Anda di halaman 1dari 9

A

cost estimate method for bridge


superstructures using regression
analysis and bootstrap

Nikolaos Fragkakis Sergios Lambropoulos John-Paris Pantouvakis


Ph.D. Candidate Associate Professor Associate Professor
Centre for Construction Innovation, Centre for Construction Innovation, Centre for Construction Innovation,
Department of Construction Department of Construction Department of Construction
Engineering and Management, Faculty Engineering and Management, Faculty Engineering and Management, Faculty
of Civil Engineering, National Technical of Civil Engineering, National Technical of Civil Engineering, National Technical
University of Athens University of Athens University of Athens
Athens, Greece Athens, Greece Athens, Greece

Preliminary cost estimates rely on the conceptual design of


the project and use only basic design technologies. Although
they present the lowest expected accuracy, they are often used
by key people involved in the construction process, thus playing
a significant role. Bridge construction has increased over the last
years, often exhibiting substantial overruns above estimated costs.
To overcome this problem, it is crucial for the decision makers to have
an early estimate of the final cost based on previous experience. This
paper addresses the need for easy-to-use and reliable cost estimates
during the early stages of projects for bridge superstructures,
presenting a major impact on the total bridge construction cost.
It proposes a conceptual cost estimate method that involves the
estimation of both the material quantities and the relevant costs.
It describes the development of prediction models for the material
quantities of concrete and reinforcing and prestressing steel for three
major bridge deck construction methods using regression analysis,
while a bootstrap resampling method is used to produce estimate
ranges. The material estimating models rely on the development of a
database after collecting actual data from a large sample of modern
bridges. The major assumptions underlying the correct application of
Keywords the regression methodology were tested, and necessary adjustments
construction costs; bridges; were made. The proposed conceptual cost-estimating methodology
estimation; regression uses information known before detailed plans are developed to
analysis; bootstrap provide fast and reliable results that can be very useful in the early
stages of a road project.

182 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 2 (2 )2 010
IntRoDUCtIon sults in cost overruns. To overcome this ess. On the other hand, very few stud-
problem, it is crucial for decision mak- ies rely on actual structural and eco-
Every construction project evolves ers to have an early estimate of the final nomic data collected from constructed
through a series of stages, originating cost based on previous experience. bridges in order to produce material
from the preliminary study followed Comparative studies on the transporta- and cost estimates.
by several design stages and finally tion infrastructure are rare, mainly be- Aparicio et al. (1996) developed a
the implementation of the design with cause of the lack of large, reliable, and computer-aided design system for pre-
the actual construction. Cost estimates homogeneous databases. This is due stressed concrete highway bridges.
are produced throughout the life of a to the reluctance of public clients to The software package performs the
construction project and are used for supply financial information regarding complete design and produces the ge-
different purposes depending on the constructed projects, thereby making ometry and cost of all bridge elements.
available information and their expect- research in this domain difficult. Previous efforts to create similar expert
ed accuracy. The superstructure presents a signifi- systems were made by Philbey et al.
Preliminary cost estimates, also re- cant impact on the construction cost of (1993) and Miles and Moore (1991).
ferred to as pre-design cost estimates, a modern concrete bridge. According Several research studies performed in
feasibility estimates, or screening es- to Konstantinidis and Maravas (2003), the US also address the design opti-
timates (Ritz, 2004), are made before its cost ranges from 35% to 53% of the mization of prestressed concrete road
the projects detailed plans and speci- total bridge construction cost, depend- bridges and rely on theoretical resolu-
fications are known. According to Hen- ing on the construction method used tions in order to minimize the construc-
drickson (2008), a preliminary cost es- and the design system. Consequently, tion cost of the bridge superstructure.
timate relies on the conceptual design analytical models for conceptual cost Sirca and Adeli (2005) developed an
of the project and uses only the basic estimating appear to be necessary. optimization method for the super-
technologies for the design. Although This paper addresses the need for structure cost of precast, prestressed
preliminary cost estimates present easy-to-use and reliable cost estimates concrete I-beam bridge systems, while
the lowest expected accuracy, due to for bridge superstructures during the Cohn and Lounis (1994) developed a
the limited available information, they early stages of a project and proposes three-level cost optimization approach
are often used by key people involved a conceptual cost estimate method that for the optimal superstructure design
in the construction process, including relies on information known before the of concrete motorway bridges. Lounis
project owners, designers, contrac- detailed plans and specifications are and Cohn (1993) proposed a method
tors, and lending institutions. They are identified. Prediction models for the for the selection of the most economi-
used for feasibility and budgeting pur- material quantities of concrete as well cal girder type, optimal girder spacing,
poses, the comparison and financial as reinforcing and prestressing steel for optimal prestressing force, and mini-
evaluation of alternative projects, and three major bridge deck construction mum superstructure cost per unit deck
the application of appropriate financ- methods are developed with the use of area for bridges consisting of precast
ing procedures. As such, easy-to-use, regression analysis, while a bootstrap prestressed girders with reinforced
inexpensive, and reasonably accurate resampling method is used to produce concrete slab. Sarma and Adeli (1998)
methods for preliminary cost estimat- estimate ranges. The data used have provided a review of articles pertain-
ing are needed, especially for large- been collected from the bridges of the ing to cost optimization of concrete
scale transport infrastructure projects 680-km long Egnatia Motorway travers- bridges. The aforementioned research
that have traditionally exhibited sub- ing northern Greece. studies provide preliminary cost and
stantial overruns above estimated design estimates for concrete bridge
costs by as much as 50% to 100% in Previous relevant cost studies superstructures conforming to Ameri-
most cases (Skamris and Flyvbjerg, and research can or Canadian specifications and for
1997). When reviewing the previous research standard shapes and cross sections.
Modern motorways play a major role in on cost estimating for motorway bridg- Meanwhile, Menn (1990) investigated
the transportation infrastructure. The es, it becomes evident that relevant the economy of prestressed concrete
need to have environmentally friendly cost studies fall into two categories. bridges relying on actual cost data and
designs for motorways that overcome Most research efforts perform compu- using a sample of 19 motorway bridges
difficult geological terrains and bypass ter-intensive theoretical resolutions in built in Switzerland between 1958 and
city centers or archaeological sites order to optimize the final design from 1985. Menn broke down the average
increases the necessity to construct both technical and economic view- construction costs into mobilization,
bridges. Bridge construction often re- points through a trial-and-error proc- substructure, superstructure, and ac-

n. fragkakis s. lambropoulos j.p. pantouvakis a cost estimate method for bridge ... pp 183-191 183
cessories, concluding that these fac- crane, cast-in-situ, and balanced canti- completed questionnaires, confirm the
tors contribution to the total bridge lever. Advance shoring and incremental validity of the provided data, and fill in
construction cost is 8.00%, 23.50%, launching have also been used. missing information. Furthermore, they
54.50%, and 14.00%, respectively. He Egnatia Odos S.A. (EOAE) managed conducted several interview sessions
argued that, although the sample rep- the motorway and administered its with bridge experts, academics, and
resents a wide variety of conditions, design, construction, operation, main- designers in order to improve their un-
the most important cost factors do not tenance, and exploitation. The design derstanding of bridge design.
vary significantly from one bridge to of bridges was carried out by Greek or The current bridge database includes
another; consequently, the proposed international structural design offices complete data from 68 structures: 31
breakdown of average construction following an international competition. bridges with simply supported pre-
costs can be very useful in preparing Each individual bridge design was first cast prestressed beams with compos-
preliminary cost estimates. Menn also checked by an independent consult- ite slab, 22 bridges with cast-in-situ
developed empirical equations for the ant office and then reviewed by EOAEs decks, and 15 bridges with cantilever
quantities of concrete, reinforcing steel design department prior to construc- construction. The respective Table in
and prestressing steel in the bridge tion. In addition, each study was also Appendix A includes a representative
superstructure and proposed different reviewed by the construction manager sample of 19 bridges from the data-
equations for incrementally launched commissioned by EOAE with regard to base. The database represents the final
and balanced cantilever bridge con- the adaptation to local conditions, the construction and includes all changes
struction. constructability of the structure, and that took place during the implemen-
In summary, research studies for mo- any special site conditions. In accord- tation phase due to unforeseen site
torway bridges using actual structural ance with the current Greek legislation, conditions. The actual structural data
and cost data are very limited due to the design of bridges was executed ac- and material quantities, which in many
the lack of available information and cording to the German DIN standards. cases were different from those deter-
the difficulty involved in developing For earthquake loading, the Greek mined during the design stages, were
large and reliable databases. Although Seismic Regulation for Design of Bridg- recorded.
cost estimates based on computer- es (E39/99) combined with the Greek
aided resolutions can provide helpful Standard for Design of Earthquake Re- Proposed method for pre-design
insights, they fail to address structural sistant Structures (EAK 2000) was uti- cost estimates
changes that take place during the lized. The proposed cost estimate method in-
projects construction. volves two stages: the estimation of the
Data collection and database superstructures material quantities
Concrete bridges of the egnatia development and the calculation of the relevant con-
Motorway The proposed pre-design cost estimate struction costs. The first stage is based
The Egnatia Motorway is a recently con- method for bridge superstructures re- on estimating models derived from the
structed 680-km long modern motor- lies on the development of a database statistical processing of the collected
way that constitutes part of the Trans- for modern concrete motorway bridges. data. Data input from the user include
European Network for Transport. Its A structured general questionnaire that the number of spans or cantilevers,
bridges represent approximately 16% includes all bridge sections from the the length of each span or cantilever,
of the total construction cost of the foundations up to the superstructure the width of the deck, and the deck
motorway. The largest overall bridge and covers different designs and con- construction method. The proper esti-
length exceeds 1,000 m while the larg- struction systems was developed. It mating models are applied to extract
est maximum span reaches 235 m. includes actual structural information the material quantities. The required
Each carriageway is carried by a sepa- for the bridge (e.g., the quantities of input data consist of basic parameters
rate bridge having a total width vary- concrete and reinforcing and prestress- known during the pre-design stages
ing from 10.00 m to 17.75 m. The bridge ing steel), fundamental design param- of the project. Based on contour maps
decks can be categorized into one of eters (e.g., length of spans, height of and the alignment and specifications
three types: simply supported precast piers and abutments), and construc- of the motorway under evaluation, the
prestressed beams with composite tion costs and time. The questionnaire user calculates the length and width of
slab, voided slab, or post-tensioned was initially sent to the construction the bridge and the length of the spans.
continuous box girder. The three major managers and the contractors civil The second stage requires the unit pric-
construction methods used are precast engineers. The authors visited the con- es for concrete (cc), prestressing steel
beams placed by launching beam or struction sites in order to scrutinize the (cp), and reinforcing steel (cs) as data

184 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 2 (2 )2 010
input. The relevant construction costs McCuen (1990). The p-value, used to seismic design parameters, the deck
(Cc, Cp and Cs, respectively) are derived determine the statistical significance, width and the length of the span sup-
by multiplying the estimated material denotes the probability that a regres- ported by the piers. Since the majority
quantities with the item prices. The in- sion coefficient equals zero and that of the construction projects (78% of the
tended purpose of the cost estimate the variable has no effect. In addition, data sample) was designed with similar
according to the various users substan- regression coefficients were checked seismic parameters, the authors decided
tially influences the applied unit prices. for theoretical accuracy, which should to exclude this parameter from the analy-
For example, the project owner can use reflect the effect of the independent sis and not to differentiate the proposed
the official tender unit prices determined variables on the material quantities of models based on the earthquake design
by the government and derive the cost the bridge superstructure. parameters. Thus, the length and width
for budgeting purposes or for feasibil- The adjusted coefficient of determina- of deck were the two independent varia-
ity decisions. Meanwhile, the contractor tion (R2) and the F-value were used to bles included in the analysis. The volume
can apply unit prices based on cost data examine the goodness of fit of the mod- of concrete (Vc), the weight of reinforcing
from previous projects. The model also el. R2 provides a measure of the varia- steel (Bs), and the weight of prestressing
provides parametric estimate ranges for bility explained by the model, while the steel (Bp) represent the three dependent
the total superstructure cost (TC). F-value tests the hypothesis that the variables.
coefficient of determination is zero. The Bridges with a superstructure consist-
Regression analysis significance of the F-test is the proba- ing of precast prestressed simply sup-
A parametric cost-estimating model bility that the aforementioned hypoth- ported concrete beams and composite
consists of one or more functions or esis is correct. reinforced concrete slab are typically de-
relationships between the cost as The situation where the independent signed to include several spans of equal
the dependent variable and the cost- variables of regression modeling are length in order to use a large amount
governing factors as the independent highly intercorrelated is referred to of standard precast elements, achieve
variables. Regression analysis (RA) as multicollinearity. Multicollinearity standardization of the construction
represents one of the most widely used makes it difficult for researchers to cor- process, and reduce construction time,
methods for parametric cost estimation rectly assess the marginal contribution thereby achieving economy. The initial
during early project stages. Tradition- of the variables (Belshey et al., 1980) data sample considered all superstruc-
ally, cost-estimating relationships are as it causes large standard errors of ture spans included in the 31 bridges
developed by applying RA to historical the regression coefficients and leads constructed using this method. After ex-
project information. The major advan- to deceptive results in terms of statis- cluding duplicate information, the sam-
tages of RA lie in the simplicity in its tical significance, hypothesis testing, ple includes complete data for 47 super-
use, the level of accuracy provided, and estimation, and forecasting; The Pear- structure spans. The material quantities
the parsimonious use of parameters. son product-moment correlation coeffi- include the precast concrete beams, the
Its major drawbacks are the require- cients were calculated in order to check diaphragms, the precast planks, and the
ment for a defined mathematical form the independent variables for multicol- composite slab.
that best fits the available historical linearity before being used in the initial In regard to motorway bridges with cast-
data, the difficulty in accounting for the regression. in-situ decks, after considering all super-
large number of variables present in a structure spans and excluding duplicate
construction project, and the numer- Model development information, the final sample includes
ous interactions among them (Hegazy The design of a bridge superstructure complete data from 47 superstructure
and Ayed, 1998). Recent applications of is generally affected by many variables, spans consisting of cast-in-situ box gird-
RA for cost estimating can be found in such as the seismic design parameters, ers. The material quantities do not in-
Lowe et al. (2006) and Sonmez (2008). the alignment of the bridge, the construc- clude the sidewalks as they are construct-
A linear model was considered for re- tion sequence, the arrangement of longi- ed with concrete of a lower strength com-
gression modeling in this study. The ap- tudinal prestressing, the deck width, the pared to the remaining deck and depend
proach used in the analysis includes a arrangement and use of expansion joints on the specifications of the highway.
statistical hypothesis test to determine in the deck, and the length of the span The cantilever construction method is
the significance of each independent supported by the piers (Menn, 1990). widely used for medium and long span
variable coupled with the check of the However, given that the proposed model concrete bridges when the ground mor-
rationality of the cause-and-effect rela- involves preliminary cost estimates dur- phology and local conditions render the
tionships. This approach is consistent ing the pre-design stages of a project, use of traditional scaffolding difficult,
with the suggestions of Brubaker and the current research focuses only on the impossible, or extremely expensive. This

n. fragkakis s. lambropoulos j.p. pantouvakis a cost estimate method for bridge ... pp 182-190 185
method consists of building a bridge of the span or the cantilever presents the
deck through a succession of segments, major impact on the material quanti- Y=a + 0X (2)
usually starting from one or more piers, ties; moreover, no evident problem due
where each segment placed balances the to multicollinearity exists. As a result, in where Y represents the dependent vari-
weight of the next segment on the oppo- order to reduce the number of variables able (Vc, Bs, and Bp ) and X represents the
site side of the pier and occasionally the and simplify the regression analysis, the independent variable (lsadj or lcadj).
weight of the formwork (Mathivat, 1983). adjusted length of span was defined as Regression statistics for all cases, in-
The stability of the resulting cantilever is follows: cluding the R2, the significance of the
secured at each step of construction by F-test, and the p-value, are presented in
prestressed cables arranged according Table 1 and highlight the goodness of fit
b
to the moment diagram of the cantilever; lsadj=ls (1) and the statistical significance of both
b med
as a result, the material quantities of the the regression model and the independ-
superstructure depend on the length ent variable at a 1% significance level.
of the cantilever. The bridge database where lsadj is the adjusted length of span, Table 2 presents the pre-design material
contains 15 structures constructed with ls is the length of span, b is the deck estimates models as well as the range of
the balanced cantilever method. After width, and bmed is the median value of values of the independent variable and
excluding the duplicate information, the deck width. The adjusted length of the median value of the deck width. The
these bridges include 33 cantilevers that the cantilever (lcadj), similar to the ad- Pearson product-moment correlation co-
constitute the data sample. The material justed length of span, was used for the efficients for bridges with deck type pre-
quantities do not include the sidewalks. cantilever-constructed bridges. The ex- cast girders are provided in Table 3.
The Pearson product-moment correla- amined regression model included one
tion coefficients for the dependent and independent variable in the following
independent variables were calculated form:
for all cases and indicated that the length

Precast beams Cast-in-situ Balanced cantilever


Vc Bs Bp Vc Bs Bp Vc Bs Bp
P-value 6.5E-19 1.1E-15 1.7E-17 6.4E-16 8.8E-14 1.5E-16 2.4E-19 3.9E-17 3.7E-18
R 2
0.826 0.758 0.799 0.764 0.707 0.779 0.926 0.898 0.912
F-Value 219.261 145.403 183.660 149.912 111.838 163.009 404.284 282.911 334.195
F-significance 6.5E-19 1.1E-15 1.7E-17 6.4E-16 8.8E-14 1.5E-16 2.4E-19 3.9E-17 3.7E-18

table 1. Regression statistics.

Precast beams Cast-in-situ Balanced cantilever


Vc Vc = -77.184 + 11.349 x lsadj Vc = 3.865 + 9.849 x lsadj Vc = -1705.124 + 28.807 x lcadj
Bs Bs = -6306.255 + 1336.155 x lsadj Bs = 8274.962 + 950.703 x lsadj Bs = -460706.124 + 6729.826 x lcadj
Bp Bp = -5035.551 + 432.707 x lsadj Bp = -7047.660 + 604.149 x lsadj Bp = -150397.754 + 2113.073 x lcadj
Range 20.53 < lsadj < 46.34 17.88 < lsadj < 67.17 91.29 < lcadj < 204.66
bmed 13.10 13.50 14.00

table 2. Material estimating models.

b ls Vc Bs Bp lsadj
b 1.000
ls -0.140 1.000
Vc 0.334 0.787 1.000
Bs 0.399 0.711 0.854 1.000
Bp 0.290 0.797 0.757 0.851 1.000
lsadj 0.379 0.862 0.911 0.874 0.896 1.000

table 3. Pearson product-moment correlation coefficients for bridges with deck type precast girders.

186 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 2 (2 )2 010
Validation of the models estimates prepared prior to the projects applied to derive estimates of the mate-
The R values range from 70% to 93%,
2
conceptual design. rial quantities, which subsequently led to
indicating that the proposed models pro- The derived MAPE values can be attrib- estimates of the total superstructure cost.
vide a satisfactory fit to the data. The esti- uted to the lack of standardization in the The MAPE was calculated for each bridge
mated p- and F-values also verify that the selection of the bridge deck cross section. deck; all values were averaged for each
independent variables and the selected DIN standards do not dictate the use of construction method (e.g., the average
regression models are statistically sig- specific shapes or cross sections, but pro- MAPE calculated for the cast-in-situ con-
nificant, while the regression coefficients pose several design conditions and crite- struction was 10.94%).
present theoretical correctness. ria that must be fulfilled. As a result, the The correct application of the linear re-
However, a good fit for a regression bridge designer is able to choose the al- gression methodology with one inde-
model does not always guarantee its location of material use and derive the ex- pendent variable requires three basic as-
validity. Cross-validation techniques are act dimensions of the beam shapes and sumptions to be metnamely, the error
widely used to estimate generalization the deck cross section as long as the crite- term of the model should be normally dis-
error, choose among various models, ria are fulfilled. For example, for a particu- tributed, have a mean value of zero, and
and evaluate the prediction perform- lar balanced cantilever construction, the have a constant variance (Gujarati, 1999).
ance of a model. Thus, a 10-fold valida- consumption of materials is influenced by The residuals for the proposed regression
tion method was implemented in which the aspect ratio of the box girder, the rela- models were calculated. The pattern of
the dataset was randomly divided into tionship between the overall width of the the residual plots was examined, indi-
10 subsets (the folds) of approximately top slab and the cantilever flanges, and cating the sufficiency of the regression
equal size. The regression modeling was the prestressing layout on both top and models. The assumption of normality was
then performed, omitting one of the sub- bottom slabs. Meanwhile, for a particu- also tested with the use of the Shapiro-
sets from training; the computed model lar precast prestressed beam deck, the Wilks test (Shapiro and Wilk, 1965). This
and omitted subset were then used for consumption of materials is influenced test examines the null hypothesis that
testing. This procedure was repeated for by various design decisions related to the the sample has a normal distribution and
all 10 subsets, and the selected error cri- formation of the cross section of the deck, the calculated p-value denotes the prob-
terion was averaged. The Mean Absolute such as the number of beams used and ability of incorrectly rejecting the null hy-
Percent Error (MAPE) was selected as the their slenderness, the type of the beams pothesis. A value greater than the level of
error measure. MAPE represents the av- section (T-type beam with a wide upper significance leads to the conclusion that
erage of deviations between predicted flange or I-type beam with a narrow upper the sample is normally distributed. The
and actual estimates in absolute values flange), and the type of precast planks. p-values were calculated for each sam-
expressed as a percentage of the actual Furthermore, bridge construction usually ple of residuals, verifying the normality
estimate. MAPE values for all material constitutes part of a larger construction assumption of the error terms at the 5%
estimating models, presented in Table 4, contract that involves several bridges level of significance. Furthermore, the
reveal that the proposed models are able with different parameters. The designer mean value of the residuals approached
to predict the actual superstructure ma- selects the deck shapes for each struc- the value of zero.
terial quantities with an average error of ture while considering the whole project Whites (1980) general heteroscedasticity
less than 20%. This error is considered in order to maximize the construction test was used to test the constant variance
acceptable according to the U.S. Depart- processs standardization and achieve of the error term (i.e., the homoscedastic-
ment of Energys directives for construc- economy. ity of the regression models). This test,
tion projects (1997), which propose an In order to assess the accuracy of the based on an auxiliary regression, does
accuracy range of 40% for planning/ proposed cost method, the actual and not assume a specific form of hetero-
feasibility estimates prepared prior to predicted superstructure costs were scedasticity. The test statistic equals the
conceptual design. In addition, Ritz calculated for each bridge from the data product of the sample size with the R2 of
(2004) proposes an acceptable accuracy sample using current material unit prices. the auxiliary regression. The probability
range of 25-30% for construction cost The developed estimating models were (p-value) of obtaining a chi-square value
of the test statistic and the result of the
Vc Bs Bp test for a 5% level of significance are pre-
Precast beams 11.66% 15.42% 16.14% sented in Table 5, highlighting the pres-
Cast-in-situ 14.48% 15.26% 19.30% ence of heteroscedasticity in the samples
Balanced cantilever 14.76% 17.69% 16.03% concerning the cantilever and the cast-in-
situ deck construction.
table 4. MAPe of prediction models. Despite the presence of heteroscedas-

n. fragkakis s. lambropoulos j.p. pantouvakis a cost estimate method for bridge ... pp 182-190 187
Test statistic P-value Result coefficients were chosen as the param-
Precast 1.535 >0.25 Homoscedasticity eters of interest. The same process was
repeated 1,000 times, and the numerous
Cast-in-situ 6.177 <0.05 Heteroscedasticity
Vc

bootstrap iterations of the parameters


Cantilever 13.740 <0.005 Heteroscedasticity were used to obtain bridge superstruc-
Precast 1.851 >0.25 Homoscedasticity ture material estimates and predictions
of superstructure cost. Finally, these es-
Cast-in-situ 7.604 <0.025 Heteroscedasticity
Bs

timates led to a probability distribution


Cantilever 9.167 <0.025 Heteroscedasticity function for the predicted cost item as
Precast 3.366 >0.10 Homoscedasticity well as to the relevant range estimates.
Cast-in-situ 13.767 <0.005 Heteroscedasticity
Bp

estimate ranges for case project


Cantilever 16.200 <0.005 Heteroscedasticity
A combination of the proposed regression
table 5. test statistic, p-value and result of White test. models and the bootstrap technique was
used to develop superstructure mate-
ticity, the ordinary least squares esti- parametric assumptions and simplified rial and cost estimates for a case project.
mators remain unbiased, consistent, models (Chernick, 1999). Bootstrap also The case example involved a single-span
and linear (Gujarati, 1999), and the benefits from its simplicity and alerts bridge deck consisting of precast pre-
computed regression coefficients re- the practitioner to the data variability. It stressed simply supported beams with a
tain their validity. Meanwhile, the es- represents a computer-intensive method composite slab. The values of the param-
timates of the variances are biased, that is not only in general use by statisti- eters are given in Table 6. One thousand
thereby invalidating the tests of sig- cians, but is also applied by quantitative bootstrap data sets, each containing 47
nificance (Maddala, 1992). Whites cor- researchers in various disciplines, such data points, were randomly drawn with
rected standard errors were chosen to as engineering, life sciences, medical replacement from the original data sam-
adjust for heteroscedasticity. MacKin- and social sciences, and business (Davi- ple and used to develop 1,000 regres-
non and White (1985) raised concerns son and Hinkley, 1997). The bootstrap sion coefficients. These coefficients were
about the reliability of Whites correct- method has been extensively used for utilized to make 1,000 estimates for the
ed standard errors for small samples the estimation of standard errors and example superstructure material quanti-
and proposed three tests that should empirical probability distribution func- ties, which subsequently led to predic-
be used. Long and Ervin (2000) con- tions of a population, regression and tions for the relevant superstructure
cluded that the HC3 test is the most time series analysis, confidence inter- costs by multiplying them with the unit
reliable. The HC3s small samples cor- vals, and hypothesis testing. A recent prices. Table 7 provides estimate ranges
rected standard errors and the relevant application of the bootstrap approach for materials and superstructure cost at
p-values were calculated for all cases, can be found in Hughes and Paez (2006). the 90% probability level as well as the
verifying the statistical significance of A bootstrap resampling method, similar relevant estimate figures derived by the
the independent variables. to the one applied by Sonmez (2008), proposed models, which approached the
was used in the current study to develop 50% prediction value. Figure 1 presents
Bootstrap method for estimate estimate ranges for bridge superstruc- the empirical distribution function for the
ranges ture costs. The original data set for each predicted total superstructure cost.
The parametric cost estimate method, model was resampled to form a new set
when used only with the proposed ma- of the same size as the original data
terial estimating models, produces a sample. The elements of each sample
Parameter Value Unit
single point estimate for the bridge su- were randomly chosen from the original
l 40.00 m
perstructure cost. Probabilistic estimat- data with replacements; as a result, the
b 13.00 m
ing techniques, such as bootstrap, at- bootstrap data set consists of members
tempt to provide additional information, of the original data set, some of which lsadj 39.69 m

assess the variability of the estimate, may have been chosen several times cc 200.00 / m3
and ultimately quantify its level of un- or not at all in any particular bootstrap cp 3.80 / kg
certainty. Bootstrap belongs to a larger sample. cs 1.00 / kg
class of methods that resample from the The linear regression model presented in
original data set. Its most attractive fea- equation 2 was then applied to the boot- table 6. Parameter values for the
ture includes its freedom from restrictive strap data set. The intercept and slope case project.

188 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 2 (2 )2 010
Probability level Model ConCLUsIons
5% 50% 95% estimate The conceptual cost estimate method
Vc 361.9 373.2 383.4 373.3 presented herein addresses the super-
Bs 45,253.8 46,686.7 48,078.7 46,725.7 structure (i.e., the most costly compo-
Bp 11,741.2 12,137.8 12,632.0 12,138.6 nent of the bridge) and applies to three
Cc 72,383.9 74,646.9 76,684.5 74,651.6 widely used deck construction meth-
Cs 45,253.8 46,686.7 48,078.7 46,725.7
ods. The required input data consist of
basic parameters identified during the
Cp 44,616.6 46,123.5 48,001.5 46,126.6
preliminary study of a particular bridge.
TC 162,254.3 167,457.1 172,764.7 167,503.9
Linear regression was applied in order
table 7. estimate ranges for the case example. to derive the material estimating mod-
els necessary for the cost estimate. Not
only was the fit of the models satisfac-
tory, but also the basic assumptions
of the linear regression methodology
were tested and the necessary adjust-
ments were made. The performance of
the material estimating models was
evaluated using the 10-fold validation
method; the models prediction error
was considered acceptable for feasibil-
ity estimates.
A bootstrap method was also imple-
mented in combination with the regres-
sion analysis in order to derive estimate
ranges for the predicted superstructure
costs. This probabilistic estimating
Figure 1. empirical probability distribution function for the predicted
superstructure cost.

Name Section Seismic Zone Width (m) Length (m) Deck Type Construction Method
6 11.3 II 12.70 210.00 Precast beams Precast beams
Kompsatou 14.3.2 II 15.07 416.00 Precast beams Precast beams
Erithropotamou 80.4 I 13.00 356.00 Precast beams Precast beams
Kalogirou 4.2.2 II 12.10 280.00 Precast beams Precast beams
Bridge 5 - L 13.5 II 13.10 270.00 Precast beams Precast beams
Bridge 5 - R 13.5 II 13.10 345.00 Precast beams Precast beams
Bridge 6 13.5 II 13.10 165.00 Precast beams Precast beams
Votonosi - L 3.2 II 13.00 547.00 Box girder Bal cantilever
Votonosi - R 3.2 II 13.00 536.50 Box girder Bal cantilever
Bridge 2 L 4.1.1 I 14.20 345.00 Box girder Bal cantilever
Bridge 2 R 4.1.1 I 14.20 349.00 Box girder Bal cantilever
Bridge 12 L 5.1 II 14.00 457.00 Box girder Bal cantilever
Greveniotikou 4.1.5 II 12.78 920.00 Box girder Bal cantilever
Mesovouniou 1.1.3 III 12.95 259.00 Box girder Bal cantilever
Bridge 5 - L 2.4 II 13.50 240.00 Box girder Cast-in-situ
Irinis 15.6 I 13.90 180.00 Box girder Cast-in-situ
Bridge 12 14.3.1 II 13.95 145.00 Box girder Cast-in-situ
Bridge 3 15.1.1 II 13.95 113.00 Box girder Cast-in-situ
Bridge 4 6.0 II 13.50 135.80 Box girder Cast-in-situ

Appendix A Representative sample of the bridge database

n. fragkakis s. lambropoulos j.p. pantouvakis a cost estimate method for bridge ... pp 182-190 189
technique was used in order to reduce pmbook.ce.cmu.edu/05_Cost_ bridges, John Wiley & Sons Ltd., UK.
Estimation.html (accessed 20 March Menn, C. (1990), Prestressed concrete
the level of uncertainty inherent in the
2008). bridges, Birkhauser, Germany.
estimates.
Hughes, W.O. and Paez, T.L. (2006), Miles, J.C. and Moore, C.J. (1991), An
Application of the bootstrap statistical expert system for the conceptual design
method in deriving vibroacoustic of bridges, Computers & Structures, Vol.
References specifications, paper presented at 40 No. 1, pp. 101-105.
Aparicio, A.C., Casas, J.R. and Ramos, the 9th International conference on Philbey, B.T., Miles, C. and Miles, J.C.
G. (1996), Computer aided design of Recent advances in structural dynamics, (1993), User-interface design for
prestressed concrete highway bridges, July 17-19, Southampton, United a conceptual bridge design expert
Computers & Structures, Vol. 60 No. 6, Kingdom, available at http://ntrs. system, Computing Systems in
pp.957-969. nasa.gov/archive/nasa/casi.ntrs.nasa. Engineering, Vol. 4 No. 2-3, pp. 235-241.
Belshey, D.A., Kuh, E. and Welsch, R. gov/20060056319_2006258493.pdf Ritz, G.J. (2004), Total Construction Project
(1980), Regression diagnostics: (accessed 14 March 2009). Management, Mc Graw Hill, New York.
Identifying influential data and sources Konstantinidis, D. and Maravas, A. (2003), Sarma, K.C. and Adeli, H. (1998), Cost
of collinearity, Wiley, New York. Egnatia Motorway concrete bridges optimization of concrete structures,
Brubaker, K.L. and McCuen, R.H. (1990), statistics, in 31st ASECAP Study and Journal of Structural Engineering, Vol.
Level of significance selection in Information Days proceedings of the 124 No.5, pp.570-579.
engineering analysis, Journal of international conference in Portoroz, Shapiro, S. S. and Wilk, M. B. (1965), An
Professional Issues in Engineering ASCE, Slovenia,2003, pp. 92-109. analysis of variance test for normality
Vol. 116 No. 4, pp. 375-387. Long, J.S. and Ervin, L.H. (2000), Using (complete samples), Biometrika, Vol. 52
Chernick, M.R. (1999), Bootstrap methods. heteroscedasticity consistent standard No. 3-4, pp. 591611.
A practitioners guide, John Wiley & Sons errors in the linear regression model, Sirca, G.F. and Adeli, H. (2005), Cost
Inc., USA. The American Statistician, Vol. 54, pp. optimization of prestressed concrete
Cohn, M.Z. and Lounis, Z. (1994), Optimal 217-224. bridges, Journal of Structural
design of structural concrete bridge Lounis, Z. and Cohn, M.Z. (1993), Engineering, Vol. 131 No. 3, pp. 380-388.
systems, Journal of Structural Optimization of precast prestressed Skamris, M.K. and Flyvbjerg, B. (1997),
Engineering, Vol. 120 No. 9, pp. 2653- concrete bridge girder systems, PCI Inaccuracy of traffic forecasts and cost
2674. Journal, Vol. 38 No. 4, pp. 60-78. estimates on large transport projects,
Davison, A.C. and Hinkley, D.V. (1997), Lowe, D.J., Emsley, M.W. and Harding, A. Transport Policy, Vol. 4 No. 3, pp. 141-
Bootstrap methods and their application, (2006), Predicting construction cost 146.
Cambridge University Press, USA. using multiple regression techniques, Sonmez, R. (2008), Parametric range
Gujarati, D. (1999), Essentials of Journal of Construction Engineering and estimating of building costs using
Econometrics, Irwin Mc Graw Hill, New Management, Vol. 132 No.7, pp. 750-758. regression models and bootstrap,
York. MacKinnon, J.G. and White, H. (1985), Journal of Construction Engineering and
Hegazy, T. and Ayed, A. (1998), Neural Some heteroskedasticity consistent Management, Vol. 134 No. 12, pp. 1011-
network model for parametric cost covariance matrix estimators with 1016.
estimation of highway projects, improved finite sample properties, United States Department of Energy (1997),
Journal of Construction Engineering and Journal of Econometrics, Vol. 29, pp. Types of cost estimates - guide DOE G
Management, Vol. 124 No.3, pp. 210-218. 53-57. 430.1-1, United States Department of
Hendrickson, C. (2008), Project Maddala, G.S. (1992), Introduction to Energy.
Management for Construction, Econometrics, 2nd edition, Macmillan White, H. (1980), A heteroskedasticity-
Fundamental Concepts for Owners, Publishing Company, New York. consistent covariance matrix and a
Engineers, Architects and Builders, Mathivat, J. (1983), The cantilever direct test for heteroskedasticity,
version 2.2, available at http:// construction of prestressed concrete Econometrica, Vol. 48, pp 817-838.

190 o rga nization , technology and management i n constructi on an i nte rnati onal j o urnal 2 (2 )2 010

Anda mungkin juga menyukai