GAMBAR SINGLE LINE SISTEM TENTENA

RAYON TENTENA AREA PALU


PLTD PENDOLO

LBS PANDAYORA

Catatan Kerusakan:
1 PMT Outgoing F.Pendolo (Ormazabal)
1 Unit Charger
PLTD TOMATA

CO
KOROBONO

S
35mm (18kms)

CO Barati

CO PAPE

GH TARIPA

PLTD TENDEADONGI
70mm (89,6kms)

KV 20

F.TOMATA (684 KW)


F.PENDOLO (662
KW)

70mm (22,8kms)

GI POSO
PLTM SAWIDAGO
S

MTU

MTU

CAT

LBS SAWIDAGO
EBONI

EBONI

LBS SANGIRA

F.TARIPA
)KW 1.298(

LBS JOMPO

CO SANGIRA

Catatan Kerusakan:
1 PMT Outgoing F.Luar Kota

CO KUKU
Sistem Poso

PLTM
SAWIDAGO 1
DT:380KW(
)DM:380KW

S
S

GH SULEWANA
MVA 5

MVA 12

Ren PLTM 2 X 5 MW
GH. TENTENA
35mm (11,4kms)

TENTENA

LUAR KOTA (1.203


KW)
70mm (32,5kms)

CO
Peura

70mm (71,5kms)
CO MAYAKELI

95mm (3,1kms)
GI PAMONA

F.POSO

F. TENTENA (1,550 KW /
51A)

F. KOTA
)KW 1.063(

LBS
DEPAN KANTOR

Catatan:
F. Kota : Penampang 95 mm = 3.115 kms
F. Luar Kota/Pamona Penampang 70 mm = 71.498 kms
F. Luar Kota/Pamona Penampang 35 mm = 11.375 kms
F. Taripa Penampang 70 mm = 32.528 kms
F. Pendolo Penampang 70 mm = 89.594 kms
F. Pendolo Penampang 35 mm = 18.00kms
F. Tomata Penampang 70 mm = 22.814 kms
F. Pendolo Penampang 35 mm = 71.343 kms
Total Beban Puncak = 5.163 KW

GH 5 MVA

GH 12 MVA

EKSPRESS
TENTENA

TRAFO 5 MVA
)MW 4.5

TRAFO 12 MVA
)MW 11(

PLTA SULEWANA

SISTEM POSO-TENTENA
POSO-TENTENA
SISTEM
(SETELAH +5MW)
(SEBELUM
+5MW)

Update 06 Januari 2014

CO SABENGA

CALL SIGN SISTEM TENTENA-POSO


RAYON TENTENA
GH TENTENA

: TENTENA 10

GI PAMONA

: GI PAMONA 10

PLTD TENDEADONGI

: TENDEA 10

PLTM SAWIDAGO

: SAWIDAGO 10

GH TARIPA

: TARIPA 10

GH TOMATA

: TOMATA 10

GH PENDOLO

: PENDOLO 10

RAYON POSO
GH POSO

: POSO 10

PLTD MOENGKO

: MOENGKO 10

GI POSO

: GI POSO 10

PLTM BAMBALO

: BAMBALO 10

Anda mungkin juga menyukai