Version:
Issue Date:
Review By Date:
Owned By:
Authorised By:
1.0
November 2006
June 2008
Engineering Manager D & P
Executive Manager D & P
Date of Revision
Details of Amendment
1.0
November 2006
Initial Release
The above table lists in summary the amendments which have been made with most recent issues of this standard.
The table is updated with each re-issue. The latest amendments within the documents are marked with a change
indicator (|) in the outer margin.
CONTACT
This standard is the responsibility of the
Development and Projects Division, ElectraNet.
Please contact the indicated owner of the standard
with
any
inquiries.
ElectraNet
52-55 East Terrace, Adelaide, South Australia 5000
PO Box 7096, Hutt Street Post Office,
Adelaide,
South
Australia
5000
Ph (08) 8404 7966, Fx (08) 8404 7104
2006 ElectraNet Pty Limited trading as ElectraNet. No part of this document may be
reproduced or copied in any form or by any means (graphic, electronic, mechanical,
including photocopying, recording, taping or information retrieval systems) without the prior
written permission of ElectraNet.
LCM17
ElectraNet
TABLE OF CONTENTS
17.1SCOPE...........................................................................................................................................3
17.2STANDARDS................................................................................................................................3
17.3LENGTH, LOCATION AND ORIENTATION OF ANCHORS....................................................3
17.4DEFINITIONS...............................................................................................................................3
17.5EXPERIENCED CONTRACTORS...............................................................................................4
17.6CONTRACTORS METHOD STATEMENT.................................................................................4
17.7ANCHOR COMPONENTS...........................................................................................................5
17.7.1 ANCHOR BARS...........................................................................................................................5
17.7.2 FACE PLATES AND WASHERS.....................................................................................................5
17.7.3 NUTS..........................................................................................................................................5
17.7.4 CENTRALISERS...........................................................................................................................5
17.7.5 PROTECTIVE TREATMENT..........................................................................................................5
17.8ANCHOR DRILL HOLES.............................................................................................................5
17.9INSTALLATION OF ANCHORS..................................................................................................6
17.9.1 INSTALLATION............................................................................................................................6
17.10 GROUTING OF ANCHORS......................................................................................................6
17.10.1
GENERAL............................................................................................................................6
17.10.2
17.10.3
TESTING OF GROUT............................................................................................................7
17.10.4
GROUT MIXING..................................................................................................................7
17.10.5
17.11.2
17.11.3
17.11.4
17.1 SCOPE
Section specifies the requirements for the
supply, installation, testing, stressing and
grouting of anchors. The anchors are to be hot
dipped galvanised bars encased in full column
cement grout with sheathed free length, endthreaded with plates, washers and nuts.
Anchors shall be installed to the nominated
capacities at Type 1 gantry footings as shown
on the Drawings.
Version: 1.0
Page 2 of 8
ElectraNet
LCM17
17.2 STANDARDS
The
following Australian
Standards
are
AS 1214
Hot-Dipped
Coatings on Threaded Fasteners
Galvanised
AS 1275
Fasteners
AS 1302
Concrete
AS 4680
Hot-Dipped
Galvanised
Portland
and
Blended
Cements
Unless otherwise stated, the referenced
standard shall be the issue current at the date
on which the Contractor received the tender.
17.3
LENGT
H, LOCATION AND
ORIENTATION OF
ANCHORS
The approximate numbers, lengths and
locations of the anchors will be as shown on
the Drawings. Prior to the commencement of
drilling, the Contractor shall provide access to
allow the Superintendent to closely inspect the
footing to check the suitability of the footing
type. Depending on the outcome of the
inspection, the type of footing may be varied
by the Superintendent from those shown on
the Drawings. Presentation of the foundation
for inspection by the Superintendent prior to
drilling shall constitute a HOLD POINT.
DEFINIT
17.4
IONS
Version: 1.0
LCM17
ElectraNet
17.5 EXPERIENCED
CONTRACTORS
The work for installing anchors and grouting
shall be carried out by Contractors with
proven training and experience in this type
of
17.7.3
work. Contractors shall inspect the site and
assess it in reference to reports and the
drawings provided. The contract involves
placement of rock anchors as detailed in the
drawings.
Nuts
The nut and thread shall be capable of holding
a tension force of at least twice the Design
Working Load specified, or equal to the
ultimate capacity of the bar specified. Nuts
shall comply with the requirements of AS
1275.
Treatment
17.7
ANCHO
R COMPONENTS
17.7.1
Anchor Bars
Anchor bars shall be deformed steel
reinforcing bars. The bars shall be threaded at
one end and of the diameters shown in the
Drawings. Alternatively, anchor bars shall
have a 300 mm long factory bent cog. All bars
shall be hot dipped galvanised. Cogs shall be
bent prior to galvanising.
The bars for anchors shall have a minimum
ultimate capacity of 230 kN. Bars may be
joined using mechanical couplings of strength
equal to the bars.
17.7.2
Face
Washers
Plates
and
17.8
ANCHO
R DRILL HOLES
Holes for the anchors shall be drilled as at
the locations shown on the Drawings. The
depth and diameter shall be drilled to suit the
specified bolt length, proposed grouting
procedure
and
manufacturers
in
accordance
recommendations,
with
where
applicable.
Holes may be drilled by either pneumatic
hammer drills or rotary drill as approved by
the Superintendent. Holes shall be clean, true
to size and not deviate from the initial line of
the bore by more than 50 mm per each 1 m
depth of hole.
In ground likely to collapse, the sides of the
drill hole shall be supported by suitable lining
Page 4 of 8
ElectraNet
LCM17
Installation
Anchor bars shall be inserted into the hole
before injection of grout. The Contractor shall
demonstrate to the satisfaction of the
Superintendent that all the anchors are fully
encapsulated in a homogeneous grout mass
and that the bar is centrally located in the hole,
inserted to the correct depth.
Each cleaned drill hole shall be kept sealed
until the anchor bar is ready to be installed.
Anchor bars shall be assembled outside the
borehole. Grout injection tubes, if used, shall
be securely fixed to the bar. The anchor bar
shall then be installed into the hole.
Centralisers shall be used on all anchors.
Immediately prior to installing the anchor bar,
the hole shall be probed to confirm that it is
unobstructed for the full depth. Obstructions
shall be removed (or redrilled). Anchor length
shall not be reduced without the approval of
the Superintendent. HOLD POINT
17.9
INSTAL
LATION OF
ANCHORS
The anchor shall be installed and grouted
LCM17
ElectraNet
17.10.3
Testing of Grout
A characteristic grout strength of 32MPa at 7
days is required. Representative test cylinders
shall be prepared and cured in accordance with
AS 1012.8 and tested in accordance with AS
1012.9 at the rate of 2 cylinders per grout
batch. One of the cylinders from each batch
shall be tested after 7 days. Stressing of
anchors may commence if the 7 day strength is
greater than 32 MPa. If 32 MPa (after 7 days )
strength of both test cylinders is not achieved,
the anchors may be rejected at the discretion
of the Superintendent and replacements
installed at the Contractor's cost.
17.10.4
Grout Mixing
The grout shall be mixed in a mechanical
mixer capable of imparting a high shear to the
grout components so that a colloidal grout of
Version: 1.0
Grout
and Procedure
Equipment
Page 6 of 8
ElectraNet
LCM17
17.11
TESTIN
G AND STRESSING
OF ANCHORS
Anchors shall not be stressed or tested
Procedure
Install a test anchor using the same technique
as for the production anchors and as per
drawings.
Measure
residual
load
after
immediately lock-off by a lift-off test;
17.11.1
Proving
Acceptance Tests
and
LCM17
ElectraNet
immediately locking off shall be
determined;
17.11.3
Acceptance
Test Procedure
Install a test anchor using the same technique
as for the production anchors and as per
drawings.
Measure
residual
load
after
immediately lock-off by a lift-off test;
17.12
COMPL
ETION REPORT
The Contractor shall provide a report to the
Superintendent at the completion of the gantry
foundation works compiling as-built anchor
installation configurations, proving and
acceptance
load
test
methodologies,
procedures, equipment, certificates and results.
The format of the report shall be approved by
the Superintendent prior to submission.
17.11.4
Test
Limiting Values
When load is held at test load the following
limiting values apply:
Version: 1.0
Page 8 of 8