A piped water supply scheme stage estimated costing Rs. 70.83 Lac has
been prepared for providing safe and adequate potable water through
over head service reservoir to the village Sunarpura Block Mehgaon Distt.
Bhind (M.P).
At present people are getting water through 25 Nos. hand pumps installed
in the different location of village. But due to the increasing demand of
safe drinking water through tap supply it is necessary to execute pipe
water supply scheme to fulfill the future demand of water with sufficient
pressure to the house hold of the villages.
3. POPULATION AND WATER DEMAND :
(A) SOURCE :
(G)POWER CONNECTION:
Provision has been made in the estimate for taking permanent electric
connection or proposed on Nos. 25 KVA transformers and service line as
required.
One no 25 KVA generator set is also proposed for power supply in case of
power cut or interrupted power supply. The cost of service line along with the
Generator works out to be Rs 1.60 lac (Rs one lac sixty thousand) only
(H)COST OF SCHEME:
The estimate cost of the scheme works out to be Rs. 70.83 lack.
6
( I) ANNUAL AND RUNNING MAINTENANCE COST:
STATETIC HEAD:
SUCTION HEAD : 60M
TOTAL HEAD : 85
Say : 85
Hours of pumping : 12
75X0.45
7
Hence it is proposed to provide 2 Nos. submersible pump set of 5HP capable of
discharging 3.70 litters per second against 85 meter head.
= H.P x365XO.746X4.5XHrs.
=2 Nosx45500x12 = Rs.108000.00
Total
Rs. 315036.00
ESTIMATE
Name of work: Detailed estimate for laying & jointing of G.I pipe line 80.100&150 mm dia
for distribution line Village Sunarpura
S.N Uni
Description of work Qty Rate Amount
o. t
1 Dismantling Kharjana of any thickness in
cement mortar of any mix. 450.00 cum 28.00 12600.00
3000x0.75x0.20=450.00 Cum.
2 Earth work in excavation for pipe trench
in all kind of soil and WBM in areas
including dressing, watering and
107.0
ramming and disposal of Excavated 225.00 cum 24075.00
0
earth lead upto 50 m. and lift upto 1.5 m
disposal earth to be leveled neatly
dressed.3000x0.75x0.30=225.00 Cum
3 Providing for laying & jointing following
galvanized iron (MS) pipe with specials
(Such as bed elbows , tee etc) class
light, medium & heavy i/c testing of
joints & cost of jointing materials but 454.0
excluding cost of valve & specials 2350m 0 1066900.0
300M RM 651.0 195300.0
(i) G.I Pipe 80 mm dia.
(ii) G.I. Pipe 100mm dia. 350M 0 342650.0
(iii) G.I. pipe 150mm dia 979.0 1604850.0