Base Plate It is essential the surface is clean and free from oil release or scale.

ease or scale. Air Product Data Sheet


pressure relief holes should be provided to allow venting of any isolated Version 19/07/2012
high spots.
Leveling Shims If these are to be removed after the grout has hardened, they should be
treated with a thin layer of grease.
Formwork The formwork should be constructed to be leak proof. This can be
achieved by using foam rubber strip or mastic sealant beneath the
constructed formwork and between joints. In some cases it is practical to
SikaGrout -214-11 HF2
use sacrificial semi-dry sand and cement formwork. The formwork should Special Non-shrink Cementitious Grout for High Strength and High
include outlets for pre-soaking.
Volume
Unrestrained This must be kept to a minimum gap. Generally the gap width between
Surface Area the perimeter formwork and the plate edge should not exceed 150 mm on
the pouring side and 50 mm on the opposite side. It is advisable where
practical to have no gap at the flank sides. Product SikaGrout -214-11 HF2 is used for special purpose grouting where it
Description is essential to eliminate air when completely filling the void between
Consistency of Grout The quantity of clean water required to be added into a 25 kg of SikaGrout a base plate/formwork and a substrate. Such as application would
Mix -214-11 HF2 is given below to achieve the desired consistency: be the grouting if a stanchion base plate structural reinstatement
The selected water content should be accurately measured into the mixer. works and heavy machinery stabilization work. It can also be used for
The total contents of the SikaGrout -214-11 HF2 bag should be slowly grouting turbine base and anchoring a wide range of fixings. These
added and continuous mixing should take place for 5 minutes. This will include masts, anchor bolts fence posts and bridge plates.
ensure that the grout has a smooth even consistency.
Uses SikaGrout -214-11 HF2 high strength non-shrink cementitious grout is
Notes on Application / All grouting works where its intended to use must be carried out with a supplied as a ready to use dry powder. The addition of a controlled amount
Limitations prepackaged cement based product which is chloride-free. of clean water produces a flowing non-shrink grout for gap thickness up to
100 mm.
It shall be mixed with water to the required consistency. The plastic grout
must not bleed or segregate. SikaGrout -214-11 HF2 is a blend of Portland cement, graded fillers and
chemical additives which impart controlled expansion in the plastic state
The storage, handling and placement of the grout must be in strict whilst minimizing water demand. The low water demand ensures high early
accordance with the manufacturers instruction. strength. The graded filler is designed to assist uniform mixing and produce
Performance a consistent grout.
Characteristics / Reducing gaseous expansion system compensates for shrinkage and set-

@1 day @3 days @7 days @28 days tlement in the plastic state
Advantages
Compressive 65 N/mm2 No metallic iron content to cause staining

40 N/mm2 55 N/mm2 60 N/mm2
Strength (Flowable)  Prepackaged grout overcomes potential on-site batching variations
Compressive 75 N/mm2  Develops high early strength without the use of chlorides
45 N/mm2 60 N/mm2 65 N/mm2  High ultimate strength and low permeability ensure the durability of the
Strength (Plastic)
hardened grout
Flexural strength 2.5 N/mm2 - 9.0 N/mm2 10.0 N/mm2  Against carbon dioxide and chloride diffusion

Tests
Health and Safety
Approval / Standards SikaGrout -214-11 HF2 is a high performance non-shrink cementitious
Information
grout for critical applications which has been independently tested by an
Precautions SikaGrout -214-11 HF2 is alkaline and should not come into contact with accredited laboratory in accordance with the following standards:
skin and eyes. Avoid inhalation of dust during mixing. Gloves, goggles and  ASTM C 109-95
dust mask should be worn. If contact with skin occurs, wash with water.  ASTM C 940
Splashes to eyes should be washed immediately with plenty of clean water  ASTM C 942
and seek medical advice sought.  ASTM C 827-87
Fire SikaGrout -214-11 HF2 is nonflammable
SikaGrout -214-11 HF2 is formulated to comply with ASTM C 1107-91
Grade B.

SikaGrour -214-11 HF2 1/4

SikaGrour -214-11 HF2 4/4 D03712000712E


Application Conditions /
Form
Limitations
Appearance Powder Low Temperature When the air or contact surface temperatures are 5 C or below on a falling
Colour Grey Working thermometer, warm water (30 - 40 C) is recommended to accelerate strength
development.
Packaging 25 kg / bag
For ambient temperatures below 10C the formwork should be kept in
Storage place for at least 36 hours.
Storage Conditions Keep in unopened, undamaged original packaging and protected from Normal precautions for winter working with cementitious materials should
direct sunshine in dry condition. If stored in high temperature and high then be adopted.
humidity locations the shelf life may be reduced. High Temperature At ambient temperatures above 35C cool water (below 20 C) should be
Shelf Life 12 months Working used for used for mixing the grout prior to placement.
Application
Technical Data
Instructions
Yield Allowance should be made for wastage when estimating quantities required. Mixing For best results a mechanically powered grout mixer should be used.
The approximate yield per 25 kg bag for different consistencies is: When quantities up to 50 kg are used, a slow speed drill fitted with a high
 Trowellable: 13.20 shear mixer is suitable. Larger quantities will require a high shear vane
 Flowable: 13.70 mixer. Do not use a colloidal impeller mixer.
Properties W/P ratio To enable the grouting operation to be carried out continuously, it is essential
Plastic: 0.16 - 0.17 that sufficient mixing capacity and labor are available. The use of a grout
Flowable: 0.18 - 0.19 holding tank with provision to gently agitate the grout would be required.
The following results were obtained at a water : powder ratio of 0.15 and Typical Hopper System Removable hopper:
temperature of 25C. Test method of typical result. For larger pours the grout may be hand placed or pumped into a removable
Fresh Wet Density Approximately 2,170 kg/m (Depending on actual Consistency used) hopper (trough).

Youngs Modulus 28 kN/mm ASTM 469-83 Pouring should be from one side of the void to eliminate any air or pre-soaking
water becoming trapped under the base plate. It is advisable to pour the grout
Expansion 0.25% - 1.0% ASTM C 827-84 across the shortest distance of travel. The grout head must be maintained at
all time so that a continuous grout front is achieved.
Time for Expansion
Where large volumes have to be placed SikaGrout -214-11 HF2 may be
Start : 15 Minutes pumped. A heavy duty diaphragm pump is recommended for this purpose.
Finish: 2 Hours Screw feed and piston pumps may also be suitable.
Curing On completion of the grouting operation, exposed areas should be
System thoroughly cured. This should be done by the use of curing membrane,
Information continuous application of water and/or wet Hessian.
Foundation Surface The substrate surface must be free from oil, grease or any loosely adherent Cleaning SikaGrout -214-11 HF2 should be removed from tools and equipment
material. If the concrete surface is defective or has laitance, it must be made with clean water immediately after use. Cured material can be removed
to a sound base. Bolt holes and fixing pockets must be blown clean of any mechanically, or with Sika Clean -20
dirt or debris. Placing At 20C place the grout within 20 minutes of mixing to gain full benefit of
Pre-soaking Several hours to grouting the area of cleaned foundation should be flooded the expansion process.
with fresh water. Immediately before grouting takes place any free standing SikaGrout -214-11 HF2 can be placed in thickness up to 100 mm in a
water should blow out of bolt holes and pockets. single pour when used as an under plate grout. For thicker section it is
necessary to fill out SikaGrout -214-11 HF2 with well graded silt free
aggregate to minimize heat build up, typically a 10mm aggregate is suitable.
Any bolt pockets must be grouted prior to grouting between the substrate
and the base plate.
Continuous grout is essential. Sufficient grout must be prepared before
starting. The time taken to pour a batch must be regulated to the time to
prepare the next one.