Rigid Pavements
surface preparation
surface preparation
plant operations
plant operations
mix transport
mix transport
mix placement
steel placement
compaction
general procedures
fixed form paving
slipform paving
joints
Road Construction
Source: WSDOT
Compiled by: Jurie SK
2 SURFACE PREPARATION
Major Topics on this Page
Before a pavement is actually placed at the
construction site the surface to be paved must be 2.1 Subgrade Preparation for
New Pavements
prepared. Adequate surface preparation is
essential to long-term pavement performance. 2.2 Existing Surface Preparation
Pavements constructed without adequate surface
for Overlays
preparation
may
not
meet
smoothness
specifications, may not bond to the existing 2.3 Summary
pavement (in the case of overlays) or may fail because of inadequate subgrade support.
Surface preparation generally takes one of two forms:
1. Preparing the subgrade and granular base course for new pavement. This can
involve such activities as subgrade stabilization (e.g., with lime, cement or
emulsified asphalt), over-excavation of poor subgrade, applying a prime coat
or compacting the subgrade.
2. Preparing an existing pavement surface for overlay. This can involve such
activities as removing a top layer through milling, applying a leveling course,
applying a tack coat, rubblizing or cracking and seating an underlying rigid
pavement, and replacing localized areas of extreme damage.
Specific actions for each method depend upon the pavement type and purpose,
environmental conditions, subgrade conditions, local experience and specifications.
2.1 Subgrade Preparation for New Pavements
The overall strength and performance of a pavement is dependent not only upon its
design (including both mix design and structural design) but also on the load-bearing
capacity of the subgrade soil. Thus, anything that can be done to increase the loadbearing capacity (or structural support) of the subgrade soil will most likely improve the
pavement load-bearing capacity and thus, pavement strength and performance.
Additionally, greater subgrade structural capacity can result in thinner (but not
excessively thin) and more economical pavement structures. Finally, the finished
subgrade should meet elevations, grades and slopes specified in the contract plans.
This subsection covers:
Repair
Tack coats
Leveling (both by applying a leveling coarse and by milling)
Flexible overlays on rigid pavement
Rigid overlays on flexible pavement
2.2.1 Repair
Generally, pavement overlays are used to restore surface course (both flexible and rigid)
characteristics (such as smoothness, friction and aesthetics) or add structural support to
an existing pavement. However, even a structural overlay needs to be placed on a
structurally sound base. If an existing pavement is cracked or provides inadequate
structural support these defects will often reflect through even the best-constructed
overlay and cause premature pavement failure in the form of cracks and deformations.
To maximize an overlays useful life, failed sections of the existing pavements should be
patched or replaced and existing pavement cracks should be filled.
At most, overlays are designed to add only some structural support; the remaining
structural support must reside in the existing pavement. Therefore, small areas of
localized structural failure in the existing pavement should be repaired or replaced to
provide this structural support (see Figure 7.3). Often, existing pavement failure may be
caused by inadequate subgrade support or poor subgrade drainage. In these cases, the
existing pavement over the failed area should be removed and the subgrade should be
prepared as it would be for a new pavement.
Existing pavement crack repair methods
depend upon the type and severity of
cracks.
Badly
cracked
pavement
sections,
especially those with pattern cracking
(e.g., fatigue cracking) or severe slab
cracks, must be patched or replaced
because these distresses are often
symptoms of more extensive pavement
or subgrade structural failure (TRB,
2000). Existing cracks other than those
symptomatic of structural failure should
be cleaned out (blown out with
pressurized air and/or swept) and filled
with a crack-sealing material when the
Road Construction
Source: WSDOT
Compiled by: Jurie SK
cracks are clean and dry (TRB, 2000). Cracks less than about 10 mm (0.375 inches) in
width may be too narrow for crack-sealing material to enter. These narrow cracks can be
widened with a mechanical router before sealing. If the existing pavement has an
excessive amount of fine cracks but is still structurally adequate, it may be more
economical to apply a general bituminous surface treatment (BST) or slurry seal instead
of filling each individual crack.
In all, pavement repair should be extensive enough to provide an existing pavement with
adequate structural support. Pavement management techniques should provide for
overlays before an existing pavement has lost most or all of its structural support
capability.
2.2.2 Tack Coats
Before overlaying, a tack coat should be placed on an existing pavement to ensure
adequate bonding of the overlay to the existing pavement surface. Proper tack coat
application can be critical to long-term pavement performance.
2.2.3 Leveling
The existing pavement should be made as smooth as possible before being overlaid. It
is difficult to make up elevation differences or smooth out ruts by varying overlay
thickness. For flexible overlays, HMA tends to differentially compact; a rule of thumb is
that conventional mixes will compact approximately 6 mm per 25 mm (0.25 inches per 1
inch) of uncompacted thickness (TRB, 2000). Therefore, before applying the final
surface course the existing pavement is typically leveled by one or both of the following
methods:
1. Applying a leveling course (flexible pavements). The first lift applied to the
existing pavement is used to fill in ruts and make up elevation differences.
The top of this lift, which is relatively smooth, is used as the base for the
wearing course.
2. Milling (flexible pavements). A top layer is milled off the existing pavement to
provide a relatively smooth surface on which to pave. Milling is also
commonly used to remove a distressed surface layer from an existing
pavement.
3. Diamond grinding (rigid pavements). A thin top layer can be milled off of an
existing pavement to smooth out relatively small surface distortions prior to
flexible or rigid overlay.
2.2.3.1 Leveling Course - Flexible Pavements
Road Construction
Source: WSDOT
Compiled by: Jurie SK
Typical Range
Comments
Cut Width
75 mm (3 inches) to
4.5 m (14 feet)
Cut Depth
up to 250 mm
(10 inches) per pass
Production Rate
Typical size.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
Road Construction
Source: WSDOT
Compiled by: Jurie SK
After a pavement has been milled the resulting surface is quite dirty and dusty. The
surface should be cleaned off by sweeping or washing before any overlay is placed
otherwise the dirt and dust will decrease the bond between the new overlay and the
existing pavement (see Figure 7.12 and 7.13). When sweeping, more than one pass is
typically needed to remove all the dirt and dust. If the milled surface is washed, the
pavement must be allowed to dry prior to paving.
Milling also produces a rough, grooved surface, which will increase the existing
pavements surface area when compared to an ungrooved surface. The surface area
increase is dependent on the type, number, condition and spacing of cutting drum teeth
but is typically in the range of 20 to 30 percent, which requires a corresponding increase
in tack coat (20 to 30 percent more) when compared to an unmilled surface (TRB, 2000).
2.2.3.3 Leveling Course vs. Milling
For many situations, milling may be a superior alternative to a leveling course. Leveling
course quantities are difficult to accurately estimate and leveling course thicknesses are
usually small, precluding the use of nuclear gauge density testing. Thus, adequate mix
density is difficult to achieve and measure. In some overlay projects a combination of
milling and leveling course application may be best.
2.2.3.4 Diamond Grinding - Rigid Pavements
Although typically used for rigid pavement surface restoration, diamond grinding can be
used to eliminate relatively small surface distortions in existing rigid pavement prior to
flexible or rigid overlays. Because it roughens the existing rigid pavement surface,
diamond grinding also improves the bond between the existing pavement and the
overlay.
2.2.4 Flexible Overlays on Rigid Pavement
Road Construction
Source: WSDOT
Compiled by: Jurie SK
10
Prevent the slabs or sections from moving by stabilizing the material beneath
them. This involves drilling holes in an unstable PCC slab or section and
injecting an asphaltic or cementitious material to fill any underlying voids.
Typically, this method is only an option for isolated instances of instability. It
does not work well as a general roadway treatment.
Make the flexible structure strong enough to resist cracking. This usually
involves extra granular base layers between the flexible overlay and the
existing rigid pavement or extremely thick flexible layers, both of which are
often not cost effective. Even if these types of preventative measures are
used, they still cannot be guaranteed to prevent reflective cracking.
Crack/break and seat the underlying rigid pavement. This involves breaking
the underlying rigid pavement into relatively small pieces (on the order of
about 0.3 m2 to 0.6 m2 (1 ft2 to 2 ft2) by repeatedly dropping a large weight (see
Figure 7.14). The pieces are then seated by 2 to 3 passes of a large rubber
tired roller. The result is a pavement made of small firmly-seated pieces (see
Figure 7.15). Video 7.2 briefly shows the process.
Rubblize the underlying rigid pavement. This involves reducing the underlying
rigid pavement to rubble. This rubble is then used as a high quality base
course to support the flexible overlay. Rubblizing is typically done with one of
the following two pieces of equipment:
o Resonant pavement breaker (see Figure 7.16 and Video 7.3). This
equipment strikes the rigid pavement at low amplitude with a small plate at
the resonant frequency of the slab (usually about 44 Hz) causing the slab
to break apart (see Figure 7.17) (Roberts et al., 1996). Usually it takes
about 14 to 18 passes for a resonant pavement breaker to rubblize an
entire 3.6 m (12 ft.) lane (NCAT, 2001).
o Multi-head breaker (MHB) (see Figures 7.18, 7.19 and Video 7.4). This
equipment uses a series of independently controlled high amplitude drop
hammers to smash the slab. Typically, there are between 12 and 16
hammers, each weighing between 450 - 680 kg (1000 - 1500 lbs.).
Hammers can be dropped from variable heights (0.3 - 1.5 m (1 - 5 ft.)) to
create impact energies between 2,700 - 16,300 N-m (2,000 - 12,000 ft.lbs.). Hammers cycle at a rate of 30 - 35 impacts per minute. MHBs can
rubblize an entire lane (up to 4 m (13 ft.)) in a single pass (Antigo
Construction, 2001).
Road Construction
Source: WSDOT
Compiled by: Jurie SK
11
Figure 7.14: Drop Hammer Used for Cracking and Figure 7.15: PCC Pavement After Cracking and
Seating PCC
Seating with Drop Hammer
Figure 7.16: Resonant Pavement Breaker Used to Figure 7.17: PCC Pavement After Rubblization With
Rubblize PCC Pavement
a Resonant Pavement Breaker
Road Construction
Source: WSDOT
Compiled by: Jurie SK
A 38-state survey published in 1999 (Ksaibati, Miley and Armaghani, 1999) revealed the
following about rigid pavement rubblizing:
Given the expense of these techniques, some agencies just choose to live with joint
reflection cracking rather than prevent it. This is especially true on low volume, low
speed roads where ride smoothness and structural integrity may not be given the high
priority they are on high volume, high speed roads like interstates.
2.2.5 Rigid Overlays on Flexible Pavement (from ACPA, 2001b)
2.2.5.1 Unbonded Overlays
Unbonded rigid overlays do not require much surface preparation, which is one of the
principal reasons they are used.
2.2.5.2 Bonded Overlays
Bonded rigid overlays of flexible pavement require several additional considerations.
First, the success of a bonded overlay is contingent on a good bond between the rigid
overlay and the underlying flexible pavement. In order to develop this bond, the
underlying flexible pavement must have a clean, rough surface. Preferably, the flexible
pavement should be milled, however, as a minimum, water or abrasive blasting should
be used to clean the HMA surface. If water blasting is used, the surface must be allowed
to air dry before the PCC is placed.
Once the flexible pavement surface is clean, it must be kept clean until the bonded
overlay is placed. Dust, dirt and debris that falls or blows onto the asphalt surface must
be removed. If the surface is cleaned on the day prior to paving, air cleaning may be
required on the day of paving to remove dirt and dust. If traffic is allowed on the milled
surface, the surface must be cleaned again prior to paving.
2.3 Summary
Pavements should be placed only on properly prepared surfaces to ensure they perform
properly. Pavements constructed on inadequately prepared surfaces may be
excessively rough, may not bond to the existing pavement (in the case of overlays) or
may fail because of inadequate subgrade support. For a new pavement, surface
preparation involves compacting, grading and possibly stabilizing the underlying
subgrade. For an overlay, surface preparation involves repairing, leveling and cleaning
the existing pavement.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
13
Road Construction
Source: WSDOT
Compiled by: Jurie SK
14
Road Construction
Source: WSDOT
Compiled by: Jurie SK
15
4 FLEXIBLE - TRANSPORT
Mix transport involves all actions and equipment required to convey HMA from a
production facility to a paving site including truck
loading, weighing and ticketing, hauling to the Major Topics on this Page
paving site, dumping of the mix into the paver or 4.1 Truck Types
material transfer vehicle hopper, and truck return to
4.2 Operational Considerations
the HMA production facility (Roberts et al., 1996).
Ideally, the goal of mix transport should be to 4.3 Summary
maintain mix characteristics between the
production facility and the paving site. Transport practices can have a profound effect on
mix temperature at the paving site, aggregate and/or temperature segregation of the mix
and mat quality. This section will discuss the types of trucks used for mix transport and
the various considerations involved with mix transport.
4.1 Truck Types
There are three basic truck types used for mix transport classified by their respective
HMA discharge methods:
End dump
Bottom dump (or belly dump
Live bottom (or flo-boy)
16
Road Construction
Source: WSDOT
Compiled by: Jurie SK
17
Each truck type is capable of adequately delivering HMA from a production facility to a
paving site. However, certain situations such as the ones listed in Table 7.2 below, may
make one truck type advantageous over another.
Table 7.2: Truck Type Situations
Situation
Road Construction
Source: WSDOT
Compiled by: Jurie SK
18
Bottom Dump
Better
maneuverability
because it has no trailer and
is smaller than a bottom
dump or live bottom truck.
Live bottom trucks deliver the
HMA by conveyor, which
minimizes segregation.
Usually has a larger capacity
than
end
dump
trucks
(therefore fewer trucks are
needed) but requires space
and equipment for windrows.
19
Road Construction
Source: WSDOT
Compiled by: Jurie SK
20
In most cases, truck transport appears to cool only the surface of the transported HMA
mass, however this cool surface crust can have detrimental effects on overall mat quality
if not properly dealt with. Actions such as reducing transport time, insulating truck beds
or tarping trucks can decrease HMA surface cooling rate. Additionally, since the majority
of the HMA mass is still at or near its original temperature at loading, mixing the crust
and interior mass together at the paving site (remixing) will produce a uniform mix near
the original temperature at loading.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
21
Ideally, all operations are designed to meet optimal mat laydown rates. However, these
rates can vary based on paving width and lift thickness. Also, complicated paving
locations such as intersections or near manholes and utility vaults can temporarily
increase or decrease the laydown rate.
Truck transport should be planned such that the HMA transport rate (expressed in
tons/hr) closely matches plant production rate and laydown rate. Some factors to
consider are:
Traffic plays a large role in HMA delivery rates because it affects truck speed. Especially
in congested urban areas, heavy and/or unpredictable traffic may substantially increase,
or at least vary, truck travel time. As truck travel time increases, more trucks are needed
to provide a given HMA delivery rate. Therefore, as traffic gets worse, trucking costs
increase. Additionally, the unpredictability of traffic may result in either long paver idle
Road Construction
Source: WSDOT
Compiled by: Jurie SK
22
times as it waits for the next truckload of HMA or large truck backups as several trucks
all reach the paving site or production facility at the same time.
Finally, production facility output is typically controlled to match haul or laydown rate.
However, this can result in suboptimal plant efficiency or HMA uniformity, which may
increase plant exhaust output, shorten emission control device lifetimes, and affect
contractual payment if payment is tied to HMA uniformity. It may often be more
economical to run the production facility at maximum rate and store excess material in
storage silos for discharge into trucks as they arrive. Storage silo insulation has
progressed to a state where dense-graded HMA can be stored in them for up to a week
at a time without significantly affecting HMA characteristics. However, gap graded mixes
such as SMA or OGFC should still not be stored for more than about 2 to 3 hours.
In sum, synchronization should be the goal but it is often difficult to achieve (based on
varying laydown rates, haul time and traffic) and may result in plant inefficiency and HMA
quality degradation. If a production facility has modern well-insulated, airtight storage
silos and is producing a dense-graded HMA, it may be beneficial to run the plant at
maximum production rate and store the mix until needed rather than try and match haul
or laydown rate.
4.3 Summary
Mix transport can have a large impact on flexible pavement construction quality and
efficiency. Mix characteristics such as laydown temperature, aggregate segregation and
temperature differentials are largely determined by transport practices. In general, there
are three types of HMA transport trucks: the end dump, bottom dump and live bottom
dump (flo boy). End dump trucks are most common, however bottom dumps and live
bottom dumps are well-suited for certain situations. Key considerations in mix transport
are:
If properly managed, mix transport can successfully move HMA from the production
facility to the paving site with little or no change in mix characteristics.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
23
5 FLEXIBLE - PLACEMENT
Mix placement and compaction are the two most Major Topics on this Page
important
elements
in
HMA
pavement 5.1 Placement Considerations
construction.
Mix placement involves any
5.2 Asphalt Paver
equipment or procedures used to place the
delivered HMA on the desired surface at the 5.3 Material Transfer Vehicles
(MTV)
desired thickness. Mix placement can involve
complicated asphalt paver operations or simple 5.4 Summary
manual shoveling. This section provides a basic
description of HMA placement operations. The Hot Mix Asphalt Paving Handbook (TRB,
2000) and the Asphalt Institute's HMA Construction manual (2001) contains detailed
information on asphalt paver components.
5.1 Placement Considerations
There are, of course, many considerations to take into account when placing HMA.
Many are dependent upon local materials, weather, crew knowledge and training, and
individual experience. This subsection presents a few of the basic considerations that
apply in virtually all situations:
Longitudinal joints. The interface between two adjacent and parallel HMA
mats. Improperly constructed longitudinal joints can cause premature
deterioration of multilane HMA pavements in the form of cracking and raveling.
Handwork. HMA can be placed by hand in situations where the paver cannot
place it adequately. This can often occur around utilities, around intersection
corners and in other tight spaces. Hand-placing should be minimized because
it is prone to aggregate segregation and results in a slightly rough surface
Road Construction
Source: WSDOT
Compiled by: Jurie SK
24
25
The tractor contains the material feed system, which accepts the HMA at the front of the
paver, moves it to the rear and spreads it out to the desired width in preparation for
screed leveling and compaction. The basic tractor components are:
Push Roller and Truck Hitch. The push roller is the portion of the paver that
contacts the transport vehicle and the truck hitch holds the transport vehicle in
contact with the paver (see Figures 7.32 and 7.33). They are located on the
front of the hopper.
Hopper. The hopper is used as a temporary storage area for HMA delivered
by the transport vehicle. Therefore, the paver can accept more material than
is immediately needed and can use the volume in the hopper to compensate
for fluctuating material demands created by such things as paving over
irregular grades, utility access openings or irregular intersection shapes.
Hopper sides (or wings) can be tilted up (or folded) to force material to the
middle where it is carried to the rear by the conveyor system (see Figure 7.34).
Hoppers can also be fit with inserts to allow them to carry more HMA (see
Figure 7.35). These inserts are typically used in conjunction with a material
transfer vehicle (MTV).
Road Construction
Source: WSDOT
Compiled by: Jurie SK
26
Conveyor. The conveyor mechanism carries the HMA from the hopper, under
the chassis and engine, then to the augers (see Figure 7.36 and 7.37). The
amount of HMA carried back by the conveyors is regulated by either variable
speed conveyors and augers or flow gates, which can be raised or lowered by
the operator or, more often, by an automatic feed control system.
Auger. The auger receives HMA from the conveyor and spreads it out evenly
over the width to be paved (see Figure 7.38). There is one auger for each side
of the paver and they can be operated independently. Some pavers allow the
augers to be operated in reverse direction so that one can be operated
forward and the other in reverse to send all the received HMA to one side of
the paver. The auger gearbox can either be located in the middle (between
the augers as shown in Figure 7.39) or on the outside edge of each auger. If
an inadequate amount of HMA is distributed under a middle-located gearbox
the result can be a thin longitudinal strip of mat aligned with the gearbox that
exhibits lower densities from aggregate segregation and/or temperature
differentials (see Figures 7.40 and 7.41).
Road Construction
Source: WSDOT
Compiled by: Jurie SK
27
Operation of the tractor, and specifically the material feed system, can have significant
effects on overall construction quality and thus long-term pavement performance.
Although there are many detailed operational concerns, the two broad statements below
encompass most of the detailed concerns:
1. HMA must be delivered to maintain a relatively constant head of material in
front of the screed. This involves maintaining a minimum amount of HMA in
the hopper, regulating HMA feed rate by controlling conveyor/auger speed and
flow gate openings (if present), and maintaining a constant paving speed. As
the next section will discuss, a fluctuating HMA head in front of the screed will
affect the screed angle of attack and produce bumps and waves in the finished
mat.
2. The hopper should never be allowed to empty during paving. This results in
the leftover cold, large aggregate in the hopper sliding onto the conveyor in a
concentrated mass and then being placed on the mat without mixing with any
hot or fine aggregate. This can produce aggregate segregation or temperature
differentials, which will cause isolated low mat densities. If there are no
transport vehicles immediately available to refill the hopper it is better to stop
Road Construction
Source: WSDOT
Compiled by: Jurie SK
28
the paving machine than to continue operating and empty the hopper (TRB,
2000).
5.2.2 Screed
The most critical feature of the paver is the self-leveling screed unit, which determines
the profile of the HMA being placed (Roberts et al., 1996). The screed takes the head of
HMA from the material delivery system, strikes it off at the correct thickness and provides
initial mat compaction. This section describes:
Screed terminology
The basic forces acting on the screed
Screed factors affecting mat thickness and smoothness
Automatic screed control
Screed operation summary
Long beams that attach the screed to the tractor unit (see
5. Tow point. Point at which the screed arm is attached to the tractor unit (see
Figure 7.43).
6. Depth crank. The manual control device used to set screed angle and
ultimately, mat thickness (see Figure 7.42).
7. Screed heater. Heaters used to preheat the screed to HMA temperature.
HMA may stick to a cold screed and cause mat tearing. After the screed has
been in contact with the HMA for a short while (usually about 10 minutes) its
temperature can be maintained by the HMA passing beneath it and the heater
can be turned off. If the screed is removed from contact with HMA for an
extended period of time, it may need to be pre-heated again before resuming
paving.
8. Screed vibrator. Device located within the screed used to increase the
screeds compactive effort. Screed compaction depends upon screed weight,
vibration frequency and vibration amplitude.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
29
30
2. Force from the HMA head resisting the towing force. This is provided by the
HMA in front of the screed and is controlled by the material feed rate and HMA
characteristics.
3. Weight of the screed acting vertically downward. This is obviously controlled
by screed weight.
4. Resistive upward vertical force from the material being compacted under the
screed. This is also a function of HMA characteristics and screed weight.
5. Additional downward force applied by the screeds tamping bars or vibrators.
This is controlled by vibratory amplitude and frequency or tamping bar force.
6. Frictional force between the screed and the HMA under the screed. This is
controlled by HMA and screed characteristics.
5.2.2.3 Factors Affecting Mat Thickness and Smoothness
Since the screed is free floating it will slide across the HMA at an angle and height that
will place these six forces in equilibrium. When any one of these forces is changed, the
screed angle and elevation will change (which will change the mat thickness) to bring
these forces back into equilibrium. Therefore, changing anything on the paver that
affects these forces (such as paver speed, material feed rate or screed tow point) will
affect mat thickness. Furthermore, since mat thickness needs to be closely controlled,
pavers have controls to manually set screed angle rather than rely on a natural
equilibrium to determine mat thickness. In typical paving operations the screed angle is
adjusted to control mat thickness. In order to understand how a manually controlled
screed angle affects mat thickness, a brief discussion of how the paver parameters of
speed, material feed rate and tow point elevation affect screed angle, screed height and
therefore mat thickness is provided.
Speed
Paver speed affects mat thickness by changing the screed angle. If a paver speeds up
and all other forces on the screed remain constant, the screed angle decreases to
restore equilibrium, which decreases mat thickness. Similarly, as paver speed
decreases, screed angle increases, which increases mat thickness.
Material Feed Rate
The amount of HMA in front of the screed (the material head) can also affect screed
angle and thus mat thickness. If the material head increases (either due to an increase
in material feed rate or a reduction in paver speed), screed angle will increase to restore
equilibrium, which increases mat thickness. Similarly, if the material head decreases
(either due to a decrease in material feed rate or an increase in paver speed), screed
angle will decrease to restore equilibrium, which decreases mat thickness (TRB, 2000).
Therefore, in order to maintain a constant mat thickness for a change in paver speed or
material head in front of the screed, the natural equilibrium of forces on the screed
cannot be relied upon and the screed angle must be manually adjusted using a
thickness control screw or depth crank. Screed angle adjustments do not immediately
change mat thickness but rather require a finite amount of time and tow distance to take
effect. Figure 7.47 shows that it typically takes five tow lengths (the length between the
tow point and the screed) after a desired level is input for a screed to arrive at the new
level.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
31
Figure 7.47: Screed Reaction to a Manual Decrease in Screed Angle (after TRB, 2000)
Because of this screed reaction time, a screed operator who constantly adjusts screed
level to produce a desired mat thickness will actually produce an excessively wavy,
unsmooth pavement.
Tow Point Elevation
Finally, tow point elevation will affect screed angle and thus mat thickness. As a rule-ofthumb, a 25 mm (1-inch) movement in tow point elevation translates to about a 3 mm
(0.125 inch) movement in the screed's leading edge. Without automatic screed control,
tow point elevation will change as tractor elevation changes. Tractor elevation typically
changes due to roughness in the surface over which it drives. As the tow point rises in
elevation, the screed angle increases, resulting in a thicker mat. Similarly, as the tow
point lowers in elevation, the screed angle decreases, resulting in a thinner mat.
Locating the screed tow point near the middle of the tractor significantly reduces the
transmission of small elevation changes in the front and rear of the tractor to the screed.
Moreover, because the screed elevation responds slowly to changes in screed angle, the
paver naturally places a thinner mat over high points in the existing surface and a thicker
mat over low points in the existing surface (TRB, 2000).
The interaction of paver speed, material feed rate and tow point elevation determine the
screed position without the need for direct manual input. This is why screeds are
sometimes referred to as "floating" screeds.
5.2.2.4 Automatic Screed Control
As discussed previously, the screed angle can be manipulated manually to control mat
thickness. However, tow point elevation is not practical to manually control. Therefore,
pavers usually operate using an automatic screed control, which controls tow point
elevation using a reference other than the tractor body. Since these references assist in
controlling HMA pavement grade, they are called grade reference systems and are
listed below (Roberts et al., 1996):
Road Construction
Source: WSDOT
Compiled by: Jurie SK
32
Road Construction
Source: WSDOT
Compiled by: Jurie SK
33
In addition to grade control, the screed can also be set to control pavement slope and/or
crown. A slope controller uses a slope sensor mounted on a transverse beam attached
to the screed to determine screed slope, then adjusts screed slope to the desired
amount. Generally, one side of the screed is set up to control grade and the opposite
side is set up to control slope based on that grade. The usual practice is to run grade
control on the side of the screed nearest the pavement centerline and run slope control
on the screed side nearest the pavement edge because it is easier to match the
centerline joint if grade control is used on that side of the paver (TRB, 2000).
Screed crown (the elevation of the middle in relation to the edges) can also be
controlled. Typically screeds offer separate front and rear crown controls. If crown
control is used, the front control is usually set to a slightly more severe crown than the
rear control to allow for easier passage of HMA under the screed.
5.2.2.5 Screed Operation Summary
The floating screeds used by todays pavers are acted upon by six basic forces, which
when left undisturbed result in an equilibrium screed angle and elevation that determines
mat thickness. Adjusting paver speed, material feed rate or tow point elevation will
change these forces and result in a new equilibrium screed angle and elevation and
eventually a new mat thickness. In order to achieve the most consistent thickness and
smoothest possible surface, pavers attempt to maintain a constant speed, use automatic
feed controls to maintain a consistent head of material in front of the paver, and use
automatic screed control to maintain a consistent tow point. Although the screed angle
can be adjusted manually to change mat thickness, excessive adjustments will result in a
wavy, unsmooth mat. In addition to grade, screeds can also control mat slope and crown
to provide almost complete control over mat elevation at any location.
5.3 Material Transfer Vehicles (MTVs)
Material transfer vehicles (MTVs) are used to assist the paver in accepting HMA. Most
pavers are equipped to receive HMA directly from end dump or live bottom trucks,
however in certain situations it can be necessary or advantageous to use an MTV.
Paving using bottom dump trucks and windrows requires a windrow elevator MTV (see
Figure 7.49 and 7.50), while other MTVs are used to provide additional surge volume,
which is advantageous because it allows the paver to operate continuously without
stopping, minimizes truck waiting time at the paving site and may minimize aggregate
segregation and temperature differentials. This subsection covers:
Windrow elevators
Surge volume and remixing MTVs
34
operations typically have some method (e.g., a loader) available to add or subtract
material from the windrow. Some windrow paving operations establish a windrow
laydown rate slightly less than the paver laydown rate then periodically add material to
the windrow with an end dump truck. Other windrow paving operations leave periodic
spaces in the windrow to control avoid paver overloading.
Other MTVs are used to provide an additional surge volume for the paver (see Figures
7.51 through 7.54). This surge volume allows for continuous paver operations because
with an MTV the paver no longer has to stop while one truck leaves and the next truck
backs up. Additionally, the MTV serves as a buffer between the paver and the haul
trucks, which eliminates most truck bumping problems. Finally, most MTVs offer some
sort of remixing capability that remixes the cool HMA crust formed during transport with
the hot interior HMA to produce a more uniform mix entering the paver. This remixing
can essentially eliminate aggregate segregation and temperature differentials. Some states
have actually implemented specifications that require a remixing MTV for paving
contracts where segregation and temperature differentials are of concern.
5.3.2 Surge Volume and Remixing MTVs
Surge volume / remixing MTVs are typically used in tandem with a paver hopper insert
that increases the capacity of the paver hopper (see Figure 7.35). The insert is
removable and sometimes contains remixing apparatus (such as a pugmill) near the
bottom. At least one manufacturer has developed a paver solely for use with an MTV.
The Roadtec Stealth paver uses gravity feed and does not contain conveyors, hopper
wings or push rollers, which reduces initial cost as well as maintenance costs (Roadtec,
2001).
Road Construction
Source: WSDOT
Compiled by: Jurie SK
35
36
Remixing Auger
In summary, MTVs assist with the transfer of HMA from the transport trucks to the paver.
There are two basic types of MTVs: windrow elevator MTVs and surge volume / remix
MTVs. Windrow elevator MTVs are used to pick up HMA from a windrow and place it
into the paver hopper while surge volume / remix MTVs provide an additional material
surge volume that allows for continuous paving and/or a remix capability that can reduce
aggregate/temperature segregation. MTV use costs money and will increase the per ton
cost of HMA paving but can help provide superior mat quality. However, MTVs should
not be used as a substitute for good production and laydown practices, which are
fundamental to good mat quality.
5.4 Summary
Mix placement is one of the most important elements in HMA pavement construction.
The key piece of equipment in mix placement, the asphalt paver, consists of two major
systems: the tractor system and the screed system. Proper operation of these systems
results in an independent machine that is capable of placing a smooth, continuous HMA
pavement. MTVs can be used to augment mix transfer to the asphalt paver. Proper
employment of MTVs can increase laydown rates, streamline mix transfer and help
reduce segregation problems.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
37
6 FLEXIBLE - COMPACTION
It has been said that the top three factors in real
estate are location, location, location. It can also Major Topics on this Page
be said that the top three factors in HMA pavement 6.1 Compaction
Measurement
construction
are
compaction,
compaction,
and Reporting
compaction. Compaction is the process by which
the volume of air in an HMA mixture is reduced by 6.2 Compaction Importance
using external forces to reorient the constituent 6.3 Factors Affecting Compaction
aggregate particles into a more closely spaced
6.4 Compaction Equipment
arrangement. This reduction of air volume in a
mixture produces a corresponding increase in 6.5 Roller Variables
HMA unit weight, or density (Roberts et al., 1996). 6.6 Summary
Numerous
researchers
have
stated
that
compaction is the greatest determining factor in dense graded pavement performance
(Scherocman and Martenson, 1984; Scherocman, 1984; Geller, 1984; Brown, 1984; Bell
et. al., 1984; Hughes, 1984; Hughes, 1989). Inadequate compaction results in a
pavement with decreased stiffness, reduced fatigue life, accelerated aging/decreased
durability, rutting, raveling, and moisture damage (Hughes, 1984; Hughes, 1989).
6.1 Compaction Measurement and Reporting
Compaction reduces the volume of air in HMA. Therefore, the characteristic of concern
is the volume of air within the compacted pavement. This volume is typically quantified
as a percentage of air voids by volume and expressed as percent air voids. Percent air
voids is calculated by comparing a test specimens bulk density with its theoretical
maximum density (TMD) and assuming the difference is due to air. Once TMD is known,
portable devices can be used to measure HMA density in-place. The terms percent air
voids and density are often used interchangeably. Although this is not wrong, since
density is used to calculate percent air voids, the fundamental parameter of concern is
always percent air voids.
Percent air voids is typically calculated by using AASHTO T 269, ASTM D 3203 or an
equivalent procedure (AASHTO, 2000). These procedures all use laboratory-determined
bulk specific gravity and theoretical maximum specific gravity in the following equation:
G Gmb
where:
Gmm
Road Construction
Source: WSDOT
Compiled by: Jurie SK
38
Gmb
These procedures require a small pavement core (usually 100 - 150 mm (4 - 6 inches) in
diameter), which is extracted from the compacted HMA (see Figure 7.56 and 7.57). This
type of air voids testing is generally considered the most accurate but is also the most
time consuming and expensive.
Since core extraction is time consuming and expensive, air voids are often measured
indirectly using a portable density-measuring device such as a nuclear density gauge
(see Figure 7.58) or electrical density gauge (see Figure 7.59).
Each contracting agency usually specifies the compaction measurement methods and
equipment to be used on contracts under their jurisdiction. Most agencies stipulate
some sort of extracted core density testing and usually allow testing by nuclear gauge.
Electric density gauges are relatively new on the market (in the last five years).
Accurate calibration of these devices is essential for their proper use.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
39
Although percent air voids is the HMA characteristic of interest, measurements are
usually reported as a measured density in relation to a reference density. This is done
by reporting density as a (1) percent of TMD (sometimes called Rice density), (2) percent
of a laboratory density or (3) percent of a control strip density (a control strip is a short
pavement strip that is compacted to the desired value under close scrutiny then used as
the compaction standard for a particular job).
In sum, percent air voids is the critical HMA characteristic with which compaction is
concerned. It can be measured using pavement cores or portable nuclear or electric
gauges; measurement specifications vary from one contracting agency to the next.
Percent air voids is usually reported as a density in one of three forms: (1) percent TMD,
(2) percent of laboratory density or (3) percent of control strip density. Regardless of the
measurement device or reporting method, the key characteristic is percent air voids.
6.2 Compaction Importance
The volume of air in an HMA pavement is important because it has a profound effect on
long-term pavement performance. An approximate "rule-of-thumb" is for every 1 percent
increase in air voids (above 6-7 percent), about 10 percent of the pavement life may be
lost (Linden et al., 1989). Keep in mind that this rule-of-thumb was developed using
limited project data, should be used with extreme caution and applies to air voids above
6 - 7 percent. According to Roberts et al. (1996), there is considerable evidence that
dense graded mixes should not exceed 8 percent nor fall below 3 percent air voids
during their service life. This is because high air void content (above 8 percent) or low
air void content (below 3 percent) can cause the following pavement distresses (this list
applies to dense-graded HMA and not open-graded HMA or SMA):
1. Decreased stiffness and strength. Kennedy et al. (1984) concluded that
tensile strength, static and resilient moduli, and stability are reduced at high air
void content.
2. Reduced Fatigue Life. Several researchers have reported the relationship
between increased air voids and reduced fatigue life (Pell and Taylor, 1969;
Epps and Monismith, 1969; Linden et. al., 1989). Finn et al. (1973) concluded
...fatigue properties can be reduced by 30 to 40 percent for each one percent
increase in air void content. Another study concluded that a reduction in air
voids from eight percent to three percent could more than double pavement
fatigue life (Scherocman, 1984a).
3. Accelerated Aging/Decreased Durability. In his Highway Research Board
paper, McLeod (1967) concluded compacting a well-designed paving mixture
to low air voids retards the rate of hardening of the asphalt binder, and results
in longer pavement life, lower pavement maintenance, and better all-around
pavement performance.
4. Raveling. Kandhal and Koehler (1984) found that raveling becomes a
significant problem above about eight percent air voids and becomes a severe
problem above approximately 15 percent air voids.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
40
Environmental Factors
Temperature
Ground temperature
Air temperature
Wind speed
Solar flux
Construction Factors
Rollers
Type
Number
Speed and timing
Number of passes
Lift thickness
Other
HMA production
temperature
Haul distance
Haul time
Foundation support
Environmental factors are determined by when and where paving occurs. Paving
operations may have some float time, which allows a limited choice of when but paving
location is determined by road location so there is essentially no choice of where. Mix
and structural design factors are determined before construction and although they
Road Construction
Source: WSDOT
Compiled by: Jurie SK
41
should account for construction practices and the anticipated environment, they often
must compromise ease of construction and compaction to achieve design objectives.
Obviously construction factors are the most controllable and adaptable of all the factors
affecting compaction. Although some factors like haul distance/time, HMA production
temperature, lift thickness and type/number of rollers may be somewhat predetermined,
other factors associated with roller timing, speed, pattern and number of passes can be
manipulated as necessary to produce an adequately compacted mat. This subsection
discusses:
Section 6.4, Compaction Equipment and 6.5, Roller Variables discuss construction
factors.
6.3.1 Temperature
HMA temperature has a direct effect on the viscosity of the asphalt cement binder and
thus compaction. As HMA temperature decreases, its asphalt cement binder becomes
more viscous and resistant to deformation, which results in a smaller reduction in air
voids for a given compactive effort. As the mix cools, the asphalt binder eventually
becomes stiff enough to effectively prevent any further reduction in air voids regardless
of the applied compactive effort. The temperature at which this occurs, commonly
referred to as cessation temperature, is a function of the mix property factors in Table
7.4. In some literature it is reported to be about 79oC (175F) for dense-graded HMA
(Scherocman, 1984b; Hughes, 1989). Below cessation temperature rollers can still be
operated on the mat to improve smoothness and surface texture but further compaction
will generally not occur. Conversely, if the binder is too fluid and the aggregate structure
is weak (e.g., at high temperatures), roller loads will simply displace, or shove the mat
rather than compact it. In general, the combination of asphalt cement binder and
aggregate needs to be viscous enough to allow compaction but stiff enough to prevent
excessive shoving.
Mat temperature then, is crucial to both the actual amount of air void reduction for a
given compactive effort, and the overall time available for compaction. If the initial
temperature and cool-down rate are known, the temperature of the mat at any time after
laydown can be calculated. Based on this calculation rolling equipment and patterns can
be employed to:
1. Take maximum advantage of available roller compactive effort. Rollers can be
used where the mat is most receptive to compaction and avoided where the
mat is susceptible to excessive shoving.
2. Ensure the mat is compacted to the desired air void content before cessation
temperature is reached. This can be done by calculating the time it takes the
mat to cool from initial temperature to cessation temperature. All compaction
must be accomplished within this time available for compaction.
The major factors affecting time available for compaction are (Roberts et al., 1996):
Road Construction
Source: WSDOT
Compiled by: Jurie SK
42
Initial mat temperature. Higher initial mat temperatures require more time to
cool down to cessation temperature, thus increasing the time available for
compaction. However, overheating the HMA will damage the asphalt binder
and cause emissions.
Mat or lift thickness. Thicker lifts have a smaller surface-to-volume ratio and
thus lose heat more slowly, which increases the time available for compaction.
Temperature of the surface on which the mat is placed. Hotter surfaces will
remove heat from the mat at a slower rate, increasing the time available for
compaction.
Ambient temperature. Hotter air temperatures will remove heat from the mat
at a slower rate, increasing the time available for compaction.
Wind speed. Lower wind speeds will decrease mat heat loss by convection,
which will increase the time available for compaction.
Jordan and Thomas (1976) point out additional factors affecting mat cool-down rate that
include mat density, pavement layer thermal conductivity, specific heat, convection
coefficient, incident solar radiation and coefficients of emission and absorption of solar
radiation for the pavement surface.
Table 7.5 is a sampling of MultiCool output for some representative values of pavement
thickness and ambient temperature.
Table 7.5: Sample MultiCool Calculations
Mat Thickness
Base Temperature
Mix Temperature
Approximate Time
to Cool to
79 C (175 F)
25 mm
(1 inch)
25 mm
(1 inch)
50 mm
(2 inches)
50 mm
(2 inches)
149 C
(300 F)
149 C
(300 F)
121 C
(250 F)
121 C
(250 F)
16 C
(60 F)
-4 C
(25 F)
16 C
(60 F)
-4 C
(25 F)
105 mm
(4.2 inches)
121 C
(250 F)
16 C
(60 F)
54 minutes
105 mm
(4.2 inches)
121 C
(250 F)
-4 C
(25 F)
39 minutes
9 minutes
7 minutes
16 minutes
12 minutes
Road Construction
Source: WSDOT
Compiled by: Jurie SK
4.
5.
6.
7.
8.
9.
MultiCool is quick and powerful. It can easily be installed on a laptop and used by
contractors or inspectors to give a general idea of the time available for compaction
on a given job site, which can be quite helpful in determining roller use and patterns.
Figure 7.60 relates HMA temperature with typical aspects of compaction.
HMA temperature affects its binder viscosity, which affects compaction in two ways: (1)
the colder and more viscous the binder, the less actual amount of air void reduction for a
given compactive effort, and (2) HMA can only be compacted until it reaches cessation
temperature, therefore initial HMA temperature and mat cool-down rate establish a
fundamental compaction parameter the overall time available for compaction. Many
factors influence HMA temperature and cool-down rate including initial mat temperature,
mat thickness, temperature of the surface on which the mat is placed, ambient
temperature and wind speed. Using these factors as inputs, MultiCool, a program
developed at the University of Minnesota, can easily produce a mat cool-down curve and
calculate the time available for compaction.
6.3.2 Mix Properties
Mix aggregate and binder properties can also affect compaction. They do so by affecting
(1) the ease with which aggregate will rearrange under roller loads and (2) the viscosity
of the binder at any given temperature.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
44
Gradation affects the way aggregate interlocks and thus the ease with which aggregate
can be rearranged under roller loads. In general, aggregate effects on compaction can
be broken down by aggregate size (TRB, 2000):
1. Coarse aggregate. Surface texture, particle shape and the number of
fractured faces can affect compaction. Rough surface textures, cubical or
block shaped aggregate (as opposed to round aggregate) and highly angular
particles (high percentage of fractured faces) will all increase the required
compactive effort to achieve a specific density.
2. Midsize fine aggregate (between the 0.60 and 0.30-mm (No. 30 and No. 50)
sieves). High amounts of midsize fine, rounded aggregate (natural sand)
cause a mix to displace laterally or shove under roller loads. This occurs
because the excess midsize fine, rounded aggregate results in a mix with
insufficient voids in the mineral aggregate (VMA). This gives only a small void
volume available for the asphalt cement to fill. Therefore, if the binder content
is just a bit high it completely fills the voids and the excess serves to (1) resist
compaction by forcing the aggregate apart and (2) lubricate the aggregate
making it easy for the mix to laterally displace.
3. Fines or dust (aggregate passing the 0.075-mm (No. 200) sieve). Generally,
a mix with a high fines content will be more difficult to compact than a mix with
a low fines content.
The asphalt binder grade affects compaction through its viscosity. A binder that is higher
in viscosity will generally result in a mix that is more resistant to compaction.
Additionally, the more a binder hardens (or ages) during production, the more resistant
the mix is to compaction.
Asphalt binder content also affects compaction. Asphalt binder lubricates the aggregate
during compaction and therefore, mixes with low asphalt content are generally difficult to
compact because of inadequate lubrication, whereas mixes with high asphalt content will
compact easily but may shove under roller loads (TRB, 2000).
Sometimes, a combination of mix design factors produces what is known as a tender
mix. Tender mixes are internally unstable mixes that tend to displace laterally and shove
rather than compact under roller loads.
6.4 Compaction Equipment
There are three basic pieces of equipment available for HMA compaction: (1) the paver
screed, (2) the steel wheeled roller and (3) the pneumatic tire roller. Each piece of
equipment compacts the HMA by two principal means:
1. By applying its weight to the HMA surface and compressing the material
underneath the ground contact area. Since this compression will be greater
for longer periods of contact, lower equipment speeds will produce more
compression.
Obviously, higher equipment weight will also increase
compression.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
45
Road Construction
Source: WSDOT
Compiled by: Jurie SK
46
In addition to their own weight, some steel wheel rollers can be ballasted with either
sand or water to increase their weight and thus, compactive effort. Although this
ballasting is a fairly simple process (see Figure 7.63), it is usually done before rolling
operations start and rarely during rolling operations. Since asphalt cement binder sticks
to steel wheels, most steel wheel rollers spray water on the drums to prevent HMA from
sticking, and are equipped with a transverse bar on each drum to wipe off HMA (see
Video 7.10). Note, however, that this water will cool the HMA and can reduce the time
available for compaction.
Parameter
Typical Values
Frequency
Amplitude
The ideal vibratory frequency and amplitude settings are a compromise based on
desired mat smoothness, HMA characteristics and lift thickness. Low vibration
frequencies combined with high roller speeds will increase the distance between surface
Road Construction
Source: WSDOT
Compiled by: Jurie SK
47
impacts and create a rippled, unsmooth surface. In general, higher frequencies and
lower roller speeds are preferred because they decrease the distance between surface
impacts, which (1) increases the compactive effort (more impacts per unit of length) and
(2) provides a smoother mat. The recommended impact spacing is 3 - 4 impacts per
meter (10 - 12 impacts per foot). Table 7.7 shows basic guidance for vibratory settings.
Frequency
Amplitude
Thin Lifts
(< about 30mm (1.25
inches))
Low amplitude
Lifts
beyond
(2.5 inches)
High frequency
Higher amplitude
High frequency
Higher amplitude
65
mm
Road Construction
Source: WSDOT
Compiled by: Jurie SK
48
In general, steel wheel rollers provide the smoothest mat finish of all compaction
equipment. When operated in the vibratory mode, they also provide substantial
compactive effort.
6.4.3 Pneumatic Tire Rollers
The pneumatic tire roller is a self-propelled compaction device that uses pneumatic tires
to compact the underlying HMA. Pneumatic tire rollers employ a set of smooth (no
tread) tires on each axle; typically four on one axle and five on the other. The tires on
the front axle are aligned with the gaps between tires on the rear axel to give complete
and uniform compaction coverage over the width of the roller. Compactive effort is
controlled by varying tire pressure, which is typically set between 400 kPa (60 psi) and
800 kPa (120 psi) (TRB, 2000).
Asphalt binder tends to stick to cold pneumatic tires but not to hot pneumatic tires. A
release agent (like water) can be used to minimize this sticking, however if asphalt
binder pickup (the asphalt binder sticking to the tires) is not permanently damaging the
mat it is better to run the roller on the hot mat and let the tires heat up to near mat
temperature. Tires near mat temperature will not pick up an appreciable amount of
asphalt binder. Insulating the tire area with rubber matting or plywood helps maintain the
tires near mat temperature while rolling (see Figure 7.64).
Figure 7.64: Pneumatic Tire Roller (notice rubber matting insulation around tire area as well as
tire marks left in the new mat in front of the roller)
In addition to a static compressive force, pneumatic tire rollers also develop a kneading
action between the tires that tends to realign aggregate within the HMA. This results in
both advantages and disadvantages when compared to steel wheel rollers:
Advantages (Brown, 1984)
1. They provide a more uniform degree of compaction than steel wheel rollers.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
49
Not all these variables are infinitely adjustable, but by adjusting a combination of them a
rolling plan can be developed that will optimize mat compaction.
6.5.1 Compaction Sequence
HMA compaction is typically accomplished by a sequential train of compaction
equipment (see Figure 7.65). This allows each piece of equipment to be used only in its
most advantageous situation resulting in a higher quality mat (both in density and in
smoothness) than could be produced with just a single method of compaction.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
50
51
mat. For instance, a mat compacted to eight percent air voids and then
opened to heavy traffic (e.g., an interstate freeway) may further compact to
about three to five percent air voids in the wheelpaths over time.
Each position in the roller train (breakdown, intermediate and finish) may be performed
by one roller or several rollers in parallel. For instance, a large paving project may use
two vibratory steel wheel rollers for breakdown rolling, one pneumatic tire roller for
intermediate rolling and two static steel wheel rollers for finish rolling. The determination
of the best rolling sequence and the number of rollers is generally made on a case by
case basis and depends upon the desired final air voids, available rollers and their
operating parameters, rolling patterns, mix properties, and environmental conditions.
6.5.2 Roller Speed
Rollers are slow; for the fastest, operating speeds may reach about 11 km/h (7 mph). In
order to provide complete and uniform mat compaction, rollers should be operated at a
slow, constant speed. Operating at high speeds will reduce compactive effort while
varying roller speed can cause non-uniform compaction. Table 7.8 shows typical roller
speeds.
Type of Roller
Breakdown
3.2 5.6 km/h
Static Steel Wheel
(2.0 3.5 mph)
3.2 5.6 km/h
Pneumatic
(2.0 3.5 mph)
Vibratory
Steel 3.2 4.8 km/h
Wheel
(2.0 3.0 mph)
Intermediate
Finish
5.6km/h
(2.5 3.5 mph)
As mentioned previously, roller compactive effort comes in two forms: (1) material
compression under the ground contact area and (2) shear stress between the
compressed area and adjacent uncompressed areas. Operating at lower speeds allows
the roller to remain in contact with a particular mat location longer than it would at higher
speeds. This results in more compression per roller pass and therefore increases
compactive effort. Speed also affects the magnitude of shear stress developed. Lower
speeds result in the shearing force between compressed and uncompressed areas
being applied for a longer period of time for a particular area (giving a lower shear rate),
which results in a higher shear stress. The higher the shear stress, the better able it is to
rearrange aggregate into a denser configuration. Therefore, as roller speed decreases,
shear stress increases and compactive effort increases.
Because speed affects compactive effort, varying roller speed will vary compactive effort
resulting in uneven compaction. Varying roller speed typically occurs when operators
are not closely monitoring their speed or when they speed up to roll an area more quickly
Road Construction
Source: WSDOT
Compiled by: Jurie SK
52
so that they can catch up to the paver. If the mat is being laid down at a faster rate than
it can be rolled, the solution should not be to speed up the rollers but rather should
involve one of the following options (TRB, 2000):
1. Slow down the paver.
delivery rate as well.
2. Use more rollers. Adding rollers can increase the number of roller passes in a
given time without reducing the compactive effort per pass.
3. Use larger, wider rollers. Wider rollers allow greater coverage per pass.
Finally, rollers should not be stopped on a fresh mat because they can cause large
indentations that are difficult, if not impossible, to remove.
Roller speed directly affects compactive effort. The best compactive effort and most
uniform densities are achieved by slow, consistent roller speeds. If rollers cannot keep
up with the pace of the paving operation, they should not be operated at higher speeds
because this reduces compactive effort. Rather, the paving operation should be slowed
or more/larger rollers should be used.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
53
Supporting Data:
(1998).
Figure 7.66: Density and Measured Mat Temperature vs. Time (note the increase in density for
each roller pass). From Chadbourn et al., 1998.
Test Strip
Contractors will often (and are sometimes required to) construct a test strip to help
determine the necessary number of passes. A test strip is a small section of mat laid out
at the beginning of a project with the purpose of determining the best roller type,
sequence, number of passes and rolling pattern to use.
54
breakdown roller(s) should operate as close to the paver as possible to achieve the most
compaction per roller pass. Likewise, the intermediate roller(s) and finish roller(s) should
be placed on the mat at a safe distance from the roller in front of them and begin rolling
as soon as possible. Sometimes when a tender mix is placed, these general rules do
not apply.
6.5.5 Roller Pattern
The roller pattern combines roller sequence, speed, number of passes and location to
provide complete coverage of the entire mat in such a manner that results in (1) uniform
compaction to a specified level of air voids, (2) acceptable surface smoothness and (3)
complete compaction before cessation temperature is reached.
Uniform compaction depends on getting the same number of roller passes over each
area of the mat. This means that a pattern must be developed that covers the entire mat
with an equal number of roller passes from each type of roller. For example, if two
vibratory steel wheel rollers are operating as the breakdown rollers they must work
together so each portion of the mat receives the same number of passes, but since they
are the same type of roller it is not necessary for each roller to cover the entire mat. If
two different rollers such as a vibratory steel wheel roller and a pneumatic tire roller are
performing breakdown rolling, each roller should cover the entire mat an equal number
of times, otherwise compaction may be non-uniform. Although roller patterns can vary
widely, some general rules-of-thumb are:
Road Construction
Source: WSDOT
Compiled by: Jurie SK
55
mat and only overlap the older mat by about 0.15 m (0.5 ft.) (Roberts et al.,
1996; Ingersoll-Rand, 2001).
Joints should be compacted with the roller operating parallel to the joint.
Although transverse joints cannot always be compacted this way,
perpendicular rolling does not compact the hot/new side as well.
For steel wheeled rollers, operate the powered wheel on the paver side. This
will minimize humps that can be caused by the drive wheel.
The above thumb-rules are just general guidance; other methods may work. However,
without a clear roller pattern, the center of a lane typically receives more roller passes
than the outsides. This is of particular concern because most wheel loads occur nearer
the edges of any particular lane in the wheelpaths. In summary, any method that
achieves uniform coverage, acceptable density and acceptable smoothness without
damaging the mat can be considered a good method.
6.6 Summary
Although compaction looks like a simple job, it is far from it. Variables such as
sequence, speed, number of passes, location, pattern and mat temperature make it quite
complex. All these variables have a profound effect on air voids and thus pavement
performance. Simply put, good compaction is essential to quality pavement.
56
dry batched into a concrete mixing truck then blended in the truck either at the batching
plant or in route to the job site. Central mixed PCC is batched and mixed in a central
facility and then loaded into a truck for transport to the job site. Shrink mixed PCC is
partially mixed in a plant mixer and then discharged into a truck mixer where the mixing
is completed. This section provides a brief overview of truck, central and shrink mixing.
More detailed information on plant operations can be found in:
Figure 7.67: Typical Charging Order for Truck Mixed PCC (redrawn from ACPA, 1995)
Truck mixed PCC (see figure 7.68) is appropriate for all types of pavement construction,
but is particularly well-suited for instances that can take advantage of a concrete mixing
truck's monitored, continuously agitated storage volume (the mixing drum) and its ability
to precisely deliver PCC through its chute (see Figure 7.69). These situations might
include: intersection paving, street paving, pavement repair, urban environments, high
traffic areas and staged/phased construction. Disadvantages of truck mixed PCC are
longer load and unload times (due to the nature and opening size of the mixing drum)
and the higher operating cost of a concrete mixing truck when compared to an end or
bottom dump truck. Truck mixer specifics are covered in Section 8, Mix Transport.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
57
Road Construction
Source: WSDOT
Compiled by: Jurie SK
58
59
Road Construction
Source: WSDOT
Compiled by: Jurie SK
60
8 RIGID - TRANSPORT
Mix transport involves all actions and equipment required to convey PCC from a
batching facility to a paving site including truck Major Topics on this Page
loading, weighing and ticketing, hauling to the
paving site, mixing (if required), agitation, placing, 8.1 Truck Types
truck washing and truck return to the batching 8.2 Operational Considerations
facility. The goal of mix transport is to delivery
PCC to the paving job site that conforms to the 8.3 Summary
specified mix design. Transport practices can affect such mix characteristics as (1)
homogeneity, (2) workability, (3) water content and (4) air content. This section will
discuss the types of trucks used for mix transport and the various considerations
involved with mix transport.
8.1 Truck Types
There are two basic truck types used for mix transport:
Truck mixer. Truck mixers, use a truck-mounted rotating drum that is capable
of mixing (if necessary) and agitating the ready mixed PCC.
Non-agitating truck. Non-agitating trucks are not able to mix or agitate their
payload and usually consist of end dump, bottom dump or side-dump trucks.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
61
Drum rotation (see Video 7.12) is used for two purposes: mixing and agitation. High
speed rotation (on the order of 12 - 15 rpm) is used to mix PCC ingredients into a
homogenous material. This type of mixing typically takes between 50 and 100
revolutions depending upon PCC characteristics and environmental factors. After this
period of mixing, the PCC is usually required to meet at least 5 of the 6 homogeneity
specifications listed in Table 7.9. Samples for these specifications should be taken from
widely separated portions but should also come from the middle 15 - 85 percent of the
load so as not to be influenced by beginning and end of load abnormalities.
Table 7.9: Ready-Mix Concrete Homogeneity Test Requirements from AASHTO M 157 and ASTM C
94
Parameter
Maximum Permissible
Difference in Results of Tests
Taken from Two Locations in
the PCC Batch
Metric
English
16 kg/m3
1 lb/ft3
Air content
1.0 %
1.0 %
25 mm
1.0 inch
38 mm
1.5 inches
6.0 %
6.0 %
1.6 %
1.6 %
7.5 %
7.5 %
Slump
Road Construction
Source: WSDOT
Compiled by: Jurie SK
62
Low speed rotation (about 2 rpm) is used to agitate the PCC to (1) maintain its
homogeneity and (2) prevent slump loss while in transit. Truck mixers are equipped with
a revolution counter to help maintain tight control over the total number of drum
revolutions. Mixing, which is generally short in duration, is usually planned for a specific
time or place. If not mixing, truck mixers usually operate in the low speed agitation
mode. Mixing is typically done using one of the following three methods (NRMCA,
2002):
Mixing at the batching facility. The drum is turned at high speed (12 - 15 rpm)
for about 50 revolutions while at the production facility, which allows for a quick
check of batch characteristics. The PCC is then agitated (< 2 rpm) while in
transit to the paving site.
Mixing in transit. The drum is turned at medium speed (about 8 rpm) for 70
revolutions while driving to the job site. The PCC is agitated (< 2 rpm) until
discharge.
Mixing at the paving site. The PCC is agitated (< 2 rpm) while in transit to the
paving site. Upon arrival, the PCC is mixed (12 - 15 rpm) for 70 to 100
revolutions, or about five minutes.
In general, short times between mixing and placement can better avoid the problems of
premature hardening and slump loss that result from potential delays in transit.
Regardless of the mixing mode, PCC is a perishable construction material. First, if it
begins to set before being placed and consolidated it is of little use. Second, if it is
mixed and agitated excessively it can loose its air entrainment or the effects of certain
admixtures can diminish. Therefore, a typical specification will require that ready mixed
PCC delivered to the paving site meet the following criteria:
A minimum time (often 1 to 2 hours) between the time at which when the
mixing water was introduced to the portland cement and aggregates and
discharge at the site.
A maximum number of revolutions (typically around 300) between the time at
which when the mixing water was introduced to the portland cement and
aggregates and discharge at the site.
Quick Loading and discharge. Unlike truck mixers, which have a relatively
small loading hopper and discharge chute, the loading and discharge areas for
a dump truck are quite large.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
63
Quick cycle times. Because of their quicker loading and unloading times,
dump truck cycle times are shorter than mixing truck cycle times, thus
requiring fewer trucks to maintain a particular delivery rate.
Lower maintenance/cost. Fewer moving parts and greater accessibility make
dump trucks less expensive to maintain and use than truck mixers.
Because they are not designed to transport PCC, dump trucks also have some severe
disadvantages, which limit their use:
No mixing/agitating ability. Dump trucks can only be used with central mixed
PCC. Further, the lack of agitation over long haul distances may allow
segregate and excessive slump loss.
No integral cover. Although most dump trucks can be covered with a tarp, the
tarp is not integral to the bed and usually allows some water into the bed.
Thus, when operating in the rain, rainwater can unintentionally increase the
water-cement ratio of the transported PCC. Additionally, hot weather may
cause excessive water evaporation, which can also change the water-cement
ratio.
Limited placing ability. Dump trucks can only place PCC at their discharge
point. They are not practical on small jobs (such as sidewalks) nor can they
place material in confined areas.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
64
At the production facility after loading (called "wash off"). Applicable to mixing
trucks, the driver should "wash off" the back of the mixer to prevent buildup of
materials. The driver must take care to minimize water entry into the drum.
Generally, a consistent amount of water (such as 20 liters or 5 gallons) is used
to wash off the back hopper and fins because this water will run off into the
drum. If the volume is known, it can be counted as part of the mixing water.
After unloading at the paving site (called "wash down"). Applicable to mixing
trucks, the chute and discharge hopper should be washed to prevent buildup
of materials. Wash down locations need to be determined in advance
because wash water should not be discharged into catch basins, road ditches
or environmentally sensitive areas. PCC left in the drum after discharge can
be either washed out or recycled.
At the production facility at the end of the day (called "washout"). The
drum/bed should be washed out at the end of the day to prevent material
buildup. Prior to loading the next day, the drum should be run discharged or
the bed dumped to eliminate any remaining water. See Figure 7.79.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
65
66
Ideally, all operations are designed to meet optimal PCC placement rates because a
consistently moving PCC paver can, in general, produce a smoother pavement than one
that must constantly start and stop while trying to match its paving rate to the material
delivery rate. Truck transport should be planned such that the PCC transport rate
(expressed in m3/hr or yd3/hr) closely matches plant production rate and paving rate.
Some factors to consider are:
Traffic plays a large role in PCC delivery rates because it affects truck speed. Especially
in congested urban areas, heavy and/or unpredictable traffic may substantially increase
or at least vary truck travel time. As truck travel time increases more trucks are needed
to provide a given PCC delivery rate. Additionally, PCC usually must be delivered within
a specified amount of time. Therefore, as traffic gets worse, trucking costs increase.
Additionally, the unpredictability of traffic may result in either long paver idle times as it
waits for the next truckload of PCC or large truck backups as several trucks all reach the
paving site or production facility at the same time.
In sum, synchronization should be the goal but it is often difficult to achieve (based on
varying paving rates, haul time and traffic) and may result in paving inefficiency and
degraded PCC quality.
8.3 Summary
Mix transport can have a large impact on rigid pavement construction quality and
efficiency. Mix characteristics such as homogeneity, workability, water content and air
content are all affected by mix transport practices. In general, there are two types of mix
transport trucks: the truck mixer and the non-agitated truck. The most common one, the
Road Construction
Source: WSDOT
Compiled by: Jurie SK
67
truck mixer, hauls the mix in a large rotating drum giving it the capability to actually
perform PCC mixing as well as the ability to agitate the PCC while in transport. Nonagitating trucks, which are typically dump trucks, are much simpler in design and are
often used to transport central mixed PCC over short haul distances.
Key
considerations in mix transport are proper mixing and batch at the production facility,
truck cleanliness, water management, unloading timeliness and location, and operation
synchronization. If properly managed, mix transport can successfully move PCC over
long distances with no impact to final pavement quality.
68
pavement construction. This section discuss the placement of dowel bars, tie bars, and
reinforcing steel during the construction process.
9.1 Dowel Bars
Dowel bars can be placed either before PCC placement by using dowel baskets, or after
PCC placement by using an automatic dowel bar inserter. Their placement is crucial to
proper joint load transfer. Skewed, shallow or excessively corroded dowels can fail
causing faulting and/or cracking at the joint. This subsection covers:
Road Construction
Source: WSDOT
Compiled by: Jurie SK
69
Figure 7.84: Dowel Basket Figure 7.85: Dowel Baskets Placed on a Lean Concrete
Placed on an HMA Base
Base in Advance of PCC Placement
Road Construction
Source: WSDOT
Compiled by: Jurie SK
70
Road Construction
Source: WSDOT
Compiled by: Jurie SK
71
Figure 7.88: Tie Bar Insertion Equipment for Side Tie Bars
Road Construction
Source: WSDOT
Compiled by: Jurie SK
72
Manual method
Mechanical
method
Road Construction
Source: WSDOT
Compiled by: Jurie SK
73
Additionally, CRCP pavements (and JRCP pavements when they were more routinely
constructed) can be placed in two lifts. First, the bottom lift is placed, followed by
reinforcing bar placement, and then finished with a second PCC lift. Although feasible,
Road Construction
Source: WSDOT
Compiled by: Jurie SK
74
this method can be costly as it usually requires two passes of the PCC paver. However,
some equipment companies offer pavers capable of placing two lifts simultaneously.
10 RIGID - GENERAL PROCEDURE
The general rigid pavement construction
Major Topics on this Page
procedure involves placement, consolidation,
10.1 Placement
finishing, curing and jointing in rapid succession.
"Placement" involves any equipment or 10.2 Screeding (Strikeoff)
procedures used to place the delivered PCC on
the desired surface at the desired thickness; 10.3 Consolidation
"consolidation" involves any means used to 10.4 Finishing
eliminate undesirable voids; "finishing" involves
any equipment or procedures used to impart 10.5 Curing
desirable surface characteristics; "curing" is the 10.6 Joints
maintenance of satisfactory moisture and
10.7 Summary
temperature in PCC as it sets and hardens such
that the desired properties can develop; and "jointing" involves all those actions used to
insert purposeful discontinuities in the pavement and seal them appropriately. This
section provides a generic description of these six steps and any associated
considerations. Specifics of how they are accomplished in fixed form and slipform
paving are shown in the next two sections. More detailed information can be found in:
10.1 Placement
PCC can be placed directly in the desired location by truck or truck attachments (see
Figures 7.95 and 7.96), or can be fed into a placement machine for more accurate and
even placement. PCC that is moved excessively once it has been unloaded from the
transport truck will tend to segregate (become less homogeneous).
Too much vibration, either by allowing vibrators to operate too long in one area
or by using to high a vibration rate, can result in (1) non-uniform distribution of
coarse aggregate particles, (2) loss of entrained air, and (3) bleeding (water
accumulation on the surface). All of these results can greatly reduce PCC
durability.
Too little vibration, either by not allowing vibrators enough time to operate in
one area or by using to low a vibration rate, can result in (1) non-uniform
Road Construction
Source: WSDOT
Compiled by: Jurie SK
76
distribution of coarse aggregate particles, and/or (2) large air voids within the
PCC mass. Again, either result can greatly reduce PCC durability.
Vibrator static head (amount of PCC above the vibrator) influences efficiency.
Higher static heads will help push coarse aggregate particles together behind
the vibrator as it travels along.
10.4 Finishing
Finishing involves all processes and equipment used to create the final surface finish
and texture of fresh PCC. Generally, finishing can be divided into floating and texturing:
Floating. A flat surface is run across the PCC in order to eliminate high and
low spots, embed larger aggregate particles beneath the surface, remove
slight imperfections and to compact the mortar at the surface in preparation for
texturing (PCA, 1988). Floating can involve a number of different tools and
may involve multiple passes over the same surface.
Texturing. After floating, fresh PCC is usually quite smooth. In order to create
a slip resistant surface for traffic, a rough pattern is usually imparted by
dragging a broom, rough-textured item, or tined instrument across the
surface. Typically, texturing is divided into the following two categories
(FHWA, 1999):
o Microtexture (Figure 7.98). This is achieved by dragging a section
of burlap or artificial turf behind the paver. Microtexture enhances
friction between vehicle tires and the pavement surface, and
enhances safety at low speeds.
o Macrotexture (Figure 7.99). This is generally achieved by tining the
pavement surface. Macrotexture permits water to escape from
between tires and the pavement surface and enhances safety at
high speeds. Typically, an average texture depth of 0.7 mm (0.03 in)
will substantially reduce both total and wet weather accident rates.
Tining practices vary by agency, but many states require transverse
grooves on the order of 3 - 5 mm (0.12 - 0.20 inches) deep, 3 mm
(0.12 inches) wide and spaced 12 - 20 mm (0.47 - 0.79 inches)
apart (ACPA, 1995). Sometimes the area over the future joint
locations is not textured in order to provide a good sawing and
sealing surface. Some agencies consider microtexturing sufficient
and
do
not
macrotexture
their
rigid
pavements.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
77
10.5 Curing
Curing refers to the maintenance of satisfactory moisture and temperature within a PCC
mass as it sets and hardens such that the desired properties of strength, durability and
density can develop (PCA, 1988). The desired properties of strength, durability and
density are related to the extent of hydration within the PCC mass; the more complete
the hydration, the better a PCC's properties. The extent and rate of hydration depend on
two critical construction-controlled parameters: moisture and temperature. This
subsection covers:
10.5.1 Moisture
Hydration requires portland cement and water. The extent of hydration is controlled by
the limiting ingredient, which is usually portland cement. However, if any substantial
portion of water is lost to evaporation, hydration may be limited by a lack of water,
causing it to slow or virtually stop. Thus, inadequate moisture will inhibit hydration, which
results in a weaker, less durable PCC. Rapid moisture loss will also cause excessive
shrinking and cracking. Therefore, a high relative humidity around a hydrating PCC
mass will ensure an adequate water supply for hydration and limit shrinkage cracking.
Generally, some method of curing is specified in order to maintain the relative humidity
within the hydrating PCC at an adequate level.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
78
10.5.2 Temperature
Hydration rate is also dependent upon temperature. Higher temperatures speed up
hydration's chemical reactions, while lower temperatures slow them down. Therefore,
temperature will affect PCC strength gain. Often, minimum ambient temperatures for
PCC construction are specified to ensure an adequate hydration rate and thus, strength
gain.
Maturity
Since hydration progresses over time, and the rate of this progression is dependent on
temperature, it should be possible to estimate the extent of hydration by tracking time
and temperature. "Maturity" is the term used to describe this concept. Most maturity
measures are expressed as a function of the product of curing time and temperature
(see Figure 7.100). For example, the Nurse-Saul expression is:
t
M T T0 t
0
where:
t = time interval
T
T0
Road Construction
Source: WSDOT
Compiled by: Jurie SK
79
Often, maturity is correlated to PCC strength gain by laboratory testing prior to PCC
placement. A non-destructive maturity measurement can then be used to estimate
strength and avoid destructive strength tests during construction. ASTM C 1074 defines
the maturity method as "...a technique for estimating concrete strength that is based on
the assumption that samples of a given concrete mixture attain equal strengths if they
attain equal values of maturity index." The maturity method is useful because it can
provide strength estimates of in-place PCC subject to actual environmental temperatures
rather than relying solely on controlled-environment laboratory tests. There are also a
number of significant limitations when using maturity to estimate strength (Mindess and
Young, 1981):
In sum, the maturity method is not a physical law, but rather a convenient way to
estimate strength gain. In PCC pavement applications, maturity meters (see Figures
7.101 and 7.102) can be used to estimate the appropriate time for form removal, joint
cutting or opening a pavement to traffic, but should not be entirely substituted for basic
laboratory strength tests.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
80
Joint location
Saw cutting timing
Saw cutting depth
Joint sealing
10.6.1 Location
Road Construction
Source: WSDOT
Compiled by: Jurie SK
81
Typical joint locations are covered in Module 2, Section 6: Rigid Pavement Types, and
are not repeated here. However, it is important to note that joint locations should be
indicated on the construction plans and planned in advance (see Figure 7.103).
Intersection joint locations can be quite complex and should be marked out on the base
in advance (see Figure 7.104).
Road Construction
Source: WSDOT
Compiled by: Jurie SK
82
Thus, as the PCC hydrates and strengthens, there is a short window of time in which
sawing can occur as illustrated by Figure 7.107.
83
Figure 7.109: Joints Sealed with Hot-Pour Liquid Sealant on a Freeway On-Ramp
(normally, joints should coincide with lane divisions as they do near the horizon of this
photograph)
10.7 Summary
This section has provided an overview of the basic elements of rigid pavement surface
course construction: placement, consolidation, finishing, curing and jointing. These basic
elements are common to both fixed form and slipform paving; the differences are in the
equipment and methods.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
84
In fixed form paving, side forms are used to hold 11.1 Forms and Placement
fresh PCC in place at the proper grade and
alignment until it sets and hardens. These forms 11.2 Screed/Paver
may also serve as tracks for various pieces of 11.3 Consolidation
placing and finishing equipment. Fixed form
paving is most appropriate for small jobs (see 11.4 Finishing
Figure 7.110), complicated geometry pavements 11.5 Curing
or variable width pavements, however it can be
used for large jobs as well (see Figure 7.111). Particular advantages of fixed form
paving are (ACPA, 1995):
Tight tolerances and side clearances. Existing curbs or other features can be
used as forms.
Custom geometry. Forms can be placed in just about any pavement
geometry, which allows for multiple changes in pavement width, smooth
curves, blockouts and other abnormalities.
Better construction staging. Forms can be placed such that staged
construction can be used to maintain traffic flow or intersection use (see Figure
7.112).
Less expensive equipment and mobilization. Forms and equipment are less
expensive than slipform paving equipment. If paving operations are small
enough, this cost savings can more than offset the higher production rates of
slipform paving.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
85
Figure 7.112:
Construction Staging Using Fixed Form Paving
This section presents PCC forms, placement, consolidation, finishing and curing as they
are typically done in fixed form paving. Often more than one of these steps can be
performed by the same piece of equipment, such as a vibrating screed, which serves to
strike off and consolidate the fresh PCC, or a traveling carriage paver which can perform
all three steps.
11.1 Forms and Placement
Fixed form paving uses a series of preset molds (or "forms") to shape a rigid pavement.
These forms are placed on the graded base or subgrade in the desired shape of the final
rigid pavement. They can be made of anything from welded steel sections to simple
lumber. Typically, larger jobs use 3 m (10 ft.) welded steel sections (see Figure 7.113
and 7.115), while small jobs often use stock lumber (see Figure 7.114). The following
lists some general guidance when using forms (ACPA, 1995):
Form depth should be equal to PCC slab thickness. This way PCC slab
elevation can be tightly controlled out to and including the edges.
Forms should have some base width to provide stability. If they do not, they
may fall over when subject to the loading imposed by the fresh PCC.
The top of the form should be straight and true. Specifications vary, but
generally anything more than 3 mm (0.12 inches) every 3 m (10 ft.) is
considered excessive.
Form ends should be able to lock together. If not, they may come apart when
subject to the loading imposed by the fresh PCC.
Forms should be attached to the ground (via stake) every 1 - 2 m (3 - 6 ft.).
Forms that are not staked may move and forms that are infrequently staked
may bow out between stakes.
Forms should be cleaned and oiled before use. Dirty, unlubricated forms will
cause surface defects in the slab sides and may stick to the slab during
removal.
Curves less than about 30 m (100 ft.) in radius should be done with flexible
forms (e.g., wood) or curved metal forms. Above 30 m (100 ft.) straight 3 m
(10 ft.) long metal forms can be laid in a smooth enough curve.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
86
Form placement (or "setting") should be a careful process that is entirely completed
before PCC placement. Forms are quite easy to adjust before PCC is placed and near
impossible to adjust afterwards. Form placement is also crucial to rigid pavement quality
because finishing equipment generally rides on the forms making final pavement
smoothness dependent on form elevation uniformity. Forms can often be removed as
soon as 6 to 8 hours after placement (ACPA, 1995).
11.2 Screed/Paver
Road Construction
Source: WSDOT
Compiled by: Jurie SK
87
Fixed form screeds vary in complexity from a simple hand screed (sometimes even as
simple as a small piece of lumber) to an automatic self-propelled combination screedfinisher. Often, these combination machines are referred to as "pavers" because of their
multiple functions. Some typical screed/paver types are listed below:
Manual screed (Figure 7.116 and 7.117). Consists of just about anything that
is straight and flat enough to strike off PCC at a desired elevation. Figure
7.117 shows a manual screed consisting of a long-handled metal straightedge.
88
Traversing roller tube paver (Figure 7.122 and 7.123). Consists of a traveling
carriage mounted on a truss frame. The carriage travels along the truss frame
from one end to the other, with the machine moving forward after each
carriage pass. Typically, the traveling carriage can screed and finish PCC in
one pass. The truss frame upon which the carriage travels can be set to
provide flat, parabolic, crowned, super-elevated and tapered surfaces.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
89
11.3 Consolidation
There are three general consolidation options in fixed form
paving:
1. Omit (not recommended). Sometimes, on very
small jobs such as the one pictured in Figure
7.113, vibration is omitted. However, this Figure 7.124: Hand-Operated
Vibrator
increases the risk of leaving large voids in the
PCC mass, which creates a honeycomb-like structure.
2. Hand-operated vibrators. The typical vibrator, sometimes known as a "spud
vibrator" is a long vibrating rod powered by either air pressure or a small 1.53.0 kW (2-4 horsepower) motor (See Figures 7.124 and 7.125).
3. Screed vibration. Equipment like the vibrating truss screed and the traveling
carriage screed will vibrate the placed PCC while striking it off. Vibration is
usually accomplished by mechanical or air power.
11.4 Finishing
Road Construction
Source: WSDOT
Compiled by: Jurie SK
90
Fixed form finishing is usually accomplished by hand tools or form riding equipment.
Typically, after the PCC has been screeded it is floated using hand floats (see Figure
7.126 and 7.128) and straightedges (see Figure 7.126) in order to eliminate any
remaining high/low spots and to embed large aggregate particles. Finally, texturing is
added using a hand tining tool (see Figure 7.129) or a traveling carriage attachment.
11.5 Curing
Fixed form construction uses both wet and sealed curing. Wet curing is typically limited
to small jobs, while sealed curing, which is more prevalent, can be used on any job size.
Curing seals can be distributed from machines that straddle the finished pavement or
from hand-operated sprayers (see Figure 7.130).
Road Construction
Source: WSDOT
Compiled by: Jurie SK
91
12.1 Placer/Spreader
Road Construction
Source: WSDOT
Compiled by: Jurie SK
12.2 Paver
surface finish a PCC mass by pulling the forms continuously through and surrounding
the plastic concrete mass.
Slipform paving is most appropriate for larger jobs that require high production rates.
Particular advantages of slipform paving are (ACPA, 1995):
This section presents PCC placement, consolidation, finishing and curing as it is typically
done in slipform paving. Most often, these steps are accomplished by three pieces of
equipment: the placer/spreader (used for rough placement), the concrete paver (used for
final placement, consolidation and initial finishing), and the texturing and curing
machine. These machines usually travel together in series down the length of the
project.
12.1 Placer/Spreader
Although not always used, placer/spreaders are quite common. They place a metered
supply of PCC in front of the paver using a series of conveyor belts, augers, plows and
strikeoff devices (see Figures 7.131 and 7.132). Using a placer/spreader allows the
contractor to receive material from transport vehicles and place a uniform amount of
PCC in front of the entire paver width, while minimizing segregation.
12.2 Paver
The paver usually performs screeding, consolidation and initial finishing. A typical trackmounted, self-propelled paver operates at speeds between 1 and 2.5 m/minute (3 and 8
ft./min) (ACPA, 1995). Some pavers are equipped to place reinforcing steel (if needed),
dowel bars and tie rods as well. Figure 7.133 shows the basic slipform paving process
as it occurs underneath the paver. First, an auger spreads the PCC in front of the strike
off plate. Second, the strike off plate (screed) removes excess portions of the augerplaced PCC and brings the slab near its final elevation. Third, the PCC is consolidated
by a group of vibrators. Fourth, a tamper (typically operating between 0 and 150 strokes
per minute), if present, pushes large aggregate particles below the slab surface. Finally,
the profile pans level off the slab at the right elevation and provide initial finishing. The
remainder of this section describes this process in more detail.
12.2.1 Screeding
Slipform pavers first use an auger to perform any final material spreading and then strike
off the PCC at the correct elevation using a simple strike off plate, or screed.
12.2.2 Consolidation
After screeding, the paver consolidates the fresh PCC using a series of vibrators (see
Figure 7.134). Typically, the most effective vibrator position is after the strike-off
mechanism and at the final slab elevation. Depending upon mix design and slab depth,
vibrators are usually set in the 7,000 - 9,000 vibrations per minute (VPM) range.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
94
Vibrators are positioned next to one another such that their influence zones overlap by
about 50 - 75 mm (2 - 3 inches) at normal paver speed (ACPA, 1995). Gaps between
the influence zones (caused by incorrect vibrator settings or excessively fast paver
operation) can cause segregation (ACPA, 1995). Most pavers use fully adjustable
vibrator spacing to account for different conditions and mix types, while still providing
adequate influence zone overlap.
However, a tamper may not be necessary on many jobs. Although it forces the coarse
aggregate away from the surface, making finishing easier, it can also creates a mortarrich surface layer which could scale or craze (USACE, 1995). Usually, a tamper is not
Road Construction
Source: WSDOT
Compiled by: Jurie SK
95
necessary with a well designed PCC mixture, however, it may be helpful when finishing a
harsh, low-slump mixture.
Additional finishing, when needed, occurs just behind the profile pan and is usually
accomplished using simple floats (see Figure 7.136). Microtexturing is usually
accomplished by dragging a section of burlap (see Figure 7.137) or artificial turf (see
Figure 7.138) behind the paver.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
96
Road Construction
Source: WSDOT
Compiled by: Jurie SK
97
13 RIGID - JOINTS
Joints are common to all rigid pavements and
both rigid pavement construction methods. Even Major Topics on this Page
CRCP uses longitudinal joints and periodic
13.1 Sawed Joints
transverse joints. Joints can be formed in two
ways. Contraction joints are most often sawed in 13.2 Other Joints
after PCC placement. Others such as expansion,
isolation and construction joints, are created by formwork before the PCC is placed.
Each one of these methods of joint construction has its own method and set of
considerations.
13.1 Sawed Joints
Most sawed joints are contraction joints. This section covers:
Saw blades
Sawing equipment
A general sawing procedure
98
cutting and generally must be cooled by water to prevent the saw blade metal from
overheating and melting. Water also prevents dust formation during sawing.
13.1.1.2 Abrasive Blades
Dry sawing uses abrasive blades that are usually made from fiber reinforced silicone
carbide or carborundum since these types of blades do not require water for cooling
(ACPA, 1995). These abrasive blades have less cutting ability than diamond blades and
are usually used on PCC with softer aggregate (ACPA,
1995). When cutting, these blades will wear down over
time making it important to periodically check the sawed
depth and saw blade diameter to ensure adequate joint
depth (ACPA, 1995). Additionally, unless water is used
to prevent it, these types of blades will generate sawing
dust.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
99
13.1.3 Procedure
Joint sawing is generally accomplished in two passes. First, an initial thin cut is made to
control shrinkage cracking. The timing of this joint cut is critical in order to avoid
permanent slab damage. Later on, a second, wider cut is made over the first cut in order
to make the joint wide enough to accommodate joint filler material. Some joint cutting
considerations are:
Ensure adequate PCC is available to finish the last slab of the day. The
construction joint is set before all the PCC is placed. If truck delivery is
stopped to soon, the temptation may be to use the lower-quality PCC that has
been pushed in front of the screed to fill the remaining volume. This lowquality PCC may contain little portland cement, excess water, low air and/or
segregated aggregate.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
100
Ensure proper consolidation. Typically, the paver does not traverse the
construction joint. Therefore, the construction joint is not consolidated by the
paver vibrators and it should be manually consolidated.
Dowel placement should not segregate or cause air voids in the adjacent
PCC. Sometimes, dowel bars are placed after the PCC has been placed up to
the header. If dowel bars are pounded in by hammer, the resultant vibrations
may cause air pockets or segregated aggregate.
Road Construction
Source: WSDOT
Compiled by: Jurie SK
101