Tunnelling in adverse geological occurrence A case study of tail race tunnel of Tala
hydroelectric project
KARMA GYAMTSHO, M. C. OHIR,
KARMA TSHERI NG AND R. K. OOGRA
TCI/Clllydmeltrtrir Projel"l AI,I/wrily, 8/111/(111
III I 33
7.00 In horseshoe shaped with two adits, i.e., Intermediate Ad it of length 520 m.
7.0 m D-shaped and O utfall adit of length 166 m. 7 m D-shaped. Owing to the 300
diversion of tail race tunne l at RD 1140 m dIs from Intermediate adit. the revised
length of tail race tunne l works out 10 3. 156 km after six tail race manifold as
shown in Fig. 1, 1 to 6 of size 4 x 4.5 m D-shaped.
At RD 1160 m, the Genguchu nallah is encou ntered in the present alignment with
vertical rock cover of 60 m. The revised layout has been planned for increased lateral
and vertical rock cover for better rock mass conditions and less seepage.
111/34
at high speed, which flowed in about 10 m length of tunnel. The face was full of slush
and muck and it gal stabilized inherently. The slush which had flowed for to m length
was cleared cautiously and the face was packed with gunny bags filled with gravels and
then shotcreted at a pressure of 8 bars.
[n order to prevent the gunny bags filled with gravel from sliding, 10 pipes of
32 mm dia were driven vertically. And the cement, sand grouting of ratio 1:1 were
proceeded fo r furthe r stabilization from the crown. A hole of 4" dia of 12 m long
perforated MS pipe was drilled by Pu ntel machine (Fig. 2) in order to ascertain the
geological strata. It was predicted that 5 m reach from face were loose and thereafter
the geology would improve. 30 nos. of holes were drilled and 4" dia. 12 m long
perfomled pipes were inserted for neat cement grouti ng. The neat cement grouting was
done with wlc ratio 0.5 to 0.7 at the pressure of 8 bar. The pattern of grouting done
from bottom of LHS of crown and bottom RHS of crown simultaneously and contin ued
up to crown in order to avoid chocking of drilled holes.
illl~rllk:,halc
aUIl.
After completion of this grouting, further strengthening was done by drilli ng six
more holes of 3" dia and 8 m long at crown behind the face and forepoled for grouting
at the pressure of to bar and grouting was completed. Setting time was given before the
advancement.
In TRT U/S from outfall adit
Advancement ofTRT excavation from uls of outfall adit was held up due to occurrence
of a shear zone. When arrangements were made for laying the wall beam and erection
of rib segments, loose mass started falling from the crown , resulting into formation of
111 / 35
cavi ty. the face was immediately blocked with gunny bags filled with muck and 2 nos.
4" and I no. 6" dia MS pipe were embedded to fill concrete/grout in the cavity portion.
Subsequently box forepoles of ISA 50 x 50 x 6 of 19 nos. of 7 m long were inserted in
the cavity for umbrella fonnations, strengthening of bulkhead was done by welding
various steel sections and SFRS was spmyed. An attempt was made to fill the cavity
area with concrete (cement sand and aggregme A 10). BUI rejection was observed
hence cement sand grout ( I: I) by weight was injected into the cavity in stages. After
selling time the drainage holes of 6 m and 7 m length were drilled at identified
localions. When face was opened. lumps of cement sand grout were observed m Ihe
crown. water seepage staned to flow from Ihe opening in between lumps of cement
s.md grout and gave passage to the fl ow of gauzy material. An attempt was made to
erect the segment of rib of ISMB 250 x 125 mm but cou ld not succeed. however
bulkhead was reinstalled and cement sand grouting (1:1) continued. After completion
of th is grouti ng further strengthening of the affected zone from 1.50 m behind the
existing bul khead by providing forepol ing (Fig. 3) of 32 mm di a. 8 m long at 20 to 30
inclination was done. Neat cement grouting with wlc 0.6 to 0 .5 with sodi um silicate
was continued wi th pressu re grouting machine at pressure of 8 to 10 kglcm 2. The fuce
was opened wi th central drift of size 0.75 m x 2.2 m x 1.5 meL. B. H). rib segment was
erected with temporary colu mn support and backfilled after erecting lagging. Similarly
excavation was extended at left and ri ght hand side.
During advancement another shear zone was observed at U/S of T RT from outfall
adi!. it was tack led with multiple drift excavation wi th erection of segmental rib and
backfilling. Keepi ng in view the prevail ing geological condition of the si te. it was
decided to provide forepo le umbrella of MS pipes of 11 4 mm diametre with puntel
forepoling machine for making further advancement. Forepoles, 12 m long were
provided at the crown periphery fonning umbrella. During the process of dri lli ng of
III f
36
forepoles minor seepage was observed and initial 5- 6 m reach was found to be of loose
stmla, next 6-12 m was observed in liule improved slmta. Multistage cement grouting
through these perforated forepoles was carried out with the help of hydrau lic packer at
the pressure varying 4- 12 bar with wlc ratio varying 0.7 to 0.5. The face was opened
after giving 3 days seuing time. Further heading advancement was done @ 0.6 m with
rib support and backfill concrete below forepole umbrella zone.
A drift of size 0.75 m x 2.2 m x 1.5 m (L. S , H) was excavated aI the crown
and the segmental steel rib of ISMB 250 x 125 mm in 14 crown segment was
erected manually as shown in Fig. 4. Steel runners of ISMC 100 x 50 mm
were we lded with existing ribs for newly erected segment to hold it in place.
M: 15 grade of concrete was used for backfilling after erecting the steel
lagging.
(ii)
Excavation was then extended to right side of crown in a width of 1.5 m and
another 14 crown segment of ISMB 250 x 125 mm was erected . Proper
backfill of M: 15 A 20 grade of concrete was done after steel lagging.
(iii ) The excavation was carried out gradually downward by extending the drift
excavated at step- I to the spring level. A segmental steel rib, 1/4 crown
segment of ISMB 250 x 125 mm was erected and backfilled after the steel
lagging.
(iv) The excavation was then carried out gradually downward by extending the
drift excavated at slep-2 to the spring level. A segmental steel rib, 1/4 crown
[]] f
37
Method - 2
This method was sui table where crown portion was unstable with inadequate stand up
time and backfill with concrete was not possible. It was adopted for tailrace tunnel uls
from outfall adit in class VI and beyond rock .
(i)
A drift of size 0.75 m x 2.2 m x 1.5 m (L, B, H) was excavated from the
spring level. After the installation of 1,4 crown segment of 15MB 250 x 125
mm, the steel lagging was erected and backfill concrete completed with dry
mix of ralio (l :2:4) and grouted with neat cement of wlc = 0.6 (as shown in
Fig. 5). This was done to save time of installation of concrete pump. pipes
etc. in view of flowing condition from crown.
Oi)
A drift of 1.5 m of another side of section was excavated from the spring
level. l/.s crown segment of ISMB 250 x 125 mm was installed and backfilled
with dry mix of ratio I :2:4 after fixing the steel laggi ng. Neat cement
grouting of wlc =0.6 was done.
(i ii ) The excavation for the drift was extended from the excavated drift of step- 1
to the crown level. 1.4 crown segment of ISMB 250 x 125 mm was installed.
Dry mix of ratio (1:2:4) was filled after steel lagging was erected. When
111 / 38
required vol ume of dry mix was filled , neat cement grouting of wlc = 0.6 was
done.
(iv)
Remai ning excavation was done from the excavated drift of step-2 to Ihe
crown level. Neat cement grouting of wlc = 0.6 was done when required
volume of dry mix (1 :2:4) was backfi lled.
lIIi~
t! 2:4)
Method - 3
This method was adopted when whole of the strata above spring level was unstable
with inadequate standup time. h was adopted for tailrace tunnel uJs from Outfall adit in
class VI and beyond rock.
(i)
(ii)
(iii ) Similarly drift was extended to another s ide of the crown by excavating
gradually downward upto the spring level and was properl y backfilled after
installation of rib segment and lagging.
111 1 39
Post excavation consolidation grouting of above spring level reach was completed
when heading advance was 1.8-2.4 m. Drainage holes were drilled for release of water
pressure.
Excavation for benching 'was carried out and erection of column of 15MB 250 x
125 mm. usually twO column s at a time @ 0.6 m at one side of the tunnel were erected
and backfilled after erection of laggi ng. During the erecti on of column , check for
verticn lity and centre line was done. Similarly the erection of columns on other side of
tunnel was done with a lag of 3 m.
111/40
was done in three stages using hydraulic packers (8- 12 m stage, 4-8 m stage, 0-4 m
stag.e) m a pressure of 10 bnr wilh wnter cement rmin vnrying from 0.5 III 0.7.
CONCLUSION
Geotechnical uncertainties are expected in tunnel construction work. Further advance
was made possible in a conventional manner by grouting, multiple drifting followed by
c6ntrolled excavation depending on the Strata with immediate installation of support at
face. Forepoling with puntel machine Upl0 12 m followed by high pressure grouting
was effective in T RT in class V I and beyond rock used state of 'Irt method.
Conventional methods are more time consuming and less effective vis-a-vis tackling
such strata wi th a forepoling machine. Therefore it is important to incorporate
forepoling equipment at tender stage to tackle such strata in mega-tunnelling projects
for timely completio n. If class V I and beyond reach is envisaged ' in a considerable
reach based on actual excavation inputs, realignment of tunnel can prove to be cost and
time effective.
REFERENCE
Karol . R.H.. (1 990). "Chemical groutin g" 2 Ed. New York and lladcL. marcel Dekker inc. Pl" 4954. 4294 32.