SCOMI RAIL BHD

WZS welding project


Manufacturing estimated cost
Processes (hrs)
No

*
*
*
*
*

Part

Picture

Qty

Bevel

Welding

Total

Main Frame

1 unit

0.5

4.5

Weldment

1 unit

Weldment_4

1 unit

Weldment_5

1 unit

All welding use TIG


Require detail welding information on item1,2&4
1 skilled welder allocated for each part
Welding time is consider fitup, welding sequence and complete welding activity
Jig is required to manufacture this part, otherwise supplied by client

Consumable usage

Remarks

Welding rod - 80 rods


Gas - est RM200

welding hrs based on full weld process


require detail welding information
(full/staged/spot weld)

welding rod - 40 rods


Gas - est RM100

welding hrs based on full weld process


require detail welding information
(full/staged/spot weld)

Welding rod - 16 rods


Gas - est RM50

Welding rod - 30 rods


Gas - est RM50

welding hrs based on full weld process


require detail welding information
(full/staged/spot weld)