Ref :
SAFE WORK METHOD STATEMENT
Rev. No. :
Issue Date :
Contractor:
Work Location:
Duration: From
Prepared by:
Reviewed by:
Name & Designation
Name & Designation
Signature/Date
Signature/Date
Document Status
Revision No Date Description Reviewed by Approved by
Doc. Ref :
SAFE WORK METHOD STATEMENT
Rev. No. :
Issue Date :
2. Identifies the hazards associated with each step of the work activity.
3. Assesses the risks associated with each step of the work activity.
4. Defines the controls to manage risks associated with each step of the work activity based on the
hierarchy of controls Eliminate, Substitute, Isolate, Engineer, Administrate and PPE.
5. Provides a description of the plant / equipment that will be used in carrying out the work activity
(including equipment maintenance and inspection requirements, certification by qualified person
and / or registration, etc.).
6. Describes the qualifications and training of personnel carrying out the work activity, including
supervisors experience / competency, licenses, operators certification, etc.
7. Refers to and confirms compliance with relevant EH&S Legislation, Standards, Codes, Regulations
and / or guidelines.
9. Includes design requirements, engineered details or certification for both temporary and permanent
structures, platforms or access ways/ladders.
10. Where PPE is nominated, the type of PPE is specifically listed and when it is required.
11. Defines who is responsible to ensure that the work activity is monitored and carried out in
accordance with the SWMS.
12. Defines the process and frequency of reviews and methods for ensuring the work complies with the
SWMS controls.
14. Identifies where any Subcontractors will be used, who is responsible to monitor and supervise the
works, and how hazards arising from interaction between trades will be communicated and
managed (e.g. induction into more than 1 SWMS).
15. For complex or high risk work activities (where appropriate), uses photos / diagrams / sketches /
summary to enhance the SWMS.
16. Includes the name and signature of the person who developed the SWMS, a current date and
revision number.
17. The SWMS includes specific EH&S controls for key high risk hazards as listed below:
(Tick all boxes relevant to the tasks outlined in the SWMS and ensure they are specifically addressed)
Work at height, work near / with penetrations Objects falling from height Electrical work
Use of plant and equipment Work in a confined space Overhead electrical services
Hot work Excavation Demolition
Manual handling Specialised work tasks e.g. tunnels, railways Underground services
Hazardous material removal and disposal e.g. Use of hazardous substances or dangerous Traffic and pedestrian segregation - work site
asbestos goods and public areas
Works requiring the implementation of an
Where an exclusion zone is required, the SWMS must clearly state the detail of the required
exclusion zone
exclusion zone, including the person responsible for implementation and supervision.
Doc. Ref :
SAFE WORK METHOD STATEMENT
Rev. No. :
Issue Date :
B SCOPE OF WORK
Mobilisation of blocks at site.
Storage to be designated.
Designated are is barricaded and signage placed.
5 - Improbable: very unlikely to happen; may assume exposure will not happen. C C D D
Risk Index Description Definition
A Intolerable Operation not permissible - risk shall be reduced by all possible means.
B Undesirable Further risk reduction required - high priority remedial action to be taken immediately.
C Tolerable Risk shall be accepted subject to demonstration that the level of risk is as low as reasonably practicable - remedial action to be taken at appropriate time to reduce risk level.
D Acceptable Risk acceptable - discretionary remedial action to be taken.
Plant/Equipment Used: Materials Used
Mobile crane Wire rope Sling Hazardous Substances:
Transporter Rope as tag line NA
MSDS available:
Yes No
Applicable Relevant EH&S Legislation Approved Codes of Practice (COP) Applicable to the Works
Likely-hood
Risk Level
Likely-hood
No Job Steps / Ill Health & Designation /
Risk Level
Existing Risk Control / Additional Risk Control
Severity
Severity
Hazards
Persons at Risk Preventive Measures / Preventive Measures Follow-up Date
1. Mobilisation / storage Overloading of Breakdown during Ensure that transporter 4 4 D Planning between Site 4 5 D Site engineer
area to be trailer mobilisation have inspected trailer team and surveyor. Site supervisor
established. before proceeding Sub-contractor
from yard. Only load to Mechanic to be 4 4 D
capacity. standby/ on call.
2. Storage area miscommunicati Work carried out at All have been briefed 4 4 D Site engineer
identified 4 points on the location of of the storage area; Site supervisor
for MLT. storage by other other trade are made Sub-contractor
trade. know of the location.
3. Transporter will be Loaded trailer Sunk into ground Ground condition is 4 3 C Compactor is used to 4 4 D Site Supervisor
guided into the site inspected and checked compact ground. Sub-contractor
immediately as they to confirm ground supervisor
arrive to avoid condition is good to be Site safety
congestion outside to travelled on. personal
public.
Traffic controller will
guide the transporter
to the designated area.
4. All blocks will be miscommunication Work carried out at the Exclusion zone will be 4 5 D Lay out of work will be 4 5 D Site Supervisor
placed at the area location of storage by established at the displayed on notice Sub-contractor
designated. other trade. designated area with board. supervisor
signage.
SWMS 009 Kent ledge mobilisation and storage PG5
Designated are will Warning signage will Site safety
be placed near to be placed. Netting personal
testing area as easy barricade will be
to carry out MLT test. installed at area.
Blocks are 2 Ton to
2.5 Ton.
Location attach.
5. Mobile crane Legal Illegal crane used PMA to be obtained 4 5 D All documents to be 4 5 D Site Supervisor
requirement kept as record at site obtain before crane is Sub-contractor
and placed on the mobilised at site. supervisor
crane where it can be Site safety
seen visually. . personal
To ensure no hydraulic
leaks or black oil
leakage is spilled on to
ground.
A spill tray to be
stationed in the event
a leak is observed
Mobile crane Condition Overload devise / To ensure the 2 3 B Testing of load must 4 4 D Crane operator
Mechanical Load arrest overload alarm is in be done during first Safety
malfunction working condition. inspection of the supervisor
causing loads to crane.
fall.
Riggers to be trained
and competent/
experienced.
6. Once item no5. Is Ground Toppling of crane Ground condition to be 2 3 B Compactor will be 4 4 D Site Supervisor
completed and condition checked and mobilised to compact Sub-contractor
established crane Unstable soil confirmed stable for the area once more supervisor
will be mobilise at condition positioning of crane before crane is Site safety
designated area. mobilised. personal
Crane out riggers to be
25T Mobile crane will fully extended. Ground condition must
be Used to lift and be checked every time
unload blocks on Steel plate to be after bad weather.
designated area. placed as a platform
stabiliser.
7. Transporter and Communication Positioning of Site supervisor to brief 4 3 C Pre Planning of Task 4 5 D Site Supervisor
mobile crane are crane is not proper. the operators and Sub-contractor
position to unload workers of the work supervisor
materials to method. Site safety
designated area. personal
Ground Unstable causing Ground condition to be 3 3 C Compactor to be used 4 4 D Site Supervisor
crane to topple checked, path taken to compact ground Sub-contractor
Transporter stuck by the transporter to before trailer moves in supervisor
cant move in. be checked. To avoid to designate area. Site safety
any unstable ground personal
8. Workers riggers to Miscommunicati Work method not Experienced rigger to 2 3 B Task to be briefed, 4 4 D Site Supervisor
be positioned. on followed. perform work. lead man identified to Sub-contractor
Not sure of task lead the crew. supervisor
Access platform will be Training for riggers will Lead man
used as means to be conducted. Site safety
access to secure the personal
blocks with wire sling.
9. Workers accessing Work at height/ Injury due to fall Access will be 2 3 B The side barriers will 3 4 D Site Supervisor
the top of trailer to Fall from height provided for workers to not be opened or Sub-contractor
secure sling for access the body of the taken off from the supervisor
unloading of blocks transport. trailer as it will be used Site safety
from the trailer as a edge protection personal
for the riggers.
10. Lifting equipment Damage Sling tear/ snapped All lifting equipments 2 3 B SWL shall be more 4 4 D Site Supervisor
wire rope to be used equipment inspected and good than 2.5 ton per sling. Sub-contractor
to unload the blocks. working condition. supervisor
Hooks shall be closed Site safety
SWL of the load to be hook. personal
observed.
Crane hook fitted with
safety latch
16. Housekeeping works All machineries to be Where practicable all Site Supervisor
maintained and machineries to be Sub-contractor
inspected daily to cleaned up and kept supervisor
ensure smooth well. Site safety
operations. Proper personal
records to be Mobile crane boom to
maintained. be boomed down and
parked.
Any leak to be fixed
and repaired
immediately.
Spill tray to be
stationed placed
during any works with
leak of hydraulics or
black oils.
18. communication Miscommunicati Wrong instruction This SWMS will be Site Engineer
on communicated to all
including GWSB site
SWMS 009 Kent ledge mobilisation and storage PG12
team, Sub Contractors Sub-contractor
and involving the supervisor
security.
THE BELOW ITEM WILL BE FILLED UP DURING THE TOOL BOX BRIEFING THAT WILL BE CONDUCTED BEFORE THE TASK
IS PERFORMED.
Section 4: Instruction & Communication
This Job Safety Analysis and associated Safe Work Method have been developed through consultation with the following crew members and have been instructed through induction, read and understood, and signed by all employees
undertaking the works.
Qualifications / Experience & Training to
Name Designation Duties & Responsibilities Signature Date
Complete the Tasks
Section 5: Verification
I have provided, to the best of my knowledge, as such accurate and sufficient information and instructions pertaining to this Job Safety Analysis / Risk Assessment - the hazards associated with each work process / activity and type of potential incident
or accident, the risk controls / reasonably practicable measures to be taken in the course of work and during an emergency - to ensure its / their safe undertaking.
Instructed by (print name): .................................................................. Signed: .............................................................. Date: .../..../... Time: .............. am / pm
PIC (print name): .......................................................... Signed: .............................................................. Date: ......./..../.... Time: .............. am / pm
The works associated with this SWMS has been completed and the work area made safe and fit for subsequent use.
Subcontractor (print name): ................................................................. Signed: ...................................................................... Date: ......./..../.... Time: .............. am / pm
PIC (print name): ........................................................... Signed: ...................................................................... Date: ......./..../.... Time: .............. am / pm