Anda di halaman 1dari 5

Thyristor-Based HVDC Transmission System (Average Model)

This example shows the steady-state and transient performance of a 12-pulse,


1000 MW (500 kV-2kA) 50/60 Hz HVDC transmission system.
Silvano Casoria (Hydro-Quebec)

Detailed Versus Average Model


When modeling line-commutated converter based HVDC systems you can use
two types of model, depending on the range of frequencies to be represented:
The detailed model such as the one presented in the power_hvdc12pulse model
includes detailed representation of the converter unit with its power electronic
thyristor bridge and converter transformer. This model is well suited for
observing harmonics and control system dynamic and transient performance.
The average model such as the one presented here where the converter unit
(bridge and transformer) is represented by an equivalent voltage source
generating the bridge average DC voltage and AC sources generating the
fundamental component of the currents flowing into the network. This model
does not represent harmonics, but the dynamics resulting from control system
and power system interaction is preserved. This model allows using a time step
that is higher than the one of the control system or the network. Optimal
performance however is obtained by using the same time step of the control
system regulators.
Description

A 1000 MW (500 kV, 2kA) DC interconnection is used to transmit power from a


500 kV, 5000 MVA, 60 Hz network to a 345 kV, 10 000 MVA, 50 Hz network. The
rectifier and the inverter are average models of 12-pulse converters representing
two 6-pulse thyristor bridges connected in series. The rectifier and the inverter
are interconnected through a 300 km distributed parameter line and two 0.5 H
smoothing reactors.
The converter transformer linear representation is part of the average model
block. The transformer tap changers are not simulated and fixed taps are
assumed as model inputs. At the rectifier the tap ratio (Nprimary/Nsecondary) is
0.9 (pu) and at the inverter it is 0.96 (pu). Reactive power required by the
converters is provided by a set of capacitor banks plus 11th, 13th and high pass
filters for a total of 600 Mvar on each side. Note that since no harmonics are
generated by the average converter model the Mvar could be provided entirely
by capacitor banks.
Two circuit breakers are used to apply faults on the inverter AC side and rectifier
DC side. The rectifier and inverter control systems use the Discrete HVDC
Controller block of the Extras/Discrete Control Blocks library. Note that since
thyristor valves are not present the 12-pulse Firing Control block is no longer
necessary in the average mode.
DC Protection functions are implemented in each converter. At the rectifier, the
DC fault protection will detect and force the delay angle into the inverter region
so to extinguish the fault current. At the inverter, the commutation failure
prevention control will detect AC faults and reduce the maximum delay angle
limit in order to decrease the risk of commutation failure. Note that the
commutation failure phenomenon is not possible in the average model.
To assist the user in identifying conditions that may produce this phenomenon an
indication from the model is provided ( CF_alarm signal available from the Bus
Selector block of the rectifier and inverter models). The Low AC Voltage
Detection blocks will lock the DC fault protection when a drop in the AC voltage is
detected. The Master Control block initiates the starting and stopping of the
converters as well as the ramping up and down of the current references.
A description of the control systems is provided in the HVDC Transmission
System Case Study of the User's Manual. The firing angle order (alpha_ord)
output of the controller is an input of the average model.
The power system and the control system are both discretized for a sample time
Ts=50 us. The "Model initialization" section of the model automatically sets Ts =
50e-6 in your MATLAB workspace. It also sets the average model time step
Ts_avg equal to Ts.
Simulation
The system is programmed to start and reach a steady state. Then steps are
applied on the reference current of the rectifier and on the inverter reference
voltage in order to observe the dynamic response of the regulators. Finally, a

stop sequence is initiated to bring the DC power down before blocking the
converters.
Start the simulation, open the RECTIFIER and INVERTER scopes (in the Data
Acquisition subsystem) and observe the DC line voltage on trace 1 (1pu = 500
kV) and the DC line current (reference and measured values) on trace 2 (1pu = 2
kA).
Start-up and Stop
In the Master Control, the converters are unblocked and started by ramping the
rectifier and inverter reference current.
At t = 0.02 s (i.e. when the converters at unblocked), the reference current is
ramped to reach the minimum value of 0.1 pu in 0.3 s (0.33 pu/s). At the end of
this first ramp (t = 0.32 s) the DC line is charged at its nominal voltage and DC
voltage reaches steady-state.
At t= 0.4 s, the reference current is ramped from 0.1 pu to 1 pu (2kA) in 0.18 s (5
pu/s). At the end of this starting sequence (t=0.58 s), the DC current reaches
steady state. The RECTIFIER then controls the current and the INVERTER controls
the voltage.

In steady-state, the alpha firing angles (trace 3) are 17.7 degrees and 144.5
degrees respectively on the RECTIFIER and INVERTER sides. Note that in the
detailed model these traces (16.5 for the rectifier and 143 for the inverter) are
not the measured firing delay angles but the corresponding orders from the
control regulators. In the detailed model, the firing angles are smaller because
the regulators must advance the firing orders by two time steps in order to
compensate for the delays introduced by interfacing of input AC voltages and
output firing pulses of the 12-pulse Firing Control block. The extinction angle
gamma value is an output of the average model. It is used at the INVERTER and
shown in trace 5. In steady-state, its value is 23 degrees.
The control mode of operation (an integer between 0 to 6) is shown in trace 4
(0= blocked; 1=Current control; 2=Voltage control; 3=Alpha minimum limitation;
4=Alpha maximum limitation; 5=Forced or constant alpha; 6=Gamma control).
At t = 1.4 s the Stop sequence is initiated by ramping down the current to 0.1 pu.
At t = 1.6 s a Forced-alpha at the Rectifier extinguishes the current and at the
Inverter the Forced-alpha brings down the DC voltage.
At t = 1.7 s the pulses are blocked in both converters.
Step response of current and voltage regulators
Verify in the Master Control that the "Enable Ref. Current Step" switch is in the
upper position. This switch is used to apply a step on the reference voltage. Also

verify that the Ref. Voltage Step is enabled in the Inverter Control. Start the
simulation.
At t=0.7 s, a -0.2 pu step is first applied on the reference current (decrease from
1 pu to 0.8 pu ) and at t=0.8 s, the reference current is reset to its 1 pu original
value. The current stabilizes in approximately 0.1 seconds. Steps are also applied
on the reference voltage of the inverter (-0.1 pu / +0.1 pu at t=1.0 s / 1.1s).
DC line fault at the rectifier
Deactivate the steps applied on the current reference and on the voltage
reference in the Master Control and in the inverter control respectively by setting
the switches in lower position.
The DC Fault protection (DCPROT) in the rectifier is activated by default. In the
DC Fault block, change to 1 the 100 multiplication factor in the Switching times
so that a fault is now applied at t = 0.7 s.
Reduce the Simulation stop time from 2 to 1.4 s. Open the FAULT scope to
observe the DC fault current. Restart the simulation.
At fault application the DC current quickly increases to 2.63 pu and the DC
voltage falls to zero at the rectifier. This DC voltages drop is seen by the Voltage
Dependent Current Order Limiter (VDCOL) which reduces the reference current to
0.3 pu at the rectifier. A DC current still continues to circulate in the fault.
At t = 0.77 s, the rectifier alpha firing angle is forced to 166 degrees by the DC
protection because a DC voltage drop is detected (VdL< 0.5 pu for more than 70
ms). The rectifier now operates in inverter mode. The DC line voltage becomes
negative and the energy stored in the line is returned to the AC network, causing
rapid extinction of the fault current at its next zero-crossing.
Alpha is released at t = 0.82 s and the normal DC voltage and current recover in
approximately 0.4 s.
AC line-to-ground fault at the inverter
In the DC Fault block, change the multiplication factor of 1 in the Switching times
to 100, so that the DC fault is now disabled. In the A-G Fault block, change to 1
the 100 multiplication factor in the Switching times so that a 6 cycles line-toground fault is now applied at t = 0.7 s.
The Low AC voltage detection (LACVD) subsystem in the rectifier and inverter
protections and the Commutation Failure Prevention Control (CFPREV) in the
inverter protection are activated by default.
Restart the simulation.
Note that the 120 Hz oscillations in the DC voltage and currents which are
normally observed during single-phase fault with a detailed model do not exist in
the average model. Indeed, only positive-sequence fundamental components of

AC quantities are significant in the average model. The VDCOL would not operate
during the fault. The system recovers in approximately 0.2 s after fault clearing
(see the measured DC power Pd).
Abnormal inverter operation resulting from a commutation failure malfunction
(CF) due to AC faults are not correctly represented by the average model
equations. To assist the user in identifying such a condition an alarm signal
(CF_alarm) is set whenever the onset of a CF is predicted.
Look at the CF_alarm signal at the inverter, triggered at t = 0.73 s. Open the
CF_alarm block (inside the HVDC_CONV_AVG block of the inverter model) to
examine the logic.
Look at the A_min_I signal of the PROTECTION INVERTER scope. This signal
monitors the Commutation Failure Prevention (CFPREV) output of the Inverter
Protection block. The A_min signal is used to decrease the delay angle limit in
order to increase the commutation margin during and after the fault.
Finally, deactivate the CFPREV protection by deselecting the "ON State" in the
CFPREV dialog box. Restart the simulation and observe the difference in recovery
time of the DC transmission.

Anda mungkin juga menyukai