Sl No Technical Query

1
2
3
4
5
6

As per the drawing AF 1314035 V 210-B00010 location of sight glass is


overlapping with horizontal tank weld joints.
Refer the Drwaing AF 1314035P330-B00200,1'' IA-15508A Iso drawing
is not available in the package.
Hydrotesting is shown to the pump skid drain line and casing
line.Excemption of Hydrotesting of drain lines
Refer line 4''-PZ-15167 And 3''-PZ-15162 Lines are open trench drain
and,Excemption of Hydrotesting of drain lines
Detailrequired of materaial shown in the drawing no 8016S C340Z00100 for storage tank foundation as highlighted
If we have to proceed for seal welding around the corner of zinc plate
with bottom plates of storage tank TK 1551
Reference the DWG 8016S C310-Z00100 of layout for TK 5550 in
Plant V,P5550A/B located exactly over highvoltage cable trench and
cables as attached.
Pipe to pipe connection are not mentioned in the line 1 1/2'' HAL5132

Date

Recommendation

Status

26-Nov-16 Sight Glass location lowerd 55mm to avoid Interference

Closed

20-Nov-16 As per site redmarkup can be used after approval

open

24-Nov-16 Pump skid and Casing drain line can be excempt from the Hydrotest

Closed

27-Oct-16

Drain Line Hydrotest not required

Closed

12-Jan-16

Recommended Materials are bond liner with ring and crushed stone

Closed

14-Aug-16 Please proceed with seal welding

Closed

20-Oct-16

Location of Pump and tank shall be replaced and distance between


foundation reduced 200mm

Closed

4-Apr-16

couplings A 105 LB3000 SW Shall be used.

Closed

Can we exempt the hydortesting of below lines which are darin,vent


and open to atmsphere.
1)2''-PZ18-Sep-16
T51-B-13-1,2''-HAL-TK51-N-7,2''-HAL-TK51-N-7,1''-PZ-T52-N-7,1''-PZV53-N-5-1,3/4''-PZ-E51-N,3/4''-PZ-E51-N-9&3/4-PZ-E51-N-10

100% NDT to be performed in lieu of Hydotest

Closed

10

Can we use SS 316 Intead of 304 fittings as per attached drawings

4-Apr-16

SS 316 can be used for fittings/pipes

Closed

15-Jun-16

Higher Sizes can be used

Closed

7
8

11
12
13
14
15
16
17
18
19

According to AF-1314035P321-B00200,use of 200x80 channel instaed


of C 152X88.9
according to BOM we require ERW A53/A106 pipe but we requires
SMLS pipe from MHI
Use of ERW Grade A pipe Intstaed of GR B for Tank Handrail
Use of Flange A 182-ANSI SCH 40 Flange instaed of SCH 10S,Reference
drawing AF-1314035P330-C00302
Refer the Line AL-16205 As per Isometrics is overlapping with plant
road.To maintain distance between plant raod and pipeline route
changed as per red markup
Pneumatic Pressure of below lines are not 1.1. times of design
pressure.2''-IA,2''PA & 2''N
Use of cahnnel 75x40 Instead of C 50X38
Hydrotest Pressure of Below lines are not 1.5 times of Design
pressure.2''-PZ-15156-A,2''-PZ-15156 And 1 1/2 HAL-15139C
radiography mentioned in the drawing 2'' PA-15210 AND 2''-PTW11033 is not applicable as these are threaded lines.

14-May-16 SMLS can be used instead of ERW

Closed

16-Jul-16

Proceed for Grade A if Grade B readliy available with supplier

Closed

19-Jul-16

Please proceed with 40 SCH

Closed

20-Jul-16

Redmarkup approved as per site condition.

Closed

6-Oct-16

1.1 Times of design pressure for pneumatic test is ok

Closed

30-Oct-16

Ok As per site conditions

Closed

8-Oct-16

1.5 itmes of design pressure is ok

Closed

8-Oct-16

RT not required.

Closed

20

As per attached survey analysis theere is a rectifiable deviation


between easting and Northing of shifted BM-1.Approval for survey
works from anchor bolts of pipe rack PR-203,PR-142A And PR-142B

12-Jan-16

Proceed as per revised drawing

Closed

21

Refer to the Power cable specification mentioned in Cable Schedule


Plant II colour code of multicore cable is mentioned is Brown,Black &
Grey but according to SABIC standra it Red,Yellow and Blue

3-Jan-16

Brown,black and grey is required but sleeves can be used at the end.

Closed

22

Refer to the Instrument Cable Schedule/BOQ/Hookup(Documents


#8016SK477-B00100,REV-01-01) Voltage ratings of cables are not
mentioned in all AR RAZI documents these ratings are mandatoru for
procuring cables.

4-Jan-16

300 Volts is required

Closed

23

Refernce to Drwg AF-1314035C305-Z100 for TK-1551 theitems asphalt


impregnated fibre boards is avaible with 12mm nd 18mm in the
14-Jan-16
market.Drawing 20mm thck shown

Approval is subjected to installation as per IFC adraings requiremnts

Closed

24

As pe rattached Drwaing B00720 confirmation required ,there are bolt


to bolt dimension affecting the attached edge distance.Minimum bolt 15-Mar-16 As per attached drawing with comments.
to bolt distance required 50mm but in details 45mm

Closed