Chapter 3
Foreword
South Africa and the region require an effective and efficient This framework provides the building blocks for the
rail system to support economic development. The LTPF 2013 modernisation of rail in South Africa and all stakeholders
is a visionary and credible 30-year development planning are urged to support and use it to guide the Company in the
framework indicating how the rail network, terminals and yearsahead.
rolling stock should evolve and what interventions and
investments will be required. It demonstrates how rail can
grow market share and fulfil its rightful role in the regional Mr Siyabonga Gama
transport arena and where future capacity developments
Chief Executive: Transnet Freight Rail
should be focussed.
1 Introduction
The rail section of the Long-term Planning Framework (LTPF) provides the development plans for the rail network, terminals
and rolling stock. It is based on providing the required capacity to meet both the unconstrained demand and development of
astrategic network to enhance economic development within South Africa and its neighbouring states.
The following development areas are included in the Hubs and terminals
LTPF2013: Updated hubs and terminal views indicate the continued
growth in the container, automotive and palletised goods
Infrastructure
markets.
Infrastructure condition assessment allows for the effect
of increased maintenance on corridors where condition
isnot to the required standards;
There are four steps to increase volume throughput on a rail Axle loading across feeder system and main lines to be
network (not in order of priority): standardised; and
Reduce throughput time; The utilisation of diesel DP/ECP to overcome gradient
Run longer trains; challenges.
Run heavier trains; and
The utilisation of distributed power technology allows for the
Run more trains.
operation of longer trains, but has a major impact on the siding
Therefore, the supporting operating levers need to be and yard layouts. It is preferred if locomotives are positioned
explored during the early system design stage. For example, at the front or the back of the train.
to run more trains on the system, the operating levers Heavier axle loading on existing infrastructure can be
should include upgrading of both train control systems and achieved by merely replacing the loose components (ballast,
electrification systems, improving asset security systems sleepers and rail). The formation, however, needs to be
and enhancing trackside monitoring systems. suited for the bearing capacity of trains. It is often possible
This should be done in conjunction with the following to increase from 20t/axle to 26t/axle loading, but not from
supporting technologies: 20t/axle to higher than 26t/axle.
The illustration demonstrates the application of the principles Cognisance should be taken that the implementation of
of finding practical solutions for infrastructure ahead of quantum infrastructure development is associated with
demand. It considers the operational improvements prior massive investment and extensive disruption of operations.
to implementation of major and costly new infrastructure
It may be appropriate to jump straight to the top of the
solutions. The impact of the bottom-up capacity solution
pyramid, but in most cases an incremental approach offers
pyramid is that quick changes derived from operational
the best cost to benefit ratio.
discipline and redesign are in most cases affordable,
whereas quantum infrastructure is only required for a high
demandforecast.
During the recent Presidential Infrastructure Co-ordination SIP 3: South eastern node and corridor development.
Committee (PICC) plan for South Africa, it emerged that SOEs Ngqura transhipment hub, Integrated CDC development
are required to participate meaningfully and also lead some of and manganese export corridor development forms the
the identified Strategic Integrated Projects (SIPs). Transnet project supporting the SIP;
has identified projects that would support this initiative in the SIP 5: Saldanha Northern Cape Development Corridor.
following SIPs: Identified projects include the iron ore export capacity
SIP 1: Unlocking the northern mineral belt with Waterberg expansion and the oil and gas port capacity development to
as the catalyst. This will include the SA Coal transportation support the proposed IDZ;
system development, export coal line, Waterberg link SIP 10: Electricity transmission and distribution. Transnet
development, Swazi rail link, coal backbone capacity and future energy demand and energy supply plan;
Eskom road to rail migration plan; SIP11: Agri-logistics and rural infrastructure. Rail and port
SIP 2: Durban-Free State-Gauteng Logistics and Industrial capacity to support agri-logistics including branch lines
Corridor. Projects identified include the Port of Durban development; and
expansions, new dig-out port, Port of Durban rail terminals SIP 17: Regional integration for African co-operation
and yards development, Natcor rail capacity expansion, and development. Transnets Africa strategy for trans-
Gauteng hubs and terminals development, and the Gauteng continental economic transport corridors (see chapter 10,
freight ring; SADC Region).
Rail gauge is defined as the distance between the inner sides of Although the term standard gauge has become a popular
the two parallel rails. This distance then determines the wheel term to refer to the gauge used in parts of Europe and the
spacing on the rolling stock that can be safely operated on the USA, it is by no means the common gauge of choice in the
line and has a major impact on vehicle dynamics, permissible world. As can be seen from the map, there are many different
axle load and vehicle size. In South Africa there are basically gauges, ranging from 610mm to 1676mm, each with its own
three gauges, namely: characteristics andorigins.
Standard gauge at 1 435mm only the Gautrain passenger
network;
Cape gauge at 1 067mm the core network plus the majority
of the branch line network; and
Narrow gauge at 610mm some isolated lines on the branch
line network.
The South African rail system is gauge-wise well connected Ease of procurement it is sometimes easier and cheaper
to the Southern African region and any gauge change will to procure systems and rolling stock from providers with
certainly disconnect the network from its neighbours. On the an established gauge specification Gautrain is a good
other hand, selective consideration of wider gauge for high example; and
axle load (in the case of freight) or high speed (in the case of Installed legacy systems to change the gauge for a whole
passengers) applications should be considered where new network may be impractical and not economically viable.
lines and services are to be introduced, since the benefits
could be significant. From a freight perspective alone, the opportunities for
developments on a different gauge are considered to be
The selection of gauge needs to be considered against the
limited. However, consideration should be given to future high
backdrop of:
speed intercity passenger services, where a broader gauge
Regional and cross-border connectivity an important may be viable and also be used for freight services. Such plans
consideration for regional interoperability and economic are under development and may very well reveal the need for
development; major conversions or upgrades.
Application certain applications such as high speed
passenger services benefit from wider gauges;
Figure 9: Railway network development before 1910 Figure 10: Railway network development after 1910
South Africas railway system started with two pioneer In 1910, the Union of South Africa was established and with it
railways in Cape Town and Durban, connected to the ports. a decision to use railways to unify the countrys widespread
Between 1872 and 1877, these lines became Government towns and cities. The South African Railways and Harbours
property. The discovery of diamonds and later gold and coal in (SAR&H) administration was also established. By the 1930s,
Kimberley and the Transvaal Republic respectively, triggered anetwork of rail lines covered most of South Africa, and the
the building of the lines between Cape Town and Johannesburg big cities were serviced by metropolitan commuter rail.
via Kimberley as well as Durban and Johannesburg.
The SAR&H was restructured in the 1970s and network
At that stage, the narrower rail gauge of 1 067mm (now expansion now turned to capacity enhancement with many
referred to as Cape Gauge) was chosen for its advantages in projects aimed at realigning and upgrading lines to modern
construction costs and also its suitability to the mountainous standards. During this time, considerable portions of the lines
topography in the areas of South Africa in which it was to were electrified to the much more advanced 25kV AC standard,
be installed. As the map shows, the majority of what is now and new train control standards were also introduced.
termed the Core Network was developed by 1910, with links
Since the early 1980s, investment in infrastructure has been
between Gauteng and Cape Town, Durban, Port Elizabeth,
declining steadily and with it Transnet has seen a huge loss of
EastLondon and Maputo having been established.
market share. Since 2000, both Transnet and its Shareholder
(Government) realised that a major investment programme
would be required to get rail back on track, and in 2006 this
negative trend was reversed for the first time.
Figure 11: Electrification development map Figure 12: Electrification installed technology map
Electric traction exists in three forms in South Africa: 3kV DC, Traction on the rail network is either diesel (non-electrified),
25kV AC and 50kV AC. Electrification of the network in South 3kV DC, 25kV AC or 50kV AC. The 3kV DC is the older
Africa was initialised in 1925, when a portion of the section system with the substations at relatively shorter intervals.
between Ladysmith and Pietermaritzburg on the Natal Thenetwork comprises approximately 20 800 route
Mainline was upgraded to 3kV DC traction. Shortly thereafter kilometres of Cape gauge lines (1 067mm), of which 4900km
in the Cape, the inner city line was electrified from Monument (24%) are electrified at 3kV DC, 2300km (11%) at 25kV AC,
to Sea Point. and 861km (4%) at 50kV AC.
Over the following decade, these sections and areas of The latter is the Sishen to Saldanha Ore line, which is the
electrification were extended and the inner Johannesburg only route electrified by this system. In addition there are
network was electrified. The 1950s and 1960s saw major 15switchable route kilometres electrified at either 3kV DC or
3kVDC electrification of the core network corridors 25kV AC. These are changeover locations, where the voltage
connecting Johannesburg to Durban and Cape Town. This can be switched from one system to the other to permit
system is especially suitable for light traffic and urban through working by dual voltage locomotives, or a locomotive
applications, with short distances between stations. change without the need to use diesel traction to haul the
train through an intermediate non-electrified section.
Electrification of the Sishen-Saldanha line, as well as the
Richards Bay Corridor was completed in the late 1970s and
the majority of the remaining core network was upgraded
into the 1980s. During this stage of development, the more
advanced 25kV AC system was introduced. It is currently
the international standard for freight railways and can cover
much longer distances without significant line losses.
2.6 Standardisation
This section identifies the key issues and constraints based on
the current network installed technology configuration, which
must be standardised in the network development plans.
In the global context, the South African rail system is ranked Aton-kilometre, abbreviated aston-km, is a unit of measure
number 11 in terms of routekm. However, the route distance of rail freight transportation, which represents the transport
does not directly translate to the measure of freight volumes of one ton of goods over a distance of one kilometre.
railed in ton kilometre (ton-km). For example, the above
illustration shows that China transported the most traffic,
even though its rail network is less than a third of that of the
United States of America.
Figure 19: 2012 Flows map Figure 21: 2032 Flows map
The demand per section ranges from less than 1mtpa to more The Cape, Natcor and Lephalale corridors show significant
than 60mtpa for the export coal system to Richards Bay and growth due to increased containers, domestic coal to Tutuka
the export iron ore from Sishen to Saldanha. Large differences power station and Waterberg coal respectively. The volume
are evident and a substantial part of the total volumes are growth along the central port corridor from Hotazel to Ngqura
concentrated on only a few of the corridors. is largely due to high forecast of the export manganese and
container businesses.
As indicated earlier, network analysis requires matching Double lines: the capacity of a double track railway line is
capacity with demand. The diagram indicates how these determined by the headway between two trains and therefore
functions relate to each other and are used to determine is typically a function of signal spacing and running speeds.
network capacity utilisation.
Single lines: on single track lines, the capacity is governed by
Capacity: following the conversion of traffic demand to train the available opportunities to pass trains at crossing loops
requirements per day, the installed network capacity per line that are long enough to accommodate them. Running longer
segment is determined. This is the number of trains able to trains on single lines can actually reduce capacity, if sufficient
run along a defined section of infrastructure per direction crossing loops that are long enough, are not available.
per day and is generally referred to as theoretically available
Mixed traffic capacity calculation on single lines: where more
train slots. Line capacity calculations are based on several
than one train length are operated on single line sections,
infrastructure characteristics: passing opportunities,
capacity is calculated as a combination of short and long train
operating speeds, headways and train control systems.
capacity, each with its own limits. Some passing loops cannot
Thecalculation varies, depending on whether the section
accommodate long trains, so where there is a significant
is single or double line. This high level capacity utilisation
number of a commodities that run in long trains over a single
calculation is based on the assumption that only 65% of the
track section, the operational capacity of that section will be
theoretically available train slots can be used for normal
affected. The constraining distance between passing loops
train operations, as the remaining 35% will be used for track
for each train length is then used to calculate headway and
maintenance activities and business recovery purposes.
ultimately, a weighted average of the overall operational
capacity of that section.
Operational capacity is the capacity in the form of train To calculate the condition-based or practical capacity,
slots that are usable for trains to pass through the system; these lost slots need to be subtracted;
The operational capacity is then determined by subtracting By comparing the capacity needed (demand driven) with the
maintenance slots and operational allowances assuming practical capacity, it is possible to determine the minimum
that the infrastructure is in optimal condition; condition level that a line would need to be maintained at in
When calculating operational capacity, it may be tempting order not to impact on volumes. (Dont let the Z-slots drop
to allow for additional maintenance slots or operational below the X-slots below);
failures due to poor condition. This should be avoided; Once the Z-slots reaches the Y-slots level (ideal condition),
The only additional allowances should be due to external additional infrastructure interventions are needed;
or inherent design; issues, eg installed alignment, clay It is indeed more complex since assets have an age to
conditions or difficult operational regimes; condition relationship (life cycle) and refurbishments and
Where better information is not readily available, the replacements need to be considered as well; and
guideline is to assume that operational capacity is 65% of End of life replacements and refurbishments can increase
theoretical capacity. This assumption has been tried and the installed capacity if these are upgrades.
tested and is safe to use under most conditions;
The current condition may be below the threshold, where
it negatively impacts on the installed capacity due to
speed restrictions, increased failure rates and corrective
maintenance;
The core network is made up of 18 individual sections that can Export ore system
be rolled up to five systems: Heavy haul lines linking the Northern Cape with Saldanha
and Port Elizabeth/Ngqura;
Gauteng to Durban system
Predominantly export iron ore to Saldanha and domestic
Predominantly a general freight route with containers,
iron ore to steel plants as well as export manganese ore to
domestic coal, fuel and other general freight traffic; and
Port Elizabeth/Ngqura; and
Train size is light to medium.
Train size is predominantly heavy.
North eastern system
Gauteng to Cape Town system
General freight traffic with predominantly agricultural
Links between the Gauteng, Western Cape and Free State
products and fuel. Limpopo coal and other minerals are
provinces;
expected to increase tonnage on this system; and
Traffic is predominantly containers, domestic coal to
Train size is light to medium.
Saldanha and other general freight. Some container and
Coal system automotive traffic to Port Elizabeth also flow on part of the
route; and
Feeder lines from the Mpumalanga and Lephalale areas to
domestic destinations, Richards Bay and Maputo, including Trains are mostly light to medium.
the proposed Swaziland link;
Predominantly export and domestic coal, as well as
domestic iron ore to steel plants. Substantial component
of existing trains convey bulk traffic and the proposed
Swaziland link will be aligned to this; and
Train size is medium to heavy.
The coal system includes Lephalale to Pyramid, Pyramid The status quo of major sections is summarised below:
to Ogies, Ogies to Ermelo (coal backbone) and Ermelo to
(a) Lephalale to Pyramid
RichardsBay. Although the section from Komatipoort to
Richards Bay is not yet part of the coal system, it is included Status quo
here as it is expected to have an impact on the coal system The Lephalale to Pyramid link is a single tracked general
once the Swazi link is constructed. The network status quo freight line. The section from Lephalale to Thabazimbi is
includes the following attributes: non-electrified, while that from Thabazimbi to Pyramid
Network layout representation of the system on the isenergised at 25kV AC. Both sections are designed to
geographical map showing the rail network per province; carry axle tonnage of up to 20t/axle.
Failure rate the two bar scale represents a measure of General issues
delay, in minutes per million ton-km, due to track component
Slot capacity: constrained due to electrification and short
failures in the section compared to the network average.
passing loops; and
The right hand bar shows that delay due to section failures
Formation: accelerated sleeper replacement required,
is slightly above the network average;
extensive clay formation issue prevents increase to
Line properties describe the physical properties in terms
26t/axle design.
of line type, axle load, traction, train control, curvature and
gradients; and Section performance
Condition high level infrastructure components condition The section performance of the line is slightly below the
indicators for good (green), average (yellow) or poor (red). network average. The clay soil conditions prevalent on
this section inhibit its ability to effectively absorb future
traffic or increases in axle load.
Status quo
This section is a general freight line that connects Glencoe
on the Natcor line and Vryheid on the Coal line. It is a single
line with an axle load capacity of 20t/axle. It is electrified
at 3kV DC AC. It carries general freight and shorter coal
trains from Glencoe to Vryheid. The shorter coal trains are
compiled into 200-wagon coal trains at Vryheid and sent to
Richards Bay.
Section performance
The performance of this section is better than the network
average. Delay of trains caused by faults on the section
islower than the network average.
In the figure above, the bar graphs show the demand In the opposite direction, volumes are considerably lower
forecast for both directions of the section from Lephalale to andare made up of a variety of mining products and
RichardsBay. The top right table presents the actual volumes containertraffic.
in mtpa ofthe top 10 commodities reflected for the base year
(b) Welgedag to Ermelo
2012 andprojected for the seventh year 2019 and 2042 in the
dominant direction. Demand
The line volumes are dominated by export coal in the direction
The bottom part of the figure shows a line diagram of the
towards Richards Bay and domestic coal in the opposite
railway section, corresponding capacity utilisation chart and
direction to power stations. General freight and containers
segmented view of the commodities in both directions of the
show some growth, but this is constrained by the huge volumes
network by the year 2042.
of coal. Export coal ramps up from 60mtpa to 110mtpa on this
The aim is to illustrate the effect of growth in commodity section over the next 30 years.
volumes on the network in relation to the installed
(c) Ermelo to Richards Bay
infrastructure capacity. The colour coding is based on the
description provided above in section 3.2 Translating tonnage Demand
to capacity utilisation. A short summary description of the Like the northern section, volumes are dominated by export
demand and capacity requirements is given below: coal in the direction of Richards Bay. Export coal ramps up
(a) Lephalale to Pyramid from 69 to 110mtpa, where it is capped. The opposite direction
shows much lower projections than north of Ermelo, as it is not
Demand impacted by power stations demands. Containers and other
The section displays the ramp up in Waterberg coal exports, non-iron based mining show quick growth, although ultimate
which provides the majority of the tonnage over the section. tonnages are low.
Volumes of export coal reach 70mtpa, as they gradually
In the segmented view, export coal volumes increase along the
replace Mpumalanga coal. Domestic coal and iron ore are also
section, whilst still in mining areas, but there is little added
volume contributors and travel the length of the section.
thereafter. In the opposite direction, containers are added
tothe line at Vryheid, most likely coming from Natcor across
the Glencoe link.
The interventions shown in the figure above serve to alleviate The existing line is double tracked from the Welgedag region
congestion on the coal line. They include upgrades to sections through to Richards Bay, with the exception of the Overvaal
of the existing line as well as the construction of new tunnel, which is a significant bottleneck, Doubling of the tunnel
infrastructure to handle future demand. is planned from 2014 to 2017 to alleviate the bottleneck.
Additional crossing loops as well as extensions of existing Furthermore, a new line is planned from Lothair in Mpumalanga
loops to accommodate 100-wagon trains are proposed for to Swaziland. Construction of this link, which is planned to be
the northern section of the line, Lephalale to Pyramid. Anew completed by 2017, would enable rerouting of general freight
heavy haul line from Thabazimbi to Ermelo is planned to traffic through Swaziland to Richards Bay, thereby freeing up
be constructed by 2026 to carry domestic and export coal capacity on the coal line for coal traffic.
traffic. This would overcome the current load restriction due
The proposed interventions with their corresponding costs
to the poor load carrying capacity of the existing line resulting
and yearly cash flows are shown in the development plan
from its clayey formation.
section below.
Upgrade selected line sections to 26t/axle. Provide new link from Lothair to Sidvokodvo in Swaziland.
Also upgrade the section from Sidvokodvo to Phuzumoya;
Train control and
Provide signal infill scheme to reduce the train running Double the Overvaal tunnel and track.
times.
Alignments
Electrical
Provide grade separations at Sikame and Ilangakazi.
Maintain 3kV DC system until the long term 25kV AC plan
isimplemented on the adjacent network; and (d) Komatipoort to Richards Bay
Build third line at 25kV AC from Geluksplaas to Ermelo.
Axle loading
Capacity expansion options Doubling and upgrade to 26t/axle for 200 wagons trains.
Provide demand flexibility by adding a fourth line between
Train control
Ogies and Ermelo.
Provide signal infill scheme to reduce the running time over
Alignments the section.
Sufficient at the current 1:100 gradient.
Electrical
(c) Ermelo to Richards Bay Keep existing diesel system.
Commuters: plans to expand service on the Hammanskraal Line use: forecast increase based on aggressive magnetite
section segregated freight and passenger; and volume growth;
Shosholoza Meyl: increased traffic between Polokwane Slot capacity: slot utilisation for longer trains at limits
and Pretoria, plus service running to Musina and Zimbabwe. competing with maintenance demands;
Axle loading: Groenbult to Hoedspruit to be upgraded to
20t/axle; and
Commuters: plans to expand service to this section.
Segregation of lines is recommended.
Demand
Demand and capacity utilisation for the Greenview to The opposite direction shows a similar pattern and with
Komatipoort section is higher than for the Pyramid to similar total tonnages beginning with 7mtpa and reaching
Musina and Groenbult to Hoedspruit sections. Demand on up to 35mtpa. Containers, although not a major contributor
this corridor is constituted of a variety of commodities, to total tonnages, are targeted as a key commodity for
most of which only travel on certain sections of the whole market share growth.
corridor. Magnetite in particular show aggressive growth Capacity overview
in the first seven years of the forecast period, but this
Magnetite coming from Phalaborwa, as well as new coal
slows thereafter. Magnetite is a special commodity,
from Groenbult, highlight constraints on the Kaapmuiden
requiring a specific buyer, as it is relatively abundant and
to Komatipoort section around 2030; and
therefore does not have much margin for profit, especially
Another major constraint is the section from Waterval
when transported over long distances. These commodities
Boven to Waterval Onder, where trains of not more than
come from Phalaborwa and are destined for Richards
50wagons can be operated safely.
Bay, meaning that they only travel on the short section
of Kaapmuiden to Komatipoort. Export coal destined
for Matola (Maputo) makes up a considerable portion of
thetraffic.
(a) Musina to Pyramid The relatively low traffic volumes expected on this line in the
The figure below shows the locations of planned interventions next 30 years do not require large-scale capacity expansion.
and their impact on capacity utilisation on the Musina to However, two crossing loops near Pyramid would require
Pyramid line. lengthening within the 30-year planning horizon to enable
them to accommodate the crossing of 50-wagon trains.
The figure below shows the locations of planned interventions Four crossing loops are proposed to be lengthened. Isolated
and their impact on capacity utilisation on the Groenbult to short sections of the line are proposed to be doubled to
Kaapmuiden line. create long loops. If required in future, the southern section
of the line may be doubled by doubling the few remaining
The low demand forecast for the link does not warrant
single sections.
asignificant upgrade in its infrastructure capacity. However,
as some of the crossing loops on the line cannot accommodate
40-wagon trains, lengthening of these loops is necessary.
The figure below shows the locations of planned interventions It is proposed that capacity be increased by phased doubling
and their impact on capacity utilisation on the Greenview to of the line. The first phase of doubling is proposed to be
Komatipoort line. completed by 2016 and the last phase, within the current
planning horizon of 30 years, is expected to be completed by
In order to accommodate the expected demand on this corridor,
year 2031.
significant upgrades to existing infrastructure are necessary.
The short distances between existing crossing loops limit the
capacity that could be created through constructing additional
crossing loops.
The network development strategies for the North-eastern (b) Groenbult to Kaapmuiden
system are summarised as follows:
Axle loading
(a) Pyramid to Musina Upgrade Groenbult to Hoedspruit section to 20t/axle.
Alignments
Keep existing alignments.
The export ore system consists of Sishen to Saldanha, Hotazel Power distribution capacity is inadequate. Current service
to Kimberley, Kimberley to De Aar and De Aar to Port Elizabeth. is based on a mix of diesel and electric traction. Although
The status quo of the three major sections is characterised it is not fully utilising the quantity of power, which Eskom
asfollows: is contracted to supply, significant capacity improvement
isdependent on the ability of Eskom to supply more power.
(a) Sishen to Saldanha
Section performance
Status quo
The performance of the section is well above network
The Sishen to Saldanha railway line is an 861km long, heavy average; however, there are plans (resignalling project or
haul, single railway line, which connects iron ore mines near SIMIS-S) to achieve quicker turnaround of trains to meet
Sishen in the Northern Cape with the port at Saldanha Bay increased traffic demands.
in the Western Cape. The line is energised at 50kV AC,
carrying axle loads of up to 30t/axle. It has crossing loops
designed for 342-wagon trains; and
Overall condition of the line infrastructure is good taking
into consideration that it carries the heaviest axle tonnage
(30t/axle). It represents a high standard of infrastructure,
all infrastructure components are performing well.
General issues
Restrictions on line capacity at present are associated with:
The operations of Sishen and Salkor yards. Current
infrastructure and operating procedures do not permit
sufficiently quick turnaround of trains to meet the demands
of increased service levels; and
Status quo
Kimberley to De Aar is a general freight section that also
caters for passenger services. It consists of a single line
electrified at 25kV AC with an axle load capacity of 20t per
axle. Crossing loops are designed to allow for the passing
of 104-wagon manganese ore trains.
General issues
Line use: this is increasing due to increased manganese
ore demand through Port Elizabeth (current) and Ngqura
(future);
Shosholoza Meyl: 3 to 4 passenger trains are run per day.
This severely disrupts operations due to the different
running speeds of passenger and freight trains; and
Maintenance: restricted due to high utilisation.
To expand capacity on the Manganese export line, heavier and New crossing loops are also planned at suitable locations to
longer trains are proposed. Crossing loops are earmarked to reduce section lengths and thereby increase line capacity.
be lengthened to accommodate the proposed increased train These new loops are required from 2019 onwards.
length. Loop extensions are required from 2015 on an as-and-
To further expand capacity, the Beaconsfield to De Aar section
when required basis.
of the line will require doubling within the next 30years.
Additional 20 loops, expand the Salkor yard and make Long term: Hotazel to Kimberley 25kV AC.
alterations to access lines to third tippler.
The Gauteng to Cape Town system includes Cape Town to Section performance
DeAar, Kimberley to Houtheuwel and Noupoort to Vereeniging. The performance of the line is not acceptable as delays
The status quo of the major sections is summarised below: caused by failures on the section are above the network
average. Implementation of state-of-the-art traffic control
(a) Cape Town to De Aar
and safety systems can greatly improve operational
Status quo performance that degrade present service and inhibit the
Cape Town to De Aar is a general freight and long distance ability to effectively absorb future traffic. This would also
passenger single railway line, which connects Gauteng to enhance the ability of the section to carry mixed (passenger
the Western Cape. This section is electrified to 3kV DC from and freight) traffic.
Cape Town to Beaufort West and 25kV AC from Beaufort (b) Kimberley to Vereeniging
West to De Aar, carrying axle tonnages of up to 20t/axle.
Status quo
General issues
Kimberley to Vereeniging line is used for both heavy
Train control: some very old train control systems are still haul andpassenger services, it consists of both double
in use on the section between Worcester and Kraaifontein. and single line sections. The line is electrified to 3kV
These need to be replaced with CTC; DC and carries axle tonnages of up to 20 tons. Crossing
Substations and electrical supply: this is a constraining loops onthe singleline sections allow for the crossing of
factor on capacity. 25kV AC system has more capacity than 104wagon79trains.
the 3kV system that suffers from low voltage problems;
Shosholoza Meyl: shared infrastructure can lead to
operational challenges; and
Telecoms: signalling to be connected with optic fibre along
the whole route.
Figure 52: Gauteng to Cape Town system demand and current capacity
Demand Demand
Containers have a reasonably high growth forecast. This The lines demand is made up of traffic travelling between
section sees relatively similar flows in either direction, with the Western Cape, Northern Cape and Eastern Cape and the
large potential growth, particularly in containers. Rail volumes rest of the country. The tonnage flowing over this section,
in both directions and are mainly made up of containers, coal relative to the network, is very high, with a very high growth
and agricultural products. Whilst most commodities see steady rate expected. Dry bulk commodities make up the major
growth, container growth is forecast to be considerable. constituent of the tonnage and the section also accommodates
PRASA traffic.
The segmented demand views show a similar picture in both
directions. Over half of the 2042 tonnages are destined or Iron ore shows a very aggressive growth curve, which should
originating in, the greater Cape Town area, with the remainder be closely monitored. Some container growth in the long
of volumes destined for and originating from the port itself. term on the Cape corridor is driven by (a) Cape Town-Gauteng
volumes and (b) the development of Ngqura as a container
port. Export manganese ore to Richards Bay and Durban is
currently relatively high, but may not be sustainable. Demand
for Shosholoza Meyl trains is reducing capacity significantly.
The network development strategies for the Cape Town- In order to be consistent with long-term aims, all passing
Gauteng system are given below per section: loop upgrades or track additions should be built to 26 ton
axle load standards.
(a) Cape Town to De Aar
Train control
Axle load
Optimise existing system.
Maintain existing 20t/axle.
Electrical
Electrical
Long term: this section is a strong candidate for migrating
Cheaper to add more 3kV DC substations rather than
to 25kV AC, but this must be done in conjunction with the
convert to 25kV AC; and
sequencing interface with Natcor north and the proposed
Sharing 3kV DC network with commuter trains, therefore
25kV upgrade of the Hotazel to Kimberley section.
rather not upgrade electrification.
Capacity expansion
Train control
Interim capacity increases would be achieved by additional
Provide signal infill scheme to reduce the running time
passing loops and line doubling of some sections; and
when doubling the line.
All new loops or loop extensions to be based on 100-wagon
(b) Kimberley to Houtheuwel general freight and 75-wagon Anaconda container
trainlengths.
Axle loading
Short term: maintain the current 20t/axle and consider
26t/axle migration in the long term; and
Network average
10,0
9,0 Natcor infrastructure is heavily utilised but constrained by
8,0 poor alignment design. Poor formation and tunnel design
7,0 infringe capacity development opportunities
6,0
5,0 Gauteng freight ring capacity is constrained by single line
4,0 Perway sections. OHTE theft and obsolete train control technology
3,0 Telecoms impacts severely on train operations
2,0 Electrical
1,0
KZN North and South coast signalling equipment is obsolete
Signals
-
Line properties
Section Line type Axle load Traction Train control Sharpest curve Steepest gradient
1. Pyramid Houtheuwel Single/Double 20t 3kV DC CTC 305m 1:100
2. Rietvallei Glencoe Mostly Double 20t 3kV DC CTC 285m 1:66
3. Glencoe Booth Double 20t 3kV DC CTC 150m 1:50
4. Nsese Durban Single/Double 20t 3kV DC CTC/TWS 250m 1:66
5. Durban Port Shepstone Single 18.5t 3kV DC RTO 250m 1:66
General condition
The Rietvallei to Booth section is a general freight line, but Line use: single line section from Rooikop to Rietvallei and
carries substantial heavy haul tonnages of coal and iron ore the line configuration to Jupiter are causing bottlenecks.
to the Majuba power station and Newcastle AMSA plant. High cube containers cannot be accommodated safely due
The section is double track with 3kV DC electrification. to height restrictions;
Axle loads are currently supported up to 20t/axle, but Slot capacity: current capacity is sufficient, further
there are plans to upgrade one of the two tracks of the expansion will be expensive due to difficult topography;
line from Rietvallei to Glencoe into Heavy Haul or 26t/axle Train control: theft of signal cables result in major service
operations due to high demand of iron ore destined for disruptions. Migration from copper is a priority. Obsolete
Newcastle; and interlocking and track circuit components need to be
Overall condition of the existing network infrastructure replaced;
is not acceptable with formation, bridges and tunnels Formation: Rietvallei to Booth is problematic due to poor
requiring more attention. drainage in tunnels and weak formation;
Shosholoza Meyl trains: significant freight and passenger
train scheduling, planning and operations challenges; and
Commuter trains: high frequency of commuter trains on
the Cato Ridge to Booth section impacting on capacity
utilisation.
Glencoe
Booth
The hubs and terminals status quo map shows the positions The traffic in the ports on the east coast of South Africa has
of the intermodal terminals, general freight terminals and recently increased by up to 14% annually, and it is expected to
mineral nodes. The position of each terminal is linked to its increase more rapidly in the near future.
purpose:
Transnets long-term aim is to achieve 80% market share
The intermodal terminals consist of inland and port
of rail suitable transportation of containerised traffic,
container terminals serving the container business;
representing a significant modal shift over existing levels.
General freight terminals are small terminals used for Therefore, to accommodate the expected significant growth
repackaging of commodities; and of container demand in the short, medium and long term,
Mineral nodes represent the loading and offloading existing infrastructure, facilities, and operational planning
facilities either inland or at the port for the export of for the accommodation and movement of this traffic by
bulkminerals. rail requires improvement. To this end, existing container
Containerised freight traffic is increasing globally by up to 8% terminals have been identified for expansion and in the
per annum and in some developing countries, such as South longer term the development of new additional facilities have
Africa, the growth in port container handling is expected to beenidentified.
be even greater. The increased national economic growth
and global container trends have resulted in a steep increase
inthe demand for container handling capacity throughout
South African ports.
The mineral nodes are also expected to grow due to higher Of particular importance will be the development of mega
market demand for the bulk minerals especially in the or super-terminals in the Gauteng and Durban areas to cope
Asianmarkets. with the growth in container demand along this corridor.
Theindicated freight nodes are not necessarily informed by
The location of future intermodal terminals as well as their
the demand forecast, but are proposed by public sector in
typical sizes and nature are shown on this map. The existing
support of the economic development and promotion of the
first generation terminals are unlikely to disappear altogether,
Free Trade Zones.
but may continue to serve niche market requirements.
Inthis illustration, the philosophy of hub-to-hub long-haul
rail operations is supported by mega or super-terminals in
Gauteng with direct links with the port systems.
In early 2012, City Deep terminal capacity was expanded It is envisaged that Gauteng will require seven standard
to 280 000TEUs through infrastructure upgrades and the container terminals, one or two standard automotive
commissioning of additional cranes. Additional plans are terminals and four standard palletised terminals by 2042.
underway to further increase City Deep terminal capacity to The study also determined that it would be operationally
400 000TEUs by 2016. more efficient to develop a few super terminals rather than
many smaller terminals. At least three locations (Pyramid,
The container strategy study, commissioned by Transnet
Sentrarand and Tambo Springs) were identified for the
completed in April 2011, estimated that in order for rail to
development of these few super terminals.
achieve its desired market share, an additional 4 million
TEUs handling capacity will be required in the Gauteng area
by2042.
Gauteng terminals development strategy includes: terminal, one palletised terminal and one automotive
Expanding City Deep terminal to an estimated terminal. Initially a small container terminal is to be
400000TEUs to 2016; and constructed at Pyramid to replace the current Pretcon
Expanding Kascon terminal to an estimated 300 000TEUs terminal. Once the demand exists Pyramid can be upgraded
by 2019. to operate at full capacity (500 000TEUs per annum); and
Tambo Springs is envisaged to have two container terminals As the demand gradually increases and other terminal
and a palletised terminal. Each container terminal will have volumes are phased, the first container terminal (Phase 1)
a capacity of 500 000TEUs per annum (1 million TEUs/pa by will initially handle 250 000TEUs per annum from 2019 and
2027) and the palletised terminal handle 4 500 000 pallets ramped up to 500 000TEUs per annum in 2020. The second
per annum by 2025. terminal will handle 500 000TEUs by 2027.
Sentrarand intermodal terminal development will handle Sentrarand intermodal terminal will have a four phase
anestimated 2 million TEUs of container traffic per annum, container terminal development (Phase one-four by 2030,
with four container terminals each with a capacity of 2032, 2037 and 2040 respectively). The intermodal terminal
500000TEUs per annum. The development will also include will include two palletised terminals developed in two phases
two palletised terminals each with a capacity of 4 500 000 (Phase one and two by 2020 and 2038 respectively.)
pallets per annum.
At present the Port of Durban has two container terminals From a previous study it is envisaged that in order for rail to
and a buffer stack, which provide a combined capacity of meet its desired market share it is necessary for Durban to
450000TEUs. The existing yards and terminals are designed increase its intermodal terminal capacity to approximately
to handle only 50-wagon container trains, which is problematic 4,1 million TEUs by 2042. This means that approximately six to
with the current running of the daily 75-wagon Anaconda eight standard container terminals and one or two standard
trains. It has to be broken up and shunted into shorter rakes automotive terminals are required by 2042. These terminals
upon arrival and reassembled before departure. would be allocated to service both the Port of Durban and the
proposed dig-out port.
Durban is considered South Africas most significant port
in terms of container and automotive imports and exports.
Future port developments are being assessed in order to
increase South Africas economic competitiveness.
Durbans back of port rail development plans are as follows: Additional actions
2014 Reconfigure Bayhead yard into a yard that can Separate freight trains and commuter trains between
accommodate 100-wagon container trains. Upgrade the Wentworth and Clairwood, as well as between
ports handling system to optimally utilise the Kings Rest Umbogintwini and Airport;
buffer stack; Develop the airport link;
2016/17 Convert Kings Rest into an intermodal terminal; Consider a terminal on NATCOR at the urban edge (Cato
decommission Pier 1 terminal; Ridge or Umlaas Road);
2022/23 Develop a 75-wagon intermodal terminal at Consider a terminal in the vicinity of the new airport (Dube
Airport Dig Out (Phase 1); Reconfigure Umbogintwini into Trade Port); and
an arrivals and departures yard in order to accommodate Consider new high capacity bypass line (such as Cato Ridge
75 and/or 100-wagon container trains and link to airport Bypass) to compliment NATCOR line.
site;
2024/25 Develop an intermodal terminal at Airport
Dig-out (Phase 2);
2027/28 Develop new 75-wagon intermodal terminal in
Pier 1 (Phase 1: only if Salisbury infill occurs);
2029/30 Develop an additional 75-wagon intermodal
terminal in Pier 2 (Phase 2: only if infill between Pier 1
and Pier 2 occurs). Expand automotive terminal to handle
longer trains; and
2035/36 Develop an intermodal terminal at Airport
Dig-out (Phase 3).
Figure 79: Pier 1 and Durban Dig-out airport (D14) concept (2042)
In the next 30 years the identified sections will be converted Hotazel to Newcastle iron ore, manganese and coal
to heavy haul status, with axle load increased to 26t/axle and corridor. The iron ore and manganese is mainly transported
electrification system upgraded to 25kV AC. These sections to the steel plants in Vanderbijlpark and Newcastle.
comprise of the following rail segments: The coal from either Waterberg or Mpumalanga is also
Lephalale to Ermelo extension of the export coal line to transported along the Natcor to the Eskom power stations;
the Waterberg coal fields. Based on the demand forecast Ogies to Ermelo the coal back bone handling most of
exceeding 30mtpa, a new line may need to be constructed the domestic coal to the Eskom power stations in the
to be able to run 200-wagon trains from Richards Bay to the Mpumalanga area. The joint Eskom and Transnet strategy
Waterberg coalfields. A link to Botswana will be necessary to migrate coal from road to rail will be major contributor
to connect the South African network with the Botswana to the system expansion requirements; and
rail network, thereby allowing the railage of coal from the Pyramid to Houtheuwel this section forms part of the
Botswana coal field to South Africa for consumption or Freight Ring, which will receive traffic from Waterberg,
export purposes; Northern Cape, Limpopo and Mpumalanga coal fields.
Hotazel to the Port of Ngqura manganese export corridor Thegeneral freight traffic is also high in this area.
from the Northern Cape to the deep sea Port of Ngqura in
the Eastern Cape;
Due to different train operating speeds, required track There are other routes, which are not as highly utilised as the
standards and the impact on capacity, passenger and freight heavy haul lines, which can serve as alternate routes for light
traffic are not compatible on a shared network. Transnet industrial traffic, containers and passenger trains.
and PRASA have initiated joint planning sessions to resolve
These lines are indicated on the map as upgraded passenger
the incompatibility of both passenger and freight traffic on
and light industrial routes. Due to the nature of the traffic
specific networks. Considering traffic density by 2042 as well
it is believed that these traffic types are interoperable at a
as the freight type on specific routes, Transnet has developed
medium speed of approximately 160km/h. The track standard
a series of capacity creation interventions, including the
will have to be improved on these specific routes to support
upgrade of some lines to heavy haul standards. By 2042
the light industrial medium speed traffic types. By developing
theheavy haul lines will cover the routes shown here in red.
another corridor for light industrial traffic, additional
On these routes, compatibility with passenger services will
capacity is released or created for heavy haul, light industrial
become problematic.
and passenger traffic.
In the long term, it is highly likely to introduce the high speed Sishen Link rail link connecting the iron ore network to
passenger service between Gauteng and Durban. Gauteng, Botswana and the Waterberg Coalfields using
the existing West Rand to Mahikeng section; and
Other regional and strategic connections are also considered,
such as: Trans Kalahari regional rail link from Walvis Bay in Namibia
to link with the South African network via Botswana.
Coastal Rail rail connection from the Western Cape to
KwaZulu-Natal via the Eastern Cape province;
The network future state map for electrification shows the The Beaufort West to Cape Town and Gauteng to Durban
impact of specific corridor upgrades and a general shift via Newcastle lines will also be upgraded to 25kV AC.
towards 25kV AC electrification of the core network. The ore Thestandardised view shows the remainder of the core
line remains at 50kV AC. The new alignment from Waterberg network will be 3kV DC and non-electrified. Some of the
to Ermelo and Swazi link will be installed with 25kV AC existing electrified lines that have low volumes will be
traction, as well as the northern coal line, and Maputo corridor. de-electrified, with the view that the future volumes do not
The route from Hotazel to Gauteng via Kimberley is converted support the electrical maintenance or upgrade.
to support the commodity flows that utilise the sections,
inparticular iron ore.
Legend
The core network and lines with substantial volumes are This is done with the view of simplifying operations on the
upgraded to CTC signalling train control. The necessity for network and improves turnaround times. CTC signaling to be
upgrading train control is primarily a factor for the volumes rolled out firstly on heavy haul lines to maximise throughput
running over a section, with high volume forecast being the and improve system safety, secondary lines to track warrant
most eligible candidates. and minor lines to radio train order.
(c) New rolling stock Figure 89: Locomotive availability and reliability
A set of key planning principles were used for compiling the (a) Locomotive availability and reliability
long-term plans. The intent is that whenever the plans are
compiled or revised, these plans be tested against the key Availability and reliability data includes an adjusted target,
planning principles in order to ensure alignment within the which is derived from an international benchmark, but
business as a whole, and also that all the important aspects adjusted for local conditions and the current fleet.
are addressed. Listed below are the key planning principles Availability is defined as the percentage of the total
for wagons and locomotives. active rolling stock fleet, which is available for operational
8.1 Locomotives current fleet deployment. The non-available locomotives are typically
receiving scheduled or unscheduled maintenance. The
Locomotive fleet size
active fleet is defined as the total fleet less the rolling stock
damaged in accidents and derailments or staged.
The following new locomotives are currently in the 20E dual voltage general freight locomotives (3kV DC and
procurement process: 25kV AC)
15E electric locomotive (50kV AC). An order has been placed during 2012 for 95 of these new
New high powered, high technology locomotives procured general freight locomotives.
for replacing the 9E and diesel locomotives on the ore line.
39D diesel electric locomotive
Continuous tractive effort of the 15E rated at 454kN versus
These locomotives are from upgraded 34 class diesel electric
the 388kN of the existing 9E. First prototype locomotives
locomotives with newer technology to extend life and
delivered by mid-2010 with final delivery by 2012/13.
increase efficiency. The tractive effort is improved from the
19E dual voltage electric locomotive (3kV DC and 25kV AC) current 218kN to 273kN. The first prototype locomotives
New high technology dual voltage (3kV DC and 25kV AC) were delivered during 2009 with the fleet of 50 in full service
locomotives are being procured for replacing the 10E and 7E in 2011.
locomotives on the coal line. The first prototype locomotives
43D
delivered during 2009 with the total fleet to be expected in
A 143 new general electric locomotives are being procured to
service towards the end of 2013.
replace older diesel locomotives. First prototype locomotives
were received during 2011 with final delivery in 2013.
Figure 92: New locomotive committed investment Figure 93: Locomotives fleet required in the future
Figure 98: Future wagon fleet required Figure 99: Wagons investments (30 years)
The figure indicates the total wagon fleet demand for (a) Wagon investment
the 30-year forecast as from the Freight Demand Model.
The wagon investment plan is shown in the Figure Wagon
Theefficiency parameters of TFR were applied for the
investment, and also compared with the total fleet size and
seven-year period and the improvement in efficiencies
the long-term investment estimate. The TFR and LTPF plans
cause wagon requirement to increase at a lower rate than
correlate well, but it needs to be kept in mind that the TFR
trafficdemand.
seven-year efficiency targets were incorporated into the
It should be noted that a significant wagon requirement, due to LTPF calculations.
volume growth up to 2018, is planned to be addressed by means
The future wagon fleet requirement is calculated from traffic
of efficiency improvements, which is in line with continuous
demand projections over the full 30-year period. However, the
improvement, but with the associated risk if not achieved.
wagon investment plan for the 30 years is smoothed after the
Thisrisk also impacts on the overall growth plan of TFR.
first seven years to ensure a prudent procurement processes.
The coal line shortfall to build Jumbo wagons in order to
As the wagon fleet plan relies intensely on efficiency
cascade the Smalls to GFB, was addressed by means of
improvements to meet the freight demand, it is believed that
approval of the business case recently. The new container
the current investment plan may be at risk of being insufficient
wagons requirement need to be addressed. The conversion
to support the required growth due to the risk of not achieving
of BA wagons to C type wagons will be alleviated by the
the assumed efficiency improvements.
influx of Smalls (CCR1/3) wagons from the coal line cascading
programme. The new Jumbo wagons for the coal line volume Again important to note that the TFR fleet plans are limited to
growth are essentially in process and will also be addressed the seven-year volume target for General Freight of 174mtpa.
with the 81mtpa expansion plan. The ore line fleet is sufficient
for the current volumes and additional wagons will be procured
as ore line projected traffic grows.
The coal export line can still benefit from distributed power
and dual voltage locomotives, which are now being delivered.
Many of the current branch lines have been in existence Transnets strategy supports development of economic
for nearly 100 years and nearly all have not been operating activity within rural areas and to recapture traffic back from
profitably. road to rail requires renewed focus on revitalising many of
these branch lines.
By 1935 most branch lines were already constructed and are
now a substantial part of the total network. They are found in Transnet and Government have initiated a branch line
all provinces. revitalisation programme to provide opportunities for
refurbishment and, where desirable, for external operators
About 7 500km of the South African network are classified
on these lines. Transnet Freight Rail will, however, continue
as Branch lines with the potential to service communities
to operate through an independent unit called Branch Line
and activities not directly on the main corridors. Branch lines
Operations and Management Unit (BLOM).
are important links to rural areas of the country and when
active contribute to main line tonnages. This network is a This has resulted in the:
combination of lifted and stolen lines, closed lines and active Commencement of refurbishment of some branch lines
lines. and allocation of funds to refurbish others in the next
Branch line strategy fewyears;
Efficiently operating branch lines are crucial for economic Confirmation of market interest to operate branch lines;
development of particularly rural areas of the country, and and
to reopen and operate them sustainably require different Commencement of a process to select operators and
strategic, funding and operating models to that of mainlines. conclude the necessary agreements.
Figure 103: Figure 101: Eastern Cape (north) cluster and proposed KwaZulu-Natal rail link
Figure 108: Western Cape, Eastern Cape and Northern Cape clusters
The SADC has a Cape gauge rail system that is reasonably Focussed maintenance strategies and improved operational
well connected and can contribute significantly to economic efficiencies can contribute to regain rail capacity, but
development. for many corridors, this will not be sufficient and rail
infrastructure will require major rebuilding to meet current
However, most of the regional rail network is operating
and future imperatives.
at well below design capacity as infrastructure condition,
(asdescribed further on in this document), and rolling Rebuilding some of the more important rail corridors and
stock condition, availability and reliability have severely construction of a few additional strategic connecting lines
impacted on ability to match design capacity or meet present will contribute significantly to increased economic growth
transportdemands. and development and regional competitiveness.
Status quo
For decades there has been a lack of maintenance and The reasons for this have been well debated and studied
investment. As a result, most of the railways are badly for many years and are also well understood initial loss
run-down, requiring substantial rehabilitation of both of volumes and income from road transport deregulation,
infrastructure and rolling stock. followed by lack of investment and deferred maintenance,
leading to declining reliability and further loss of traffic.
During wars and civil disturbances, railways are often one of
the first targets for destruction and this has affected railways Reference: The SADC Regional Infrastructure Development Plan: Draft
either directly (eg Angola and Mozambique) or indirectly by Final Transport Sector Plan: 31 May 2012: Version 1.0.
separating inland railways from their ports (eg Malawi).
Reference: The SADC Regional Infrastructure Development Plan: Draft Final Transport Sector Plan: 31 May 2012: Version 1.0.
Note: The draft report prepared for the SADC titled: The Malawi has two clusters one to the south that is being
SADC Regional Infrastructure Development Plan: Draft Final threatened by relations with Mozambique and a slowly
Transport Sector Plan: 31 May 2012: Version 1.0 contains a far developing cluster in the northern part of the country that
more complete list of proposed rail, road and air development could link into the Mtwara corridor as well as Mbeya. The
plans for the region and will, for the sake of brevity, not be cluster in the south is based on mining, agriculture, power,
repeated here. cement and logistics through to Mozambique, whilst the
cluster in the north is based on mining and agriculture and
The SADC has identified various development corridors, of
links to Zambia/Tanzania (possibly ports, power, roads
which the North-South corridor is considered one of the most
andrail);
important.
Tanzania has major long-term developments beginning to
In a recent study that Whitehouse and Associates presented unfold: the Mtwara corridor, with the petrochemical-driven
on 18 April 2012 to the Built Environment Professions Export cluster at Mtwara and the iron-coal and power cluster at
Council (BEPEC) on Opportunities along the North-South Mchuchuma-Liganga. There is also the central corridor,
corridor, they identified 11 key clusters of development. directly in the ambit of the NSC, which includes agriculture-
The figure above indicates these clusters, which includes the industrial, mining, power and cement developments;
summary of the overall development in the relevant countries Mozambique is the focus of some of the regions key clusters
as follows: notably in Tete, and including the logistics that this will
Botswana is developing a cluster of energy, mining and unlock through to the ports of Nacala and Beira. In addition,
related infrastructure from Orapa to Selebi Phikwe and it is thought that the Niassa province could have more
south, as well as a minor cluster around the Kazungula potential than Tete and will be the next major growth node.
border post. Mining cluster developing from Orapa to Allied to the Niassa province is the development of the huge
Selebi Phikwe is based on gas, coal and uranium; gas fields in northern Mozambique that should unlock major
projects in the next decade. There is also a development
node around Maputo based primarily on industrial and
commercial developments, urban development, airports
and the proposed new Port of Techobanine;
Zambias major thrusts are the copperbelt and movement Some of the reasons given are:
to the North-western province, and the southern cluster Low levels of economic freedom in SADC;
from Lusaka to Kafue and the borders with Botswana Lack of regional co-operation;
and Zimbabwe. The copperbelt development is based on Insufficient access to capital;
mining and the Lusaka area for industry, property and
Lack of ability to exploit/utilise FDI (foreign direct
logistics. The developments in the North West province
investment);
are particularly exciting and the area will in all likelihood
Highly complex consessioning arrangements;
become another Tete. There is already a proposal on the
table for the development of an industrial park in Solwezi High levels of political interference; and
to serve the mines. High levels of bribery and corruption.
10.7 Future regional integration Rail development projects associated with bulk mining such
Suggested uniform rail standards are being considered for as coal exports, appear to have a better chance of success
sub-Saharan Africa, with regional uniform standards, such as: due to simple funding arrangements and control.
Uniform general axle loads, likely about 20t, allowing 80t Opportunities for Transnet to participate in regional railways
wagons with 60t payloads; can take the form of:
Uniform track geometric standards, allowing train speeds Engineering and development agent;
of up to 80km/h; Concession holder or partner for build, operate and
Uniform track maintenance procedures; maintain phases;
Uniform track gauge, likely to be retained at 1 067mm; Track and rolling stock maintenance agency;
Standard wagon, coupling and braking systems, (dual Rolling stock OEM and supplier;
vacuum and air, gradually moving to air only to allow for Rolling stock leasing agent; and
longer trains) already in force;
Training and development.
Standardised maximum train lengths, often limited by
poor track condition, but ideally up to 50 wagons, requiring
passing loops of 900m; and
Ideally, a standardised mainline locomotive fleet, such as
a GE type +3000hp unit, allowing for ease of maintenance
and improved availability and utilisation.