ABSTRACT
Commendable words of introduction one might say! but
how does one go about this planning exercise, being
creative and having lateral thinking, receive participation
from other operators within this industry to achieve a:
The Oil and Gas industry until now has been rather slow
and reluctant to respond to the idea that abandonment is
right around the corner. A question that has been so
prevalent in recent days, "WHY PLAN"?
ABANDONMENT
During the planning
process for abandonment
there are limited periods
of time that the process
can stop, but ultimately
the facility must be
abandoned and removed
to some degree.
Abandonment of
platforms does not
necessarily rely on
conventional methods
e.g. SSCV's
OTC 7478
1.
94
for
OTC 7478
2.
3.
4.
5.
6.
7.
CONVENTIONS 1972
These conventions introduced regulations primarily to
govern and protect the marine environment from
pollution. The London Convention prohibits global
dumping of oil and requires a special permit to be granted
for the dumping of scrap metal and bulky material, this
would include such things as platform topsides and
structures. This is perhaps less clear in the Oslo
Convention which covers specifically the North East
Atlantic and the North Sea. Although dumping of waste
from a platform is prohibited, it is not clear if the intent is
to cover the disposal of topsides and' structures by
dumping. The Oslo and London Conventions are
implemented in the UKCS under the Dumping at Sea Act
of 1974, prohibiting the permanent disposal of substances
and articles at sea, except in accordance with these
conventions.
UNCLOS 1981
95
OTC7478
What methods
deconstruction.
What methods
deconstruction.
are
are
available
for
available
for
topsides
jacket
OTC 7478
3.
2.
97
OTC 7478
EXECUTION PLAN
OPPORTUNITY TO DEVELOP
FOR DE-CONSTRUCTION
METHODOLOGY
Development of the Execution Plan is on the critical path
during the early stages of design activities drawing upon
the various areas of expertise such as design contractors,
fabricators, marine contractors and specialised trades etc.
Major limiting factors to be addressed are such things as
essential personnel, logistics, specialised trades, equipment
and even the weather. Considering that the deconstruction
site may be two or three hundred miles from shore in a
hostile offshore environment, making it critical that work
activities are clearly defined with resources, material and
work plan.
DECONSTRUCTION METHODS
Considering how great this opportunity really is, why have
so many failed to recognise it and enjoy the benefits.
There are many apparent reasons for this. The industry
takes it for granted that if we build under certain criteria,
then all we need to do is reverse the process. Contractual
issues around the sale of oil and gas are key drives for the
engineering design, procurement, construction and
installation, and in many ways precludes innovative and
effective engineering and true integration with design
engineers, construction and operational personal. Without
developing de-contructability programmes and assigning
of expertise at an early time in the project, the
opportunity is lost to develop the most cost effective,
environmentally acceptable and safe option for the final
disposition of an offshore production facility.
98
OTC 7478
These issues that have been outlined present the key to the
way forward, giving an opportunity to improve deconstruction programme and the true cost effectiveness of
the project. Highlighting the potential hurdles and
methods to be overcome them enables management and
engineers and contractors to seize the opportunity to
develop innovative and lateral thinking to develop the cost
effective, environmentally acceptable and safe solution for
deconstruction and disposal.
ESSENTIAL
ELEMENTS
PROJECT PLANNING
FOR
SUCCESSFUL
99
2.
3.
4.
5.
UNCLOS 1981
6.
7.
INTERNATIONAL MARITIME
ORGANISATION 1987
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
SUMMARY
In summary, the practise of simple procedures and
OTC 7478
ACKNOWLEDGEMENT
The author wish to thank Amoco (UK) Exploration
Company for their permission to publish this paper and
the co-operation received from Amoco Resource
Development Groups.
BmLIOGRAPHY
Source documents (4) 1986, (45) 1989, (48) 1990
Amoco, Abandonment Feasibility Study Vol. 1-5, 1993
ABBREVIATIONS
UK
UKCS
DTI
HSE
DoE
DoAF
UNCLOS
HLV
SSCV
LAT
SMFL
TCV
VLCC
MOB
DEMOB
LSA
CCTV
United Kingdom
United Kingdom Continental Shelf
Department of Trade and Industry
Health and Safety Executive
Department of the Environment
Department of Agriculture and Fisheries
United Nations Conference on the Law of
the Sea
Heavy Lift Vessel
Semi Submergible Crane Vessel
Lowest Astronomical Tide
Ship Mounted Fork Lift
Travelling Crane Vessel
Very Large Crude Carrier
MObilisation
De-mobilisation
Low Specific Activity
Closed Circuit Television
REFERENCES
1.
100