DAFTAR ANALISA BIAYA KONSTRUKSI ( ABK )

SNI ( STANDAR NASIONAL INDONESIA )

JENIS PEKERJAAN
KODE KOEFISIEN SATUAN HARGA SATUAN JUMLAH HARGA
BAHAN DAN UPAH KERJA
A. PEKERJAAN PERSIAPAN

A.1 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK


A.1.1 Bahan
0.012 M3 Balok Kayu 5/7 Kelas III @ Rp 1,568,750.00 Rp 18,825.00
0.020 Kg Paku Biasa 2" - 5" @ Rp 16,000.00 Rp 320.00
0.007 M3 Kayu Papan 3/20 Kelas III @ Rp 1,212,500.00 Rp 8,487.50
Jumlah ( 1 ) Rp 27,632.50

A.1.2 Tenaga
0.100 Oh Tukang Kayu @ Rp 74,500.00 Rp 7,450.00
0.100 Oh Pekerja @ Rp 46,500.00 Rp 4,650.00
0.010 Oh Kepala tukang Kayu @ Rp 82,500.00 Rp 825.00
0.005 Oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah ( 2 ) Rp 13,292.50
Jumlah ( 1 ) + ( 2 ) Rp 40,925.00

A.2 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT


A.2.1 Bahan
1.700 Btg Dolken kayu O 8-10/400 cm @ Rp 7,500.00 Rp 12,750.00
0.210 M3 Kayu @ Rp 1,212,500.00 Rp 254,625.00
0.300 Kg Paku Biasa 2" - 5" @ Rp 16,000.00 Rp 4,800.00
10.500 Kg Semen Portland @ Rp 1,200.00 Rp 12,600.00
0.030 M3 Pasir Beton @ Rp 155,000.00 Rp 4,650.00
0.050 M3 Koral Beton @ Rp 225,000.00 Rp 11,250.00
1.500 Lbr Seng Gelombang bjls 32 @ Rp 75,000.00 Rp 112,500.00
Jumlah ( 1 ) Rp 413,175.00

A.2.2 Tenaga
2.000 Oh Tukang @ Rp 74,500.00 Rp 149,000.00
1.000 Oh Pekerja @ Rp 46,500.00 Rp 46,500.00
0.200 Oh Kepala tukang @ Rp 82,500.00 Rp 16,500.00
0.050 Oh Mandor @ Rp 73,500.00 Rp 3,675.00
Jumlah ( 2 ) Rp 215,675.00
Jumlah ( 1 ) + ( 2 ) Rp 628,850.00

A.3 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN


A.3.1 Tenaga
0.100 Oh Pekerja @ Rp 46,500.00 Rp 4,650.00
0.050 Oh Mandor @ Rp 73,500.00 Rp 3,675.00
Jumlah Rp 8,325.00

B. PEKERJAAN TANAH

B.1 1 M3 GALIAN TANAH BIASA ( KedaLaman maks. 1 M' )


B.1.1 Tenaga
0.750 Oh Pekerja @ Rp 46,500.00 Rp 34,875.00
0.025 Oh Mandor @ Rp 73,500.00 Rp 1,837.50
Upah Kerja Galian Jumlah Rp 36,712.50

B.2 1 M3 GALIAN TANAH BIASA ( Kedalaman maks. 2 M' )


B.2.1 Tenaga
0.900 Oh Pekerja @ Rp 46,500.00 Rp 41,850.00
0.045 Oh Mandor @ Rp 73,500.00 Rp 3,307.50
Upah Kerja Galian Jumlah Rp 45,157.50

Analisa Biaya Konstruksi 1


B.3 1 M3 GALIAN TANAH BIASA ( KedaLaman maks. 3 M' )
B.3.1. Tenaga
1.050 Oh Pekerja @ Rp 46,500.00 Rp 48,825.00
0.067 Oh Mandor @ Rp 73,500.00 Rp 4,924.50
Upah Kerja Galian Jumlah Rp 53,749.50

B.4 1 M3 PEMADATAN TANAH (PER 20CM)


B.4.1 Tenaga
0.500 Oh Pekerja @ Rp 46,500.00 Rp 23,250.00
0.050 Oh Mandor @ Rp 73,500.00 Rp 3,675.00
Upah Kerja Pemadatan Jumlah Rp 26,925.00

B.5 1 M3 URUGAN
B.5.1 Bahan
1.200 M3 Pasir Urug @ Rp 105,300.00 Rp 126,360.00
1.200 M3 Tanah Timbunan @ Rp 67,500.00 Rp 81,000.00

B.5.2 Tenaga
0.300 Oh Pekerja @ Rp 46,500.00 Rp 13,950.00
0.010 Oh Mandor @ Rp 73,500.00 Rp 735.00
Upah Kerja Urugan Jumlah 2 Rp 14,685.00
Jumlah ( 1 ) + ( 2 ) Pasir Urug Rp 141,045.00
Tanah Timbunan Rp 95,685.00

B.6 1 M3 URUGAN SIRTU


B.6.1 Bahan
1.200 M3 Sirtu @ Rp 162,750.00 Rp 195,300.00
1.200 M4 Kerikil @ Rp 225,000.00 Rp 270,000.00

B.6.2 Tenaga
0.250 Oh Pekerja @ Rp 46,500.00 Rp 11,625.00
0.025 Oh Mandor @ Rp 73,500.00 Rp 1,837.50
Upah Kerja Urugan Sirtu Jumlah Rp 13,462.50
Jumlah ( 1 ) + ( 2 ) Sirtu Rp 208,762.50
Kerikil Rp 283,462.50

B.7 1 M2 PASNGAN IJUK LAPISAN TEBAL 10 CM, UNTUK BIDANG PERESAPAN


B.7.1 Bahan
6.000 Kg Ijuk @ Rp 10,000.00 Rp 60,000.00
Jumlah ( 1 ) Rp 60,000.00

B.7.2 Tenaga
0.150 Oh Pekerja @ Rp 46,500.00 Rp 6,975.00
0.015 Oh Mandor @ Rp 73,500.00 Rp 1,102.50
Jumlah ( 2 ) Rp 8,077.50
Jumlah ( 1 ) + ( 2 ) Rp 68,077.50

C. PEKERJAAN PONDASI
C.1 1 M3 PASANGAN PONDASI BATU GUNUNG, 1 PC : 4 Ps
C.1.1 Bahan
1.200 M3 Batu Gunung @ Rp 165,000.00 Rp 198,000.00
163.000 Kg Semen @ Rp 1,200.00 Rp 195,600.00
0.520 M3 Pasir Pasang @ Rp 175,000.00 Rp 91,000.00
Jumlah ( 1 ) Rp 484,600.00

C.1.2 Tenaga
0.750 Oh Tukang Batu @ Rp 73,500.00 Rp 55,125.00
0.075 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 6,337.50
1.500 Oh Pekerja @ Rp 46,500.00 Rp 69,750.00
0.075 Oh Mandor @ Rp 73,500.00 Rp 5,512.50
Jumlah ( 2 ) Rp 136,725.00
Jumlah ( 1 ) + ( 2 ) Rp 621,325.00

Analisa Biaya Konstruksi 2


C.2 1 M3 PASANGAN PONDASI BATU KOSONG
C.2.1 Bahan
1.200 M3 Batu Gunung @ Rp 165,000.00 Rp 198,000.00
0.432 M3 Pasir Urug @ Rp 105,300.00 Rp 45,489.60
Jumlah ( 1 ) Rp 243,489.60
C.2.2 Tenaga
0.390 Oh Tukang Batu @ Rp 73,500.00 Rp 28,665.00
0.039 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 3,295.50
0.780 Oh Pekerja @ Rp 46,500.00 Rp 36,270.00
0.039 Oh Mandor @ Rp 73,500.00 Rp 2,866.50
Jumlah ( 2 ) Rp 71,097.00
Jumlah ( 1 ) + ( 2 ) Rp 314,586.60

C.3 1 M2 PASANGAN PAVING BLOK


C.3.1 Bahan
50.000 Bh Paving Blok t = 6 Cm @ Rp 3,000.00 Rp 150,000.00
0.200 M3 Pasir Urug @ Rp 105,300.00 Rp 21,060.00
Jumlah ( 1 ) Rp 171,060.00
C.3.2 Tenaga
0.135 Oh Tukang Batu @ Rp 73,500.00 Rp 9,922.50
0.0135 Oh Kepala tukang batu @ Rp 84,500.00 Rp 1,140.75
0.720 Oh Pekerja @ Rp 46,500.00 Rp 33,480.00
0.036 Oh Mandor @ Rp 73,500.00 Rp 2,646.00
Jumlah ( 2 ) Rp 47,189.25
Paving Blok t = 6 Cm Rp 218,249.25

D. PEKERJAAN DINDING

D.1 1 M2 PASANGAN BATU MERAH TEBAL 1 BATU, 1 PC : 4 Ps


D.1.1 Bahan
140.000 Bh Batu Merah 5x11x22cm @ Rp 700.00 Rp 98,000.00
26.550 Kg Semen @ Rp 1,200.00 Rp 31,860.00
0.093 M3 Pasir pasang @ Rp 175,000.00 Rp 16,275.00
Jumlah ( 1 ) Rp 146,135.00
D.1.2 Tenaga
0.200 Oh Tukang Batu @ Rp 73,500.00 Rp 14,700.00
0.020 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 1,690.00
0.600 Oh Pekerja @ Rp 46,500.00 Rp 27,900.00
0.030 Oh Mandor @ Rp 73,500.00 Rp 2,205.00
Jumlah ( 2 ) Rp 46,495.00
Jumlah ( 1 ) + ( 2 ) Rp 192,630.00

D.2 1 M2 PASANGAN BATU MERAH TEBAL 1/2 BATU, 1 PC : 4 Ps


D.2.1 Bahan
70.000 Bh Batu Merah 5x11x22cm @ Rp 700.00 Rp 49,000.00
11.500 Kg Semen @ Rp 1,200.00 Rp 13,800.00
0.043 M3 Pasir pasang @ Rp 175,000.00 Rp 7,525.00
Jumlah ( 1 ) Rp 70,325.00
D.2.2 Tenaga
0.100 Oh Tukang Batu @ Rp 73,500.00 Rp 7,350.00
0.010 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 845.00
0.300 Oh Pekerja @ Rp 46,500.00 Rp 13,950.00
0.015 Oh Mandor @ Rp 73,500.00 Rp 1,102.50
Jumlah ( 2 ) Rp 23,247.50
Jumlah ( 1 ) + ( 2 ) Rp 93,572.50

Analisa Biaya Konstruksi 3


E. PEKERJAAN PLESTERAN

E.1 1 M2 ACIAN TEMBOK SEMEN PC


E.1.1 Bahan
3.250 Kg Semen PC @ Rp 1,200.00 Rp 3,900.00
Jumlah ( 1 ) Rp 3,900.00

E.1.2 Tenaga
0.100 Oh Tukang Batu @ Rp 73,500.00 Rp 7,350.00
0.010 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 845.00
0.200 Oh Pekerja @ Rp 46,500.00 Rp 9,300.00
0.01 Oh Mandor @ Rp 73,500.00 Rp 735.00
Jumlah ( 2 ) Rp 18,230.00
Jumlah ( 1 ) + ( 2 ) Rp 22,130.00

E.2 1 M2 PLESTERAN 1 PC : 3 Ps, TEBAL 15 MM


E.2.1 Bahan
7.776 Kg Semen @ Rp 1,200.00 Rp 9,331.20
0.023 M3 Pasir Pasang @ Rp 175,000.00 Rp 4,025.00
Jumlah ( 1 ) Rp 13,356.20

E.2.2 Tenaga
0.150 Oh Tukang Batu @ Rp 73,500.00 Rp 11,025.00
0.015 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 1,267.50
0.300 Oh Pekerja @ Rp 46,500.00 Rp 13,950.00
0.015 Oh Mandor @ Rp 73,500.00 Rp 1,102.50
Jumlah ( 2 ) Rp 27,345.00
Jumlah ( 1 ) + ( 2 ) Rp 40,701.20

E.3 1 M2 PLESTERAN 1 PC : 4 Ps, TEBAL 15 MM


E.3.1 Bahan
6.240 Kg Semen @ Rp 1,200.00 Rp 7,488.00
0.024 M3 Pasir Pasang @ Rp 175,000.00 Rp 4,200.00
Jumlah ( 1 ) Rp 11,688.00

E.3.2 Tenaga
0.150 Oh Tukang Batu @ Rp 73,500.00 Rp 11,025.00
0.015 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 1,267.50
0.300 Oh Pekerja @ Rp 46,500.00 Rp 13,950.00
0.015 Oh Mandor @ Rp 73,500.00 Rp 1,102.50
Jumlah ( 2 ) Rp 27,345.00
Jumlah ( 1 ) + ( 2 ) Rp 39,033.00

E.4 1 M2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 MM


E.4.1 Bahan
5.184 Kg Semen @ Rp 1,200.00 Rp 6,220.80
0.026 M3 Pasir Pasang @ Rp 175,000.00 Rp 4,550.00
Rp 10,770.80

E.4.2 Tenaga
0.150 Oh Tukang Batu @ Rp 73,500.00 Rp 11,025.00
0.015 Oh Kepala tukang Batu @ Rp 84,500.00 Rp 1,267.50
0.300 Oh Pekerja @ Rp 46,500.00 Rp 13,950.00
0.015 Oh Mandor @ Rp 73,500.00 Rp 1,102.50
Jumlah ( 2 ) Rp 27,345.00
Jumlah ( 1 ) + ( 2 ) Rp 38,115.80

Analisa Biaya Konstruksi 4


F. PEKERJAAN KAYU

F.1 1 M3 PASANG KUSEN PINTU DAN JENDELA KAYU KELAS I


F.1.1 Bahan
1.100 M3 Balok Kayu @ Rp 7,875,000.00 Rp 8,662,500.00
1.250 Kg Paku 10 Cm @ Rp 16,000.00 Rp 20,000.00
1.000 Kg Lem Kayu @ Rp 45,900.00 Rp 45,900.00
Jumlah ( 1 ) Rp 8,728,400.00

F.1.2 Tenaga
21.000 Oh Tukang Kayu @ Rp 74,500.00 Rp 1,564,500.00
2.100 Oh Kepala tukang kayu @ Rp 84,500.00 Rp 177,450.00
7.000 Oh Pekerja @ Rp 46,500.00 Rp 325,500.00
0.350 Oh Mandor @ Rp 73,500.00 Rp 25,725.00
Jumlah ( 2 ) Rp 2,093,175.00
Jumlah ( 1 ) + ( 2 ) Rp 10,821,575.00

F.2 1 M2 PASANG PINTU PANEL KAYU KELAS I


F.2.1 Bahan
0.040 M3 Papan Kayu KLs I @ Rp 10,500,000.00 Rp 420,000.00
0.500 Kg Lem Kayu @ Rp 45,900.00 Rp 22,950.00
Jumlah ( 1 ) Rp 442,950.00

F.2.2 Tenaga
3.000 Oh Tukang kayu @ Rp 74,500.00 Rp 223,500.00
0.300 Oh Kepala tukang kayu @ Rp 84,500.00 Rp 25,350.00
1.000 Oh Pekerja @ Rp 46,500.00 Rp 46,500.00
0.050 Oh Mandor @ Rp 73,500.00 Rp 3,675.00
Jumlah ( 2 ) Rp 299,025.00
Jumlah ( 1 ) + ( 2 ) Rp 741,975.00

F.3 1 M2 PASANG PINTU KLAMP KAYU KELAS II


F.3.1 Bahan
0.040 M3 Papan Kayu @ Rp 3,281,250.00 Rp 131,250.00
0.050 Kg Paku biasa 1" - 5" @ Rp 16,000.00 Rp 800.00
Jumlah ( 1 ) Rp 132,050.00
F.3.2 Tenaga
1.050 Oh Tukang Kayu @ Rp 74,500.00 Rp 78,225.00
0.105 Oh Kepala tukang kayu @ Rp 84,500.00 Rp 8,872.50
0.350 Oh Pekerja @ Rp 46,500.00 Rp 16,275.00
0.018 Oh Mandor @ Rp 73,500.00 Rp 1,323.00
Jumlah ( 2 ) Rp 104,695.50
Jumlah ( 1 ) + ( 2 ) Rp 236,745.50

F.4 1 M2 PASANG PINTU DAN JENDELA KACA KAYU KELAS I ATAU KELAS II
F.4.1 Bahan
0.024 M3 Papan Kayu KLs II @ Rp 3,281,250.00 Rp 78,750.00
0.300 Kg Lem Kayu @ Rp 45,900.00 Rp 13,770.00
Jumlah ( 1 ) Rp 92,520.00
F.4.2 Tenaga
2.400 Oh Tukang Kayu @ Rp 74,500.00 Rp 178,800.00
0.240 Oh Kepala tukang kayu @ Rp 84,500.00 Rp 20,280.00
0.800 Oh Pekerja @ Rp 46,500.00 Rp 37,200.00
0.040 Oh Mandor @ Rp 73,500.00 Rp 2,940.00
Jumlah ( 2 ) Rp 239,220.00
Jumlah ( 1 ) + ( 2 ) Rp 331,740.00

F.5 1M' PASANG LISTPLANK UKURAN ( 2 X 30 ) CM, WOODPLANK


F.56.1 Bahan
1.00 m' Papan Woodplank @ Rp 26,250.00 Rp 26,250.00
0.100 Kg Skrup @ Rp 25,000.00 Rp 2,500.00
Jumlah ( 1 ) Rp 28,750.00
F.5.2 Tenaga
0.200 oh Tukang Kayu @ Rp 74,500.00 Rp 14,900.00
0.025 oh Kepala tukang kayu @ Rp 84,500.00 Rp 2,112.50
0.100 oh Pekerja @ Rp 46,500.00 Rp 4,650.00
0.005 oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah ( 2 ) Rp 22,030.00
Jumlah ( 1 ) + ( 2 ) Rp 50,780.00

Analisa Biaya Konstruksi 5


G. PEKERJAAN BETON

G.1 1 M MEMBUAT LANTAI KERJA BETON MUTU Fc = 7.4 Mpa (K 100), Slump (3-6)CM, w/c = 0.87
G.1.1 Bahan
230.000 Kg Semen @ Rp 1,200.00 Rp 276,000.00
0.638 m Pasir @ Rp 155,000.00 Rp 98,867.86
0.761 m Kerikil ( maksimum 30 mm) @ Rp 225,000.00 Rp 171,166.67
Jumlah (1) Rp 546,034.52
G.1.2 Tenaga
1.200 Oh Pekerja @ Rp 46,500.00 Rp 55,800.00
0.200 Oh Tukang Batu @ Rp 73,500.00 Rp 14,700.00
0.020 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,690.00
0.060 Oh Mandor @ Rp 73,500.00 Rp 4,410.00
Jumlah (2) Rp 76,600.00
Jumlah (1) + (2) Rp 622,634.52

6.5 1 M MEMBUAT BETON MUTU Fc = 9,8 Mpa (K 125), Slump (122)Cm


6.5.1 Bahan
276.000 Kg Semen @ Rp 1,200.00 Rp 331,200.00
0.591 M3 Pasir @ Rp 155,000.00 Rp 91,671.43
0.750 M3 Kerikil ( maksimum 30 mm) @ Rp 225,000.00 Rp 168,666.67
Jumlah (1) Rp 591,538.10
Tenaga
1.650 Oh Pekerja @ Rp 46,500.00 Rp 76,725.00
0.275 Oh Tukang Batu @ Rp 73,500.00 Rp 20,212.50
0.028 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,366.00
0.083 Oh Mandor @ Rp 73,500.00 Rp 6,100.50
Jumlah (2) Rp 105,404.00
Jumlah (1) + (2) Rp 696,942.10

G.2 1 M MEMBUAT BETON MUTU Fc = 121.7 Mpa (K 225), Slump (122)Cm


G.2.1 Bahan
371.000 Kg Semen @ Rp 1,200.00 Rp 445,200.00
0.499 m Pasir @ Rp 155,000.00 Rp 77,278.57
0.776 m Kerikil ( maksimum 30 mm) @ Rp 225,000.00 Rp 174,500.00
Jumlah (1) Rp 696,978.57
G.2.2 Tenaga
1.650 Oh Pekerja @ Rp 46,500.00 Rp 76,725.00
0.275 Oh Tukang Batu @ Rp 73,500.00 Rp 20,212.50
0.028 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,366.00
0.083 Oh Mandor @ Rp 73,500.00 Rp 6,100.50
Jumlah (2) Rp 105,404.00
Jumlah (1) + (2) Rp 802,382.57

G.3 1 M MEMBUAT BEKESTING UNTUK PONDASI


G.3.1 Bahan
0.040 m Kayu Kelas III @ Rp 1,212,500.00 Rp 48,500.00
0.300 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 4,800.00
0.100 Liter Minyak Bekesting @ Rp 12,500.00 Rp 1,250.00
Jumlah (1) Rp 54,550.00
G.3.2 Tenaga
0.520 Oh Pekerja @ Rp 46,500.00 Rp 24,180.00
0.260 Oh Tukang Batu @ Rp 73,500.00 Rp 19,110.00
0.026 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,197.00
0.026 Oh Mandor @ Rp 73,500.00 Rp 1,911.00
Jumlah (2) Rp 47,398.00
Jumlah (1) + (2) Rp 101,948.00
Untuk 2 x Pakai Rp 50,974.00

Analisa Biaya Konstruksi 6


G.4 1 M PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR
G.4.1 Bahan
10.500 Kg Besi Beton ( Polos / Ulir) @ Rp 10,000.00 Rp 105,000.00
0.150 Kg Kawat Beton @ Rp 17,000.00 Rp 2,550.00
Jumlah (1) Rp 107,550.00
G.4.2 Tenaga
0.070 Oh Pekerja @ Rp 46,500.00 Rp 3,255.00
0.070 Oh Tukang Batu @ Rp 73,500.00 Rp 5,145.00
0.007 Oh Kepala Tukang @ Rp 84,500.00 Rp 591.50
0.004 Oh Mandor @ Rp 73,500.00 Rp 294.00
Jumlah (2) Rp 9,285.50
Jumlah (1) + (2) Rp 116,835.50
Untuk Pembesian 1Kg Rp 11,683.55

G.5 1 M MEMBUAT BEKESTING UNTUK SLOEF


G.5.1 Bahan
0.045 m Kayu Kelas III @ Rp 1,212,500.00 Rp 54,562.50
0.300 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 4,800.00
0.100 Liter Minyak Bekesting @ Rp 12,500.00 Rp 1,250.00
Jumlah (1) Rp 60,612.50

G.5.2 Tenaga
0.520 Oh Pekerja @ Rp 46,500.00 Rp 24,180.00
0.260 Oh Tukang Batu @ Rp 73,500.00 Rp 19,110.00
0.026 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,197.00
0.026 Oh Mandor @ Rp 73,500.00 Rp 1,911.00
Jumlah (2) Rp 47,398.00
Jumlah (1) + (2) Rp 108,010.50
Untuk 2 x Pakai Rp 54,005.25

G.6 1 M MEMBUAT BEKESTING UNTUK KOLOM PRAKTIS


G.6.1 Bahan
0.040 m Kayu Kelas III @ Rp 1,212,500.00 Rp 48,500.00
0.400 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 6,400.00
0.200 Liter Minyak Bekesting @ Rp 12,500.00 Rp 2,500.00
0.015 m Balok Kayu Kelas II @ Rp 3,181,000.00 Rp 47,715.00
2.000 Btg Bambu @ Rp 7,500.00 Rp 15,000.00
Jumlah (1) Rp 120,115.00
G.6.2 Tenaga
0.660 Oh Pekerja @ Rp 46,500.00 Rp 30,690.00
0.330 Oh Tukang Batu @ Rp 73,500.00 Rp 24,255.00
0.033 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,788.50
0.033 Oh Mandor @ Rp 73,500.00 Rp 2,425.50
Jumlah (2) Rp 60,159.00
Jumlah (1) + (2) Rp 180,274.00
Untuk 4 x Pakai Rp 45,068.50

G.7 1 M MEMBUAT BEKESTING UNTUK KOLOM


G.7.1 Bahan
0.040 m Kayu Kelas III @ Rp 1,212,500.00 Rp 48,500.00
0.400 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 6,400.00
0.200 Liter Minyak Bekesting @ Rp 12,500.00 Rp 2,500.00
0.015 m Balok Kayu Kelas II @ Rp 3,181,000.00 Rp 47,715.00
2.000 Btg Bambu @ Rp 7,500.00 Rp 15,000.00
Jumlah (1) Rp 120,115.00
G.7.2 Tenaga
0.660 Oh Pekerja @ Rp 46,500.00 Rp 30,690.00
0.330 Oh Tukang Batu @ Rp 73,500.00 Rp 24,255.00
0.033 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,788.50
0.033 Oh Mandor @ Rp 73,500.00 Rp 2,425.50
Jumlah (2) Rp 60,159.00
Jumlah (1) + (2) Rp 180,274.00
Untuk 2 x Pakai Rp 90,137.00

Analisa Biaya Konstruksi 7


G.8 1 M MEMBUAT BEKESTING UNTUK BALOK
G.8.1 Bahan
0.040 m Kayu Kelas III @ Rp 1,212,500.00 Rp 48,500.00
0.400 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 6,400.00
0.200 Liter Minyak Bekesting @ Rp 12,500.00 Rp 2,500.00
0.018 m Balok Kayu Kelas II @ Rp 3,181,000.00 Rp 57,258.00
2.000 Btg Bambu @ Rp 7,500.00 Rp 15,000.00
Jumlah (1) Rp 129,658.00
G.8.2 Tenaga
0.660 Oh Pekerja @ Rp 46,500.00 Rp 30,690.00
0.330 Oh Tukang Batu @ Rp 73,500.00 Rp 24,255.00
0.033 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,788.50
0.033 Oh Mandor @ Rp 73,500.00 Rp 2,425.50
Jumlah (2) Rp 60,159.00
Jumlah (1) + (2) Rp 189,817.00
Untuk 2 x Pakai Rp 94,908.50

G.9 1 M MEMBUAT BEKESTING UNTUK LANTAI


G.9.1 Bahan
0.040 m Kayu Kelas III @ Rp 1,212,500.00 Rp 48,500.00
0.400 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 6,400.00
0.200 Liter Minyak Bekesting @ Rp 12,500.00 Rp 2,500.00
0.015 m Balok Kayu Kelas II @ Rp 3,181,000.00 Rp 47,715.00
6.000 Btg Bambu @ Rp 7,500.00 Rp 45,000.00
Jumlah (1) Rp 150,115.00
G.9.2 Tenaga
0.660 Oh Pekerja @ Rp 46,500.00 Rp 30,690.00
0.330 Oh Tukang Batu @ Rp 73,500.00 Rp 24,255.00
0.033 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,788.50
0.033 Oh Mandor @ Rp 73,500.00 Rp 2,425.50
Jumlah (2) Rp 60,159.00
Jumlah (1) + (2) Rp 210,274.00
Untuk 2 x Pakai Rp 105,137.00

G.10 1 M MEMBUAT BEKESTING UNTUK DINDING


G.10.1 Bahan
0.030 m Kayu Kelas III @ Rp 1,212,500.00 Rp 36,375.00
0.400 Kg Paku 5 Cm - 10 Cm @ Rp 16,000.00 Rp 6,400.00
0.200 Liter Minyak Bekesting @ Rp 12,500.00 Rp 2,500.00
0.020 m Balok Kayu Kelas II @ Rp 3,181,000.00 Rp 63,620.00
3.000 Btg Bambu @ Rp 7,500.00 Rp 22,500.00
4.000 Buah Formite/Penjaga Jarak Bekesting @ Rp Rp -
Jumlah (1) Rp 131,395.00
G.10.2 Tenaga
0.660 Oh Pekerja @ Rp 46,500.00 Rp 30,690.00
0.330 Oh Tukang Batu @ Rp 73,500.00 Rp 24,255.00
0.033 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,788.50
0.033 Oh Mandor @ Rp 73,500.00 Rp 2,425.50
Jumlah (2) Rp 60,159.00
Jumlah (1) + (2) Rp 191,554.00
Untuk 2 x Pakai Rp 95,777.00

H. PEKERJAAN LANTAI KERAMIK DAN KERAMIK DINDING

H.1 1 M MEMASANG LANTAI KERAMIK UKURAN (40 X 40) CM

H.1.1 Bahan
6.630 Buah Keramik 40x40 @ Rp 9,843.67 Rp 65,263.51
9.800 Kg Semen @ Rp 1,200.00 Rp 11,760.00
0.045 m Pasir @ Rp 175,000.00 Rp 7,875.00
1.300 Kg Semen Warna @ Rp 2,250.00 Rp 2,925.00
Jumlah (1) Rp 87,823.51
H.1.2 Tenaga
0.250 Oh Pekerja @ Rp 46,500.00 Rp 11,625.00
0.125 Oh Tukang Batu @ Rp 73,500.00 Rp 9,187.50
0.013 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,098.50
0.013 Oh Mandor @ Rp 73,500.00 Rp 955.50
Jumlah (2) 22,866.50
Jumlah (1) + (2) 110,690.01

Analisa Biaya Konstruksi 8


H.2 1 M MEMASANG LANTAI KERAMIK UKURAN (30 X 30) CM

H.2.1 Bahan
11.870 Buah Keramik 30x30 @ Rp 3,500.00 Rp 41,545.00
10.000 Kg Semen @ Rp 1,200.00 Rp 12,000.00
0.045 m Pasir @ Rp 175,000.00 Rp 7,875.00
1.500 Kg Semen Warna @ Rp 2,250.00 Rp 3,375.00
Jumlah (1) Rp 64,795.00
H.2.2 Tenaga
0.700 Oh Pekerja @ Rp 46,500.00 Rp 32,550.00
0.350 Oh Tukang Batu @ Rp 73,500.00 Rp 25,725.00
0.035 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,957.50
0.035 Oh Mandor @ Rp 73,500.00 Rp 2,572.50
Jumlah (2) 63,805.00
Jumlah (1) + (2) 128,600.00

H.3 1 M MEMASANG LANTAI KERAMIK UKURAN (20 X 20) CM

H.3.1 Bahan
26.500 Buah Keramik 20x20 @ Rp 1,500.00 Rp 39,750.00
10.400 Kg Semen @ Rp 1,200.00 Rp 12,480.00
0.045 m Pasir @ Rp 175,000.00 Rp 7,875.00
1.620 Kg Semen Warna @ Rp 2,250.00 Rp 3,645.00
Jumlah (1) Rp 63,750.00
H.3.2 Tenaga
0.700 Oh Pekerja @ Rp 46,500.00 Rp 32,550.00
0.350 Oh Tukang Batu @ Rp 73,500.00 Rp 25,725.00
0.035 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,957.50
0.035 Oh Mandor @ Rp 73,500.00 Rp 2,572.50
Jumlah (2) 63,805.00
Jumlah (1) + (2) 127,555.00
H.4 1 M MEMASANG DINDING KERAMIK UKURAN ( 20 X 25 ) CM

H.4.1 Bahan
22.000 Buah Keramik Aristik @ Rp 2,490.00 Rp 54,780.00
8.190 Kg Semen @ Rp 1,200.00 Rp 9,828.00
0.045 m Pasir @ Rp 175,000.00 Rp 7,875.00
2.750 Kg Semen Warna @ Rp 2,250.00 Rp 6,187.50
Jumlah (1) Rp 78,670.50
H.4.2 Tenaga
0.700 Oh Pekerja @ Rp 46,500.00 Rp 32,550.00
0.350 Oh Tukang Batu @ Rp 73,500.00 Rp 25,725.00
0.035 Oh Kepala Tukang @ Rp 84,500.00 Rp 2,957.50
0.035 Oh Mandor @ Rp 73,500.00 Rp 2,572.50
Jumlah (2) 63,805.00
Jumlah (1) + (2) 142,475.50

I PEKERJAAN BESI, ALUMUNIUM, PLAFOND DAN KONSTRUKSI PENUTUP

I.1 1 KG MEMASANG BESI PROFIL

I.1.1 Bahan
1.150 Kg Besi Profil Siku 50.50.5 @ Rp 5,685.23 Rp 6,538.02
1.150 Kg Besi Profil Siku 70.70.7 @ Rp 10,372.63 Rp 11,928.52
Jumlah (1) Siku 50.50.5 Rp 6,538.02
Jumlah (1) Siku 70.70.7 Rp 11,928.52
I.1.2 Tenaga
0.060 Oh Pekerja @ Rp 46,500.00 Rp 2,790.00
0.060 Oh Tukang Las @ Rp 66,500.00 Rp 3,990.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.003 Oh Mandor @ Rp 73,500.00 Rp 220.50
Jumlah ( 2 ) Rp 7,507.50
Siku 50.50.5 Rp 14,045.52
Siku 70.70.7 Rp 19,436.02

Analisa Biaya Konstruksi 9


I.2 1M MEMASANG ROLLING DOOR ALUMUNIUM

I.2.1 Bahan
1.000 m Rolling Door Alumunium @ Rp 500,000.00 Rp 500,000.00
Jumlah (1) 500,000.00
I.2.2 Tenaga
1.000 Oh Pekerja @ Rp 46,500.00 Rp 46,500.00
1.000 Oh Tukang Aluminium @ Rp 66,500.00 Rp 66,500.00
0.100 Oh Kepala Tukang @ Rp 84,500.00 Rp 8,450.00
0.050 Oh Mandor @ Rp 73,500.00 Rp 3,675.00
Jumlah ( 2 ) Rp 125,125.00
Jumlah (1) + (2) Rp 625,125.00

I.3 1 M2 PEK. RANGKA ATAP BAJA RINGAN


I.3.1 Bahan
3.500 M' Canal C Truss 75 @ Rp 14,000.00 Rp 49,000.00
3.000 M' GOC 0.35 mm (Reng+Skoring Angin) @ Rp 8,250.00 Rp 24,750.00
2.250 M' L Braket @ Rp 14,000.00 Rp 31,500.00
8.000 Bh Dynabolt @ Rp 3,000.00 Rp 24,000.00
25.000 Lbr Self Drilling Screw @ Rp 275.00 Rp 6,875.00
1.000 Ls Alat Bantu @ Rp 15,000.00 Rp 15,000.00
Jumlah ( 1 ) Rp 151,125.00
I.3.2 Tenaga
0.300 oh Tukang @ Rp 73,500.00 Rp 22,050.00
0.030 oh Kepala tukang @ Rp 84,500.00 Rp 2,535.00
0.300 oh Pekerja @ Rp 46,500.00 Rp 13,950.00
0.015 oh Mandor @ Rp 73,500.00 Rp 1,102.50
Jumlah ( 2 ) Rp 39,637.50
Jumlah ( 1 ) + ( 2 ) Rp 190,762.50

I.4 1M2 PASANG ATAP ZINCALUME (SPANDEK)


I.4.1 Bahan
1.100 m2 Atap Spandek 0,30 mm @ Rp 60,000.00 Rp 66,000.00
6.000 bh Paku skrup+Mur @ Rp 275.00 Rp 1,650.00
Jumlah ( 1 ) Rp 67,650.00
I.4.2 Tenaga
0.006 oh Pekerja @ Rp 46,500.00 Rp 279.00
0.120 oh Tukang @ Rp 73,500.00 Rp 8,820.00
0.060 oh Kepala tukang @ Rp 84,500.00 Rp 5,070.00
0.006 oh Mandor @ Rp 73,500.00 Rp 441.00
Jumlah ( 2 ) Rp 14,610.00
Jumlah ( 1 ) + ( 2 ) Rp 82,260.00

I.5 1M2 PASANG ATAP NOK ZINCALUME


I.5.1 Bahan
1.100 m' Nok Zincalume @ Rp 28,750.00 Rp 31,625.00
6.000 bh Paku skrup+Mur @ Rp 275.00 Rp 1,650.00
Jumlah ( 1 ) Rp 33,275.00
I.5.2 Tenaga
0.150 oh Tukang @ Rp 73,500.00 Rp 11,025.00
0.070 oh Kepala tukang @ Rp 84,500.00 Rp 5,915.00
0.008 oh Pekerja @ Rp 46,500.00 Rp 372.00
0.006 oh Mandor @ Rp 73,500.00 Rp 441.00
Jumlah ( 2 ) Rp 17,753.00
Jumlah ( 1 ) + ( 2 ) Rp 51,028.00

I.6 1 M2 PASANG RANGKA HOLLOW + PLAFOND GYPSUM BOARD 9 mm


I.6.1 Bahan
4.600 m' Besi Hollow 20x40 & 40x40 @ Rp 15,000.00 Rp 69,000.00
0.250 Kg Kawat Penggantung @ Rp 17,000.00 Rp 4,250.00
0.110 Kg Skrup @ Rp 25,000.00 Rp 2,750.00
0.364 Lbr Gypsum Board @ Rp 70,000.00 Rp 25,480.00
Jumlah ( 1 ) Rp 101,480.00
I.6.2 Tenaga
0.050 oh Tukang Plafond @ Rp 73,500.00 Rp 3,675.00
0.005 oh Kepala tukang @ Rp 84,500.00 Rp 422.50
0.100 oh Pekerja @ Rp 46,500.00 Rp 4,650.00
0.005 oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah ( 2 ) Rp 9,115.00
Jumlah ( 1 ) + ( 2 ) Rp 110,595.00

Analisa Biaya Konstruksi 10


I.7 1 M2 PASANG RANGKA HOLLOW + PLAFOND CALSIBOARD 3,5 mm
I.7.1 Bahan
4.600 m' Besi Hollow 20x40 & 40x40 @ Rp 15,000.00 Rp 69,000.00
0.250 Kg Kawat Beton @ Rp 17,000.00 Rp 4,250.00
0.110 Kg Skrup @ Rp 25,000.00 Rp 2,750.00
0.364 Lbr Calsiboard 3,5 mm @ Rp 62,475.00 Rp 22,740.90
Jumlah ( 1 ) Rp 98,740.90
I.7.2 Tenaga
0.050 oh Tukang Plafond @ Rp 73,500.00 Rp 3,675.00
0.005 oh Kepala tukang @ Rp 84,500.00 Rp 422.50
0.100 oh Pekerja @ Rp 46,500.00 Rp 4,650.00
0.005 oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah ( 2 ) Rp 9,115.00
Jumlah ( 1 ) + ( 2 ) Rp 107,855.90

J PEKERJAAN PIPA DAN SANITER

J.1 1 BH MEMASANG KLOSET DUDUK/MONOBLOK

J.1.1 Bahan
1.000 Bh Kloset Duduk/Monoblok @ Rp 1,706,000.00 Rp 1,706,000.00
6.000 % Perlengkapan @ Rp 102,360.00 Rp 102,360.00
Jumlah (1) Rp 1,808,360.00
J.1.2 Tenaga
3.000 Oh Pekerja @ Rp 46,500.00 Rp 139,500.00
1.100 Oh Tukang Batu @ Rp 73,500.00 Rp 80,850.00
0.001 Oh Kepala Tukang @ Rp 84,500.00 Rp 84.50
0.160 Oh Mandor @ Rp 73,500.00 Rp 11,760.00
Jumlah (2) Rp 232,194.50
Jumlah (1) + (2) Rp 2,040,554.50

J.2 1 BH MEMASANG KLOSET JONGKOK PORSELEN

J.2.1 Bahan
1.000 Bh Kloset Jongkok Porselen @ Rp 242,000.00 Rp 242,000.00
6.000 Kg Semen Portland @ Rp 1,200.00 Rp 7,200.00
0.010 m Pasir Pasang @ Rp 175,000.00 Rp 1,750.00
Jumlah (1) Rp 250,950.00
J.1.2 Tenaga
1.000 Oh Pekerja @ Rp 46,500.00 Rp 46,500.00
1.500 Oh Tukang Batu @ Rp 73,500.00 Rp 110,250.00
1.500 Oh Kepala Tukang @ Rp 84,500.00 Rp 126,750.00
0.160 Oh Mandor @ Rp 73,500.00 Rp 11,760.00
Jumlah (2) Rp 295,260.00
Jumlah (1) + (2) Rp 546,210.00

J.4 1 BH MEMASANG 1 BUAH URINIOR

J.4.1 Bahan
1.000 Bh Urinoir @ Rp 918,000.00 Rp 918,000.00
30.00 % Perlengkapan dari nilai Material @ Rp 9,180.00 Rp 275,400.00
6.000 Kg Semen Portland @ Rp 1,200.00 Rp 7,200.00
0.010 m Pasir Pasang @ Rp 175,000.00 Rp 1,750.00
Jumlah (1) Rp 1,202,350.00
J.4.2 Tenaga
1.000 Oh Pekerja @ Rp 46,500.00 Rp 46,500.00
1.000 Oh Tukang Batu @ Rp 73,500.00 Rp 73,500.00
0.100 Oh Kepala Tukang @ Rp 84,500.00 Rp 8,450.00
0.100 Oh Mandor @ Rp 73,500.00 Rp 7,350.00
Jumlah (2) Rp 135,800.00
Jumlah (1) + (2) Rp 1,338,150.00

Analisa Biaya Konstruksi 11


J.23 1M' MEMASANG PIPA GIP DIAMETER 3 "

J.23.1 Bahan
1.200 m' Pipa GIP @ Rp 126,866.67 Rp 152,240.00
35.00 % Perlengkapan dari Nilai Material @ Rp 1,268.67 Rp 44,403.33
Jumlah (1) Rp 196,643.33
J.23.2 Tenaga
0.108 Oh Pekerja @ Rp 46,500.00 Rp 5,022.00
0.180 Oh Tukang @ Rp 73,500.00 Rp 13,230.00
0.018 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,521.00
0.005 Oh Mandor @ Rp 73,500.00 Rp 396.90
Jumlah (2) Rp 20,169.90
Jumlah (1) + (2) Rp 216,813.23

J.2 1M' MEMASANG PIPA UNION UNTUK KABEL DIAMETER 5/8 "

J.2.1 Bahan
1.200 m' Pipa Union Untuk Kabel @ Rp 1,625.00 Rp 1,950.00
35.00 % Perlengkapan dari Nilai Material @ Rp 16.25 Rp 568.75
Jumlah (1) Rp 2,518.75
J.2.2 Tenaga
0.036 Oh Pekerja @ Rp - Rp -
0.060 Oh Tukang Batu @ Rp - Rp -
0.006 Oh Kepala Tukang @ Rp - Rp -
0.002 Oh Mandor @ Rp - Rp -
Jumlah (2) Rp -
Jumlah (1) + (2) Rp 2,518.75

J.3 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 1/2 "

J.3.1 Bahan
1.200 m' Pipa PVC @ Rp 1,750.00 Rp 2,100.00
35.00 % Perlengkapan dari Nilai Material @ Rp 17.50 Rp 612.50
Jumlah (1) Rp 2,712.50
J.3.2 Tenaga
0.036 Oh Pekerja @ Rp 46,500.00 Rp 1,674.00
0.060 Oh Tukang Batu @ Rp 73,500.00 Rp 4,410.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.002 Oh Mandor @ Rp 73,500.00 Rp 132.30
Jumlah (2) Rp 6,723.30
Jumlah (1) + (2) Rp 9,435.80

J.4 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 3/4 "

J.4.1 Bahan
1.200 m' Pipa PVC @ Rp 2,400.00 Rp 2,880.00
35.00 % Perlengkapan dari Nilai Material @ Rp 24.00 Rp 840.00
Jumlah (1) Rp 3,720.00
J.4.2 Tenaga
0.036 Oh Pekerja @ Rp 46,500.00 Rp 1,674.00
0.060 Oh Tukang Batu @ Rp 73,500.00 Rp 4,410.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.002 Oh Mandor @ Rp 73,500.00 Rp 132.30
Jumlah (2) Rp 6,723.30
Jumlah (1) + (2) Rp 10,443.30

J.5 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 1 "

J.5.1 Bahan
1.200 m' Pipa PVC @ Rp 3,266.67 Rp 3,920.00
35.00 % Perlengkapan dari Nilai Material @ Rp 32.67 Rp 1,143.33
Jumlah (1) Rp 5,063.33
J.5.2 Tenaga
0.036 Oh Pekerja @ Rp 46,500.00 Rp 1,674.00
0.060 Oh Tukang Batu @ Rp 73,500.00 Rp 4,410.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.002 Oh Mandor @ Rp 73,500.00 Rp 132.30
Jumlah (2) Rp 6,723.30
Jumlah (1) + (2) Rp 11,786.63

Analisa Biaya Konstruksi 12


J.6 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 1 1/2 "

J.6.1 Bahan
1.200 m' Pipa PVC @ Rp 5,466.67 Rp 6,560.00
35.00 % Perlengkapan dari Nilai Material @ Rp 54.67 Rp 1,913.33
Jumlah (1) Rp 8,473.33
J.6.2 Tenaga
0.036 Oh Pekerja @ Rp 46,500.00 Rp 1,674.00
0.060 Oh Tukang Batu @ Rp 73,500.00 Rp 4,410.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.002 Oh Mandor @ Rp 73,500.00 Rp 132.30
Jumlah (2) Rp 6,723.30
Jumlah (1) + (2) Rp 15,196.63

J.7 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 2 "

J.7.1 Bahan
1.200 m' Pipa PVC @ Rp 7,650.00 Rp 9,180.00
35.00 % Perlengkapan dari Nilai Material @ Rp 76.50 Rp 2,677.50
Jumlah (1) Rp 11,857.50
J.8 Tenaga
0.054 Oh Pekerja @ Rp 46,500.00 Rp 2,511.00
0.090 Oh Tukang Batu @ Rp 73,500.00 Rp 6,615.00
0.009 Oh Kepala Tukang @ Rp 84,500.00 Rp 760.50
0.003 Oh Mandor @ Rp 73,500.00 Rp 198.45
Jumlah (2) Rp 10,084.95
Jumlah (1) + (2) Rp 21,942.45

J.9 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 2 1/2 "

J.9.1 Bahan
1.200 m' Pipa PVC @ Rp 9,833.33 Rp 11,800.00
35.00 % Perlengkapan dari Nilai Material @ Rp 98.33 Rp 3,441.67
Jumlah (1) Rp 15,241.67
J.9.2 Tenaga
0.036 Oh Pekerja @ Rp 46,500.00 Rp 1,674.00
0.060 Oh Tukang Batu @ Rp 73,500.00 Rp 4,410.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.002 Oh Mandor @ Rp 73,500.00 Rp 132.30
Jumlah (2) Rp 6,723.30
Jumlah (1) + (2) Rp 21,964.97

J.10 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 3 "

J.10.1 Bahan
1.200 m' Pipa PVC @ Rp 12,016.67 Rp 14,420.00
35.00 % Perlengkapan dari Nilai Material @ Rp 120.17 Rp 4,205.83
Jumlah (1) Rp 18,625.83
J.10.2 Tenaga
0.081 Oh Pekerja @ Rp 46,500.00 Rp 3,766.50
0.135 Oh Tukang Batu @ Rp 73,500.00 Rp 9,922.50
0.014 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,140.75
0.0041 Oh Mandor @ Rp 73,500.00 Rp 301.35
Jumlah (2) Rp 15,131.10
Jumlah (1) + (2) Rp 33,756.93

J.11 1M' MEMASANG PIPA PVC TIPE AW DIAMETER 4 "

J.11.1 Bahan
1.200 m' Pipa PVC @ Rp 18,583.33 Rp 22,300.00
35.00 % Perlengkapan dari Nilai Material @ Rp 185.83 Rp 6,504.17
Jumlah (1) Rp 28,804.17
J.11.2 Tenaga
0.081 Oh Pekerja @ Rp 46,500.00 Rp 3,766.50
0.135 Oh Tukang Batu @ Rp 73,500.00 Rp 9,922.50
0.014 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,140.75
0.0041 Oh Mandor @ Rp 73,500.00 Rp 301.35
Jumlah (2) Rp 15,131.10
Jumlah (1) + (2) Rp 43,935.27

Analisa Biaya Konstruksi 13


J.12 1 BH MEMASANG KRAN DIAMETER 3/4 " ATAU 1/2 "

J.12.1 Bahan
1.000 Bh Kran Air @ Rp 13,500.00 Rp 13,500.00
0.250 Bh Seal Tape @ Rp 2,000.00 Rp 500.00
Jumlah (1) Rp 14,000.00
J.12.2 Tenaga
0.010 Oh Pekerja @ Rp 46,500.00 Rp 465.00
0.100 Oh Tukang Batu @ Rp 73,500.00 Rp 7,350.00
0.010 Oh Kepala Tukang @ Rp 84,500.00 Rp 845.00
0.005 Oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah (2) Rp 9,027.50
Jumlah (1) + (2) Rp 23,027.50

J.13 1 BH MEMASANG FLOOR DRAIN

J.13.1 Bahan
1.000 Bh Floor Drain @ Rp 27,500.00 Rp 27,500.00
Jumlah (1) Rp 27,500.00
J.13.2 Tenaga
0.010 Oh Pekerja @ Rp 46,500.00 Rp 465.00
0.100 Oh Tukang Batu @ Rp 73,500.00 Rp 7,350.00
0.010 Oh Kepala Tukang @ Rp 84,500.00 Rp 845.00
0.005 Oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah (2) Rp 9,027.50
Jumlah (1) + (2) Rp 36,527.50

K PEKERJAAN KUNCI DAN KACA

K. 1 1 BH MEMASANG KUNCI TANAM ANTIK

K.1.1 Bahan
1.000 Bh Kunci Tanam 2x Putar @ Rp 102,000.00 Rp 102,000.00
Jumlah (1) Rp 102,000.00
K.1.2 Tenaga
0.060 Oh Pekerja @ Rp 46,500.00 Rp 2,790.00
0.600 Oh Tukang Kayu @ Rp 74,500.00 Rp 44,700.00
0.060 Oh Kepala Tukang @ Rp 84,500.00 Rp 5,070.00
0.003 Oh Mandor @ Rp 73,500.00 Rp 220.50
Jumlah ( 2 ) Rp 52,780.50
Jumlah (1 ) + ( 2 ) Rp 154,780.50

K. 2 1 BH MEMASANG KUNCI TANAM BIASA

K.2.1 Bahan
1.000 Bh Kunci 2X Slag @ Rp 62,000.00 Rp 62,000.00
Rp Jumlah (1) Rp 62,000.00
K.2.2 Tenaga
0.010 Oh Pekerja @ Rp 46,500.00 Rp 465.00
0.500 Oh Tukang Kayu @ Rp 74,500.00 Rp 37,250.00
0.010 Oh Kepala Tukang @ Rp 84,500.00 Rp 845.00
0.005 Oh Mandor @ Rp 73,500.00 Rp 367.50
Jumlah ( 2 ) Rp 38,927.50
Jumlah (1 ) + ( 2 ) Rp 100,927.50

K. 3 1 BH MEMASANG KUNCI KAMAR MANDI

K.3.1 Bahan
1.000 Bh Kunci Kamar Mandi @ Rp 62,000.00 Rp 62,000.00
Rp Jumlah (1) Rp 62,000.00
K.3.2 Tenaga
0.005 Oh Pekerja @ Rp 46,500.00 Rp 232.50
0.500 Oh Tukang Kayu @ Rp 74,500.00 Rp 37,250.00
0.005 Oh Kepala Tukang @ Rp 84,500.00 Rp 422.50
0.0025 Oh Mandor @ Rp 73,500.00 Rp 183.75
Jumlah ( 2 ) Rp 38,088.75
Jumlah (1 ) + ( 2 ) Rp 100,088.75

Analisa Biaya Konstruksi 14


K. 4 1 BH MEMASANG LEMARI MUTU BAIK

K.4.1 Bahan
1.000 Bh Kunci lemari mutu baik @ Rp 15,500.00 Rp 15,500.00
Rp Jumlah (1) Rp 15,500.00
K.4.2 Tenaga
0.005 Oh Pekerja @ Rp 46,500.00 Rp 232.50
0.500 Oh Tukang Kayu @ Rp 74,500.00 Rp 37,250.00
0.005 Oh Kepala Tukang @ Rp 84,500.00 Rp 422.50
0.0025 Oh Mandor @ Rp 73,500.00 Rp 183.75
Jumlah ( 2 ) Rp 38,088.75
Jumlah (1 ) + ( 2 ) Rp 53,588.75

K. 5 1 BH MEMASANG ENGSEL PINTU

K.5.1 Bahan
1.000 Bh Engsel Pintu @ Rp 32,500.00 Rp 32,500.00
Rp Jumlah (1) Rp 32,500.00
K.5.2 Tenaga
0.015 Oh Pekerja @ Rp 46,500.00 Rp 697.50
0.150 Oh Tukang Kayu @ Rp 74,500.00 Rp 11,175.00
0.015 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,267.50
0.00075 Oh Mandor @ Rp 73,500.00 Rp 55.13
Jumlah ( 2 ) Rp 13,195.13
Jumlah (1 ) + ( 2 ) Rp 45,695.13

K. 7 1 BH MEMASANG ENGSEL JENDELA

K.7.1 Bahan
1.000 Bh Engsel Jendela @ Rp 26,000.00 Rp 26,000.00
Rp Jumlah (1) Rp 26,000.00
K.7.2 Tenaga
0.020 Oh Pekerja @ Rp 46,500.00 Rp 930.00
0.200 Oh Tukang Kayu @ Rp 74,500.00 Rp 14,900.00
0.020 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,690.00
0.010 Oh Mandor @ Rp 73,500.00 Rp 735.00
Jumlah ( 2 ) Rp 18,255.00
Jumlah (1 ) + ( 2 ) Rp 44,255.00

K. 8 1 BH MEMASANG PEGANGAN PINTU / DOOR HOLDER

K.8.1 Bahan
1.000 Bh Door Holder @ Rp 46,500.00 Rp 46,500.00
Rp Jumlah (1) Rp 46,500.00
K.8.2 Tenaga
0.050 Oh Pekerja @ Rp 46,500.00 Rp 2,325.00
0.500 Oh Tukang Kayu @ Rp 74,500.00 Rp 37,250.00
0.050 Oh Kepala Tukang @ Rp 84,500.00 Rp 4,225.00
0.0025 Oh Mandor @ Rp 73,500.00 Rp 183.75
Jumlah ( 2 ) Rp 43,983.75
Jumlah (1 ) + ( 2 ) Rp 90,483.75

K. 9 1 M MEMASANG KACA , TEBAL 5 mm

K.9.1 Bahan
1.100 m Kaca 5 mm @ Rp 82,000.00 Rp 90,200.00
Rp Jumlah (1) Rp 90,200.00
K.9.2 Tenaga
0.015 Oh Pekerja @ Rp 46,500.00 Rp 697.50
0.150 Oh Tukang Kayu @ Rp 74,500.00 Rp 11,175.00
0.015 Oh Kepala Tukang @ Rp 84,500.00 Rp 1,267.50
0.00075 Oh Mandor @ Rp 73,500.00 Rp 55.13
Jumlah ( 2 ) Rp 13,195.13
Jumlah (1 ) + ( 2 ) Rp 103,395.13

Analisa Biaya Konstruksi 15


L PEKERJAAN PENGECATAN

L.1 1 M PENGECATAN BIDANG KAYU BARU ( 1 LAPIS PLAMIR) , 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
L.1.1 Bahan
0.200 Kg Cat meni @ Rp 19,600.00 Rp 3,920.00
0.150 Kg Plamir @ Rp 26,500.00 Rp 3,975.00
0.170 Kg Cat Dasar @ Rp 47,200.00 Rp 8,024.00
0.260 Kg Cat Penutup 2 Kali @ Rp 47,200.00 Rp 12,272.00
Jumlah ( 1 ) Rp 28,191.00
L.1.2 Tenaga
0.070 Oh Pekerja @ Rp 46,500.00 Rp 3,255.00
0.009 Oh Tukang Cat @ Rp 73,500.00 Rp 661.50
0.0060 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.0025 Oh Mandor @ Rp 73,500.00 Rp 183.75
Jumlah ( 2 ) Rp 4,607.25
Jumlah ( 1 ) + ( 2 ) Rp 32,798.25

L.2 1 M PENGECATAN TEMBOK BARU ( 1 LAPIS PLAMUR , 1 LAPIS CAT DASAR , 2 LAPIS CAT PENUTUP )
L.2.1 Bahan
0.100 Kg Plamur @ Rp 26,500.00 Rp 2,650.00
0.100 Kg Cat Dasar @ Rp 13,000.00 Rp 1,300.00
0.260 Kg Cat Penutup 2 X @ Rp 13,000.00 Rp 3,380.00
Jumlah ( 1 ) Rp 7,330.00
L.2.2 Tenaga
0.020 Oh Pekerja @ Rp 46,500.00 Rp 930.00
0.063 Oh Tukang Cat @ Rp 73,500.00 Rp 4,630.50
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 532.35
0.0025 Oh Mandor @ Rp 73,500.00 Rp 183.75
Jumlah ( 2 ) Rp 6,276.60
Jumlah ( 1 ) + ( 2 ) Rp 13,606.60

M PEKERJAAN KELISTRIKAN

M.1 1 M' KABEL JARINGAN LISTRIK


M.1.1 Bahan
1.200 m' Kabel Jaringan Listrik NYA 2.5mm @ Rp 14,000.00 Rp 16,800.00
15 % Perlengkapan dari Nilai Material @ Rp 1,400.00 Rp 2,100.00
Jumlah ( 1 ) Rp 18,900.00
M.1.2 Tenaga
0.036 Oh Pekerja @ Rp 46,500.00 Rp 1,674.00
0.060 Oh Tukang Listrik @ Rp 73,500.00 Rp 4,410.00
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 507.00
0.002 Oh Mandor @ Rp 73,500.00 Rp 132.30
Jumlah ( 2 ) Rp 6,723.30
Jumlah ( 1 ) + ( 2 ) Rp 25,623.30

M.2 1 BH MEMASANG PANEL MCB


M.2.1 Bahan
1.000 BH Panel MCB @ Rp 26,250.00 Rp 26,250.00
Jumlah ( 1 ) Rp 26,250.00
M.2.2 Tenaga
0.042 Oh Pekerja @ Rp 46,500.00 Rp 1,965.32
0.085 Oh Tukang Listrik @ Rp 73,500.00 Rp 6,212.93
0.008 Oh Kepala Tukang @ Rp 84,500.00 Rp 714.28
0.008 Oh Mandor @ Rp 73,500.00 Rp 621.29
Jumlah ( 2 ) Rp 9,513.82
Jumlah ( 1 ) + ( 2 ) Rp 35,763.82

M.3 1 BH MEMASANG LAMPU SL 20 WATT


Bahan
M.3.1 1.000 Buah Lampu SL 20 watt @ Rp 43,181.25 Rp 43,181.25
Jumlah ( 1 ) Rp 43,181.25
M.3.2 Tenaga
0.007 Oh Pekerja @ Rp 46,500.00 Rp 336.91
0.014 Oh Tukang Listrik @ Rp 73,500.00 Rp 1,065.07
0.001 Oh Kepala Tukang @ Rp 84,500.00 Rp 122.45
0.001 Oh Mandor @ Rp 73,500.00 Rp 106.51
Jumlah ( 2 ) Rp 1,630.94
Jumlah ( 1 ) + ( 2 ) Rp 44,812.19

Analisa Biaya Konstruksi 16


M.4 1 BH MEMASANG LAMPU SL 15 WATT
Bahan
M.4.1 1.000 Buah Lampu SL 15 watt @ Rp 40,096.88 Rp 40,096.88
Jumlah ( 1 ) Rp 40,096.88
M.4.2 Tenaga
0.010 Oh Pekerja @ Rp 46,500.00 Rp 486.65
0.021 Oh Tukang Listrik @ Rp 73,500.00 Rp 1,538.44
0.002 Oh Kepala Tukang @ Rp 84,500.00 Rp 176.87
0.00004 Oh Mandor @ Rp 73,500.00 Rp 3.20
Jumlah ( 2 ) Rp 2,205.15
Jumlah ( 1 ) + ( 2 ) Rp 42,302.03

M.5 1 BH MEMASANG STOP KONTAK 16 Amp.


Bahan
M.5.1 1.000 Buah Stop kontak 16 Amp. @ Rp 14,500.00 Rp 14,500.00
Jumlah ( 1 ) Rp 14,500.00
M.5.2 Tenaga
0.023 Oh Pekerja @ Rp 46,500.00 Rp 1,085.60
0.047 Oh Tukang Listrik @ Rp 73,500.00 Rp 3,431.91
0.005 Oh Kepala Tukang @ Rp 84,500.00 Rp 394.55
0.005 Oh Mandor @ Rp 73,500.00 Rp 343.19
Jumlah ( 2 ) Rp 5,255.25
Jumlah ( 1 ) + ( 2 ) Rp 19,755.25

M.6 1 BH MEMASANG SAKLAR TUNGGAL


Bahan
M.6.1 1.000 Buah Saklar Tunggal @ Rp 10,500.00 Rp 10,500.00
Jumlah ( 1 ) Rp 10,500.00
M.6.2 Tenaga
0.017 Oh Pekerja @ Rp 46,500.00 Rp 786.13
0.034 Oh Tukang Listrik @ Rp 73,500.00 Rp 2,485.17
0.003 Oh Kepala Tukang @ Rp 84,500.00 Rp 285.71
0.003 Oh Mandor @ Rp 73,500.00 Rp 248.52
Jumlah ( 2 ) Rp 3,805.53
Jumlah ( 1 ) + ( 2 ) Rp 14,305.53

M.7 1 BH MEMASANG SAKLAR GANDA


Bahan
M.7.1 1.000 Buah Saklar Ganda @ Rp 15,750.00 Rp 15,750.00
Jumlah ( 1 ) Rp 15,750.00
M.7.2 Tenaga
0.025 Oh Pekerja @ Rp 46,500.00 Rp 1,179.19
0.051 Oh Tukang Listrik @ Rp 73,500.00 Rp 3,727.76
0.005 Oh Kepala Tukang @ Rp 84,500.00 Rp 428.57
0.005 Oh Mandor @ Rp 73,500.00 Rp 372.78
Jumlah ( 2 ) Rp 5,708.29
Jumlah ( 1 ) + ( 2 ) Rp 21,458.29

M.8 1 BH MEMASANG PANIL BOX


Bahan
M.8.1 1.000 Buah Panil Box + Accecories + Lengkap @ Rp 75,000.00 Rp 75,000.00
Jumlah ( 1 ) Rp 75,000.00
M.8.2 Tenaga
0.031 Oh Pekerja @ Rp 46,500.00 Rp 1,459.95
0.063 Oh Tukang Listrik @ Rp 73,500.00 Rp 4,615.32
0.006 Oh Kepala Tukang @ Rp 84,500.00 Rp 530.61
0.006 Oh Mandor @ Rp 73,500.00 Rp 461.53
Jumlah ( 2 ) Rp 7,067.41
Jumlah ( 1 ) + ( 2 ) Rp 82,067.41

Analisa Biaya Konstruksi 17


M.9 1 BH MEMASANG INSTALASI TITIK LAMPU
Bahan
M.9.1 1.000 Buah Fitting Lampu @ Rp 7,500.00 Rp 7,500.00
Jumlah ( 1 ) Rp 7,500.00
M.9.2 Tenaga
0.007 Oh Pekerja @ Rp 46,500.00 Rp 336.91
0.014 Oh Tukang Listrik @ Rp 73,500.00 Rp 1,065.07
0.001 Oh Kepala Tukang @ Rp 84,500.00 Rp 122.45
0.001 Oh Mandor @ Rp 73,500.00 Rp 106.51
Jumlah ( 2 ) Rp 1,630.94
Jumlah ( 1 ) + ( 2 ) Rp 9,130.94

M.10 1 BH MEMASANG INSTALASI STOP KONTAK & SAKLAR


Bahan
M.10.1 1.200 m' Instalasi Kabel NYA 1,5mm @ Rp 3,920.00 Rp 4,704.00
Jumlah ( 1 ) Rp 4,704.00
M.10.2 Tenaga
0.007 Oh Pekerja @ Rp 46,500.00 Rp 336.91
0.014 Oh Tukang Listrik @ Rp 73,500.00 Rp 1,065.07
0.001 Oh Kepala Tukang @ Rp 84,500.00 Rp 122.45
0.001 Oh Mandor @ Rp 73,500.00 Rp 106.51
Jumlah ( 2 ) Rp 1,630.94
Jumlah ( 1 ) + ( 2 ) Rp 6,334.94

Sumber :
* SNI Tahun 2007 Tentang Tata Cara Perhitungan Harga Satuan Pekerjaan Konstruksi
Bangunan Gedung dan Perumahan Departemen Pekerjaan Umum
* Handbook SNI Tahun 2008 Tentang Tata Cara Perhitungan Harga Satuan Pekerjaan Konstruksi
Bangunan Gedung dan Perumahan Badan Standarisasi Nasional

Analisa Biaya Konstruksi 18