Anda di halaman 1dari 102

DAFTAR ANALISA BIAYA

ANALISA

JENIS PEKERJAAN

(1)

(2)

JBT

JBT

JBT

JBT

JBT

JBT

1 M2 PEMBERSIHAN LAPANGAN
0.0250 Hr Pekerja
0.0010 Hr Mandor
1 M' PENGUKURAN BOUWPLANK
0.0040 Hr Pekerja
0.0200 Hr Tukang
0.0200 Hr Mandor
0.0250 M3 Papan Sembarang
0.0010 Kg Paku
1 M3 GALIAN TANAH
0.7500 Hr Buruh tak terlatih
0.0250 Hr Mandor
1 M3 URUGAN TANAH
0.3750 Hr Buruh tak terlatih
0.0120 Hr Mandor
1 M3 TIMBUNAN TANAH BIASA
0.2500 Hr Pekerja
0.0120 Hr Mandor
1.2000 M3 Tanah Timbun
1 M2 URUGAN PASIR
0.2500 Hr Buruh tak terlatih

HARGA
SATUAN
(Rp.)
(3)

UPAH
(Rp.)
(4)

45,000.00
47,500.00
Jumlah

1,125.00
47.50
1,172.50

45,000.00
52,500.00
47,500.00
1,300,000.00
10,000.00
Jumlah

180.00
1,050.00
950.00
0.00

35,000.00
47,500.00
Jumlah

26,250.00
1,187.50
27,437.50

35,000.00
47,500.00
Jumlah

13,125.00
570.00
13,695.00

45,000.00
47,500.00
30,000.00
Jumlah

11,250.00
570.00
11,820.00

35,000.00

8,750.00

0.0120 Hr Mandor
1.2000 M3 Pasir Urug
JBT

JBT

JBT

JBT

1 M3 BETON TAK BERTULANG K.175


6.0000 Hr Pekerja
1.0000 Hr Tukang
0.1000 Hr Kepala Tukang
0.0300 Hr Mandor
6.8000 Zak Semen
0.5000 M3 Pasir
1.0000 M3 Kerikil
0.4000 M3 Papan Begisting
4.0000 Kg Paku
2.4096 Jam Concrete Mixer
1 M3 BETON
0.6000
0.1000
0.0300
0.0100
1.0000
110.0000
2.0000

BERTULANG K.175
Hr Pekerja
Hr Tukang
Hr Mandor
Hr Kepala Tukang
M3 Beton K.175
Kg Tulangan Baja
Kg Kawat Beton

1 M3 PASANGAN BATU BELAH


4.5000 Hr Pekerja
1.5000 Hr Tukang
0.2250 Hr Mandor
0.1500 Hr Kepala Tukang
1.2000 M3 Batu Kali
0.5200 M3 Pasir
3.2400 Kg Semen (PC)
1 M3 MEMASANG LANTAI JEMBATAN
0.0480 Hr Pekerja
0.1500 Hr Tukang
0.0020 Hr Mandor
0.0150 Hr Kepala Tukang
0.3990 M3 Kayu Kelas II
2.5900 Kg Paku

47,500.00
55,000.00
Jumlah

570.00
9,320.00

45,000.00
52,500.00
55,000.00
47,500.00
30,000.00
65,000.00
70,750.00
1,700,000.00
10,000.00
23,424.11
Jumlah

270,000.00
52,500.00
5,500.00
1,425.00
329,425.00

45,000.00
52,500.00
47,500.00
55,000.00
1,413,117.73
6,500.00
5,000.00
Jumlah

27,000.00
5,250.00
1,425.00
550.00
34,225.00

45,000.00
52,500.00
47,500.00
55,000.00
65,000.00
65,000.00
30,000.00
Jumlah

202,500.00
78,750.00
10,687.50
8,250.00
300,187.50

45,000.00
52,500.00
47,500.00
55,000.00
2,000,000.00
10,000.00
Jumlah

2,160.00
7,875.00
95.00
825.00
10,955.00

JBT

JBT

JBT

JBT

JBT

1 M2 LAPIS PENUTUP LANTAI


0.5250 Hr Pekerja
0.0260 Hr Mandor
0.0300 M3 Batu Pecah 2/3
0.0700 M3 Batu Pecah 5/7
4.0000 Kg Aspalt
0.0200 M3 Pasir
0.5000 Lbr Seng Plat BJLS. 20
1 M2 PEKERJAAN PLESTERAN
0.4000 Hr Pekerja
0.2000 Hr Tukang
0.0200 Hr Mandor
0.0200 Hr Kepala Tukang
0.0120 M3 Pasir
0.1630 Kg Semen (PC)
1 M2 PENGECETAN LOANNING
1.4000 Hr Pekerja
0.3500 Hr Mandor
0.3500 Kg Cat Tembok
1.0000 Set Alat Bantu
1 M2 PENGECETAN SANDARAN
1.4000 Hr Pekerja
0.3500 Hr Mandor
0.3500 Kg Cat Besi
1 M2 PEMBERSIHAN DAN PENGETERAN
0.1000 Hr Pekerja
0.0050 Hr Mandor
0.3500 Kg Teer

45,000.00
47,500.00
85,000.00
85,000.00
6,500.00
65,000.00
32,500.00
Jumlah

23,625.00
1,235.00
24,860.00

45,000.00
52,500.00
47,500.00
55,000.00
65,000.00
30,000.00
Jumlah

18,000.00
10,500.00
950.00
1,100.00
30,550.00

45,000.00
47,500.00
7,500.00
12,000.00
Jumlah

63,000.00
16,625.00
12,000.00
91,625.00

45,000.00
47,500.00
18,000.00
Jumlah

63,000.00
16,625.00
79,625.00

45,000.00
47,500.00
6,500.00
Jumlah

4,500.00
4,500.00

JUMLAH
UPAH+BAHAN
(Rp.)
(6)

BAHAN
(Rp.)
(5)

0.00

1,125.00
47.50
1,172.50

32,500.00
10.00
32,510.00

180.00
1,050.00
950.00
32,500.00
10.00
32,510.00

0.00

26,250.00
1,187.50
27,437.50

0.00

13,125.00
570.00
13,695.00

36,000.00
36,000.00

11,250.00
570.00
36,000.00
47,820.00

8,750.00

66,000.00
66,000.00

570.00
66,000.00
75,320.00

204,000.00
32,500.00
70,750.00
680,000.00
40,000.00
56,442.73
1,083,692.73

270,000.00
52,500.00
5,500.00
1,425.00
204,000.00
32,500.00
70,750.00
680,000.00
40,000.00
56,442.73
1,413,117.73

1,413,117.73
715,000.00
10,000.00
2,138,117.73

27,000.00
5,250.00
1,425.00
550.00
1,413,117.73
715,000.00
10,000.00
2,172,342.73

78,000.00
33,800.00
97,200.00
209,000.00

202,500.00
78,750.00
10,687.50
8,250.00
78,000.00
33,800.00
97,200.00
509,187.50

798,000.00
25,900.00
823,900.00

2,160.00
7,875.00
95.00
825.00
798,000.00
25,900.00
834,855.00

2,550.00
5,950.00
26,000.00
1,300.00
16,250.00
52,050.00
-

23,625.00
1,235.00
2,550.00
5,950.00
26,000.00
1,300.00
16,250.00
76,910.00

780.00
4,890.00
5,670.00

18,000.00
10,500.00
950.00
1,100.00
780.00
4,890.00
36,220.00

2,625.00
2,625.00

63,000.00
16,625.00
2,625.00
12,000.00
94,250.00

6,300.00
6,300.00

63,000.00
16,625.00
6,300.00
85,925.00

237.50
2,275.00
2,512.50

4,500.00
237.50
2,275.00
7,012.50

DAFTAR ANALISA BIAYA


PEKERJAAN
LOKASI
KABUPATEN
PROPINSI

:
:
:
:

KOMPONEN

ANALISA
(1)
A.

NORMALISASI SUNGAI
DESA LANCANG PASILO JUMERANG
PIDIE
NANGGROE ACEH DARUSSALAM

(2)

SATUAN
(3)

TENAGA
1 Pekerja
2 Mandor

Jam
Jam

Jumla
B.

PERALATAN
1 Excavator
2 Alat Bantu

Jam
Set

Jumla
C.

JUMLAH HARGA DAN PERALATAN (A + B)

OVERHEAD & PROPIT = 10 % x C

HARGA SATUAN PEKERJAAN ( C + D )

URAIAN ANALISA HARGA SATUAN


PEKERJAAN
LOKASI
KABUPATEN
PROPINSI

NO.

:
:
:
:

NORMALISASI SUNGAI
DESA LANCANG PASILO JUMERANG
PIDIE
NANGGRO ACEH DARUSSALAM

U RAIAN

KODE

NO.

U RAIAN

I.
1
2
3
4
5
II.
1
2
3

III.

KODE

ASUMSI
Menggunakan alat berat ( cara mekanik )
Lokasi pekerjaan :
Kondisi drainase : selesai dibersihkan
Jam kerja efektif
Luas penampang saluran

Ttk
L

URUTAN KERJA
Penggalian sungai dengan menggunakan
Alat Berat Excavator
Hasil galian ditimbun disamping sungai dan
membentuk tanggul
Sekelompok pekerja membersihkan daerah
galian dan merapikan hasil galian, sekaligus
membentuk tanggul saluran
PEMAKAIAN ALAT DAN TENAGA

ALAT
- Excavator
Kapasitas Bucket
Faktor Bucket
Faktor Efisiensi Alat
Waktu Siklus :
- Menggali dan menimbun
- Lain - lain
Kap. Produksi/Jam

C03
V
Fb
Fa
TS1
T1
T2
TS1
Q1

= V x Fb x fa x 60
TS1

Koef. Alat/Km

Galian Saluran
Q1

1 (2 + 1)/2 x 1

C03
Q1

ALAT BANTU
- Cangkul
- Sekop
2

TENAGA
Produksi Kebutuhan Tenaga

C10

Q1

- Pekerja
- Mandor
Koefisien Tenaga :
- Pekerja (P x Tk) : Q1
- Mandor (M x Tk) : Q1

URAIAN ANALISA HARGA SATUAN ALAT


JENIS ALAT
SATUAN
LOKASI
KABUPATEN
PROPINSI

:
:
:
:
:

BULDOZER 100 -150 HP


DESA LANCANG PASILO JUMERANG
PIDIE
NANGGRO ACEH DARUSSALAM

P
M
L01
L02

NO.

U RAIAN

A.
1
2
3
4

B.

KODE

URAIAN PERALATAN
Jenis Peralatan
Tenaga
Kapasitas
Alat Baru :
a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
Alat yang dipakai :
a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat ( * )

BULDOZER 100
Pw
Cp
A
W
B
A'
W'
B'

BIAYA PASTI PER JAM KERJA


1

Nilai sisa alat = 10 % x B

Faktor Angsuran Modal =

Biaya pasti per jam :


a. Biaya pengembalian modal =
b. Asuransi dan lain - lain =

C
1 x (1+1) ^ A'
(1+1) ^ A' - 1

( B' - C ) x D
W'
0,002 x B'
W'

Biaya pasti per jam = ( E + F )


C.

F
G

BIAYA PASTI PER JAM KERJA


1
2
3
4
5

Bahan Bakar = ( 0,175 Ltr/HP/Jam ) x Pw x Ms


Pelumas
= ( 0,01 Ltr/HP/Jam ) x Pw x Mp
Perawatan dan Perbaikan =
( 12,5 % ) x B
W'
Operator = ( 1 orang/Jam ) x U1
Pembantu Operator = ( 1 orang/Jam ) x U2

H
I
K
L
M

Biaya Operasi per Jam = ( H + 1 + K + L + M )

D.

TOTAL SEWA ALAT PER JAM = ( G + P )

E.

LAIN - LAIN
1
2
3
4
5
6

Tingkat suku bunga


Upah operator/sopir
Upah pembantu operator/pembantu sopir
Bahan Bakar bensin
Bahan bakar solar
Minyak Pelumas

URAIAN ANALISA HARGA SATUAN ALAT

i
U1
U2
Mb
Ms
Mp

PERKIRAAN
VOLUME
(4)

HARGA
SATUAN
(Rp.)
(5)

JUMLAH
HARGA
(Rp.)
(6)

0.625
6,428.57
0.077
6,785.71
Jumlah Harga Tenaga A

4,017.86
522.50
4,540.36

0.051
247,475.36
1.000
12,000.00
Jumlah Harga Tenaga B

12,621.24
12,000.00
24,621.24
29,161.60
2,916.16
32,077.76

KOEF.

SATUAN

KETERANGAN

KOEF.

SATUAN

7.00
1.50

KETERANGAN

Jam
M2

Ls
0.65
0.90
0.83
0.50
0.50
1.00
29.13

M3

Menit
Menit
M3/Jam
-

0.05

Jam

Ls

22.41

M3

2.00
0.25

Jam
Jam

0.625
0.077

Jam
Jam

KOEFISIEN

BULDOZER 100 - 150 HP


140.00

SATUAN

HP

5.00
1,600.00
512,500,000.00

Tahun
Jam
Rupiah

5.00
1,600.00
410,000,000.00

Tahun
Jam
Rupiah

41,000,000.00

Rupiah

0.65
0.90
0.83
0.50
0.50
1.00
29.13

0.05

M3

Rupiah
Rupiah
Rupiah

Rupiah
Rupiah
Rupiah
Rupiah
Rupiah

22.41

Rupiah

KETERANGAN

2.00
0.25

9,500.00
6,000.00
4,500.00
4,300.00
12,500.00

Rupiah

%/Tahun
Rp./Jam
Rp./Jam
Liter
Liter
Liter

LIST OF WAGES, BUILDING MATERIAL AND EQUIPM


PROJECT

WORK ITEM
CODE
NAME OF OWNER
LOCATION

:
:
:
:

NO.

REHABILITATION OF FISHPOND
KEMBANG TANJUNG SUB DISTRIC PIDIE DISTRIC NANGGROE ACEH DARR
REPLACEMENT OF SEMI PERMANENT BRIDGE WITH 6 METER SPAN

JEUMANANG, PASI LHOK, LANCANG VILLAGES

EXPLANATION

(1)

(2)

A.
1
2
3
4
5
6
7
8
9
10

NO.

WAGES UNIT PRICE


Non Skill Laborer
Laborer
Foremen
Skill Laborer
Chief Laborer
Heavy Duty Operator
Chain Saw Operator
Assistent Operator
Surveyor
Assistent Surveyor

(2)

B.
1
2
3
4
5
6
7
8

(3)

Man-hours
Man-hours
Man-hours
Man-hours
Man-hours
Man-hours
Man-hours
Man-hours
Man-hours
Man-hours

EXPLANATION

(1)

UNIT

UNIT
(3)

BUILDING MATERIAL UNIT PRICE


Common Timber
M3
1st Class Timber
M3
2nd Class Timber
M3
Log Timber dia. 15 Cm
Bh
Nail
Kg
Plywood Nail
Kg
Zincplate Nail
Kg
Porland Cement @ 50 Kg
Zak

WAGE/DAY

WAGE/HOURS

(Rp.)
(4)

(Rp.)
(5)

35,000.00
45,000.00
60,750.00
67,500.00
80,500.00
67,500.00
67,500.00
45,000.00
75,000.00
50,000.00

UNIT PRICE
(Rp.)
(4)

750,000.00
3,000,000.00
2,500,000.00
5,200.00
9,250.00
9,250.00
19,000.00
41,000.00

5,000.00
6,428.57
8,678.57
9,642.86
11,500.00
9,642.86
9,642.86
6,428.57
10,714.29
7,142.86

TRANSPORTA
TION
(Rp.)
(5)

9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44

NO.
(1)

Soil for Filler


Sand for Filler
Sand for Mortar
Sand for Concrete
Gravel
River Stone
Crushed Stone 2/3
Crushed Stone 5/7
Reinforced Concrete Steel
Reinforced Concrete Wire
IWF 300.150.6,5.9 Steel
IWF 150.75.5.7 Steel
IWF 250.125.6.9 Steel
IWF 125.60.6.8 Steel
L 75.75.7 Steel Profile
L 60.60.6 Steel Profile
Steel Aungkur
Bolt
Corrugated Zinc BJLS 20 K
Zinc Rige BJLS 35 K
Rubber Block
Cast Iron dia. 1,5"
PVC Pipe dia. 3/4"
PVC Pipe dia. 4"
Acrylic Painting
Oil Painting
Tinner for Painting
Filler for Painting
Base Painting
Sand Paper
Wood Painting
Teer
Zinc Plate
Gasoline
Solar
Grase

EXPLANATION
(2)

M3
M3
M3
M3
M3
M3
M3
M3
Kg
Kg
M'
M'
M'
M'
M'
M'
Unit
Unit
Unit
Unit
Unit
M1
M1
M1
Kg
Kg
Kg
Kg
Kg
Piece
Kg
Kg
M2
Litre
Litre
Litre

UNIT
(3)

30,000.00
55,000.00
79,500.00
79,500.00
70,750.00
65,000.00
65,000.00
65,000.00
8,000.00
10,000.00
480,000.00
188,000.00
340,000.00
130,000.00
88,000.00
64,000.00
7,200.00
3,500.00
45,000.00
30,000.00
23,000.00
15,000.00
12,000.00
30,000.00
7,500.00
23,000.00
5,200.00
4,500.00
18,000.00
2,750.00
15,000.00
6,500.00
32,500.00
4,500.00
4,300.00
12,500.00

PRICE

RENTAL
COST/HOURS

(Rp.)
(4)

(Rp.)
(5)

C.
1
2
3
4
5
6
7
8
9
10

EQUIPMENT RENTAL UNIT PRICE


Chain Saw
Unit
Concrete Mixer
Unit
Excavator 80 - 140 HP
Unit
Buldozer 100 - 150 HP
Unit
Dump Truck 3 - 4 M3
Unit
Dump Truck
Unit
Stamper
Unit
Jack Hammer
Unit
Generator Set
Unit
Supporting Equipment
Unit

4,510,000.00
9,840,000.00
410,000,000.00
512,500,000.00
110,700,000.00
123,000,000.00
6,150,000.00
5,330,000.00
41,000,000.00
12,000.00

25,995.80
23,424.11
247,475.36
354,640.56
109,978.54
131,678.96
11,008.29
16,306.18
151,168.79
12,000.00

STRIC NANGGROE ACEH DARRUSALAM


GE WITH 6 METER SPAN

NOTE
(6)

PRICE ON
LOCATION
(Rp.)
(6)

750,000.00
3,000,000.00
2,500,000.00
5,200.00
9,250.00
9,250.00
19,000.00
41,000.00

30,000.00
55,000.00
79,500.00
79,500.00
70,750.00
65,000.00
65,000.00
65,000.00
8,000.00
10,000.00
480,000.00
188,000.00
340,000.00
130,000.00
88,000.00
64,000.00
7,200.00
3,500.00
45,000.00
30,000.00
23,000.00
15,000.00
12,000.00
30,000.00
7,500.00
23,000.00
5,200.00
4,500.00
18,000.00
2,750.00
15,000.00
6,500.00
32,500.00
4,500.00
4,300.00
12,500.00

NOTE
(6)

DAFTAR HARGA SATUAN UPAH DAN BAHAN


NO.

URAIAN

SATUAN

(1)

(2)

(3)

A.
1
2
3
4
5
6
7
8
9
10

HARGA SATUAN UPAH


Buruh Tak Terlatih
Pekerja
Mandor
Tukang kayu
Kepala Tukang
Operator Alat Berat
Operator Chain Saw
Pembantu Operator
Juru Ukur
Pembantu Juru Ukur

OH
OH
OH
OH
OH
OH
OH
OH
OH
OH

UPAH/HARI
(Rp.)
(4)
35,000.00
45,000.00
47,500.00
52,500.00
55,000.00
66,500.00
55,500.00
42,000.00
65,000.00
45,000.00

NO.

URAIAN

SATUAN

HARGA SATUAN
(Rp.)

(1)

(2)

(3)

(4)

B.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32

HARGA SATUAN BAHAN


Kayu /Papan Sembarang
Kayu / Papan kelas II
Kayu / Papan kelas III
Kayu Bulat dia. 15 Cm
Paku Biasa
Paku Triplek
Paku Seng / Atap
Semen PC (40 Kg)
Tanah Timbun
Pasir Urug
Pasir Pasang
Pasir Beton
Kerikil
Batu Kali
Batu Belah 2/3
Batu Belah 5/7
Besi beton
Kawat beton
Besi IWF 300.150.6,5.9
Besi IWF 150.75.5.7
Besi IWF 250.125.6.9
Besi IWF 125.60.6.8
Besi L 75.75.7
Besi L 60.60.6
Angker/Sengkang
Angkur/Baut
Seng Gelombang BJLS 20 K
Rabung Seng BJLS 35 K
Karet Mati
Saluran Air Bersih Pipa dia. 1,5"
Saluran Air Kotor Pipa dia. 3/4"
Saluran Air Kotor Pipa dia. 4"

M3
M3
M3
Bh
Kg
Kg
Kg
Zak
M3
M3
M3
M3
M3
M3
M3
M3
Kg
Kg
M'
M'
M'
M'
M'
M'
Bh
Bh
Bh
Bh
Bh
M1
M1
M1

1,300,000.00
2,000,000.00
1,700,000.00
1,200.00
10,000.00
9,250.00
19,000.00
30,000.00
30,000.00
55,000.00
65,000.00
79,500.00
70,750.00
65,000.00
85,000.00
65,000.00
6,500.00
5,000.00
480,000.00
188,000.00
340,000.00
130,000.00
88,000.00
64,000.00
7,200.00
3,500.00
45,000.00
30,000.00
23,000.00
15,000.00
12,000.00
30,000.00

33
34
35
36
37
38
39
40
41
42
43
44

Cat tembok
Cat Minyak
Minyak Cat
Dempul
Cat Menie
Amplas
Cat Kayu
Teer
Seng Plat
Minyak Bensin
Minyak Solar
Minyak Pelumas

Kg
Kg
Kg
Kg
Kg
Lbr
Kg
Kg
M2
Ltr
Ltr
Ltr

7,500.00
23,000.00
5,200.00
4,500.00
18,000.00
2,750.00
15,000.00
6,500.00
32,500.00
4,500.00
4,300.00
12,500.00

NO.

URAIAN

SATUAN

HARGA SATUAN
(Rp.)

(1)

(2)

(3)

(4)

C.
1
2
3
4
5
6
7
8
9
10

HARGA SATUAN ALAT


Chain Saw
Concrete Mixer
Excavator 80 - 140 HP
Buldozer 100 - 150 HP
Dump Truck 3 - 4 M3
Dump Truck
Stamper
Jack Hammer
Generator Set
Alat Bantu

OH
OH
OH
OH
OH
OH
OH
OH
OH
OH

4,510,000.00
9,840,000.00
495,000,000.00
512,500,000.00
110,700,000.00
123,000,000.00
6,150,000.00
5,330,000.00
41,000,000.00
12,000.00

UPAH/JAM
(Rp.)
(5)

KETERANGAN
(6)

5,000.00
6,428.57
6,785.71
7,500.00
7,857.14
9,500.00
7,928.57
6,000.00
9,285.71
6,428.57

ONGKOS
ANGKUT
(Rp.)
(5)

JLH HARGA
DILOKASI
(Rp.)
(6)

1,300,000.00
2,000,000.00
1,700,000.00
1,200.00
10,000.00
9,250.00
19,000.00
30,000.00
30,000.00
55,000.00
65,000.00
79,500.00
70,750.00
65,000.00
85,000.00
65,000.00
6,500.00
5,000.00
480,000.00
188,000.00
340,000.00
130,000.00
88,000.00
64,000.00
7,200.00
3,500.00
45,000.00
30,000.00
23,000.00
15,000.00
12,000.00
30,000.00

7,500.00
23,000.00
5,200.00
4,500.00
18,000.00
2,750.00
15,000.00
6,500.00
32,500.00
4,500.00
4,300.00
12,500.00

ONGKOS
ANGKUT
(Rp.)
(5)

25,995.80
23,424.11
247,475.36
354,640.56
109,978.54
131,678.96
11,008.29
16,306.18
151,168.79
12,000.00

JLH HARGA
DILOKASI
(Rp.)
(6)

10,077.92

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
DEEP SOIL EXCAVATION
GALIAN TANAH DALAM

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR
EXPLANATION

ASUMTION
1 Soil excavation doing by man
power
2 Result of soil excavation
be moved from digging
3 Depth excavation be containing
water and having balance factor

URAIAN :

LABOUR
PEKERJA

Foreman
Non skill Laborer

1 Penggalian tanah dengan tenaga


manusia
Tanah galian disingkirkan dari
2
lobang tenaga
galian
3 Galian dalam terdapat air dan
adanya faktor kesesuaian

1
2
3
4
5

ANGGAPAN :

1
2
3
4
5

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
8.000

1.000
1.000

1.000
8.000

Using man power


Capacity of working group
Average of excavation up
For the stony the work wit
be multiplicated by 1,5 fac
For drying be suporting by

Penggunaan tenaga manu


Kapasitas kerja kelompok
Kedalaman rata - rata s/d
Untuk jenis berbatu harga
dikalikan dengan faktor 1
Untuk proses pengeringan

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
35,000.00

UNIT

MATERIAL
BAHAN

SUM
JUMLAH

UNIT
SATUAN

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

VOLUME E

2.000

SATUAN

M3

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

(Rp.)
HARGA
SATUAN
(Rp.)

HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
SOIL FILLER FOR OPRIT
TIMBUNAN TANAH/OPRIT

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG

KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

LABOUR
PEKERJA

Foreman
Non skill Laborer
Operator

MATERIAL
BAHAN

Soil Filler

EQUIPMENT
PERALATAN

1 For the pilling of building


material must be clean
from the organic matter
2 Construction of filling doing
layer by layer

ASUMTION

1
2

Material cost be calculated


Compaction coefisien 1,30

ANGGAPAN :

1
2

Harga bahan sampai di lo


Koefisien pemadatan 1,30

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
35,000.00
66,500.00

1 Tempat penimbunan bahan


untuk konstruksi bersih dari
bahan organik
2 Pekerjaan ditempatkan untuk
timbunan pada konstruksi lapis
demi lapis.

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
4.000
1.000

1.000
1.000
1.000

1.000
4.000
1.000

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)

SUM
JUMLAH

UNIT
SATUAN

26.000

M3

30,000.000

TOTAL
EQUIPMENT
JUMLAH

WORK
DAYS
HARI

WORK
HOURS
JAM

UNIT PRICE
(Rp.)
HARGA

Roller Stell Whell

VOLUME E

ALAT

KERJA

KERJA

1.000

3.000

1.000

SATUAN

M3

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

SATUAN
(Rp.)
55,500.00

HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
SOIL RE-FILL
URUGAN TANAH KEMBALI

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Soil from excavation be filled


to the digging location
2 The organic disposal from
digging be throwing
1 Tanah bekas galian diurug kembali
ke bekas galian
2 Membuang sampah - sampah dari
bekas galian

ASUMTION

Tanah urugan diratakan da


cara menumbuk.

ANGGAPAN :

Soil filler be flated and be


hand compaction

LABOUR
PEKERJA

Foreman
Non skill Laborer
Operator

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

0.012
0.375

1.000
1.000

0.012
0.375

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
35,000.00

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)

MATERIAL
BAHAN

SUM
JUMLAH

UNIT
SATUAN

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

Water Pump

VOLUME E

1.000

SATUAN
D/E

0.00

M3
HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
LOG TIMBER 15 s/d 20 Cm FOR PILLIN
PENGADAAN TIANG PANCANG 15 s/d 20 C

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Material on out of job site


2 Transportation the material by man
power to the job site
Material be pilled on the pic up
3
location
The distance of pick up location
3
max
5 km
1 Bahan/material berada

ASUMTION

1
2

Cost of material franco on


Length of timber 7 M be l

ANGGAPAN :

1
2

Harga bahan sesuai denga


Panjang kayu kurang lebi
4 orang

diluar

lokasi pekerjaan
diangkut oleh tenaga
manusia ketempat pekerjaan
Bahan ditumpuk ditempat
3
pengambilan
Jarak pengambilan maksimum 5
4
Km
2 Bahan

TOTAL

TOTAL

BILLING

LABOUR
PEKERJA

Foreman
Chief Laborer
Skill Laborer
Non skill Laborer

MATERIAL
BAHAN

Timber

EQUIPMENT
PERALATAN

VOLUME E

PERSONEL
JUMLAH
ORANG

DAYS
HARI

MAN/DAYS
JUMLAH
HARI/ORANG

0.010
0.030
0.250
0.100

1.000
1.000
1.000
1.000

0.010
0.030
0.250
0.100

RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
35,000.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)

SUM
JUMLAH

UNIT
SATUAN

0.220

M3

1,300,000.000

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

7.000

SATUAN

M'

D/E

HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
LOG TIMBER 15 s/d 20 Cm PILLING
PEMANCANGAN TIANG PANCANG KAYU
CEROCOK dia. 15 S/D 20 CM

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Material and equipment stand


by on job site by supplyer
2 Material be located near job
site
1 Bahan/Alat siap dilapangan oleh
supplier
2 Bahan diletakkan kedudukannya
dekat dengan lokasi pekerja

ASUMTION

1
2
3
4

ANGGAPAN :

1
2
3
4

LABOUR
PEKERJA

Foreman
Chief Laborer
Skill Laborer
Non skill Laborer

MATERIAL
BAHAN

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

0.050
0.030
1.800
0.350

1.000
1.000
1.000
1.000

0.050
0.030
1.800
0.350

SUM
JUMLAH

UNIT
SATUAN

Weight of hammer minimu


Pilling be stoped after 10 k
masuk = 1 cm
Foundation using the timb
Pile set up be diging befor

Berat penumbuk minimal


Penghentian pemancanga
masuk = 1 cm
Pondasi digunakan peman
Letak pancang dilubangi l

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
35,000.00
UNIT
(Rp.)
HARGA

SATUAN
(Rp.)
-

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

1.000

0.140

1.000

SATUAN

M'

Hammer

VOLUME E

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

HARGA SATUAN

11,415.00

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
SAND FILLER UNDER THE FOUNDATIO
URUGAN PASIR PADA BAWAH PONDASI

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

LABOUR
PEKERJA

Foreman
Skill Laborer
Operator

MATERIAL
BAHAN

Sand Filler

EQUIPMENT
PERALATAN

1 Filling be compacted
each 20 cm per layer

ASUMTION

1
2

Material cost be calculated


Capacity of working group

1 Timbunan harus dipadatkan


setiap lapisan setebal 20 cm

ANGGAPAN :

1
2

Harga bahan sampai dilok


Kapasitas kerja kelompok
pemadatan 1 : 2

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
52,500.00
0.00

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

0.012
0.375
-

1.000
1.000
-

0.012
0.375
-

SUM
JUMLAH

UNIT
SATUAN

1.200

M3

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
55,000.00

WORK
HOURS
JAM
KERJA

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

VOLUME E

1.000

SATUAN
D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

M3
HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
RIVER STONE PAIRING CONTRUCTION
KONSTRUKSI PASANGAN BATU

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Material and equipment stand


by on job site by supplyer
2 Stone crushed be install with
PC and Sand mortar
1 Material disiapkan di lokasi oleh
supplier
2 Batu belah dipasang dengan ikatan
spesi semen PC + Pasir

ASUMTION

2
3
4
ANGGAPAN :

2
3

Using culvert, bridge and


ather structure with stone
wit water proofing mortar
Material be delivered on j
Not included the excavatio
Mortar 1 : 3

Digunakan pada gorong penahan dan struktur-stru


menggunakan pasangan b
Material dikirim sampai l
tidak termasuk pekerjaan

LABOUR
PEKERJA

Foreman
Skill Laborer
Non Skill Laborer

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

0.010
4.000
12.000

1.000
1.000
1.000

0.010
4.000
12.000

MATERIAL
BAHAN

SUM
JUMLAH

UNIT
SATUAN

Batu belah 10-15 cm


Pasir
Semen (40 Kg)

5.000
1.250
15.000

M3
M3
zak

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

5.000

SATUAN

M3

VOLUME E

D/E

HARGA SATUAN

Adukan spesi 1 : 3

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
52,500.00
35,000.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
65,000.000
65,000.000
30,000.000

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
-

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
PLESTERING
PLESTERAN

FRENCH RED CROSS

PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Material and equipment stand


by on job site by supplyer
2 Material be located near job
site
1 Bahan/Alat siap dilapangan oleh
supplier
2 Bahan diletakkan kedudukannya
dengan pekerja

ASUMTION

1
2
3
4

ANGGAPAN :

1
2
3
4

LABOUR
PEKERJA

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

Weight of hammer minimu


Pilling be stoped after 10 k
masuk = 1 cm
Foundation using the timb
Pile set up be diging befor

Berat penumbuk minimal


Penghentian pemancanga
masuk = 1 cm
Pondasi digunakan peman
Letak pancang dilubangi l

BILLING
RATE
(Rp./Days/Man)
UPAH

Foreman
Chief Laborer
Skill Laborer
Non skill Laborer

MATERIAL
BAHAN

1.000
1.000
6.000
12.000

1.000
1.000
1.000
1.000

1.000
1.000
6.000
12.000

SUM
JUMLAH

UNIT
SATUAN

0.780
7.900

M3
zak

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

VOLUME E

50.000

SATUAN

M2

Concrete Sand
PC @40 Kg

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

HARGA SATUAN

(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
35,000.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
65,000.000
30,000.000

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE FORM WORK

FRENCH RED CROSS


PALANG MERAH PERANCIS

PEKERJAAN CETAKAN UNTUK BETON

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

1 The equipment be installed on


concrete or stone pairing
with the slope to below or
ather
To be installed palm fibre round
2
the PVC pipe
dalam peralon.

ASUMTION

3
4
ANGGAPAN :

URAIAN :

LABOUR
PEKERJA

Foreman
Non Skill Laborer
Operator

MATERIAL
BAHAN

Paralon 2 "
Ijuk

1 Memasang peralatan pada


pasangan batu/beton pada talud
dengan miring ke bawah bagian
lainnya
2 Memasang ijuk disekeliling bagian
dalam peralon.

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
4.000
-

1.000
1.000
-

1.000
4.000
-

UNIT
SATUAN

40.000
20.000

M'
Kg

1
2
3
4

TOTAL
PERSONEL
JUMLAH
ORANG

SUM
JUMLAH

1
2

Material cost be calculated


Cutting of PVC pipe dia. 2
wall thickess.
Palm fibre be install on th
PVC be calculated @ 40 m

Harga bahan dihitung dite


Setiap potongan peralon 2
tebal dinding.
Ijuk dipasang diujung sek
Hitungan peralon per 40 m

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
35,000.00
0.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
15,000.00
4,000.00

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

VOLUME E

40.000

SATUAN

M'

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CANAL REPLECEMENT BY HEAVY DUTY
MEMBUAT SALURAN
(MENGGUNAKAN ALAT BERAT)

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE NANGGROE ACEH DARUSSALAM PR
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

1 Canal excavation doing by


Excavation
2 Soil from canal excavation be

ASUMTION

1
2

Using the excavator (140


Tree and any planting be c
following the dykes be co

throwing on side of canal


3 Man power be throwing the
roots and ather disposal
URAIAN :

LABOUR
PEKERJA

Foreman
Skill Operator
Operator Ass.
Non Skill Laborer

1
2

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
66,500.00
42,000.00
35,000.00

Menggali saluran dengan


Exavator.
excavator
2 Tanah galian diangkat ke
samping saluran yang digali.
3 Tenaga manusia membuang akarakar kayu dan sampah-sampah
lainnya.
1

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000
1.000
5.000

1.000
1.000
1.000
1.000

1.000
1.000
1.000
5.000

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)

MATERIAL
BAHAN

SUM
JUMLAH

UNIT
SATUAN

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

1.000

1.000

5.000

Exavator 140 HP

Menggunakan alat berat e


Pohon-pohon dan semak b
pada waktu pembentukan

ANGGAPAN :

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
247,475.36

VOLUME E

140.000

SATUAN
D/E

M3
HARGA SATUAN

(Rp.)

Hal. 1
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
DEEP SOIL EXCAVATION
GALIAN TANAH DALAM

CODE
KODE
K.224 A

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Using man power


Capacity of working group 100/ day
Average of excavation up to 3 m
For the stony the work with code K.224
be multiplicated by 1,5 factor
For drying be suporting by pump

Penggunaan tenaga manusia


Kapasitas kerja kelompok 100/ hari
Kedalaman rata - rata s/d 3 m
Untuk jenis berbatu harga satuan pekerjaan K.224
dikalikan dengan faktor 1,5
Untuk proses pengeringan perlu dibantu pompa

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
280,000.00

COST

327,500.00
SUB TOTAL

(Rp.)
BIAYA
(Rp.)

B (Rp.)
SUB JUMLAH
B (Rp.)

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

327,500.00

40,937.50

Per M3

Hal. 2
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
SOIL FILLER FOR OPRIT
TIMBUNAN TANAH/OPRIT

CODE
KODE
K.225

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG

UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


Compaction coefisien 1,30

Harga bahan sampai di lokasi pekerjaan


Koefisien pemadatan 1,30

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
140,000.00
66,500.00
COST
(Rp.)
BIAYA
(Rp.)

254,000.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

780,000.00
780,000.00
COST
(Rp.)
BIAYA

SUB TOTAL
C (Rp.)
SUB JUMLAH

(Rp.)

C (Rp.)

166,500.00
166,500.00
JUMLAH (Rp.)

1,200,500.00

150,062.50

Per M3

Hal. 3
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
SOIL RE-FILL
URUGAN TANAH KEMBALI

CODE
KODE
1/2 A.1

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Tanah urugan diratakan dan dipadatkan dengan


cara menumbuk.
Soil filler be flated and be compacted by
hand compaction

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

570.00
13,125.00
13,695.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

COST
(Rp.)
BIAYA
(Rp.)

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

1,711.88

13,695.00

Per M3

Hal. 4
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
LOG TIMBER 15 s/d 20 Cm FOR PILLING
PENGADAAN TIANG PANCANG 15 s/d 20 Cm

CODE
KODE
K.900

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Cost of material franco on pick up location


Length of timber 7 M be lifted by 4 man

Harga bahan sesuai dengan tempat pengambilan


Panjang kayu kurang lebih 7 M diangkut oleh
4 orang

COST

SUB TOTAL

(Rp.)
BIAYA
(Rp.)

A (Rp.)
SUB JUMLAH
A (Rp.)

475.00
1,650.00
13,125.00
3,500.00
COST
(Rp.)
BIAYA
(Rp.)

18,750.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

286,000.00

286,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

304,750.00

43,535.71

Per M'

Hal. 5

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
LOG TIMBER 15 s/d 20 Cm PILLING
PEMANCANGAN TIANG PANCANG KAYU
CEROCOK dia. 15 S/D 20 CM

CODE
KODE
K.901

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Weight of hammer minimum 0.75 - 1 Ton


Pilling be stoped after 10 kali ditumbuk
masuk = 1 cm
Foundation using the timber piling and pillar
Pile set up be diging before

Berat penumbuk minimal 0.75 - 1 Ton


Penghentian pemancangan setelah 10 kali ditumbuk
masuk = 1 cm
Pondasi digunakan pemancang kayu dan pilar
Letak pancang dilubangi lebih dahulu.

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

2,375.00
1,650.00
94,500.00
12,250.00
COST
(Rp.)
BIAYA

110,775.00
SUB TOTAL
B (Rp.)
SUB JUMLAH

(Rp.)

B (Rp.)

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

1,598.10
1,598.10
JUMLAH (Rp.)

112,373.10

112,373.10

Per M'

Hal. 6
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
SAND FILLER UNDER THE FOUNDATION
URUGAN PASIR PADA BAWAH PONDASI

CODE
KODE
A. 18

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


Capacity of working group 100/ day
Harga bahan sampai dilokasi pekerjaan
Kapasitas kerja kelompok 100/ hariKoefisien
pemadatan 1 : 2

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

570.00
19,687.50

COST
(Rp.)
BIAYA
(Rp.)

20,257.50
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

66,000.00
66,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

86,257.50

10,782.19

Per M3

Hal. 7
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
RIVER STONE PAIRING CONTRUCTION
KONSTRUKSI PASANGAN BATU

CODE
KODE
K.810

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Using culvert, bridge and shear wall and


ather structure with stone pairing
wit water proofing mortar
Material be delivered on job site
Not included the excavation and filling
Mortar 1 : 3
Digunakan pada gorong - gorong, jembatan, tembok
penahan dan struktur-struktur yang lain yang
menggunakan pasangan batu kedap air
Material dikirim sampai lokasi
tidak termasuk pekerjaan galian/timbunan

Adukan spesi 1 : 3

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

475.00
210,000.00
420,000.00
COST
(Rp.)
BIAYA
(Rp.)
325,000.00
81,250.00
450,000.00

COST
(Rp.)
BIAYA
(Rp.)

630,475.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)
856,250.00
SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

297,345.00

1,486,725.00

Per M3

Hal. 8
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
PLESTERING
PLESTERAN

CODE
KODE
K.811

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Weight of hammer minimum 0.75 - 1 Ton


Pilling be stoped after 10 kali ditumbuk
masuk = 1 cm
Foundation using the timber piling and pillar
Pile set up be diging before
Berat penumbuk minimal 0.75 - 1 Ton
Penghentian pemancangan setelah 10 kali ditumbuk
masuk = 1 cm
Pondasi digunakan pemancang kayu dan pilar
Letak pancang dilubangi lebih dahulu.

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
55,000.00
315,000.00
420,000.00
COST
(Rp.)
BIAYA
(Rp.)

837,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)
-

50,700.00
237,000.00

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

837,500.00

16,750.00

Per M2

Hal. 9
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE FORM WORK

CODE
KODE

PEKERJAAN CETAKAN UNTUK BETON

K. 890

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


Cutting of PVC pipe dia. 2 " depend on wall thickess
wall thickess.
Palm fibre be install on the end of PVC
PVC be calculated @ 40 m'
Harga bahan dihitung ditempat pekerjaan
Setiap potongan peralon 2 " panjang tergantung lebar/
tebal dinding.
Ijuk dipasang diujung sekeliling peralon bagian dalam.
Hitungan peralon per 40 m'

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
140,000.00

COST
(Rp.)
BIAYA
(Rp.)
600,000.00
80,000.00

187,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

680,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

867,500.00

21,687.50

Per M3

Hal. 9a
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CANAL REPLECEMENT BY HEAVY DUTY EQ.
MEMBUAT SALURAN
(MENGGUNAKAN ALAT BERAT)

CODE
KODE
K. 110 A

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


T PIDIE NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Using the excavator (140 M3/hari)


Tree and any planting be clean up
following the dykes be construction.

Menggunakan alat berat exavator (140 M3/hari)


Pohon-pohon dan semak belukar sudah dibersihkan
pada waktu pembentukan tanggul samping.

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
66,500.00
42,000.00
175,000.00
COST
(Rp.)
BIAYA
(Rp.)

331,000.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

0.00
COST
(Rp.)
BIAYA
(Rp.)

1,237,376.80

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

1,237,376.80
JUMLAH (Rp.)

11,202.69

1,568,376.80

Per M3

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE FORM WORK
PEKERJAAN CETAKAN UNTUK BETON

FRENCH RED CROSS


PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR
EXPLANATION
URAIAN :

ASUMTION
ANGGAPAN :
1 Menyiapkan bahan memotong, pada
mengergaji, memaku dan

1 1/3 dari bahan masih dapat digu


cetakan lain.

2 Kapasitas produksi = 2 M3 / ha

memasang
2 Membongkar cetakan setelah
beton mengeras.

10 Formwork
10 Cetakan dibongkar oleh pekerja
atau ijin Direksi.

LABOUR
PEKERJA

Foreman
Chief Laborer

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000

1.000
1.000

1.000
1.000

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00

Skill Laborer
Non Skill Laborer

MATERIAL
BAHAN

6.000
4.000

1.000
1.000

6.000
4.000

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
1,300,000.00
10,000.00

SUM
JUMLAH

UNIT
SATUAN

0.800
8.000

M3
Kg

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

VOLUME E

2.000

SATUAN

M3

Kayu Begisting
Paku

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

52,500.00
35,000.00

HARGA SATUAN

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CLEANING AND COATING
PEMBERSIHAN DAN CAT TEMBOK

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION
URAIAN :

ASUMTION
ANGGAPAN :
1 Membersihkan tempat yang akan
dicat.

2
3

2 Cat dituang kedalam baskom


dan dicatkan dengan roll kuas.

LABOUR
PEKERJA

Foreman
Skill Laborer
Operator

MATERIAL
BAHAN

Cat Tembok

EQUIPMENT
PERALATAN

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000
-

1.000
1.000
-

0.010
0.200
-

Bahan dihitung ditempat p


1 kg can be covered on 6 m
1 kg dapat menghasilkan 6
Calculated per 1 m2
Hitungan per 1 m2

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
52,500.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)

SUM
JUMLAH

UNIT
SATUAN

0.300

Kg

7,500.000

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

UNIT PRICE
(Rp.)
HARGA
SATUAN

(Rp.)

VOLUME E

1.000

SATUAN
D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

M2
HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE REINFORCEMENT
PENULANGAN BETON

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Bahan disediakan oleh Supplier


2 Besi dipotong dibentuk dan diikat.

ASUMTION

1 200 Kg besi dapat disiapk


2 Cost of material besed on
2 Harga material berdasark
Pemakaian bahan tulanga
3 membengkok dan penyam

ANGGAPAN :

1 200 Kg besi dapat disiapk


2 Cost of material besed on
2 Harga material berdasark

1 Bahan disediakan oleh Supplier


2 Besi dipotong dibentuk dan diikat.

Pemakaian bahan tulanga


3 membengkok dan penyam

LABOUR
PEKERJA

Foreman
Laborer
Skill Laborer
Non skill Laborer

MATERIAL
BAHAN

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000
2.000
2.000

1.000
1.000
1.000
1.000

1.000
1.000
2.000
2.000

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
6,500.00
5,000.00

SUM
JUMLAH

UNIT
SATUAN

220.000
2.000

Kg
Kg

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

VOLUME E

2.000

SATUAN

M3

Besi Beton
Kawat Ikat

D/E

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
52,500.00
45,000.00
35,000.00

HARGA SATUAN

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

(Rp.)

FRENCH RED CROSS


PALANG MERAH PERANCIS

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE K. 175
B E T O N K. 175

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Material and equipment stand


by on job site by supplyer
2 Before using the agregat must be
cleaning
3 Concrete be mixed by mechanical
mixer and near the job site.

ASUMTION

1
2
3
4
5

Material cost be calculated


Productivity of concrete m
Mix design 1 : 2 : 3.
Length of mixing is 9 min
The weight of 1 M3 concr
1 Pocket PC 40 Kg.

ANGGAPAN :

1
2
3
4
5

Harga/material dihitung d
Kapasitas produksi aduka
Campuran 1 : 2 : 3.
Lamanya setiap kali peng
1 M3 beton beratnya 2.40
40 Kg

1 Bahan/material disediakan oleh


Supplier.
2 Sebelum digunakan agregat harus
dibersihkan dahulu
3 Beton diaduk dengan pengaduk
mekanis didekat lokasi
pengecoran.

TOTAL

TOTAL

BILLING

LABOUR
PEKERJA

Foreman
Chief Laborer
Skill Laborer
Non skill Laborer
Operator Non skill

MATERIAL
BAHAN

Batu Kerikil
Semen PC
Pasir Beton

EQUIPMENT
PERALATAN

Concrete Mixer

VOLUME E

PERSONEL
JUMLAH
ORANG

DAYS
HARI

MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000
1.000
8.000
1.000

1.000
1.000
1.000
1.000
1.000

1.000
1.000
1.000
8.000
1.000

SUM
JUMLAH

UNIT
SATUAN

1.650
16.480
1.080

M3
Zak
M3

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

1.000

8.000

2.000

SATUAN

M3

D/E

HARGA SATUAN

RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
35,000.00
35,000.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
70,750.000
30,000.000
79,500.000

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
23,424.11

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
REINFORCEMENT CONCRETE
BETON BERTULANG LANDASAN PLAT INJA
DAN GLAGAR

FRENCH RED CROSS

PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

LABOUR
PEKERJA

Pek. Beton
Pek. Besi
Pek. Cetakan
Operator

MATERIAL
BAHAN

1 Reinforcement steel and concrete


workform be ready in jab site
2 Concrete be mixing by mechanic
mixer and near the concrete
location

ASUMTION

1
2
3

Concrete mixing 1 : 2 : 3
Capacity are 2 M3/days
Material cost be calculated

ANGGAPAN :

1
2
3

Campuran beton 1 : 2 : 3
Kapasitas 2 M3/hari
Haraga bahan dilokasi pek

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
470,000.00
260,000.00
557,500.00
42,000.00

1 Bahan besi dan cetakan telah siap


ditempat.
2 Beton diaduk dengan mesin
pengaduk mekanis didekat lokasi
pengecoran.

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.400
0.400
1.000

1.000
1.000
1.000
1.000

1.000
1.400
0.400
1.000

SUM
JUMLAH

UNIT
SATUAN

UNIT
(Rp.)
HARGA

Beton
Besi
Cetakan

EQUIPMENT
PERALATAN

Concrete Mixer

VOLUME E

SATUAN
(Rp.)
696,997.50
1,440,000.00
1,120,000.00

1.000
1.400
0.400

(1)
(1)
(1)

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

1.000

8.000

2.000

SATUAN

M3

D/E

FRENCH RED CROSS

PALANG MERAH PERANCIS

HARGA SATUAN

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
23,424.11

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TIMBER BEAM AND BRANCH
MEMASANG GELAGAR/SEKUR

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

LABOUR
PEKERJA

Foreman
Chief Laborer
Skill Laborer
Laborer

MATERIAL
BAHAN

Paku/baut
Kayu
Besi begel

EQUIPMENT
PERALATAN

1 Balok pemikul dipasang diatas


tiang pancang.
2 Gelagar dipasang diatas balok
pemikul.
3 Untuk perkuatan masing-masing
sambungan memakai baut/paku
dan begel.

ASUMTION

1
2
3
4

With man pawer


Main Beam 25/30
Timber 5/30
Be calculated per 1 M3

ANGGAPAN :

1
2
3
4

Dengan tenaga manusia


Balok utama ukuran 25/30
Balok melintang ukuran 2
Dihitung per 1 M3

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
45,000.00

1 Balok pemikul dipasang diatas


tiang pancang.
2 Gelagar dipasang diatas balok
pemikul.
3 Untuk perkuatan masing-masing
sambungan memakai baut/paku
dan begel.

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000
2.000
6.000

1.000
1.000
1.000
1.000

1.000
1.000
2.000
6.000

SUM
JUMLAH

UNIT
SATUAN

6.500
1.000
3.015

Kg
M3
Bh

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
10,000.000
2,000,000.000
7,200.000

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

Alat bantu

VOLUME E

1.000

Set

1.000

SATUAN

M3

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

12,000.000

HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TIMBER RUNNING FLOOR
PEKERJAAN KAYU BANTALAN LANTAI

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Kayu diketam terlebih dahulu.


Kayu dipotong sesuai dengan
2
ukuran
dalam desain.
1 Kayu diketam terlebih dahulu.
Kayu dipotong sesuai dengan
2
ukuran
dalam desain.

ASUMTION

1
2

Material cost be calculated


Be calculate per 1 M3

ANGGAPAN :

1
2

Hitungan bahan ditempat


Dihitung per 1 M3

LABOUR
PEKERJA

Foreman
Chief Laborer
Skill Laborer
Laborer

MATERIAL
BAHAN

Paku
Kayu

EQUIPMENT
PERALATAN

VOLUME E

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

0.200
1.200
12.000
4.000

1.000
1.000
1.000
1.000

0.200
1.200
12.000
4.000

SUM
JUMLAH

UNIT
SATUAN

0.750
1.000

Kg
M3

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

1.000

SATUAN

M3

D/E

HARGA SATUAN

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
45,000.00
UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
10,000.000
1,300,000.000

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
-

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
COATING FOR RAILING
PENGECATAN SANDARAN

FRENCH RED CROSS

PALANG MERAH PERANCIS

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

LABOUR
PEKERJA

1 Membersihkan tempat yang akan


dicat.
2 Cat dikerjakan dengan kuas.

ASUMTION

1
2
3

Material cost be calculated


1 Kg anty terminete can b
Calculated per 1 m2

1 Membersihkan tempat yang akan


dicat.
2 Cat dikerjakan dengan kuas.

ANGGAPAN :

1
2
3

Bahan dihitung ditempat p


1 Kg dapat menghasilkan
Hitungan per 1 M2

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

BILLING
RATE
(Rp./Days/Man)
UPAH

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

Foreman
Chief Laborer
Skill Laborer
Laborer

MATERIAL
BAHAN

Nail/Bolt
Timber

EQUIPMENT
PERALATAN

Suporting Eq.

VOLUME E

1.000
0.200
2.000
4.000

1.000
1.000
1.000
1.000

1.000
0.200
2.000
4.000

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
10,000.00
1,700,000.00

SUM
JUMLAH

UNIT
SATUAN

6.500
1.000

Kg
M3

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

1.000

Set

1.000

SATUAN

M3

D/E

FRENCH RED CROSS

PALANG MERAH PERANCIS

(Rp./Hr/Orang
47,500.00
45,000.00
52,500.00
55,000.00

HARGA SATUAN

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
12,000.000

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TMBER FOR BRIDGE FLOOR

FRENCH RED CROSS


PALANG MERAH PERANCIS

MEMASANG LANTAI JEMBATAN

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

LABOUR
PEKERJA

Foreman
Chief Laborer
Skill Laborer
Non Skill Laborer

MATERIAL
BAHAN

Nail/Bolt

1 Papan diketam terlebih dahulu.


2 Papan dipotong sesuai lebar
jembatan.
3 Papan dibaut pada kayu bantalan
lantai

ASUMTION

1
2
3

Material cost be calculated


Papan lantai tebal 8 Cm da
Hitungan per 1 M2

ANGGAPAN :

1
2
3

Hitungan bahan ditempat


Papan lantai tebal 8 Cm da
Hitungan per 1 M2

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
55,000.00
52,500.00
35,000.00

1 Papan diketam terlebih dahulu.


2 Papan dipotong sesuai lebar
jembatan.
3 Papan dibaut pada kayu bantalan
lantai

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
1.000
2.000
6.000

1.000
1.000
1.000
1.000

1.000
1.000
2.000
6.000

SUM
JUMLAH

UNIT
SATUAN

6.500

Kg

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
10,000.00

Timber

1.000

M3

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

VOLUME E

1.000

SATUAN

M2

D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

1,300,000.00

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TIMBER FOR FLOORING CO
LAPIS PENUTUP LANTAI

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

1 Membersihkan kayu yang akan


diteer.
2 Teer dioleskan dengan kuas.

ASUMTION

1
2
3

Material cost be calculated


1 Kg anty terminete can b
Calculated per 1 m2

URAIAN :

LABOUR
PEKERJA

Foreman
Laborer
Operator

1 Membersihkan kayu yang akan


diteer.
2 Teer dioleskan dengan kuas.

1
2
3

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
52,500.00
0.00

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

1.000
6.000
-

1.000
1.000
-

1.000
6.000
-

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)
65,000.00
85,000.00
6,500.00
65,000.00
45,000.00

MATERIAL
BAHAN

SUM
JUMLAH

UNIT
SATUAN

Stone Crush 5/7 cm


Stone Crush 2/3 cm
Terminite (Teer)
Sand
Seng Plat BJLS 20

0.070
0.030
4.000
0.020
0.500

M3
M3
Kg
M3
Lbr

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

2.000

Set

Supporting Eq.

Bahan dihitung ditempat p


1 Kg teer mengerjakan 3 m
Hitungan per 1 m2

ANGGAPAN :

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)
12,000.000

VOLUME E

1.000

SATUAN
D/E

FRENCH RED CROSS


PALANG MERAH PERANCIS

M2
HARGA SATUAN

(Rp.)

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
CLEAN OUT AND TERMINITE COATING
PEMBERSIHAN DAN PENGETERAN

REHABILITATION AND RECONSTRUCTION OF THE FISHPONDS IN JEUMERANG, PASI LH


KEMBANG TANJUNG SUB DISTRICT PIDIE DISTRICT NANGGROE ACEH DARUSSALA
REHABILITASI TAMBAK UDANG DI DESA JEUMERANG, PASI LHOK, LANCANG
KECAMATAN KEMBANG TANJUNG KABUPATEN PIDIE PROPINSI NANGGROE ACEH DAR

EXPLANATION

URAIAN :

1 Membersihkan kayu yang akan


diteer.
2 Anty termite painting be
coating by shaving brush
1 Membersihkan kayu yang akan
diteer.
2 Teer dioleskan dengan kuas.

ASUMTION

1
2
3

Material cost be calculated


1 Kg anty terminete can b
Calculated per 1 m2

ANGGAPAN :

1
2
3

Bahan dihitung ditempat p


1 Kg teer mengerjakan 3 m
Hitungan per 1 m2

LABOUR
PEKERJA

Foreman
Skill Laborer
Operator

MATERIAL
BAHAN

TOTAL
PERSONEL
JUMLAH
ORANG

DAYS
HARI

TOTAL
MAN/DAYS
JUMLAH
HARI/ORANG

0.080
0.540
-

1.000
1.000
-

0.080
0.540
-

UNIT
(Rp.)
HARGA
SATUAN
(Rp.)

SUM
JUMLAH

UNIT
SATUAN

0.400

Kg

EQUIPMENT
PERALATAN

TOTAL
EQUIPMENT
JUMLAH
ALAT

WORK
DAYS
HARI
KERJA

WORK
HOURS
JAM
KERJA

VOLUME E

1.000

SATUAN

M2

Termite

D/E

BILLING
RATE
(Rp./Days/Man)
UPAH
(Rp./Hr/Orang
47,500.00
52,500.00
0.00

6,500.00

HARGA SATUAN

UNIT PRICE
(Rp.)
HARGA
SATUAN
(Rp.)

(Rp.)

Hal. 10
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE FORM WORK
PEKERJAAN CETAKAN UNTUK BETON

CODE
KODE
K. 710

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

1/3 dari bahan masih dapat digunakan lagi untuk


cetakan lain.
Kapasitas produksi = 2 M3 / hari.

COST
(Rp.)
BIAYA
(Rp.)
47,500.00
55,000.00

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

315,000.00
140,000.00
COST
(Rp.)
BIAYA
(Rp.)

557,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

1,040,000.00
80,000.00
1,120,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

671,000.00

1,677,500.00

Per M3

Hal. 11
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CLEANING AND COATING
PEMBERSIHAN DAN CAT TEMBOK

CODE
KODE
K.813

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Bahan dihitung ditempat pekerjaan.


1 kg can be covered on 6 m2
1 kg dapat menghasilkan 6 m2
Calculated per 1 m2
Hitungan per 1 m2

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

475.00
10,500.00
COST
(Rp.)
BIAYA
(Rp.)

10,975.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

2,250.00
2,250.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

13,225.00

13,225.00

Per M2

Hal. 12
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE REINFORCEMENT
PENULANGAN BETON

CODE
KODE
K. 715

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

200 Kg besi dapat disiapkan dalam 1 hari


Cost of material besed on job site
Harga material berdasarkan ditempat pekerjaan.
Pemakaian bahan tulangan dilebihkan 10 % untuk
membengkok dan penyambungan.
200 Kg besi dapat disiapkan dalam 1 hari
Cost of material besed on job site
Harga material berdasarkan ditempat pekerjaan.

Pemakaian bahan tulangan dilebihkan 10 % untuk


membengkok dan penyambungan.

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
52,500.00
90,000.00
70,000.00
COST
(Rp.)
BIAYA
(Rp.)

260,000.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

1,430,000.00
10,000.00
1,440,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

850,000.00

1,700,000.00

Per M3

Hal. 13
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CONCRETE K. 175
B E T O N K. 175

CODE
KODE
K.725

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


Productivity of concrete mixer is 10 M3/hari.
Mix design 1 : 2 : 3.
Length of mixing is 9 minute
The weight of 1 M3 concrete 2.400 Kg and
1 Pocket PC 40 Kg.
Harga/material dihitung dilokasi pekerjaan.
Kapasitas produksi adukan beton 10 M3/hari.
Campuran 1 : 2 : 3.
Lamanya setiap kali pengadukan 9 menit
1 M3 beton beratnya 2.400 Kg dan 1 Zak PC beratnya
40 Kg

COST

SUB TOTAL

(Rp.)
BIAYA
(Rp.)

A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
55,000.00
52,500.00
280,000.00
35,000.00
COST
(Rp.)
BIAYA
(Rp.)

470,000.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)
696,997.50

116,737.50
494,400.00
85,860.00

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

187,392.88
187,392.88
JUMLAH (Rp.)

677,195.19

1,354,390.38

Per M3

Hal. 14

WORK COST ESTIMATE ANALIZE


ANALISA PERKIRAAN BIAYA PEKERJAAN
REINFORCEMENT CONCRETE
BETON BERTULANG LANDASAN PLAT INJAK
DAN GLAGAR

CODE
KODE
K.725 A

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Concrete mixing 1 : 2 : 3
Capacity are 2 M3/days
Material cost be calculated on the job site
Campuran beton 1 : 2 : 3
Kapasitas 2 M3/hari
Haraga bahan dilokasi pekerjaan.

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

470,000.00
364,000.00
223,000.00
42,000.00
COST
(Rp.)
BIAYA

1,099,000.00
SUB TOTAL
B (Rp.)
SUB JUMLAH

(Rp.)

B (Rp.)

696,997.50
2,016,000.00
448,000.00
3,160,997.50
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

187,392.88
187,392.88
JUMLAH (Rp.)

2,223,695.19

4,447,390.38

Per M3

Hal. 15
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TIMBER BEAM AND BRANCHING
MEMASANG GELAGAR/SEKUR

CODE
KODE
K.900E

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

With man pawer


Main Beam 25/30
Timber 5/30
Be calculated per 1 M3
Dengan tenaga manusia
Balok utama ukuran 25/30
Balok melintang ukuran 25/30
Dihitung per 1 M3

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
55,000.00
105,000.00
270,000.00
COST
(Rp.)
BIAYA
(Rp.)
65,000.00
2,000,000.00
21,708.00

COST
(Rp.)
BIAYA
(Rp.)

477,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)
2,086,708.00
SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

12,000.00

12,000.00
JUMLAH (Rp.)

2,576,208.00

2,576,208.00

M3

Hal. 16
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TIMBER RUNNING FLOOR
PEKERJAAN KAYU BANTALAN LANTAI

CODE
KODE
K. 903

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


Be calculate per 1 M3
Hitungan bahan ditempat pekerjaan.
Dihitung per 1 M3

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

9,500.00
66,000.00
630,000.00
180,000.00
COST
(Rp.)
BIAYA
(Rp.)
7,500.00
1,300,000.00

COST
(Rp.)
BIAYA
(Rp.)

885,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)
1,307,500.00
SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

2,193,000.00

2,193,000.00

Per M3

Hal. 17
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
COATING FOR RAILING
PENGECATAN SANDARAN

CODE
KODE
K.813 A

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


1 Kg anty terminete can be covered 3 m2 area
Calculated per 1 m2
Bahan dihitung ditempat pekerjaan
1 Kg dapat menghasilkan 3 M2
Hitungan per 1 M2

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
9,000.00
105,000.00
220,000.00
COST
(Rp.)
BIAYA
(Rp.)

381,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

65,000.00
1,700,000.00
1,765,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

12,000.00

12,000.00
JUMLAH (Rp.)

2,158,500.00

2,158,500.00

Per M3

Hal. 18
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TMBER FOR BRIDGE FLOORING

CODE
KODE

MEMASANG LANTAI JEMBATAN

K.902

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


Papan lantai tebal 8 Cm dan lebar 20 - 25 Cm
Hitungan per 1 M2
Hitungan bahan ditempat pekerjaan
Papan lantai tebal 8 Cm dan lebar 20 - 25 Cm
Hitungan per 1 M2

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
55,000.00
105,000.00
210,000.00
COST
(Rp.)
BIAYA
(Rp.)
65,000.00

417,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

1,300,000.00
1,365,000.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

1,782,500.00

1,782,500.00

Per M2

Hal. 19
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
INSTALL THE TIMBER FOR FLOORING COVER
LAPIS PENUTUP LANTAI

CODE
KODE
K. 813 B

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


1 Kg anty terminete can be covered 3 m2 area
Calculated per 1 m2

Bahan dihitung ditempat pekerjaan.


1 Kg teer mengerjakan 3 m2 luasan
Hitungan per 1 m2

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

47,500.00
315,000.00

COST
(Rp.)
BIAYA
(Rp.)

362,500.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

4,550.00
2,550.00
26,000.00
1,300.00
22,500.00
56,900.00
COST
(Rp.)
BIAYA
(Rp.)

24,000.00

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

24,000.00
JUMLAH (Rp.)

419,400.00

419,400.00

Per M2

Hal. 20
WORK COST ESTIMATE ANALIZE
ANALISA PERKIRAAN BIAYA PEKERJAAN
CLEAN OUT AND TERMINITE COATING
PEMBERSIHAN DAN PENGETERAN

CODE
KODE
K. 813 B

OF THE FISHPONDS IN JEUMERANG, PASI LHOK, LANCANG,


IE DISTRICT NANGGROE ACEH DARUSSALAM PROVINCE
G DI DESA JEUMERANG, PASI LHOK, LANCANG
UPATEN PIDIE PROPINSI NANGGROE ACEH DARUSSALAM

Material cost be calculated on the job site


1 Kg anty terminete can be covered 3 m2 area
Calculated per 1 m2
Bahan dihitung ditempat pekerjaan.
1 Kg teer mengerjakan 3 m2 luasan
Hitungan per 1 m2

COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
A (Rp.)
SUB JUMLAH
A (Rp.)

3,800.00
28,350.00
32,150.00
SUB TOTAL
B (Rp.)
SUB JUMLAH
B (Rp.)

COST
(Rp.)
BIAYA
(Rp.)

2,600.00
2,600.00
COST
(Rp.)
BIAYA
(Rp.)

SUB TOTAL
C (Rp.)
SUB JUMLAH
C (Rp.)

0.00
JUMLAH (Rp.)

34,750.00

34,750.00

Per M2

Anda mungkin juga menyukai