PV =
FV
( 1+i )t
PERT
( P+4 ML+O)
6
PERT =
1 SD =
2
V = ( SD )
Cost Variance
CV = EV AC
CPI = EV / AC
SV = EV PV
Schedule Variance
( PO)
6
Estimate To Complete
Assume we will to continue to spend at
the same rate
Variance At Completion
TCPI using BAC
TCPI using EAC
Number of Communication
Channels
Point of Total Assumptions
ETC = EAC AC
ETC: Estimate To Complete
EAC
Assume the remaining work will be
accomplished at the original planned
rate
EAC
Assume both the CPI & SPI will influence
the remaining work
EAC = AC + (BAC-EV)
EAC = AC + ((BAC EV)/
(SPI*CPI))
EAC
Assume plan and current spending do
not represent future
ETC
Estimate need to re-estimate