA CONEXIONES DOMICILIARIAS

834.00

26.06

04.03.02.02
04.03.02.03

PREPARACION CAMA DE APOYO P/FONDOS TUB. PVC. e=0.10M TSR A=0.6M


RELLENO CONEXION DOMICILIARIA

m
m

834.00
834.00

7.41
12.76

04.03.02.04

ELIMINACION DE MATERIAL EXCEDENTE D PROM = 1KM C/ EQUIPO

m3

104.34

15.32

1,598.49

0.00%

0.00

0.00%

0.00

0.00%

0.00

104.34

100.00%

1,598.49

und

278.00

465.76

129,481.28

0.00%

0.00

0.00%

0.00

0.00%

0.00

278.00

100.00%

129,481.28

04.03.03
04.03.03.01
04.04
04.04.01
04.04.02
05
05.01
05.01.01
05.01.01.01
05.01.01.01.01
05.01.01.01.02
05.01.01.02

CONEXIONES DOMICILIARIAS
CONEXION DE DESAGUE
VARIOS
PRUEBA HIDRAULICA A ZANJA ABIERTA

9,822.39

1.14

11,197.52

PRUEBA HIDRAULICA + DESINFECCION TUBERIA 8" (200mm) A ZANJA TAPA

9,822.39

1.74

17,090.96

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

9,822.39
9,822.39

100.00%
100.00%

11,197.52
17,090.96

429.70
43.21

1.17
2.84

502.75

0.00%

0.00

0.00%

0.00

0.00%

0.00

429.70

100.00%

502.75

122.72

0.00%

0.00

0.00%

0.00

0.00%

0.00

43.21

100.00%

122.72

PLANTA DE TRATAMIENTO AGUAS RESIDUALES


PTAR 2
CAMARA DE REJAS
OBRAS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

m2
m2

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item

Descripcin

Und.

Metrado

Precio S/.

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

112.78

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

42.26
43.21

100.00%
100.00%

1,267.80
112.78

1,083.97

0.00%

0.00

0.00%

0.00

0.00%

0.00

42.26

100.00%

1,083.97

15.32

459.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

30.00

100.00%

459.60

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

m3

42.26

05.01.01.02.02

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

43.21

2.61

05.01.01.02.03

RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO

m3

42.26

25.65

ELIMINACION DE MATERIAL EXCEDENTE

m3

30.00

05.01.01.03

METRADO

05.01.01.02.01

05.01.01.02.04

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

30.00

1,267.80

CONCRETO SIMPLE

05.01.01.03.01

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

m2

7.06

36.22

255.71

0.00%

0.00

0.00%

0.00

0.00%

0.00

7.06

100.00%

255.71

05.01.01.04
05.01.01.04.01

CONCRETO ARMADO
CONCRETO EN CAMARA DE REJAS f'c=210kg/cm2

m3

5.73

435.50

2,495.42

ACERO CORRUGADO FY= 4200 kg/cm2 CAMARA DE REJAS

kg

237.95

5.23

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

5.73
237.95

100.00%
100.00%

2,495.42
1,244.48

ENCOFRADO Y DESENCOFRADO NORMAL EN CAMARA DE REJAS

m2

56.62

44.72

1,244.48
2,532.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

56.62

100.00%

2,532.05

m2

35.41

35.81

1,268.03

0.00%

0.00

0.00%

0.00

0.00%

0.00

35.41

100.00%

1,268.03

und

1.00

275.77

275.77

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

275.77

m2

23.76

2.84

67.48

0.00%

0.00

0.00%

0.00

0.00%

0.00

23.76

100.00%

67.48

m3

81.41

30.00

2,442.30

0.00%

0.00

0.00%

0.00

0.00%

0.00

81.41

100.00%

2,442.30

65.15

05.01.01.04.02
05.01.01.04.03
05.01.01.05
05.01.01.05.01

REVOQUES ENDUCIDOS Y MOLDADURAS


TARRAJEO CON IMPERMEABILIZANTES

05.01.01.06

COMPUERTAS Y ACCESORIOS

05.01.01.06.01
05.01.02
05.01.02.01
05.01.02.01.01
05.01.02.02
05.01.02.02.01

COMPUERTAS Y ACCESORIOS
TANQUE IMHOFF
TRABAJOS PRELIMINARES
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS
EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

05.01.02.02.02

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

24.96

2.61

05.01.02.02.03

RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO

m3

25.00

25.65

641.25

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

24.96
25.00

100.00%
100.00%

65.15
641.25

m3

170.70

15.32

2,615.12

0.00%

0.00

0.00%

0.00

0.00%

0.00

170.70

100.00%

2,615.12

05.01.02.02.04
05.01.02.03
05.01.02.03.01
05.01.02.04
05.01.02.04.01
05.01.02.04.02
05.01.02.04.03

ELIMINACION DE MATERIAL EXCEDENTE


OBRAS DE CONCRETO SIMPLE

m2

24.96

36.22

904.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

24.96

100.00%

904.05

CONCRETO EN LOSAS CIMENTACION f'c=210 kg/cm2


ACERO CORRUGADO FY= 4200 kg/cm2 LOSA DE CIMENTACION

m3
kg

32.08
3,362.27

435.50
5.23

13,970.84

0.00%

0.00

0.00%

0.00

0.00%

0.00

32.08

100.00%

13,970.84

17,584.67

0.00%

0.00

0.00%

0.00

0.00%

0.00

3,362.27

100.00%

17,584.67

ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m2

224.87

40.05

9,006.04

0.00%

0.00

0.00%

0.00

0.00%

0.00

224.87

100.00%

9,006.04

m2

238.96

35.81

8,557.16

0.00%

0.00

0.00%

0.00

0.00%

0.00

238.96

100.00%

8,557.16

glb

1.00

7,800.00

7,800.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

7,800.00

BUZON TIPO I - h=1.20m

und

4.00

2,646.80

10,587.20

0.00%

0.00

0.00%

0.00

0.00%

0.00

4.00

100.00%

10,587.20

BUZON TIPO II - h=3.00m

und

2.00

3,146.71

6,293.42

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.00

100.00%

6,293.42

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


OBRAS DE CONCRETO ARMADO

05.01.02.05

REVOQUES ENDUCIDOS Y MOLDADURAS

05.01.02.05.01
05.01.02.06

TARRAJEO CON IMPERMEABILIZANTES


INSTALACIONES HIDRAULICAS

05.01.02.06.01
05.01.02.07
05.01.02.07.01
05.01.02.07.02
05.01.03

COMPUERTAS Y ACCESORIOS TANQUE IMHOFF


BUZONES

LECHO DE SECADO

05.01.03.01

OBRAS PRELIMINARES

05.01.03.01.01
05.01.03.02

TRAZO Y REPLANTEO INICAL


MOVIMIENTO DE TIERRAS

m2

75.53

2.84

214.51

0.00%

0.00

0.00%

0.00

0.00%

0.00

75.53

100.00%

214.51

05.01.03.02.01

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

m3

501.06

30.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

501.06

100.00%

15,031.80

05.01.03.02.02

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m2

79.21

2.61

15,031.80
206.74

0.00%

0.00

0.00%

0.00

0.00%

0.00

79.21

100.00%

206.74

05.01.03.02.03
05.01.03.02.04

RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO


ELIMINACION DE MATERIAL EXCEDENTE

m3
m3

39.30
577.19

25.65
15.32

1,008.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

39.30

100.00%

1,008.05

8,842.55

0.00%

0.00

0.00%

0.00

0.00%

0.00

577.19

100.00%

8,842.55

05.01.03.03

CONCRETO SIMPLE

05.01.03.03.01

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

m2

42.25

36.22

1,530.30

0.00%

0.00

0.00%

0.00

0.00%

0.00

42.25

100.00%

1,530.30

05.01.03.04
05.01.03.04.01

CONCRETO ARMADO
CONCRETO EN LOSAS CIMENTACION f'c=210 kg/cm2

m3

67.42

435.50

29,361.41

0.00%

0.00

0.00%

0.00

0.00%

0.00

67.42

100.00%

29,361.41

kg

1,684.14

5.23

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,684.14

100.00%

8,808.05

153.76

40.05

8,808.05
6,158.09

m2

0.00%

0.00

0.00%

0.00

0.00%

0.00

153.76

100.00%

6,158.09

m2

21.60

35.81

773.50

0.00%

0.00

0.00%

0.00

0.00%

0.00

21.60

100.00%

773.50

glb

1.00

950.00

950.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

950.00

140.00

29.24

4,093.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

140.00

100.00%

4,093.60

LIMPIEZA MANUAL DE TERRENO NORMAL

m2

429.70

1.17

TRAZO Y REPLANTEO INICAL

m2

43.21

2.84

502.75
122.72

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

429.70
43.21

100.00%
100.00%

502.75
122.72

05.01.03.04.02
05.01.03.04.03
05.01.03.05
05.01.03.05.01

ACERO CORRUGADO FY= 4200 kg/cm2 LOSA DE CIMENTACION


ENCOFRADO Y DESENCOFRADO MUROS REFORZADOS
REVOQUES ENDUCIDOS Y MOLDADURAS
TARRAJEO CON IMPERMEABILIZANTES

05.01.03.06

VARIOS

05.01.03.06.01
05.01.03.07

SUMINISTRO Y COLOCACION / LECHO SECADO


CERCO PERIMTRICO

05.01.03.07.01
05.02
05.02.01
05.02.01.01
05.02.01.01.01
05.02.01.01.02
05.02.01.02
05.02.01.02.01
05.02.01.02.02

CERCO PERIMTRICO
PTAR 1
CAMARA DE REJAS
OBRAS PRELIMINARES

MOVIMIENTO DE TIERRAS
EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA
REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

0.00
m3

42.26

30.00

1,267.80

0.00%

0.00

0.00%

0.00

0.00%

0.00

42.26

100.00%

1,267.80

m2

43.21

2.61

112.78

0.00%

0.00

0.00%

0.00

0.00%

0.00

43.21

100.00%

112.78

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
05.02.01.02.03
05.02.01.02.04
05.02.01.03
05.02.01.03.01
05.02.01.04
05.02.01.04.01
05.02.01.04.02
05.02.01.04.03
05.02.01.05
05.02.01.05.01
05.02.01.06
05.02.01.06.01
05.02.02

Descripcin

Und.

Metrado

Precio S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

459.60

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

42.26
30.00

100.00%
100.00%

RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO

m3

42.26

25.65

1,083.97

ELIMINACION DE MATERIAL EXCEDENTE

m3

30.00

15.32

VALORIZADO
1,083.97
459.60

CONCRETO SIMPLE
m2

7.06

36.22

255.71

0.00%

0.00

0.00%

0.00

0.00%

0.00

7.06

100.00%

255.71

CONCRETO EN LOSAS CIMENTACION f'c=210 kg/cm2

m3

5.73

435.50

2,495.42

0.00%

0.00

0.00%

0.00

0.00%

0.00

5.73

100.00%

2,495.42

ACERO CORRUGADO FY= 4200 kg/cm2 CAMARA DE REJAS


ENCOFRADO Y DESENCOFRADO NORMAL EN CAMARA DE REJAS

kg
m2

237.95
56.62

5.23
44.72

1,244.48

0.00%

0.00

0.00%

0.00

0.00%

0.00

237.95

100.00%

1,244.48

2,532.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

56.62

100.00%

2,532.05

m2

35.41

35.81

1,268.03

0.00%

0.00

0.00%

0.00

0.00%

0.00

35.41

100.00%

1,268.03

und

1.00

275.77

275.77

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

275.77

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


CONCRETO ARMADO

REVOQUES ENDUCIDOS Y MOLDADURAS


TARRAJEO CON IMPERMEABILIZANTES
COMPUERTAS Y ACCESORIOS
COMPUERTAS Y ACCESORIOS
TANQUE IMHOFF

05.02.02.01

TRABAJOS PRELIMINARES

05.02.02.01.01
05.02.02.02

TRAZO Y REPLANTEO INICAL


MOVIMIENTO DE TIERRAS

m2

58.58

2.84

166.37

0.00%

0.00

0.00%

0.00

0.00%

0.00

58.58

100.00%

166.37

05.02.02.02.01

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

m3

476.87

30.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

476.87

100.00%

14,306.10

05.02.02.02.02
05.02.02.02.03

REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR


RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO

m2
m3

58.58
243.32

2.61
25.65

14,306.10
152.89

0.00%

0.00

0.00%

0.00

0.00%

0.00

58.58

100.00%

152.89

6,241.16

0.00%

0.00

0.00%

0.00

0.00%

0.00

243.32

100.00%

6,241.16

05.02.02.02.04

ELIMINACION DE MATERIAL EXCEDENTE

m3

243.32

15.32

3,727.66

0.00%

0.00

0.00%

0.00

0.00%

0.00

243.32

100.00%

3,727.66

05.02.02.03

OBRAS DE CONCRETO SIMPLE

05.02.02.03.01
05.02.02.04

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


OBRAS DE CONCRETO ARMADO

05.02.02.04.01
05.02.02.04.02
05.02.02.04.03
05.02.02.05
05.02.02.05.01

m2

58.72

36.22

2,126.84

0.00%

0.00

0.00%

0.00

0.00%

0.00

58.72

100.00%

2,126.84

CONCRETO EN LOSAS CIMENTACION f'c=210 kg/cm2

m3

71.13

435.50

30,977.12

ACERO CORRUGADO FY= 4200 kg/cm2 LOSA DE CIMENTACION

kg

2,351.23

5.23

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

71.13
2,351.23

100.00%
100.00%

30,977.12
12,296.93

m2

605.91

40.05

12,296.93
24,266.70

0.00%

0.00

0.00%

0.00

0.00%

0.00

605.91

100.00%

24,266.70

m2

403.28

35.81

14,441.46

0.00%

0.00

0.00%

0.00

0.00%

0.00

403.28

100.00%

14,441.46

glb

1.00

7,800.00

7,800.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

7,800.00

BUZON TIPO I - h=1.20m

und

4.00

2,646.80

10,587.20

BUZON TIPO II - h=3.00m

und

2.00

3,146.71

6,293.42

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

4.00
2.00

100.00%
100.00%

10,587.20
6,293.42

ENCOFRADO Y DESENCOFRADO MUROS REFORZADOS


REVOQUES ENDUCIDOS Y MOLDADURAS
TARRAJEO CON IMPERMEABILIZANTES

05.02.02.06

INSTALACIONES HIDRAULICAS

05.02.02.06.01
05.02.02.07

COMPUERTAS Y ACCESORIOS TANQUE IMHOFF


BUZONES

05.02.02.07.01
05.02.02.07.02
05.02.03
05.02.03.01

LECHO DE SECADO
OBRAS PRELIMINARES
m2

75.53

2.84

214.51

0.00%

0.00

0.00%

0.00

0.00%

0.00

75.53

100.00%

214.51

05.02.03.02.01
05.02.03.02.02

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA


REFINE Y NIVELACION INTERIOR Y APISIONADO MANUAL EN TSR

m3
m2

501.06
79.21

30.00
2.61

15,031.80

0.00%

0.00

0.00%

0.00

0.00%

0.00

501.06

100.00%

15,031.80

206.74

05.02.03.02.03

RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO

m3

39.30

25.65

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

79.21
39.30

100.00%
100.00%

206.74
1,008.05

ELIMINACION DE MATERIAL EXCEDENTE

m3

577.19

15.32

1,008.05
8,842.55

05.02.03.02.04

0.00%

0.00

0.00%

0.00

0.00%

0.00

577.19

100.00%

8,842.55

m2

42.25

36.22

1,530.30

0.00%

0.00

0.00%

0.00

0.00%

0.00

42.25

100.00%

1,530.30

CONCRETO EN LOSAS CIMENTACION f'c=210 kg/cm2

m3

67.42

435.50

29,361.41

0.00%

0.00

0.00%

0.00

0.00%

0.00

67.42

100.00%

29,361.41

ACERO CORRUGADO FY= 4200 kg/cm2 LOSA DE CIMENTACION


ENCOFRADO Y DESENCOFRADO MUROS REFORZADOS

kg
m2

1,684.14
153.76

5.23
40.05

8,808.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,684.14

100.00%

8,808.05

6,158.09

0.00%

0.00

0.00%

0.00

0.00%

0.00

153.76

100.00%

6,158.09

m2

21.60

35.81

773.50

0.00%

0.00

0.00%

0.00

0.00%

0.00

21.60

100.00%

773.50

glb

1.00

950.00

950.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

950.00

140.00

29.24

4,093.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

140.00

100.00%

4,093.60

m2
m2

5.53
3.15

1.17
2.84

6.47

0.00%

0.00

5.53

100.00%

6.47

5.53

100.00%

6.47

0.00%

0.00

8.95

0.00%

0.00

3.15

100.00%

8.95

3.15

100.00%

8.95

0.00%

0.00

293.70

9.79

100.00%

293.70

0.00%

0.00

05.02.03.01.01
05.02.03.02

TRAZO Y REPLANTEO INICAL


MOVIMIENTO DE TIERRAS

05.02.03.03
05.02.03.03.01

CONCRETO SIMPLE
SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

05.02.03.04

CONCRETO ARMADO

05.02.03.04.01
05.02.03.04.02
05.02.03.04.03
05.02.03.05

REVOQUES ENDUCIDOS Y MOLDADURAS

05.02.03.05.01
05.02.03.06

TARRAJEO CON IMPERMEABILIZANTES


VARIOS

05.02.03.06.01
05.02.03.07
05.02.03.07.01
05.03
05.03.01
05.03.01.01
05.03.01.01.01
05.03.01.01.02
05.03.01.02

SUMINISTRO Y COLOCACION / LECHO SECADO


CERCO PERIMTRICO
CERCO PERIMTRICO
PTAR 3

CAMARA DE REJAS
OBRAS PRELIMINARES
LIMPIEZA MANUAL DE TERRENO NORMAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

05.03.01.02.01

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

m3

9.79

30.00

293.70

0.00%

0.00

9.79

100.00%

05.03.01.02.02
05.03.01.02.03

NIVELACION INTERIOR Y APISONADO MANUAL


RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO

m2
m3

5.53
5.95

2.61
25.65

14.43

0.00%

0.00

5.53

100.00%

14.43

5.53

100.00%

14.43

0.00%

0.00

152.62

0.00%

0.00

5.95

100.00%

152.62

5.95

100.00%

152.62

0.00%

0.00

05.03.01.02.04

ELIMINACION DE MATERIAL EXCEDENTE

m3

4.80

15.32

73.54

0.00%

0.00

4.80

100.00%

73.54

4.80

100.00%

73.54

0.00%

0.00

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
05.03.01.03

Descripcin

Und.

Metrado

Precio S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

CONCRETO SIMPLE
m2

3.14

36.22

113.73

0.00%

0.00

3.14

100.00%

113.73

3.14

100.00%

113.73

0.00%

0.00

CONCRETO EN LOSAS CIMENTACION f'c=210 kg/cm2

m3

3.28

435.50

1,428.44

0.00%

0.00

3.28

100.00%

1,428.44

3.28

100.00%

1,428.44

0.00%

0.00

05.03.01.04.02

ENCOFRADO Y DESENCOFRADO NORMAL EN CAMARA DE REJAS

m2

19.59

44.72

0.00%

0.00

19.59

100.00%

876.06

19.59

100.00%

876.06

0.00%

0.00

ACERO CORRUGADO FY= 4200 kg/cm2 CAMARA DE REJAS

kg

396.62

5.23

876.06
2,074.32

05.03.01.04.03

0.00%

0.00

396.62

100.00%

2,074.32

396.62

100.00%

2,074.32

0.00%

0.00

m2

7.48

35.81

267.86

0.00%

0.00

0.00%

0.00

0.00%

0.00

7.48

100.00%

267.86

und

1.00

65.41

65.41

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

65.41

LIMPIEZA MANUAL DE TERRENO NORMAL

m2

22.94

1.17

0.00%

0.00

22.94

100.00%

26.84

22.94

100.00%

26.84

0.00%

0.00

m2

22.94

2.84

26.84
65.15

TRAZO Y REPLANTEO INICAL

0.00%

0.00

22.94

100.00%

65.15

22.94

100.00%

65.15

0.00%

0.00

m3

85.90

30.00

2,577.00

0.00%

0.00

85.90

100.00%

2,577.00

85.90

100.00%

2,577.00

0.00%

0.00

59.87
588.41

0.00%

0.00

22.94

100.00%

59.87

22.94

100.00%

59.87

0.00%

0.00%

0.00

22.94

100.00%

588.41

22.94

100.00%

588.41

0.00%

0.00

1,076.54

0.00%

0.00

0.00%

0.00

0.00%

0.00

100.00%

1,076.54

05.03.01.03.01
05.03.01.04
05.03.01.04.01

05.03.01.05
05.03.01.05.01
05.03.01.06
05.03.01.06.01
05.03.02
05.03.02.01
05.03.02.01.01
05.03.02.01.02
05.03.02.02
05.03.02.02.01

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10


CONCRETO ARMADO

REVOQUES ENDUCIDOS Y MOLDADURAS


TARRAJEO CON IMPERMEABILIZANTES
VARIOS
SUMINISTRO E INSTALACION DE REJAS F LISO ? 3/8" o 1 1/2 " 90x70 cm
TANQUE SEPTICO
OBRAS PRELIMINARES

MOVIMIENTO DE TIERRAS
EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

0.00

05.03.02.02.02

NIVELACION INTERIOR Y APISONADO MANUAL

m2

22.94

2.61

05.03.02.02.03
05.03.02.02.04

RELLENO CON MATERIAL PROPIO COMPACTADO C/EQUIPO


ELIMINACION DE MATERIAL EXCEDENTE

m3
m3

22.94
70.27

25.65
15.32

m2

14.52

36.22

525.91

0.00%

0.00

14.52

100.00%

525.91

14.52

100.00%

525.91

0.00%

0.00

m3

9.69

435.50

4,220.00

0.00%

0.00

9.69

100.00%

4,220.00

9.69

100.00%

4,220.00

0.00%

0.00

93.20
794.31

100.00%
100.00%

4,167.90
4,154.24

93.20
794.31

100.00%
100.00%

4,167.90
4,154.24

0.00%
0.00%

0.00
0.00

05.03.02.03
05.03.02.03.01
05.03.02.04
05.03.02.04.01

70.27

CONCRETO SIMPLE
SOLADO DE CONCRETO E=4" DE CONCRETO 1:10
CONCRETO ARMADO
CONCRETO F'C=210KG/CM2

05.03.02.04.02

ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS

m2

93.20

44.72

4,167.90

05.03.02.04.03

ACERO CORRUGADO FY= 4200 kg/cm2 CAMARA DE REJAS

kg

794.31

5.23

4,154.24

0.00%
0.00%

0.00
0.00

m2

85.95

35.81

3,077.87

0.00%

0.00

0.00%

0.00

0.00%

0.00

85.95

100.00%

3,077.87

und

1.00

56.97

56.97

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.00

100.00%

56.97

LIMPIEZA MANUAL DE TERRENO NORMAL

m2

60.00

1.17

70.20

TRAZO Y REPLANTEO INICAL

m2

14.40

2.84

40.90

0.00%
0.00%

0.00
0.00

60.00
14.40

100.00%
100.00%

70.20
40.90

60.00
14.40

100.00%
100.00%

70.20
40.90

0.00%
0.00%

0.00
0.00

EXCAVACION CON MAQUINARIA PARA POZO DE PERCOLACION

m3

33.93

30.00

1,017.90

0.00%

0.00

33.93

100.00%

1,017.90

33.93

100.00%

1,017.90

ELIMINACION DE MATERIAL EXCEDENTE

m3

42.41

15.32

649.72
0.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

m2
m2

14.14
19.60

36.22
52.84

512.15

0.00%

0.00

14.14

100.00%

512.15

14.14

100.00%

512.15

1,035.66

0.00%

0.00

19.60

100.00%

1,035.66

19.60

100.00%

1,035.66

2.49

100.00%

947.15

2.49

100.00%

05.03.02.05
05.03.02.05.01

REVOQUES ENDUCIDOS Y MOLDADURAS


TARRAJEO CON IMPERMEABILIZANTES

05.03.02.06

SISTEMAS DE ADITAMENTO

05.03.02.06.01
05.03.03
05.03.03.01
05.03.03.01.01
05.03.03.01.02
05.03.03.02
05.03.03.02.01
05.03.03.02.02
05.03.03.03
05.03.03.03.01
05.03.03.03.02
05.03.03.04

ACCESORIOS ADITAMENTOS EN TANQUE SEPTICO


POZO DE PERCOLACION (2 UND)
OBRAS PRELIMINARES

MOVIMIENTO DE TIERRAS

CONCRETO SIMPLE
SOLADO DE CONCRETO E=4" MEZACLA 1:10
ENCOFRADO Y DESENCOFRADO DE CIMIENTO CORRIDO

0.00%

0.00

100.00%

649.72

0.00%

0.00

0.00%

0.00

947.15

0.00%

0.00
0.00

42.41

CONCRETO ARMADO

05.03.03.04.01

CONCRETO PARA POZO DE PERCOLACION F'C=175KG/CM2

m3

2.49

380.38

947.15

0.00%

0.00

05.03.03.04.02
05.03.03.04.03

ENCOFRADO Y DESENCOFRADO NORMAL


ACERO CORRUGADO FY=4200 kg/cm2

m2
kg

19.21
2,499.52

44.72
5.23

859.07

0.00%

0.00

19.21

100.00%

859.07

19.21

100.00%

859.07

0.00%

13,072.49

0.00%

0.00

2,499.52

100.00%

13,072.49

2,499.52

100.00%

13,072.49

0.00%

0.00

4,167.89

0.00%

0.00

0.00%

0.00

0.00%

0.00

37.33

100.00%

4,167.89

05.03.03.05

MUROS Y TABIQUES

05.03.03.05.01

MAPOSTERIA DE PIDRA ANGULOSA E=.25m

m2

37.33

111.65

05.03.03.06
05.03.03.06.01

TUBERIAS Y ACCESORIOS VARIOS


ACCESORIOS PARA POZO DE PERCOLACION

und

2.00

19.30

38.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.00

100.00%

38.60

05.03.03.07

FILTROS
m3
m3

5.89
27.35

59.30
51.05

349.28

0.00%

0.00

0.00%

0.00

0.00%

0.00

5.89

100.00%

349.28

1,396.22

0.00%

0.00

0.00%

0.00

0.00%

0.00

27.35

100.00%

1,396.22

0.00%

0.00

05.03.03.07.01
05.03.03.07.02
05.03.04

RELLENO CON PIEDRA MEDIANA EN FONDO MAX 3" - 5"


RELLENO CON GRAVA 1/2"
CAJAS DE DISTRIBUCION (01 UND.)

05.03.04.01

OBRAS PRELIMINARES

05.03.04.01.01
05.03.04.02

LIMPIEZA MANUAL DE TERRENO NORMAL


MOVIMIENTO DE TIERRAS

m2

4.49

1.17

5.25

0.00%

0.00

4.49

100.00%

5.25

4.49

100.00%

5.25

05.03.04.02.01

EXCAVACION MANUAL DE ZANJAS

m3

6.51

24.93

162.29

NIVELACION INTERIOR Y APISONADO MANUAL

m2

2.34

2.61

0.00
0.00

100.00%
0.00%

162.29
0.00

6.51
-

100.00%
0.00%

162.29
0.00

2.34

0.00%
100.00%

0.00
6.11

05.03.04.02.03
05.03.04.02.04

RELLENO CON MATERIAL PROPIO


ELIMINACION DE MATERIAL EXCEDENTE

m3
m3

1.81
5.87

19.73
15.32

6.11
35.71

0.00%
0.00%

6.51

05.03.04.02.02

0.00%

0.00

0.00%

0.00

0.00%

0.00

1.81

100.00%

35.71

89.93

0.00%

0.00

0.00%

0.00

0.00%

0.00

5.87

100.00%

89.93

CONCRETO F'C=210 KG/CM2

m3

0.95

435.50

413.73

0.00%

0.00

0.00%

0.00

0.00%

0.00

0.95

100.00%

413.73

ENCOFRADO Y DESENCOFRADO NORMAL


ACERO CORRUGADO FY=4200 kg/cm2

m2
kg

13.04
39.59

44.72
5.23

583.15

0.00%

0.00

0.00%

0.00

0.00%

0.00

13.04

100.00%

583.15

207.06

0.00%

0.00

0.00%

0.00

0.00%

0.00

39.59

100.00%

207.06

05.03.04.03
05.03.04.03.01
05.03.04.03.02
05.03.04.03.03
05.03.04.04

CONCRETO ARMADO

REVOQUES ENDUCIDOS Y MOLDADURAS

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
05.03.04.04.01
05.03.05
05.03.05.01
05.03.05.01.01
05.03.05.02
05.03.05.02.01
05.03.05.02.02
05.03.05.02.03
05.03.05.03

Descripcin
TARRAJEO CON IMPERMEABILIZANTES

Und.

Metrado

m2

6.94

Precio S/.
35.81

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO

Parcial S/.

METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

248.52

0.00%

0.00

0.00%

0.00

0.00%

0.00

6.94

100.00%

VALORIZADO
248.52

INSTALACIONES SANITARIAS
OBRAS PRELIMINARES
m2

32.00

1.17

37.44

0.00%

0.00

0.00%

0.00

0.00%

0.00

32.00

100.00%

37.44

EXCAVACION MANUAL DE ZANJAS

m3

9.60

24.93

239.33

0.00%

0.00

0.00%

0.00

0.00%

0.00

9.60

100.00%

239.33

CAMA DE APOYO
RELLENO CON MATERIAL PROPIO

m
m3

32.00
4.80

32.08
19.73

1,026.56

0.00%

0.00

0.00%

0.00

0.00%

0.00

32.00

100.00%

1,026.56

94.70

0.00%

0.00

0.00%

0.00

0.00%

0.00

4.80

100.00%

94.70

LIMPIEZA MANUAL DE TERRENO NORMAL


MOVIMIENTO DE TIERRAS

TUBERIAS

05.03.05.03.01

TUBERIA PVC UF DN 200 SERIE 25

4.00

11.73

46.92

0.00%

0.00

0.00%

0.00

0.00%

0.00

4.00

100.00%

46.92

05.03.05.03.02
05.03.05.04

TUBERIA PVC UF DN 100 SERIE 25


CONCRETO SIMPLE

28.00

8.85

247.80

0.00%

0.00

0.00%

0.00

0.00%

0.00

28.00

100.00%

247.80

CONCRETO F'C=175 Kg/CM2

m3

0.38

380.38

0.00%

0.00

0.00%

0.00

0.00%

0.00

0.38

100.00%

144.54

m2

2.88

44.72

144.54
128.79

ENCOFRADO Y DESENCOFRADO NORMAL

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.88

100.00%

128.79

m2

20.00

3.28

0.00%

0.00

0.00%

0.00

0.00%

0.00

20.00

100.00%

65.60

20.00

2.84

65.60
56.80

m2

0.00%

0.00

0.00%

0.00

0.00%

0.00

20.00

100.00%

56.80

EXCAVACION MASIVA EN TERRENO SEMIROCOSO CON RETROEXCAVADORA

m3

36.00

30.00

1,080.00

REFINE Y NVELACION EN TERRENO NORMAL

20.00

1.63

32.60

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

36.00
20.00

100.00%
100.00%

1,080.00
32.60

m3

93.60

15.32

1,433.95

0.00%

0.00

0.00%

0.00

0.00%

0.00

93.60

100.00%

1,433.95

m2

20.00

36.22

724.40

0.00%

0.00

0.00%

0.00

0.00%

0.00

20.00

100.00%

724.40

CONCRETO EN LOSAS MACISAS f'c=210 kg/cm2


ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS

m3
m2

14.39
172.00

370.80
40.05

5,335.81

0.00%

0.00

0.00%

0.00

0.00%

0.00

14.39

100.00%

5,335.81

6,888.60

0.00%

0.00

0.00%

0.00

0.00%

0.00

172.00

100.00%

6,888.60

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60

kg

289.88

5.23

1,516.07

0.00%

0.00

0.00%

0.00

0.00%

0.00

289.88

100.00%

1,516.07

m2

172.00

30.73

5,285.56

0.00%

0.00

0.00%

0.00

0.00%

0.00

172.00

100.00%

5,285.56

und

2.00

1,583.78

3,167.56

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.00

100.00%

3,167.56

120.00

29.24

3,508.80

0.00%

0.00

0.00%

0.00

0.00%

0.00

120.00

100.00%

3,508.80

m2

92.96

3.28

304.91

0.00%

0.00

0.00%

0.00

0.00%

0.00

92.96

100.00%

304.91

m2

95.96

2.84

272.53

0.00%

0.00

0.00%

0.00

0.00%

0.00

95.96

100.00%

272.53

213.81

30.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

213.81

100.00%

6,414.30

05.03.05.04.01
05.03.05.04.02
05.03.06
05.03.06.01
05.03.06.01.01
05.03.06.01.02
05.03.06.02
05.03.06.02.01
05.03.06.02.02
05.03.06.02.03
05.03.06.03
05.03.06.03.01
05.03.06.04
05.03.06.04.01
05.03.06.04.02
05.03.06.04.03

CAMARA DE CONTACTO DE CLORO (2 UND)


TRABAJOS PRELIMINARES
LIMPIEZA DEL TERRENO MANUAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

ELIMINACION DE MATERIAL EXCEDENTE


OBRAS DE CONCRETO SIMPLE
SOLADO DE CONCRETO E=4" DE CONCRETO 1:10
OBRAS DE CONCRETO ARMADO

05.03.06.05

REVOQUES ENDUCIDOS Y MOLDADURAS

05.03.06.05.01
05.03.06.06

TARRAJEO INTERIOR CON IMPERMEABILIZANTES


ACCESORIOS

05.03.06.06.01
05.03.06.07
05.03.06.07.01
05.03.07
05.03.07.01
05.03.07.01.01
05.03.07.01.02
05.03.07.02

0.00

ACCESORIOS PARA CAMARA DE CONTACTO


CERCO PERIMETRICO
CERCO PERIMTRICO
FILTRO BIOLOGICO (2 UND)
TRABAJOS PRELIMINARES
LIMPIEZA DEL TERRENO MANUAL
TRAZO Y REPLANTEO INICAL
MOVIMIENTO DE TIERRAS

05.03.07.02.01

EXCAVACION EN TERRENO COMPACTO

m3

05.03.07.02.02

REFINE Y NVELACION EN TERRENO NORMAL

92.96

1.63

6,414.30
151.52

0.00%

0.00

0.00%

0.00

0.00%

0.00

92.96

100.00%

05.03.07.02.03
05.03.07.02.04

RELLENO CON MATERIAL PROPIO


ELIMINACION DE MATERIAL EXCEDENTE

m3
m3

18.59
253.78

19.73
15.32

366.78

0.00%

0.00

0.00%

0.00

0.00%

0.00

18.59

100.00%

366.78

3,887.91

0.00%

0.00

0.00%

0.00

0.00%

0.00

253.78

100.00%

3,887.91

151.52

05.03.07.03

OBRAS DE CONCRETO SIMPLE

05.03.07.04

SOLADO DE CONCRETO E=4" DE CONCRETO 1:10

m2

92.96

36.22

3,367.01

0.00%

0.00

0.00%

0.00

0.00%

0.00

92.96

100.00%

3,367.01

05.03.07.05
05.03.07.05.01

OBRAS DE CONCRETO ARMADO


CONCRETO F'C=210 KG/CM2

m3

53.61

370.80

19,878.59

0.00%

0.00

0.00%

0.00

0.00%

0.00

53.61

100.00%

19,878.59
22,622.64

m2

564.86

40.05

0.00%

0.00

0.00%

0.00

0.00%

0.00

564.86

100.00%

ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60


REVOQUES ENDUCIDOS Y MOLDADURAS

kg

1,516.50

5.23

22,622.64
7,931.30

05.03.07.05.03
05.03.07.06

0.00%

0.00

0.00%

0.00

0.00%

0.00

1,516.50

100.00%

7,931.30

05.03.07.06.01

TARRAJEO INTERIOR CON IMPERMEABILIZANTES

m2

462.50

30.73

14,212.63

TARRAJEO EN EXTERIORES

m2

195.64

19.76

3,865.85

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00%
0.00%

0.00
0.00

462.50
195.64

100.00%
100.00%

14,212.63
3,865.85

4.00

71.32

285.28

0.00%

0.00

0.00%

0.00

0.00%

0.00

4.00

100.00%

285.28

m3

176.64

51.05

9,017.47

0.00%

0.00

0.00%

0.00

0.00%

0.00

176.64

100.00%

9,017.47

52.00

20.80

1,081.60

0.00%

0.00

glb

1.00

36,502.99

36,502.99

0.00%

0.00

mes

6.00

500.00

3,000.00

0.00%

0.00

05.03.07.05.02

05.03.07.06.02
05.03.07.07
05.03.07.07.01
05.03.07.07.02
05.03.08
05.03.08.01
06
06.01
07

ENCOFRADO Y DESENCOFRADO NORMAL

INSTALACIONES SANITARIAS
TUBERIA PVC UF DN 10" SERIE 25
MATERIAL FILTRANTE 02

CARPINTERIA METALICA
VERTEDEROS DE REPARTICIION
FLETE
FLETE TERRESTRE

0.60

0.00%

0.00

60.00%

21,901.79

0.00%

0.00

0.60

0.00%

0.00

52.00

100.00%

1,081.60

60.00%

21,901.79

0.40

40.00%

14,601.20

0.00%

0.00

6.00

100.00%

3,000.00

IMPACTO AMBIENTAL

07.01
07.01.01

OBRAS PROVISIONALES
PROVISION E INSTALACION DE SERVICIOS HIGIENICOS

07.02

REFORESTACION

VALORIZACION DE OBRA N 01
OBRA
ENTIDAD
UBICACIN
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MODALIDAD
MONTO CONTRACT.

FIRMA DE CONTRATO
ENTREGA DE TERRENO
PLAZO DE EJECUCION
INICIO DE OBRA
FECHA DE TERMINO PREVISTA

SEGN EXPEDIENTE TECNICO


Item
07.02.01
07.03

Descripcin
SEMBRADO DE ARBUSTOS DE LA ZONA

Und.

Metrado

Precio S/.

Parcial S/.

VALORIZACION
AVANCE ACTUAL

ANTERIOR ACUMULADO
METRADO

VALORIZADO

METRADO

SALDO
AVANCE ACUMULADO
VALORIZADO

METRADO

VALORIZADO

METRADO

VALORIZADO

m2

530.00

37.73

19,996.90

0.00%

0.00

0.00%

0.00

0.00%

0.00

530.00

100.00%

19,996.90

CAPACITACION Y SENSIBILIZACION

07.03.01

CAPACITACION - EN EDUCACION SANITARIA AGUA

glb

2.00

3,550.00

7,100.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.00

100.00%

7,100.00

07.03.02

CAPACITACION Y FORMACION JASS

glb

2.00

3,550.00

7,100.00

0.00%

0.00

0.00%

0.00

0.00%

0.00

2.00

100.00%

7,100.00

COSTO DIRECTO
GASTOS GENERALES 8%
UTILIDADES 7%
SUBTOTAL
IGV 18%
TOTAL PRESUPUESTO
PROCENTAJES

3,445,769.26
275,661.54
241,203.85
3,962,634.65
713,274.24
4,675,908.89

0.00
0.00
0.00
0.00
0.00
0.00
0.00%

573,973.62
45,917.89
40,178.15
660,069.66
118,812.54
778,882.20
16.66%

573,973.62
45,917.89
40,178.15
660,069.66
118,812.54
778,882.20
16.66%

2,871,795.66
229,743.65
201,025.70
3,302,565.01
594,461.70
3,897,026.71
83.34%

OBRA
ENTIDAD
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MONTO CONTRACTUAL :
VALORIZACION N :

AVA N C E P O RC EN TUA L

MES :

CUADRO COMPARATIVO DE AVANCE DE OBRA


PROGRAMADO VS EJECUTADO ACUMULADO

1.2

CURVA
"S"

92.11%
0.8

67.57%
0.6

42.76%

1 6 .6 6 %

0.4

0 .0 0 %

0.00%

0 .0 0 %

11.71%

0 .0 0 %

25.34%

0 .0 0 %

0 .0 0 %

0.2

CUADROS DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO
CONTRACTUAL

REAL

MONTOS TOTAL (no Inc/ IGV)


MESES

C.D. PARCIAL S/.

ACUMULADO S/..

AVANCE PORCENTUAL

MONTOS TOTAL (no Inc/ IGV)

PARCIAL %

ACUMULADO %

MESES

INICIO

C.D. PARCIAL S/.


0

26 OCTUBRE - 30 NOVIEMBRE

463,853.94

463,853.94

11.71%

11.71%

26 OCTUBRE - 30 NOVIEMBRE

01 DICIEMBRE - 31 DICIEMBRE

540,254.65

1,004,108.59

13.63%

25.34%

01 DICIEMBRE - 31 DICIEMBRE

01 ENERO - 31 ENERO

690,464.12

1,694,572.71

17.42%

42.76%

01 ENERO - 31 ENERO

01 FEBRERO - 28 FEBRERO

983,038.27

2,677,610.98

24.81%

67.57%

01 FEBRERO - 28 FEBRERO

01 MARZO - 31 MARZO

972,382.92

3,649,993.90

24.54%

92.11%

01 MARZO - 31 MARZO

01 ABRIL - 24 ABRIL

312,640.75

3,962,634.65

7.89%

100.00%

01 ABRIL - 24 ABRIL

TOTAL

3,962,634.65

100.00%

TOTAL

660,069.66

660,069.66

O COMPARATIVO DE AVANCE DE OBRA

PROGRAMADO VS EJECUTADO ACUMULADO

CURVA
"S"

100.00%
92.11%

67.57%

42.76%

0 .0 0 %

0 .0 0 %

0 .0 0 %

0 .0 0 %

34%

ADROS DEL PORCENTAJE DE AVANCE


PROGRAMADO VS EJECUTADO
REAL
MONTOS TOTAL (no Inc/ IGV)

AVANCE PORCENTUAL

ACUMULADO S/.

PARCIAL %

ACUMULADO %

0.00%

0.00%

660,069.66

16.66%

16.66%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00

16.66%

CUADRO COMPARATIVO DE AVANCE DE OBRA


OBRA
ENTIDAD
CONTRATISTA
SUPERVISION
SUPERVISOR
RESIDENTE
MONTO CONTRACTUAL S/ :
VALORIZACION N :
MES :

92.11%

AVANCE MENSUAL

AVANCE PROGRAMADO vs EJECUTADO

100.00%
67.57%

90.00%
80.00%

42.76%

70.00%
60.00%
25.34%

50.00%

11.71%

30.00%
20.00%

16.66%

40.00%

01 ENERO - 31
ENERO

01 FEBRERO - 28
FEBRERO

0.00%

01 DICIEMBRE - 31
DICIEMBRE

0.00%

26 OCTUBRE - 30
NOVIEMBRE

0.00%

INICIO

0.00%

0.00%

0.00%

0.00%

10.00%
01 MARZO - 31
MARZO

01 ABRIL

CUADRO COMPARATIVO DE AVANCE MENSUAL


PROGRAMADO VS EJECUTADO
N VALORIZACION

PERIODO DE EJECUCION

PORCENTAJES DE AVANCES MENSUALES


PROGRAMADO
ACUMULADO

0.00

INICIO

1.00
2.00
3.00
4.00
5.00

26 OCTUBRE - 30 NOVIE

6.00

01 DICIEMBRE - 31 DICIE
01 ENERO - 31 ENERO
01 FEBRERO - 28 FEBRER
01 MARZO - 31 MARZO
01 ABRIL - 24 ABRIL

0.00%
11.71%
25.34%
42.76%
67.57%
92.11%
100.00%

RO COMPARATIVO DE AVANCE DE OBRA

01 MARZO - 31
MARZO

0.00%

01 FEBRERO - 28
FEBRERO

0.00%

01 ENERO - 31
ENERO

0.00%

EMBRE - 31
BRE

0.00%

0.00%

25.34%

42.76%

67.57%

92.11%

100.00%

PROGRAMADO vs EJECUTADO

01 ABRIL - 24 ABRIL

CUADRO COMPARATIVO DE AVANCE MENSUAL


PROGRAMADO VS EJECUTADO
PORCENTAJES DE AVANCES MENSUALES
EJECUTADO
ACUMULADO

0.00%
16.66%
0.00%
0.00%
0.00%
0.00%
0.00%

Anda mungkin juga menyukai