Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 1
Doc. Title
Doc. No
CM MS BW - 023
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
CONTENT
1.
Purpose
Page 3
2.
Scope of Work
Page 3
3.
Page 3
4.
Shop Drawing
Page 4
5.
Work Procedure
Page 4
6.
Quality Control
Page 7
7.
Safety Control
Page 7
Appendix 1-2
Page 2
Doc. Title
Doc. No
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Page 3
Doc. Title
Doc. No
CM MS BW - 023
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
1. PURPOSE
The Purpose of this Method Statement is to describe the process of painting works for exterior
and interior emulsion paint in compliance with all the required specifications, standards, and
proper construction procedures for the building finishing works of the project.
2. SCOPE OF WORK
The scope of work for the construction of the items are as follows :
Supply, rub down and apply emulsion paint for plastered surface (Exterior)
Supply, rub down and apply emulsion paint for plastered surface (Interior)
4. SHOP DRAWING
Shop drawings shall be submitted to the Engineer by separated document for review and
approval before carrying out the works.
5. WORK PROCEDURE
5.1.
Applying Skimcoat
Thickness Checking
Dry Surface
Finishing Coat (Layer 1)
Confirm Surface
Thickness Inspection
Surface Sanding
Apply Sealer
Fail
Page 4
Sampling
Brick Laying
/ Testing
Finish
Sampling
Plastering
/ Testing
Doc. Title
Doc. No
CM MS BW - 023
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Dry surface
Minimum drying time : 16 hours at 250C
Confirm Surface
Use appropriate device for checking to make sure dried surface meet the required thickness
is not greater than 1mm
Surface must be dry and firm
Surface Grinding
Use sandpaper to grind coated surface to make a smooth and fine surface
Apply Sealer
Dilute sealer with 5% of water if necessary.
Stir up within 3 minutes
Apply sealer paint on grinding surface by paint roller to get 1003 microns wet face
thickness (dry face thickness approx. 353 microns)
Wait 2 hour at 300C before applying finishing coat.
Thickness checking
Use Elcometer device to check, ensure the required dry face thickness (353 microns) to
prevent foreign object and increase bond between painting layers
Page 5
Doc. Title
Doc. No
CM MS BW - 023
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Thickness Inspection
Painted surface must be dry, clean, firm, smooth and uniform in color.
Total dry face thickness must be at least 703 micron.
Finish
All painting layer testing can be applied after 7 days at 300C
6. QUALITY CONTROL
6.1.
Before start Painting, Inspection and Testing Plan shall be established to keep proper quality of
the works in accordance with specification and standard. ITP shall be submitted to the
Engineer for approval.
6.2.
Delivery Inspection
After deliver the materials to the site, delivery inspection shall be conducted with witnessed by
the Engineer. Frequency of delivery inspection shall be indicated in the ITP.
6.3.
Thickness measurement :
7. SAFETY CONTROL
7.1. Fundamental Policy
Safety is the First Priority"
7.2. Key Activities
Pick up hazardous factors of each work activity and always reflect them at the safety
meetings.
Page 6
Doc. Title
Doc. No
CM MS BW - 023
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
7.4. Point out them every day at the meetings in order to let individual worker to renovate his safety
consciousness
Page 7
Doc. Title
Doc. No
Rev. No.
Date
May, 2012
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal
Appendix 1
Inspection and Testing Plan
Page 8