15
1. Malt Reception
Holding Capacity of the silos 300 Ton*4= 1200 Tones ,2*30 tones
Major Activities Dust, Stones and other metals are removed by dust blowers, de-stoners & magnets
respectively.
The malt is conveyed to the roller mill through bucket elevators.
The silos are appropriate for space utilization & safe storage of malt.( i.e the malt will be protected
from rodents & other insects.
There is an option to fumigate the silos to avoid attack by insects.
Capacity : 5 t/h
Sieve inclination :(2-15 )
Ambient temperature range :20 C/40 C
Pressure air loss :1200 Pa
3
Air consumption :120 m /min
Length :2210 mm
Width :1310 mm
Height :2200 mm
1.
2.
Only well trained person must operate the processing section PS 01, PS 02.
Malt is taken to silos the volume of which is 4 x 300 t, 2 x 30t,
When the line for malt inlet to silos is turned on, you must adjust the transport line for particular silo.
When the intake to the silo position 01.10/1 takes place the drive of the gate valve 01.09 is turned
on as the first and then next drive of the chain conveyor position 01.08/1. In this case next and next
drives follow to the drive of intake basket including aspiration. This happens according to block scheme
which is operated by automat when the operator adjusts the transport line in the operating room.
4.
When the transport line is adjusted for the malt supply from the silo no. 1 (this is only an example of the
transport line adjustment):
All the drives in the mill room must be turned on in the automatic mode. The operator will close the
gate valve 01.15. The chain conveyor 01.13 drives will start working and the screw conveyor 01.12/1 as
well. The electric gate valve under the silo 1 position 01.07/1 will open.
IT IS NECESSARY TO CHANGE THE POSITION OF THE MANUAL GATE VALVE AND REGULATE THE MALT
FLOW TO PS 02.
When the operation of malt intake and the operation of mill room take place, the intake aspiration and
mill room aspiration must take place as well.
Line 1 is the aspiration of the stone separator in PS 02. This aspiration is used only when the
line for cleaning of the malt for the beer batch is turned on.
The second system is for central aspiration of whole intake PS 01 and transport lines PS 02.
Aspiration system works in the full-blown automatic mode.
You have to change the sacks with waste. There are three sacking necks. It is necessary for the
aspiration system operation that at least 5bar of the air, for blowing of the filtrating hoses of
the filter (regeneration of the filtrating hoses), is in the central air distributor.
The grains stocked in the silos must be pre-cleaned and dry (humidity 14 %).
The outdoor large silos are equipped with 1 ventilator (only the outdoor silos), which through
the canals with perforation in the hopper will blow whole layer of the grains.
In the case of the active ventilation, it is necessary to check the parameters of the grains and
the ventilation air.
Small internal silos are protected by the building and so they do not have to be aerated.
Each silo is equipped with thermometer with several places of measuring.
The thermometer is place at the silo axis. Silos are equipped with continuous measuring of the
volume.
The upper sensor checks the volume so that the silo could not get overfilled and the lower
signalizes that the silo is empty.
The grains are drained from silos by gravitation through centre output.
Close both side outlet holes and let the grains flow away thanks to the gravity.
The flow regulation is done by manual gate valve or by the change of screw conveyor
frequency.
The grains are transport from silo by the screw conveyor.
When automatic mode takes place, everything is adjusted for the mode and the operator does
not have to change the parameters.
When manual mode takes place (we do not recommend this), the operator has to turn on the
drives in the direction of the malt flow from the last drive. See PC scheme.
a.
b.
c.
d.
e.
f.
g.
h.
Vertical quadrilateral vessel with conical bottom & flat lid, designed to guarantee full emptying of the
crushed malt.
Vessel will be delivered in parts bolted at site.
It designed for storage of 100% of the crushed malt loading for one brew (6545 kg).
Vessel is supported by legs via load.
Effective capacity :13.7 m3
3
Total capacity : 19.5 m
Length : 2800 mm
Width ; 1900 mm
Total height :approx. 4710 mm
Material : carbon steel
a. Worm conveyor
Inlet 410 * 2700 mm
Outlet 219 * 219 mm
Transported material : crushed malt ( Ro=0.50 t/m3)
Output : 25 t/h
Input power drive :3 KW
b. Worm conveyor DS 300 * 5 m-for transport of crushed malt
With one inlet 219 * 219 mm & one outlet 219 * 219 mm
Consisting of worm, coupling, gear box & electric motor with safety switch, including flanges,
sealing & joining material. Worm conveyor is equipped by induction sensor of revolutions &
induction sensor of overloading.
Transported material : crushed malt ( Ro=0.50 t/m3)
The malt is transported from any silo or from two different silos by means of conveyors to milling room
onto Drum sieve where foreign matters bigger than a kernel are separated from the malt.
It continues from drum sieve into the de-stoner where stones are separated and it follows into magnetic
separator where iron foreign matters are separated.
Detached impurities are transported in stands with bags (wastes)
Cleaned malt is transported by means of conveyors in Hammer mill where it is milled on required
grading. Crushed malt falls from Hammer mill into crushed malt hopper.
So milling is finished.
Milling line is provided with an aspiration dust suction from the equipment. The dust is caught by
means of air filter with a fun.
10
The malt is transported from any silo or from two different silos by means of conveyors to milling room
onto Drum sieve where foreign matters bigger than a kernel are separated from the malt.
It continues from drum sieve into the de-stoner where stones are separated and it follows into magnetic
separator where iron foreign matters are separated.
Detached impurities are transported in stands with bags (wastes)
Cleaned malt is transported by means of conveyors in Hammer mill where it is milled on required
grading. Crushed malt falls from Hammer mill into crushed malt hopper.
So milling is finished.
Milling line is provided with an aspiration dust suction from the equipment. The dust is caught by
means of air filter with a fun.
2.6. Preparation
Brewing process is automated fully except some control steps. Before wort boiling it is necessary to put
in receipt memory parametric values of some constants:
1. Before milling start it is necessary to check put parametric values of some constants in the receipt; e.g.
Malt volume form which one wort brew is produced, Speed of feeding equipment from the silo Except
the silo from which milling is started it is possible to adjust in parameters another silo from which milling
will continue when first silo is empty eventually
An overview of parametric values is shown is the manual Manual Brewery Raya_ r 03_Prop_VR
2. The operator starts the program of fore mashing C
3. The operator starts Start of aspiration. The operator checks whether aspiration fun M1222 and
aspiration filter M1224 are put in operation.
4. The operator starts Start of Classic mill.
5. Program steps for Classic mill follow:
5.1)
INITIAL STATE
5.2)
5.3)
SYNCHRONIZATION
5.5)
READY CONFIRMATION
5.6)
5.7)
5.8)
5.9)
5.10)
5.11)
5.12)
5.13)
5.14)
5.15)
5.16)
5.17)
5.18)
5.19)
MILLING
11
6.
The operator starts Start of line. Conveyors and apparatuses of milling line are put in the operation
stepwise on this instruction. Last equipment of milling line Classic mill is put in operation automatically
first, than conveyors M 2206, M2203, Destoner M22012, Drum sieve M 002.0100.050, conveyor M2201
and corresponding transporting & feeding equipment from selected silo.
7. The step Milling follows where sub steps of program sequence Classic mill are going; it is milling of
required malt volume from selected silos. In the same time the aspiration is running.
8. Should some silo is empted out during milling; conveyors are switched automatically so that milling
continues from other selected silo.
9. When required malt volume from selected silos is milled; automatic steps finishing milling process are
made:
10. STOP OF LINE during this step all conveyors are switched off and apparatuses of milling line in reverse
order than it was put in the operation.
11. STOP OF Classic mill
11.1)
11.2)
11.3)
11.4)
STOP 23
11.5)
STOP 24
11.6)
STOP 25
11.8)
11.9)
11.10)
11.11)
11.12)
DEDUSTING
11.13)
MILLING COMPLETED
So milling process is finished and crushed malt is prepared in crushed malt hopper.
Description of Classic Mill is in the manual of Meura 9716.1.3 FDS CLM
12
13
14
Time monitor can be set for each step. If the actual time >= monitoring time program
will stop and a new alarm message will appear in the alarm window. If monitoring
time is set to 0, the step duration is not checked.
INITIALSTATE
1.
START OF ASPIRATION
2.
START OF CLASSICMILL
3.
START OF LINE
4.
MILLING
5.
6.
STOP OF LINE
7.
STOP OF CLASSICMILL
8.
STOP OF ASPIRATION
15
INITIAL STATE
1.
2.
SYNCHRONIZATION
3.
READY CONFIRMATION
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
REST
15.
REST
16.
17.
18.
19.
MILLING
20.
21.
22.
23.
STOP 23
24.
STOP 24
25.
STOP 25
26.
27.
28.
29.
30.
DEDUSTING
31.
MILLING COMPLETED
16
3.2 Pre-masher
Producer : Meura, Belgium
For mashing-in process
a. Cold water circuit
1 hand operated butterfly valve
1 pneumatic modulation valve
1 non-return valve
1 pneumatically actuated double valve
b. Hot water circuit
1 hand operated butterfly valve
1 pneumatic modulation valve
1 non-return valve
1 pneumatically actuated double valve
c. Mixed water circuit
1 electromagnetic flow meter
1 temperature probe with convertor
d. Instrumentation
1 electromagnetic flow meter
1 temperature probe with convertor
1 thermometer
1 pressure gauge
e. Water pumps for pre mashing
Cold water pump
3
Flow rate : 63 m /hr
Body : cast iron
Impeller : stainless steel
Tightness : single mechanical seal
Hot water pump
Flow rate : 63 m3/hr
Body : cast iron
Impeller : stainless steel
Tightness : single mechanical seal
17
Type : vertical
Capacity :nominal 25 tons malt grist/h
Producer : Meura
Material : all parts in contact with the product are made of ASI 304 stainless steel
Fittings :
1 mixing vessel with side inlet from grist hydrator
1 sight glass
1 cleaning ball
1 overflow pipe
Accessories
Instrumentation
1 high level probe indicating an inlet overflow
1 low level probe at the pre-masher outlet
1 level transmitter for level regulation
Process valves
1 pneumatically operated butterfly valve
CIP valves
2 pneumatically operated butterfly valve
18
b. Fittings
instrumentation
1 compensating device
1 pressure switch
For rope seal of the pump
1 hand operated ball valve
1 filter
1 selonoid valve
1 adjusting valve
1 pressure gauge
1 flow switch
1 adjusting valve
3.6 Mashing-in
3.7 Mashing
During Mashing in mash tun, take sample when the level of mash in the mash tun reaches 50% for mash
PH; soon add mash additives (cacl2, caso4 & Enzyme (CEREMIX)).
During the 1st rest (52 C) add H3po4 based on the PH of the mash measured above to adjust the PH to
(5.35 -5.4) by referring your previous result.
nd
Again take sample after the 2 rest (72 C) when saccharification test confirmation blinks on the
operating screen & add iodine drops to the sample.
If solution looks blue black wait the time for more conversion & recheck till you see yellow color .when
you see yellow color soon click confirm saccharification test.
If all the conditions are ok after heating to mash off temperature (76C), click start on mash filter
operating screen to transfer the mash to mash filter.
If problem in the wort kettle is happened you could late the mash in the mash tun by controlling the
steam flow take the time to be delay time.
19
kg
The process starts when the operator clicks the button start on the control panel of mash kettle
Mashing-in starts automatically when the route is open and all control modules are controlled
by program sequence
Mashing-in is finished when the minimum is reached in the malt hopper and total volume of
water is reached (recipe)
Description of Mashing-in tank is in the manual of Meura 9716.1.3 FDS Mashing-in tank
Then the heating in the Mash kettle starts
When program goes through the steps of low and high sacharification temperature the process
in the Mash kettle finishes
After that Mash kettle heats to the filtration temperature
20
21
Preparing for
cleaning
22
23
Time monitor can be set for each step. If the actual time >= monitoring time program
will stop and a new alarm message will appear on the alarm window. If monitoring
time is set to 0, the step duration is not checked.
Idle
7.
8.
9.
10.
11.
12.
Pre-filling - Regulation
Stabilization - Fixed speed
Stabilization - Regulation
Open route for grist
Waiting for grist supply
Mashing-in
24
Rinsing spray ball - Pump
13.
Rinsing spray ball - Hydrator
14.
After Run
15.
Emptying
16.
End confirmation
17.
Draining
18.
End program
19.
CIP - Check starting condo
50.
CIP - Synchronization
51.
CIP - Cleaning
52.
B. Steps of Mash kettle
0.
1.
INITIAL STATE
WAITING FOR MASHING-IN TANK
2.
3.
4.
5.
6.
7.
MASHING-IN
DELAY AFTER MASHING-IN
ADDING ENZYM
HEATING TO 52C
MASHING-IN
DELAY AFTER 52C
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
50.
25
4. Mash Filter
4.1 Process Description
Prepare wort kettle additives based on the standard (Znso4 ,Caramel, HOP Pellet, HOP Extract)
Wort kettle should be empty to start mash filtration.
Valves should be in automatic mode.
After mash off (end of mashing) to start mash filtration click "start" on mash filter operating screen.
At the open filter step of mash filter (43), helper/operator must go to the mash filter to rinse the plates
with hot water (Temperature of 55C) after removal of the spent grain by controlling the shifting of the
plates.
First wort should be sampled after 5 minutes of start of filtration /transferring to wort collector to be
checked by laboratory (Extract, PH, color).
nd
Last running/weak wort should be sampled after 8 minutes of 2 compression to be checked by
laboratory (Extract, PH,
The process of the Mash filter can start if the conditions are fulfilled
The Mash filter is used for the filtration of the Mash.
Description of Mashing-in tank is in the manual of Meura 9716.1.3 FDS MF2001 and 9716.1.3 FDS
Spent Grains Conveyor
Conditions must be checked in the beginning of the process all conditions must be in state OK within
this step
Be sure that mash filter, pre-masher & mash tun are not on working conditions.
Hot water tank( temperature (76 -78)C, volume >550 hl)
Cold water tank volume >400hl
The water comes to pre-masher & then to mash filter.
When mash filter has not been in used for long period (more than 48 hrs) it requires proceeding to a
Preheating of the plates before starting production or cleaning.
The temperature gap between the product & polypropylene plates cannot be higher than 50C.
Independent from room temperature, it is not necessary to preheat the mash filter, if it stays less than
48 hours without function.
26
0.
1.
2.
3.
IDLE
RESERVE
MF01.01 - CHECK START. COND.
MF01.02 - SYNCHRONISATION
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
24.
25.
26.
27.
28.
29.
30.
31.
MF07.02 - SPARGING 1
MF07.03 - SPARGING 2
MF07.04 - SPARGING 3
MF07.05 - CLOSE MASHFILTER INLET
MF07.06 - STOP MASH PUMP
MF08.01 - FIRST COMPRESSION
32.
33.
34.
35.
36.
37.
MF09.03 - RINSING
MF09.04 - STOP MASH PUMP
22.
23.
27
38.
39.
40.
MF10.01 - EMPTYING
MF10.02 - COMPLETED
MF11.01 - CHECK VENT VALVE MASH SIDE OPEN
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
RESERVE
RESERVE
RESERVE
CIP - CHECK STARTING CONDITIONS
CIP - SYNCHRONISATION
CIP - CLEANING, NEUTRALISATION
53.
54.
55.
28
Conditions must be checked in the beginning of the process all conditions must be in
state OK within this step
29
30
-Time monitor can be set for each step. If the actual time >= monitoring time program will
stop and a new alarm message will appear in the alarm window. If monitoring time is set to
0, the step duration is not checked.
31
IDLE
1.
2.
3.
4.
5.
6.
RESERVE
CHECK STARTING CONDITIONS
SYNCHRONISATION
READY CONFIRMATION
PREDRAINING
REQUEST WATER SUPPLY
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
OPEN ROUTE
START MASH PUMP
FILLING
OVERFILLING
CLOSE MASHFILTER INLET
STOP MASH PUMP
PRE-HEATING
EMPTYING
DRAINING
SWITCH LOCAL BOX N*1 TO AUTOMATIC
SYNCHRONISATION
OPEN FILTER
SHIFTING PLATES
CLOSE FILTER
DRAIN SPENT GRAINS HOPPER
COMPLETED
32
IDLE
CHECK STARTING CONDITIONS
CONFIRMATION DESTINATION
WAIT FOR SHIFTING
START HOPPER & WAIT FOR LEVEL
WAITING FOR EXPELLING
6.
7.
EXPELLING
CONVEYOR DRAIN RINSING
8.
9.
10.
11.
12.
13.
HOPPER RINSING
EMPTYING
DRAINING
COMPLETED
RESERVE
RESERVE
14.
50.
RESERVE
CIP
33
6. Wort- Collector
Idle
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
WASHING 2
DELAY AFTER WASHING 2
CIRCULATION OF CHANGER
DRAINING
34
7. Wort Boiling
7.1 Preparation
After complete transferring of Clear filtered sweet wort from wort collector.
Constant stream flow, cold-water & compressed water has to be available
At start of boiling take sample from wort pan ,to be checked by laboratory for (Extract ,PH ,color,)
HOP Extract & Caramel should be prepared in the first vessel & automatic dosing time will be during
pressure increase &1st hoping step @96C.
HOP pellet & Znso4 should be prepared in the second vessel & automatic dosing time will be during
nd
pressure boiling &2 hoping step @98C.
At the end of boiling, take sample from wort pan, to be checked by laboratory for (Extract, PH, color,) of
the wort.
H
P at the end of boiling should be within (5.2-5.25).
Wort is boiled in wort pan with the addition of HOP components in order to;
35
36
37
38
will stop and a new alarm message will appear in the alarm window. If monitoring
time is set to 0, the step duration is not checked.
39
INITIALSTATE
PUMPING TO WORT PAN
PUMPING AND BOILING
WAITING TO TOTAL VOLUME
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
HEATING TO BOIL
ATMOSPHERIC BOILING 01
PRESSURE INCREASE
PRESSURE BOILING
PRESSURE REDUCTION
ATMOSPHERIC BOILING 02
RESERVE
RESERVE
RESERVE
BOILING
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
50.
RINSING 2 - DELAY
END
Cleaning
16.
17.
40
8. Whirlpool
8.1 Preparation
After end of boiling from the wort kettle take sample of end of boiling & "confirm sampling for wort
transfer to the wort settling tank from the wort pan operating window.
Boiled and hopped-wort is separated from trub materials & clarified by pumping the wort in a
Whirlpool & allowing hot-trub to settle for 20'.
Put the CCT number on the whirl pool window on the Number of Target CCT
Trub tank
Total capacity : 2 m3
Inside diameter :1350 mm
Height :2900 mm
Top angle of bottom :70
Material :stainless steel
8.3 wort-cooling
41
Aerated & agitated Yeast (for about 3 hrs)is pitched with first brew in automatic mode (Yeast will be
pitched based on the consistency & viability result from microbiology) refer under yeast pitching
topic.(by fermentation operator)
If the wort is for yeast propagation purpose follow the procedure under yeast propagation.
After 15 minutes, take sample for cold wort to be checked by laboratory (Original wort gravity /cold
wort Extract, PH, Color & for organoleptic taste (by brew house operator).
At the end the wort is pushed to CCT with water (7hl) & is drained, when the water is reached at the
CCT, by switching on the CIP outlet automatic valve of the CCT or wort is completely filled to the CCT by
switching off wort inlet automatic valve of the CCT.
8.4 Preparation
When the wort is completely transferred to CCT, trub will be drained to the trub tank (see step 22 of
whirlpool)
The separated hot trub shall be dosed for next brews when transferring of mash from mash tun to mash
filter in automatic mode (when 25hl mash is left on mash kettle), if it is not stayed more than 24 hrs
otherwise released to the drainage.
42
Picture 1: whirlpool
Wort to propagation
Air to wort
43
44
Time monitor can be set for each step. If the actual time >= monitoring time
program will stop and a new alarm message will appear in the alarm window.
If monitoring time is set to 0, the step duration is not checked.
INITIAL STATE
PUMPING 1 TO WHIRLPOOL
PUMPING 2 TO WHIRLPOOL
END OF PUMPING
REST
WAITING FOR PROPAGATION
6.
7.
8.
9.
10.
11.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
RINSING 2 - DELAY
RINSING 3
RINSING 3 - DELAY
RINSING 4
32.
33.
RINSING 4 - DELAY
RINSING 5
12.
13.
14.
15.
45
34.
35.
50.
INITIALSTATE
DELAY
CIRCULATION
PUMPING TO MASHFILTER
RINSING
DELAY AFTER RINSING
PUMPING RINSING TO MF
PUSHING WITH WATER
RINSING 2
DRAINING
Water system is used for mashing-in, sparging, and rinsing the tanks in the Brew house
Vapor way is used for heating the technological water.
Technological water pre-heats the mash to wort pan
Pump M5201 is started, if the water for rinsing the tanks in the Brew house is needed
Pipes for mashing-in and sparging are directly connected to hot and cold water tanks
46
47
48
When the Silo is full the spent grain should be transported by truck for cattle feed.
Controlled/operated by Brew house of operator in automatic/manual mode.
Thermolized yeast may add to the spent grain if there is thermolized yeast.
Spent malt from the mash filter is stored in spent malt tank
If the dispensing of malt starts, malt valve under the conveyor opens. After that the conveyor starts
In the step issue of malt the air is flipping and water valve is opened
Dispensing of malt finishes, when the operator presses the button End
Button Pause pauses the process Stops the conveyor, air valve and water valve will be closed, only
malt valve will be opened
49
50
Idle
1.
2.
ENABLE OF ISSUE
OPEN OF M3220
ISSUE OF SPENT
END OF ISSUE
3.
4.