Anda di halaman 1dari 13

DAFTAR HARGA SATUAN PEKERJAAN WINNER T.

F
KEGIATAN : PROYEK PEMBANGUNAN RUMAH 20307046
PEKERJAAN : KONSTRUKSI RUMAH 3 TB 01
LOKASI : JAKARTA
TAHUN ANGGARAN : 2008

NO URAIAN PEKERJAAN SATUAN INDEKS BAHAN DAN UPAH (Rp) JUMLAH (Rp)

I PEKERJAAN PERSIAPAN
1 PEMBERSIHAN LAHAN
Pekerja 10m 0.75 55,798.00 41,848.50
Mandor 10m 0.025 85,607.00 2,140.18
TOTAL 43,988.68

2 PEMASANGAN BOUWPLANK
Papan dan Pancang m 0.01 8,050,000.00 80,500.00
Paku m 0.1 15,000.00 1,500.00
Tukang Kayu m 0.8 65,734.00 52,587.20
Kepala Tukang Kayu m 0.08 75,671.00 6,053.68
Pekerja m 0.28 55,798.00 15,623.44
Mandor m 0.014 85,607.00 1,198.50
TOTAL 157,462.82

3 GALIAN TANAH U/ PONDASI


Pekerja m 0.75 55,798.00 41,848.50
Mandor m 0.025 85,607.00 2,140.18
TOTAL 43,988.68

4 URUGAN PASIR BWH PONDASI


Pasir m 1.2 180,000.00 216,000.00
Pekerja m 0.3 55,798.00 16,739.40
Mandor m 0.01 85,607.00 856.07
TOTAL 233,595.47
5 URUGAN PASIR BWH LANTAI
Pasir m 1.2 180,000.00 216,000.00
Pekerja m 0.3 55,798.00 16,739.40
Mandor m 0.01 85,607.00 856.07
TOTAL 233,595.47

6 URUGAN TANAH KEMBALI SISI PONDASI


Pekerja m 0.75 55,798.00 41,848.50
Mandor m 0.025 85,607.00 2,140.18
TOTAL 43,988.68

7 URUGAN TANAH PENINGGIAN LANTAI


Pekerja m 0.75 55,798.00 41,848.50
Mandor m 0.025 85,607.00 2,140.18
TOTAL 43,988.68

NO URAIAN PEKERJAAN SATUAN INDEKS BAHAN DAN UPAH (Rp) JUMLAH (Rp)

II PEKERJAAN PONDASI
1 PONDASI BATU KALI
Batu Kali m 1.2 160,000.00 192,000.00
Semen m 4.26 52,000.00 221,520.00
Pasir Pasang m 0.34 160,000.00 54,400.00
Tukang Batu m 0.6 65,734.00 39,440.40
Kepala Tukang Batu m 0.06 75,671.00 4,540.26
Pekerja m 1.5 55,798.00 83,697.00
Mandor m 0.015 85,607.00 1,284.11
TOTAL 596,881.77

III PEKERJAAN BETON


1 SLOOF BETON
Upah Pembesian m 0.75 1,095,000.00 821,250.00
Kepala tukang batu m 0.039 75,671.00 2,951.17
Pekerja m 0.781 55,798.00 43,578.24
Mandor m 0.078 85,607.00 6,677.35
TOTAL 874,456.75

2 KOLOM BETON
Upah Pembesian m 0.75 1,095,000.00 821,250.00
Kepala tukang batu m 0.039 75,671.00 2,951.17
Pekerja m 0.781 55,798.00 43,578.24
Mandor m 0.078 85,607.00 6,677.35
TOTAL 874,456.75

3 RING BALK BETON


Upah Pembesian m 0.75 1,095,000.00 821,250.00
Kepala tukang batu m 0.039 75,671.00 2,951.17
Pekerja m 0.781 55,798.00 43,578.24
Mandor m 0.078 85,607.00 6,677.35
TOTAL 874,456.75

4 MEJA DAPUR
Semen m 8.5 52,000.00 442,000.00
Pasir beton m 0.54 160,000.00 86,400.00
Kerikil m 0.82 260,000.00 213,200.00
Tukang batu m 1 65,734.00 65,734.00
Pekerja m 3 55,798.00 167,394.00
Mandor m 0.1 85,607.00 8,560.70
TOTAL 983,288.70

5 LIST PLANK
Semen m 8.5 52,000.00 442,000.00
Pasir beton m 0.54 160,000.00 86,400.00
Kerikil m 0.82 260,000.00 213,200.00
Tukang batu m 1 65,734.00 65,734.00
Pekerja m 3 55,798.00 167,394.00
Mandor m 0.1 85,607.00 8,560.70
TOTAL 983,288.70

NO URAIAN PEKERJAAN SATUAN INDEKS BAHAN DAN UPAH (Rp) JUMLAH (Rp)

6 TOPI TERAS
Semen m 8.5 52,000.00 442,000.00
Pasir beton m 0.54 160,000.00 86,400.00
Kerikil m 0.82 260,000.00 213,200.00
Tukang batu m 1 65,734.00 65,734.00
Pekerja m 3 55,798.00 167,394.00
Mandor m 0.1 85,607.00 8,560.70
TOTAL 983,288.70

7 LANTAI KERJA
Semen m 8.5 52,000.00 442,000.00
Pasir beton m 0.54 160,000.00 86,400.00
Kerikil m 0.82 260,000.00 213,200.00
Tukang batu m 1 65,734.00 65,734.00
Pekerja m 3 55,798.00 167,394.00
Mandor m 0.1 85,607.00 8,560.70
TOTAL 983,288.70

IV PEKERJAAN PASANGAN DINDING DAN PLESTERAN


1 PASANGAN DINDING BATA MERAH ( 1:2 )
Batu bata merah m 80 260.00 20,800.00
Semen m 0.52 35,100.00 18,252.00
Pasir pasang m 0.042 169,000.00 7,098.00
Tukang batu m 0.16 65,734.00 10,517.44
Kepala T. Batu m 0.016 75,671.00 1,210.74
Pekerja m 0.48 55,798.00 26,783.04
Mandor m 0.048 85,607.00 4,109.14
TOTAL 88,770.35

2 PASANGAN BATU ROLLAG ( 1:4 )


Batu bata merah m 475 260.00 123,500.00
Semen m 2.4 35,100.00 84,240.00
Pasir pasang m 0.416 169,000.00 70,304.00
Tukang batu m 1.5 65,734.00 98,601.00
Kepala T. Batu m 0.15 75,671.00 11,350.65
Pekerja m 3 55,798.00 167,394.00
Mandor m 0.15 85,607.00 12,841.05
TOTAL 568,230.70

3 PLESTERAN DAN ACI ( 1:2, TEBAL 15 mm )


Semen m 0.2368 35,100.00 8,311.68
Pasir pasang m 0.019 169,000.00 3,211.00
Tukang batu m 0.214 65,734.00 14,067.08
Kepala T. Batu m 0.021 75,671.00 1,589.09
Pekerja m 0.4 55,798.00 22,319.20
Mandor m 0.02 85,607.00 1,712.14
TOTAL 51,210.19

NO URAIAN PEKERJAAN SATUAN INDEKS BAHAN DAN UPAH (Rp) JUMLAH (Rp)

V PEKERJAAN LANTAI DAN DINDING


1 LANTAI KERAMIK ( 30X30 CM )
Ubin keramik 30x30 m 1.05 150,000.00 157,500.00
Pasir pasang m 0.03 169,000.00 5,070.00
Semen m 0.2 35,100.00 7,020.00
Semen warna m 0.07 2,210.00 154.70
Tukang batu m 0.4 65,734.00 26,293.60
Kepala T. Batu m 0.075 75,671.00 5,675.33
Pekerja m 0.2 55,798.00 11,159.60
Mandor m 0.02 85,607.00 1,712.14
TOTAL 214,585.37

LANTAI KERAMIK ( 20X20 CM)


Ubin keramik 20x20 m 1.05 70,000.00 73,500.00
Pasir pasang m 0.03 169,000.00 5,070.00
Semen m 0.2 35,100.00 7,020.00
Semen warna m 0.1 2,210.00 221.00
Tukang batu m 0.4 65,734.00 26,293.60
Kepala T. Batu m 0.075 75,671.00 5,675.33
Pekerja m 0.2 55,798.00 11,159.60
Mandor m 0.02 85,607.00 1,712.14
TOTAL 130,651.67

2 DINDING KERAMIK ( 20X25 CM )


Ubin keramik 20x25 m 1.05 70,000.00 73,500.00
Pasir pasang m 0.03 169,000.00 5,070.00
Semen m 0.2 35,100.00 7,020.00
Semen warna m 1 2,210.00 2,210.00
Tukang batu m 0.5 65,734.00 32,867.00
Kepala T. Batu m 0.1 75,671.00 7,567.10
Pekerja m 0.25 55,798.00 13,949.50
Mandor m 0.025 85,607.00 2,140.18
TOTAL 144,323.78

3 PLIN KERAMIK
Plin keramik m 1.01 17,500.00 17,675.00
Semen m 0.025 35,100.00 877.50
Pasir pasang m 0.03 169,000.00 5,070.00
Tukang batu m 0.1 65,374.00 6,537.40
Kepala T. Batu m 0.01 75,671.00 756.71
Pekerja m 0.15 55,798.00 8,369.70
Mandor m 0.01 85,607.00 856.07
TOTAL 40,142.38
VI PEKERJAAN ATAP
1 KUDA-KUDA ATAP RUMAH

Balok kayu bengkirai m 1.100 8,050,000.00 8,855,000.00

Paku kg 3.000 8,000.00 24,000.00

Besi strip kg 15.000 8,900.00 133,500.00

Tukang Kayu org/hr 15.000 65,374.00 980,610.00

Kepala Tukang Kayu org/hr 1.500 75,671.00 113,506.50

Pekerja org/hr 5.000 55,798.00 278,990.00

Mandor org/hr 0.250 85,607.00 21,401.75


10,407,008.25

2 GORDING KAYU

Balok kayu bengkirai m 1.1000 8,050,000.00 8,855,000.00

Paku kg 2.900 8,000.00 23,200.00

Tukang Kayu org/hr 4.5000 65,374.00 294,183.00

Kepala Tukang Kayu org/hr 0.4500 75,671.00 34,051.95

Pekerja org/hr 1.5000 55,798.00 83,697.00

Mandor org/hr 0.0750 85,607.00 6,420.53


9,296,552.48

3 KASO DAN RENG

Kaso m 0.0120 6,900,000.00 82,800.00

Reng m 0.0053 6,900,000.00 36,570.00


Paku Rata-rata kg 0.1500 8,000.00 1,200.00

Tukang Kayu org/hr 0.1000 65,374.00 6,537.40

Kepala Tukang Kayu org/hr 0.0100 75,671.00 756.71

Pekerja org/hr 0.1000 55,798.00 5,579.80

Mandor org/hr 0.0050 85,607.00 428.04


133,871.95

4 LISTPLANK KAYU 3/20

Papan kayu Samarinda m 0.0070 9,430,000.00 66,010.00

Paku Rata-rata kg 0.0500 8,000.00 400.00

Tukang Kayu org/hr 0.2000 65,374.00 13,074.80

Kepala Tukang Kayu org/hr 0.0200 75,671.00 1,513.42

Pekerja org/hr 0.1000 55,798.00 5,579.80

Mandor org/hr 0.0050 85,607.00 428.04


87,006.06

5 PASANG ATAP GENTENG PRESS BETON

Genteng Press Beton bh 11.100 3,300.00 36,630.00

Tukang Batu org/hr 0.100 65,374.00 6,537.40

Kepala Tukang Batu org/hr 0.010 75,671.00 756.71

Pekerja org/hr 0.200 55,798.00 11,159.60

Mandor org/hr 0.010 85,607.00 856.07


55,939.78
6 PASANG NOK GENTENG PRESS BETON

Nok Genteng Press Beton bh 4.040 4,000.00 16,160.00

Semen zak 0.216 35,100.00 7,581.60

Pasir Beton m 0.032 130,000.00 4,160.00

Papan Ruiter Kamper m 0.003 6,900,000.00 20,700.00

Tukang Batu org/hr 0.200 65,374.00 13,074.80

Kepala Tukang Batu org/hr 0.020 75,671.00 1,513.42

Pekerja org/hr 0.400 55,798.00 22,319.20

Mandor org/hr 0.020 85,607.00 1,712.14


87,221.16

Pekerjaan Talang Datar Seng 0,3 mm + Alas Papan, tebal 2


7 Cm

Papan Kamper 2/20 m 0.008 6,900,000.00 55,200.00

Kaso m 0.002 6,900,000.00 16,560.00

Seng plat tebal 0,3 mm m' 1.050 20,000.00 21,000.00

Paku Rata-rata kg 0.150 8,000.00 1,200.00

Paku Seng kg 0.150 10,000.00 1,500.00

Timah kg 0.100 1,500.00 150.00

Tukang Besi org/hr 0.200 65,374.00 13,074.80

Tukang Kayu org/hr 0.150 65,374.00 9,806.10

Kepala Tukang Besi org/hr 0.020 75,671.00 1,513.42

Pekerja org/hr 0.200 55,798.00 11,159.60


Mandor org/hr 0.010 85,607.00 856.07
132,019.99

VII PEKERJAAN PLAFOND


1 Plafond Eternit/Asbes Ukuran eternit 60x120x0,5 cm

Eternit/asbes plat 60x120 lbr 1.400 27,600.00 38,640.00

Paku Rata-rata kg 0.030 8,000.00 240.00

Tukang Kayu org/hr 0.160 65,374.00 10,459.84

Kepala Tukang Kayu org/hr 0.016 75,671.00 1,210.74

Pekerja org/hr 0.112 55,798.00 6,249.38

Mandor org/hr 0.006 85,607.00 513.64


57,313.59

2 Rangka Plafond Kayu (Grid 60 x 60 Cm)

Balok kayu bengkirai m 0.005 8,050,000.00 40,250.00

Kaso Kayu m 0.020 6,900,000.00 138,000.00

Paku Rata-rata kg 0.200 8,000.00 1,600.00

Tukang Kayu org/hr 0.400 65,374.00 26,149.60

Kepala Tukang Kayu org/hr 0.040 75,671.00 3,026.84

Pekerja org/hr 0.280 55,798.00 15,623.44

Mandor org/hr 0.014 85,607.00 1,198.50


225,848.38

VIII PEKERJAAN KUSEN, PINTU, JENDELA


1 Pekerjaan Kaca (tebal < 10 mm)
Kaca polos m 1.100 5,000.00 5,500.00

Tukang Kayu org/hr 0.240 65,374.00 15,689.76

Kepala Tukang Kayu org/hr 0.024 75,671.00 1,816.10

Pekerja org/hr 0.080 55,798.00 4,463.84

Mandor org/hr 0.004 85,607.00 342.43


27,812.13

Daun Pintu/ Jendela Jalusi/ Krepyak (Kayu Kamper, tebal 3,5


2 cm)

Papan kayu Samarinda m 0.064 9,430,000.00 603,520.00

Paku rata-rata kg 0.200 8,000.00 1,600.00

Lem kayu kg 0.300 8,000.00 2,400.00

List kayu m' 4.000 27,600.00 110,400.00

Tukang Kayu org/hr 5.4000 65,374.00 353,019.60

Kepala Tukang Kayu org/hr 0.5400 75,671.00 40,862.34

Pekerja org/hr 1.8000 55,798.00 100,436.40

Mandor org/hr 0.0900 85,607.00 7,704.63


1,219,942.97

IX PEKERJAAN CAT
1 Cat Kayu (2 Lapis)
Termasuk Pekerjaan : Plamur, mengamplas

Plamur Kayu kg 0.150 9,750.00 1,462.50

Amplas lbr 0.500 2,000.00 1,000.00


Cat dasar kg 8,000.00 1,200.00
0.150

Cat Kayu kg 0.300 20,000.00 6,000.00

Thinner ltr 0.150 8,000.00 1,200.00

Kuas bh 0.050 6,500.00 325.00

Tukang Cat org/hr 0.250 65,374.00 16,343.50

Kepala Tukang Cat org/hr 0.025 75,671.00 1,891.78

Pekerja org/hr 0.200 55,798.00 11,159.60

Mandor org/hr 0.010 85,607.00 856.07


41,438.45

2 Cat Dinding Interior (Dinding Baru, 3 Lapis)

Plamur Tembok kg 0.200 9,750.00 1,950.00

Amplas lbr 0.500 2,000.00 1,000.00

Cat dasar kg 0.100 50,000.00 5,000.00

Cat Tembok kg 0.200 50,000.00 10,000.00

Kuas roll bh 0.015 9,000.00 135.00

Tukang Cat org/hr 0.250 65,374.00 16,343.50

Kepala Tukang Cat org/hr 0.025 75,671.00 1,891.78

Pekerja org/hr 0.200 55,798.00 11,159.60

Mandor org/hr 0.010 85,607.00 856.07


48,335.95

3 Cat Dinding Exterior (Dinding Baru, 3 Lapis) ICI


Alkali ICI sebelum pengecatan kg 50,000.00 6,250.00
0.125

Cat tembok ICI Wheathershield kg 0.200 20,000.00 4,000.00

Amplas lbr 0.500 2,000.00 1,000.00

Kuas roll bh 0.015 9,000.00 135.00

Tukang Cat org/hr 0.280 65,374.00 18,304.72

Kepala Tukang Cat org/hr 0.030 75,671.00 2,270.13

Pekerja org/hr 0.160 55,798.00 8,927.68

Mandor org/hr 0.010 85,607.00 856.07


41,743.60