Anda di halaman 1dari 13

GE Oil & Gas

New solutions for the improvement


of turbocompressor availability
By Filippo Cinelli, Riccardo Valorosi, Gianni Mochi, Antonio Pumo, Dante Sabella / GE Oil & Gas

GE imagination at work
1
GE Oil & Gas

New solutions for the improvement


of turbocompressor availability
By Filippo Cinelli, Riccardo Valorosi, Gianni Mochi, Antonio Pumo, Dante Sabella / GE Oil & Gas

Abstract
In recent years, market demand for plant uptime has progressively increased. Turbocompressor
technology usually represents the core equipment of a plant and its availability is one of the key
factors in optimizing plant uptime. OEMs have concentrated significant engineering efforts on
developing new hardware to extend the mean time between maintenance (MBTM) and to reduce
the need for downtime inspection activities.

The new generation of material technology for hot gas path parts is focused on enhancing the
durability of machines. The combination of proven materials and advanced technology from
other industries, such as the aircraft engine industry, accelerates the introduction of improved
materials, coatings and design solutions into new machines as well as into retrofit kits to uprate
installed base units. Uprate kits are designed to be fully interchangeable with original parts.
Hence, they can be installed during planned shutdowns of a unit with no additional impact on
the plant downtime, and in some cases, even significantly reducing the downtime.

In addition, substantial improvements in specialized software to manage and analyze data on


operating equipment have been made, which provide faster and more accurate troubleshooting.
Predictive capabilities have also been embedded into software tools and in the near future it is
expected that they will be able to cover residual life assessment of hot gas path components as well.

These advances are all key to extending equipment availability, which translates into additional
days of production as well as reduced life cycle cost.

Introduction FOH = Forced Outage Hours: period of time


Uptime is one of the areas where oil and gas during which the maintenance team is
OEMs are concentrating their effort, investing actually working during forced outages
in new technology for products which address POH = Planned Outage Hours: period of
this key need. Maximizing up time means time during which the maintenance team is
reducing outages, extending the mean time actually working during planned outages
between maintenance, shortening site
activities and reducing unplanned shutdowns Key factors critical to enhancing up time
due to failures. include:

Reliability and availability are the metrics Reduction of site activities turn around time
used to measure up time, and are specified Reduction of planned maintenance
by the ISO3977-9 definition [1]: Reduction of unplanned maintenance

Reliability R = [(PH-FOH)/PH]x100 The cases addressed by this paper concentrate


Availability A = [(PH-(FOH+POH))/PH]x100 on the FR5/2 D model gas turbine.

Where The FR5/2 is an heavy-duty, double-shaft


F = number of failures gas turbine. The 17-stage axial compressor is
PH = Period Hours: cumulative hours a high efficiency model. The 12 combustion
of monitoring chambers, which have individual burners,

1
This paper was prepared for presentation and awarded at the SAOGE 2008 in Dammam, Saudi Arabia, November 15-17, 2008
GE Oil & Gas

are set parallel to the machines centerline. A gas turbine maintenance program can be
Expansion is achieved in 2 turbine stages with split into:
impulse rotor buckets: the first stage drives
the axial compressor and the two together Preventive maintenance
comprise the high-pressure shaft; the second Inspection during operation
stage drives the low-pressure shaft and load. This consists of logging the key operational
The partition airfoils of the first stage fixed parameter during start-up and while the unit
nozzles are cooled with air from compressor is in service. Subsequent analysis of this data
bleed, while the partition airfoils of the second establishes the general conditions of the unit
stage fixed nozzles have an adjustable angle and auxiliary systems.
which enables broad speed range and load Standby inspection
flexibility. Owing to their flexibility, high This is conducted when units are out of
capacity, simplicity and low maintenance operation due to the plant schedule and
requirements, these units are ideal drivers for therefore does not interfere with availability
pipeline centrifugal compressors. The FR5/2D but increase reliability.
is also used in natural gas re-injection plants
to drive high pressure re-injection centrifugal Activities may include changing filters,
compressors checking the lube oil level, checking and
regulating instrumentation, etc.
An overview of the case study presented is
shown in Table 1. Scheduled maintenance
Scheduled maintenance is performed with
Cycle Simple
machines out of service, as the unit has to be
Fuel Natural gas disassembled so that internal components can
NOX emission reduc. system Not installed be inspected. The scope of the area to be dis-
assembled depends on the type of inspection.
Type of application Mechanical drive
Inspections start from the most critical zone,
Type of operation Continuous which is the point where the temperature is
Type of installation site On shore highest, and continue to cover the entire mach-
ine at subsequent increased inspection levels:
Inlet plenum Side

Exhaust plenum Side


Combustion inspection = CI
Liners and transition pieces
Acoustic enclosure inspection = LTPI
Type of enclosure under shed (with
an overhead crane)
Major inspection = MI

Table 1 Case study gas turbine configuration The zones covered by the above mentioned
inspections are shown in the cross-section
Maintenance drawing of the turbine in Figure 1.
Operation of a gas turbine, like any other
rotating machine generating mechanical
power, must include a maintenance program
for repair and/or replacement of parts when
needed to ensure maximum availability and
reliability of the unit. Naturally, this maintenance
program will begin with minor operations,
which will increase in scope over time and
according to the severity of operation up to the
point of a major inspection. This maintenance
pattern is repeated cyclically. figure 1 FR5/2D Gas turbine maintenance sections 2.1.

2
GE Oil & Gas

Scheduled maintenance frequency of the MO on site challenged GE to complete it


Based on a wide variety of actual operating in 12 days vs. the standard 24 days considering
experience of heavy-duty gas turbines installed that the site team was organized for double
worldwide, the scheduled maintenance shifts of 12 hours each.
spacing method has been developed as an
initial guideline.
The major overhaul of
FR5/2D the FR5/2 gas turbine
inspections scheduled maintenance standard frequency -
was on the critical path
whichever occurs first of the entire LNG plant
shutdown. A 100%
CI
reduction of time could
LTPI not be achieved with the
HGPI standard maintenance
approach of stripping the
MI
unit and replacing the
firing hours: 0 12,000 24,000 36,000 48,000 hot gas path parts at the
firing starts: 0 800 1,200 2,400 site as recommended
by the maintenance
Turn around day 3 14 5 3 36
policy. The breakthrough
Table 2 OEM recommended maintenance plan came directly form the
aeroderivative approach of swapping the
The frequency of scheduled maintenance entire engine with a fully refurbished engine.
indicated in Table 2, expressed in terms of
INITIAL
fired hours accumulated by a machine, is to COOLING
DOWN OF THE
be considered as a standard calculated based MHE WARM CONDITIONS
MHE TO REACH
-68
LNG LNG
on the following operating conditions:
DE-BLINDING

OFF ON
BLINDING

COLD
WORKS NO WORKS
Natural gas fuel ONLY HOT WORKS / OPEN FLAME ACTIVITIES

Continuous operation APRIL 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21


COOLING STARTUP
Base load (100%) DOWN
CHEMICAL
GE SCOPE:
ENGINES EXCHANGE AUX INSPECTION START PUNCH
No water/steam injection CLEANING LISTING OF
RE-INSTALLED
PROCESS SYSTEM INSPECTION
Best maintenance practice EQUIPMENT

A day of site activities Table 4 LNG plant shut down plan


equals 12 working hours
As a result of the introduction of the engine
Optimization of Site Activities swap concept, the duration of site activities
GEs first efforts to reduce the duration of site decreased to 13 days (26 shifts). The major
activities during an outage focused on the overhaul turn around was cut from an average
major overhaul (MO). The target set by one of 634 hours and Best record 560 hours, to
the leaders in the LNG industry for execution average 428 hours and best record 332 hours.

Implementing the lessons


Year 2 Year 4 Year 6 Year 8 learned and fine tuning the
16,000 32,000 48,000 64,000 procedures, a major over-
Standard
CI HG CI MI haul using modular exchange
Maintenance
5days 14 days 5days 24 days
Extendor could potentially be further
improved by an additional
Modular CI HG CI MR
3 days. The areas to explore
Replacement 5days 14 days 5days 12 days
are: team relationship and
Table 3 Duration of planned maintenance site activities communications, and the

3
GE Oil & Gas

selection of the team members based on PROS CONS


skills and experience.
Planning
Skillfull problem
Lessons learned VISA problems
Flexible
tools and certifications not in place
Relationships and communication channels
are key to the success of the effort. Table 4 Team players Manpower not enough skilled (lack

reports the highlights of specific experience of experience)
Optimized
Slow pace of mechanical workers
from this case study.
Bad English speakers
PROS CONS Communications problems
Daily progress meetings Permit to work system
Continuous intern too complex Table 6 Contractors selection lessons learned
between parties Delays & confusion

Customer very sensitive Arbitrary interpretation Finally some low-impact engineering


to EHS matters of safety rules modification proposed by the outage field
Accident-free campaign Unnecessary suspension team and maintenance engineering can
Toolboxes of work
further facilitate the modular replacement
Stop cards Recertification of
tools and devices operation speed.

Instead of delivering rigid pipes for lube oil


Table 5 Relationships and communication
lessons learned adduction and cooling air line, enhanced
alignment devices, and pre-packaged new
Additional outage experience provides the turbine modules, these kits will be pre-
following lessons learned: packaged with flex pipes to reduce outage
time by one day or more.
Improve preliminary agreements with
customer (outage excellence) The engineered solution addresses the
following areas:
Clarify operating and safety procedures to
avoid delays due to misunderstandings or Cooling & sealing air piping
arbitrary interpretation of rules - Air manifolds pre-installed on new engines
- Use of flexible piping
Improve the issuing of work permits
Exhaust plenum
Single interface between GE and the
- Use insulation mats
customer
Alignment
It is estimated that by applying the lessons
- Jacking bolts to facilitate positioning
learned, the team could save an additional
on the 2 axes
two shifts in the next modular replacement.
- Guiding frame for reduction of turbine
People are the other key to success. The misalignment
lesson learned is to carefully select the
Lube oil piping
personnel and all contractors specifically for
- Use of flexible pipes for lube oil line inlet
the shutdown, ensuring that each individual
possesses all of the necessary skills for the New engine preparation
execution of his role in the project. - Tailored spare parts list for engine
exchange procedure
The estimated savings by precise staffing based
on the specific project is about three shifts. Lighting system
- Redesign of lighting system in turbine
compartment

4
GE Oil & Gas

Figure 2 From left to right: bearing #1 flexible lube oil piping, bearing #4 flexible lube oil piping, extended pin for
engine positioning

These improvements optimize the hardware the maintenance intervals recommended by


for modular replacement and allow the team the OEM.
to save one shift.
Departing from standard maintenance
In total, based on the FR5/2 modular intervals can have a very positive impact
replacement experience, a reduction of 10 on plant production but, at the same time,
days is potentially achievable. To further might compromise machinery reliability.
reduce the turn around time, another Careful and rigorous management of reduced
breakthrough in the maintenance approach maintenance activities can help in extending
would be required, but associated with the maintenance intervals while at the same
dramatic change in the GT package design. time avoiding the deterioration of reliability.
Days Standard major overhaul
26 Days

Engine swap
5 initiation
early mature breakthrough
18 phase
(planning)
phase phase needed

10
Jet
13 12 13 15

5 20
2006 2006 2007 2007 2008
Events
Experience
Figure 3 Left: GE Oil & Gas modular replacement experience. Right: Modular replacement learning curve

Required information for this assessment


Enhancing availability of hot gas path
includes:
parts by departure records
Technical risk analysis of the critical turbo Full remote monitoring (torquemeter
compressor components allows the OEM and fuel flow rate measurements are
to assess by how much the maintenance normally required)
intervals can be extended. The aim is to
Presence of site engineer
manage the technical risk when extending

5
GE Oil & Gas

Supervision of inspection activities maintenance shut downs, RAM Engineers


participate in the site inspection to collect
Tracking of repair activities all the information needed for defect maps,
Laboratory analyses including destructive accumulated damage assessment, etc.
testing of removed parts (depending on the 6. Lab test plan
type and severity of damage)
As a part of the interval extension program,
Unit history and spare parts tracking a residual life assessment of the critical
Phases of the assessment parts is performed to provide quantitative
The various phases of the project are information on how much additional
described below: operation the parts might sustain without
maintenance.
1. Analysis of operating conditions
Such an analysis, together with the site
A detailed analysis of the actual operating inspection findings and the operating para-
conditions is needed in order to identify meters record from RM&D, are used to validate
factors impacting the aging of turbine the programs assumptions and manage the
components, such as fuel type and quality, risk of stretching the intervals.
over/under-firing, etc.
As an additional step, the need for the injection
2. Analysis of unit configuration of new technology into the parts design may
be raised, leading to the initiation of research
A detailed analysis of the actual machinery
and development programs dedicated to the
configuration is performed in order to
successful achievement of interval extension
identify the part numbers of the installed
targets.
components
GE Oil & Gas has substantial experience in
3. Analysis of the fleet maintenance history
the use of departure records for maintenance
When working on defining the potential planning and diagnostic purposes. One of the
failure modes of a specific unit, GE Oil & Gas most significant availability improvement
takes advantage of the extensive feedback successes was with a series of 10 turbo-
from sites which is continuously collected compressor trains driven by FR5/2C and
and which includes various applications D model gas turbines. The analysis of operating
and all possible ambient conditions. A fleet data combined with the information obtained
analysis is always conducted to identify through laboratory analysis of the metallurgy
the failure modes. of similar components and the findings from
parts removed in previous inspections provided
4. Analysis of unit maintenance history the necessary information for assessing the
risk of extending the combustion inspection
The above-mentioned fleet experience
interval The risk of failure due to skipping the
shows that in specific installations some
combustion inspection of these particular
failure modes may predominate. For this
turbocompressors while maintaining the
reason, the fleet experience is compared
operating conditions the same was determined
with the specific history of the unit over
to be negligible, and the owner accepted the
time, in terms of events, part damage,
OEM recommendation to move the combustion
inspections, findings, etc.
inspection from the original 12,000 hours to
5. Run-test plan 24,000. As a result of the use of the departure
record, the availability expected over the full
On the basis of the above analyses, a life of the turbocompressor trains improved
gradual increase in planned maintenance by 0.6 points.
intervals is usually defined. During planned

6
GE Oil & Gas

Data from RM&D Info from laboratory Info from inspections


Firing temp. Destructive analyses Statistical analyses
Trip trends Residual life assessment Defect maps
Pulsations

MTBM extension
Figure 4 Departure record enablers

Figure 5 The Power Crystal kit

Enhancing availability by injecting the In those plants where plant down time is
latest design technology critical, plug and play is a winning solution.
GE Oil & Gas over the years has consistently A heavy-duty machine plus centrifugal
invested in new technology and new compressor, customized to meet the required
materials to improve the mean time between plant pressure and service configuration is
maintenance of its products. The focus of the most common type of train for oil and gas
the research and development team has applications. In these designs, maintenance
also extended to the installed fleet, seeking activities are scheduled to match the plant
solutions that can be easily retrofitted into production cycle and the life cycle of the
a machine that has been running for years, critical components of the machinery that is
without increasing the plant complexity and driven by the hot gas path of the gas turbine
the management of the turbotrain. and the compressor wear parts.

7
GE Oil & Gas

GE Oil & Gas R&D efforts strive to create The first stage nozzle and shroud complete
products and solutions that closely match the the path of the turbine components that have
MTBM targets demanded by applications, the been analyzed to rejuvenate the product, and
market and customer expectations. The Power light modifications have been included.
Crystal kit, for the GE frame 5 two shaft
machine is one of the outcomes of this effort. A new material has been applied to the shroud
and a new cooling system design is now embed-
The Power Crystal kit builds on the long history ded into the final machined first stage nozzle.
of successful Frame 5 upgrades since the
introduction of the first A model in 1970. Combustion hardware is a critical area for the
The features of the kit allow the maintenance operating life of a gas turbine that requires
schedule to be extended with no impact on the periodic inspection. The duty cycle and type
reliability and availability of the gas turbine. of fuel used are the key factors in determining
the recommended combustion intervals since
The Power Crystal kit is composed of the these factors directly influence the amount
turbine first stage buckets made of single of thermal barrier coating erosion, material
crystal material that have given the name to creep, thermal stress and wear of the
the kit, and of other hot gas path components combustion components.
such as combustion hardware, shrouds and
first stage nozzles that complete the supply. The Power Crystal kit includes extendorized
combustion parts that can increase inspection
Power Crystal technology intervals by significantly reducing combustion
The latest advance in hot part technology component wear. Wear is the most critical
has seen the introduction of single crystal failure mode of combustion hardware in HD
buckets, which offer the potential of further gas turbines.
improving the strength of high temperature
materials through the control of crystal The new extendor kit consists of the latest
orientation. With a single crystal material, all hard coating material and the redesign of
grain boundaries are eliminated from the parts to reduce wear on various combustion
structure and a single crystal with controlled system components.
orientation is produced in an airfoil shape.
By eliminating all grain boundaries and with
associated strengthening additives, a subst-
antial increase in the melting point of the alloy
can be achieved, thus providing a corresponding CL OF CROSSFIRE TUBE

increase in high temperature strength. The


creep and fatigue strength are also increased,
compared to equi-ax or directionally solidified
structures. This technology has been applied
in GE, especially in aero engine applications,
for more than 15 years. Almost all aviation Figure 6 FR5/2 liner showing redesigned areas to
engines produced after 1990, including the improve wears resistance
famous CFM, CF6 and the latest GE90, rely on
The redesign was implemented to reduce
the outstanding properties of single crystal
the relative movement between combustion
alloys. GE also has extensive experience in the
components and to reduce the forces and
use of single crystal material in aeroderivative
vibrations at wear interfaces.
gas turbines such as the LM2500+, LM2500+G4,
LM6000PD and LMS100 along with all FB
and H class industrial turbines.

8
GE Oil & Gas

extensive operating and laboratory data


available, and represent incremental evolution
of the products in accordance with the
conservative philosophy of the oil and gas
industry. Recently available communication
technologies have dramatically increased the
capability of technical groups to share data
which has been very useful in pushing the
availability boundaries with controlled risk.

Figure 7 FR5/2 transition piece showing redesigned


Considering that the majority of site
areas to improve wear resistance technicians are focused on daily operations,
the remote support services and highly
By incorporating proven wear-resistant specialized diagnostic capabilities provided
materials developed by the GE Global by gas turbine and centrifugal compressor
Research Center, the new design provides manufacturers have strengthened the
critical clearance control at the various wear relationship between industrial plants and
interfaces such as the liner stops, fuel nozzle original equipment manufacturer technical
tip to combustion liner, fuel nozzle collar, teams. The main components of a distributed
crossfire tube to combustion liner tube collar, diagnostic system are site data acquisition
combustion liner hula seal to transition piece systems and sensors, connectivity devices,
forward sleeve, transition piece forward and finally, remote data centers staffed with
supports and bracket, and transition piece experts. The principle services delivered
aft picture frame seal. by remote diagnostic centers are anomaly
management and engineering analysis of
As a consequence of the redesign of the
performance. Recent studies have shown that
wear contact points, some of the gas turbine
the availability of monitored units increases
combustion inspections can be skipped,
compared to unmonitored units. The benefits
increasing the availability of the whole machine
of improved communication between the site
by about 0.6 points over the life cycle.
and remote support teams include solving
With these proven advanced materials derived technical issues proactively and quickly, and
from jet engine technology and from our also, better coordination of site activities.
research centers, the life of the critical turbine Starting from the data available at the site, the
components and hence the MTBM can be value of the information increases with the data
extended to 24,000 hours for the combustion analysis and abstraction that is achieved
parts and 72,000 for the other components. through the use of specialized tools and
expertise available from the equipment manu-
This kit delivers to customers increased facturer. Figure 8 illustrates the different levels
availability and production with a moderate of data abstraction starting from site data.
investment and a simple plug
Engineering content

and play installation that is, in


terms of time and complexity,
the equivalent of a normal hot Post processed data
gas path inspection.
Abstraction

Data analysis
Normalized data
All the recent technology
developments have been Site raw data
conducted in partnership with
Customers, fully exploiting the Figure 8 Data layers

9
GE Oil & Gas

Examples of raw data are the parameters and diagnostic tools. Applying this approach
acquired by the unit control system to control systematically to data acquired remotely,
and protect the machine during site operations; the analysis of the diagnostic engineer can
normalized data are typically ratios between be concentrated at higher levels to increase
raw data to decrease the level of variation of the the effectiveness of service and to support
phenomena and enable easier data manage- maintenance technicians in making decisions
ment both at the unit and fleet level. Post- during scheduled maintenance activities or in
processed data represent the maximum level case of emergencies.
of abstraction and are normally derived
parameters or performance parameters Remote monitoring and diagnostic tools
including polytropic and isentropic efficiencies, represent a means of increasing the value of
power at reference conditions and non- information from raw data; using site data
dimensional coefficients or internal design flows. acquired and processed by an RM&D system
and taking into account the added accuracy [2]
As an example of a set of data, we can that this process provides, a set of systematic
start from an axial compressor discharge analysis can be started and used to help in
temperature, then normalize it to the inlet the troubleshooting of rotating equipment
temperature, and calculate the expected under real operating conditions.
values at the same thermodynamic conditions.
Comparing data at the same inlet guide The following diagram represents the link
vane angle and plotting the data against the between site data sources and intermediate
compression ratio, the following results can tools used to define the symptoms of
be obtained: performance losses.
Statistic feedback

Set of Machine system


symptoms or component

Weighted
RCA

Figure 10 Definition of symptoms

Once the symptoms have been defined, a


sophisticated system is used to define the link
Axial Compressor is. eff. vs. corrected speed between the symptoms and root cause analysis.
0.91

0.89
Recent development efforts have been
dedicated to developing the root cause
PRT-GT:E2D3 [-]

0.87

0.85
analysis (RCA) process.
0.83
On the anomalies management side, diagnostic
0.81
engineers are assisted by a prognostic engine
0.79
designed to manage anomalies by exceptions,
0.77
based on diagnostic rules. By analyzing site
0.75
4600 4700 4800 4900 5000 5100 5200 5300 5400 data and using the historical unit behavior or
NHP_CORR [RPM] signatures, a set of prognostic rules is used to
Figure 9 Data analysis (actual data vs. baselines) trigger anomaly notifications. The prognostic
engine for anomaly evaluation and an expert
In general, data are available as raw measure-
system to expedite the RCA are important
ments and the following levels of abstraction
tools in used by the RM&D team .
are normally reached through the use of design

10
GE Oil & Gas

feedback the condition as an anomaly. As soon as


advised, the customer bypassed the faulty
Site data sensor to avoid a trip and maintained the unit
in production avoiding an availability loss of
Current
performance about 5 hours. Figure 6 shows the trend and
main events relevant to this anomaly.
Expected
Performance Symptoms (increased
information)

Figure 11 Root cause analysis

As a first example of anomaly detection,


a deviation from a system signature is
considered. When running at normal conditions,
a centrifugal compressor driven by an FR5/2D
gas turbine presented the following ratio
between the inlet and discharge temperatures
vs. the compression ratio. After some period
Figure 13 Trend captured around the event; DIAG is the
of operation, the rule processor identified a
diagnostic threshold used to trigger notification
step change and highlighted it with colors in
the pictorial representation shown in Figure 13. All the above processes and analyses are used
The colors are associated with the timing of to help maintain high availability by enabling
the event in hours, the reddish ones are closer a continuous link between the site equipment
to the event. A step change in the efficiency is and diagnostic engineers, providing a continuous
strongly linked with the step highlighting wear process to improve machine performance in a
of an internal component. controlled risk environment both for customers
1.095 0
and external service providers. Significant MTBF
1.09 -5 improvements derive from this approach and
1.085
-10 availability is significantly enhanced by the
1.08 short anomaly resolution time.
TT OUT/TT IN

-15
1.075

1.07
-20
Conclusions
1.065
-25
We saw how the availability of a FR5/2 turbo-
1.06
-30 compressor can be dramatically improved.
1.055 -35
The modular replacement maintenance
1.05
approach can result in savings of nearly 50%
-40
1.22 1.24 1.26 1.28 1.3 1.32
PT OUT/PT IN
1.34 1.36 1.38 1.4
of the major overhaul down time. This means
an average of an additional 2 days of up time
Figure 12 Compressor anomaly identified by variation
of historical baseline
per year over the life of the gas turbine.

After notification, the compressor was opened We also saw that the introduction of the Power
to replace the component, and efficiency was Crystal kit allows the combustion inspection
recovered thereby avoiding loss of production to be pushed from 12,000 to 24,000 hours and
at the same available power. the Major Overhaul from 48,000 to 72,000
hours, with an expected availability improve-
In another case, a temperature sensor started ment of 2 days per year over the entire gas
to deviate from its normal behavior. The change turbine life.
was detected by the prognostic engine below
the trip limit of the machine and identified

11
GE Oil & Gas

Finally, exploiting the departure record can For more information


improve the availability by extending the Via Felice Matteucci, 2
MTBM of components through analysis of 50127 Florence, Italy
the information that operating data provides T +39 055 423 211
F +39 055 423 2800
in combination with the OEM know-how. The customer.service.center@ge.com
data and analysis available through RM&D Nuovo Pignone S.p.A.
can result in as much as 1 point of additional
availability ge.com/oilandgas
The information contained herein is general in nature and is
As an overall result of the initiatives discussed, not intended for specific construction, installation or application
purposes. GE reserves the right to make changes in specifications
the up time of an FR5/2 can theoretically be or add improvements at any time without notice or obligation.
improved by 4-7 days considering the combin-
ation of modular replacement to shorten site 2009 General Electric Company
All Rights Reserved
activities, maximizing the exploitation of the
operating data for proactive identification of
incipient faults and faster diagnosis of failures,
as well as by modifying the hardware with
the application of Power Crystal or through
the use of departure record initiatives. The
specific FR5/2 case initiatives discussed in
this article can be easily extended to other
gas turbine models.

References
[1] IEEE Transactions of Industry Application vol 31, no. 4
July/ August 1995

[2] K.Brun, R.Kurz; Measurement Uncertainties


Encountered During Gas Turbine Driven Compressor
Field Testing

Anda mungkin juga menyukai