Summary of All works

1Sump Tank
2Installation of Steel Tank And Foundation Constru
3Surge Tank Foundation construction
4Supply of Pressed Steel Tank And it Fittings

Total

ndation Construction
it Fittings

Sump Tank Bill of Quantity


ITEM

DESCRIPTION

UNIT

1
1.1

Earth Work
Clearing the top soil and unwanted material to a depth of 200 mm

m2

1.2

Bulk excavation in ordinary soil to depth not greater than 1.5 m

m3

1.3

Cart away all excavated material, deposit to appropriate distance not


exceeding 1 km
250 mm thick hard trachyte stone hard core hand picked

m3

1.4
2
2.1

2.2

Concrete Work
lean concrete before construction of foundation
70mm thick lean concrete with mix ratio (1:3:6) under the reservoir base
slab, well compacted with vabirator compactor, curing and avoid
segregations and bleeding of concrete

m2

m2

Foundation structure
Reinforced concrete with grade C-35/30 n/mm2 filled into form work
and vibrated around reinforcement bar. Contractor should determine mix
ratio conducting concret cube/cylinderical compressive strenght test for
the specified concrete strenght of C 35/30 with 25mm maximum
aggregate as described in the following, curing and removal of formwork
in accordance to technical specification, provide concrete cover of 45mm
minimum Price shall include provision and fixing of formwork.

2.2.1

Base slab

m3

2.2.2

Concrete wall

m3

2.2.3

Column

2.2.4

Top slab

m3
m3

2.2.5

Ring Beam

m3

2.4

2.3.1
2.3.2
2.3.3
3

Provide, cut, bend and fix in position reinforced steel bar. All according
to structural drawing. Price should include tying wires
Diameter 8 mm deformed bar
Diameter 12 mm deformed bar
Diameter 16 mm deformed bar
Accessories & Finishing

kg
kg
kg

3.1.1

Provide and apply 50mm cement screed to the reservoir floor

m2

3.1.2

Provide and apply 3 coats of plaster to internal walls, and to embedded


part of external wall surface, water proof plaster type

m2

3.1.3

Rendering external wall

m2

3.1.5

Provide and fix 6 mm sheet metal access cover with latch and lock for
valve chamber and reservoir
Provide and apply two coats of bituminous asphalt over the plastered
surface of the embedded part of the reservoir

No

3.1.6

4
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
4.1.8

Supply & install pipes and fittings for Inlet pipe, complete with
gaskets, bolts, nuts, washers, etc
Inlet pipe
DN 100mm DCI flanged bell mouth
DN 100mm DCI double flanged pipe, L= 2.0 meters
DN 100mm DCI duck foot 90o deg double flanged bend

m2

No
No
No
No

4.1.9
4.1.10
4.1.11
4.1.12

DN 100mm DCI 90o double flanged bend


DN 100mm DCI double flanged pipe L=0.3 meters
DN 100mm DCI flanged gate valve
DN 100mm DCI dismantling joint
DN 100mm DCI double flanged pipe, L= 1.0 meters with puddle flange
in the middle
DN 100mm DCI flanged UPVC adopter
DN 100mm DCI double socket coupling
DN 100mm DCI flanged spigot
Pipe support with pipe clamp, wall bracket, foot plate and anchor bolt

No
No
No
No
No

4.2
4.2.1

Outlet pipe
DN 100mm flanged strainer

No

4.2.2

DN 100mm DCI double flanged 90 deg bend

No

4.2.3

No

4.2.4
4.2.5
4.2.6
4.2.7

DN 100mm DCI double flanged pipe, L=1.0 meters with puddle flange
in the middle
DN 100mm DCI double flanged gate valve
DN 100mm DCI flanged dismantling piece
DN 100mm DCI double flanged water meter
DN 100mm DCI double flanged pipe, L= 3.0 meters.

4.3
4.3.1
4.3.2
4.3.3
4.3.4

Overflow and Drain Pipe


DN 75mm DCI single flanged short piece
DN 75mm DCI double flanged 90 deg bend
DN 75mm DCI duck foot 90 deg double flanged bend
DN 75 DCI double flanged pipe L=1.0 meters

No
No
No
LS

No
No
No
No

No
No
No
No

4.3.5
4.3.6
4.3.7
4.3.8
4.3.9
4.3.10
4.3.11
4.4
4.5
4.6

DN 75mm DCI double flanged pipe L=0.2 meters


DN 75/75 DCI all flanged tee
DN 75mm DCI single flanged pipe, L= 1.0 meters with puddle flange in
the middle
DN 75mm DCI double flanged gate valve
DN 75mm DCI flanged dismantling piece
DN 75mm DCI flanged bell mouth
Pipe support with pipe clamp, wall bracket, foot plate and anchor bolt

No
No
No

Level indicator, complete as per the drawings


Galvanized steel ladder, for the inside and outside, complete as per the
drawings
DN 65mm ventilation pipe with dome L= 1.0 meters with screen elbow

set
LS

No
No
No
LS

No

4.7

Installation of Manhole cover 1200 x 1200 mm made of chrome plated


nickel steel with ventilation and safety lock

LS

4.8

Testing of the reservoir for leakage should be caried out on week

LS

total

QUANTIT
Y

RATE
(USD)

AMOUNT
(USD)

36

60

60

10

40

12

25.2

0.27

3
358
4759

40

75.6

75.6

25.2

3.00
6
3
3

4
4
1
4
3

3
1
3
3

3
3

3
3
3
3

1
3
1
1

1
1
1

1
1
2
1

1
1

Burao Water Supply Expansion Sub-Project

LOT - Install two 1000m3 Reservoirs on the Gro


ITEM

DESCRIPTION

1 Scope of work
The contractor/supplier shall supply (including transportation to the
site), install, sterilize and test for leackage a 1000 cubic meter tank
complete with piping and attached to the foundation Bed and ring
Beam as per the specifications, bill of quantities and drawings.

Foundation Construction Of 1000m3 Tank

Excavation and Earthwork


1.1 Excavation including maintaining and supporting sides and keeping free
from water, mud and fallen materials by bailing, pumping or otherwise

1.1.1 Raft foundation excavation commencing at reduced levels depth not exceeding
1000mm deep as shown on the drawings
1.1.2 Extra-over for excavation in soft rock
1.1.3 Extra-over for excavation in hard rock
1.1.4 Backfill (with origional excavated soil) around foundation and water meter
chamber
1.1.5 Remove surplus excavated material from site for 10km away as directed by
engineer
1.2 provision of backfill for 200mm thick with handpicked stone and 50mm literite full
compacted with 95% compaction
2

Concrete work

2.1

Lean concrete blinding C 15 with 70mm thick maximum aggregate size 20mm
with proper curing as per specification

2.2

Vibrated Mass concrete with grade C-35/30 N/mm2 filled into form work
and vibrated around reinforcement bar. Contractor should determine mix
ratio conducting concret cube/cylinderical compressive strenght test for the
specified concrete strenght of C 35/30 with 25mm maximum aggregate as
described in the following, curing and removal of formwork in accordance
to technical specification, provide concrete cover of 45mm minimum Price
shall include provision and fixing of formwork.

2.2.1 Matt Foundation Slab 0f 300mm thick


2.2.2 Ring beam support to the Steel beam

Steel & Reinforcement

3.1

Provide, cut, bend and fix in position reinforced steel bar. All according to
structural drawing. Price should include tying wires
Diameter 18 mm deformed bar
Diameter 16 mm deformed bar
Diameter 12 mm deformed bar

3.1.1

3.2

Provide steel I /H beam under the pressed steel tank size of

Concrete block work

A Supply and construct water meter chamber concrete block wall including internal
plastering using cement sand mortar 1:3 as per the drawings.

Sub-Total to Collection

5 Installation of pressed Water Tank


A install complete galvanized steel tank size 16m long x 12.5m wide x 4m high
made of pressed hot deep galvanized steel pannels as per the drawings.
Thickness of the pannels shall be 5 mm. The supply and installation includes
internal and external ladders as per the drawings and specifications.
The tank shall have the following accessories:
1) install internal and external ladders (to the tank roof) made of galvanized steel.
The ladders shall be fitted with safety cages and intermediate landing plateform.
The ladder to be painted with 2 coat of aluminum paint and shall conform to BS
4211.
2) Two fresh air vent pipes shall be fixed to the roof of the tank. They shall be
coiled to prevent rain from entering and fully mosquito-proofed with fine meshed
gauge all fixed to the satisfaction of the Engineer.
3) Float water level indicators that shall be attached to the side of each
compartment with vitreous enameled scales graduated at intervals of 0.5 metres
and clearly marked in indelible paint. Pointer and float shall be connected by a
steel cable. Guides for the cable shall be provided to prevent snagging or fouling
of cable travel.
4) Lightening Protection: the water tower structures are to be re-earthed at a
position at the base of the tower.
5) two lockable manhole cover.
6) Two sign posts to be fixed on to the sides of the water tank. Dimention of each
sign post is 2.25 M x 3 M.

C Supply and install all the requisite pipe work including inlet, outlet, overflow, and
washout pipework to the sock away pit as following and as per the drawings:
Supply and install the piping system, which includes:
- One inlet made with 8" (200 mm) stainless steel pipe (24 meters long),
complete with all necessary fittings and valves as shown on the drawings.
- Overflow pipes made with 8" (200 mm) stainless steel pipes (37 meters long),
complete with all necessary fittings and valves as shown on the drawings.
- Drain pipe made with 4" (100 mm) stainless steel pipes (around 18 meters
long) to be connected to the overflow, complete with all necessary fittings and
valves as shown on the drawings.
- Outlet pipe made with 8" (200 mm) stainless steel pipes (19 meters long),
complete with all necessary fittings, valves, water meter, as shown on the
drawings.

D Sterilizing/disinfecting and testing for leakage:


Sterilze tanks by filling them with potable water containing 50 mg/l of chlorine and
permitting them to stand 6 hours when full. Thereafter the residual chlorine shall
be measured. If no residual is found the process must be repeated.
Supply water fill the tanks to test for leakage as per the advise of the site Engineer

Expansion Sub-Project

Reservoirs on the Ground


UNIT

RATE
(USD)

QTY

Note

m3

60
40
40

m3

30

m3

120

m3

50

m2

14

m3
m

Note
m3

60

m3

57.6

AMOUNT
(USD)

Note
kg
Kg
Kg

10080
884.80
497

no

20

m2

10.32

No
No

1
1

LS

LS

Surge Tank Bill of Quantity


ITEM

DESCRIPTION

UNIT

Foundation & Frame support structure for Surge Tank


1 Concrete Work
1.1 Vibrated rcc concrete with grade C-35/30 n/mm2 filled into

form work and vibrated around reinforcement bar.


Contractor should determine mix ratio conducting concret
cube/cylinderical compressive strenght test for the specified
concrete strenght of C 35/30 with 25mm maximum
aggregate as described in the following, curing and removal
of formwork in accordance to technical specification,
provide concrete cover of 45mm minimum Price shall
include provision and fixing of formwork.

1.1.1

Column

Note
m3

1.1.3

Footing

m3

2 Reinforcement Bars

2.1

2.1.1
2.1.2
2.1.3

Provide, cut, bend and fix in position reinforced steel bar.


All according to structural drawing. Price should include
tying wires
Diameter 8 mm deformed bar
Diameter 12 mm deformed bar
Diameter 16 mm deformed bar

kg
kg
kg

3 Steel

Provide Steel I Beam welding Plate connection bolted to


the column support
Total

Surge Tank

no

Quantity
RATE
(USD)

QUANTITY

AMOUNT (USD)

0.54

1.728

$
$

$
$
$
$

3
358
264

Bill of Quantity
Supply Of 1000m3 Pressed Steel Tank Bill of Quantity
Item

Description
A Supply complete galvanized steel tank size 16m long x 12.5m wide x 4m high made of
pressed hot deep galvanized steel pannels as per the drawings. Thickness of the
pannels shall be 5 mm. The supply and installation includes internal and external
ladders as per the drawings and specifications.
The tank shall have the following accessories:
1) Supply internal and external ladders (to the tank roof) made of galvanized steel. The
ladders shall be fitted with safety cages and intermediate landing plateform. The ladder
to be painted with 2 coat of aluminum paint and shall conform to BS 4211.
2) Supply fresh air vent pipes shall be fixed to the roof of the tank. They shall be coiled
to prevent rain from entering and fully mosquito-proofed with fine meshed gauge all
fixed to the satisfaction of the Engineer.
3) Supply Float water level indicators that shall be attached to the side of each
compartment with vitreous enameled scales graduated at intervals of 0.5 metres and
clearly marked in indelible paint. Pointer and float shall be connected by a steel cable.
Guides for the cable shall be provided to prevent snagging or fouling of cable travel.
4) Supply Lightening Protection: the water tower structures are to be re-earthed at a
position at the base of the tower.
5) two lockable manhole cover.
6) Two sign posts to be fixed on to the sides of the water tank. Dimention of each sign
post is 2.25 M x 3 M.

B
C Supply all the requisite pipe work including inlet, outlet, overflow, and washout pipework
to the sock away pit as following and as per the drawings:
Supply the piping system, which includes:
- One inlet made with 12" (315 mm) stainless steel pipe (24 meters long), complete
with all necessary fittings and valves as shown on the drawings.
- Overflow pipes made with 8" (200 mm) stainless steel pipes (37 meters long),
complete with all necessary fittings and valves as shown on the drawings.
- Drain pipe made with 4" (100 mm) stainless steel pipes (around 18 meters long) to
be connected to the overflow, complete with all necessary fittings and valves as shown
on the drawings.
- Outlet pipe made with 12" (315 mm) stainless steel pipes, complete with all
necessary fittings, valves, water meter, as shown on the drawings.

D Sterilizing/disinfecting and testing for leakage:


Sterilze tanks by filling them with potable water containing 50 mg/l of chlorine and
permitting them to stand 6 hours when full. Thereafter the residual chlorine shall be
measured. If no residual is found the process must be repeated.
Supply water fill the tanks to test for leakage as per the advise of the site Engineer

Total Sum

Tank Bill of Quantity


Unit

Quantity

Rate

Total

No
No

$
$

LS

LS