GE imagination at work
1
GE Oil & Gas
Abstract
In recent years, market demand for plant uptime has progressively increased. Turbocompressor
technology usually represents the core equipment of a plant and its availability is one of the key
factors in optimizing plant uptime. OEMs have concentrated significant engineering efforts on
developing new hardware to extend the mean time between maintenance (MBTM) and to reduce
the need for downtime inspection activities.
The new generation of material technology for hot gas path parts is focused on enhancing the
durability of machines. The combination of proven materials and advanced technology from
other industries, such as the aircraft engine industry, accelerates the introduction of improved
materials, coatings and design solutions into new machines as well as into retrofit kits to uprate
installed base units. Uprate kits are designed to be fully interchangeable with original parts.
Hence, they can be installed during planned shutdowns of a unit with no additional impact on
the plant downtime, and in some cases, even significantly reducing the downtime.
These advances are all key to extending equipment availability, which translates into additional
days of production as well as reduced life cycle cost.
Reliability and availability are the metrics Reduction of site activities turn around time
used to measure up time, and are specified Reduction of planned maintenance
by the ISO3977-9 definition [1]: Reduction of unplanned maintenance
1
This paper was prepared for presentation and awarded at the SAOGE 2008 in Dammam, Saudi Arabia, November 15-17, 2008
GE Oil & Gas
are set parallel to the machines centerline. A gas turbine maintenance program can be
Expansion is achieved in 2 turbine stages with split into:
impulse rotor buckets: the first stage drives
the axial compressor and the two together Preventive maintenance
comprise the high-pressure shaft; the second Inspection during operation
stage drives the low-pressure shaft and load. This consists of logging the key operational
The partition airfoils of the first stage fixed parameter during start-up and while the unit
nozzles are cooled with air from compressor is in service. Subsequent analysis of this data
bleed, while the partition airfoils of the second establishes the general conditions of the unit
stage fixed nozzles have an adjustable angle and auxiliary systems.
which enables broad speed range and load Standby inspection
flexibility. Owing to their flexibility, high This is conducted when units are out of
capacity, simplicity and low maintenance operation due to the plant schedule and
requirements, these units are ideal drivers for therefore does not interfere with availability
pipeline centrifugal compressors. The FR5/2D but increase reliability.
is also used in natural gas re-injection plants
to drive high pressure re-injection centrifugal Activities may include changing filters,
compressors checking the lube oil level, checking and
regulating instrumentation, etc.
An overview of the case study presented is
shown in Table 1. Scheduled maintenance
Scheduled maintenance is performed with
Cycle Simple
machines out of service, as the unit has to be
Fuel Natural gas disassembled so that internal components can
NOX emission reduc. system Not installed be inspected. The scope of the area to be dis-
assembled depends on the type of inspection.
Type of application Mechanical drive
Inspections start from the most critical zone,
Type of operation Continuous which is the point where the temperature is
Type of installation site On shore highest, and continue to cover the entire mach-
ine at subsequent increased inspection levels:
Inlet plenum Side
Table 1 Case study gas turbine configuration The zones covered by the above mentioned
inspections are shown in the cross-section
Maintenance drawing of the turbine in Figure 1.
Operation of a gas turbine, like any other
rotating machine generating mechanical
power, must include a maintenance program
for repair and/or replacement of parts when
needed to ensure maximum availability and
reliability of the unit. Naturally, this maintenance
program will begin with minor operations,
which will increase in scope over time and
according to the severity of operation up to the
point of a major inspection. This maintenance
pattern is repeated cyclically. figure 1 FR5/2D Gas turbine maintenance sections 2.1.
2
GE Oil & Gas
OFF ON
BLINDING
COLD
WORKS NO WORKS
Natural gas fuel ONLY HOT WORKS / OPEN FLAME ACTIVITIES
3
GE Oil & Gas
4
GE Oil & Gas
Figure 2 From left to right: bearing #1 flexible lube oil piping, bearing #4 flexible lube oil piping, extended pin for
engine positioning
Engine swap
5 initiation
early mature breakthrough
18 phase
(planning)
phase phase needed
10
Jet
13 12 13 15
5 20
2006 2006 2007 2007 2008
Events
Experience
Figure 3 Left: GE Oil & Gas modular replacement experience. Right: Modular replacement learning curve
5
GE Oil & Gas
6
GE Oil & Gas
MTBM extension
Figure 4 Departure record enablers
Enhancing availability by injecting the In those plants where plant down time is
latest design technology critical, plug and play is a winning solution.
GE Oil & Gas over the years has consistently A heavy-duty machine plus centrifugal
invested in new technology and new compressor, customized to meet the required
materials to improve the mean time between plant pressure and service configuration is
maintenance of its products. The focus of the most common type of train for oil and gas
the research and development team has applications. In these designs, maintenance
also extended to the installed fleet, seeking activities are scheduled to match the plant
solutions that can be easily retrofitted into production cycle and the life cycle of the
a machine that has been running for years, critical components of the machinery that is
without increasing the plant complexity and driven by the hot gas path of the gas turbine
the management of the turbotrain. and the compressor wear parts.
7
GE Oil & Gas
GE Oil & Gas R&D efforts strive to create The first stage nozzle and shroud complete
products and solutions that closely match the the path of the turbine components that have
MTBM targets demanded by applications, the been analyzed to rejuvenate the product, and
market and customer expectations. The Power light modifications have been included.
Crystal kit, for the GE frame 5 two shaft
machine is one of the outcomes of this effort. A new material has been applied to the shroud
and a new cooling system design is now embed-
The Power Crystal kit builds on the long history ded into the final machined first stage nozzle.
of successful Frame 5 upgrades since the
introduction of the first A model in 1970. Combustion hardware is a critical area for the
The features of the kit allow the maintenance operating life of a gas turbine that requires
schedule to be extended with no impact on the periodic inspection. The duty cycle and type
reliability and availability of the gas turbine. of fuel used are the key factors in determining
the recommended combustion intervals since
The Power Crystal kit is composed of the these factors directly influence the amount
turbine first stage buckets made of single of thermal barrier coating erosion, material
crystal material that have given the name to creep, thermal stress and wear of the
the kit, and of other hot gas path components combustion components.
such as combustion hardware, shrouds and
first stage nozzles that complete the supply. The Power Crystal kit includes extendorized
combustion parts that can increase inspection
Power Crystal technology intervals by significantly reducing combustion
The latest advance in hot part technology component wear. Wear is the most critical
has seen the introduction of single crystal failure mode of combustion hardware in HD
buckets, which offer the potential of further gas turbines.
improving the strength of high temperature
materials through the control of crystal The new extendor kit consists of the latest
orientation. With a single crystal material, all hard coating material and the redesign of
grain boundaries are eliminated from the parts to reduce wear on various combustion
structure and a single crystal with controlled system components.
orientation is produced in an airfoil shape.
By eliminating all grain boundaries and with
associated strengthening additives, a subst-
antial increase in the melting point of the alloy
can be achieved, thus providing a corresponding CL OF CROSSFIRE TUBE
8
GE Oil & Gas
Data analysis
Normalized data
All the recent technology
developments have been Site raw data
conducted in partnership with
Customers, fully exploiting the Figure 8 Data layers
9
GE Oil & Gas
Examples of raw data are the parameters and diagnostic tools. Applying this approach
acquired by the unit control system to control systematically to data acquired remotely,
and protect the machine during site operations; the analysis of the diagnostic engineer can
normalized data are typically ratios between be concentrated at higher levels to increase
raw data to decrease the level of variation of the the effectiveness of service and to support
phenomena and enable easier data manage- maintenance technicians in making decisions
ment both at the unit and fleet level. Post- during scheduled maintenance activities or in
processed data represent the maximum level case of emergencies.
of abstraction and are normally derived
parameters or performance parameters Remote monitoring and diagnostic tools
including polytropic and isentropic efficiencies, represent a means of increasing the value of
power at reference conditions and non- information from raw data; using site data
dimensional coefficients or internal design flows. acquired and processed by an RM&D system
and taking into account the added accuracy [2]
As an example of a set of data, we can that this process provides, a set of systematic
start from an axial compressor discharge analysis can be started and used to help in
temperature, then normalize it to the inlet the troubleshooting of rotating equipment
temperature, and calculate the expected under real operating conditions.
values at the same thermodynamic conditions.
Comparing data at the same inlet guide The following diagram represents the link
vane angle and plotting the data against the between site data sources and intermediate
compression ratio, the following results can tools used to define the symptoms of
be obtained: performance losses.
Statistic feedback
Weighted
RCA
0.89
Recent development efforts have been
dedicated to developing the root cause
PRT-GT:E2D3 [-]
0.87
0.85
analysis (RCA) process.
0.83
On the anomalies management side, diagnostic
0.81
engineers are assisted by a prognostic engine
0.79
designed to manage anomalies by exceptions,
0.77
based on diagnostic rules. By analyzing site
0.75
4600 4700 4800 4900 5000 5100 5200 5300 5400 data and using the historical unit behavior or
NHP_CORR [RPM] signatures, a set of prognostic rules is used to
Figure 9 Data analysis (actual data vs. baselines) trigger anomaly notifications. The prognostic
engine for anomaly evaluation and an expert
In general, data are available as raw measure-
system to expedite the RCA are important
ments and the following levels of abstraction
tools in used by the RM&D team .
are normally reached through the use of design
10
GE Oil & Gas
-15
1.075
1.07
-20
Conclusions
1.065
-25
We saw how the availability of a FR5/2 turbo-
1.06
-30 compressor can be dramatically improved.
1.055 -35
The modular replacement maintenance
1.05
approach can result in savings of nearly 50%
-40
1.22 1.24 1.26 1.28 1.3 1.32
PT OUT/PT IN
1.34 1.36 1.38 1.4
of the major overhaul down time. This means
an average of an additional 2 days of up time
Figure 12 Compressor anomaly identified by variation
of historical baseline
per year over the life of the gas turbine.
After notification, the compressor was opened We also saw that the introduction of the Power
to replace the component, and efficiency was Crystal kit allows the combustion inspection
recovered thereby avoiding loss of production to be pushed from 12,000 to 24,000 hours and
at the same available power. the Major Overhaul from 48,000 to 72,000
hours, with an expected availability improve-
In another case, a temperature sensor started ment of 2 days per year over the entire gas
to deviate from its normal behavior. The change turbine life.
was detected by the prognostic engine below
the trip limit of the machine and identified
11
GE Oil & Gas
References
[1] IEEE Transactions of Industry Application vol 31, no. 4
July/ August 1995