DAFTAR SATUAN BAHAN DAN UPAH

KABUPATEN MIMIKA
TAHUN ANGGARAN 2017
NO URAIAN SATUAN
1 2 3
I DAFTAR BAHAN
1 Alat Bantu Ls
2 Semen PC Zak
3 Pasir Beton m3
4 Pasir Pasangan m3
5 Pasir Urug/ Timbunan m3
6 Kerikil Cor / Batu Pecah 2-3 m3
7 Semen Putih Zak
8 Semen Warna Kg
9 Sirtu Timbunan m3
10 Tanah Timbunan m3
11 Batu Kali m3
12 Batu Tela m3
13 Batu Terawang/ Roster Bh
14 Besi Beton U-24 Kg
15 Besi Beton Ulir U-24 Kg
16 Kawat Ikat (Bandrat) Kg
17 Plat Besi Baja Kg
18 Plat Siku L30.30.3 Kg
19 Besi Strip 2x3 Kg
20 Kawat Las Kg
21 Balok Kayu Kelas I (Kayu Besi) m3
22 Balok Kayu Kelas II m3
23 Balok Kayu Kelas III m3
24 Papan Kelas I (2/20 dan 2,5/25) Kayu Besi m3
25 Papan Kelas II (2/20 dan 2,5/25) m3
26 Papan Kelas III (Bekisting dan Bouwplank) m3
27 List Profil m
28 Tripleks 4 mm Lbr
29 Tripleks 9 mm Lbr
30 Teackwood Lbr
31 Formika Lbr
32 Socket Pipa Galvanis 3/4" Bh
33 Lem Pipa Kg
34 Floor Drain Alumnium Bh
35 Stop Kran 1/2" Bh
36 Stop Kran 3/4" Bh
37 Kloset Jongkok (TOTO) Bh
38 Kloset Duduk (TOTO) Set
39 Wastafel Standar (TOTO) Bh
40 Wastafel Lengkap (TOTO) Set
41 Paku Campur Kg
42 Paku Seng Kg
43 Paku Spandek Kg
44 Paku Tripleks Kg
45 Seng Plat BJLS 30 Kg
46 Seng Gelombang BJLS 30 Lbr
47 Seng Plat Bubungan BJLS 30 m
48 Spandek (ZINCALUME / BLUE SCOPE STEEL) m2
49 Nok Spandek (ZINCALUME / BLUE SCOPE STEEL) m
50 Kaca Bening 5mm (ASAHI) m2
51 Paving Block Bh
52 Keramik 10 cm x 20 cm Dos
53 Keramik PC Abu-abu 20 cm x 20 cm Dos
54 Keramik 30 cm x 30 cm Dos
55 Kunci Kuda Terbang 2 Slag Bh
56 Kunci 2 Slag Bh
57 Engsel H Pintu Bh
58 Engsel H Jendela Bh
59 Grendel Pintu Sedang Bh
60 Grendel Jendela Sedang Bh
61 Grendel Tanam Sedang Bh
62 Hak Angin Biasa Bh
63 Kertas Gosok (Amplas) Lbr
64 Plamur (WATER BASE) Kg
65 Dempul Kg
66 Residu (PINO GUARD) Ltr
67 Meni Kayu Kg
68 Cat Tembok (DANA PAINT/ DANA BRITE) Kg
69 Cat Kilat Kayu ( DANA PAINT/ DANA LAC) Kg
70 Cat Besi (DANA PAINT/ DANA LAC) Kg
71 Tinner (DANA GLOSS) Ltr
72 Plitur Teack Oil (DANA WOOD) Ltr
73 Kuas Biasa Bh
74 Kuas Roll Bh
75 Lampu TL (1 x 40 Watt) PHILIPS Set
76 Lampu TL (2 x 40 Watt) PHILIPS Set
77 Lampu TL (1 x 20 Watt) PHILIPS Set
78 Lampu Philips XL 20 Watt Set
79 Saklar Tunggal (CLIPSAL) Set
80 Saklar Gandan (CLIPSAL) Set
81 Stop Kontak (CLIPSAL) Set
82 Kabel NYM 2,5mm m
83 Klem Kabel Bh
84 Mangkok Saklar Bh
85 Minyak Bekisting Ltr
II DAFTAR UPAH
1 Mandor Oh
2 Kepala Tukang Oh
3 Tukang Oh
4 Pekerja Oh
UPAH

HARGA (Rp.)
4

50,000.00
85,000.00
950,000.00
950,000.00
900,000.00
950,000.00
150,000.00
11,500.00
475,000.00
450,000.00
950,000.00
3,500.00
14,000.00
35,500.00
32,500.00
35,000.00
365,000.00
156,000.00
68,500.00
45,000.00
3,800,000.00
3,000,000.00
2,350,000.00
3,800,000.00
3,000,000.00
2,350,000.00
8,500.00
115,000.00
145,000.00
105,000.00
175,000.00
8,500.00
25,000.00
85,000.00
75,000.00
95,000.00
350,000.00
1,800,000.00
900,000.00
1,300,000.00
25,000.00
30,000.00
20,000.00
25,000.00
65,000.00
65,000.00
35,000.00
300,000.00
75,000.00
150,000.00
2,000.00
50,000.00
60,000.00
58,000.00
75,000.00
150,000.00
24,000.00
18,000.00
15,000.00
15,000.00
15,000.00
8,000.00
5,000.00
25,500.00
35,800.00
28,000.00
26,000.00
35,500.00
45,000.00
50,000.00
27,000.00
55,000.00
15,000.00
17,500.00
45,000.00
125,000.00
39,000.00
40,000.00
27,000.00
45,000.00
35,000.00
14,500.00
5,000.00
3,000.00
20,000.00

200,000.00
150,000.00
135,000.00
115,000.00
ANALISA HARGA SATUAN
KABUPATEN MIMIKA
TAHUN ANNGARAN 2017

HARGA UPAH
NO URAIAN PEKERJAAN
(Rp.)

ANALISA BIAYA KONSTRUKSI PEKERJAAN PERSIAPAN


1 1 M2 PEMBERSIHAN LOKASI
0.1000 H.o Pekerja 115,000.00
0.0100 H.o Mandor 200,000.00
0.0010 Ls Alat Bantu

2 1 M' PASANGAN BOUWPLANK


0.0120 M3 Papan Kayu Matoa
0.1000 Gloss Benang
0.0100 Kg Paku Campur
0.0400 H.o Pekerja 115,000.00
0.0600 H.o Tukang 135,000.00
0.0060 H.o Kepala Tukang 150,000.00
0.0030 H.o Mandor 200,000.00

3 1 M3 URUGAN KEMBALI
0.1920 H.o Pekerja 115,000.00
0.0190 H.o Mandor 200,000.00

4 1 M3 PEMADATAN TANAH
0.5000 H.o Pekerja 115,000.00
0.0500 H.o Mandor 200,000.00

5 1 M3 URUGAN PASIR
1.2000 M3 Pasir Urug
0.3000 H.o Pekerja 115,000.00
0.0100 H.o Mandor 200,000.00

6 1 M3 URUGAN SIRTU
1.2000 M3 Sirtu
0.2500 H.o Pekerja 115,000.00
0.0250 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN PONDASI


1 1 M3 GALIAN TANAH BIASA
0.7500 H.o Pekerja 115,000.00
0.0250 H.o Mandor 200,000.00
2 1 M3 PASANGAN BATU KOSONG
0.4320 M3 Pasir Urug
1.2000 M3 Batu Kali
0.7800 H.o Pekerja 115,000.00
0.3900 H.o Tukang Batu 135,000.00
0.0390 H.o Kepala Tukang 150,000.00
0.0390 H.o Mandor 200,000.00

3 1 M3 PASANGAN PONDASI BATU KALI 1 : 4


0.5200 M3 Pasir Pasangan
1.2000 M3 Batu Kali
3.2600 Zak Semen PC
1.5000 H.o Pekerja 115,000.00
0.6000 H.o Tukang Batu 135,000.00
0.0600 H.o Kepala Tukang 150,000.00
0.0750 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN DINDING


1 1 M2 PASANGAN BATU TELA/ BATAKO 1 : 4
0.0430 M3 Pasir Pasangan
20.0000 Bh Batu Tela
0.2300 Zak Semen PC
0.4500 H.o Pekerja 115,000.00
0.1500 H.o Tukang Batu 135,000.00
0.0150 H.o Kepala Tukang 150,000.00
0.0030 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN PLESTERAN


2 1 M2 PLESTERAN 1 : 4 Tebal 20 mm
0.0280 M3 Pasir Pasangan
0.1736 Zak Semen PC
0.2500 H.o Pekerja 115,000.00
0.2000 H.o Tukang Batu 135,000.00
0.0200 H.o Kepala Tukang 150,000.00
0.0125 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN BETON


1 1 M3 MEMBUAT BETON TUMBUK 1 Pc : 3 Ps : 5 Kr
4.3600 Zak Semen PC
0.5200 M3 Pasir Beton
0.8700 M3 Kerikil Beton
1.6500 H.o Pekerja 115,000.00
0.2500 H.o Tukang Batu 135,000.00
0.0250 H.o Kepala Tukang 150,000.00
0.0800 H.o Mandor 200,000.00

2 1 M3 MEMBUAT SLOOF KOLOM & RINGBALK BETON BERTULANG (110 Kg Besi + Bekisting)
0.2700 M3 Papan Kayu Matoa
2.0000 Kg Paku Campur
0.6000 Ltr Minyak Bekisting
110.0000 Kg Besi Beton Polos
2.5000 Kg Kawat Beton
6.4600 Zak Semen PC
0.5200 M3 Pasir Beton
0.7800 M3 Kerikil Beton
4.8500 H.o Pekerja 115,000.00
0.3500 H.o Tukang Batu 135,000.00
1.5600 H.o Tukang Kayu 135,000.00
1.4000 H.o Tukang Besi 135,000.00
0.3310 H.o Kepala Tukang 150,000.00
0.1700 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN KUNCI


1 MEMASANG 1 BUAH KUNCI TANAM BIASA
1.0000 Bh Kunci Tanam Biasa
0.0100 H.o Pekerja 115,000.00
0.5000 H.o Tukang Kayu 135,000.00
0.0100 H.o Kepala Tukang 150,000.00
0.0050 H.o Mandor 200,000.00

2 MEMASANG 1 BUAH ENGSEL PINTU


1.0000 Bh Engsel Pintu
0.0100 H.o Pekerja 115,000.00
0.5000 H.o Tukang Kayu 135,000.00
0.0100 H.o Kepala Tukang 150,000.00
0.0050 H.o Mandor 200,000.00

3 MEMASANG 1 BUAH GRENDEL TANAM


1.0000 Bh Grendel Tanam
0.0200 H.o Pekerja 115,000.00
0.2000 H.o Tukang Kayu 135,000.00
0.0200 H.o Kepala Tukang 150,000.00
0.0100 H.o Mandor 200,000.00

4 MEMASANG 1 BUAH PASANGAN KAIT ANGIN


1.0000 Bh Kait Angin
0.0150 H.o Pekerja 115,000.00
0.1500 H.o Tukang Kayu 135,000.00
0.0150 H.o Kepala Tukang 150,000.00
0.0008 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN ELEKTRIKAL


1 INSTALASI LISTRIK
6.0000 M' Kabel NYM 2.5 mm
2.5000 M' Pipa PVC 3/4 & 5/8
1.0000 Ls Accessories & Alat Bantu
0.5000 H.o Pekerja 115,000.00
1.0000 H.o Tukang Listrik 135,000.00

2 1 TTK STOP KONTAK


1.0000 Bh Stop Kontak
0.2500 H.o Tukang Listrik 135,000.00
0.0500 H.o Pekerja 115,000.00

3 1 TTK LAMPU TL X 40 WATT


1.0000 Bh Lampu TL 40 Watt
0.2500 H.o Tukang Listrik 135,000.00
0.0500 H.o Pekerja 115,000.00

4 1 TTK LAMPU PHILIPS XL 20 WATT


1.0000 Bh Lampu XL 20 WATT
0.2500 H.o Tukang Listrik 135,000.00
0.0500 H.o Pekerja 115,000.00

5 1 BH SEKRING BOX 2 GROUP


1.0000 Bh Sekring Box + Sekring
0.2500 H.o Tukang Listrik 135,000.00
0.0500 H.o Pekerja 115,000.00

6 1 Bh SAKLAR DOUBLE
1.0000 Bh Saklar Double
0.2500 H.o Tukang Listrik 135,000.00
0.0500 H.o Pekerja 115,000.00

7 1 Bh SAKLAR TUNGGAL
1.0000 Bh Saklar Tunggal
0.2500 H.o Tukang Listrik 135,000.00
0.0500 H.o Pekerja 115,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN BESI DAN ALUMNIUM


1 MEMASANG 1 M2 PINTU BESI TEBAL 2MM RANGKA BAJA SIKU
1.0000 M2 Besi Plat Baja
15.0000 Kg Besi Siku L 30.30.3
0.0500 Kg Kawat Las
1.0500 H.o Pekerja 115,000.00
1.0500 H.o Tukang Besi Konstruksi 135,000.00
0.1050 H.o Kepala Tukang 150,000.00
0.0520 H.o Mandor 200,000.00

2 MEMASANG 1 M2 TERALI BESI


11.5000 M2 Besi Strip 2x3
1.2000 Kg Pekerja 115,000.00
1.2000 Kg Tukang Las 135,000.00
0.0120 H.o Kepala Tukang 150,000.00
0.0008 H.o Mandor 200,000.00

ANALISA BIAYA KONSTRUKSI PEKERJAAN PENGECATAN


1 Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat dasar, 2 lps cat penutup ) /m2
0.1000 Kg Plamir tembok
0.1000 Kg Cat dasar tembok
0.2600 Kg Cat finishing tembok
0.0200 H.o Pekerja 115,000.00
0.0630 H.o Tukang Cat 135,000.00
0.0063 H.o Kepala Tukang 150,000.00
0.0030 H.o Mandor 200,000.00
N

HARGA BAHAN
JUMLAH (Rp.)
(Rp.)

AN PERSIAPAN

11,500.00
2,000.00
50,000.00 50.00
13,550.00

2,350,000.00 28,200.00
5,000.00 500.00
25,000.00 250.00
4,600.00
8,100.00
900.00
600.00
43,150.00

22,080.00
3,800.00
25,880.00

57,500.00
10,000.00
67,500.00

900,000.00 1,080,000.00
34,500.00
2,000.00
1,116,500.00

475,000.00 570,000.00
28,750.00
5,000.00
603,750.00

AAN PONDASI

86,250.00
5,000.00
91,250.00

900,000.00 388,800.00
950,000.00 1,140,000.00
89,700.00
52,650.00
5,850.00
7,800.00
1,684,800.00

950,000.00 494,000.00
950,000.00 1,140,000.00
85,000.00 277,100.00
172,500.00
81,000.00
9,000.00
15,000.00
2,188,600.00

AAN DINDING

950,000.00 40,850.00
3,500.00 70,000.00
85,000.00 19,550.00
51,750.00
20,250.00
2,250.00
600.00
205,250.00

AN PLESTERAN

950,000.00 26,600.00
85,000.00 14,756.00
28,750.00
27,000.00
3,000.00
2,500.00
102,606.00

JAAN BETON

85,000.00 370,600.00
950,000.00 494,000.00
950,000.00 826,500.00
189,750.00
33,750.00
3,750.00
16,000.00
1,934,350.00
0 Kg Besi + Bekisting)
2,350,000.00 634,500.00
25,000.00 50,000.00
20,000.00 12,000.00
35,500.00 3,905,000.00
35,000.00 87,500.00
85,000.00 549,100.00
950,000.00 494,000.00
950,000.00 741,000.00
557,750.00
47,250.00
210,600.00
189,000.00
49,650.00
34,000.00
7,561,350.00

JAAN KUNCI

75,000.00 75,000.00
1,150.00
67,500.00
1,500.00
1,000.00
146,150.00

24,000.00 24,000.00
1,150.00
67,500.00
1,500.00
1,000.00
95,150.00

15,000.00 15,000.00
2,300.00
27,000.00
3,000.00
2,000.00
49,300.00
8,000.00 8,000.00
1,725.00
20,250.00
2,250.00
160.00
32,385.00
AN ELEKTRIKAL

14,500.00 87,000.00
27,000.00 67,500.00
15,000.00 15,000.00
57,500.00
135,000.00
362,000.00

35,000.00 35,000.00
33,750.00
5,750.00
74,500.00

45,000.00 45,000.00
33,750.00
5,750.00
84,500.00

40,000.00 40,000.00
33,750.00
5,750.00
79,500.00

100,000.00 100,000.00
33,750.00
5,750.00
139,500.00

45,000.00 45,000.00
33,750.00
5,750.00
84,500.00

27,000.00 27,000.00
33,750.00
5,750.00
66,500.00
ESI DAN ALUMNIUM
365,000.00 365,000.00
156,000.00 2,340,000.00
45,000.00 2,250.00
120,750.00
141,750.00
15,750.00
10,400.00
2,995,900.00

68,500.00 787,750.00
138,000.00
162,000.00
1,800.00
160.00
1,089,710.00
N PENGECATAN
nutup ) /m2
25,500.00 2,550.00
35,500.00 3,550.00
35,500.00 9,230.00
2,300.00
8,505.00
945.00
600.00
27,680.00
DAFTAR KUANTITAS DAN HARGA

NAMA KEGIATAN : PEMBANGUNAN INSFRASTRUKTUR - PLN


NAMA PEKERJAA : PEMBANGUNAN PAGAR PLN - MAPURUJAYA
LOKASI : TIMIKA - PAPUA
TAHUN ANGGARA: 2017

NO JENIS PEKERJAAN SAT. VOLUME

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi M2 2,100.00
2 Pengukuran & Pas. Bouwplank M' 190.00
3 Direksi Ket M2 4.00

II PEKERJAAN TANAH DAN PASIR


1 Galian Tanah untuk Pondasi M3 228.00
2 Urugan Tanah Kembali M3 76.00

III PEKERJAAN PONDASI


1 Pasangan Batu Kosong (Aanstamping) M3 38.00
2 Pasangan Pondasi Batu Kali Camp 1 : 4 M3 95.80

IV PEK. DINDING & BETON BERTULANG


1 Cor Sloof Beton 25/20 Cm M3 9.20
2 Tiang Kolom Beton 20/20 M3 7.60
3 Ring Balk Beton 20/20 M3 5.20
4 Pasang Dinding Batu Tela, Camp. 1 : 4 M2 274.40
5 Plesteran Camp 1 : 4 & 1 : 3 M2 608.80

V PEKERJAAN BESI DAN ALUMNIUM


1 Memasang Pintu Besi M2 6.90
2 Memasang Terali besi M2 62.10

VI PEKERJAAN PENGECATAN
1 Cat Dinding M2 334.40

VII PEKERJAAN AKHIR


Pembersihan Akhir Ls 1.00
Laporan-laporan Ls 1.00
DAN HARGA

HARGA SATUAN JUMLAH


(Rp.) (Rp.)

44,653,500.00
13,550.00 28,455,000.00
43,150.00 8,198,500.00
2,000,000.00 8,000,000.00

22,771,880.00
91,250.00 20,805,000.00
25,880.00 1,966,880.00

273,690,280.00
1,684,800.00 64,022,400.00
2,188,600.00 209,667,880.00

285,136,832.80
7,561,350.00 69,564,420.00
7,561,350.00 57,466,260.00
7,561,350.00 39,319,020.00
205,250.00 56,320,600.00
102,606.00 62,466,532.80

88,342,701.00
2,995,900.00 20,671,710.00
1,089,710.00 67,670,991.00

9,256,192.00
27,680.00 9,256,192.00

3,500,000.00
1,000,000.00 1,000,000.00
2,500,000.00 2,500,000.00
REKAPITULASI ANGGARAN BIAYA

NAMA KEGIATAN : PEMBANGUNAN INSFRASTRUKTUR - PLN


NAMA PEKERJAAN : PEMBANGUNAN PAGAR PLN - MAPURUJAYA
LOKASI : TIMIKA - PAPUA
TAHUN ANGGARAN : 2017

NO. URAIAN

I PEKERJAAN PERSIAPAN

II PEKERJAAN TANAH & PASIR

III PEKERJAAN PONDASI

IV PEKERJAAN DIDING & BETON BERTULANG

V PEKERJAAN BESI DAN ALUMNIUM

VI PEKERJAAN PNGECATAN

VII PEKERJAAN AKHIR

REAL COST
PPN 10%
TOTAL COST
DIBULATKAN
AN BIAYA

UKTUR - PLN
- MAPURUJAYA

HARGA
PEKERJAAN
(Rp.)

44,653,500.00

22,771,880.00

273,690,280.00

285,136,832.80

88,342,701.00

9,256,192.00

3,500,000.00

727,351,385.80
72,735,138.58
800,086,524.38
800,086,000.00