Quick Manual for SAP ERP Project System

(PS)

By: Choten Tshering


Engineer

220KV PROJECT DIVISION OFFICE


DEVELOPMENT & CONSTRUCTION DEPARTMENT

BHUTAN POWER CORPORATION LIMITED


JIGMELING: BHUTAN

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

1|P a g e

QUICK GUIDE OF SAP ERP


A-Project System:
1. Create Activity
You can create Internal, external, services and General cost activity
a. External activity
Cj20n right click on WBS (at which you wanted to create activity or
inure expanse)click on external Enter fill up all mandatory
(Descriptions, cost element(GL), Qty & unit, Price, purchasing group
and material group) EnterSave
b. Service activity
Cj20n right click on WBS (at which you wanted to create activity or
inure expanse)click on ServicesEnter fill up (Descriptions,
purchasing group and material group) Enter(new window will pop
up) Fill up (Service no/Service text, Qty & UoM, cost
element(GL))Enterback Save.
2. Create Purchase Requisition (PR)
Cj20n Click on ActivityEditRelease save Note the PR number
3. Release Purchase Requisition (PR)
Note: Release the Activity in Cj20n where automatically PR number will
generate
Me54nDocument overview on Selection variant select purchase
requisition double click on PR  Enter display/change icon(pencil
icon) release strategy click on change/display icon (pencil icon at the tool
bar)click on pencil icon and one tick mark) save.

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

2|P a g e

4. To Create Many Purchase order to one Purchase order


Me21nDocument overview on Selection variant select purchase
requisition click on all PR (clt+ each PR no)Adopt  document type
(Project Service) Enter vendor EnterStart date( we have done the signing
date of contract) validity date( end date of contract)Select payment
processingretention (say 10%) EnterCheck save.( kindly note the PR
number)
3. Release the PO
Me29nother purchase orderEnter PO number Enter Headerrelease
strategy click on change/display icon (pencil icon at the tool bar)click on
pencil icon and one tick mark) save.
4. Print Set up for Purchase order (PO)
Message o/p type (NEU)Medium(print output)Language(English
communication logical destination(LOCL) back further data dispatch
item select third one(send with application own transaction)
backbackfinish Header text(terms of payment, terms of delivery etc)
5. Create SES
ML81N Other purchase order Enter PO numberCreate Short
Text(RA-number)Enter Click Service SelectionEnter Select or click
on specific BOQ items Click on Adopt service Enter qty Save
yes(note the Entry sheet document no.)
6. Approve SES
ML81Ndouble click on overviewsClick
icon)click on accept(Flag symbol) saveyes

display/change

(pencil

Note: You can approve the SES soon after you are done with the qty entry. The
process will start from display or change

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

3|P a g e

7. Park the invoice for FICO


Mir7 Invoice date Posting dateReference (write abt the RA
number)PO referenceinsert PO number EnterEnter( till nothing
appears at the bottom of the screen) copy the amount that appears on the
balance box to the amount at the amount box at left corner of screen( amount at
balance should be zero)  Click on withholding tax select I2(3% for foreign
contractor and supplier )Enter the retention due dateclick on simulate at the
top of the screenSave park document(Yellow colour will appears) note the
park document number and give this number to Finance along with contractors
invoice and our MB.

8. Park the credit memo for FICO


Mir7 Invoice date Posting dateReference (write abt the RA
number)short text (write abt the recovery)PO referenceinsert PO
number Enter balance box at left corner of screen( amount at balance
should be zero)  De-select all the line itemClick G/L (write the G/L
account No)enter the amount of recoveryclick on simulate at the top of the
screenSave park document(Yellow colour will appears) note the park credit
memo document number and give this number to Finance along with
contractors invoice and our MB.
Note1: if recovery to be done to Project System, give WBS number to Finance
to Post the document
Note2: Credit memo is done for recovery from the vendor such as LD.
9. Progress
a. Update progress
Cj20nclick on WBSClick on ActivityEditConfirmActual date(date
on which you wanted to confirm)QtyBackSave.
b. View Progress
ZPSPRGEnter Project definition (say DCD-BPC-03001) Enter
yearmonth to Month (say 2 to 3)Execute.

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

4|P a g e

B. Purchase of Miscellaneous item


1. Create Purchase Order (PO)
1 .i. line items less than 1
ML-21ndocument type (manual /emergency) Insert vendorAccount
Assignment (Pprojects) materials group (0061service) Plant head
(thd1) Enter insert short text instead of material number qty Rate
Enter system will pop another screen ( Enter WBS no, GL account no.)
Enter Check Save Note the PO number.
1. ii. Line item more than two
ML-21ndocument type (manual /emergency) Insert vendorAccount
Assignment (Pprojects) Item category (Dservices) materials group
(0061service) Plant head (thd1) Enter in short text wirte the name of
items you are procuring say stationary item, R&M of Vehicle BG-2A-0636) 
Enterinsert short text instead of material number qty Rate Enter
system will pop shall screen (Enter WBS no, GL account no.) Enter
Check Save Note the PO number
Note: In1.i, item category need not entered and is acting as the external
services where you have to do good receipt by using T-code migo. In 1.ii
item category is assign as D i.e. services activities where you have to do
service entry sheet using T-code ML81n.

2. Release PO
Me29nother purchase orderEnter PO number Enter Headerrelease
strategy click on change/display icon (pencil icon at the tool bar)click on
pencil icon and one tick mark) save.
3. Good Receipt
Migodocument type (Select good receipt) click on other purchase
orderEnter PO number click on item OK checkPost note the GR
note document number.

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

5|P a g e

4. Print Set up for Good Receipt (GR)


Message o/p type (GIN/GRN)Medium(print output)Language(English
communication logical destination(LOCL) back further data dispatch
item select third one(send with application own transaction)
backbackfinish Header text(terms of payment, terms of delivery etc)
5. Create SES
ML81N Other purchase order Enter PO numberCreate Short Text
(Bill No)Enter Click Service SelectionEnter Select or click on specific
line items Click on Adopt service Enter qty Save yes(note the Entry
sheet document no.)
6. Approve SES
ML81Ndouble click on overviewsClick
icon)click on accept(Flag symbol) saveyes

display/change

(pencil

Note: You can approve the SES soon after you are done with the qty entry.
The process will start from display or change
7. Park the invoice for FICO
Mir7 Invoice date Posting dateReference (write abt the bill
number)PO referenceinsert PO number EnterEnter( till nothing
appears at the bottom of the screen) copy the amount that appears on the
balance box to the amount at the amount box at left corner of screen( amount at
balance should be zero) Click on withholding tax select I1(2% for
Bhutanese contractor and supplier)(Note: if you know the exact percentage of
the TDS, else leave for FAS) click on simulate at the top of the screenSave
park document(Yellow colour will appears) note the park document number
and give this number to Finance along with vendors invoice.

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

6|P a g e

C. Procurement of Asset in Project System


a. Procure by Plant
1. Create material reservation:
Cj20nclick on specific WBS (say Vehicle) Right click on the WBS
CreateInternal ActivityEnter Name the activity (say Two wheeler)fill
up all the mandatory one Enter SaveRight click on activity Create
Material componentsearch the material from the material master(if material is
not created in the material master, you should ask to MM functional lead to
create the material giving all the details of the asset) enter storage location,
plant head, delivery date) save.
Note:
1. You can create reservation in internal activity only
2. When you save it you will get the reservation number and give this to MM
people to for creating the PO or you may create PO from PS only.
2. Create PO
Me21ndocument type (Project material)material numberplant Storage
location quantity rate fun centre manually in account assignment (i.e.
item details of PO (say 220kv_TSI)) and save PO.
Note: no need of entering the item category and account assignment
3. Release PO
As in A.3 & B2
4. Good Receipt
As in B.3
Note: check that the material is going in the correct storage location under
the Plant and the same is going in Unrestricted stock.
5. Stock Overview
MMBEMaterial PlantStorage

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

7|P a g e

Note: If the GR is done correctly, then your stock will be reflected in your
plant.
6. Issue material to reservation:
Migomaterial reservationReservation Number Qtycheckpost
Note: Give the materials details to FAS to create Asset code
7. To check the goods in our stock
MB5TPlant headcompany code Issuing PlantExecute.
8. Good receipt form Store
MigoPurchase order or (STO number) As usual

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

8|P a g e

Process Flow Chart for Procurement


Yes

Purchase
Order is to
be created

Purchase
Asset
Item??

/NAS01
Create New Asset
Master Record

No

/NME21N
Create Purchase Order

/NME29
Release Purchase Order
/NME9F
Print Purchase Order

Goods is physically
received

Purchase
Order

/NMIGO
Perform Goods Receipt

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

9|P a g e

Asset Item
Purchased?

Invoice is received

Approve
Invoice

/NAs02
Update Asset Master
Record

Send Invoice
to Office of
Finance

Office of Finance
Process for Payment

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

10 | P a g e

b. Asset procure by RSD, P/ling

1.
2.
3.
4.

Create Internal Activity to create material reservation(see C1a)


Migo Transfer posting ReservationCheckPost
Ask FAS to create asset code
Send the asset code with details to functional lead for settlement

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

11 | P a g e

SAP ERP TRANSACTION CODE


(PS)

Cj20n: Project Builder


Cj40: Project Cost Planning
Cj30 : Project Budget Approval
Cj32: Project Budget Release
Cj34: Project Budget Transfer
Cj36: Project Budget Supplement
Cj35: Project Budget Return
Me54n: Release Purchase Requisition(PR)
Me5j: Check PR
Me21n: Create Purchase Order (PO)
Me2j:Check PO
Me29n: Release Purchase Order
Ml81n: create/approved Service Entry Sheet(SES)
Me2s: Report of SES
Cn41: Report of structure overview
Mir7: Parking invoice
Migo: goods Receipt
Me22n: Amend PO

SAP ERP TRANSACTION CODE


(MM)
Me41: Create Request for Quotation (RFQ)
Me47: Maintain Quotation
Me49 : Price Comparison List

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

12 | P a g e

Me31K : Create Contract


Me35K : Release (Approved) purchasing document
Me21n: Create Purchasing Order (PO)
Me29n : Release PO
F-47 : Down Payment Request
F-48 : Post Vendor Down Payment
Migo: Goods Receipt Purchase Order
Mmbe: Stocks Overview
Miro : Enter Incoming Invoice
Shift+F12: Display Invoice Document
Mrbr : Release Blocked Invoice
F-54 : Clear Vendor Down Payment
F-536 : Post Outgoing Payments
Fk10n : Vendor Balance Display
Fbl1n : Vendor Line item display
Faglb03: G/L Account Balance display
Fagll03 : G/L Account line item display G/L view

LIST OF G/L ACCOUNT FOR PS

470000: Project Material Consumption


470100: Project External Expenses
470200: Project Services Expenses
470300: Project Miscellaneous
470400: Project TA/DA
354000: Project Liquidated Damage

LIST OF G/L ACCOUNT FOR CURRENT EXPANSES

430000
430200
430300
430500

TA/DA ( In Country)
Rent on Buildings Hired
Rent on Other Properties Hired/ Lease Line Rent
Water Cess/ Sewerage Charges

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

13 | P a g e

430600
430700
430800
430900
431700
431800
431900
432000
432100
202900
203000
203100
203200
203900
204100
204500
205000
450100
450400
450500
450600
450700

Leasehold Rent
Telephone/Fax/Internet
Postage and Courier
Printing and Stationery
Hospitality and Entertainment Expenses
Publicity and Advertisement
Books , Periodicals and Newspapers
Electricity Charges
Misc. Administration and General expenses
Firefighting equipments
Computer and Peripherals
Telecommunication equipments
Office Equipment
Tools and Implements
Computer Software
Vehicles and Transport Equipment
Furniture, Fixture and Fittings
Repair & Maitenance-Services
R & M of Furniture, Fixtures and Fittings
Repair & Maintenance-Office Equipment
Repair & Maintenance-Vehicle Running Expenses (POL)
Repair & Maitenance-Consumables

Choten Tshering, Engineer, 220kV Transmission Project Office, D&CD, BPC, jigmeling, E-mail:choten@bpc.bt,
Contact: +0975-17769435

14 | P a g e