Rev
Date
Prepared By
Document No. : DOC-02-14-1005-BIL
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
TABLE OF CONTENTS
TABLE OF CONTENTS ........................................................................................................................................ 2
1.
INTRODUCTION ......................................................................................................................................... 3
2.
OBJECTIVES ................................................................................................................................................. 3
3.
REFERENCES ................................................................................................................................................ 3
4.
5.
6.
SUMMARY OF CALCULATIONS............................................................................................................ 8
6.1 BILGE PIPE SPESIFICATION ................................................................................................................... 8
6.2 BILGE PUMP SPECIFICATION ............................................................................................................... 8
ATTACHMENT 1 ................................................................................................................................................... 9
ATTACHMENT 2 ................................................................................................................................................. 10
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
1. INTRODUCTION
Bilge system is system that use to drain water in the void compartments when ship in
the flooding condition. Because of that bilge well shall put in every void space below
the sea level. The bilge pump can be couple with other pump such as ballast pump,
stand by sea water cooling pump and general service pump.
2. OBJECTIVES
1. To knowing the diameter of main and branch bilges pipes.
2. To calculating the capacity of Bilge Pump.
3. To determine the volume of bilge well.
4. To design the system on ship layout
3. REFERENCES
1.
GL Rules 2015
4. LIST OF ABBREVIATIONS
dH
l1
B
H
dZ
l
Q
:
:
:
:
:
:
:
5. DESIGN REQUIREMENTS
Design requirement for bilge system arrange in GL 2015 Part I Sec 11 Bilge Piping
System
Table 1. Design requirements for bilge system.
Keyword
Pipe
Thickness
Pipes laid
through
tanks
Reference
GL I Part
I- Chapter
2 Section
11 N.1.1.4
Design Requirement
The required of bilge lines is to be in
accordance with Table 11.5.
GL I Part
I- Chapter
2 Section
11 N.1.2.1
GL I Part
I- Chapter
2 Section
Remark
Keyword
Reference
11 N.1.2.2
Bilge
Suction
and
Strums
GL I Part
I- Chapter
2 11
Section
N.1.3.1
GL I Part
I- Chapter
2 Section
11 N.1.3.2
GL I Part
I- Chapter
2 Section
11 N.1.3.3
GL I Part
I- Chapter
1 Section
27. C.4.1
Bilge
Suction
and
Strums
Bilge Wells
GL I Part
I- Chapter
4 Section
6 H.1
Bilge
Valves
GL I Part
I- Chapter
2 Section
11 N.1.4.1
GL I Part
I- Chapter
2 Section
11 N.1.4.2
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
Design Requirement
bottom are to be fitted with nonreturn valve directly at the point of
entry into the tank.
Bilge suctions are to be so arranged as
not to impede the cleaning of bilges
and bilge wells. They are to be fitted
with easily detachable, corrosionresistance strums.
Emergency bilge suctions are to be
arranged such that they are accessible,
with free flow at a suitable distance
from the tank or the ship bottom
For the size and design of bilge wells
see GL Rules for Hull Structure (I-1-1)
Section 27 ,C.4.1
Remark
Keyword
Bilge
Valves
Pipe
Layout
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
Reference
GL I Part
I-Chapter
2 Section
11 N.1.5.1
Design Requirement
A screw-down non return valve or a
combination of a non-retrun valve
without positive means of closing and a
shut-off valve are recognized as reverse
flow protection.
GL I Part
I-Chapter
2 Section
11 N.1.6.1
GL I Part
I-Chapter
2 Section
11 N.1.6.2
GL I - Part
IChapter 2
Section 11
N.1.6.3
GL I - Part
IChapter 2
Section 11
N.1.6.4
GL I - Part
IChapter 2
Section 11
N.2.2.3
GL I - Part
IChapter 2
Section 11
N.2.2.b
GL I - Part
IChapter 2
Section 15
B.4.1.1
GL I - Part
A
c
c
e
s
s
o
r
i
e
s
a
n
d
Pipe
Diameter
Project
Remark
dH
3.0
(B
H)
dZ
2.15
(B H)
35 [mm ]
25 [mm]
Keyword
Reference
IChapter 2
Section 15
B.4.1.3
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
Design Requirement
tankers according to A.1.2.b) the
diameter of the main and branch bilge
lines are calculated as follows :
dH
1.68
(B
H)
(B
H)
(b
h)
T2
Remark
25
dZ
2.15
Capacity
of Bilge
Pump
Bilge Pump
Use other
pumps for
bilge
pumping
Machinery
Space
GL I - Part
IChapter 2
Section 11
N.2.4
GL I Part
I Chapter
2, Section
11 N. 3.1
GL I Part
I Chapter
2, Section
11 N.
3.4.1
GL I Part
I Chapter
2, Section
11 N.
3.4.2
GL I Part
I Chapter
2, Section
11 N.
3.4.3
GL I Part
I Chapter
2, Section
11 N.
3.4.4
GL I - Part
IChapter 2
(b
h)
25
Keyword
Bilge
Alarms
GL I-Part IChapter 2
Section 11
N.1.3.4
GL I Part
I- Chapter
4 Section
6 H.2
Support System
Material
Reference
Section 11
N.4.1.1
GL I Part
I- Chapter
4 Section
6 H.3
Pipe
Material
GL I Part
I Chapter
2, Section
11
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
Design Requirement
pumped as follows:
Remark
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
6. SUMMARY OF CALCULATIONS
6.1 BILGE PIPE SPESIFICATION
Pipe Line
Nominal
Size
4
3
Main Pipe
Branch Pipe
dO
[mm]
114.3
88.9
dH
[mm]
102.26
77.92
s
[mm]
6.02
5.49
Pipe
Class
III
III
Pump Name
General Service 1
General Service 2
Brand
Type
Sili Pump
Sili Pump
VSN-250-30
VSN-250-30
Q
[m3/h]
240
240
H
[m]
30
30
P
[kW]
30
30
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
ATTACHMENT 1
DETAIL CALCULATION
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
PREFACE
This document explain about the detail calculation of Bilge System. There are 3 main point
calculation in this documement such as bilge pipe diameter, pump spesification, and
volume of bigle well.
A. BILGE SYSTEM
Bilge system is system that use to drain water in the void compartement when ship
in the flooding condition. Because of that bilge well shall put in every void space
below the sea level. The bilge pump can be couple with other pump such as ballast
pump, stand by sea water cooling pump and general service pump.
3 .0
(B
H)
35
[mm]
where,
dH
1
= 15.8
H
= 3 .0
=
=
=
3 .0
(B
H)
35
(15 .8 8 .4 ) 13 .8 35
89.82 mm
3.54 inches
Then accroding to the Table 11.5 about pipe minimum diameter the thickness
group is M . Where in the group M the minimum diameter is 4.5 mm.
Spesification of pipe accroding to ANSI
1
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
Nominal Size
4 inches
Inside Diameter
4.02598 inches
102.26 mm
Outside Diameter
4.5 inches
114.3 mm
Schedule Number
40
Thickness
6.02 mm
0.23701 inches
= 2 . 15
(B
H)
25 (mm)
[mm]
where,
dZ
= 15.8
H
= 2 . 15
=
=
(B
H)
25
68.35 mm
2.69 inches
Then accroding to the Table 11.5 about pipe minimum diameter the thickness
group is M . Where in the group M the minimum diameter is 4.5 mm.
Spesification of pipe accroding to ANSI
Nominal Size
3 inches
Inside Diameter
3.06772 inches
77.92 mm
Outside Diameter
3.5 inches
88.9 mm
Schedule Number
40
Thickness
0.21614 inches
5.49 mm
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
= 5.75 10
dH 2
[m3/h]
where,
Q
dH
The result is
Q
-3
= 5.75 x 10 x 102.26
60.13
m3/h
0.017
m3/s
hs + hp + hv + hts + htd
Where
H
hs
hp
= head pressure[m]
hts
htd
= 7.95 m
Head Pressure
hp
Head Velocity
Head Velocity (Hv) is difference velocity of fluid between in suction line in
suction and discharge of pump. we can make assumption not difference
between suction and discharge about flow velocity.
3
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
Head Loss
Head losses are the sum of head major and minor on both of suction and
discharge.
Head Loses
= Hsuction
+ Hdischarge
= (DxV)/
where,
D
mm
Rn
= 2.03
m/s
= 0.0000849
cst pada 30 C
= 8.49E-11
m2/s
= 2450720510
(trubulent)
f x L x v / ( D x 2g )
2/
= 0.069 x90x 2.03 0.10226x2x9.81
12.79
Where,
= friction factor gets from the
moody diagram with e 0.05
0.069
90 m
Type
nxk
1 Butterfly Valve
0.86
0.86
2 elbow 90
0.3
0.30
4
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
3 Flange
0.87
4.35
4 Flexible coupling
0.08
0.32
5 SDNRV
1.23
1.23
6 SDNRV remotely
1.35
1.35
7 Strainer
1.5
3.00
8 T joint
4.00
0.17
0.17
15.58
9 Enlargement
hm =
K x V2 / 2g
3.29
= (DxV)/
where,
D
Rn
mm
m/s
= 0.0000849
= 8.49E-11
m2/s
= 2450720510
(trubulent)
f x L x v2 / ( D x 2g )
2/
= 0.069 x90x 2.03 0.10226x2x9.81
1.13
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
Where,
= friction factor gets from the
moody diagram with e 0.05
0.069
7.95 m
nxk
1 Butterfly Valve
0.86
0.86
2 elbow 90
0.3
0.00
3 Flange
0.87
0.00
4 Flexible coupling
0.08
0.00
5 SDNRV
1.23
2.46
6 SDNRV remotely
1.35
0.00
7 Strainer
1.5
0.00
8 T joint
2.00
5.32
hm =
K x V / 2g
1.12
hs + hp + hv + hts + htd
26.28
Sili Pump
Type
VSN-250-30
Capacity
Head
30 m
RPM
1500 rpm
50 Hz
Power
30 kW
240 m3/h
250 mm
Bore Dis
250 mm
Project
ME 141603
Doc.No
02-14-1005-BIL
Rev.No
*The bilge pump is couple with the ballast pump to comply with GL requirment.
( GL I Part I- Chapter 2 Section 11 N.3.5) .
3 BILGE WELL
Bilge wells shall have a capacity of more than 0,2 m3.
Dimension of Bilge Well :
Length
0.7
High
0.8
Width
0.5
Volume
0.28
*in the engine room the length of Bilge Well is 0.6 m (accroding to the frame spacing)
No
1
Item
General Service Pump
n
1
Power [kW]
Spec
Eff
Real
30
0.95
31.58
Total
31.58
31.58
Project
ME 141603
Doc. No
02-14-1005-BIL
Rev. No
ATTACHMENT 2
SPEC OF EQUIPMENT