Technology Office
May 2012
June-July
Conducted and assessed major events handled by the project such as project
briefing and pre-launching, together with the stakeholders and the partner
agencies.
Participated in the National Science and Technology Week.
Conducted Redmine orientation and briefing to Project Management Component
members.
Prepared Fiber Core Network Plan with identified loops and agencies to be
connected.
The Infrastructure team met with MRTC and LRTA for preliminary discussions. All
right-of-way (ROW) issues were approved in principle.
Fiber Core Network Plan: TelOf and ASTI conducted ocular inspection at MRT
North Avenue Station on July 13, 2012.
TelOf conducted MRT Station Inspection on July 17, 2012 and found that
underground stations like the one in Buendia need poles. The one in Taft Avenue,
on the other hand, is too crowded and have to be redesigned.
U/Sec. Louis Napoleon Casambre, together with the component members, met
with MMDAChairman Francis N. Tolentino on July 18, 2012.
A budget of Php 50 million was allocated for the two data centers: Manila (Php 30
M) and Cebu (Php 20).
Two suppliers, ATI and Prime Access, joined the initial site survey of the Manila
Data Center.
Consultations for IP Network were held with Ericsson on May 7 and Google on May
9.
August
Baseline infrastructure
diagram for the Fiber Optic Network was submitted on
August 10.
Drafted MOAs with LRT, MRTC, DND, MMDA and NAP.About 15 sites were identified
as network switches.
Two suppliers, ATI and Prime Access, came for the site survey for the Manila Data
Center.
TelOf Cebu was identified
as the Cebu Data Center. Cable route plan was
approved.
A schematic diagram for IPNetwork was developed in consultation with Google
and Ericsson.
Conducted bid opening for PKI
Identified potential Registration Authorities for PKI
Completed walk-through review for eBayad.
Conducted exploratory meeting with various payment gateways, such as Bastion
Payment Systems, YESpayments, AsiaPay and Dragonpay.
Conducted bid opening for GovMail.
Drafted MOA and TOR for NaRMISand for Forms Generator.
The Social Marketing conducted a lecture on Development of Systems Engineering
and Risk Analysis Tools for Managing Disaster Consequences on Interdependent
Infrastructure and Economic Systems.
The Policy Standards and Development team drafted policy for the systems and
applications.
Brownbag sessions held for project
staff on Redmine Training, Project
Management, Mindmap, Fibercore for Dummies and Prezi.
Training conducted on Managing ICT, Governance in the Public Sector to the iGov
Social Marketing Component.
KfrC finalized iGov Communications Plan and contents to be included on website.
It also revised the first printed brochure
September
PMO drafted the Quality Plan, Procurement Plan, Project Scope Plan
Drafted MOAs with TelOf VII - ICTO (transfer of funds for the development of Cebu
Data Center and deployment of fiber optic cables in Cebu government offices),
and with the National Archives of the Philippines.
Finalized the Fiber Network Plan. Prioritized Quezon City loop.
Fiber Infra team conducted LRT 1 Fiber Testing Debriefing on September 11.
Fiber Network Equipment team met Huawei on September 11 for the finalization
of TOR and discussion of fiber infra network map, hardware equipment,
maintenance and monitoring and fiber specs to be used.
The TOR for refurbishment and repair of Manila Data Center was submitted to the
Philippine International Trading Corporation (PITC).
The Notice of Award (NOA) for data center equipment was issued to bidder. Order
confirmation has been issued.
Submitted two propossals for eBayad and forms generator.
Identified
and reviewed potential
Registration Authorities
(RAs) for PKI.
Guidelines were released.
Identified DBM and DOSTas pilot agencies for NaRMIS.
October
Conducted Detail Implementation Planning on PKI, Govmail and iGovPhil Cloud on
October 27-29, 2012 in Subic.
Finalized MOAs with LRTAand ICTO, DND and DOsT and drafted the template MOA
for Node Agencies.
Purchase Confirmation for data center equipment was signed on October 3, 2012.
Notice to Proceed given to TIM-ssl on October 17, 2012.
Preliminary pre-procurement for fiber optic network conducted on October 24,
2012 at PITe.
Technical Evaluation Sheet for PKI was signed by AsTI on October 17, 2012.
Pre-procurement for Rack Mountable Firewall was held on October 24, 2012 at
PITe.
November
Presented ebayad's Enterprise Architecture to DBM, ICTO, NCC, BTr, COA and BsP
on November 27,2012.
Finalized TOR for NaRMls development.
OP-PCDsPOand AsTI met and agreed on standards for websites of NGAs, sUCs and
LGUs in three platforms: Wordpress, Drupal and Joomla!
A training, sponsored by IBM, on Installation and Configuration of Data Center
Servers was held on November 7-9.
A Brownbag session for technical staff, VI/VM Text Editor, was held on November
21.
A training for technical staff on Domain Name System was held on November 28.
December
Planned to put additional active fiber equipment between nodes at Congress, DA,
PAGASA, LRT Tayuman, LRT Central, LRT Gil Puyat, NEA, NICA. (ASTI and TelOf
computation exceeds 6db maximum loss allowance at these points).
Updated FOC TOR and map submitted to PITC on December 21. Eight-node server
and appliance firewall has been delivered at NCe.
Submitted a rebidding of PACU/ACU refurbishment for Manila Data Center.
Delivery and installation of equipment at TelOf Cebu was conducted on December
4-7,2012.
Presentation of the government website template for NGAs, SUCs, LGUs was
conducted on December 14, 2012. Attendees were from the ASTI, NCC, OPPCDSPO,CHED, DILG and DFA.
Installation
and configuration
and customization
of Red Hat Enterprise
Virtualization platform and Zimbra Collaboration Suite for GovMail were started
and still going on.
Met with Securemetric for PKI on December 12, 2012. (The schedule was moved
due to the late issuance of Notice to Proceed. TOR requirement in PKI: same
schedule of delivery of hardware and software.)
Brown Bag sessions on Linux for data center personnel were held on December 5,
12, and 19, 2012.
Cluster Meeting for Priority 2 and 3 agencies was held on December 12, 2012.
MOAs
Concluded MOAs with DOTC-MRT3-ICTO, TRC, and Template MOA for node
agencies. MOAs for
review: DND-DOST, LRTA-ICTO, MMDA-ICTO, NAP-ICTO, UPCEd-ICTO MOA, ICTO-NM-NAPTripartite MOA, and iSchools Mother MOA.
Prepared by:
~
HERNAN MELENCIO
Information Officer III
Knowledge and Communications
Noted by:
ANTON~RRES
progra1tra~~~;c