Anda di halaman 1dari 22

Top 10 Mistakes Made in Managing Project Risks

Top Ten Mistakes Made in


Managing
g g Project
j
Risks
Joe Lukas, PMP, PM, CCE

Chapter Dinner / Lunch Meetings


March 19 & 20, 2012

Consulting and Training (online, public and private)

project management
business analysis
Agile projects
Interpersonal skills

Free Educational Webinars


Earn ~10 PDUs per year
http://www.pmcentersusa.com

Webinars on Demand
Tips & Techniques
White Papers

March 19 & 20, 2012

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Presentation Objectives
Are you making any of the common errors in
risk management?
This talk will cover the top ten mistakes Project
Managers make in dealing with project risks
This presentation will also discuss how to avoid
these mistakes, along with effective risk
techniques that should be used on projects

Joe Lukas-March 19 & 20, 2012

Top 10 Risk Mistakes


1. Not considering opportunities just threats
2 C
2.
Confusing
f i risk
i k causes, risk
i k events
t & iimpacts
t
3. Using checklists and not scanning the
horizon for other risks
4. Understating risk impacts, and not scaling the
impacts based on project drivers
5. Not using 100% probability during planning

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Top 10 Risk Mistakes
6. Not considering sensitivity with Risk Analysis
7 Calling
7.
C lli risk
i k response planning
l
i mitigation
iti ti
8. Not considering contingency plans when
doing risk response planning
g specific
p
p
project
j
team members
9. Not making
responsible for specific risk events
10. Not making risk management an on-going
process
Joe Lukas-March 19 & 20, 2012

Mistake #1
Not Considering Opportunities Just Threats
Risk Management is the process of identifying,
analyzing, and responding to all project risks
Risks typically related to highly chancy or
hazardous activities, but need to consider the
probability and impacts with a goal to:
maximize for positive events
minimize for adverse events
RISK = OPPORTUNITIES & THREATS
Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #1
Not Considering Opportunities Just Threats
Client example of risk management procedure
b i used
being
d tto manage projects
j t

Joe Lukas-March 19 & 20, 2012

Examples of Opportunities
Special pricing offered by a supplier
Competitive market conditions for a specific
service
Sudden availability of a key resource for a short
time period due to their project being postponed
Availability of some needed equipment (such as
servers or desktop computers) from another
company downsizing their operations
Availability of an government investment tax
credit for work done before a specified date
Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #2
Confusing risk causes, risk events & impacts
Common error during risk identification: failing
to distinguish among the causes of risk,
genuine risk events, and the impacts of risks
Result:
Dilutes the value of the risk process
Introduces distractions at early stages
Can obscure genuine risks

Joe Lukas-March 19 & 20, 2012

Causes-Risk Events-Impacts
Causes: Definite events or sets of
circumstances that exist in the project or its
environment and which give rise to uncertainty
Examples:
Doing a project in a developing country
Using unproven technology
Lacking skilled personnel

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

10

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Causes-Risk Events-Impacts
Risk Events: Uncertain activities that, if they
occur,, will effect the project
p j
objectives.
j
Examples:
Exchange rate fluctuations
Contractor delivery
Client expectations misunderstood

Joe Lukas-March 19 & 20, 2012

11

Causes-Risk Events-Impacts
Impacts: Unplanned variations from project
objectives (positive or negative) which are a
result of risks occurring.
Examples:
Milestone date missed
Budget under-run
Failure to meet performance target

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

12

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Causes-Risk Events-Impacts
Risks events have one unique dimension:
uncertainty (described as probability or

likelihood
off occurrence)
)
Need to maintain a clear separation between
Causes, Risk Events, and Impacts
Format: (1) Due to <cause>,
< i k event>
<risk
t> could
ld occur,
resulting in <impact>
(1)

Project Risks, Identifying Causes, Risks and Effects, Dave Hillson, PMP, PM
Network, September, 2000

Joe Lukas-March 19 & 20, 2012

13

Identified Risk Example


Due to <the many job opportunities for top-notch
programmers>, <the
th lloss off key
k project
j t personnel>
l
could occur, resulting in <higher costs and a
longer schedule>

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

14

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Identified Risk Example
Due to <other systems projects underway>, <a
lack of space to support the new application on
existing servers> could occur, resulting in <the
need to purchase a new server>

Joe Lukas-March 19 & 20, 2012

15

Identified Risk Example


Due to <a lack of training resources>, <system
launch without the necessary training materials>
materials
could occur, resulting in <poor data quality
because untrained users enter incomplete data>

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

16

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Identified Risks Example
IMPACT
CAUSE
Need to purchase
equipment from
foreign supplier

RISK EVENT
Exchange
E
h
rate fluctuation

Doing a project in
a foreign country

Equipment held
up in customs

Lack of skilled
equipment
mechanics

Problems
installing hi-tech
manufacturing
equipment

17

Joe Lukas-March 19 & 20, 2012

Identified Risks Example:


IMPACT
CAUSE

RISK EVENT

Sharing senior software Work overload


programmer
Occurs
between two projects

Using new software


technology

Unanticipated

integration errors

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

18

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Risk Identification Tools
Risk Causes

Causes
1
4

Category = Legal Risks

a lawsuit against the


Department of Health
and/or the Homeowners
Association

Impacts
Cost

Time
Quality

P = 20%

I = 10

RF = 2.0

1.
2
2.
3.
4.
5.
6.
7.

Function

Keep Risk Causes on


separate sheet

Use Post-It notes set-up as shown


to capture and analyze risks
Joe Lukas-March 19 & 20, 2012

19

Mistake #3
Using checklists and not scanning the horizon
for other risks
Checklists listings of risk events
typically encountered on a specific
type of project, but the team doesnt
consider whats not on the list!

Use Brainstorming free flow of ideas


used to generate a listing of other
potential risk events that may occur
Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

20

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #4
Understating risk impacts, and not scaling the
impacts based on project drivers
Four possible consequences to any risk event:
Cost
Schedule
Functionality
Quality

Need to look at largest impact in the four areas


Joe Lukas-March 19 & 20, 2012

21

Prioritize the Project Drivers

Time

Scope:

Cost

Needs and
Expectations
of
Stakeholders

Quality

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

22

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Sample Project Impact Scale
Impact
Value

Cost

Schedule

10

5% variance

5% variance

4% variance

4% variance

3% variance

3% variance

2% variance

2% variance

1% variance

1% variance

Functionality
Major Issue

Quality
Major Issue

Medium Issue Medium Issue


Minor Issue

Minor Issue

Very Small
Issue
-

Very Small
Issue
-

Need to consider relative importance of project impacts


(are all impacts weighted equal?)
23

Joe Lukas-March 19 & 20, 2012

Weighted Project Impact Scale


Impact
Value

Cost

Schedule

Functionality

10

Very high
Impact
High Impact

Major Issue

8
6

Medium
Impact
Low Impact

Medium
Impact
Low Impact

Major Issue

Medium Issue Medium Issue

Major Impact

Minor Issue

Minor Issue

Very Small
Issue
-

Very Small
Issue
-

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

Quality

24

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #5
Not using 100% probability during planning

Probability Description
1.0
Certain to occur (100%)
0.9
Almost certain to occur (>90%)
0.7
Highly likely (>70%)
0.5
Likely (>50%)
Low likelihood (<30%)
0.3
0.1
Very unlikely (<10%)
0.0
No chance
Joe Lukas-March 19 & 20, 2012

25

Mistake #5
Not using 100% probability during planning
Can have 100% probability during planning
phase
h
but
b t th
the P
Project
j tT
Team needs
d tto ttake
k
actions to reduce it below 100% or somehow
incorporate the item into the Project Plan
Example: due to the very heavy workload in the
client area making key personnel unavailable,
k requirements
key
i
t may b
be missed,
i
d resulting
lti iin
What actions can be taken to reduce this risk
event to <100% probability?
Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

26

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #6
Not Considering Sensitivity with Risk Analysis

Risk Simulation
Improves project risk management by determining
the biggest risks for risk response planning
Education tool for management to
help them understand project
Also improves estimate (cost & schedule)
accuracy and determine a contingency
amount for an acceptable risk level
27

Joe Lukas-March 19 & 20, 2012

Risk Simulation Software


Risk analysis software provides:
Frequency of

probable cost or
schedule outcomes
Time or $s

Cumulative
C
l ti costt or

schedule with
overrun probabilities
Time or $s

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

28

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Risk Simulation Problem
Project team needs to assign most likely,
optimistic and pessimistic values to each risk:
There is a

BIG tendency to understate risk impact!

One option: define standards for risk ranges to

minimize debate

Low = -5% to +10%

Medium = -10%
10% to +50%

High = -20% to +100%

Very High = -30% to +300%

Joe Lukas-March 19 & 20, 2012

29

Mistake #7
Calling risk response planning mitigation
Client example
p of risk management
g
tool being
g
used to manage projects

This tool mistakes mitigation as


being the only risk response action!

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

30

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #7
Calling risk response planning mitigation
The product
p
of risk management
g
is called the
Risk Register and it includes:
List of identified risks
Risk analysis
Risk response plans including contingency plans

Its not
A Risk Management Plan
A Mitigation Plan
A Risk Assessment

Joe Lukas-March 19 & 20, 2012

31

Risk Response Techniques


For Threats:

For Opportunities:

Avoid

E l it
Exploit

Transfer

Share

Mitigate

Enhance

For Both:
Acceptance
Contingency Plans
Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

32

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Avoidance & Exploit
Avoidance: eliminating specific
threats, usually by eliminating
the cause

Exploit: Seeks to provide


d fi iti causes th
definitive
thatt will
ill eliminate
li i t
uncertainty and allow the risk
realization for an opportunity

Joe Lukas-March 19 & 20, 2012

33

Transfer & Share


Contractual agreements may be used to
transfer negative risks to others
Allocating ownership to a
third party who is best able
to capture the opportunity
for the benefit of the project
is a share example

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

34

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mitigate & Enhance
Mitigate: reducing the risk factor by reducing the
probability of occurrence and/or the risk event
impact
Enhance: make the risk event more likely by
increasing the probability of occurrence and/or
the risk event impact

Joe Lukas-March 19 & 20, 2012

35

Acceptance
Applies to both opportunities and
threats since seldom possible to
eliminate all threats or take advantage
of all opportunities
Can be passive acceptance do
nothing
Can be active acceptance developing a contingency plan and/or
reserve (time, money and/or
resources)

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

36

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #8
Not considering contingency plans when doing
risk response planning
Strategies for threats and opportunities are
actions taken before the risk event occurs
Contingency plans are actions taken after the
risk event occurs
Risk response planning should deal with both!

Joe Lukas-March 19 & 20, 2012

37

Example Risk Response Plan


Risk Event: Missing key project requirement
Expected Value: 9.0
Mitigation Plan: Include in resource plan
activities & hours need by key resources; get
management commitment to dedicate key
personnel to project
Contingency Plan: If key resources not
available, elevate issue to project sponsor

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

38

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Example Risk Event Plan
Risk Event: System launch w/o training materials
56
Expected Value: 5.6
Mitigation Plan: Get management commitment
to dedicate personnel to project (addresses
probability)
Contingency Plan: Get proposal from vendor
training companies to prepare materials, issue
Purchase Order to vendor if personnel dont start
as promised
39

Joe Lukas-March 19 & 20, 2012

Mistake #9
Not making specific project team members
responsible for specific risk events
Th
The Project
P j tM
Manager should
h ld iinvolve
l th
the
Project Team in owning project risks!
Risk Register
Project Title: New Project Portfolio System
Joe Lukas
Completed By:
14-May-04
Date Completed:

RISK EVENT

RF

ASSIGNED

PxI

TO
Mimi

incomplete user functional


requirements
q
1

contractors being hired who


are not familiar with Sunoco
systems
lack of justification for this
project at a 20% return

Project ID:
Project Manager:
Status Date:

0.9

10

9.0

0.7

5.6

0.2

10

2.0

RISK PLANNING
(RESPONSE & CONTINGENCY PLANS)
Mitigation: Get commitment from Business
Sponsor on making key users available for
requirements definition.
Contingency: If users don't show up, send
absent list to Business Sponsor for follow-up
phone calls.

STATUS
Specific dates and times for JAD
sessions being planned. Will look
for firm commitments on
attendance.

Mimi

Mitigation: Contact preferred supplier and try Working with Purchasing and
to reserve Sunoco experienced contractors. supplier on staffing plan.
Transference: consider using a fixed price
contract on this project.

Joe

Next project estimate update


Avoidance: Do sensitivity study early in
project to ensure this is a viable project.
planned for June, will update
Mitigation: recheck business financials every business case at same time.
time the project estimate is updated.

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

B004
Mimi Hoke
14-May-04

40

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Mistake #10
Not making risk management an on-going
process

Joe Lukas-March 19 & 20, 2012

41

Mistake #10
At each team meeting.
Ask if any new risks on the horizon
Check to see if any risk triggers occurred
Update status on execution of risk plans
Update probability and impact values
based on actions taken
Evaluate effectiveness of actions
taken in managing risks

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

42

Joseph A. Lukas
PMP, PE, CCE

Top 10 Mistakes Made in Managing Project Risks


Conclusion
Watch for the common risk management
g
mistakes outlined in this presentation
Establish a risk management procedure with
supporting templates for your company dont
leave it up to each Project Manager to invent a
process and/or tools
p

Joe Lukas-March 19 & 20, 2012

43

Questions???

Name: Joseph A. Lukas, PMP, PE, CCE


Email:
a joe
joe.lukas@pmcentersusa.com
u as@p ce te susa co
Phone: 609-575-9306

Joe Lukas-March 19 & 20, 2012

March 19 & 20, 2012

44

Joseph A. Lukas
PMP, PE, CCE

Anda mungkin juga menyukai